Scott Tod v. Indy Goldmine, LLC (mem. dec.) ( 2017 )


Menu:
  • MEMORANDUM DECISION                                                            FILED
    May 09 2017, 10:09 am
    Pursuant to Ind. Appellate Rule 65(D), this
    Memorandum Decision shall not be regarded as                                   CLERK
    Indiana Supreme Court
    precedent or cited before any court except for the                            Court of Appeals
    and Tax Court
    purpose of establishing the defense of res judicata,
    collateral estoppel, or the law of the case.
    ATTORNEY FOR APPELLANT                                 ATTORNEYS FOR APPELLEES
    S. Andrew Burns                                        David L. Byers
    Cox, Sargeant & Burns, P.C.                            Andrew J. Noone
    Indianapolis, Indiana                                  Holwager, Byers, & Caughey
    Beech Grove, Indiana
    IN THE
    COURT OF APPEALS OF INDIANA
    Scott Tod,                                                 May 9, 2017
    Appellant/Plaintiff/Counterclaim                           Court of Appeals Case No.
    49A04-1609-CT-2157
    Defendant,
    Appeal from the Marion Superior
    Court
    v.
    The Hon. Thomas J. Carroll, Judge
    Indy Goldmine, LLC, d/b/a IG                               Trial Court Cause No.
    Home Improvements, and Aaron                               49D06-1508-CT-28726
    McGee,
    Appellees/Defendants/Counterclaim
    Plaintiffs.
    Bradford, Judge.
    Court of Appeals of Indiana | Memorandum Decision 49A04-1609-CT-2157 | May 9, 2017                 Page 1 of 8
    Case Summary
    [1]   Appellant/Plaintiff/Counterclaim Defendant Scott Tod appeals from the trial
    court’s entry of judgment in favor of Appellees/Defendants/Counterclaim
    Plaintiffs Indy Goldmine, LLC, d/b/a IG Home Improvements (“IG”), and
    Aaron McGee (collectively, “Defendants”). When Tod purchased his
    Indianapolis home, he obtained a rehabilitation loan and executed a series of
    agreements with IG (collectively, “the Contract”) to perform a series of
    renovations, including replacement of the roof. After IG completed some
    renovations, Tod ultimately hired another contactor to replace his roof, which
    violated the terms of the Contract.
    [2]   Tod sued Defendants for breach of contract, conversion, and unjust
    enrichment, and Defendants countersued Tod for breach of contract. At one
    point, Tod served Defendants with a request for admissions, which included
    requests that they admit that Tod had paid them some $21,000.00 for
    renovations, they had not completed the contracted-for work, and Tod had
    received no more than $10,000.00 of value. Because Defendants did not timely
    respond to Tod’s requests, the admissions were deemed conclusively
    established. Following a bench trial, the trial court entered judgment in favor of
    Defendants and awarded them $8987.50 in damages. Tod contends that the
    trial court erred because Defendants’ admissions automatically entitle Tod to
    judgment. Because we disagree, we affirm.
    Facts and Procedural History
    Court of Appeals of Indiana | Memorandum Decision 49A04-1609-CT-2157 | May 9, 2017   Page 2 of 8
    [3]   Tod purchased his Indianapolis home on October 31, 2014, and began to
    remodel it to address some health and safety issues. To that end, Tod obtained
    a $35,000.00 203(k) loan.1 IG was referred to Tod as a provider of contracted
    203(k) services. Tod and IG executed a Contract for work on the home, which
    obligated IG to do many things, including installation of railing on three decks
    and a handrail for exterior stairs, replacement of rotten trim, demolition, mold
    remediation, and roof replacement, only some of which IG ultimately
    completed. IG began work in the first week of November 2014, after Tod
    closed on the home. Soon after work started, Tod became dissatisfied with IG’s
    work and began to speak with other contractors, eventually having another
    contractor repair and replace the roof. On December 29, 2014, Tod sent IG a
    termination notice.
    [4]   On August 24, 2015, Tod filed suit against Defendants, alleging breach of
    contract, conversion of funds, and unjust enrichment. On November 24, 2015,
    Defendants answered Tod’s complaint and filed a counterclaim, alleging breach
    of contract by Tod. On January 26, 2016, Tod served a request for admissions
    on Defendants, which included the following requests:
    REQUEST FOR ADMISSIONS NO. 1: Please admit that
    you/IG received and cashed a check in the amount of $6,000.00
    from Plaintiff on or about November 1, 2014.
    …
    1
    A 203(k) loan is a “rehabilitation loan” as defined by 24 C.F.R. § 203.50 and that is eligible for insurance
    pursuant to Section 203(k) of the National Housing Act. See 12 U.S.C. 1709(k).
    Court of Appeals of Indiana | Memorandum Decision 49A04-1609-CT-2157 | May 9, 2017                   Page 3 of 8
    REQUEST FOR ADMISSIONS NO. 2: Please admit that
    you/IO received and cashed a check in the amount of $14,987.50
    from Plaintiff on or about November 7, 2014.
    …
    REQUEST FOR ADMISSIONS NO. 3: Please admit that to
    date no monies have been returned to Plaintiff by Defendants.
    …
    REQUEST FOR ADMISSIONS NO. 4: Please admit that
    you/IG have/has not performed all services requested by the
    Plaintiff.
    …
    REQUEST FOR ADMISSIONS NO. 5: Please admit that there
    is no single document which memorializes the terms of the
    agreement reached between you/IG and the Plaintiff.
    …
    REQUEST FOR ADMISSIONS NO. 6: Please admit that there
    is no single document which lists all of the services you/IG were
    committed to provide to or for the benefit of the Plaintiff.
    …
    REQUEST FOR ADMISSIONS NO. 7: Please admit that you
    and your crew or agents damaged a water pipe on the real estate
    owned by the Plaintiff.
    …
    REQUEST FOR ADMISSIONS NO. 8: Please admit that you
    did not provide goods and/or services to or for the benefit of the
    Plaintiff in an amount in excess of $10,000.00.
    Appellant’s App. pp. C9-C10.
    [5]   Defendants untimely responded to Tod’s request for admissions on July 14,
    2016, which had the effect of deeming the admissions conclusively established.
    On August 16, 2016, defendants moved to withdraw their admissions, which
    Court of Appeals of Indiana | Memorandum Decision 49A04-1609-CT-2157 | May 9, 2017   Page 4 of 8
    motion the trial court denied on August 24, 2016. Also on August 24, 2016, the
    matter was tried to the bench, after which the trial court ruled that Tod could
    take nothing by way of his complaint and entered judgment in favor of
    Defendants on their breach-of-contract counterclaim in the amount of $8987.50.
    Tod contends that Defendants’ admissions required the entry of judgment in his
    favor, while Defendants argue that entry of judgment in their favor was still
    permissible, even taking their admissions into account.
    Discussion and Decision
    [6]   The trial court’s judgment here is not supported by specific findings of fact or
    conclusions thereon. Under such circumstances,
    [t]he applicable standard of appellate review is clear. In the
    absence of special findings, we review a trial court decision as a
    general judgment and, without reweighing evidence or
    considering witness credibility, affirm if sustainable upon any
    theory consistent with the evidence. Sizemore v. H & R Farms,
    Inc., 
    638 N.E.2d 455
    , 457 (Ind. Ct. App. 1994); Bedford Recycling,
    Inc. v. U.S. Granules Corp., 
    634 N.E.2d 1361
    , 1363 (Ind. Ct. App.
    1994); Quebe v. Davis, 
    586 N.E.2d 914
    , 917 (Ind. Ct. App. 1992).
    In reviewing a general judgment, we must presume that the trial
    court correctly followed the law. Sizemore; Turpen v. Turpen, 
    537 N.E.2d 537
    , 539 (Ind. Ct. App. 1989); Baker v. Baker, 
    488 N.E.2d 361
    , 364 (Ind. Ct. App. 1986).… On appellate review, due
    regard must be given the trial court’s opportunity to judge the
    credibility of witnesses, and the judgment should not be set aside
    unless clearly erroneous. Ind. Trial Rule 52(A); Ind. Appellate
    Rule 15(N).
    Perdue Farms, Inc. v. Pryor, 
    683 N.E.2d 239
    , 240-41 (Ind. 1997).
    Court of Appeals of Indiana | Memorandum Decision 49A04-1609-CT-2157 | May 9, 2017   Page 5 of 8
    [7]   Tod’s sole argument is that Defendants’ admissions that they received
    $20,987.50 from Tod, did not complete all of the contracted-for work, and did
    not provide services in excess of $10,000.00 required the trial court to enter
    judgment in his favor. Defendants counter that, even if all of the above is true
    (they concede that their admissions are conclusively established), none of this
    precludes a breach on Tod’s part. We agree with Defendants on this point; the
    facts established by the admissions are just as consistent with a breach by Tod
    as they are with a breach by Defendants. The admissions, at most, establish
    that Defendants did not perform (which they concede) but have nothing to do
    with why, which they claim was due to Tod’s breach.
    [8]   That said, we conclude that Defendants did produce sufficient evidence to
    sustain a finding that their failure to perform was due to Tod’s breach. The
    validity of the Contract is not in dispute, nor is the fact that Tod violated its
    terms when he hired his own roofing contractor. Although Tod presented
    evidence that he hired a new roofing contractor and terminated IG because of
    substandard work, among other reasons, the trial court was not required to
    credit this evidence or conclude that it justified Tod’s actions.
    [9]   As for Defendants, we conclude that the record is sufficient to permit a finding
    of substantial performance, with their ultimate failure to perform caused by
    Tod’s breach. “No mathematical rule relating to the percentage of the price, of
    cost of completion, or of completeness can be laid down to determine
    substantial performance of a building contract.” Johnson v. Taylor Bldg. Corp.,
    
    371 N.E.2d 404
    , 407 (Ind. Ct. App. 1978). Defendants produced evidence that
    Court of Appeals of Indiana | Memorandum Decision 49A04-1609-CT-2157 | May 9, 2017   Page 6 of 8
    work began on the project in the first week of November 2014, with the main
    component being a replacement roof. Prior to termination, Defendants
    completed the following: (1) installation of deck railing for three decks, (2)
    installation of a handrail for exterior stairs, (3) replacement of rotten trim, (4)
    demolition work, (5) removal of drywall ceiling in the basement, and (6) mold
    remediation. Regarding the replacement of the roof, which was a significant
    part of the work to be done, Defendants produced evidence of their diligence in
    attempting to complete the work. Defendants came to Tod’s home at least
    twice to show him materials. Tod did select a roofing material and issued a
    check, but then notified Defendants that he wanted a metal, rather than shingle,
    roof. Defendants then spent over thirty hours researching and collecting
    multiple bids for a metal roof, only to have Tod tell them that the price was too
    high. Despite Defendants informing Tod that he could not do so pursuant to
    the Contract, Tod pursued third-party options, eventually having the roof
    installed by another contractor and eventually terminating the Contract with
    Defendants. Moreover, McGee testified that IG was “very, very busy” at the
    time and had to forego other projects in order to take on Tod’s. Tr. Vol. II p.
    69. We conclude that Defendants produced sufficient evidence to sustain a
    finding that they stood ready to fulfil their contractual obligations but were
    prevented by Tod’s hiring of another roofing contractor and termination of
    them. Consequently, Tod has failed to establish that the trial court’s entry of
    judgment in favor of Defendants is clearly erroneous.
    Court of Appeals of Indiana | Memorandum Decision 49A04-1609-CT-2157 | May 9, 2017   Page 7 of 8
    [10]   The judgment of the trial court is affirmed.2
    Najam, J., and Riley, J., concur.
    2
    Tod does not dispute the trial court’s award of damages to Defendants, which represents the full, agreed-
    upon contract price of $29,975.00 minus the $20,987.50 already paid, for a total award of $8987.50. Tod
    makes no argument that this damages award should have been reduced by the cost of labor and materials
    Defendants would have expended had they completed Tod’s roof replacement.
    Court of Appeals of Indiana | Memorandum Decision 49A04-1609-CT-2157 | May 9, 2017                Page 8 of 8