State of Indiana, acting on behalf of the Indiana Family & Social Services Administration v. International Business Machines Corporation , 4 N.E.3d 696 ( 2014 )


Menu:
  • FOR PUBLICATION
    ATTORNEYS FOR APPELLANT:                            ATTORNEYS FOR APPELLEE:
    PETER J. RUSTHOVEN                                  JAY P. LEFKOWITZ
    JOHN R. MALEY                                       STEVEN J. MENASHI
    Barnes & Thornburg, LLP                             Kirkland & Ellis, LLP
    Indianapolis, Indiana                               New York, New York
    STEVEN D. McCORMICK
    DOUGLAS G. SMITH
    Kirkland & Ellis, LLP
    Chicago, Illinois
    Feb 13 2014, 12:40 pm
    ANDREW W. HULL
    DANIEL K. BURKE
    Hoover Hull, LLP
    Indianapolis, Indiana
    IN THE
    COURT OF APPEALS OF INDIANA
    STATE OF INDIANA,                                   )
    acting on behalf of the Indiana Family              )
    & Social Services Administration,                   )
    )
    Appellant-Defendant,                         )
    )
    vs.                                   )    No. 49A02-1211-PL-875
    )
    INTERNATIONAL BUSINESS                              )
    MACHINES CORPORATION,                               )
    )
    Appellee-Plaintiff.                          )
    APPEAL FROM THE MARION SUPERIOR COURT
    The Honorable David J. Dreyer, Judge
    Cause No. 49D10-1005-PL-21451
    February 13, 2014
    OPINION - FOR PUBLICATION
    VAIDIK, Chief Judge
    Case Summary
    Indiana’s poorest residents live hand-to-mouth trusting that they will receive food
    stamps to eat and Medicare or other state health insurance in order to receive basic medical
    care. These citizens do not have the luxury of being able to wait to eat or go to a doctor
    while a phone goes unanswered, an appointment cannot be scheduled, or an application
    sits on a desk. The needs of the poor are immediate.
    Indiana entered into an arrangement with the federal government to distribute
    federal funds to those in greatest need. Part of the State’s responsibility was to make certain
    that only the poorest received aid and to help welfare recipients find work. If the State
    failed to comply with federal guidelines, then it would be penalized by the federal
    government, resulting in less federal aid for our citizens.
    By all accounts, the State was failing in performing its duties. As a result, in
    December 2006, the State, on behalf of its agency the Indiana Family and Social Services
    Administration (FSSA),1 entered into a ten-year, $1.3 billion contract with International
    Business Machines Corporation (IBM) to modernize and improve the State’s welfare
    system. IBM agreed to the State’s proposal, although it argues that the system design was
    doomed to fail. Nonetheless, IBM received $437 million while assuring the State that it
    1
    The FSSA—the State’s largest agency—is charged with, among other things, administering
    Medicaid, Food Stamp, and Temporary Assistance to Needy Families (TANF) programs for the State of
    Indiana. Each of these programs provides welfare benefits to individuals and families in need of financial
    assistance in Indiana. To be deemed eligible for a particular program, an individual must be certified as
    eligible by the FSSA and recertified either annually or semi-annually depending on the particular program.
    See Perdue v. Gargano, 
    964 N.E.2d 825
    , 830 (Ind. 2012).
    2
    was up to the task. Less than three years into the ten-year contract, the State terminated
    the contract citing IBM performance issues, and the parties sued each other for breach of
    contract on the same day in Marion Superior Court. The State sought over $170 million in
    damages, and IBM sought almost $100 million. Appellant’s App. p. 239-40. The trial
    court granted IBM summary judgment for $40 million in assignment fees and, after a six-
    week bench trial in 2012, found no material breach on IBM’s part and awarded IBM an
    additional $9,510,795 in Equipment fees, $2,570,621 in Early Termination Close Out
    Payments, and $10,632,333 in prejudgment interest, totaling $62,713,749.
    While IBM’s software, computers, and employee training aided in delivering
    welfare services, the primary focus of the contract was to provide food and medical care to
    our poorest citizens in a timely, efficient, and reliable manner within federal guidelines, to
    discourage fraud, and to increase work-participation rates. In the most basic aspect of this
    contract—providing timely services to the poor—IBM failed. We therefore reverse the
    trial court’s finding that there was no material breach.
    Despite finding a material breach on IBM’s part, we affirm the trial court’s award
    of $40 million in assignment fees and $9,510,795 in Equipment fees to IBM. We do so
    because the State and IBM agreed under the terms of the contract that the State would pay
    these fees. Further, the State would be unjustly enriched if it were to keep IBM’s
    equipment and to assume IBM’s subcontracts without paying IBM. We further affirm the
    trial court’s denial of Deferred Fees to IBM, reverse the trial court’s award of $2,570,621
    in Early Termination Close Out Payments and $10,632,333 in prejudgment interest to IBM,
    and remand the case to the trial court to determine the amount of fees IBM is entitled to for
    3
    Change Orders 119 and 133. Finally, we remand the case to the trial court to determine
    the State’s damages for IBM’s material breach of the contract and to offset any damages
    awarded to IBM. We therefore affirm in part, reverse in part, and remand the case to the
    trial court.
    Facts and Procedural History
    The facts in this case are largely undisputed.2 During Governor Mitch Daniels’s
    first term as governor, he declared Indiana’s welfare system “broken.” Appellant’s App.
    p. 166. It was “plagued by high error rates, fraud, wasted dollars, poor conditions for its
    employees, and very poor service to its clients.” 
    Id.
     Indiana’s welfare-to-work record was
    the worst in the country. Id. at 167. Consequently, Governor Daniels dubbed Indiana’s
    welfare system “America’s worst welfare system.” Press Release, Governor accepts
    recommendation         to    modernize       FSSA       eligibility processes         (Nov.     29,    2006),
    http://goo.gl/Tfbas4 (Ex. 612).
    2
    The State does not set forth any background facts in its brief. See Appellant’s Br. p. 4-14. IBM
    sets forth some background facts, but its citations for these facts are to the trial court’s nearly thirty-five
    pages of findings of facts—not to the official transcript. Because no party challenges the findings of facts,
    we use the trial court’s findings when setting forth the background facts of this case.
    In addition, we note that our review of this case has been hampered by the trial court’s citations to
    the uncertified, and thus unofficial, transcript of this case. See Appellant’s App. p. 166 n.3 (trial court
    explaining in its July 2012 order that “[c]itations to trial testimony are taken from the uncertified transcript
    and are unofficial.”). The record shows that in advance of trial, both “parties collaboratively arranged for
    a team of John Connor & Associates certified court reporters to prepare daily trial transcripts for each day
    of trial and throughout the trial and those transcripts have been paid for by the parties.” State v. Int’l Bus.
    Machs. Corp., Cause No. 49A02-1211-PL-875, Agreed Mot. Regarding Submission of R. Items for
    Purposes of Appeal (filed Jan. 3, 2013). In the meantime, “the Marion Superior Court, Civil Division 10,
    court reporters . . . prepared the ‘official’ trial transcript,” resulting in discrepancies between the two
    records. Id. Because the parties and trial court cited the unofficial transcript in the trial court, they asked
    this Court if they could use the unofficial transcript for purposes of appeal because “citing to the newly
    generated and re-paginated ‘official’ trial transcripts will be laborious for the parties and confusing for all
    concerned, including this Court.” Id. However, an order from our former Chief Judge denied the parties’
    request to cite the unofficial trial transcript prepared by private court reporter John Connor & Associates
    because it did not comport with Indiana Appellate Rules 28, 29, and 30. State v. Int’l Bus. Machs. Corp.,
    Cause No. 49A02-1211-PL-875 (Ind. Ct. App. Jan. 18, 2013).
    4
    Shortly after Governor Daniels was elected in November 2004, he and senior
    officials—including former Indianapolis Mayor Stephen Goldsmith and FSSA Secretary
    Mitch Roob—set out to modernize and improve Indiana’s welfare system. The new system
    was modeled after the system in Texas. Under the new model, Indiana citizens would
    apply for benefits “via web and call center” without the need for a face-to-face meeting
    with a case worker, and eligibility determinations would be made on a centralized,
    statewide basis rather than in the local county welfare offices. Appellant’s App. p. 167.
    One of the State’s requirements for the new system was to “reduce the number of
    mandatory visits to local offices” by “giving clients more avenues to interact with the
    agency,” such as “the Internet, an automated and interactive phone system, and local
    organizations in the community.” Id. at 168. Analysts had found that citizens most in need
    of FSSA’s help were forced to make more than two million unnecessary trips a year. Id.
    In October 2005, FSSA began seeking vendors for the project. Id. at 169. IBM and
    a group of twelve coalition companies, including Dallas, Texas-based ACS Human
    Services, submitted a bid. In May 2006, the State announced its intention to award the
    contract to the IBM Coalition.3
    After months of negotiations, on December 27, 2006, the State of Indiana and IBM
    signed a ten-year, $1.3 billion Master Services Agreement (“MSA”). Specifically, the
    MSA sought to “transform and modernize the process by which information needed or
    related to making eligibility determinations is collected, organized, and managed . . . in
    3
    Other participating bidders dropped out, leaving the IBM Coalition as the only potential contract
    partner. Appellant’s App. p. 169-70. The largest portion of the work among Coalition members went to
    ACS. Id. at 169.
    5
    order to improve access to, and responsiveness of, that system and process, and to assure
    the integrity, reliability and efficiency of the public assistance contemplated by such
    programs[.]” Id. at 566. During the process of negotiating and drafting the agreement, the
    State was represented by outside counsel as well as the Office of the Attorney General,
    which reviewed the contract as it was being drafted and approved it for “form and legality.”
    Id. at 172. Governor Daniels signed the MSA for the State. Id. The MSA contains more
    than 160 pages plus extensive attachments, including 10 exhibits, 24 schedules, and 10
    appendices. Id.
    As part consideration for the MSA, a Memorandum of Understanding (“MOU”)
    was also signed on the same day as the MSA. According to the MOU—which was
    executed by IBM, the Indiana Economic Development Corporation, Purdue University,
    and Indiana University—IBM agreed to undertake collaborative activities designed to
    promote economic activity in the state, including creating 1000 full-time new jobs. Ex.
    1709.
    The MSA incorporated the various goals that were important to the State in deciding
    to overhaul Indiana’s welfare system. MSA § 1.1(1) identified the following “Policy
    Objectives”:
    (1) The overarching policy objectives of the Modernization Project and this
    Agreement are (i) to provide efficient, accurate and timely eligibility
    determinations for individuals and families who qualify for public assistance,
    (ii) to improve the availability, quality and reliability of the services being
    provided to Clients[4] by expanding access to such services, decreasing
    inconvenience and improving response times, among other improvements,
    (iii) to assist and support Clients through programs that foster personal
    4
    “Client” means “any individual or family (1) who receives or applies for assistance under a Public
    Assistance Program during the Term, or (ii) whose Records or Personal Information have been delivered
    to Vendor pursuant to the Agreement for receipt of benefits under a Program.” Appellant’s App. p. 761.
    6
    responsibility, independence and social and economic self-sufficiency, (iv)
    to assure compliance with all relevant Laws, (v) to assure the protection and
    integrity of Personal Information gathered in connection with eligibility
    determination, and (vi) to foster the development of policies and procedures
    that underscore the importance of accuracy in eligibility determinations,
    caseload integrity across all areas of public assistance and work and work-
    related experience for Clients in the Programs.
    *****
    (5) Vendor recognizes that (i) the Services to be performed under this
    Agreement are vital to the State and its citizens who currently are and in the
    future will be legally eligible for and reliant upon the assistance available
    under the Programs and must be continued without interruption and (ii) upon
    Termination, a Successor must be able to continue to provide the Services in
    as seamless a transition from Vendor as possible.
    Appellant’s App. p. 567. In addition, MSA § 1.4, entitled Construction and Interpretation,
    provided that the agreement “shall be” construed in a manner consistent with the Policy
    Objectives:
    (5) In the event of any uncertainties regarding the interpretation of any
    particular provision or term used in this Agreement, or in the event of any
    ambiguity, vagueness or inconsistency therein or thereof, such provisions
    and terms shall be read in a manner consistent with the Policy Objectives. In
    all events, the provisions and terms of this Agreement shall be interpreted
    with a view toward achieving those objectives. Notwithstanding the
    foregoing, in no event shall the Policy Objectives change or expand Vendor’s
    obligations hereunder unless expressly agreed to by the Parties pursuant to a
    Change.
    Id. at 571.
    Under the terms of the MSA, IBM would assist the State in processing the
    applications for public assistance under the State’s existing procedures in all ninety-two
    Indiana counties. The new system would then be rolled out in phases on a region-by-region
    basis according to a “preliminary” “Initial Transition Timeline.” Id. at 175 (citing MSA §
    3.2.1(2)). The final stage of the process, or “Steady State,” would be reached when the
    7
    new system was rolled out to all ninety-two counties. Id. (citing MSA § 3.2.1(1) &
    Appendix I). As it would turn out, Steady State was never reached because the State
    terminated the MSA and moved to a hybrid system when only about half of Indiana’s
    counties were operating under the modernized system.
    In any event, according to the MSA, the State retained operational control
    throughout the project, including “general authority and responsibility for operational,
    technical, financial, and general management and oversight of the Services provided under
    the Agreement.” Id. (citing MSA App. V, § 3.7.2). The State also retained all policy-
    making authority over the project. Id. at 175-76 (citing MSA § 3.1.1(6)). Finally, the State
    made final eligibility determinations for the public-assistance programs. Id. at 176 (citing
    MSA § 3.1.1(1)).
    In order to assess IBM’s performance, the parties agreed on four categories of
    “Performance Standards”:
    (1) Critical Transition Milestones, which were penalties imposed if IBM did
    not achieve the milestones identified by the State that were critical to the
    successful transition of the Services;
    (2) Transition Key Performance Indicators, which were performance
    measurements for the “as-is” counties during the transition;
    (3) Key Performance Indicators, which were performance measurements for
    the modernized system in force originally only during Steady State; and
    (4) Service Level Metrics, which related primarily to service levels that
    guided the priorities of IBM, also in force only during Steady State.
    Id. at 178-79, 737, 738. These were attached to the MSA in Schedule 10. See id. at 735.
    Twenty Key Performance Indicators were designed to measure performance only during
    Steady State. See id. at 744-48. However, eleven of the Key Performance Indicators were
    accelerated by agreement of the parties in Change Order 64 and began on September 1,
    8
    2008. Id. at 179-81 (citing Ex. 1500.064). Many significant metrics, such as the Service
    Level Metrics, did not apply until Steady State, which was never reached.
    All of these standards included liquidated-damages provisions. They ranged from
    $150,000 to $350,000 for Critical Transition Milestones and far smaller sums—$500 to
    $5000—for the Key Performance Indicators and others. See, e.g., id. at 744-48.
    Under Article 16 of the MSA, the State could terminate the agreement (1) for
    convenience or (2) for cause. Id. (citing MSA §§ 16.3.1, 16.3.2). The termination-for-
    cause section provided that the State could terminate the agreement in three ways:
    (1) The State may terminate this Agreement, in whole or in part, for cause in
    any of the following circumstances:
    (A) a breach by Vendor[5] of this Agreement which is material
    considering this Agreement as a whole occurs which cannot
    reasonably be cured by Vendor within thirty (30) days after delivery
    of the Termination Notice (the “Notice Period”);
    (B) a breach by Vendor of this Agreement which is material
    considering this Agreement as a whole occurs which can reasonably
    be cured by Vendor within the Notice Period but which has not been
    cured within the Notice Period unless Vendor (i) has submitted to the
    State within the Notice Period a Corrective Action Plan to cure the
    breach within sixty (60) days after the date Vendor receives notice of
    the breach from the State (the “Extended Cure Period”), (ii) proceeds
    diligently according to such Plan, and (iii) cures the breach within the
    Extended Cure Period (in which case the State’s termination shall
    become effective when Vendor fails to perform any one of steps (i),
    (ii), or (iii)); or
    (C) a series of breaches of Vendor’s obligations, none of which
    individually, constitutes a breach of this Agreement which is material
    considering this Agreement as a whole, but which, in view of
    Vendor’s history of breaches, whether or not cured, collectively
    constitute a breach of this Agreement which is material when
    considering this Agreement as a whole, provided that the State’s
    5
    According to the MSA, “Vendor” is defined as IBM. Appellant’s App. p. 782, 566.
    9
    notice to Vendor shall be provided within a maximum of three (3)
    months after the last such breach upon which the State bases its
    termination. For the purposes of clarity, the cure periods set forth in
    Sections 16.3.1(1)(A) and 16.3.1(1)(B), as appropriate, shall apply to
    a notice given under this Section 16.3.1(1)(C) as to any breach for
    which a cure period has not previously been provided.
    Id. at 692-93 (MSA § 16.3.1(1)). Under the termination-for-convenience provision, the
    State could terminate the agreement, in whole or in part, “for any reason” that the State
    determined was “in its best interest.” Id. at 693 (MSA § 16.3.2).
    The MSA included a range of payment provisions in the event that the agreement
    was terminated. Some of these, however, depended on whether the contract was terminated
    for convenience or for cause. In Article 14 governing Subcontractors, Section 14.8.1(3)
    gave the State the option of assuming IBM’s subcontracts but provided for subcontractor
    assignment fees in certain circumstances:
    (3) In the event the State exercises its right to accept assignment of one or
    more Subcontracts pursuant to this Section 14.8, the State shall not be
    required to pay to Vendor the Early Termination Close Out Payments that
    are directly attributable to the performance of such assigned Subcontract(s),
    but, instead for each Subcontract assigned to the State, the State shall pay
    Vendor the following upon the applicable Services Termination Date:
    (A) if the replaced Subcontractor is ACS, (i) the amount of the
    Deferred Fees for Vendor’s Subcontract with ACS as set forth in
    Schedule 24 [Deferred Fees], plus (ii) Ten Million Dollars
    ($10,000,000), if the applicable Services Termination Date is within
    Contract Years one through seven . . . .; and
    (B) for each assigned Subcontract with a Key Subcontractor (other
    than ACS) and each other assigned Primary Subcontract (other than
    those Subcontracts with an aggregate contract value of less than Five
    Million Dollars ($5,000,000)), Five Million Dollars ($5,000,000), if
    the applicable Services Termination Date is within Contract Years one
    through seven . . . .
    10
    provided, however, that the provisions of this Section 14.8.1(3) shall not
    apply if all the Services contained within an applicable Subcontract are
    terminated by the State pursuant to Sections 16.3.1 [termination for cause],
    16.3.4(2) [insolvency events], or 16.3.4.(3) [wrongful conduct], except that
    the unamortized balance of the Deferred Fees shall still be payable in such
    event.
    Id. at 681. Similarly, Section 16.6.1(4) provided that the Disengagement Plan “shall” detail
    the transfer of Equipment and that “[u]pon receipt of payment for” the Equipment, IBM
    “shall provide the Successor with an agreed upon bill of sale . . . .” Id. at 700. Section
    16.6.6 required the State to pay IBM Early Termination Close Out Payments, including
    Deferred Fees, in the event that the MSA was terminated. Id. at 702. However, as the
    trial court later determined on summary judgment, IBM was not entitled to Deferred Fees
    if the State terminated the MSA for cause. Id. at 383-87 (trial court’s January 25, 2012
    order).
    “Phase 1” of the rollout began in March 2007. It consisted of informing the public
    as well as recruiting and transferring about 1500 State employees to IBM subcontractors.
    Id. at 183. “Phase 2” occurred over a seven-month period from October 2007 to May 2008
    as the parties rolled out the modernized system in three stages. Id. On October 25, 2007,
    the State approved the rollout of the project to a twelve-county pilot area in north-central
    Indiana. Id. During this pilot phase, the State’s Modernization Project team evaluated the
    IBM Coalition’s performance, including the readiness of the Service Centers, document-
    processing center, general infrastructure, and application processing. Id. The team,
    including Secretary Roob, regularly met with the IBM team during the Pilot Phase and
    throughout the Modernization Project.        Id. The parties “saw implementation issues
    immediately,” including unanswered calls and the untimely processing of applications. Id.;
    11
    see also id. (June 2007 email from Secretary Roob to IBM Vice President of State and
    Local Government Brian Whitfield: “tens of thousands of calls unanswered, honestly
    perhaps the worst performance I have ever seen in a call center.” (citing Ex. 8021)).
    The trial court found that two background factors contributed to these initial
    difficulties. First, by December 2007, which was two months after rollout of the pilot
    region, the State and the country began to feel the effects of the “Great Recession.”6 Id. at
    185.   Benefit applications skyrocketed, and over the next two years, the State’s
    unemployment rate more than doubled. Id. at 185-86.
    Second, in 2008, Indiana was hit by a series of natural disasters that cost the State
    nearly $2 billion in economic damage. Id. at 186. All but ten of Indiana’s counties were
    declared Presidential Disaster Areas. Id. at 186-87. These disasters affected the rollout of
    the project, which was eventually suspended by mutual agreement of the parties in
    September 2008 in Change Order 69 in order to accommodate disaster-relief efforts. Id. at
    188. The State directed the reassignment of approximately one-third of the State and IBM
    Coalition workforce to help process tens of thousands of emergency food-stamp
    applications and thousands of FEMA applications. Id. at 187.
    Despite these challenges, in March 2008, the IBM Coalition received the State’s
    approval to begin providing modernized services to Region 2A, which represented twenty-
    seven counties in southern and central Indiana. Id. After two months of operating these
    counties under the modernized system, on May 5 the State gave its approval to rollout the
    project to Region 2B, which represented twenty counties divided between southwest and
    6
    The trial court cited a document from the National Bureau of Economic Research for the
    proposition that the recession began in December 2007. See Appellant’s App. p. 185 n.30.
    12
    northeast Indiana. Id. In total, the modernized system was implemented in fifty-nine of
    Indiana’s ninety-two counties.
    During the rollout, the State conducted a series of project assessments. In May
    2008, FSSA Secretary Roob reported to the Indiana General Assembly that although they
    “still ha[d] more work to do,” modernization had allowed the State to serve “more people
    statewide and in a timelier manner than we ever have before.” Id. at 189; Ex. 34. In August
    2008, FSSA reported to federal authorities that although the start and finish dates of several
    key milestones had to be adjusted, the Modernization Project had “‘already made
    substantial progress toward its goals and objectives.’” Appellant’s App. p. 189 (quoting
    Ex. 247, a document requesting Federal Financial Participation for the costs projected
    during FY2009).     In October 2008, the director of the FSSA’s Division of Family
    Resources gave IBM primarily 9s and 10s (out of a possible 10) in IBM’s annual customer
    satisfaction survey. Id. (citing Ex. 208). And in a December 2008 interview, which was
    nine months before the State terminated the MSA, Governor Daniels said that the new
    system was “a work in progress” and “far from perfect” but “far better than what preceded
    it,” noting that critics wanted to “go back to a system where you had to beg for an
    appointment face to face,” which was “atrocious.” Id.; Ex. 630.
    The State expanded the scope of IBM’s work numerous times during the course of
    the project, which added $178 million to the contract price. Appellant’s App. p. 190. These
    expansions were reflected in Change Orders 23, 33, 53, 60, 64, 67, 68, 90, 93, 119, and
    13
    133.7 Id. at 190-91. For example, the State significantly increased the scope of the project
    in 2007 with Change Order 23 in order to include the Healthy Indiana Plan (HIP), which
    provides health insurance to uninsured Indiana residents who fall below a certain income
    level. Id. at 184. When the HIP launched, the number of applications regularly exceeded
    the State’s predictions, which caused IBM to fall behind on application processing, thereby
    placing additional strain on the modernized system. Id. at 184-85.
    But, as even the trial court found, these accolades and expansions did not mean that
    the project did not have problems. Id. at 191 (Finding No. 53). In November 2008, the
    IBM Coalition met with Secretary Roob to propose changes to the project because of
    problems including inconsistent feedback, document acceptance and processing, case-
    processing timeliness, quality, and higher volumes. Ex. 65, p. 12. Secretary Roob
    approved many of IBM’s proposed reforms. Appellant’s App. p. 191. Shortly after
    Secretary Roob approved the IBM Coalition’s proposed reforms, Governor Daniels
    appointed Roob as Indiana’s Secretary of Commerce and CEO of the Indiana Economic
    Development Corporation; Anne Murphy replaced Roob as FSSA Secretary. Id.
    In March 2009, Secretary Murphy sent the IBM Coalition a letter drafted by the
    State’s outside counsel requesting a Corrective Action Plan. Id.; Ex. 75 (“The State of
    Indiana has raised with IBM multiple issues with the Modernization Project that need to
    be addressed immediately and believes that it is in the best interest of the State and IBM to
    enter into a Corrective Action Plan as contemplated by Section 15.4.1 of the [MSA].”).
    7
    In addition, there is an issue on appeal as to whether IBM admitted Change Orders 71 and 102
    into evidence. This issue is addressed in IBM’s cross-appeal, which challenges the trial court’s failure to
    award IBM fees for four change orders, including Change Orders 71 and 102.
    14
    The letter identified thirty-six “issues” that the State wanted the IBM Coalition to address,
    including excessive wait times at local offices, incorrectly categorized imaged documents,
    high turnover of staff, scheduling problems, inaccurate and incomplete data gathering,
    clients not receiving mailed correspondence, poor communication to all staff, unresolved
    help-desk tickets, untimely expedited food-stamp processing, excessive wait times for
    applicant appointments, and failure to process Food Stamp, TANF, and Medicaid
    applications in a timely manner. Ex. 75. The IBM Coalition responded to the State’s letter
    and denied that a formal Corrective Action Plan was required under the MSA; nonetheless,
    it expressed a willingness to work with the State to address the issues. Appellant’s App.
    p. 192. The IBM Coalition also argued that twenty-one of the thirty-six issues did not
    relate to any contractual measure or performance standard contained in the MSA while six
    of them related to performance standards that were not yet in effect. Id. While the State
    found “some” of IBM’s responses helpful, it found many of them to be “incomplete, non-
    responsive, insufficient or otherwise unsatisfactory.” Ex. 1929. This implied to the State
    that:
    IBM has not fully appreciated the depth of the State’s concerns about the
    status of the Modernization Project and the Coalition’s failure to achieve
    expected performance objectives in the modernized regions, ongoing failures
    in the As-Is regions and failure to make satisfactory progress on the overall
    implementation of the Modernization Project. These concerns have been
    expressed as well by many key constituencies, including State legislators,
    federal agencies, client advocates and other stakeholders.
    Id.
    On July 2, 2009, the parties agreed on a Corrective Action Plan to address the issues
    that had been raised by the State’s March 2009 letter as well as an independent analysis
    15
    undertaken by IBM. The Corrective Action Plan included twenty-two short-term “Quick
    Wins” and thirty-one long-term initiatives. Appellant’s App. at 192 (citing Ex. 5409).
    But in late July 2009, the federal agency overseeing Medicaid programs—Centers
    for Medicare and Medicaid Services (CMS)—found that Indiana was “consistently not
    meeting Federal eligibility processing requirements.” Id. at 834. CMS noted that since the
    Modernization Project’s rollout, it was “plagued” “by ongoing issues and complaints that
    consumers are losing Medicaid benefits or being denied benefits inappropriately.” Id. The
    problems included extended wait times for processing enrollment applications and in
    receiving responses to Call Center inquiries, lack of responses to enrollment applications,
    and inappropriate disenrollments. Id. CMS noted that these problems, which had garnered
    media attention, “indicate a serious situation in Indiana that is negatively impacting
    consumers’ access to Medicaid.” Id. at 834, 837. Finding that the State was not in
    compliance with several provisions of the United States Code and the Code of Federal
    Regulations, CMS ordered the State to provide its own “Corrective Action Plan (CAP) for
    ensuring that the Federal eligibility requirements are met.” Id. at 837.
    The trial court found that by mid-October 2009, the IBM Coalition had made
    “substantial progress” on the Corrective Action Plan entered into between the State and
    IBM. Id. at 193. As support for this finding, the trial court relied on statements made by
    an attorney general in a September 2009 hearing in Thornton v. Anne Murphy in the United
    States District Court for the Southern District of Indiana. Id. The litigation concerned how
    long it took the State to process applications. The attorney general, speaking for the
    defendant, stated:
    16
    We looked at what were the causes. We tried to identify the causes; and
    we’ve initiated a number of activities to correct those causes, many of
    which—they call it Quick Win[s], but we have made substantial progress in
    a very short period of time.
    Ex. 304, p. 70. The trial court also cited a late September 2009 email which contained
    public statements from Secretary Murphy that “a team of vendors led by IBM Corp. has
    already made improvements in technology and added more staff under a corrective action
    plan submitted in July”; however, Secretary Murphy added that “the timeliness of
    processing applications for food stamps, Medicaid and other benefits has not improved.”8
    Ex. 111.
    Nevertheless, in September 2009, two months after the State and IBM signed the
    Corrective Action Plan, the State decided to change course and adopt a hybrid approach to
    welfare modernization, which the State and IBM referred to as “Plan B.” Id. at 194. Most
    notably, Plan B abandoned the centralized Call Center, moving the eligibility
    determinations to the local office where clients would experience face-to-face interactions
    with FSSA staff handling their cases. Id. at 194-95 (citing Ex. 2085). The State noted that
    “‘[t]he largest difference between the Hybrid System and the modernized system will be
    8
    To support its finding that the IBM Coalition had made substantial progress, the trial court also
    cited an email that contained a June 29, 2009 newspaper article in the Evansville Courier & Press quoting
    Governor Daniels. Two Evansville lawmakers—a State senator and representative—said that their
    constituents had repeatedly complained of long waits on hold with the new call center, lost documents in
    the online system, and lines at local agency offices. Ex. 1105. Although Governor Daniels was quoted as
    saying that the “backlogs are coming way down. Complaints are dropping,” he was also quoted as saying
    that he was “very dissatisfied with at least certain aspects” of the Modernization Project, which led to “one
    very direct conversation with IBM and their partners.” Id. Governor Daniels said that as a result, the
    “contractors understand they have a responsibility to make the new system work without all the glitches.”
    Id. Notably, the article said, “Data showing improvement is not available now.” Id. The article also
    previewed the Corrective Action Plan that the parties ultimately signed on July 2, 2009, which included
    hiring hundreds of workers, retraining workers, and reviewing documents more quickly—all at the IBM
    Coalition’s expense. Id.
    17
    an increased focus on the face-to-face contact.’” Id. at 195 (quoting Ex. 97). The State
    approached IBM about implementing the hybrid plan, but an agreement was never reached
    between the parties because the State could not afford the price that IBM was charging for
    the plan. Id. at 196-98. Even after the parties failed to agree on an IBM-led rollout of the
    hybrid plan, the State encouraged IBM to continue as the technology vendor. Id. at 198.
    On October 15, 2009—less than three years into the ten-year contract—Secretary
    Murphy delivered a letter to IBM explaining that the State was terminating the MSA “in
    whole” “for cause” effective December 14, 2009. Ex. 1555. The State alleged that IBM’s
    breaches included “numerous and repeated quality and timeliness failures.”          Id. In
    addition, the State alleged that pursuant to Section 16.3.1(1)(A) of the MSA, IBM’s
    breaches were material considering the MSA as a whole and IBM could not reasonably
    cure them within thirty days of the notice. Id. The State also alleged that pursuant to
    Section 16.3.1(1)(B) of the MSA, some—but not all—of IBM’s breaches were the subject
    of IBM’s July 2009 Corrective Action Plan, but IBM had not proceeded diligently
    according to the Corrective Action Plan. Id. Finally, the State alleged that pursuant to
    Section 16.3.1(1)(C) of the MSA, IBM’s series of breaches, in view of IBM’s history of
    breaches, collectively constituted a breach of the MSA, which was material considering
    the MSA as a whole, with the last of such breaches occurring within three months of the
    notice of termination. Id.
    On the same day as the termination letter, Governor Daniels held a press conference
    to announce the termination of the MSA and the State’s plan for a “hybrid” system. Ex.
    52. According to the press release, the hybrid system would “incorporate successful
    18
    elements of the old welfare delivery system and what is known as the modernized system”
    and “include more face-to-face contact and more localized team-based case management.”
    Press Release, State ends contract with IBM for welfare services (Oct. 15, 2009),
    http://goo.gl/4d63PF. Also according to the press release, the State canceled the contract
    with IBM because IBM “did not make satisfactory progress to improve services to welfare
    applicants and recipients under a plan to correct deficiencies.” Id. The press release
    continued:
    “The fraud appears to have been stopped and we’re still on track to save
    taxpayers hundreds of millions of dollars, but the intended service
    improvements have not been delivered, and that’s not acceptable,” said
    Daniels. “Those who raised concerns about service quality were correct and
    we appreciate their efforts. We’ll now take the best parts of the old and new
    and move ahead with a hybrid system in what amounts to a major mid-course
    correction.”
    Id. The press release stated that the IBM system suffered from two fundamental flaws in
    concept: (1) the system tried to remove the burden of required face-to-face meetings and
    (2) it used a task-based approach rather than a case-based approach to process applications.
    Id.
    In total, the State paid IBM approximately $437 million under the MSA.
    Appellant’s Br. p. 2; see also Appellee’s Br. p. 8 (“The State continued to make payments
    to IBM and its subcontractors each month without objection, including more than $428
    million over 36 months.” (citing Appellee’s App. p. 247)).
    19
    After the State notified IBM of the termination of the MSA, the State and IBM
    entered into a Disengagement Plan on December 11, 2009.9 See Appellant’s App. p. 869;
    Ex. 472.      The Disengagement Plan set forth the activities of the State and the
    Disengagement Services to be provided by IBM as required by the State in connection with
    its termination of the MSA. Ex. 472, p. 1. Under the Disengagement Plan, the State was
    required to pay IBM $4,412,200 for Disengagement Services. Ex. 472, p. 36. IBM does
    not dispute that the State has paid it $4.4 million for such services. Tr. p. 6739-40. Under
    the section of the Disengagement Plan called “Schedule A—Transfer of Dedicated
    Equipment,” the State was to specify the equipment that it wished to be transferred to it.
    IBM invoiced the State $9,349,654.93 for the computers and furniture that it kept.
    Appellant’s App. p. 889. The State, however, never paid this invoice.
    On May 13, 2010, the State filed a complaint for damages and declaratory relief
    against IBM in Marion Superior Court seeking over $170 million. The State alleged that
    IBM materially breached the MSA as follows:
    9
    The parties contemplated such a plan in the MSA in the event that the contract was terminated.
    MSA § 16.6.1 provided:
    Vendor acknowledges that, upon Termination of this Agreement or Services for any
    reason, in whole or in part, either the State or another service provider (either, a
    “Successor”) may provide services similar to the Services and the Delegated Activities (or
    such portion thereof related to the portion of this Agreement and the Services so
    terminated). In such event, Vendor shall furnish adequate and appropriate phase-out
    services (“Disengagement Services”) pursuant to a Disengagement Plan (“Disengagement
    Plan”), which plan shall be executed prior to the Services Termination Date, with
    Disengagement Services commencing upon the direction of the State and continuing for
    up to six (6) months after this Agreement terminates or such longer period as the State may
    reasonably require (up to a maximum of an additional six (6) months) (“Disengagement
    Period”). The Disengagement Plan shall include the following assistance upon the State’s
    request . . . .
    Appellant’s App. p. 699.
    20
    157. IBM failed to roll out the Modernized system to the entire State by the
    agreed date, implementing the Modernized service in just 59 of Indiana’s 92
    counties.
    158. IBM failed to achieve its promise of improving timeliness, accuracy,
    and client satisfaction and failed to meet established performance measures.
    159. In the counties where IBM rolled out the Modernized system,
    performance standards fell significantly below the non-Modernized counties,
    fell below the counties’ performance prior to the roll-out, and was below
    Federal and State guidelines.
    160. The State provided IBM the opportunity to cure its defective
    performance through the [Corrective Action Plan]; however, IBM failed to
    satisfy the requirements of the [Corrective Action Plan].
    161. IBM has failed to cure its deficient performance.
    Id. at 280. IBM filed a complaint against the State for breach of contract that same day.
    Specifically, IBM sought Deferred Fees of $43,416,738 plus $9,369,898.93 for equipment,
    “pray[ing] for a judgment against the State in the amount of $52,786,636.93, plus
    applicable interest, and for such further relief as warranted under the contract and Indiana
    law as the Court deems just and proper. IBM is entitled to both pre-judgment and post-
    judgment interest, as required under the MSA and Indiana law.” Id. at 337.
    Twelve motions for summary judgment have been filed in this case, three of which
    have bearing on this appeal. An emergency transfer has also been taken to the Indiana
    Supreme Court concerning whether Governor Daniels had to submit to a deposition. See
    State v. Int’l Bus. Machs. Corp., 
    964 N.E.2d 206
     (Ind. 2012). Regarding one of the
    summary-judgment motions, IBM filed a partial motion for summary judgment on its claim
    for subcontractor assignment fees. The MSA included fixed-sum “assignment fees” of $5
    million or $10 million per subcontract to be paid to IBM post-termination if the State
    21
    assumed IBM’s prime-contractor role within the first seven years. The trial court found
    that the State accepted assignment of the seven subcontracts at issue10 and that the
    assignment fees were not an unenforceable penalty as argued by the State because payment
    was not triggered by a breach; rather, the court found that the fees were “compensation for
    valuable contract rights.” Appellant’s App. p. 159-60. Finding no genuine issues of
    material fact and that IBM had demonstrated that it was entitled to judgment as a matter of
    law with respect to its claim for subcontractor assignment fees, the court granted IBM’s
    motion for partial summary judgment on this issue, thereby awarding IBM $40 million in
    assignment fees. Id. at 161 (trial court’s January 25, 2012 summary-judgment order).
    The State filed a motion for summary judgment relating to the impact of the
    economic downtown and flooding on IBM’s performance.                      The trial court granted
    summary judgment on this issue in favor of the State:
    [T]he Court GRANTS the State’s motion for summary judgment number 5,
    and RULES that any contention by IBM at trial that the economic downturn
    or flooding rendered its performance “impossible,” or otherwise excuses any
    failure by IBM to meet any of its contractual obligations under the MSA, is
    precluded as a matter of law[.]
    Id. at 390-91 (trial court’s January 25, 2012 summary-judgment order).
    This case proceeded to a bench trial before the Honorable David J. Dreyer on
    February 27, 2012. The trial lasted six weeks and concluded April 3, 2012. Eight attorneys
    appeared for the State, and eleven attorney appeared for IBM. Id. at 230. Ninety-two
    witnesses testified, and 7500 exhibits were admitted. Id. at 231. During trial, the State
    moved for reconsideration of the trial court’s earlier summary judgment in favor of IBM
    10
    The subcontracts at issue were for ACS, Arbor, Haverstick, Interactive Intelligence, Phoenix,
    PostMasters, and RCR.
    22
    on subcontractor assignment fees, which the trial court denied. Id. at 396 (trial-court
    order). Then, on July 18, 2012, the trial court issued sixty-five pages of findings of fact
    and conclusions of law plus an eight-page appendix. In the order, the trial court ruled as
    follows:
    Breach for cause or for convenience?—the trial court found that the State
    failed to prove that IBM materially breached the MSA and that IBM
    substantially performed under the contract (which practically meant that the
    court found that termination was for convenience rather than for cause). Id.
    at 201.
    Subcontractor Assignment Fees—the trial court affirmed its earlier
    summary-judgment order that awarded IBM $40 million in assignment fees.
    Id. at 220.
    Deferred Fees—the trial court found that IBM failed to show that the
    $43,416,738 claimed in Deferred Fees was reasonable and proportionate as
    liquidated damages. Id. at 224-227.
    Early Termination Close Out Payments—the trial court found that IBM
    was entitled to $2,570,621 in Early Termination Close Out Payments due
    under MSA § 16.6.6, which included actual costs that IBM incurred as a
    result of the State’s premature termination of the MSA.11 Id. at 221-22.
    11
    According to the trial court’s order:
    128. IBM is entitled to $2,570,621 in “Early Termination Close Out Payments” due under
    MSA § 16.6.6. These include actual costs IBM incurred as a result of the State’s premature
    termination. The State’s only defense to payment of these costs is that they are not due in
    the event of termination for cause. The State did not introduce any credible evidence
    suggesting that IBM did not incur these costs or challenging the amount of these costs. The
    Early Termination Close Out Payments owed by the State are as follows: (1) $2,305,964.37
    in prepared software costs owed under MSA § 16.6.6(3); (2) $31,143.58 in lease
    termination payments owed under MSA § 16.6.6(3)(C) to end the lease on IBM’s
    Indianapolis office space; (3) $61,284 in improvement costs IBM incurred in improving its
    Indianapolis offices owed under MSA § 16.6.6(3)(D); and (4) $101,763 in salary and labor
    costs for IBM employees and $71,466 for Crowe employees idled as a result of the
    termination, which are owed under MSA § 16.6.6(4)(B) because the State gave less than
    75 days notice.
    Appellant’s App. p. 221-22 (footnotes omitted).
    23
    Equipment—the trial court found that IBM was entitled to $9,510,795 for
    the value of the Equipment that the State kept after terminating the MSA. Id.
    at 220.
    Change Order Fees—the trial court found that IBM was not entitled to fees
    for four Change Orders because the record showed evidence for only two of
    the four Change Orders. As for the two Change Orders in the record, the
    court found that the changes predated the MSA and therefore IBM should
    have initially incorporated them into the project. Id. at 227-28.
    Prejudgment Interest—the trial court found that IBM was entitled to
    prejudgment interest and gave IBM thirty days to submit a separate petition
    calculating the prejudgment interest. Id. at 222.
    IBM timely submitted a petition calculating the prejudgment interest, to which the
    State objected on grounds that state law forbids prejudgment interest against the State.
    Nevertheless, on August 14, the trial court awarded IBM $10,632,333 in prejudgment
    interest.
    The State appeals, and IBM cross-appeals. We held an extended oral argument in
    this case on November 25, 2013. Both parties then filed post-argument submissions.
    Discussion and Decision
    This case involves the interpretation of a $1.3 billion contract entered into by two
    sophisticated parties—the State of Indiana—represented by both outside counsel and the
    Attorney General’s Office—and IBM—a multinational technology and consulting
    company—represented by multiple attorneys. Both parties alleged breach of this more
    than 160-page contract.
    The ultimate goal of any contract interpretation is to determine the intent of the
    parties when they made the agreement. Citimortgage, Inc. v. Barabas, 
    975 N.E.2d 805
    ,
    813 (Ind. 2012), reh’g denied. We begin with the plain language of the contract, reading
    24
    it in context and, whenever possible, construing it so as to render each word, phrase, and
    term meaningful, unambiguous, and harmonious with the whole. 
    Id.
     “A contract is
    ambiguous if a reasonable person would find the contract subject to more than one
    interpretation.” 
    Id.
     (quotation omitted). If the language is unambiguous, we may not look
    to extrinsic evidence to expand, vary, or explain the instrument but must determine the
    parties’ intent from the four corners of the instrument. Bd. of Commr’s of Delaware Cnty.
    v. Evans, 
    979 N.E.2d 1042
    , 1046 (Ind. Ct. App. 2012); Niezer v. Todd Realty, Inc., 
    913 N.E.2d 211
    , 215 (Ind. Ct. App. 2009), trans. denied.           However, if the language is
    ambiguous, we may look to extrinsic evidence and will construe the terms to determine
    and give effect to the intent of the parties when they entered into the contract. Barabas,
    975 N.E.2d at 813. “[C]onstruction of the terms of a written contract is a pure question of
    law for the court, reviewed de novo.” Harrison v. Thomas, 
    761 N.E.2d 816
    , 818 (Ind.
    2002).
    I. Material Breach
    The first issue to be determined is whether IBM materially breached the contract.
    The trial court concluded that the State failed to prove that IBM materially breached the
    MSA. Whether IBM materially breached the contract impacts other issues in this case.
    The trial court determined on summary judgment that IBM was not entitled to $43,416,738
    in Deferred Fees if it materially breached the contract. Moreover, whether the State must
    pay Early Termination Close Out Payments depends on whether it terminated the contract
    for cause or for convenience. Because of the significance of the breach issue, we address
    it first.
    25
    According to MSA § 16.3.1(1)(A), in order to terminate the MSA for cause, the
    State had to prove a breach by IBM that was “material considering this Agreement as a
    whole[.]” Appellant’s App. p. 692. A material breach is one that goes to the heart of the
    contract. Steve Silveus Ins., Inc. v. Goshert, 
    873 N.E.2d 165
    , 175 (Ind. Ct. App. 2007). In
    determining whether a breach is material, the following five factors are considered:
    (a) the extent to which the injured party will be deprived of the benefit which
    he reasonably expected;
    (b) the extent to which the injured party can be adequately compensated for
    the part of that benefit of which he will be deprived;
    (c) the extent to which the party failing to perform or to offer to perform will
    suffer forfeiture;
    (d) the likelihood that the party failing to perform or to offer to perform will
    cure his failure, taking account of all the circumstances including any
    reasonable assurances;
    (e) the extent to which the behavior of the party failing to perform or to offer
    to perform comports with standards of good faith and fair dealing.
    Collins v. McKinney, 
    871 N.E.2d 363
    , 375 (Ind. Ct. App. 2007); see also Ream v. Yankee
    Park Homeowner’s Ass’n, Inc., 
    915 N.E.2d 536
    , 543 (Ind. Ct. App. 2009), trans. denied;
    Frazier v. Mellowitz, 
    804 N.E.2d 796
    , 803 (Ind. Ct. App. 2004) (adopting the Restatement
    (Second) of Contracts § 241 (1981)). Whether a breach is material is generally a question
    of fact to be decided by the trier of fact. Collins, 
    871 N.E.2d 375
    ; see also Roche
    Diagnostics Operations, Inc. v. Marsh Supermarkets, LLC, 
    987 N.E.2d 72
    , 83 (Ind. Ct.
    App. 2013), trans. denied.
    We also must look to the Performance Measurements set forth in the MSA.
    Pursuant to MSA § 3.8.1,
    Vendor will ensure that the Services will be performed and delivered in a
    manner that (i) meets or exceeds the required levels of performance,
    including the Performance Standards specified in or pursuant to this
    Agreement, (ii) is effective, efficient and courteous to the Clients, and (iii)
    26
    uses Commercially Reasonable Efforts[12] to support the State’s achievement
    of its Policy Objectives.
    Appellant’s App. p. 591. According to MSA § 3.8.2, satisfactory performance of the
    Agreement by IBM “will be measured by” eight standards:
    (1) Adherence to all the terms of this Agreement, including all covenants,
    obligations, representations and warranties;
    (2) Performance in accordance with and compliance with the Modernization
    Project work plans, schedules, and milestones agreed to by the Parties;
    (3) Performance of the Services in accordance with all applicable
    requirements of this Agreement, including the Performance Standards set
    forth in Schedule 10 [Performance Standards];
    (4) Satisfactory results of Audits by the State, its representatives, or other
    authorized Persons in accordance with Article 9 (with all results of such
    Audits being addressed in accordance with the Governance Plan);
    (5) Attendance at and participation in the DFR financial review and other
    meetings conducted from time to time by FSSA (both internally and with the
    public);
    (6) Timeliness, completeness, and accuracy of required reports;
    12
    “Commercially Reasonable Efforts” means “taking commercially reasonable steps and
    performing in such a manner as a well managed entity would undertake with respect to a matter in which it
    was acting in a determined, prudent, businesslike and reasonable manner to achieve a particular result.”
    Appellant’s App. p. 761-62.
    27
    (7) Determination by the State of (i) Vendor’s satisfactory performance of
    the Services[13] and the Delegated Activities,[14] and (ii) Vendor’s satisfactory
    oversight and management of the Subcontractors; and
    (8) Vendor’s efforts to assist the State in achieving the Policy Objectives.
    Id. at 591-92.
    Because the trial court entered special findings and conclusions according to Indiana
    Trial Rule 52(A), our standard of review is two-tiered.15 Marion Cnty. Auditor v. Sawmill
    Creek, LLC, 
    964 N.E.2d 213
    , 217 (Ind. 2012) (citation omitted). We first determine
    whether the evidence supports the findings and then whether the findings support the
    judgment. 
    Id.
     Appellate courts “shall not set aside the findings or judgment unless clearly
    erroneous.” Ind. Trial Rule 52(A). “In reviewing the trial court’s entry of special findings,
    13
    The MSA defined “Services” as:
    the tasks, functions, and responsibilities of Vendor under the Agreement expressly assigned
    and delegated to Vendor, and any incidental or ancillary tasks, functions, or responsibilities
    not expressly described in the Agreement but that are necessary and appropriate subtasks
    for the successful performance of the Services and the Agreement, including Delegated
    Activities. The Services will include such additional activities as are from time to time
    agreed between the Parties but do not include Retained Activities.
    Appellant’s App. p. 776-77.
    14
    The MSA defined “Delegated Activities” as:
    all functions and responsibilities being performed by the Affected Employees as of the
    Service Commencement Date, except as modified by the Agreement, the activities set forth
    in the Statement of Work (but excluding the Retained Activities), and any additional
    functions that may thereafter be delegated to Vendor by mutual agreement of the Parties.
    Appellant’s App. p. 764.
    15
    Although the parties submitted proposed findings and conclusions, it is not clear whether this
    was at the trial court’s request or in accordance with a Trial Rule 52(A) motion. If the trial court entered
    findings and conclusions sua sponte, our standard of review is slightly altered. On those issues which the
    trial court has not found, or for which the findings are inadequate, we treat the judgment as a general one,
    and we may affirm a general judgment on any legal theory the evidence supports. Harrison v. Thomas, 
    761 N.E.2d 816
    , 819 (Ind. 2002).
    28
    we neither reweigh the evidence nor reassess the credibility of the witnesses.” Sawmill
    Creek, 964 N.E.2d at 216 (citation omitted).          We view the evidence in the light
    most favorable to the judgment, and we will defer to the trial court’s factual findings if they
    are supported by the evidence and any legitimate inferences therefrom. Id. at 217 (citation
    omitted). Legal conclusions, conversely, are reviewed de novo. Id. “A judgment is clearly
    erroneous if it applies the wrong legal standard to properly found facts.” Id. (citation
    omitted).
    The trial court concluded that the State failed to prove that IBM materially breached
    the contract by employing a balancing test:
    100. Looking at the whole contract and IBM’s whole performance, at least
    substantial performance is clearly shown as a matter of fact. The State’s case
    extrapolates from a number of general examples of frustrated welfare
    applicants and State workers, and even attempts to estimate from data that as
    many as 80,000 or more applications (out of 1 million) were processed late
    during the 12 measured months of IBM’s management. Taken as true, these
    examples still have to be balanced against the whole contract and IBM’s
    whole performance showing benefits to the State and adhering to MSA policy
    objectives. Accordingly, the heart of the contract remained intact, although
    sometimes beating irregularly.
    Appellant’s App. p. 210 (emphasis added). In determining whether any breach went to
    the heart of the contract, we find that the core of the contract is identified in the following
    “Policy Objectives” in the MSA:
    The overarching policy objectives of the Modernization Project and this
    Agreement are (i) to provide efficient, accurate and timely eligibility
    determinations for individuals and families who qualify for public assistance,
    (ii) to improve the availability, quality and reliability of the services being
    provided to Clients by expanding access to such services, decreasing
    inconvenience and improving response times, among other improvements,
    (iii) to assist and support Clients through programs that foster personal
    responsibility, independence and social and economic self-sufficiency, (iv)
    to assure compliance with all relevant Laws, (v) to assure the protection and
    29
    integrity of Personal Information gathered in connection with eligibility
    determination, and (vi) to foster the development of policies and procedures
    that underscore the importance of accuracy in eligibility determinations,
    caseload integrity across all areas of public assistance and work and work-
    related experience for Clients in the Programs.
    Id. at 567 (MSA § 1.1(1)). In other words, the essence of the Modernization Project was
    to provide and expand access to services for welfare recipients in a timely, reliable, and
    efficient manner within federal guidelines, to discourage fraud, and to increase work-
    participation rates—all of which were problems that plagued the earlier system. Contrary
    to the trial court’s implication in Conclusion No. 100, whether IBM materially breached
    the contract does not require balancing the number of benefits the State received versus the
    number of performance standards that IBM failed. Rather, the issue is whether any breach
    went to the essence of the contract—to provide and expand access to services for welfare
    recipients in a timely, reliable, and efficient manner within federal guidelines, to discourage
    fraud, and to increase work-participation rates.
    A. The State’s Arguments
    The State’s Dissatisfaction with IBM’s Performance.           Although the evidence
    showed that the State was not satisfied with IBM’s performance, the trial court concluded
    that the State’s dissatisfaction with IBM’s performance did not support a claim of breach
    (much less a claim of material breach); instead, it was merely one of eight enumerated
    ways in which IBM’s performance was to be judged.
    According to MSA § 3.8.2, satisfactory performance of the Agreement by IBM “will
    be measured by” eight standards, including “Determination by the State of (i) Vendor’s
    satisfactory performance of the Services and the Delegated Activities.” Id. at 592. The
    30
    State presented evidence at trial from several people establishing that the State was not
    satisfied with IBM’s performance, including Brian Whitfield, IBM Vice President of State
    and Local Government when the MSA was executed. Whitfield testified that the “project
    didn’t perform at a level that I would have found to be satisfactory” and conceded that the
    State was not satisfied with IBM’s performance in 2009 and had a reasonable basis to be
    dissatisfied. Tr. p. 6381-82. Steve Zaudtke, IBM on-site project executive, similarly
    testified that there were problems in 2009 with IBM’s performance and that overall the
    State was not satisfied. Id. at 6867-68. And John Lyons, IBM’s trial representative,
    conceded that over the course of the six-week trial he never heard any of the witnesses say
    that IBM’s performance was good in 2009. Id. at 7670.
    Despite this clear evidence of the State’s dissatisfaction, the trial court concluded:
    107. Beyond Schedule 10, the State points to record evidence, including
    confirming documents and testimony by IBM witnesses, that the State was
    “dissatisfied” with aspects of the Modernization Project (as was IBM), and
    claims IBM was in breach under § 3.8.2(7). However, this provision does
    not say that the State’s dissatisfaction will support a claim of breach (much
    less a claim of material breach), but rather that the State’s level of satisfaction
    is one of eight enumerated ways in which IBM’s performance will be judged.
    As found above, the problems with the Modernization Project that can be
    attributed to IBM under the contract are not material when compared to the
    MSA as a whole and the bargained-for benefits that the State received.
    Appellant’s App. p. 214 (emphasis added).
    A party to a contract involving requirements of commercial quality, operative fitness,
    or mechanical utility may condition its obligation to pay upon that party’s satisfaction that
    the other party’s performance meets the applicable standard. Greg Allen Constr. Co. v.
    Estelle, 
    762 N.E.2d 760
    , 772-73 (Ind. Ct. App. 2002), summarily aff’d in pertinent part by
    
    798 N.E.2d 171
     (Ind. 2003), reh’g denied. A party’s evaluation of the other party’s
    31
    performance under these criteria will be judged against a reasonable-person standard, and
    dissatisfaction may not be claimed arbitrarily, capriciously, or unreasonably. Id. at 773. A
    party should be satisfied with another party’s performance if a reasonable person in the
    same circumstances would be satisfied. Id.
    The State argues that under this standard, it had a reasonable basis to be dissatisfied
    with IBM’s performance and that IBM’s unsatisfactory performance is not “immaterial.”
    Although the State’s determination of whether IBM’s performance of Services was
    satisfactory was just one standard to be considered, IBM witnesses admitted that the State
    was and had a reasonable basis to be dissatisfied with its performance. The State’s
    dissatisfaction should have been considered by the trial court in determining whether there
    was a material breach.
    Failing Performance Standards. The State argues that the trial court erred by
    concluding that IBM’s failing Key Performance Indicators were not cause to terminate the
    Agreement because IBM paid liquidated damages under MSA § 15.2.3(3) as an alternative
    means of performance. Appellant’s App. p. 212-13 (Conclusion No. 105). In the event of
    a breach by IBM, MSA § 15.2.5(3) permitted liquidated damages as follows:
    The Liquidated Damages and Service Level Credits prescribed in Schedule
    10 [Performance Standards] and referenced in this Section are not intended
    to be in the nature of a penalty, but are intended to be reasonable estimates
    of the State’s projected financial loss and damage resulting from Vendor’s
    breach, including financial loss as a result of Modernization Project delays
    or other events identified in Schedule 10. Accordingly, in the event an event
    set forth in Schedule 10 occurs, the State may assess Liquidated Damages
    and Service Level Credits as set forth in Schedule 10.
    32
    Id. at 685. The trial court noted that the State’s main argument and focus was the Schedule
    10 timeliness metric.16 Id. at 211. Although the trial court found that “[Key Performance
    Indicator] metrics for timeliness were consistently missing the mark,” the court explained
    that the MSA and Schedule 10 showed that the timeliness metric was “of the same
    importance as the 19 of 24 [Key Performance Indicators] that the Coalition consistently
    met, including performance reporting, system availability, document scanning, document
    indexing, constituent care response time, and Help Center availability.” Id. at 210, 211.
    Accordingly, the trial court concluded:
    105. The [Key Performance Indicators], including timeliness, were
    associated with identical liquidated damages, in an amount that the State
    described as “miniscule,” a reasonable indicator of the weight the parties
    gave to these measures in the agreement. . . . The MSA provides that the
    specified liquidated damages constitute “reasonable estimates of the State’s
    projected financial loss and damage resulting from Vendor’s breach . . . .”
    (MSA § 15.2.5(3)). Liquidated damages were paid in lieu of performance
    and provided IBM with an alternative means of performance that was
    satisfied by payment (which payment is undisputed). . . . The Court finds
    based on the complete record in this case, including the testimony of the
    witnesses, that the Coalition’s failures to meet certain Schedule 10 metrics
    did not constitute a breach of the MSA in light of IBM’s payment of
    liquidated damages.
    Id. at 212-13.
    The State acknowledges that the MSA provided that the liquidated damages
    prescribed in Schedule 10 were the “sole and exclusive remedy” for certain damages
    arising out of or caused by IBM’s Key Performance Indicator failures; however, the MSA
    also provided that this “shall not limit (i) any applicable State termination rights in Article
    16
    The trial court specifically found that “[t]he State claims that the Coalition (in this case the
    primary subcontractor, ACS) consistently missed the [Key Performance Indicators] for Call Center
    abandonment, timely processing of applications and redeterminations, and the SLMs for adherence to
    proper process procedures . . . .” Appellant’s App. p. 211.
    33
    16 . . . .” Id. at 685 (MSA § 15.2.5(4)). Notably, MSA § 16.3.1(1)(C) authorized
    termination for cause, including for:
    a series of breaches of Vendor’s obligations, none of which individually,
    constitutes a breach of this Agreement which is material considering this
    Agreement as a whole, but which, in view of Vendor’s history of breaches,
    whether or not cured, collectively constitute a breach of this Agreement
    which is material when considering this Agreement as a whole . . . .
    Id. at 692. Accordingly, the State argues that treating MSA § 15.2.5(3) liquidated-damages
    payments as the State’s exclusive remedy was “flat error.” Appellant’s Br. p. 40. We
    agree. Not only did the MSA address alternative remedies, but it also stated that IBM’s
    paying liquidated damages for Key Performance Indicator failures did not deprive the State
    of any termination rights, including for-cause termination for a “series” or “history of
    breaches, whether or not cured.” Therefore, the trial court should have considered the IBM
    Coalition’s failures to meet certain Schedule 10 metrics in determining whether there was
    a material breach.
    IBM’s Failure to Satisfy Legal Standards. The State argues that the trial court’s
    conclusion that IBM’s breaches were not material “ignored other MSA provisions and
    uncontradicted evidence, including that IBM’s performance failed to meet Federal legal
    standards.” Id. The MSA’s first-listed Policy Objective was “to provide efficient, accurate
    and timely eligibility determinations for individuals and families who qualify for public
    assistance.”   Appellant’s App. p. 567.      Notably, the trial court found that “[Key
    Performance Indicator] metrics for timeliness were consistently missing the mark.” Id. at
    210. In other words, the IBM Coalition was failing on the very issues that the Policy
    Objectives deemed to be vital. Accordingly, in determining whether there was a material
    34
    breach, the trial court should have considered the IBM Coalition’s breach of performance
    obligations on the very matters that the MSA stated were its overarching policy objectives.
    In addition, ensuring “compliance with all relevant Laws” was another explicit
    Policy Objective. Id. at 567. The State cites evidence that in late July 2009, which was
    less than two months before the State terminated the MSA for quality and timeliness issues,
    CMS—the federal agency overseeing Medicaid programs—found that Indiana was
    “consistently not meeting Federal eligibility processing requirements.” Id. at 834. CMS
    noted that since the Modernization Project’s rollout, it was “plagued” “by ongoing issues
    and complaints that consumers are losing Medicaid benefits or being denied benefits
    inappropriately.”   Id.   The problems included extended wait times for processing
    enrollment applications and in receiving responses to Call Center inquiries, lack of
    responses to enrollment applications, and inappropriate disenrollments. Id. CMS noted
    that these problems, which had garnered media attention, “indicate a serious situation in
    Indiana that is negatively impacting consumers’ access to Medicaid.” Id. at 834, 837.
    Finding that the State was not in compliance with several provisions of the United States
    Code and the Code of Federal Regulations, CMS ordered the State to provide its own
    “Corrective Action Plan (CAP) for ensuring that the Federal eligibility requirements are
    met.” Id. at 837. CMS noted that while the State and IBM’s Corrective Action Plan was
    a “good start in the monitoring of IBM’s performance,” the State needed its own plan. Id.
    35
    IBM responds that the parties specifically agreed in MSA § 15.2.6(1) that the State’s
    “sole and exclusive” remedy for “failure to meet the Federal Program Targets” 17 was
    liquidated damages amounting to 50% of the State’s federal penalty and that this remedy
    was available only during Steady State, a phase that was never reached. See id. at 686-87.
    But as the State points out, IBM does not acknowledge the very next sentence in the MSA,
    which states: “the foregoing shall not limit any applicable termination rights of the State
    set forth in Article 16 [which governs termination].” Id. at 687. Accordingly, the trial
    court should have considered IBM’s failures to meet Federal Program Targets in
    determining whether to terminate the contract for cause.
    Economic Downturn and Flooding. The State argues that the trial court improperly
    considered the economic downturn and flooding as reasons to excuse IBM’s performance.
    We start with the economic recession. Specifically, the court found that two months after
    the rollout of the pilot region, “the State and the country began to feel the effects of what
    has been termed the ‘Great Recession.’” Id. at 185 (Finding No. 42). The court observed
    that almost immediately, benefit applications increased 21% and the number of processed
    applications increased 41% compared to the previous year. Id. The court dubbed the
    recession, “the most severe crisis since the Great Depression.” Id. In addition, the court
    noted that Indiana’s unemployment rate had more than doubled since the MSA was
    executed and was higher than the national average. Id. (Finding No. 43). The court noted
    that in response to the economic crisis, in February 2009 Congress passed stimulus
    17
    “Federal Program Targets” are defined as federal TANF minimum work participation
    requirements for the All Family Participation rate and federal Food Stamp error rate requirements.
    Appellant’s App. p. 686.
    36
    legislation, which, among other things, increased the benefits to food-stamp recipients. Id.
    at 186 (Finding No. 45).
    The State argues that the trial court wrongly relied on these events because the MSA
    provided IBM an appropriate remedy “if recession and legislative responses threatened its
    performance—the Change Order Process.” Appellant’s Br. p. 42. Specifically, MSA §
    4.1.3, entitled Material Assumptions, provided:
    The Parties have negotiated the Fees in reliance upon the material
    assumptions set forth in Schedule 11 [Material Assumptions] (“Material
    Assumptions”). The Parties acknowledge that other than such Material
    Assumptions, Vendor has not relied upon any other assumptions that are
    material to this Agreement, the Services, or the Fees (or any components
    thereof). Vendor acknowledges that any changes to any of its internal,
    implied or inherent assumptions which are not included in the Material
    Assumptions shall be at its risk and shall not serve as a basis for requesting
    a Change or an increase in the Fees and that an inaccuracy or error in any of
    the Material Assumptions shall not automatically entitle Vendor to any
    Change which it may request, but any such Change shall be made solely
    pursuant to the Change Order Process. At the reasonable request of Vendor
    or the State, the Parties shall engage in good faith negotiations of any
    Changes to address any inaccuracy or error in one or more of the Material
    Assumptions.
    Appellant’s App. p. 608-09 (emphasis added). The Material Assumptions included that
    during the contract term, there would be no “material economic downturn in Indiana.” Id.
    at 754. Therefore, the State argues, while an inaccuracy or error in any of the Material
    Assumptions did not automatically entitle IBM to a Change, the MSA provided that IBM
    could request changes in light of erroneous assumptions—“but any such Change shall be
    made solely pursuant to the Change Order Process.” No such request was made here.
    As for flooding, the trial court found:
    46. Compounding the challenges presented by the economic downturn and
    the Project’s expansion to HIP, Indiana was hit by a series of natural disasters
    37
    during 2008, which displaced thousands of Hoosiers from their homes and
    caused nearly $2 billion in economic damages. As described by the State,
    “[t]he 2008 disasters in Indiana have been among the worst in our state’s
    history.” Eighty-two of Indiana’s 92 counties were declared Presidential
    Disaster Areas during 2008. . . .
    Id. at 186-87 (footnotes omitted). The trial court also found that “[t]he State directed the
    reassignment of approximately one third of the State and IBM Coalition workforce ‘from
    every available post,’ ‘modernized or as-is,’ to assist with the processing of tens of
    thousands of emergency food statement applications” and “thousands of FEMA Individual
    Assistance applications[.]” Id. at 187.
    The State again argues that “the parties anticipated and accounted for the
    implications of unpredictable weather” in the MSA. Specifically, MSA § 21.22 provided:
    In the event that because of [a] Force Majeure Event, Vendor is unable to
    perform any of its obligations under this Agreement or such performance is
    rendered impractical, Vendor shall provide notice to the State as soon as
    practicable and shall use Commercially Reasonable Efforts to resume
    performance of the Services to the extent practicable, despite the Force
    Majeure Event.
    Id. at 732. The MSA’s definition of “Force Majeure Event” included “flood.” Id. at 767.
    IBM did not give the State notice pursuant to MSA § 21.22.18
    As for both the economic downturn and flooding, the State also argues that the trial
    court ignored its pretrial rulings. That is, the State filed a motion for summary judgment
    relating to the impact of the economic downturn and flooding on IBM’s performance. The
    trial court entered summary judgment in favor of the State, concluding:
    [A]ny contention by IBM at trial that the economic downturn rendered its
    performance “impossible,” or otherwise excuses any failure to IBM to meet
    18
    However, the trial court found that these disasters affected the rollout of the project, which was
    eventually suspended by mutual agreement of the parties in September 2008 in Change Order 69 in order
    to accommodate disaster-relief efforts. Appellant’s App. p. 188.
    38
    any of its contractual obligations under the MSA, is precluded as a matter of
    law; and evidence about the claimed impact of the economic downturn on
    IBM’s ability to meet its contractual obligations is irrelevant and
    inadmissible.
    *****
    Any contention by IBM at trial that flooding rendered its performance
    “impossible,” or otherwise excuses any failure to IBM to meet any of its
    contractual obligations under the MSA, is therefore precluded as a matter of
    law; and evidence about the claimed impact of flooding on IBM’s ability to
    meet its contractual obligations is irrelevant and inadmissible.
    For these reasons, the Court GRANTS the State’s motion for
    summary judgment number 5, and RULES that any contention by IBM at
    trial that the economic downturn or flooding rendered its performance
    “impossible,” or otherwise excuses any failure by IBM to meet any of its
    contractual obligations under the MSA, is precluded as a matter of law[.]
    Id. at 390-91 (trial court’s January 25, 2012 summary-judgment order). In response to this
    argument, IBM argues that the trial court considered these circumstances “not to excuse
    IBM’s performance, but to conduct the required analysis under the Restatement [(Second)
    of Contracts] as to whether the timeliness failures amounted to a material breach.”
    Appellee’s Br. p 37. We find that this difference does not matter. See Appellant’s Reply
    Br. p. 34. Because the MSA provided IBM with a remedy in the event of an economic
    downturn or flooding, the trial court should not have considered the economic downturn
    and flooding as reasons to excuse IBM’s performance.
    Surge in Applications from the HIP. The State argues that the trial court improperly
    considered any surge in applications from the HIP as a reason for IBM’s performance
    issues. Specifically, the trial court found that the “HIP significantly increased the scope
    and cost of the Modernization Project by adding design, development, implementation,
    continuing services, and reporting requirements.” Appellant’s App. p. 184 (Finding No.
    39
    40). The court also found that the “HIP application volume regularly exceeded the State’s
    predictions. . . . The State described this as a significant challenge for the modernized
    system.” Id. at 184-85 (Finding No. 41) (citation omitted).
    However, the MSA specified procedures for seeking service and fee changes when
    IBM thought that it was warranted. MSA § 3.4.3(3) provided:
    Upon the occurrence of a Force Majeure Event or any sudden and
    material increase in the number of Clients utilizing the Services beyond that
    which might reasonably be anticipated, Vendor shall be entitled to provide
    the Services at a location other than a Service Location on a temporary basis
    . . . . Vendor may make this determination in its discretion, and any
    additional charges associated therewith shall be determined in an equitable
    manner in accordance with the Change Order Process.
    Id. at 583-84. In addition, MSA § 3.12.3(1) provided that a change “relating to an
    expansion of or change to the Services” required a Change Request.19 Id. at 597.
    As the State points out, the record shows that IBM “obtained numerous change
    orders, yielding $177 million in increased fees.” Appellant’s Br. p. 36. Moreover, the
    State notes that when the trial court explained that the HIP “significantly increased the
    scope and cost of the Modernization Project,” the court cited an actual change order—
    Change Order 23 in Exhibit 1500.023. Appellant’s App. p. 184 (Finding No. 184).
    Because the trial court cited a specific change order in its findings, the State contends that
    IBM received a “double remedy”—“IBM first received more fees; then, when it still did
    not meet performance standards, its failings were excused.” Appellant’s Br. p. 46. We
    agree with the State; in determining whether the breach was material, the trial court should
    19
    A “Change Request” is “any request by a Party for a Change as contemplated by Section 3.11.3.”
    Appellant’s App. p. 761.
    40
    not have considered any surge in applications from the HIP as a reason for IBM’s
    performance issues.
    The State’s Motives for Terminating the MSA. The State argues that the trial court
    improperly considered that the State might have had other motives for terminating the
    MSA. In its findings, the trial court noted that on the same day that the State delivered the
    MSA termination letter to IBM, Governor Daniels held a press conference in which he
    commended IBM for its work, citing a number of benefits that IBM had conferred on the
    State. Appellant’s App. p. 199. In addition, Governor Daniels acknowledged, “They
    [IBM] did try hard. If resources would have fixed the problem, we wouldn’t be making
    this announcement . . . . It wasn’t resources. It wasn’t effort. It was a flawed concept that
    simply did not work out in practice.” Id. at 199-200. In essence, IBM argues that the State
    did not terminate the MSA for “performance issues,” as they have maintained in this
    litigation.
    But as the State points out, a party’s motives or reasons for making contract
    decisions are generally regarded as irrelevant. See Epperly v. Johnson, 
    734 N.E.2d 1066
    ,
    1073 (Ind. Ct. App. 2000) (citing Vernon Fire & Cas. Ins. Co. v. Sharp, 
    264 Ind. 599
    , 
    349 N.E.2d 173
    , 180 (1976)); see also Tuf Racing Prods., Inc. v. Am. Suzuki Motor Co., 
    223 F.3d 585
    , 589 (7th Cir. 2000) (“In the law of contracts, while procuring a breach by the
    other party to your contract would excuse the breach, merely having a bad motive for
    terminating a contract would not. If a party has a legal right to terminate the contract (the
    clearest example is where the contract is terminable at will by either party), its motive for
    exercising that right is irrelevant.” (citations omitted)).
    41
    Moreover, Justice Sullivan applied these principles in the earlier decision in this
    case that vacated the trial court’s order to depose Governor Daniels. In his concurring-in-
    result opinion, Justice Sullivan found it unnecessary to discuss the gubernatorial privilege
    because—contrary to IBM’s contentions—any such testimony was irrelevant: “Neither the
    Governor’s ‘assessment of IBM’s performance’ nor his ‘state of mind’ bear in any way on
    whether or not IBM breached the contract or the State owes IBM fees or reimbursement.”
    Int’l Bus. Machs., 964 N.E.2d at 212 (Sullivan, J., concurring in result) (citing Sharp, 
    349 N.E.2d at 180
    ). In determining whether the breach was material, the trial court should not
    have considered that the State might have had other motives or reasons for terminating the
    MSA.
    B. IBM’s Arguments
    IBM, on the other hand, argues that “[o]verwhelming factual findings support the
    court’s finding of no material breach. The vast majority are not even mentioned in the
    State’s brief, much less challenged.” Appellee’s Br. p. 29. We address each of them.
    IBM’s first argument is essentially the trial court’s balancing test—because the State
    received an array of benefits, there was no material breach. IBM points to the following
    benefits that the State received: (1) dramatic improvement in work-participation rates as
    part of the welfare-to-work program, Appellant’s App. p. 204; (2) reduction in fraud, 
    id. at 205
    ; (3) programmatic and administrative cost savings totaling approximately $40 million
    per year, 
    id. at 205-06
    ; (4) modern electronic access to the eligibility system, including the
    online filing of applications, 
    id. at 206
    ; (5) the electronic “paperless” system, which was
    preferred over boxes, id.; (6) the Work Flow Management System (WFMS), which the
    42
    State carried over to the hybrid system, 
    id. at 207
    ; (7) the HIP, which state officials
    described as “an unqualified success,” id.; (8) the valuable contribution that the IBM
    Coalition members made in responding to the 2008 natural disasters, 
    id. at 208
    ; and (9)
    economic development, which, as Governor Daniels explained during his 2009 press
    conference, brought 1000 new private-sector jobs to Daleville and Anderson, 
    id. at 209
    .
    IBM argues that on top of these benefits, the trial court found that IBM’s work
    provided the foundation for the successful hybrid system. As the trial court explained,
    “Modernization is the foundation on which the State Hybrid system now stands. For better
    or worse, and through much transition difficulty, the contract, including IBM’s efforts,
    conferred the overall aggregate benefit sought by the State: a new welfare system that
    works better.” 
    Id. at 204
    .
    However, as we explained above and as the State points out, IBM misses the point
    by highlighting the benefits the State received. The State readily concedes that it received
    benefits under the MSA, “under [which] it paid IBM over $437,000,000.” Appellant’s
    Reply Br. p. 28. As the State says, “one would hope the State got something for its $437
    million.” 
    Id.
     Although it is undisputed that IBM met some objectives and provided some
    important benefits, the question is whether IBM’s failures went to the essence of the
    contract—to provide and expand access to services for welfare recipients in a timely,
    reliable, and efficient manner within federal guidelines, to discourage fraud, and to increase
    work-participation rates.
    IBM next argues that the breach was not material because the State asked IBM to
    implement the hybrid system; in other words, if the State was truly dissatisfied with IBM’s
    43
    services, it would not have asked IBM to continue providing services. The trial court found
    that beginning in September 2009, “the State actively pursued IBM in the hope that it would
    implement the Hybrid plan” and “[o]nly when the State’s budget crisis prevented the
    parties from reaching an agreement on financial terms did the State decide that it would
    ‘cut[] out the middle man’ and terminate the IBM contract.” Appellant’s App. p. 196, 198
    (citation omitted). In addition, after the parties failed to come to an agreement on an IBM-
    led roll out of the hybrid system, the State urged IBM to continue as the technology vendor.
    
    Id. at 198
    .
    However, it is not far-fetched that the State would ask IBM, a multinational
    technology and consulting company, to lead the roll-out of the hybrid system given the
    time both parties had invested in this venture and the fact that IBM was intimately familiar
    with both the State’s old system and the Modernization Project. And when the parties
    could not come to an agreement, it is just as reasonable that the State wanted IBM to
    continue in a lesser role as the technology vendor.
    IBM next argues that the trial court found that the State’s principal complaint about
    the Modernization Project resulted from a key feature of the system that the State itself
    designed and required—reduction of face-to-face interactions.
    The trial court found that Governor Daniels “sought to change one of the key
    requirements that the State had developed, that he had previously approved, and which was
    specified in the MSA—the move away from face-to-face meetings and greater reliance on
    multiple points of access to the system.” 
    Id. at 196
    . Accordingly, IBM argues that it
    “cannot be faulted, much less held in material breach, for following the design
    44
    requirements the State developed and the MSA required.” Appellee’s Br. p. 31. However,
    even though the State may have developed a system that resulted in a reduction of face-to-
    face meetings, IBM nevertheless agreed to implement this design. If IBM did not think
    that it could carry out this concept, then it presumably would not have executed the MSA.
    In addition, IBM agreed “to improve the availability, quality and reliability of the services
    being provided to Clients by expanding access to such services, decreasing inconvenience
    and improving response times, among other improvements.” Appellant’s App. p. 567.
    IBM also argues that the trial court found that the State’s breach allegations revolved
    around failure to meet Key Performance Indicators for timely processing of applications,
    but the Key Performance Indicators were not originally intended to apply during the
    transition period.
    The trial court found that the State’s main focus was the Schedule 10 timeliness
    metric; however, IBM was consistently meeting the majority of the Key Performance
    Indicators when the State announced termination of the MSA in October 2009. 
    Id. at 211
    ;
    see also 
    id.
     (“The MSA and Schedule 10 shows the timeliness metric was of the same
    importance as the 19 of 24 [Key Performance Indicators] that the Coalition consistently
    met . . . .”). Notably, the trial court found that the “[Key Performance Indicator] metrics
    for timeliness were consistently missing the mark.” 
    Id. at 210
    . In addition, the trial court
    found that the Key Performance Indicators were not originally intended to apply during the
    transition period. However, as the trial court also found, most of the Key Performance
    Indicators were accelerated pursuant to Change Order 64. 
    Id. at 212
    .
    45
    Finally, the trial court found that IBM’s performance was steadily improving in
    2009. The trial court concluded as follows:
    [T]he measured performance of IBM was steadily improving during 2009,
    especially in the months leading up to the October 2009 termination.
    Therefore, anything that could be interpreted as an IBM failure not only had
    a likelihood of being cured, but was apparently in the process of being cured
    at the time of termination.
    
    Id. at 210
     (Conclusion No. 99). Accordingly, IBM argues that the likelihood of curing any
    performance deficiencies counsels against a finding of material breach. IBM cites Frazier
    v. Mellowitz, 
    804 N.E.2d 796
     (Ind. Ct. App. 2004), in support. In Frazier, this Court noted
    that under the Restatement (Second) of Contracts, an injured party is not discharged from
    his duty to perform unless (1) the breach is material and (2) it is too late for performance
    or an offer to perform to occur. 
    Id. at 803
    . We noted that in particular, the Restatement
    (Second) of Contracts § 241 (1981) provides that in determining whether a failure to render
    or to offer performance is material, several circumstances are significant, including “the
    likelihood that the party failing to perform or to offer to perform will cure his failure, taking
    account of all the circumstances including any reasonable assurances.” Id.
    We first note that although the trial court concluded that IBM’s failure was
    “apparently” in the process of being cured at the time of termination, this is just one of five
    factors to consider in determining whether the breach is material. See Collins, 
    871 N.E.2d at 375
    . In addition, we note that the findings that the trial court used to support this
    conclusion are not persuasive. As support for this finding, the trial court relied on
    statements from an attorney general in a September 2009 hearing in Thornton v. Anne
    Murphy in the United States District Court for the Southern District of Indiana. The
    46
    litigation concerned how long it took the State to process applications. Not surprisingly,
    the attorney general, speaking for the defendant, told the judge:
    We looked at what were the causes. We tried to identify the causes; and
    we’ve initiated a number of activities to correct those causes, many of
    which—they call it Quick Win, but we have made substantial progress in a
    very short period of time.
    Ex. 304, p. 70. The trial court also cited a late September 2009 email which contained
    public statements from Secretary Murphy that “a team of vendors led by IBM Corp. has
    already made improvements in technology and added more staff under a corrective action
    plan submitted in July”; however, Secretary Murphy added that “the timeliness of
    processing applications for food stamps, Medicaid and other benefits has not improved.”
    Ex. 111. This is not persuasive evidence that IBM’s performance was steadily improving
    in 2009.
    C. Conclusion
    Although the Modernization Project reduced fraud and provided important benefits
    to the State, the record also shows that the system had problems from the very beginning,
    including unanswered calls and the untimely processing of applications. Appellant’s App.
    p. 183. Also, in November 2008—approximately a year and a half after Phase 1 was
    launched—the IBM Coalition met with Secretary Roob to propose changes to the project
    because of problems including inconsistent feedback, document acceptance and
    processing, case-processing timeliness, quality, and higher volumes. Ex. 65, p. 12. Then,
    in March 2009, Secretary Murphy sent the IBM Coalition a letter drafted by the State’s
    outside counsel requesting a Corrective Action Plan. The letter identified thirty-six issues
    that the State wanted the IBM Coalition to address, including excessive wait times at local
    47
    offices, incorrectly categorized imaged documents, high turnover of staff, scheduling
    problems, inaccurate and incomplete data gathering, clients not receiving mailed
    correspondence, poor communication to all staff, unresolved help-desk tickets, untimely
    expedited food-stamp processing, excessive wait times for applicant appointments, and
    failure to process Food Stamp, TANF, and Medicaid applications in a timely manner. Ex.
    75. On July 2, 2009, the parties agreed on a Corrective Action Plan that included twenty-
    two short-term “Quick Wins” and thirty-one long-term initiatives. Appellant’s App. p.
    192. And in late July 2009, CMS found that since the Modernization Project’s rollout, it
    was “plagued” “by ongoing issues and complaints that consumers are losing Medicaid
    benefits or being denied benefits inappropriately.” Id. at 834. The problems included
    extended wait times for processing enrollment applications and in receiving responses to
    Call Center inquiries, lack of responses to enrollment applications, and inappropriate
    disenrollments. Id. CMS noted that these problems, which had garnered media attention,
    “indicate a serious situation in Indiana that is negatively impacting consumers’ access to
    Medicaid.” Id. at 834, 837. Not surprisingly, the trial court found that the “[Key
    Performance Indicator] metrics for timeliness were consistently missing the mark.” Id. at
    210. Not only was the public not satisfied with the new system, but—according to three
    key IBM witnesses—the State was not satisfied with the new system and had a reasonable
    basis not to be satisfied. The trial court’s mission was to determine whether there was a
    material breach by IBM that went to the essence of this contract. In doing so, the trial court
    employed a balancing test that weighed the number of benefits that the State received in
    this contract. But the question before the trial court was not the number of benefits the
    48
    State received but whether the heart of this contract was breached by IBM. We find that
    the heart of this contract was to provide services to the poor in a way that complied with
    federal law. In this respect IBM’s performance, as the trial court explained, “consistently
    missed the mark.” This substandard performance by IBM, $437 million and 36 months
    later, went to the essence of this contract.
    Yet the trial court excused IBM’s substandard performance for a number of
    inappropriate reasons. In particular, the trial court took into account that the Great
    Recession and an inordinate amount of flooding occurred in Indiana during the course of
    the contract. While that is all true, this multinational company under the terms of the
    contract had the ability to request more money from the State through Change Orders to
    account for these disasters, but it did not. Strikingly, the trial court excused IBM’s
    performance in part because of the increase in the HIP applications, although IBM was
    paid extra to handle the increase in the HIP applications.
    At the same time, the trial court discounted that the State and frankly IBM were both
    dissatisfied with IBM’s performance, that IBM consistently missed the mark on Key
    Performance Indicators, and that the federal government imposed penalties on the State for
    IBM’s failings.
    We find that the failings of IBM went to the heart of the contract—to provide
    welfare services to our poorest in a timely, efficient, and reliable manner within federal
    guidelines—and that this constituted a material breach of the contract. Accordingly, we
    remand this case to the trial court to determine the State’s damages and offset any damages
    awarded to IBM.
    49
    II. Assignment Fees
    The State contends that the trial court erred in awarding IBM $40 million in
    subcontractor assignment fees. The issue of assignment fees was determined by the trial
    court on summary judgment and reaffirmed in its July 2012 order. The State first argues
    that IBM has waived this issue by pleading no operative facts and making no demand for
    relief for assignment fees in its amended complaint. Second, the State argues that the
    subcontractor assignment fees are liquidated-damages clauses amounting to an
    unenforceable penalty.
    A. Waiver
    The State first argues that IBM has waived this issue by pleading no operative facts
    and making no demand for relief for assignment fees in its amended complaint. IBM
    responds that it properly requested assignment fees in its amended complaint by generally
    stating that it was asking “for such further relief as warranted under the contract and Indiana
    law and as the Court deems just and proper.” Appellant’s App. p. 337.
    Indiana Trial Rule 8(A) requires a pleading to contain “(1) a short and plain
    statement of the claim showing that the pleader is entitled to relief, and (2) a demand for
    relief to which the pleader deems entitled.” In addition, Trial Rule 8(F) provides that “[a]ll
    pleadings shall be so construed as to do substantial justice, lead to disposition on the merits,
    and avoid litigation of procedural points.” Indiana’s notice pleading rules do not require
    the complaint to state all elements of a cause of action. Shields v. Taylor, 
    976 N.E.2d 1237
    ,
    1245 (Ind. Ct. App. 2012). Notice pleading merely requires pleading the operative facts
    so as to place the defendant on notice as to the evidence to be presented at trial. 
    Id.
    50
    Therefore, under notice pleading, the issue of whether a complaint sufficiently pleads a
    certain claim turns on whether the opposing party has been sufficiently notified concerning
    the claim so as to be able to prepare to defend it. 
    Id.
     A complaint’s allegations are
    sufficient if they put a reasonable person on notice as to why a plaintiff is suing. 
    Id.
    Here, although IBM’s amended complaint did not specifically request assignment
    fees, the State was on notice. In its answer to IBM’s amended complaint, the State raised
    as a defense: “IBM is unable to recover any damages, penalties, fees, costs, profits,
    subcontractor assignment fees, deferred fees, damages, loans, or other monies by whatever
    name or label that violate the public policy and/or Constitution of the State of Indiana,
    including Article X.” Appellant’s App. p. 343 (emphasis added). In addition, when IBM
    propounded an interrogatory to the State asking for the “factual basis for each affirmative
    defense asserted in the State’s Answer,” the State responded that “IBM has also made
    demand for payment of assignment of Subcontract fees contained in MSA § 14.8.1.” Id.
    at 160. Because the State was on notice as to assignment fees, we find that IBM has not
    waived this issue and therefore proceed to the merits.
    B. The Merits of Assignment Fees
    Next, the State argues that the $40 million in subcontractor assignment fees are
    liquidated damages amounting to an unenforceable penalty. IBM responds that the
    assignment fees were actually consideration for valuable contract rights. Appellee’s Br. p.
    18.
    Consideration is “[s]omething (such as an act, a forbearance, or a return promise)
    bargained for and received by a promisor from a promisee; that which motivates a person
    51
    to do something, esp[ecially] to engage in a legal act.” Black’s Law Dictionary 324 (8th
    ed. 2004). This Court has defined it as a “‘bargained for exchange’ whereby the promisor
    accrues a benefit or the promisee accepts a detriment.” Kelly v. Levandoski, 
    825 N.E.2d 850
    , 860 (Ind. Ct. App. 2005). “A benefit is a legal right given to the promisor to which
    the promisor would not otherwise be entitled.” 
    Id.
     (quoting DiMizio v. Romo, 
    756 N.E.2d 1018
    , 1023 (Ind. Ct. App. 2001), trans. denied).
    On the other hand, a liquidated-damages clause is “[a] contractual provision that
    determines in advance the measure of damages if a party breaches a contract.” Black’s
    Law Dictionary 949 (8th ed. 2004). In general, “[a] liquidated damages clause provides
    for the forfeiture of a stated sum of money upon a breach of contract without proof of
    damages.” Weinreb v. Fannie Mae, 
    993 N.E.2d 223
    , 232 (Ind. Ct. App. 2013), trans.
    denied. The purpose of these clauses is to compensate a non-breaching party when
    damages from a breach of contract would be uncertain, difficult, or impossible to ascertain.
    See 
    id.
       While liquidated damages are generally enforceable, contractual provisions
    constituting penalties are not. Dean V. Kruse Found., Inc. v. Gates, 
    973 N.E.2d 583
    , 591
    (Ind. Ct. App. 2012), trans. denied. The difference between a penalty and liquidated
    damages is that a penalty is imposed to compel performance under the contract by making
    a breach so expensive that a party would not breach the contract even if its damages would
    be lessened by doing so, whereas liquidated damages are an amount of money that
    reasonably estimates the non-breaching party’s damages as a result of the breach. 
    Id.
     In
    52
    other words, a penalty discourages efficient breach of a contract where a valid liquidated-
    damages clause does not.20
    The question, then, is whether the assignment fees were included in the MSA as
    consideration for valuable contract rights or to compensate IBM for damages sustained in
    the event of a termination of the contract.
    MSA § 14.8.1(3) specified fixed sums to be paid post-termination if the State
    stepped into the shoes of IBM and assumed the prime-contractor role with respect to the
    subcontractors.      If the State terminated the contract with IBM and assumed IBM’s
    subcontracts during the first seven years, the State was required to pay assignment fees to
    IBM in the amount of $10 million for the ACS subcontract and $5 million for each of the
    other subcontracts:
    (3) In the event the State exercises its right to accept assignment of one or
    more Subcontracts pursuant to this Section 14.8, the State shall not be
    required to pay to Vendor the Early Termination Close Out Payments[21] that
    are directly attributable to the performance of such assigned Subcontract(s),
    but, instead for each Subcontract assigned to the State, the State shall pay
    Vendor the following upon the applicable Services Termination Date[22]:
    (A) if the replaced Subcontractor is ACS, (i) the amount of the
    Deferred Fees for Vendor’s Subcontract with ACS as set forth in
    20
    An efficient breach is “an intentional breach of contract and payment of damages by a party who
    would incur greater economic loss by performing under the contract.” Black’s Law Dictionary 200 (8th ed.
    1999). The concept of efficient breach stems from the efficient-breach theory, which is “[t]he view that a
    party should be allowed to breach a contract and pay damages if doing so would be more economically
    efficient than performing under the contract.” Id. at 555.
    21
    Early Termination Close Out Payments are defined in MSA § 16.6.6(3). These Early
    Termination Close Out Payments include Deferred Fees as listed in Schedule 24. Appellant’s App. p. 702.
    22
    “Services Termination Date” means “the date upon which [IBM] is no longer providing the
    Services for which the State is no longer paying the Fixed Fees, with respect to all or that portion of the
    Services Terminated by the State.” Appellant’s App. p. 776.
    53
    Schedule 24 [Deferred Fees][23], plus (ii) Ten Million Dollars
    ($10,000,000), if the applicable Services Termination Date is within
    Contract Years one through seven, or Five Million Dollars
    ($5,000,000) if the applicable Services Termination Date is within
    Contract Years eight through ten; and
    (B) for each assigned Subcontract with a Key Subcontractor (other
    than ACS) and each other assigned Primary Subcontract (other than
    those Subcontracts with an aggregate contract value of less than Five
    Million Dollars ($5,000,000)), Five Million Dollars ($5,000,000), if
    the applicable Services Termination Date is within Contract Years one
    through seven, or Two Million Five Hundred Thousand Dollars
    ($2,500,000) if the applicable Services Termination Date is within
    Contract Years eight through ten;
    provided, however, that the provisions of this Section 14.8.1(3) shall not
    apply if all the Services[24] contained within an applicable Subcontract[25] are
    terminated by the State pursuant to Sections 16.3.1 [termination for cause],
    16.3.4(2) [insolvency event], or 16.3.4(3) [wrongful conduct], except that the
    unamortized balance of the Deferred Fees shall still be payable in such event.
    Appellant’s App. p. 681-82.26
    23
    Deferred Fees include fees that ACS deferred into the future. Ex. 1653. The fees due to ACS
    under Schedule 24 were amortized over a three-year period from fiscal year 2007 through fiscal year 2009.
    24
    “Services” means:
    the tasks, functions, and responsibilities of Vendor under the Agreement expressly assigned
    and delegated to Vendor, and any incidental or ancillary tasks, functions, or responsibilities
    not expressly described in the Agreement but that are necessary and appropriate subtasks
    for the successful performance of the Services and the Agreement, including Delegated
    Activities.
    Appellant’s App. p. 776-77. Put differently, services means all services of the Vendor (IBM) and all
    subcontractors that are provided to the State. While the State terminated IBM’s services for cause, it
    continued to work with the subcontractors and renegotiated with all but one of the subcontractors.
    25
    “Subcontract” means “any Contract between Vendor and a Subcontractor with respect to or
    involving the performance of any of the Services or the Delegated Activities, or any part thereof.”
    Appellant’s App. p. 779.
    26
    There was no unamortized balance remaining for ACS, the only subcontractor in Schedule 24,
    because the State paid their fees by the end of fiscal year 2009.
    54
    After the State terminated the MSA, the State assumed the ACS subcontract and six
    others to keep key subcontractors working for about one month in order to continue
    providing FSSA services while it negotiated new subcontracts. Appellant’s Br. p. 5; Oral
    Arg. at 17:10, available at http://goo.gl/0jyxtB; see also Tr. p. 4721-23 (noting that the
    State never intended to assume the contracts as they existed under the MSA and instead
    planned to renegotiate them). The State rejected an eighth subcontract, Crowe, because
    “[t]he value wasn’t there.” Appellee’s App. p. 96. According to the State, “the cost of the
    service versus the value received was not considered to be worth continuing.”             Id.
    Accordingly, IBM invoiced the State $40 million for assignment of these seven
    subcontracts—$10 million for the ACS subcontract and $30 million for the six others. See
    Appellant’s App. p. 889.
    The trial court concluded that the fees were consideration for a valuable contract
    right. See Appellee’s Br. p. 18 (“The court found that the provision of the MSA requiring
    the State to pay subcontractor assignment fees was not a liquidated-damages provision—
    let alone an unenforceable penalty . . . .”). Specifically, the trial court concluded on
    summary judgment:
    Under Indiana law, a contract provision constitutes a “penalty” if it imposes
    a grossly excessive financial payment for a breach of the contract or poor
    performance. Here, it is undisputed that the MSA’s plain language does not
    condition payment of the . . . fees on a breach of contract. In fact, it is
    undisputed that the subcontractor assignment fees constitute compensation
    for valuable contract rights, and not a financial payment to compensate a
    party for breach of contract. Thus, they do not constitute a financial penalty,
    much less an unenforceable penalty.
    Appellant’s App. p. 160-61 (citations omitted). The trial court reaffirmed this ruling in its
    July 2012 order:
    55
    123. MSA § 14.8.1(3) clearly states that “the State shall pay” the
    subcontractor assignment fees if it accepts assignment of the subcontracts
    (which the State did here), regardless of whether there was a termination for
    cause. As the Court previously ruled during summary judgment, IBM is
    entitled to Forty Million Dollars ($40,000,000.00) for such fees.
    Id. at 220.
    We agree with the trial court and IBM that these assignment fees were the price to
    which the State agreed to purchase IBM’s interest in the subcontracts. The State paid the
    $40 million assignment fee to IBM in consideration for the State accruing the legal right to
    assume IBM’s subcontracts. Brian Whitfield, IBM Vice President of State and Local
    Government when the MSA was executed, stated that IBM generally does not permit its
    clients to assume its subcontracts, but that it allowed the subcontractors to be assignable in
    this particular contract at the request of the State. Id. at 362. Indeed, this benefit was
    substantial, as it is not customarily permitted in other services contracts that IBM
    negotiates. Light v. NIPSCO Indus., 
    747 N.E.2d 73
    , 77 (Ind. Ct. App. 2001) (“A benefit is
    a legal right given to the promisor to which the promisor would not otherwise be entitled.”),
    reh’g denied, trans. denied.
    In assuming these contracts, the State received certain benefits in consideration for
    the $40 million it paid in assignment fees. The State received the benefit of a packaged
    deal of contracts that were already written to conform to their needs. Had IBM not allowed
    the State to assume its subcontracts, the State would either have had to rewrite and
    renegotiate new contracts with the same subcontractors or find new subcontractors.
    According to IBM, these contract negotiations were long and expensive. Oral Arg. at
    42:58, available at http://goo.gl/0jyxtB; see also Ex. 8908, p. 9. By assuming IBM’s
    56
    subcontracts, the State bypassed the lengthy and expensive process of renegotiating the
    contracts or finding new contractors for the services provided under the MSA.
    Additionally, the State received the benefit of a fixed contract price. The prices
    negotiated between IBM and its subcontractors were fixed for a ten-year period. Had the
    State not negotiated this assignment provision in the contract, the subcontractors could
    have demanded more money to continue working with the State upon termination of the
    MSA at the end of the Disengagement Period. Oral Arg. at 41:50.
    Furthermore, the State received the benefit of IBM hiring and training the
    employees of the subcontractors. Working with the subcontractors directly after IBM had
    trained the subcontractor’s employees would have been considerably less expensive to the
    State. The cost associated with training the subcontractors and their employees is not
    insubstantial.
    All of this evidence supports the conclusion that these assignment fees were
    consideration and not liquidated damages. The State wanted the ability to assume IBM’s
    subcontracts for the reasons stated and therefore asked that the ability to assume the
    contracts be included in the MSA. The State knew that the ability to assume IBM’s
    subcontracts benefitted them and determined that the benefit was worth $40 million. We
    determine that the fees are consideration and not liquidated damages.
    Our conclusion is bolstered by the fact that these fees are not contingent upon a
    breach of the contract, but instead are contingent on the State’s assumption of IBM’s
    subcontracts. Generally, liquidated-damages clauses are intended to compensate in the
    event of a breach when damages are uncertain or difficult to determine. Here, IBM would
    57
    be damaged, and the State would be unjustly enriched, if the State chose to assume IBM’s
    subcontracts even if the State did not breach the MSA.
    Nonetheless, the State argues that the assignment fees are a set amount meant to
    penalize the State in the event that the State terminates the contract—whether by the State’s
    breach or by the State terminating the contract for convenience—rather than payment for
    a valuable contract right. But many of the cases the State cites concerned fees due only
    when a party breaches the contract or when a party terminates after a breach. See A.V.
    Consultants, Inc. v. Barnes, 
    978 F.2d 996
    , 1001 (7th Cir. 1992) (determining that the
    administrative fee was a liquidated-damages provision after determining that one of the
    litigants breached the contract); see also Doral Bank, PR v. Fed. Home Loan Mortg. Corp.,
    
    2010 WL 3984667
     (E.D. Va. Oct. 7, 2010); CMG Realty of Conn., Inc. v. Colonnade One
    at Old Greenwich Ltd. P’ship, 
    653 A.2d 207
     (Conn. App. Ct. 1995); Allison-Williams Co.
    v. Viasource Funding Grp., LLC, 
    2010 WL 2346621
     (N.J. Super. Ct. App. Div. June 9,
    2010). Finally, while Mau does consider the enforceability of cancellation fees as a
    liquidated-damages clause where a contract was terminated for convenience, the
    cancellation fees in that case were contingent upon termination. Mau v. L.A. Fitness Int’l,
    LLC, 
    749 F. Supp. 2d 845
     (N.D. Ill. 2010). Here, however, the assignment fees were
    contingent on the State assuming the subcontracts and not on the termination of the
    contract.
    Even still, the State could have avoided these fees while at the same time terminating
    the contract. As argued by IBM both in its brief and at oral argument, the State had the
    ability to terminate the contract without paying the assignment fees. See Appellee’s Br. p.
    58
    19; Oral Arg. at 42:32, available at http://goo.gl/0jyxtB. MSA § 16.6.1 required IBM to
    provide Disengagement Services pursuant to a Disengagement Plan continuing for up to a
    period of twelve months. During this time, the State could have found and negotiated with
    new subcontractors, or it could have abandoned the Modernization Project and chosen to
    implement a new system. Instead, it chose to assume IBM’s subcontracts and continue
    working with the subcontractors. Because the State could have terminated the contract,
    not paid the $40 million in assignment fees, and operated under the Disengagement Plan
    until it found replacement contractors, the assignment fees were not contingent on the
    termination or breach of the contract. For all these reasons, we determine that the
    assignment-fees provision was consideration.
    But this does not end our inquiry. In the first portion of this opinion, we determined
    that IBM materially breached the MSA. Generally, “[a] party first guilty of a material
    breach of contract may not maintain an action against or recover damages from the other
    party to the contract.” Ream, 
    915 N.E.2d at 547
    . A breaching party may, however, recover
    the value of what he or she has provided in quantum meruit. Am. Nat’l Bank & Trust Co.
    v. St. Joseph Valley Bank, 
    180 Ind. App. 546
    , 554, 
    391 N.E.2d 685
    , 687 (1979), reh’g
    denied. “To prevail on a claim of quantum meruit—also referred to as unjust enrichment—
    the plaintiff must establish that a measurable benefit has been conferred upon the defendant
    under such circumstances that the defendant’s retention of the benefit would be unjust.”
    King v. Terry, 
    805 N.E.2d 397
    , 400 (Ind. Ct. App. 2004) (citing Inlow v. Inlow, 
    797 N.E.2d 810
    , 816 (Ind. Ct. App. 2003), trans. denied). The value of services rendered is a question
    of fact for the trial court, but the value of services is not necessarily equivalent to
    59
    consideration. See Nunn Law Office v. Rosenthal, 
    905 N.E.2d 513
    , 520 (Ind. Ct. App.
    2009).
    Here, the trial court, in determining that the assignment fees were not liquidated
    damages, determined that they represented payment for a valuable contract right. We agree
    with the trial court.
    The subcontracts themselves were valuable. Not only would the State receive the
    benefit of a packaged deal of contracts that were already written to conform to their needs,
    but they would bypass the lengthy process of renegotiating contracts with new
    subcontractors. Additionally, in assuming the subcontracts, the State would benefit from
    a negotiated fixed contract price for the remainder of the ten-year period. Otherwise, the
    subcontractors would have had the ability to leverage their negotiating position and
    increase the contract price. Also, the State saved the substantial cost of retraining an army
    of employees as IBM had already trained the subcontractors’ employees in the system that
    IBM had put into place.
    But most importantly, the State’s conduct in the negotiations and afterward indicates
    that this contractual right was of value to them. The State, through both its highly
    competent outside and inside counsel, agreed that the value to the State of assuming these
    subcontracts was $40 million.        We cannot ignore the fact that the State, a highly
    sophisticated party, determined after several months of negotiations that $40 million was
    the value of the State’s right to assume IBM’s subcontracts.
    But even more telling is that after the State terminated the contract with IBM, the
    State chose to assume certain subcontracts while not assuming at least one other
    60
    subcontract. Out of the eight subcontracts, the State chose not to assume the Crowe
    subcontract, because “[t]he value wasn’t there.” Appellee’s App. p. 96. According to the
    State “the cost of the service versus the value received was not considered to be worth
    continuing.” 
    Id.
     By admitting that the Crowe subcontract did not have value to the State,
    the State impliedly agreed that the other seven subcontracts assumed by them were “worth”
    the price.
    Based on the benefits the State received in assuming IBM’s subcontracts and the
    conduct of the State both during the negotiations of the MSA and after, we agree with the
    trial court that the assignment fees represent value to the State in the ability to assume these
    subcontracts. Because there was a measurable benefit conferred upon the State under such
    circumstances, the State’s retention of the benefit would be unjust. IBM is therefore
    entitled to $40 million in assignment fees notwithstanding a finding of material breach.
    III. Early Termination Close Out Payments
    A. Deferred Fees
    In its cross-appeal, IBM argues that the trial court erred in denying judgment on its
    claim for $43,416,482 in Deferred Fees. The State responds that the trial court did not err
    and, in any event, Deferred Fees are not payable if the MSA is terminated for cause.
    When construing the language of a contract, we must determine and effectuate the
    intent of the parties. Ryan v. Lawyers Title Ins. Corp., 
    959 N.E.2d 870
    , 875 (Ind. Ct. App.
    2011). We must “read the contract as a whole and will attempt to construe the contractual
    language so as not to render any words, phrases, or terms ineffective or meaningless.” 
    Id.
    In doing so, “[w]e must accept an interpretation of the contract that harmonizes its
    61
    provisions, rather than one that places the provisions in a conflict.” 
    Id.
     Additionally, when
    “construing a contract we presume that all provisions were included for a purpose, and if
    possible we reconcile seemingly conflicting provisions to give effect to all provisions.” 
    Id.
    If a contract contains both “general and specific provisions relating to the same subject, the
    specific provision controls.” 
    Id.
    Using these rules, we must determine whether Deferred Fees are payable only upon
    a termination for convenience or whether Deferred Fees are payable regardless of how the
    contract is terminated. MSA § 16.6.6, entitled “Closeout Payments,” provided:
    (1) In the event of a Termination of this Agreement for any reason (other
    than a Termination by expiration), the State shall pay Vendor, to the extent
    applicable, the charges set forth in Sections 16.6.6(2) and 16.6.6(3)(F) below.
    In the event of a Termination of this Agreement for any reason (other than on
    expiration or upon a Termination as set forth in Sections 16.3.1 [Termination
    for Cause], 16.3.4(2), 16.3.4(3), or 16.5, in any of which events, Vendor shall
    not be entitled to Early Termination Close Out Payments), the State shall pay
    the Early Termination Close Out Payments set forth in Section 16.6.6(3),
    16.6.6(4) and 16.6.6(5) and subject to Section 16.6.6(6) if applicable.
    Appellant’s App. p. 702 (emphases added). MSA § 16.6.6(3) then provided:
    Vendor’s and its Subcontractors’ Early Termination Close Out Payments (as
    applicable and without duplication) shall be as follows:
    *****
    (F)    Vendors and its Subcontractors’ unamortized balance of the
    Deferred Fees, as set forth in Schedule 24 [Deferred Fees].
    Id.
    The State filed a motion for summary judgment alleging that IBM was not entitled
    to Deferred Fees if the MSA was terminated for cause. The State argued that because
    Section 16.6.6(1)’s second sentence (partially emphasized above) provided that IBM was
    not entitled to Early Termination Close Out Payments—which included Deferred Fees—
    62
    in specified termination situations—including termination for cause—IBM was not
    entitled to Deferred Fees on termination for cause. In contrast, IBM argued that because
    Section 16.6.6(1)’s first sentence said that Deferred Fees would be paid on termination “for
    any reason” other than MSA expiration, it was entitled to Deferred Fees. Essentially, IBM
    argued that there was no conflict between the two provisions. See Tr. p. 62-63.
    In order to harmonize these seemingly conflicting provisions, the State argued that
    Section 16.6.6(1)’s qualifying phrase “to the extent applicable” in the first sentence
    referred to termination situations in which IBM did not receive Deferred Fees, which
    situations were then specifically identified in the next sentence. The trial court agreed with
    the State:
    IBM’s claim to be entitled to Deferred Fees on termination for cause
    rests on its reading of Section 16.6.6(1)’s first sentence in isolation. IBM’s
    argument that the sentence’s qualifying phrase “to the extent applicable”
    refers only to the amount of Deferred Fees payable, depending on when
    termination occurs, also leaves that sentence in conflict with the next
    sentence—which says IBM is not entitled to Early Termination Close Out
    Payments, which include Deferred Fees, on termination for cause. If one
    reading of a contract puts it[s] provisions in “conflict” while another brings
    them “into harmony,” then “[t]he law requires this Court to accept [the]
    interpretation [that] harmonizes the provisions of the contract.”
    The State’s reading—under which Section 16.6.6(1)’s first sentence’s
    qualifying phrase “to the extent applicable” refers to termination situations
    in which IBM is not entitled to Deferred Fees, which situations are then
    specified in the next sentence—does harmonize the two sentences. The
    State’s reading also harmonizes with other MSA provisions.
    Appellant’s App. p. 384-85 (citations omitted). The court granted summary judgment in
    favor of the State on this issue. Id. at 386-87.
    63
    We agree with the trial court’s interpretation of Section 16.6.6(1) that Deferred Fees
    are not payable to IBM in the event that the MSA was terminated for cause. The contract
    is ambiguous because the first sentence of Section 16.6.6(1) required the State to pay IBM
    the fees in Section 16.6.6(3)(F), which are Deferred Fees. Id. at 702. However, in the
    second sentence, the contract stated that if the State terminated for cause, insolvency,
    wrongful conduct, or a mutual termination, it would not be required to pay any of the
    payments in Section 16.6.6(3), which included Deferred Fees. Id.
    We read the first sentence’s qualifying phrase “to the extent applicable” to refer to
    termination situations in which IBM was not entitled to Deferred Fees. The second
    sentence clarified situations when the specified Deferred Fees were applicable—namely,
    that such fees were payable unless there was a termination for cause, an insolvency event,
    wrongful conduct, or a termination by mutual agreement. In other words, the first sentence
    of this section applied to situations not listed in the second sentence, such as termination
    for convenience. This reading is the only way to harmonize the two sentences as well as
    other provisions in the MSA without rendering any part meaningless. Because we have
    concluded that there was a material breach, the State terminated for cause, and the contract
    does not require payment of Deferred Fees upon termination for cause, IBM is not entitled
    to Deferred Fees.
    B. Other Early Termination Close Out Payments
    The trial court determined that IBM was entitled to $2,570,621 in “Early
    Termination Close Out Payments” due under MSA § 16.6.6. Specifically, the trial court
    determined that the State owed IBM: (1) $2,305,964.37 in prepared software costs owed
    64
    under MSA § 16.6.6(3); (2) $31,143.58 in lease termination payments owed under MSA §
    16.6.6(3); (3) $61,284 in improvement costs IBM incurred in improving its Indianapolis
    offices owed under MSA § 16.6.6(3)(D); and (4) $101,763 in salary and labor costs for
    IBM employees and $71,466 for Crowe employees idled as a result of the termination,
    which are owed under MSA § 16.6.6(4)(B) because the State gave less than 75 days’ notice.
    Id. at 221-22. According to the trial court’s July 2012 order, the State’s only defense to
    payment of these costs was that they are not due in the event of termination for cause. Id.
    Because we have now determined that IBM materially breached the contract, the
    State is not required to pay these Early Termination Close Out Payments. MSA § 16.6.6(1)
    states that:
    In the event of a Termination of this Agreement for any reason (other than
    on expiration or upon a Termination as set forth in Sections 16.3.1
    [Termination for Cause], 16.3.4(2), 16.3.4(3), or 16.5, in any of which
    events, Vendor shall not be entitled to Early Termination Close Out
    Payments), the State shall pay the Early Termination Close Out Payments set
    forth in Section 16.6.6(3), 16.6.6(4) and 16.6.6(5) and subject to Section
    16.6.6(6) if applicable.
    Id. at 702. In other words, if the MSA is terminated for cause, the State is not required to
    pay IBM Early Termination Close Out Payments as enumerated in Sections 16.6.6(3),
    16.6.6(4), and 16.6.6(5). Because we have now determined that the MSA was materially
    breached, the State is not required to pay IBM the $2,570,621 in Early Termination Close
    Out Payments.
    IV. Equipment Costs
    65
    The State argues that the trial court erred in ordering it to pay IBM $9,510,79527 for
    Equipment costs.
    MSA § 3.4.7 provided that the State was entitled to use IBM’s “Equipment”28
    “during the Term” of the MSA, which ended on December 14, 2009. Appellant’s App. p.
    585. MSA § 16.6.1(4) then detailed how the transfer of and payment for the Equipment
    was to occur:
    The Disengagement Plan shall provide the details regarding the transfer of
    all dedicated Equipment to the Successor, to the extent included within the
    Early Termination Close Out Payments or otherwise purchased by the
    Successor, including the machine types, serial number, attached peripherals,
    manufacturer, warranty details, and, if applicable, any packing and shipment
    details. Upon receipt of payment for such Equipment, Vendor shall provide
    the Successor with an agreed upon bill of sale and other appropriate
    documents of transfer.
    Id. at 700. As contemplated by the MSA in Section 16.6.1, see supra note 9, the State and
    IBM executed a Disengagement Plan on December 11, 2009.                                According to the
    Disengagement Plan, the State was required to pay IBM $4.4 million for Disengagement
    Services.        In addition, Schedule A—Transfer of Dedicated Equipment of the
    Disengagement Plan listed the dedicated Equipment (including the machine type, serial
    number, attached peripherals, manufacturer, warranty details, and, if applicable, any
    27
    The State notes that this figure is higher than the amount that IBM invoiced it.
    28
    The MSA defined “Equipment” as:
    telephone systems, computer equipment, machines or hardware and other hardware or
    items of tangible personal property necessary for, or used in, the performance of the
    Services or the operation of the System, which are provided to the State by Vendor and on
    which the System will operate for providing the Services to clients, including all associated
    attachments features, accessories and peripheral devices.
    Appellant’s App p. 766.
    66
    packing and shipment details) that the State wished to be transferred.29 Id. at 871. IBM
    invoiced the State $9,349,654.93 for the Equipment that the State kept. Id. at 889.
    Although the parties do not list the Equipment that the State kept, Exhibits 350 and 351 do.
    Specifically, these exhibits are emails from the State that list the Equipment that the State
    “took over from IBM during disengagement.” See Ex. 351. The State never paid IBM’s
    invoice.
    The trial court’s July 2012 order addressed Equipment costs as follows:
    124. IBM is entitled to $9,510,795, the unchallenged appraised value of the
    Dedicated Equipment the State retained after terminating the MSA,
    regardless of whether IBM materially breached the MSA. “[T]he parties
    agree that the Equipment at issue was transferred to the State pursuant to the
    MSA.” 1/25/12 Order (Replevin) at 2. “It is further undisputed that the State
    did not pay IBM’s invoice for the Equipment.” Id. The State investigated
    any discrepancies in the list of Equipment at issue until resolved, and did not
    offer any expert opinion challenging the appraisal by IBM’s expert, Ron
    Savill, who found that the fair market value of the Equipment is $9,510,795.
    The Court finds Mr. Savill’s analysis to be sound and credible.
    125. The State agreed that it only had a right to use the Equipment during the
    Term of MSA (MSA § 3.4.7), and that if it wanted to keep the Equipment, it
    would have to be “purchased by the Successor [here, the State]” (MSA §
    16.6.1(4)). The State agreed that it would not receive a bill of sale
    transferring title for the Equipment until “receipt of payment for such
    Equipment.” (Id.) The State breached the MSA by keeping the Equipment
    and refusing to pay the bill.
    126. The State argues that the Dedicated Equipment should be considered an
    “equipment cost” that falls within the Early Termination Close Out
    Payments, which it maintains are only payable in the event of termination for
    convenience. Again, the State’s position is contradicted by the MSA. The
    MSA provides that if the State wants to keep the Equipment, it must pay for
    the Equipment “to the extent included within the Early Termination Close
    Out Payments or otherwise purchased by the Successor” and that IBM is
    only required to issue a bill of sale transferring title “upon receipt of payment
    for such Equipment.” (MSA § 16.6.1(4) (emphasis added)). Thus, even if
    29
    It actually said that IBM shall provide this information “on or about November 13.” Appellant’s
    App. p. 871. And then the State would specify whether it wished the equipment to be transferred. Id.
    67
    IBM were not entitled to payment for the Equipment as an ETCOP, Section
    16.6.1(4) dictates that the State “otherwise purchase” the Equipment if it
    wanted to keep it.
    127. Consistent with these provisions, the evidence shows that even after the
    State sent a “for cause” notice of termination, the State recognized that IBM
    owned the Equipment and that the State was required to pay for it. Thus,
    after notifying IBM that the State wanted the Equipment, the State’s Doug
    Elwell acknowledged that he expected an invoice from IBM. IBM invoiced
    the State and provided “supporting documentation” for the invoice. And the
    State budgeted to pay IBM $9.5 million “for acquiring all hardware.”
    Nonetheless, it never paid the invoice or returned the Equipment. IBM is
    entitled to the fair market value of the Equipment ($9,510,795) under the
    MSA’s plain language.
    Appellant’s App. p. 220-21 (emphasis in Conclusion No. 124 added) (footnote and
    citations omitted).
    The State argues that under the MSA, IBM is not entitled to Equipment costs
    because the contract was terminated for cause.        See Appellant’s Reply Br. p. 28.
    Specifically, the State points out that MSA § 16.6.6(1) provided that if the MSA was
    terminated for cause, then IBM “shall not be entitled to Early Termination Close Out
    Payments,” which—pursuant to Section 16.6.6(3)(A)—included “Vendor’s and its
    Subcontractors’ equipment costs net of any applicable depreciation or amortization as of
    the Services Termination Date.” Appellant’s App. p. 702 (MSA); Appellant’s Br. p. 36-
    37. As illustrated above in the trial court’s Conclusion No. 126, the trial court, however,
    found that the State was required to pay for the Equipment even if the contract was
    terminated for cause. This is because MSA § 16.6.1(4) provided that if the State wanted
    to keep the Equipment, it must pay for the Equipment “to the extent included within the
    Early Termination Close Out Payments or otherwise purchased by the Successor.”
    Appellant’s App. p. 221 (Conclusion No. 126). “Thus, even if IBM were not entitled to
    68
    payment for the Equipment as an [Early Termination Close Out Payment], Section
    16.6.1(4) dictates that the State ‘otherwise purchase’ the Equipment if it wanted to keep
    it.” Id.
    We agree with the trial court that although IBM was not entitled to Equipment costs
    as an Early Termination Close Out Payment because the MSA was terminated for cause,
    MSA § 16.6.1(4) still required the State to “otherwise purchase” the Equipment that it
    wanted to keep. If the State did not want to pay for any Equipment, then it should have
    returned it. However, it is undisputed that the State kept over $9.5 million in Equipment;
    in fact, there are emails from State personnel documenting the Equipment it kept. It is
    apparent that the State went through the process of selecting pieces of IBM’s Equipment
    to keep. See Ex. 351 (listing, among other things, 339 servers, 4289 workstations, 6859
    computer monitors, 157 X Series servers, 81 VM servers, 193 P Series IBM, and 19,630
    licenses). The State cannot expect to keep millions of dollars in expensive Equipment for
    free. Therefore, the State must pay for the Equipment that it kept.
    Nevertheless, the State still argues that it should not have to pay for the Equipment
    by directing our attention to a chart, see Appellant’s App. p. 873-83, in the Disengagement
    Plan, which was the contract that governed the services IBM provided during the transition
    from the modernized system to the hybrid system. The State notes that the chart indicated
    that MSA § 16.6.1 was “Not Applicable” during the transition period.            Id. at 880.
    Therefore, the State’s argument continues, the State did not have to pay for any IBM
    Equipment, and its $4.4 million payment to IBM for Disengagement Services covered the
    69
    Equipment, too. The State, however, does not read the Disengagement Plan closely
    enough.
    According to the section in the Disengagement Plan entitled “1.0 Statement of
    Work”:
    The scope of Disengagement Services under section 16.6.1 of this MSA is
    agreed to as follows:
    1.1 OVERVIEW
    The State, on behalf of the Family and Social Services Administration
    (FSSA), has requested that IBM provide continued Application
    Development/Maintenance (“AD/M”) Disengagement Services for a portion
    of the currently implemented software applications that enable the
    Modernization Project. IBM shall provide production support, system
    maintenance (break/fix) and minor enhancements as and to the extent set
    forth in this Statement of Work. In the event of any conflict between the
    Terms of this Statement of Work and the Master Services Agreement (MSA),
    this Statement of Work shall take precedence.
    Ex. 472, p. 28. According to the section in the Disengagement Plan governing pricing, the
    State agreed to pay IBM $4,412,200 for AD/M Services. Id. at p. 36. Finally, according
    to “2.1 Applicability of Terms and Conditions Contained in the MSA,” the chart the State
    relies on—“Attachment A”—“shows the extent to which the Terms and Conditions of the
    MSA apply to the AD/M Services provided under the Disengagement Plan SOW
    [Statement of Work].” Id. at p. 39. In other words, the chart specified which provisions
    of the MSA applied to the AD/M Services IBM was performing during the transition period
    under the Disengagement Plan. Importantly, the chart did not displace IBM’s contractual
    rights to recover for breach of any of those provisions during the term of the MSA or IBM’s
    right to recover the property that it owned. In fact, the Disengagement Plan specifically
    70
    provided that IBM reserved it rights under the MSA. Id. at p. 1. Therefore, the State must
    pay IBM $9,510,795 for Equipment costs.
    V. Change Order Fees
    Also in its cross-appeal, IBM argues that the trial court erred in concluding that it
    was not entitled to Fees for four Change Orders—71, 102, 119, and 133—totaling
    $931,928. MSA § 3.11.1, entitled Mandatory Changes, provided that the State may direct
    IBM to modify its Services to comply with changes in the law that affected the Agreement:
    (1) In the event of any Legal Change which in the State’s determination
    affects this Agreement or affects Vendor’s performance of the Services, the
    State may direct Vendor to modify the Services and any of the Attachments
    (to the extent such Attachments describe the scope of Services), as may be
    necessary in the State’s discretion to comply with applicable Law following
    the Legal Change, as set forth in this Section 3.11.
    Appellant’s App. p. 594. “Legal Change” means:
    (i) any change in applicable Laws and (ii) any determination made by the
    State in its discretion that a change in the Services (or any of the Attachments
    to the extent describing the Services) or any of the Retained Activities is
    necessary or appropriate to comply with Applicable Law or to respond to any
    directive (whether formal or informal) from any Governmental Body with
    jurisdiction over, or regulatory authority with respect to, any of the Programs.
    Id. at 770. “Mandatory Change” is defined as a “Legal Change” or a “Directed Change.”
    Id. at 771.
    Once the State determined that there was a Legal Change, the State “shall deliver
    notice to Vendor of modifications the State will require to implement a Mandatory Change,
    the effective date of a Legal Change (if applicable), and the date by which the State requires
    the modification to be implemented (‘Change Notice’).” Id. at 595 (MSA § 3.11.2). Within
    fifteen days following receipt of a Change Notice, IBM must prepare and deliver to the
    71
    State and the Change Control Board a written Change Analysis, which must include an
    evaluation of the impact of the proposed change on the then-current scope, price, and
    performance of the Services. See id. at 597 (MSA § 3.12.1(5): “any changes to the Fees,
    including an analysis, with supporting documentation, of the reasons Vendor believes the
    Fees will be materially impacted by the proposed Change”). According to MSA § 3.12.2,
    the “Parties will cooperate with each other in good faith in discussing the scope and nature
    of each Change Request and related Change Analysis. . . . The Parties will evidence any
    Change by executing a written Change Order containing a description of the Change . . .
    .” Id. (emphasis added).
    In the event of a dispute over Change Order Fees, MSA § 3.12.3 guided the parties
    as follows:
    (2) If a Mandatory Change materially affects the scope, schedule, cost and/or
    manner of performing the Services (“Material Change”), the Parties will
    execute appropriate Change Orders to implement the Mandatory Change and
    will negotiate in good faith any changes in the Fees to reflect the impact of
    the Mandatory Change on the Services and the costs thereof. Otherwise,
    there will be no change in the Fees arising out of a Mandatory Change.
    Id. at 597-98.
    The trial court found that IBM was not entitled to Fees for the four Change Orders,
    reasoning:
    144. IBM claims four mandatory “law change” change orders allow fees for
    extra work under the MSA. But the record only shows evidence for Change
    Orders 119 and 133, and is insufficient for both.
    145. The “law changes” in these change orders both pre-dated the MSA and
    should have been incorporated by IBM initially into the project.
    146. CR 119 related to changes required by the Deficient [sic] Reduction
    Act of 2005. CR 133 related to changes required by FNS to comply with
    72
    provisions in 7 C.F.R. 273.2. The last time 7 CFR 273.2 was amended prior
    to CR 133 was in 2003.
    147. IBM failed to show why it is entitled to payment from the State for
    making changes to comply with laws passed prior to the enactment of the
    MSA for which IBM’s processes and procedures have already been in
    compliance.
    Id. at 227-28 (citations omitted).
    IBM first argues that the trial court erred in finding that it did not introduce evidence
    for Change Orders 71 and 102. But IBM did not introduce executed written Change Orders
    for 71 and 102; rather, it introduced Change Request Forms. See Appellee’s App. p. 213-
    14, 215-16. It also introduced internal documents calculating the costs of the Change
    Orders should they become final. Id. at 257 (Ex. 2718), 258 (Ex. 2719). Because the
    record does not contain executed written Change Orders for 71 and 102, the trial court did
    not err in concluding that IBM was not entitled to Fees for Change Orders 71 and 102.
    As for Change Orders 119 and 133, the State’s sole argument is that IBM failed to
    prove that these Change Orders materially affected the scope, schedule, cost, and/or
    manner of performing services pursuant to MSA § 3.12.3(2) and therefore IBM was not
    entitled to any Fees. The State, however, has misread this provision of the MSA, which
    provided:
    (2) If a Mandatory Change materially affects the scope, schedule, cost and/or
    manner of performing the Services (“Material Change”), the Parties will
    execute appropriate Change Orders to implement the Mandatory Change
    and will negotiate in good faith any changes in the Fees to reflect the impact
    of the Mandatory Change on the Services and the costs thereof. Otherwise,
    there will be no change in the Fees arising out of a Mandatory Change.
    Appellant’s App. p. 597-98 (emphasis added). Under this provision of the MSA, the parties
    could only execute a Change Order if a Mandatory Change (which included a Legal
    73
    Change) materially affected the scope, schedule, cost, and/or manner of performing the
    Services. Here, there is no dispute that the parties executed Change Orders 119 and 133;
    therefore, there must have been a material effect to the scope, schedule, cost, and/or manner
    of performing the Services in order for there to have been a Change Order in the first place.
    However, because there is a Change Order does not mean that there is an automatic change
    in the Fees. As MSA § 3.12.3(2) instructed, the parties “will negotiate in good faith any
    changes in the Fees to reflect the impact of the Mandatory Change on the Services and the
    costs thereof. Otherwise, there will be no change in the Fees arising out of a Mandatory
    Change.” Id. at 598.
    Change Order 119 shows that the Vendor’s Proposal was $487,448, but the State’s
    Offer was $0.00. Appellee’s App. p. 222. Similarly, for Change Order 133, the Vendor’s
    Proposal was $46,340, but the State’s Offer was $0.00. Id. at 227-28. The trial court,
    however, found that IBM was not entitled to Fees for these Change Orders because “IBM
    failed to show why it is entitled to payment from the State for making changes to comply
    with laws passed prior to the enactment of the MSA for which IBM’s processes and
    procedures have already been in compliance.” Appellant’s App. p. 228. The trial court
    erred in making this conclusion. Although Change Order 119 referenced the Deficit
    Reduction Act of 2005, which was already in existence when the MSA was executed,
    Change Order 119 was necessitated, at least in part, by laws enacted by the Indiana General
    Assembly to take effect on October 1, 2009—long after the MSA was executed. See, e.g.,
    Appellee’s App. p. 217-23 (Change Order 119 referencing P.L. 14-2009); 
    Ind. Code § 12
    -
    15-2-23 (as added by P.L. 14-2009 to become effective October 1, 2009).
    74
    As for Change Order 133, the plain language of the Change Order makes clear that
    it was dictated by a change in the existing law that took place after the MSA was executed:
    “This change request incorporates required changes sent to the State by the U.S.
    Department of Agriculture Food and Nutrition Service in a memo dated July 17, 2009 as a
    result of an annual review.” Appellee’s App. p. 226.
    Therefore, the trial court’s basis for denying IBM judgment on its claim for Fees for
    Change Orders 119 and 133 is mistaken. We therefore remand this issue to the trial court
    for it to determine the amount of Fees IBM is entitled to for Change Orders 119 and 133.
    VI. Prejudgment Interest
    The State argues that the trial court erred by awarding IBM $10,632,333 in
    prejudgment interest. IBM argues that the State has waived this issue and that in any event,
    the trial court correctly ordered prejudgment interest based on the MSA’s plain language.
    A. Waiver
    IBM requested prejudgment interest in its complaint. In its answer, the State denied
    that IBM was entitled to prejudgment interest and generally asserted that IBM’s claims
    were barred “by the doctrine of sovereign immunity.” Appellant’s App. p. 342, 343.
    According to the trial court, “Neither party ever wrote, argued or litigated any specific issue
    of interest, prejudgment or otherwise, before or during trial. 
    Id.
     at. 244. However, in its
    post-trial brief, IBM requested prejudgment interest. Appellee’s App. p. 86-87. In its July
    18, 2012 order, the trial court awarded IBM prejudgment interest as follows:
    129. IBM is entitled to prejudgment interest under I.C. § 24-4.6-1-103. The
    applicable statutory rate for prejudgment interest is 8%. I.C. §§ 24-4.6-1-
    102 & 24-4.6-1-103. IBM shall submit a separate petition for calculated
    prejudgment interest within thirty (30) days.
    75
    Appellant’s App. p. 222. On August 8, IBM timely filed a petition requesting $10,632,333
    in prejudgment interest. Id. at 541. IBM attached to its petition a document in which it
    calculated this prejudgment interest. Id. at 544 (Exhibit A). On August 13, the State filed
    an objection, arguing that “IBM misled the Court in including a claim for prejudgment
    interest in its proposed entry. Indiana law forbids prejudgment interest against the State,
    save in limited circumstances not applicable here.” Id. at 545. The next day, August 14,
    the trial court awarded IBM $10,632,333 in prejudgment interest and deemed the State’s
    objection a post-judgment motion under Trial Rule 59 as a motion to correct error. Id. at
    239, 242.
    The parties later entered into a stipulation extending the time to rule if the objection
    was deemed a Trial Rule 59 motion (which the State disputed). Id. at 551. After additional
    briefing and a hearing, on October 22, 2012, the trial court entered an Order Overruling
    State’s Objection to Prejudgment Interest and Deemed Motion to Correct Errors.
    Specifically, the trial court found that the State “failed to defend prejudgment interest at
    trial, IBM is otherwise entitled to prejudgment interest in the Judgment, and [the] State
    further waived any objection.” Id. at 243-44.
    IBM argues on appeal that the State has waived its challenge to prejudgment interest
    because it “did not contest IBM’s request for prejudgment interest until after the court
    entered its ‘Findings of Fact, Conclusions of Law, and Judgment for IBM.’” Appellee’s
    Br. p. 20. IBM argues that the State attempts to avoid waiver by characterizing the trial
    court’s July 18 order as interlocutory—“even though the State’s own notice of appeal,
    which was filed before the court awarded prejudgment interest, denominated the appeal as
    76
    from a ‘Final Judgment, as defined by [the appellate rules],’ and certified that the case
    ‘does not involve an interlocutory appeal.’” Id. at 21 (quoting Appellee’s App. p. 91-92).
    We find no waiver by the State.30 According to Indiana Appellate Rule 2(H), “A
    judgment is a final judgment if (1) it disposes of all claims as to all parties[.]” That is, a
    “final judgment” is a judgment that “disposes of all issues as to all parties, to the full extent
    of the court to dispose of the same, and puts an end to the particular case as to all of such
    parties and all of such issues.” Minott v. Lee Alan Bryant Health Care Facilities, Inc., 
    998 N.E.2d 273
     (Ind. Ct. App. 2013) (quotation omitted), reh’g denied. “A final judgment
    reserves no further question or direction for future determination.” 
    Id.
     (quotation omitted).
    Accordingly, the judgment did not become final until August 14, which is when the trial
    court actually calculated prejudgment interest, because the July 18 order did not dispose of
    all claims between the parties. See 
    id.
     (holding that although the trial court titled the
    judgment “Final Judgment,” the issue of restitution was still undecided and therefore the
    judgment “was not a true final judgment”).
    30
    As for whether the State failed to defend prejudgment interest at trial and therefore lost on the
    merits for this reason, the trial court elaborated in its October 2012 order as follows:
    When the State denied IBM’s allegation of prejudgment interest, the issue became part of
    IBM’s burden at trial. Moreover, when the State asserted its affirmative defense of
    sovereign immunity, the State also carried a burden at trial. The record clearly shows that
    the State did nothing to oppose IBM’s prejudgment claim, or to prove its sovereign
    immunity defense. Therefore, it lost on the merits.
    Appellant’s App. p. 245 (footnote and citations omitted). Notably, earlier in the same order, the trial court
    said, “Neither party ever wrote, argued or litigated any specific issue of interest, prejudgment or otherwise,
    before or during trial.” Id. at 244 (emphases added). Therefore, it appears that neither party addressed
    prejudgment interest at trial, not just the State. It was IBM’s burden to prove it was entitled to prejudgment
    interest, not just the State’s burden to disprove. Since the trial court said that neither party addressed
    prejudgment interest either before or during trial, the State cannot be singled out as the only loser on this
    basis.
    77
    As for whether the State timely filed a notice of appeal, the record shows that the
    State filed three notices of appeal to preserve its appellate rights. The State filed its first
    notice of appeal shortly after the trial court issued its July 18 order—but before the trial
    court ruled on the State’s objection to IBM’s petition for prejudgment interest. The State
    filed its second notice of appeal on September 12, which was within thirty days of the trial
    court’s August 14 orders awarding IBM prejudgment interest and deeming the State’s
    objection a partial motion to correct errors. And the State filed its third and final notice of
    appeal on November 2, which was within thirty days of the trial court’s October 22 Order
    Overruling State’s Objection to Prejudgment Interest and Deemed Motion to Correct
    Errors. The State later moved to consolidate its three notices of appeal.31 In so doing, the
    State explained that it believed the trial court had not entered a final and appealable order
    until August 14, because it was not until then that the trial court had resolved all claims
    between the parties.       The State clarified that it filed its first notice of appeal as a
    precautionary measure to preserve its right to appeal if the July 18 order was later deemed
    final and appealable.
    Although IBM argues that the State’s notice of appeal denominated this appeal as
    coming from a final judgment and certified that the case did not involve an interlocutory
    appeal, IBM misleadingly cites to the State’s first notice of appeal without mentioning the
    State’s two other notices of appeal. After examining the complicated procedural history of
    this case, it is apparent that the State has never conceded that the trial court’s July 18 order
    31
    The State filed motions in this Court on September 19, 2012, and November 7, 2012, both of
    which we granted. See State v. Int’l Bus. Machs. Corp., Cause No. 49A02-1208-PL-645 (Ind. Ct. App. Oct.
    3, 2012); State v. Int’l Bus. Machs. Corp., Cause No. 49A02-1211-PL-875 (Ind. Ct. App. Dec. 11, 2012).
    78
    was a final judgment; rather, the State filed its first notice of appeal as a safeguard. Because
    the record shows that the State has made multiple efforts at the trial-court level to challenge
    the trial court’s award of prejudgment interest, the State has not waived this issue for
    appellate review.32 We therefore proceed to the merits.
    B. Merits
    Prejudgment interest is appropriate in a breach of contract action when the amount
    of the claim rests upon a simple calculation and the terms of the contract make such a claim
    ascertainable. Kummerer v. Marshall, 
    971 N.E.2d 198
    , 201 (Ind. Ct. App. 2012), reh’g
    denied, trans. denied. The award of prejudgment interest is considered proper when the
    trier of fact does not have to exercise judgment in order to assess the amount of damages.
    
    Id.
    In addition, sovereign immunity bars prejudgment interest against the State “unless
    it binds itself by contract or statute to pay interest.” Ind. Dep’t of Pub. Welfare v. Chair
    Lance Serv., Inc., 
    523 N.E.2d 1373
    , 1379 (Ind. 1988); see also State v. Hensley, 
    716 N.E.2d 71
    , 78 (Ind. Ct. App. 1999), trans. denied; Lake Cnty. v. State ex. rel. Manich, 
    631 N.E.2d 529
    , 536 (Ind. Ct. App. 1994), reh’g denied. This application of sovereign immunity
    derives from the principle that a State does not authorize its officers to incur obligations on
    its behalf unless by contract or statute. Chair Lance, 523 N.E.2d at 1379 (citing United
    32
    The parties cite federal case law for the following proposition. “A court that has decided to award
    prejudgment interest has not entered an appealable final judgment until that amount has been calculated”;
    however, there is an exception where the uncalculated interest is free from dispute and is readily
    ascertainable from the record—that is, where only a ministerial calculation is required and the appellate
    court could perform it as easily as the trial court. Student Loan Mktg. Ass’n v. Lipman, 
    45 F.2d 173
    , 175
    (7th Cir. 1995); Pace Commc’ns, Inc. v. Moonlight Design, Inc., 
    31 F.3d 587
    , 591 (7th Cir. 1994). We do
    not need to adopt federal law to resolve this issue, but even if we did, we would find that the exception did
    not apply here because this case does not involve a simple ministerial calculation.
    79
    States v. North Carolina, 
    136 U.S. 211
     (1890)).                     Courts indulge every reasonable
    presumption against waiver of fundamental constitutional rights, including state sovereign
    immunity. See Oshinski v. N. Ind. Commuter Transp. Dist., 
    843 N.E.2d 536
     (Ind. Ct. App.
    2006).
    The MSA contains three provisions that address interest and sovereign immunity.
    MSA § 18.2, entitled Interest, provides: “Vendor may seek to recover from the State
    overdue payments under this Agreement, and interest thereon, as described in Section 4.7.”
    Appellant’s App. p. 715. In turn, MSA § 4.7, entitled Interest on Overdue Payments,
    provides:
    The State will in good faith perform its required obligations hereunder and
    does not agree to pay any penalties, liquidated damages, interest, or
    attorneys’ fees, except as permitted by Laws[33] of the State, including IC 5-
    17-5, IC 34-54-8, and IC-34-13-1. Notwithstanding the provisions contained
    in IC 5-17-5, to the extent required by Laws generally applicable to
    contractors doing business with the State, any liability resulting from the
    State’s failure to make prompt payment shall be based solely on the amount
    of funding originating from the State and shall not be based on funding from
    federal or other sources.
    33
    “Laws” means:
    all statutes, codes, ordinances, decrees, rules, or regulations having the force of law issued
    by the State or by any Governmental Body having jurisdiction over the Services, the State
    or the Vendor; municipal by-laws; judicial or arbitral or administrative or ministerial or
    department or regulatory judgments, orders, decisions, rulings or awards of general
    applicability; policies and guidelines having the force of law, or any provisions of such
    laws, including general principles of common and civil law and equity, binding on or
    applicable to the Person referred to in the context in which such word is used; as well as
    rules, regulations, standards, policies, circulars and procedures having the force of law
    enacted or promulgated by any regulatory body or pursuant to any statutory authority or
    requirement, which relate to the Services and are applicable to Vendor. “Law” means any
    one of the foregoing.
    Appellant’s App. p. 770.
    80
    Id. at 613 (emphasis added). Finally, MSA § 18.3, entitled No Waiver of Sovereign
    Immunity, provides:
    The Parties expressly agree that no provision of this Agreement is in any way
    intended to constitute a waiver by the State of any immunities from suit or
    from liability that the State may have by operation of law. The State
    acknowledges and agrees that the forgoing sentence does not limit Vendor’s
    rights against the State under IC 34-13-1.
    Id. at 715.
    The State first argues that none of the three statutes listed in MSA § 4.7 authorizes
    prejudgment interest against the State. We look at each of them.
    Indiana Code section 5-17-5-1 provides that every state agency shall pay a late-
    payment penalty at a rate of one-percent per month on amounts due on written contracts
    for public works, personal services, goods and services, equipment, and travel whenever
    the state agency fails to make a timely payment. Chapter 5-17-5, however, does not permit
    a late-payment penalty for claims subject to a good-faith dispute. A “good faith dispute”
    includes a contention by the State that the goods delivered or the services rendered were of
    less quantity or quality than ordered or specified by contract, faulty, or installed
    improperly, or any other reason giving cause for the withholding of payment by the State
    until such dispute is settled. 
    Ind. Code § 5-17-5-2
    (b). IBM did not seek interest at the one-
    percent-per-month rate established in Section 5-17-5-1.
    Indiana Code chapter 34-54-8 does not govern prejudgment interest. Indiana Code
    chapter 34-51-4—which Indiana Code chapter 34-54-8 references—governs prejudgment
    interest in tort actions, but it does not authorize prejudgment interest in tort actions against
    the State. See 
    Ind. Code § 34-54-8-4
     (“Prejudgment interest is governed by IC 34-51-4.”);
    81
    
    Ind. Code § 34-51-4-4
     (“This chapter does not impose liability for prejudgment interest on
    the state . . . .”).
    Finally, Indiana Code chapter 34-13-1, which governs express and implied contract
    claims against the State, allows post-judgment interest against the State, not prejudgment
    interest. See 
    Ind. Code § 34-13-1-6
     (“Whenever, by final decree or judgment, a sum of
    money is adjudged to be due any person from the state, an execution shall not issue but the
    judgment shall draw interest at an annual rate of six percent (6%) from the date of the
    adjournment of the next ensuing session of the general assembly until an appropriation is
    made by law for the payment and the judgment is paid.”).
    Sovereign immunity bars prejudgment interest against the State unless the State
    binds itself by contract or statute to pay such interest. Pursuant to the terms of the MSA,
    the State did not waive sovereign immunity and did not agree to pay interest “except as
    permitted by Laws of the State, including IC 5-17-5, IC 34-54-8, and IC-34-13-1.”
    Appellant’s App. p. 613 (emphasis added). None of these statutes, however, authorizes the
    8% prejudgment interest that the trial court ordered here. Nevertheless, IBM argues that it
    is a well-settled principle of construction that a list following the term “including” is non-
    exclusive and implies that the list or items enumerated are merely examples.34 Appellee’s
    Br. p. 24. Therefore, IBM’s argument continues, the State agreed to pay prejudgment
    interest because prejudgment interest is authorized by other Indiana “laws.” The State
    responds that if MSA § 4.7 “means [that] the State ‘agreed’ to pay interest authorized in
    34
    IBM does not cite MSA § 1.4(2), which provides that “the word ‘including’ shall mean
    ‘including, without limitation’ and words of similar effect, unless the context shall indicate otherwise.”
    Appellant’s App. p. 570.
    82
    any circumstance by any ‘law,’ what is the point of citing IC 5-17-5, IC 34-54-8, IC 34-
    13-1 or any other statute?” Appellant’s Br. p. 17. We agree with the State that it did not
    bind itself to pay prejudgment interest.
    This construction makes even more sense when looking at the contract as a whole,
    as we must. Under MSA § 18.3, IBM can bring contract actions against the State pursuant
    to Indiana Code chapter 34-13-1 (which authorizes post-judgment interest but not
    prejudgment interest), but the State is otherwise not waiving sovereign immunity. Under
    MSA § 18.2, IBM may seek to recover “overdue payments” and “interest thereon, as
    described in Section 4.7.” MSA § 4.7 then states the general rule that the State does not
    agree to pay interest and then cites the three exceptions, none of which apply here.
    Construing MSA § 4.7—which says that the State “does not agree” to pay any interest
    except in certain circumstances—into something that says that the State does agree to pay
    interest in all circumstances—renders MSA § 4.7 essentially meaningless. Although we
    did not take a simple path to arrive at an answer, it is still clear that the State did not bind
    itself to pay prejudgment interest by statute or contract. Accordingly, the trial court erred
    by awarding IBM prejudgment interest.
    Conclusion
    We affirm the trial court’s award of $40 million in assignment fees and $9,510,795
    in Equipment fees to IBM, affirm the trial court’s denial of Deferred Fees to IBM, reverse
    the trial court’s award of $2,570,621 in Early Termination Close Out Payments and
    $10,632,333 in prejudgment interest to IBM, and remand the case to the trial court to
    determine the amount of fees IBM is entitled to for Change Orders 119 and 133 and to
    83
    determine the State’s damages and offset any damages awarded to IBM as a result of IBM’s
    material breach of the contract.
    Affirmed in part, reversed in part, and remanded.
    BAKER, J., concurs.
    FRIEDLANDER, J., concurs in part and dissents in part with separate opinion.
    84
    IN THE
    COURT OF APPEALS OF INDIANA
    STATE OF INDIANA                                  )
    )
    Appellant/Cross - Appellee,                )
    )
    vs.                                 )      No. 49A02-1211-PL-875
    )
    INTERNATIONAL BUSINESS MACHINES                   )
    CORPORATION,                                      )
    )
    Appellee/Cross - Appellant.                )
    )
    FRIEDLANDER, Judge, concurring in part and dissenting in part.
    I believe the trial court applied the correct standard in determining that IBM did not
    materially breach the Master Services Agreement (MSA). I therefore respectfully dissent
    from the portion of the Majority’s opinion that holds to the contrary. As a result, I also
    dissent from the resultant reversal of the trial court’s award of early termination closeout
    payments to IBM in the amount of $2.6 million. Upon my conclusion that IBM did not
    materially breach the MSA, I also believe that service investment fees are recoverable in
    the amount of $20.8 million, as are transition fees. I would remand to the trial court for
    determination of the appropriate amount of transition fees. I agree with the Majority in all
    other respects, namely that IBM is entitled to $40 million in assignment fees, $9.5 million
    in equipment fees, and fees associated with Change Orders 119 and 133, but is not entitled
    to prejudgment interest and fees associated with Change Orders 71 and 102.
    85
    My primary point of disagreement with the Majority concerns the standard to be
    employed in deciding whether IBM’s breach was “material”. According to § 16.3.1(1)(A)
    of the MSA, in order to terminate the MSA for cause, the State was required to prove a
    breach by IBM that was “material considering this Agreement as a whole”. Appellant’s
    Appendix at 692. As I believe the very language of this provision suggests it should, the
    trial court employed a balancing test in which it considered IBM’s failures in the context
    of the entirety of its obligations under the MSA. The Majority concluded this was error.
    In so doing, I believe the Majority inaccurately describes the test applied by the trial court
    as “balancing the number of benefits the State received versus the number of performance
    standards IBM failed.” Slip op. at 30. Described in this fashion, it sounds as though the
    trial court merely performed a mathematical calculation whereby it compared the benefits
    realized by the State to IBM’s breaches. I believe the trial court’s analysis was much more
    thorough and nuanced than that.
    As a general matter, whether a breach is material is a question of fact to be decided
    by the trier of fact. Ream v. Yankee Park Homeowners Ass’n, Inc. 
    915 N.E.2d 536
     (Ind.
    Ct. App. 2009), trans. denied. In making that determination, as the Majority notes, the trier
    of fact generally considers five factors, including: (1) the extent to which the injured party
    will be deprived of a reasonably expected benefit; (2) the extent to which the injured party
    can be compensated for the deprived benefit; (3) the extent to which the party failing to
    perform will suffer forfeiture; (4) the likelihood of curing the failure taking into account
    all of the circumstances, including reasonable assurances; and (5) the extent to which the
    failing party’s performance comported with standards of good faith and fair dealing. 
    Id.
     I
    86
    believe that this test is at odds with, and superseded by, the test that the MSA specifies
    should be applied in this circumstance.
    The MSA provided that the performance of services under its provisions would
    conform to the following standard:
    Vendor will ensure that the Services will be performed and delivered in a
    manner that (i) meets or exceeds the required levels of performance,
    including the Performance Standards specified in or pursuant to this
    Agreement, (ii) is effective, efficient and courteous to the Clients, and (iii)
    uses Commercially Reasonable Efforts to support the State’s achievement of
    its Policy Objectives.
    Appellant’s Appendix at 591. According to the MSA, IBM’s performance would be
    evaluated against the following performance goals identified for IBM in the MSA:
    (1)    Adherence to all the terms of this Agreement, including all covenants,
    obligations, representations and warranties;
    (2)    Performance in accordance with and compliance with the
    Modernization Project work plans, schedules, and milestones agreed
    to by the Parties;
    (3)    Performance of the Services in accordance with all applicable
    requirements of this Agreement, including the Performance Standards
    set forth in Schedule 10 [Performance Standards];
    (4)    Satisfactory results of Audits by the State, its representatives, or other
    authorized Persons in accordance with Art. 9 (with all results of such
    Audits being addressed in accordance with the Government’s Plan);
    (5)    Attendance at and participation in the DFR financial review and other
    meetings conducted from time to time by FSSA (both internally and
    with the public);
    (6)    Timeliness, completeness, and accuracy of required reports;
    (7)    Determination by the State of (i) Vendor’s satisfactory performance
    of the Services and the Delegated Activities, and (ii) Vendor’s
    satisfactory oversight and management of the Subcontractors; and
    87
    (8)     Vendor’s effort to assist the State in achieving the Policy Objectives.
    
    Id. at 591-92
    .     The Majority cites, and presumably considers, these performance
    benchmarks in its analysis of the materiality question, but does so in a manner that rejects
    the trial court’s “balancing” methodology. In so doing, I believe the Majority effectively
    subjugates the MSA’s expressed test for materiality in favor of the general test set out in
    Collins v. McKinney, 
    871 N.E.2d 363
     (Ind. Ct. App. 2007). I believe the trial court got it
    right on this point.
    The MSA itself requires evaluating a breach for materiality by considering it vis-à-
    vis the MSA “as a whole.” Appellant’s Appendix at 692. Indeed, it seems to me that
    performance under a contract of this breadth and complexity, whose goals and desired
    outcomes include some that are not susceptible to quantitative measurement, can be
    measured only in this manner, i.e., by considering the nature and extent of the
    nonconforming performance in the context of the entirety of what is required under the
    contract. The Majority’s approach, on the other hand, permits a finding of material breach,
    with the attendant harsh results to the breaching party, upon the finding of “any breach
    [that] went to the essence of the contract”, which is to say in the present case any breach
    that affects the provision and expansion of access to services for welfare recipients in a
    timely, reliable, and efficient manner. It seems to me that, in view of the scope and breadth
    of the services IBM was required to perform under the contract, such a vigorous definition
    of “material breach” doomed from the beginning IBM’s effort to avoid committing a
    material breach.
    88
    As the Majority aptly notes, we will not set aside findings or a judgment unless they
    are clearly erroneous. Ind. Trial Rule 52(A). A judgment is clearly erroneous if it applies
    the wrong legal standard to properly found facts. Farmers Mut. Ins. Co. of Grant &
    Blackford Cnties. v. M Jewell, LLC, 
    992 N.E.2d 751
     (Ind. Ct. App. 2013), trans. denied.
    In announcing its conclusion and applying the test for material breach described above, the
    trial court explained its conclusion that IBM had not materially breached the contract, as
    follows:
    Looking at the whole contract and IBM’s whole performance, at least
    substantial performance is clearly shown as a matter of law. The State’s case
    extrapolates from a number of general examples of frustrated welfare
    applicants and State workers, even attempts to estimate from data that as
    many as 80,000 or more applications (out of 1 million) were processed late
    during the 12 measured months of IBM’s management. Taken as true, these
    examples still have to be balanced against the whole contract and IBM’s
    whole performance showing benefits to the State and adhering to MSA
    policy objectives. Accordingly, the heart of the contract remained intact,
    although sometimes beating irregularly.
    Appellant’s Appendix at 210.
    The trial court noted that the State’s main argument in favor of material breach
    focused on Schedule 10 timeliness metrics. The court noted that this metric was not
    identified in the MSA as more important than nineteen of twenty-four KPIs that IBM
    consistently met. The Majority disapproves of this approach to the question of whether
    IBM materially breached the contract, explaining:
    Contrary to the trial court’s implication in Conclusion No. 100, whether IBM
    materially breached the contract does not require balancing the number of
    benefits the State received versus the number of performance standards that
    IBM failed. Rather, the issue is whether any breach went to the essence of
    the contract – to provide and expand access to services for welfare recipients
    in a timely, reliable, and efficient manner within federal guidelines, to
    discourage fraud, and to increase work-participation rates.
    89
    Slip op. at 30. The Majority thus holds that materiality does not depend upon the scope of
    the breach relative to the entire contract. Rather, it concludes that a breach is material if it
    “went to” the provision and expansion of access to services for welfare recipients in a
    timely, reliable, and efficient manner. 
    Id.
     Considered in isolation and not placed in
    context, this seemingly means that if there is a single problem concerning a prospective
    welfare recipient’s receipt of welfare benefits, at least with respect to gaining access to
    benefits in a timely, reliable, and efficient manner, then IBM is guilty of material breach.
    A standard that discounts context in this manner is too harsh.
    Additionally, the Majority concludes that the trial court erroneously failed to
    consider the State’s dissatisfaction with IBM’s performance in determining whether a
    material breach had occurred. I believe this mischaracterizes the trial court’s analysis. In
    fact, the trial court noted there was evidence that the State was dissatisfied with aspects of
    IBM’s work. For instance, the trial court noted that “the State’s level of satisfaction is one
    of eight enumerated ways in which IBM’s performance will be judged.” Appellant’s
    Appendix at 51. Thus, it is clear to me that the trial court did consider the State’s
    dissatisfaction in making its determination with respect to whether the material breach had
    occurred. Perhaps, the Majority’s rejection of the trial court’s judgment in this matter was
    not based upon the trial court’s utter failure to consider the State’s dissatisfaction, but
    instead based upon the weight accorded that factor in the trial court’s analysis. Regardless,
    I believe the trial court did consider this factor, and weighed it appropriately under the
    balancing test it correctly employed.
    90
    The Majority concludes that the trial court committed “flat error” in “treating …
    liquidated-damages payments as the State’s exclusive remedy[.]” Slip op. at 34. I cannot
    agree that the trial court regarded the liquidated-damages payments in this manner. Rather,
    the trial court noted IBM’s shortcoming with respect to the timeliness metrics and indeed
    labeled it a “breach.” See Appellant’s Appendix at 49, Finding of Fact No. 105. The
    question is, was this breach “material”? The trial court concluded it was not, based largely
    upon the fact that, per the contract, the State was compensated for those breaches,
    explaining:
    [T]hat was also the contemporaneous understanding of the State’s OV&V
    contract compliance organization and lead outside. As First Data’s Sanjay
    Vaze testified, ‘if timeliness was not met in a given month but IBM paid the
    liquidated damage, then as far as [First Data was] concerned, that was
    technically not a contractual breach.’ Similarly, as the State’s James
    Maxwell acknowledged, ‘IBM could perform under the contract by paying
    the contractual penalty if it was out of … spec on any of the performance
    measures.’
    Appellant’s Appendix at 50. I do not interpret this as indicating that the trial court viewed
    the liquidated damages payments as the State’s exclusive remedy for a breach of this sort.
    Instead, the court found that, “based on the complete record in this case … the Coalition’s
    failures to meet certain Schedule 10 metrics did not constitute a breach of the MSA, in light
    of IBM’s payment of liquidated damages.” 
    Id.
     (emphasis supplied). In other words, the
    trial court concluded that, in the context of the extensive and varied services IBM was
    required to perform under the MSA, the extent and frequency of its failure to meet the
    timeliness metric was simply not a material breach. I agree with that assessment.
    This conclusion, in turn, requires me to address an issue presented upon cross-
    appeal by IBM. The MSA contained a deferred fees provision that distributed payments
    91
    over a term of years for unamortized balances due to IBM. Labeled “service investment
    fees” by the parties, this constituted deferred compensation for work IBM and its
    subcontractors performed in the early stages of the project by spreading the cost over the
    life of the contract. This was done to address budgetary concerns that arose because at
    least two years of the modernization project were unaffordable, given the State’s budgetary
    constraints. IBM sought these fees in the trial court. The trial court refused to award
    service investment fees based upon its conclusion that those deferred fees were designed
    to “prevent a future breach” and thus were not reasonably related to any harm suffered by
    IBM. Appellant’s Appendix at 225. As a result, the court concluded that the service
    investment fees sought by IBM amounted to an unenforceable penalty.
    To the contrary, the fees that were the subject of the service-investment-fees
    provision in the MSA had already been earned at the time of the lawsuit. The MSA
    provided that, in the event of termination, the State would pay the unamortized balance of
    the deferred fees to IBM. The MSA did not associate either the payment of deferred fees
    or the date those payments were due with a breach of the MSA. Thus, in my view, the trial
    court erred in declining to order the State to pay the deferred fees requested by IBM.
    Similarly, the MSA specified that IBM was entitled to fees associated with the
    transition from the system in place before this contract was executed to the system IBM
    would put in place. As was the case with the service investment fees, these fees had already
    been earned at the time this dispute arose. Accordingly, I believe the trial court erred in
    declining to order the State to pay the transition fees.
    In summary, I agree with the Majority that IBM was entitled to assignment fees and
    92
    equipment fees, as determined by the trial court. I agree that IBM was entitled to fees
    associated with Change Orders 119 and 133, but not entitled to fees associated with Change
    Orders 71 and 102. I also agree that IBM was not entitled to prejudgment interest. Upon
    my conclusion that IBM did not materially breach the contract, however, I believe IBM
    was entitled to transition fees and $20.8 million in service investment fees, and I would
    affirm the trial court’s award of $2.6 million in early termination closeout payments.
    Accordingly, I would remand this cause to the trial court to determine the amount of
    transition fees and the fees associated with Change Orders 119 and 133.
    93