Boyer Construction Group Corp. v. Walker Construction Company, Inc. and Muller Realty, LLC , 44 N.E.3d 119 ( 2015 )


Menu:
  •                                                                    Sep 24 2015, 9:15 am
    ATTORNEYS FOR APPELLANT                                    ATTORNEYS FOR APPELLEE
    Robert F. Parker                                           Edward P. Grimmer
    Nancy J. Townsend                                          Daniel A. Gohdes
    Burke Costanza & Carberry, LLP                             Crown Point, Indiana
    Merrillville, Indiana
    IN THE
    COURT OF APPEALS OF INDIANA
    Boyer Construction Group                                   September 24, 2015
    Corp.,                                                     Court of Appeals Case No.
    Appellant-Defendant,                                       45A03-1502-PL-66
    Appeal from the Lake Superior
    v.                                                 Court
    The Honorable William E. Davis,
    Walker Construction Company,                               Judge
    Inc. and Muller Realty, LLC,                               Trial Court Cause No. 45D05-
    Appellees-Plaintiffs.                                      1311-PL-127
    Riley, Judge.
    Court of Appeals of Indiana | Opinion 45A03-1502-PL-66 | September 24, 2015               Page 1 of 20
    STATEMENT OF THE CASE
    [1]   Appellant-Defendant/Cross-Appellee, Boyer Construction Group Corp.
    (Boyer), appeals the trial court’s denial of its post-judgment petition for
    attorney’s fees. Appellee-Plaintiff/Cross-Appellant, Walker Construction
    Company, Inc. (Walker), cross-appeals the trial court’s denial of its petition for
    supplemental attorney’s fees.
    [2]   We affirm in part, reverse in part, and remand.
    ISSUES
    [3]   Boyer raises two issues on appeal, which we restate as the following three
    issues:
    (1) Whether the trial court erred in concluding that Boyer had waived its claim
    for attorney’s fees;
    (2) Whether the trial court abused its discretion in denying Boyer’s post-
    judgment petition for attorney’s fees; and
    (3) Whether the trial court erred in issuing a sua sponte correction to its
    judgment, ordering Boyer to pay a portion of Walker’s attorney’s fees.
    [4]   Walker raises one issue on cross-appeal, which we restate as follows: Whether
    the trial court abused its discretion by denying Walker’s petition for
    supplemental attorney’s fees based on its mischaracterization of the fees as
    “post-judgment” work.
    Court of Appeals of Indiana | Opinion 45A03-1502-PL-66 | September 24, 2015   Page 2 of 20
    FACTS AND PROCEDURAL HISTORY
    [5]   In September of 2010, Muller Realty, LLC (Muller) contracted with Boyer, a
    general contractor, to design and build a car dealership in Merrillville, Lake
    County, Indiana. To carry out the project, Boyer subcontracted the concrete
    work to Walker. On August 1, 2011, Boyer and Walker executed two, nearly
    identical Subcontract Agreements. Under one of the Subcontract Agreements,
    the Site Concrete Contract, Boyer agreed to pay the sum of $79,400 for Walker
    to complete the concrete sidewalks, curbs, dumpster pad, and aprons at the
    street entrances. The other Subcontract Agreement, the Building Concrete
    Contract, provided that Boyer would pay Walker the sum of $215,840 for
    completing the concrete footings, foundation walls, and a colored and sealed
    slab-on-grade interior floor. In pertinent part, the Subcontract Agreements
    included the following provision to govern dispute resolution:
    Attorney’s Fees and Consulting Fees (only as needed to defend)
    in the event of any litigation between the parties hereto
    concerning the performance of either party’s services, the
    substantially prevailing party shall be entitled to recover
    reasonable attorney[’s] fees and court costs from the other party.
    (Appellant’s App. p. 39).
    [6]   Walker commenced the work on August 2, 2011. As the project progressed,
    several change orders were incorporated into the Subcontract Agreements,
    adding $8,486 to the total agreed-upon price. Upon completion of various
    phases of the project, Walker was to remit applications for progress payments to
    Boyer. Boyer could then either approve the work and submit the application to
    Court of Appeals of Indiana | Opinion 45A03-1502-PL-66 | September 24, 2015   Page 3 of 20
    Muller to make direct payment to Walker, or Boyer could reject the work and
    notify Walker in writing as to why payment was being withheld. On April 17,
    2012, Walker substantially completed the projects under both the Site Concrete
    Contract and the Building Concrete Contract. That day, Walker submitted
    invoices to Boyer to request a final payment of $30,204.40.
    [7]   In June of 2012, Boyer requested that Walker return to the project site to
    perform additional concrete work not contemplated under the original
    Subcontract Agreements. After completing the additional work, Walker
    submitted an invoice to Boyer on June 14, 2012, in the amount of $1,308.
    Then, in October of 2012, Boyer requested that Walker repair some concrete
    that had been damaged by Boyer’s asphalt subcontractor. Walker completed
    the additional work on October 31, 2012, and submitted an invoice to Boyer on
    November 8, 2012, for $372. It is unclear whether, or at what point, Boyer
    transmitted Walker’s final invoices to Muller for payment, but it is undisputed
    that Walker’s work was not rejected in accordance with the terms of the
    Subcontract Agreements, and Muller never paid Walker the outstanding
    balance of $31,884.40.
    [8]   On December 14, 2012, Walker filed its notice of intent to place a mechanic’s
    lien on the project site, and on March 1, 2013, Walker filed a Complaint for
    Foreclosure of Mechanic’s Lien against Muller and Boyer and further alleged
    that Boyer had breached the Subcontract Agreements. Walker sought judgment
    against both Muller and Boyer in the amount of $31,884.40, plus pre-judgment
    interest, reasonable attorney’s fees, and lien costs. Muller subsequently
    Court of Appeals of Indiana | Opinion 45A03-1502-PL-66 | September 24, 2015   Page 4 of 20
    counter-claimed against Walker, alleging damages resulting from substandard
    workmanship with respect to the slab-on-grade interior floor.
    [9]    On August 11, 2014, the trial court conducted a bench trial, which concluded
    when the final evidence was submitted on August 22, 2014. On November 26,
    2014, the trial court issued its Special Findings of Fact, Conclusions of Law and
    Order (Order). The trial court determined that Walker had “fully complied
    with [its] obligations” by completing the contracted work in a workmanlike
    manner. (Appellant’s App. p. 147). The trial court further concluded that
    Boyer had breached the Subcontract Agreements “by not paying for the work
    Walker did . . . and by neither submitting Walker’s invoices nor rejecting
    Walker[’]s work.” (Appellant’s App. p. 147). Finally, the trial court found that
    Walker was entitled to foreclose on its mechanic’s lien against Muller.
    Accordingly, the trial court entered judgment against Boyer in the amount of
    $1,680 plus pre-judgment interest. As against Muller, the trial court entered
    judgment in Walker’s favor in the amount of $31,884, plus attorney’s fees/costs
    of $41,854.15 and pre-judgment interest of $5,101.44, for a total of $78,839.99. 1
    [10]   On December 17, 2014, Boyer filed a motion to assess attorney’s fees against
    Walker, arguing that because “Walker’s claim against Boyer sought contract
    damages, attorney’s fees, costs, and prejudgment interest that ultimately
    amounted to $78,839.99, but recovered a judgment of only $1,680, 2.1% of the
    1
    On January 30, 2015, Muller satisfied its judgment to Walker in full and is not a party to this appeal.
    Court of Appeals of Indiana | Opinion 45A03-1502-PL-66 | September 24, 2015                          Page 5 of 20
    amount sought, Boyer is the ‘substantially prevailing party’ within the meaning
    of the Subcontract, and therefore ‘shall be entitled to recover reasonable
    attorneys’ fees and court costs’ from Walker.” (Appellant’s App. p. 151).
    Accordingly, Boyer requested an award of $62,984.40 in attorney’s fees and
    expenses. Boyer explained that this amount represented 97.9% of its total fees
    and expenses based on the fact that Walker did prevail on 2.1% of its claim
    against Boyer.
    [11]   Walker responded on December 29, 2014, arguing that Boyer had waived any
    right to recover attorney’s fees by failing to counterclaim or otherwise plead the
    issue prior to the trial court’s judgment. Moreover, Walker claimed to be the
    substantially prevailing party for purposes of the Subcontract Agreements and
    asserted that it had incurred an additional $20,400.28 in attorney’s fees and
    expenses due to extended trial days, post-trial work, and in responding to
    Boyer’s “frivolous, certainly meritless” claim for fees. (Appellant’s App. p.
    173). Walker claimed that “[t]his $20,400.28 in excess of the $41,854.15 is
    assessable against Boyer under the contract and under the doctrine of additur.”
    (Appellant’s App. p. 173).
    [12]   On January 30, 2015, the trial court conducted a hearing on the parties’ cross-
    motions for attorney’s fees. On February 9, 2015, the trial court issued an order
    denying Boyer’s motion, specifically finding that Boyer had waived its claim for
    attorney’s fees by failing to raise the issue either in its Answer, its contentions
    contained in the pre-trial order, or by any evidence at trial. The trial court did,
    however, find that it “should have entered a judgment for attorney fees” against
    Court of Appeals of Indiana | Opinion 45A03-1502-PL-66 | September 24, 2015   Page 6 of 20
    Boyer based on its breach of contract and accordingly ordered Boyer to remit
    $837.08 to Walker “based on the evidence submitted at trial.” (Appellant’s
    App. p. 26). The trial court denied Walker’s “request for additur as to post-
    judgment work.” (Appellant’s App. p. 26).
    [13]   Boyer now appeals, and Walker cross-appeals. Additional facts will be
    provided as necessary.
    DISCUSSION AND DECISION
    I. Appeal
    A. Waiver
    [14]   Boyer contends that the trial court erroneously determined that it had waived its
    claim for attorney’s fees. Our court has previously held that the determination
    of whether a party has waived its claims to attorney’s fees is a matter of law;
    therefore, our review of this issue is de novo. Kintzele v. Przybylinski, 
    670 N.E.2d 101
    , 104 (Ind. Ct. App. 1996). “Indiana adheres to the American rule that[,] in
    general, a party must pay his own attorneys’ fees absent an agreement between
    the parties, a statute, or other rule to the contrary.” R.L. Turner Corp. v. Town of
    Brownsburg, 
    963 N.E.2d 453
    , 458 (Ind. 2012). In this case, the parties
    contractually agreed that “the substantially prevailing party shall be entitled to
    recover reasonable attorney[’s] fees” in the event of litigation. (Appellant’s
    App. p. 39). Subsequent to the trial court’s judgment, Boyer petitioned the
    court for attorney’s fees pursuant to this contractual provision. Because Boyer
    did not raise the issue of attorney’s fees at any point prior to the judgment—i.e.,
    Court of Appeals of Indiana | Opinion 45A03-1502-PL-66 | September 24, 2015   Page 7 of 20
    in its Answer, in a counterclaim, in its pre-trial contentions, or during the bench
    trial—the trial court found the matter waived.
    [15]   On appeal, Boyer asserts that “[u]ntil the trial court entered a judgment
    identifying the ‘prevailing party,’ no right to fees existed and, therefore, the
    right to request such fees could not have been waived prior to the entry of
    judgment.” (Appellant’s Br. p. 7). In turn, Walker contends that “Boyer is not
    to be rewarded for its ‘stealth’ strategy to recover on an issue it did not timely
    place before the court.” (Appellee’s Br. p. 7). Walker further asserts that Boyer
    was obligated to plead its claim for attorney’s fees in a compulsory
    counterclaim under Indiana Trial Rule 13(A).
    [16]   The Indiana Supreme Court has previously stated that “[a] petition for
    [attorney’s] fees does not disturb the merits of an earlier judgment or order”;
    thus, it is not governed by the same deadlines applicable to a motion to correct
    error or motion for relief from judgment. R.L. Turner Corp., 963 N.E.2d at 459-
    60. In fact, “[a] request for attorneys’ fees almost by definition is not ripe for
    consideration until after the main event reaches an end. Entertaining such
    petitions post-judgment is virtually the norm.” Id. at 460. However, to ensure
    that parties do not abuse their right to file a post-judgment petition for
    attorney’s fees with “extremely tardy request[s,]” “trial courts must use their
    discretion to prevent unfairness to parties facing petitions for fees.” Id. In this
    case, Boyer filed its petition for attorney’s fees within a few weeks following the
    trial court’s Order, and Walker was provided with ample opportunity to
    respond with its own cross-motion and to defend against Boyer’s motion during
    Court of Appeals of Indiana | Opinion 45A03-1502-PL-66 | September 24, 2015   Page 8 of 20
    a hearing. See Evergreen Shipping Agency Corp. v. Djuric Trucking, Inc., 
    996 N.E.2d 337
    , 339 n.3 (Ind. Ct. App. 2013).
    [17]   Furthermore, our court has previously allowed claims for attorney’s fees to
    proceed where the issue was not raised prior to final adjudication. In Kintzele,
    
    670 N.E.2d at 102
    , after being dismissed from the case, the defendants filed a
    motion for attorney’s fees pursuant to Indiana Code section 34-1-32-1 (now
    codified at Indiana Code section 34-52-1-1)—i.e., the General Recovery Rule.
    The General Recovery Rule specifies that “[i]n any civil action, the court may
    award attorney’s fees as part of the cost to the prevailing party, if the court finds
    that either party: (1) brought the action or defense on a claim or defense that is
    frivolous, unreasonable, or groundless; (2) continued to litigate the action or
    defense after the party’s claim or defense clearly became frivolous,
    unreasonable, or groundless; or (3) litigated the action in bad faith.” 
    Ind. Code § 34-52-1-1
    (b). The trial court found the defendants had waived their claim for
    attorney’s fees by failing to assert such a claim in their amended answer.
    Kintzele, 
    670 N.E.2d at 102
    . On appeal, our court held that “when responding
    to a complaint, the party is not required to file a claim for attorney’s fees
    pursuant to [the General Recovery Rule] prior to a final adjudication.” 
    Id. at 103
    . Although the case at hand deals with attorney’s fees that arise under
    contract rather than statute, nothing in the Subcontract Agreements specifies
    that the parties must make an affirmative demand for the attorney’s fees prior to
    final adjudication. Rather, once prevailing party status is established, attorney’s
    fees are axiomatic.
    Court of Appeals of Indiana | Opinion 45A03-1502-PL-66 | September 24, 2015   Page 9 of 20
    [18]   Also, in Evergreen Shipping Agency Corp., 996 N.E.2d at 339, the defending
    party—a freight transport company—filed a motion for summary judgment in
    which it sought attorney’s fees from the plaintiff—a freight storage company—
    pursuant to the General Recovery Rule. Although the trial court entered
    summary judgment in favor of the defendant, it denied the request for
    attorney’s fees. Id. After our court affirmed the trial court’s summary
    judgment, the defendant filed a second request for attorney’s fees—this time
    citing the Uniform Intermodal Interchange and Facilities Access Agreement
    (UIIA), to which both parties were signatories and which “entitles the
    prevailing party to recover reasonable attorney’s fees.” Id. The trial court
    granted the defendant’s petition for attorney’s fees, and the plaintiff appealed,
    arguing, in part, that the defendant had “waived its right to seek attorney’s fees
    under the UIIA.” Id. Our court declined to find that the defendant had waived
    its right to seek attorney’s fees even though the defendant had not requested
    attorney’s fees under the UIIA until after the trial court had issued its judgment
    and after our court had decided the matter of summary judgment on appeal. Id.
    at 341. Specifically, we found that it would have been inappropriate for the
    defendant to raise the issue any sooner, such as in a motion to correct error,
    because the defendant “could not have reasonably argued that the trial court
    erred by failing to award it attorney’s fees based on a theory [the defendant] had
    not yet asserted.” Id.
    [19]   Moreover, in finding that the defendant’s claim was not barred by the doctrine
    of res judicata in light of the fact that attorney’s fees had already been requested
    Court of Appeals of Indiana | Opinion 45A03-1502-PL-66 | September 24, 2015   Page 10 of 20
    and denied under the General Recovery Rule, the Evergreen court noted that
    “[t]he UIIA allows the prevailing party to recover reasonable attorney’s fees. In
    the prior action, the trial court had to determine who the prevailing party would
    be. Only after [the defendant] was found to be the prevailing party could it seek
    attorney’s fees pursuant to the UIIA.” Id. at 340. Although we have not been
    presented with the issue of res judicata, we are nevertheless guided by the
    Evergreen court’s rationale. Here, the right to attorney’s fees was contingent
    upon the trial court’s determination of the prevailing party, which was not
    established until the trial court issued its Order. Therefore, we find that the trial
    court erred as a matter of law in determining that Boyer had waived its claim by
    not pursuing attorney’s fees prior to the issuance of the Order.
    B. “Substantially Prevailing Party”
    [20]   Boyer next contends that the trial court abused its discretion by denying its
    petition for attorney’s fees. “When reviewing an award or denial of attorney
    fees, we note that the trial court is empowered to exercise its sound discretion,
    and any successful challenge to its determination must demonstrate an abuse
    thereof.” Delgado v. Boyles, 
    922 N.E.2d 1267
    , 1270 (Ind. Ct. App. 2010), reh’g
    denied, trans. denied. We will find an abuse of discretion if “the trial court’s
    decision is clearly against the logic and effect of the facts and circumstances
    before it.” 
    Id.
    [21]   As already discussed, the Subcontract Agreements provided that “the
    substantially prevailing party shall be entitled to recover reasonable attorney[’s]
    fees and court costs from the other party.” (Appellant’s App. p. 39). According
    Court of Appeals of Indiana | Opinion 45A03-1502-PL-66 | September 24, 2015   Page 11 of 20
    to Boyer, it is entitled to an award of attorney’s fees pursuant to the Subcontract
    Agreements because it “‘substantially prevailed’ in the litigation.” (Appellant’s
    Br. p. 13). More particularly, Boyer argues that
    [t]he net effect of the trial court’s findings was that Muller was
    liable to Walker for $31,884.40 in contract damages, as well as
    attorney’s fees of $41,854.15, and $5,101.44 in pre-judgment
    interest, for a total judgment of $78,839.99. Walker sought the
    same amount against Boyer, but received a judgment for only
    $1,680, prejudgment interest on that amount, and no attorney’s
    fees. Thus, the judgment obtained by Walker against Boyer was
    approximately 2.1% of the amount sought against Boyer. In
    other words, Boyer successfully defended itself against almost
    98% of Walker’s claims.
    (Appellant’s Br. p. 13) (footnote omitted). The trial court subsequently
    amended its Order to also require Boyer to pay $837.08 in attorney’s fees to
    Walker, which “amount represents approximately 2% of the amount of
    attorney’s fees originally requested against Boyer by Walker.” (Appellant’s Br.
    p. 13 n.2). Because it claims to have defended itself against approximately 98%
    of Walker’s claims, Boyer insists that it is entitled to an award of 98% of its total
    attorney’s fees. In turn, Walker argues that Indiana “courts do not recognize
    [that] a party who did not lose as badly as it could have nevertheless ‘prevailed’
    or it is entitled to some percentage of its fees because the judgment it suffered
    was less than 100% of its worst possible day in court.” (Appellee’s Br. p. 16).
    [22]   The issue before our court is one of contract interpretation. “The goal of
    contract interpretation is to ascertain and give effect to the parties’ intent as by
    Court of Appeals of Indiana | Opinion 45A03-1502-PL-66 | September 24, 2015   Page 12 of 20
    the language of the agreement.” Delgado, 
    922 N.E.2d at 1270
    . Clear and
    unambiguous language “must be given its plain and ordinary meaning.” Reuille
    v. E.E. Brandenberger Const., Inc., 
    888 N.E.2d 770
    , 771 (Ind. 2008). Where, as
    here, “parties have executed a contractual provision agreeing to pay attorney
    fees, such agreement is enforceable according to its terms unless the contract is
    contrary to law or public policy.” 
    Id.
    [23]   As in the case at bar, in Reuille, the contract at issue specified that the
    “prevailing party” would be entitled to attorney’s fees, but the term “prevailing
    party” was not defined by the agreement. 
    Id.
     Our supreme court turned to the
    dictionary to ascertain “the ordinary meaning of the term at the time the
    contract was executed[,]” which defined “prevailing party” as follows:
    The party to a suit who successfully prosecutes the action or
    successfully defends against it, prevailing on the main issue, even
    though not necessarily to the extent of his original contention.
    The one in whose favor the decision or verdict is rendered and
    judgment entered.
    
    Id.
     (quoting BLACK’S LAW DICTIONARY 1188 (6th ed. 1990)). The supreme
    court noted that “[t]his definition appears to contemplate a trial on the merits and
    entry of a favorable judgment in order to obtain prevailing party status.” Id. at
    771-72 (emphasis added). At the time the Subcontract Agreements at issue in
    the present case were executed, the dictionary defined the “prevailing party” as
    the “party in whose favor a judgment is rendered, regardless of the amount of
    damages awarded.” BLACK’S LAW DICTIONARY 1232 (9th ed. 2009).
    Court of Appeals of Indiana | Opinion 45A03-1502-PL-66 | September 24, 2015   Page 13 of 20
    [24]   Boyer cites Burras v. Canal Const. & Design Co., 
    470 N.E.2d 1362
     (Ind. Ct. App.
    1984), to support the proposition that “Indiana courts have long allowed the
    recovery of attorney’s fees by a party that did not prevail on all of its claims or
    defenses.” (Appellant’s Br. p. 13). Boyer posits that “contractual attorney’s
    fees ought to be available not just to the party that successfully recovers a
    judgment, but also to the party that successfully defends against a claim. And
    by any reasonable measure of success, Boyer successfully defended against
    Walker’s claims in this case when it prevailed to the tune of winning 98% of the
    battle, while losing only 2%.” (Appellant’s Br. p. 14). We disagree.
    [25]   In Burras, 
    470 N.E.2d at 1364
    , a contractor was awarded damages and
    attorney’s fees following the homeowner’s breach of a construction contract,
    but the homeowners were also awarded damages in their counterclaim for
    breach of warranty. The construction contract contained a provision for
    attorney’s fees in the event that the homeowners defaulted, but on appeal, the
    homeowners challenged the award of attorney’s fees to the contractor as being
    excessive. 
    Id. at 1369-70
    . Our court agreed with the homeowners, finding that
    “the recoverable attorney fees should be reduced ‘in proportion to the amount
    recovered on the [contract] less the amount recovered on the counterclaim.’”
    
    Id. at 1370
     (alteration in original). We found that “[t]his formula enables the
    trial judge to determine the amount of success obtained by the party entitled to
    attorney fees.” 
    Id.
     at 1370 n.4.
    [26]   Contrary to Burras, Boyer did not assert (and therefore did not prevail upon)
    any counterclaims. Moreover, the trial court specifically found that Boyer had
    Court of Appeals of Indiana | Opinion 45A03-1502-PL-66 | September 24, 2015   Page 14 of 20
    not successfully defended itself as it concluded that Boyer breached the
    Subcontract Agreements “by not paying for the work Walker did at the request
    of [Boyer] and by neither submitting Walker’s invoices nor rejecting Walker’s
    work under the [S]ubcontract [Agreements].” (Appellant’s App. p. 147). Thus,
    the trial court ordered that Boyer was liable for the damages resulting
    therefrom. Regardless of the trial court’s allocation of damages between Boyer
    and Muller, the trial court entered judgment entirely in Walker’s favor and did
    not find that Boyer had succeeded on the merits as to a single issue. Therefore,
    the trial court acted within its discretion in denying Boyer’s petition for
    attorney’s fees because it is Walker—not Boyer—that is the substantially
    prevailing party for purposes of the Subcontract Agreements and is entitled to
    the award of attorney’s fees thereunder.
    C. Joint and Several Liability
    [27]   In its Complaint, Walker’s request for damages of $31,884.40 included the
    $1,680 for labor performed outside of the scope of the Subcontract Agreements.
    Similarly, Walker’s request for $41,854.15 in attorney’s fees included the
    $837.08 later assessed against Boyer. Because the trial court did not specifically
    order joint and several liability, it appears that the trial court entered judgment
    on the same $1,680 in damages and the same $837.08 in attorney’s fees against
    both Muller and Boyer, individually. Yet, Boyer presumes that the trial court
    intended to make the judgment joint and several, and because Muller has paid
    its judgment in full, Boyer contends that its liability is therefore satisfied as well.
    On the other hand, Walker argues that the trial court’s judgment was not joint
    Court of Appeals of Indiana | Opinion 45A03-1502-PL-66 | September 24, 2015   Page 15 of 20
    and several and that Boyer has not yet satisfied its obligation to pay $1,680 in
    damages, plus $837.08 in attorney’s fees.
    [28]   In support of its claim to be the substantially prevailing party for purposes of
    attorney’s fees, Boyer asserts that “[t]he adverse joint and several judgment of
    $1,680.00 suffered by Boyer was de minimis when compared to the potential
    liability of almost $80,000.00 which Walker attempted to impose on Boyer, but
    failed.” (Appellant’s Br. pp. 15-16). However, we find that by insisting that the
    trial court intended to impose joint and several liability between Muller and
    Boyer, Boyer actually weakens its own argument that it should be considered
    the “substantially prevailing party.” (Appellant’s App. p. 39). Joint and several
    liability is defined as “[l]iability that may be apportioned either among two or
    more parties or to only one or a few select members of the group, at the
    adversary’s discretion. Thus, each liable party is individually responsible for
    the entire obligation, but a paying party may have a right of contribution and
    indemnity from nonpaying parties.” BLACK’S LAW DICTIONARY 933 (8th ed.
    2004). A determination of joint and several liability would render Boyer
    equally liable with Muller for 100% of Walker’s damages, costs, and fees.
    [29]   In the absence of specificity, we will presume neither that the trial court
    intended to hold Muller and Boyer jointly and severally liable in the amount of
    $78,839.99, nor that the trial court intended to hold Boyer liable for only 2% of
    the total damages sought. Under either scenario, we maintain our finding that
    Walker—not Boyer—is the substantially prevailing party; therefore, Walker—
    not Boyer—is entitled to an award of attorney’s fees pursuant to the
    Court of Appeals of Indiana | Opinion 45A03-1502-PL-66 | September 24, 2015   Page 16 of 20
    Subcontract Agreements. However, we remand this case to the trial court with
    instructions to clarify its Order by either specifying that the judgment is joint
    and several between Muller and Boyer, or to reduce Muller’s share of the
    damages by $1,680 and its share of the attorney’s fees by $837.08.
    D. Sua Sponte Correction of Trial Court’s Order
    [30]   Although the trial court denied the parties’ cross-motions for attorney’s fees, on
    February 9, 2015, the trial court determined that because it “gave a judgment
    for [b]reach of [c]ontract[,]” it “should have entered a judgment for attorney
    fees” against Boyer in the amount of $837.08 based on the evidence submitted
    during the bench trial. (Appellant’s App. p. 26). Boyer now claims that the
    trial court’s sua sponte correction of its initial Order was improper as the court
    “was without the power to ‘correct’ its original judgment since Walker had not
    filed a Motion to Correct Errors, and the time for filing such a motion had
    passed.” (Appellant’s Br. p. 18).
    [31]   Boyer relies on Indiana Trial Rule 52(B), which provides that a trial court,
    “[u]pon its own motion at any time before a motion to correct errors (Rule 59)
    is required to be made, . . . may open the judgment, if one has been entered,
    take additional testimony, amend or make new findings of fact and enter a new
    judgment or any combination thereof” upon certain conditions. A motion to
    correct errors must be “filed not later than thirty (30) days after the entry of a
    final judgment is noted in the Chronological Case Summary.” Ind. Trial Rule
    59(C). According to Boyer’s calculation, the trial court’s deadline for amending
    Court of Appeals of Indiana | Opinion 45A03-1502-PL-66 | September 24, 2015   Page 17 of 20
    its initial Order was January 8, 2015, but the trial court did not issue its order
    requiring Boyer to pay Walker’s attorney’s fees until February 9, 2015.
    [32]   We need not consider whether the trial court issued an untimely correction
    under Trial Rule 52(B) because we find that the trial court was empowered to
    correct the judgment under Indiana Trial Rule 60(A).
    Of its own initiative or on the motion of any party and after such
    notice, if any, as the court orders, clerical mistakes in judgments,
    orders or other parts of the record and errors therein arising from
    oversight or omission may be corrected by the trial court at any
    time before the Notice of Completion of Clerk’s Record is filed
    under Appellate Rule 8.
    T.R. 60(A). In its initial Order, the trial court ordered Muller to pay Walker’s
    attorney’s fees in the amount of $41,854.15. As previously mentioned, this
    figure included the $837.08 that the trial court subsequently determined to be
    Boyer’s share of the fees. Thus, the trial court’s “correction” did not alter the
    total amount of Walker’s judgment. 2 Rather, based on its February 9, 2015
    order, it is apparent that the trial court, despite finding that Boyer breached the
    Subcontract Agreements, mistakenly failed to allocate any responsibility for
    2
    If, on remand, the trial court clarifies that its judgment against Muller and Boyer is joint and several,
    Boyer’s liability for Walker’s attorney’s fees will have been satisfied, and it will be up to Muller to seek
    contribution from Boyer. If the trial court instead determines that Boyer is individually liable for
    approximately 2% of Walker’s total damages, then Muller’s share of the attorney’s fees should be reduced
    and Boyer must pay $837.08 as ordered.
    Court of Appeals of Indiana | Opinion 45A03-1502-PL-66 | September 24, 2015                       Page 18 of 20
    Walker’s attorney’s fees to Boyer, and such an oversight was properly remedied
    by the trial court’s Trial Rule 60(A) authority.
    II. Cross-Appeal
    [33]   On cross-appeal, Walker claims that the trial court abused its discretion by
    denying its petition for supplemental attorney’s fees and expenses in the amount
    of $20,400.28. The trial court summarily denied Walker’s petition for fees for
    “post-judgment work.” (Appellant’s App. p. 26). According to Walker, the
    $20,400.28 included fees incurred as a result of a prolonged trial, post-trial
    work, and responding to Boyer’s claim for attorney’s fees, all of which “were
    [an] integral part of the litigation process to take the contract dispute to
    adjudication.” (Appellee’s Br. p. 25).
    [34]   Boyer, however, asserts that Walker is not entitled to the additional fees
    because it did not substantially prevail under the Subcontract Agreements. We
    are unpersuaded by this argument in light of our determination that Walker was
    indeed the substantially prevailing party. Alternatively, Boyer asserts that
    [c]onsidering that Walker received from Muller every penny of
    fees it requested at trial, considering that the fee award was more
    than the principal amount that Walker claimed was due it under
    the Subcontract, and considering that Walker recovered only
    $1,680.00 from Boyer under the Subcontract, the trial court was
    well within its discretion to limit Walker’s fees to the $41,854.15
    that Muller had already paid, and to decline to assess the
    additional fees solely against Boyer.
    (Appellant’s Reply Br. p. 11). Again, we disagree.
    Court of Appeals of Indiana | Opinion 45A03-1502-PL-66 | September 24, 2015   Page 19 of 20
    [35]   So long as they are not contrary to law or public policy, “courts will enforce”
    contractual provisions for payment of attorney’s fees. Rogers Grp., Inc. v.
    Diamond Builders, LLC, 
    816 N.E.2d 415
    , 420 (Ind. Ct. App. 2004), trans. denied.
    As the substantially prevailing party, Walker is entitled to recover its reasonable
    attorney’s fees and court costs. Neither the Subcontract Agreements nor
    existing case law limit Walker’s recovery of attorney’s fees to only those
    incurred in litigating the action prior to the trial court’s judgment. See, e.g.,
    O’Brien v. 1st Source Bank, 
    868 N.E.2d 903
    , 909 (Ind. Ct. App. 2007) (noting that
    “[w]hen a contract provision provides that attorney fees are recoverable,
    appellate attorney fees may also be awarded”). Accordingly, we remand this
    issue to the trial court with instructions to determine whether Walker’s
    supplemental and “post-trial” attorney’s fees, including any appellate attorney’s
    fees, are reasonable. (Appellee’s Reply Br. p. 5).
    CONCLUSION
    [36]   Based on the foregoing, we conclude that the trial court erroneously concluded
    that Boyer had waived its claim for attorney’s fees. Nevertheless, we further
    conclude that Walker—not Boyer—is the substantially prevailing party
    pursuant to the Subcontract Agreements and is therefore entitled to recover its
    reasonable attorney’s fees. We remand with instructions.
    [37]   Affirmed in part, reversed in part, and remanded.
    [38]   Brown, J. and Altice, J. concur
    Court of Appeals of Indiana | Opinion 45A03-1502-PL-66 | September 24, 2015   Page 20 of 20