RPC Liquidation Vs. Iowa Department Of Transportation ( 2006 )


Menu:
  •                    IN THE SUPREME COURT OF IOWA
    No. 47 / 04-1584
    Filed June 2, 2006
    RPC LIQUIDATION,
    Appellee,
    vs.
    IOWA DEPARTMENT OF TRANSPORTATION,
    Appellant.
    On review from the Iowa Court of Appeals.
    Appeal from the Iowa District Court for Des Moines County, John G.
    Linn, Judge.
    The Iowa Department of Transportation appeals from judgment
    entered following a bench trial that concluded a material supplier had third-
    party beneficiary status under a construction contract and that the Iowa
    Department of Transportation breached the contract.          DECISION OF
    COURT OF APPEALS VACATED; DISTRICT COURT JUDGMENT
    REVERSED AND CASE REMANDED WITH DIRECTIONS.
    Thomas J. Miller, Attorney General, Mark Hunacek, Assistant
    Attorney General, for appellant.
    Robert W. Goodwin, Goodwin Law Office, P.C., Ames, for appellee.
    2
    LAVORATO, Chief Justice.
    In this breach-of-contract action, we must decide whether several
    contracts conferred third-party beneficiary status on a material supplier.
    Following a bench trial, the district court held that they did. Because, as a
    matter of law, we conclude otherwise, we vacate the court of appeals
    decision, reverse the district court judgment, and remand the case with
    directions.
    I. Background Facts and Proceedings.
    The Iowa Department of Transportation (IDOT) had a construction
    project on part of U.S. Highway 218 near Mount Pleasant, Iowa. As a result
    of that project, the IDOT entered into contracts for bridge construction with
    contractors for the work. At issue are contracts that identify Raider Precast
    Concrete, Inc., now known as RPC Liquidation, as a source of material.
    RPC was not a signatory to the contracts. RPC fabricated the beams that
    were used by the contractors in the bridge construction.
    W.W. Transport hauled a load of concrete aggregate from Missouri to
    RPC’s fabrication plant in West Burlington, Iowa. Before this trip, W.W.
    Transport had hauled soybeans from Iowa to Missouri. When the concrete
    aggregate arrived at RPC’s plant, an RPC inspector discovered soybeans in
    the aggregate, apparently because of W.W. Transport’s previous shipment of
    soybeans. The inspector recommended that the aggregate not be used for
    the fabrication of the beams, a recommendation that RPC approved. RPC
    terminated its contract with W.W. Transport to haul coarse aggregate to
    RPC’s plant.
    Several weeks later an IDOT inspector who was on RPC’s premises
    discovered that eleven beams RPC had fabricated showed soybean
    contamination. Later the IDOT rejected ten of the eleven beams because of
    the contamination.
    3
    RPC and W.W. Transport sued the IDOT. Both plaintiffs alleged that
    they were third-party beneficiaries to the contracts between the IDOT and
    the contractors. RPC alleged that the IDOT’s rejection of the ten beams was
    a violation of the contracts resulting in damages to RPC. W.W. Transport
    alleged that as a result of the IDOT’s rejection of the beams, W.W. Transport
    lost its contract with RPC to haul coarse aggregate to RPC’s plant resulting
    in damages to it. In its answer to the allegations of both plaintiffs, the IDOT
    alleged that the contracts specifically provided that there are no third-party
    beneficiaries and that neither party is a third-party beneficiary to the
    contracts referred to in the petition.
    The IDOT moved for summary judgment, contending that neither
    party was a third-party beneficiary of the contracts in question. The district
    court denied the motion as to RPC but granted it as to W.W. Transport.
    W.W. Transport has not appealed and is not involved in these proceedings.
    The case was tried to the court, following which, the court ruled that
    RPC was a third-party beneficiary to the contracts and that the IDOT had
    breached the contracts by rejecting the ten beams. The court awarded RPC
    damages in the amount of $103,589.
    The IDOT appealed, and we transferred the case to the court of
    appeals, which summarily affirmed the district court ruling. We granted the
    IDOT’s application for further review.
    II. Issues.
    The issues are whether RPC was a third-party beneficiary under the
    contracts between the IDOT and the contractors and if so, whether the
    IDOT’s rejection of the beams containing soybeans was a breach of the
    contracts. Because we conclude RPC was not a third-party beneficiary, we
    do not address the damages issue.
    4
    III. Scope of Review.
    This contract case was brought as a law action.          Our review is
    therefore for correction of errors at law. See Fausel v. JRJ Enters., Inc., 
    603 N.W.2d 612
    , 617 (Iowa 1999). The third-party beneficiary question is a
    legal issue, one for the court. Therefore we are not bound by the legal
    conclusions of the district court. 
    Id.
    IV. Third-Party Beneficiary.
    A. Applicable law. In Midwest Dredging Co. v. McAninch Corp., we
    adopted Restatement (Second) of Contracts section 302 relating to third-
    party beneficiaries.   
    424 N.W.2d 216
    , 224 (Iowa 1988).          Section 302
    provides:
    (1) Unless otherwise agreed between promisor and promisee, a
    beneficiary of a promise is an intended beneficiary if
    recognition of a right to performance in the beneficiary is
    appropriate to effectuate the intention of the parties and either
    (a) the performance of the promise will satisfy an
    obligation of the promisee to pay money to the beneficiary; or
    (b) the circumstances indicate that the promisee intends to
    give the beneficiary the benefit of the promised performance.
    (2) An incidental beneficiary is a beneficiary who is not an
    intended beneficiary.
    Restatement (Second) of Contracts § 302, at 439-40 (1981) (emphasis
    added).
    The primary question in a third-party beneficiary case is “whether the
    contract manifests an intent to benefit a third party.” Midwest Dredging,
    
    424 N.W.2d at 224
    . Such intent, however, need not benefit a third party
    directly. Vogan v. Hayes Appraisal Assocs., Inc., 
    588 N.W.2d 420
    , 423 (Iowa
    1999). In applying section 302, we have noted that the promisee’s intent
    generally controls. Midwest Dredging, 
    424 N.W.2d at 224
    . In determining
    such intent, we look to the language of the contract and to the
    circumstances surrounding it. 
    Id. at 225
    .
    5
    When two or more parties enter into a contract, they have separate
    purposes and may be stimulated by various motives. Vogan, 
    588 N.W.2d at 423
    . A person claiming to be a third-party beneficiary may not be acutely
    aware of those motives. 
    Id.
     The general rule is that
    “ ‘[a] third party who is not a promisee and who gave no
    consideration has an enforceable right by reason of a contract
    made by two others . . . if the promised performance will be of
    pecuniary benefit to [the third party] and the contract is so
    expressed as to give the promisor reason to know that such
    benefit is contemplated by the promisee as one of the
    motivating causes of his making the contract.’ ”
    
    Id. at 423-24
     (second alteration in original) (omission in original) (citations
    omitted).
    When a contract expressly negates the creation of third-party
    beneficiaries, we have rejected the claim that such status exists.         See
    Walters v. Kautzky, 
    680 N.W.2d 1
    , 4 (Iowa 2004).          In Walters, prison
    inmates sued the Iowa State Penitentiary claiming to be third-party
    beneficiaries of an agreement between the Iowa Department of Corrections
    and the state public defender. 
    Id. at 2
    . The agreement provided that the
    state public defender would provide limited legal assistance to prison
    inmates. 
    Id. at 2-3
    . “The agreement expressly stated that ‘[t]here are no
    third party beneficiaries to this Agreement. This Agreement is intended only
    to benefit the [Department of Corrections] and the Public Defender.’ ” 
    Id.
    (first alteration in original). The agreement provided that the state public
    defender could contract with private attorneys to provide those services. 
    Id.
    The state public defender contracted with an attorney to advise inmates at
    the state penitentiary.    
    Id.
       The attorney refused to provide services
    requested by the inmates because the agreement did not provide for
    performing such services. 
    Id. at 3-4
    .
    6
    In rejecting the inmates’ third-party beneficiary claim, we relied on
    the opening language in section 302 of the Restatement (Second) of
    Contracts: “Unless otherwise agreed between promisor and promisee.” 
    Id. at 4
    . In relying on this language we said:
    The agreement between [the Department of Corrections] and
    [the state public defender] expressly negates an intention to
    benefit the inmates of the institution where the legal services
    were to be provided. Because [the attorney’s] contract served
    as the implementation of [the state public defender’s]
    agreement with [the Department of Corrections], it must be
    viewed as similarly limited as to the persons to be benefited.
    
    Id. at 4
    .
    B. Analysis. The contracts between the IDOT and the contractors
    incorporated by reference certain standard specifications. One of these
    specifications, which is central to this appeal, provided in part:
    1107.12 RESPONSIBILITY FOR DAMAGE CLAIMS.
    Notwithstanding the above, it is specifically agreed between the
    parties executing this contract that it is not intended by any of the
    provisions of any part of the contract documents to create in the
    public or any member thereof a third party beneficiary
    hereunder, or to authorize anyone not a party to this contract to
    maintain a suit for personal injuries or property damage pursuant
    to the terms or provisions of this contract.            The duties,
    obligations, and responsibilities of the parties to this contract
    with respect to third parties shall remain as imposed by law. . . .
    It is understood that no subcontractor is a third party
    beneficiary to any contract between the Contracting Authority
    and the prime contractor. Nothing in any special provision or
    any supplemental specification shall be construed as
    eliminating or superseding the requirements of this section.
    (Emphasis added.)
    In finding that RPC was a third-party beneficiary, the district court
    first determined that the express disclaimer regarding third party
    beneficiary status in specification 1107.12 did not preclude RPC from
    asserting such status.        The court then focused on section 302 of
    Restatement (Second) of Contracts to determine if RPC was an intended
    7
    beneficiary under that provision. The court concluded that RPC was indeed
    such an intended beneficiary.
    As mentioned, section 302 of the Restatement (Second) of Contracts
    begins with the language “Unless otherwise agreed between promisor and
    promisee.” Pursuant to such language we conclude, contrary to the district
    court, that the disclaimer in specification 1107.12 precluded RPC from
    being a third-party beneficiary. Because of our conclusion, we limit our
    discussion to the disclaimer. Resolving the disclaimer issue requires us to
    construe specification 1107.12.
    In deciding contract issues, our cases have frequently used the terms
    “interpretation” and “construction” interchangeably despite their distinct
    purposes. Connie’s Constr. Co. v. Fireman’s Fund Ins. Co., 
    227 N.W.2d 207
    ,
    210 (Iowa 1975).     Interpretation concerns the meaning of words in a
    contract, an issue for the court unless the meaning depends on extrinsic
    evidence or on a choice among reasonable inferences from such evidence.
    
    Id.
     Construction, on the other hand, concerns the legal effect of a contract,
    an issue that as a matter of law the court decides. 
    Id.
    Our task is to construe—that is, determine the legal effect of—
    specification 1107.12 and determine whether it provides third-party
    beneficiary status to RPC. That question turns on the parties’ intention. In
    determining the parties’ intention we are bound by what the contract says
    except in cases of ambiguity. State Public Defender v. Iowa Dist. Ct., 
    594 N.W.2d 34
    , 37 (Iowa 1999). And when the contract is not ambiguous, we
    will enforce it as written. 
    Id.
    The court construed the disclaimer on third-party beneficiary status
    in specification 1107.12 this way:
    Turning to the first sentence of [specification] 1107.12, it
    is clear that a contractor must indemnify the IDOT for any
    claim or lawsuit brought by a person against the IDOT for
    8
    injuries or damage sustained by a person because of the
    contractor’s acts, omissions, neglect, or use of unacceptable
    materials. The second portion of the indemnification clause
    authorizes the IDOT to retain money from the contractor until
    any such claims or lawsuits are settled. The next sentence of
    the paragraph starts with the phrase “notwithstanding the
    above.” This next sentence deals with third parties, but refers
    back to the preceding sentence. “Notwithstanding” means the
    same as “in spite of.” This sentence must be construed as
    meaning: in spite of the fact that it is agreed a contractor will
    indemnify the IDOT, for any type of claim or lawsuit, no
    member of the public can assert the status of being a third-
    party beneficiary if maintaining a suit for personal injuries or
    property damage. The first two sentences of [specification]
    1107.12 read together require a contractor to indemnify the
    IDOT for any claims or lawsuits brought and in spite of the fact
    that the IDOT has a right of indemnification against a
    contractor, this does not confer upon the public the status of
    third-party beneficiary for any lawsuit against the contractor or
    the IDOT for personal injuries or property damage. These two
    sentences, combined, do not foreclose [RPC] from bringing a
    third-party beneficiary contract claim. [RPC] is not bringing its
    lawsuit against any of the bridge contractors. The issue before
    the Court does not involve the IDOT pursuing indemnification
    from any of the bridge contractors. In addition, [RPC] is not
    alleging the IDOT caused personal injuries or property damage.
    [Specification] 1107.12 does not explicitly bar or prevent [RPC]
    from bringing this third-party beneficiary contract claim.
    (Emphasis added).
    Contrary to the district court’s reasoning, which RPC relies on here to
    uphold the court’s ruling, we agree with the IDOT that the above italicized
    language in specification 1107.12 unambiguously conveys two ideas. First,
    there are no third-party beneficiaries to the contracts. The phrase “public
    or any member thereof” is broad enough to express this idea. Second, none
    of the provisions of the contracts is intended to authorize a non-signatory to
    the contracts to maintain a suit for personal injuries or property damage
    pursuant to the terms or provisions of the contracts. The use of the word
    “or” clearly expresses the intent of the parties that they meant these two
    separate ideas.
    9
    In contrast, the district court’s construction (the language only meant
    that “no member of the public can assert the status of being a third-party
    beneficiary if maintaining a suit for personal injuries or property damage”)
    conveys only the second idea. The court’s construction effectively renders
    the first idea (there are no third-party beneficiaries to the contract)
    meaningless and redundant. We therefore conclude that the first idea
    clearly expresses the intent of the parties to exclude anyone from having
    third-party beneficiary status.      Such exclusion therefore necessarily
    includes RPC. See Iowa Fuel & Minerals, Inc. v. Iowa State Bd. of Regents,
    
    471 N.W.2d 859
    , 863 (Iowa 1991) (holding that a contract is construed as a
    whole and that it is assumed in first instance that no part of it is
    superfluous; an interpretation that gives a reasonable, lawful, and effective
    meaning to all terms is preferred to an interpretation that leaves a part
    unreasonable, unlawful, or of no effect); accord Restatement (Second) of
    Contracts § 203(a), at 92-93; 17A Am. Jur. 2d Contracts § 377, at 364-66
    (2004).
    We likewise reject the district court’s construction that the use of the
    word “notwithstanding” conveys the meaning that
    in spite of the fact that it is agreed a contractor will indemnify
    the IDOT, for any type of claim or lawsuit, no member of the
    public can assert the status of being a third-party beneficiary if
    maintaining a suit for personal injuries or property damage.
    We do so for two reasons. First, we have already construed specification
    1107.12 as prohibiting third-party beneficiaries to the contracts.         The
    prohibition against third-party beneficiary status is therefore not limited, as
    the district court concluded, to members of the public bringing lawsuits
    against the contracting authority for personal injuries and property damage.
    Second, we think the word “notwithstanding” is used to avoid any
    implication of a third-party beneficiary status from the indemnification
    10
    language in the first part of specification 1107.12. This intent to avoid such
    an implication is emphasized by the use of the following italicized language
    in the clause prohibiting third-party beneficiary status:
    Notwithstanding the above, it is specifically agreed between the
    parties executing this contract that it is not intended by any of
    the provisions of any part of the contract documents to create in
    the public or any member thereof a third party beneficiary
    hereunder, or to authorize anyone not a party to this contract
    to maintain a suit for personal injuries or property damage
    pursuant to the terms or provisions of this contract.
    (Emphasis added.) Clearly the language “the provisions of any part of the
    contract” and “pursuant to the terms or provisions of this contract” was
    intended to refer back to the indemnification provision.
    The district court noted that RPC did not bring its lawsuit against any
    of the bridge contractors and that the IDOT did not pursue indemnification
    from them. Like the IDOT, we think that if either scenario were the case,
    that fact proves nothing regarding whether anyone can be a third-party
    beneficiary to the contracts.
    RPC also relies on this part of the district court reasoning to uphold
    the court’s ruling:
    This conclusion [relating to the court’s determination
    that specification “1107.12 does not explicitly bar or prevent
    [RPC] from bringing this third-party beneficiary contract claim”]
    is further supported by the next sentence of the paragraph
    which reads as follows:         “The duties, obligations, and
    responsibilities of the parties to this contract with respect to
    third parties shall remain as imposed by law.” The law in Iowa
    requires the Court to determine whether the contract as a
    whole manifests an intent to benefit a third party. The first two
    sentences of [specification 1107.12] do not negate third-party
    beneficiary claims in a contract action. The third sentence
    then requires the obligations of the contractor and the IDOT,
    with respect to third parties, to remain as imposed by law.
    We likewise reject this reasoning because we have already
    determined, contrary to the district court’s conclusion, that specification
    11
    1107.12 by express language bars the public or any member thereof, which
    includes RPC, from claiming third-party beneficiary status concerning the
    contracts.     Additionally, the language “The duties, obligations, and
    responsibilities of the parties to this contract with respect to third parties
    shall remain as imposed by law” does not change this determination. As
    the IDOT points out, such language merely directs the parties to existing
    law to determine what, if any, obligations are owed to an intended
    beneficiary.   Although such language appears somewhat redundant or
    superfluous, it in no sense establishes an intent to create third-party
    beneficiary status or to negate the third-party beneficiary disclaimer
    language in specification 1107.12. Later in this opinion, we point out that
    the use of redundant or superfluous language is not always outcome-
    determinative.
    Finally, RPC relies on this part of the district court reasoning to
    uphold the court’s ruling:
    The first sentence of the second paragraph of
    [specification] 1107.12 contains a clear pronouncement that no
    subcontractor is a third-party beneficiary to the contract.
    IDOT specification 1101.03 defines the term “subcontractor.”
    The parties agree that [RPC] is not a subcontractor for the
    purpose of this lawsuit. [RPC] is a “source of material” for the
    bridge construction project. If the IDOT intended to eliminate a
    source of material as a third-party beneficiary, then the logical
    place to insert the term would be the sentence which excludes
    subcontractors from the third-party beneficiary status.
    Because a source of material is not specifically excluded from
    third-party beneficiary status, then the obligations of the IDOT
    and the contractor, with respect to third parties, should remain
    as imposed by law. Again, this goes back to construing the
    contract as a whole to determine if [RPC] is an intended
    beneficiary. In construing [specification] 1107.12, [RPC] is not
    explicitly barred or excluded as a third-party beneficiary in
    pursuing its contract claim against the IDOT.
    In short, the court reasoned that because no subcontractor is a third-
    party beneficiary, any entity other than a subcontractor would be a third-
    12
    party beneficiary. As the IDOT asserts, this reasoning might be valid if the
    only contractual provision relating to third-party beneficiary status was the
    one that excluded subcontractors. See Maytag Co. v. Alward, 
    253 Iowa 455
    ,
    460, 
    112 N.W.2d 654
    , 656 (1962) (recognizing that the rule expressio unius
    est exclusio alterius applies in the construction of contracts); Black’s Law
    Dictionary 620 (8th ed. 2004) (defining expressio unius est exclusio alterius
    as a “canon of construction holding that to express or include one thing
    implies the exclusion of the other, or of the alternative”).       The court’s
    reasoning ignores the third-party beneficiary disclaimer language in the
    preceding paragraph. See Estate of Pearson ex rel. Latta v. Interstate Power
    & Light Co., 
    700 N.W.2d 333
    , 343 (Iowa 2005) (“We construe a contract in
    its entirety by considering all of its pertinent provisions.”); see also 5
    Margaret N. Kniffin, Corbin on Contracts § 24.28, at 317 (Joseph M. Perillo
    ed., rev. ed. 1998) (“If a clearer source of information concerning the parties’
    intentions is available, the court will decline to apply the maxim [expressio
    unius est exclusio alterius].”).
    The IDOT, however, concedes that reading the two provisions
    together—the third-party beneficiary disclaimer and the subcontractor
    language—does provide some “mild redundancy.” The IDOT explains away
    this redundancy to our satisfaction.        It notes that the paragraph on
    subcontractors goes on to say: “Nothing in any special provision or any
    supplemental specification shall be construed as eliminating or superseding
    the requirements of this section.” The IDOT explains that this paragraph,
    taken as a whole, was clearly intended to respond to our decision in
    Midwest Dredging.
    In Midwest Dredging, we took notice of several special provisions of
    the contract between the IDOT and the contractor that overrode the
    provisions of the contract and that required hydraulic dredging.           424
    13
    N.W.2d at 225.     These special provisions led us to conclude that the
    dredging contractor, as a third-party beneficiary, could enforce an implied
    warranty by the IDOT that a pit designated by the IDOT could be
    hydraulically dredged in accordance with its plans and specifications. Id.
    Ultimately, it was discovered that the dredging was not feasible. Id. at 219.
    The IDOT asserts here that the subcontractor language in specification
    1107.12 was meant—even at the risk of redundancy—to ensure this
    situation would never arise again.
    Restatement (Second) of Contracts section 203, standards of
    preference in interpretation, provides in relevant part the following:
    In the interpretation of a promise or agreement or a term
    thereof, the following standards of preference are generally
    applicable:
    (a) an interpretation which gives a reasonable, lawful,
    and effective meaning to all the terms is preferred to an
    interpretation which leaves a part unreasonable, unlawful, or
    of no effect.
    Restatement (Second) of Contracts § 203(a), at 92-93 (emphasis added);
    accord Fashion Fabrics of Iowa, Inc. v. Retail Investors Corp., 
    266 N.W.2d 22
    ,
    26 (Iowa 1978).    The key words in this provision are “generally” and
    “preferred,” implying that some redundancy and superfluousness are to be
    considered harmless.
    Comment (b) to this section notes that “[s]ince an agreement is
    interpreted as a whole, it is assumed in the first instance that no part of it
    is superfluous.” Restatement (Second) of Contracts § 203 cmt. (b), at 93.
    The comment, however, also recognizes that “[e]ven agreements tailored to
    particular transactions sometimes include overlapping or redundant or
    meaningless provisions.” Id.; see also Hubbard v. Marsh, 
    241 Iowa 163
    ,
    168, 
    40 N.W.2d 488
    , 491 (1950) (“ ‘[I]t is presumed that no words were used
    14
    aimlessly and that no provision is superfluous unless plainly repetitious.’ ”
    (Citation omitted.)).
    We think the district court’s reasoning takes what is harmless
    redundancy and uses it to render what went before it meaningless. See Am.
    Soil Processing, Inc. v. Iowa Comprehensive Petroleum Underground Storage
    Tank Fund Bd., 
    586 N.W.2d 325
    , 334 (Iowa 1998) (holding that district
    court’s construction of an agreement that rendered part of an agreement a
    nullity violated the rule against construing a contract so that part of it is
    unreasonable, unlawful, or of no effect). Moreover, as the IDOT makes
    clear, it makes no sense to deny third-party beneficiary status to a
    subcontractor but not to the materials supplier. The subcontractor is more
    deserving of protection because the subcontractor has closer ties to the
    contract than the materials supplier.
    For all of these reasons we conclude as a matter of law that RPC is
    not a third-party beneficiary to the contracts.
    V. Disposition.
    Because we find the district court erred as a matter of law in
    interpreting the contracts as conferring third-party beneficiary status to
    RPC, we vacate the court of appeals decision, reverse the district court
    judgment, and remand the case for an order dismissing RPC’s petition.
    DECISION OF COURT OF APPEALS VACATED; DISTRICT COURT
    JUDGMENT REVERSED AND CASE REMANDED WITH DIRECTIONS.