Borst Brothers Construction, Inc. v. Finance of America Commercial, LLC ( 2022 )


Menu:
  •                     IN THE SUPREME COURT OF IOWA
    No. 20–0972
    Submitted March 24, 2022—Filed June 17, 2022
    BORST BROTHERS CONSTRUCTION, INC.,
    Appellee,
    vs.
    FINANCE OF AMERICA COMMERCIAL, LLC
    Appellant.
    ___________________________________
    FINANCE OF AMERICA COMMERCIAL, LLC,
    Appellant,
    vs.
    THOMAS DOSTAL DEVELOPERS, INC., and RANDY T. DOSTAL,
    Appellees,
    and
    KELLY CONCRETE COMPANY, INC., AFFORDABLE HEATING AND COOLING,
    INC., 5 STAR PLUMBING, INC., and BORST BROTHERS CONSTRUCTION,
    INC.,
    Appellees,
    ____________________________________
    BORST BROTHERS CONSTRUCTION, INC.
    Appellee,
    vs.
    FINANCE OF AMERICA COMMERCIAL, LLC,
    Appellant.
    ___________________________________
    FINANCE OF AMERICA COMMERCIAL, LLC,
    Appellee,
    2
    vs.
    THOMAS DOSTAL DEVELOPERS, INC., and RANDY T. DOSTAL,
    Appellants,
    and
    KELLY CONCRETE COMPANY, INC., DARNELL HOLDINGS, LLC d/b/a
    DARNELL CONSTRUCTION, AFFORDABLE HEATING AND COOLING, INC., 5
    STAR PLUMBING, INC., BORST BROTHERS CONSTRUCTION, INC., and KEN-
    WAY EXCAVATING SERVICE, INC.,
    Appellees.
    On review from the Iowa Court of Appeals.
    Appeal from the Iowa District Court for Linn County, Mary E. Chicchelly,
    Judge.
    A commercial lender seeks further review of a court of appeals decision
    affirming the validity and superiority of certain mechanics’ liens. DECISION OF
    COURT OF APPEALS AFFIRMED; DISTRICT COURT JUDGMENT AFFIRMED
    IN    PART   AND     REVERSED    IN   PART    ON     APPEAL,   AFFIRMED    ON
    CROSS-APPEAL.
    Mansfield, J., delivered the opinion of the court, in which Christensen,
    C.J., and Appel and Waterman, JJ., joined. McDermott, J., filed a dissenting
    opinion, in which McDonald and Oxley, JJ., joined.
    3
    John F. Fatino of Whitfield and Eddy, P.L.C., Des Moines, for appellant
    Finance of America Commercial, LLC.
    Matthew L. Preston, Brad J. Brady, and David T. Meyers (until withdrawal)
    of Brady Preston Gronlund PC, Cedar Rapids, for appellee Borst Brothers
    Construction, Inc.
    S.P. DeVolder of The DeVolder Law Firm, P.L.L.C., Norwalk, for appellees
    Thomas Dostal Developers, Inc. and Randy T. Dostal.
    William H. Roemerman of Elderkin & Pirnie, P.L.C., Cedar Rapids, for
    appellee Kelly Concrete Co., Inc.
    4
    MANSFIELD, Justice.
    I. Introduction.
    Since 2012, Iowa has used a centralized, internet-based registry for
    mechanics’ liens. To assure the smooth functioning of this registry, and also
    assure that homeowners and buyers are aware of the risk that such liens may
    be placed on a property, general contractors and owner-builders are supposed
    to post a notice of commencement of work to the central registry within ten days
    of starting work on a residential construction project. If that doesn’t occur, a
    subcontractor may nonetheless post the notice. Indeed, if no notice has already
    been posted, a subcontractor must do so before posting a preliminary lien notice
    and obtaining a mechanics’ lien.
    In this case, an owner-builder didn’t post notices of commencement on the
    registry for five residential lots that it was developing. Accordingly, two
    subcontractors did so, several months after the construction work had actually
    begun. When the project went into default, a priority dispute arose between these
    two subcontractors and the commercial lender for the project. The commercial
    lender claimed that its previously recorded mortgages had priority; the
    subcontractors argued that their mechanics’ liens came first. The district court
    found in favor of the subcontractors, as did the court of appeals. We granted the
    lender’s application for further review.
    We now agree with the courts below and conclude that the 2012 law didn’t
    change the principle that mechanics’ liens will, in some circumstances, have
    priority over previously recorded mortgages. We also conclude that the ten-day
    5
    deadline for posting the notice of commencement to the registry applies to
    general contractors and owner-builders but not to subcontractors. While the
    statutory language in isolation is potentially ambiguous, context provides clarity.
    It wouldn’t make sense to allow subcontractors to step in only if the general
    contractor or owner-builder fails to post the notice of commencement within ten
    days, while requiring subcontractors to meet the same ten-day deadline. Meeting
    a missed deadline is impossible.
    For these reasons, we affirm the decision of the court of appeals and the
    judgment of the district court on the questions of lien validity and priority in this
    case. On the remaining appellate issues, we let the decision of the court of
    appeals stand, although we modify its reasoning on one evidentiary point.
    II. Background Facts and Proceedings.
    A. Background Facts. This case concerns a residential property
    development project in Cedar Rapids known as Hawks Point Seventh Addition.
    Five of the thirty-two lots are at issue here: Lots 5, 6, 7, 8, and 10. Thomas Dostal
    Developers, Inc. owned these properties and served as general contractor for
    their development.
    In November and December 2017, Dostal Developers entered into five
    commercial loans with Finance of America Commercial (FAC)—one loan for each
    property. All five loans were memorialized by promissory notes, secured by
    6
    mortgages, and secured also by guarantees signed by Randy Dostal.1 The
    following table shows the amounts and dates of the five loans:
    Lot Principal Documents                 Mortgage
    # Amount ($)   Signed                  Recorded
    5       153,000        11/10/17        11/13/17
    6       141,750        11/10/17        11/13/17
    7       149,250        11/10/17        11/13/17
    8       170,250        11/10/17        11/13/17
    10      153,000        12/20/17        12/20/17
    By February 2018, Dostal Developers stopped making payments on these loans.
    In August, FAC sent notices of default and acceleration. Dostal Developers did
    not cure the defaults.
    Meanwhile, Dostal Developers had hired several subcontractors to work
    on the properties, including Borst Brothers Construction and Kelly Concrete
    Company. Borst put in sanitary and storm sewers, installed the water main,
    created a temporary rock road, and graded the site. Borst’s work began on July
    3, 2017, and ended on December 19, 2017. Kelly performed various concrete
    jobs between September 2017 and January 15, 2018.
    Dostal Developers never posted a statutory “notice of commencement of
    work” to the Iowa Mechanic’s Notice and Lien Registry (MNLR) to provide notice
    of contracting with subcontractors. See 
    Iowa Code § 572
    .13A(1) (2018). Instead,
    1Randy   Dostal was the president of Dostal Developers. He signed the guaranties for Lots
    5, 6, 7, and 8 as “Randy T. Dostal.” The Lot 10 guaranty was signed “Thomas T. Dostal Dev.”
    But the text of all the guaranties refers to “Randy T. Dostal” as the “Guarantor.”
    7
    Kelly posted notices of commencement for four of the lots on February 1, 2018.2
    Kelly also posted preliminary notices and mechanics’ liens that same day. See
    
    id.
     §§ 572.8(1), .13A(2), .13B(1). The following day, February 2, Borst posted a
    notice of commencement and a mechanics’ lien for all of the Hawks Point
    properties it had performed work on.
    B. The Borst–Kelly Foreclosure Action. Neither Borst nor Kelly received
    full payment for their work. On September 12, Borst filed a petition to foreclose
    its mechanics’ lien in Linn County District Court, alleging Dostal Developers still
    owed it $198,316.59 plus interest.3 Borst named other lien holders as parties,
    including FAC and Kelly.
    Kelly filed an answer, cross-claim, and counterclaim on October 12. It
    asserted that its mechanics’ liens had first-priority status and requested
    foreclosure of those liens in the amount of $39,236.21 plus interest.
    On October 17, FAC moved to dismiss the claims of Borst and Kelly. As to
    Borst, FAC asserted that it had not posted a timely notice of commencement of
    work as required by Iowa Code section 572.13A(2) or a preliminary notice as
    required by section 572.13B(4). Borst responded by posting its preliminary
    notice on November 8. As to Kelly, FAC argued that if Kelly were a subcontractor,
    it had not perfected its liens until February 1, 2018, and, therefore, they were
    inferior to FAC’s mortgages as a matter of law.
    2Thedistrict court found that Kelly failed to file a notice of commencement for the work
    performed on Lot 10.
    3Borst   later reduced its demand to $143,316.59.
    8
    C. The FAC Foreclosure Action. On November 26, the district court
    denied FAC’s motions to dismiss in the Borst–Kelly lien foreclosure action to
    allow for further development of the parties’ positions. By then, FAC had filed its
    own petition to foreclose its mortgages in the Linn County District Court.
    Therein, FAC alleged that its mortgages had priority over any mechanics’ liens of
    Borst and Kelly. FAC also named Randy Dostal individually as a defendant,
    asserting that he was personally liable as a guarantor of FAC’s loans. In total,
    FAC claimed to be owed $827,983.52 plus interest. Early in 2019, the district
    court consolidated the Borst–Kelly case and the FAC case.
    D. Summary Judgment and Trial in the Consolidated Proceedings. On
    November 22, FAC moved for summary judgment in the consolidated case. FAC
    once again argued that the mechanics’ lien holders had failed to post notices of
    commencement within ten days of beginning work, rendering their liens invalid.
    In the alternative, FAC maintained that all mechanics’ liens were junior and
    inferior to its mortgages because the subcontractors’ notices of commencement
    had not been posted until after FAC had recorded its mortgages. Kelly and Borst
    resisted. The district court denied FAC’s summary judgment motion, and the
    case proceeded to a bench trial on all issues, including FAC’s effort to enforce
    Randy Dostal’s personal guaranties.
    At trial, FAC’s vice president of credit and implementation and
    underwriting, Mark Thomas, testified. Through Thomas, FAC offered into
    evidence letters addressed to Dostal Developers that detailed the current payoff
    amounts for all five loans. FAC’s loan sub-servicer, BSI, had created these payoff
    9
    statements per FAC’s request. Thomas testified that BSI regularly provided such
    payoff statements whenever the borrower or the lender requested them. The
    Dostal defendants objected to the admission of the payoff statements on the
    ground that they were hearsay “clearly prepared for litigation purposes, not in
    the regular course of business.” The district court overruled the objection and
    allowed the payoff statements to come into evidence.
    Following trial, the district court entered a ruling that FAC, Borst, and
    Kelly were all entitled to foreclose on their respective mortgages and liens against
    Dostal Developers, with the exception of Kelly’s mechanics’ lien for Lot 10
    because Kelly had failed to post a notice of commencement for that lot. The court
    found that Borst’s and Kelly’s mechanics’ liens on the residential properties were
    valid because the preliminary notices met the requirements for subcontractors
    as set forth in Iowa Code section 572.13B. The court also rejected Dostal
    Developers’ argument that FAC had failed to meet a contractual requirement that
    it give notice before accelerating the balances due under the loans.
    Yet the district court found that Randy Dostal, despite having signed
    personal guaranties, was not personally liable for amounts due on the FAC loans.
    The court reasoned that there was “no evidence in the record to suggest that
    Randy Dostal took any actions herein as an individual. Rather, all actions taken
    by Randy Dostal, the Court finds, were done in his capacity on behalf of Dostal
    Developers.”
    Turning to the question of priority, the district court determined that the
    mechanics’ liens of Kelly and Borst had priority over FAC’s mortgages because
    10
    Iowa Code section 572.18 gives a timely posted mechanics’ lien priority over “all
    other liens” that are perfected subsequent to the beginning of the contractor’s
    work. In the district court’s view, Kelly and Borst posted their mechanics’ liens
    on time—i.e., within ninety days of finishing their work on the properties.
    Therefore, their liens were superior to FAC’s mortgages that were recorded after
    Kelly and Borst began their work. See 
    Iowa Code § 572.18
    . As between Borst and
    Kelly, Kelly had first priority because Kelly had posted its liens first. The district
    court also awarded attorney fees to FAC, Borst, and Kelly as prevailing parties.
    See 
    id.
     § 572.32(1).
    E. The Decision of the Court of Appeals. FAC appealed, and the Dostal
    defendants cross-appealed. FAC raised three issues on appeal, contending:
    (1) the mechanics’ liens of Borst and Kelly were invalid and if not, their liens were
    inferior to FAC’s mortgages; (2) Randy Dostal signed the guaranties in his
    personal capacity and was personally liable; and (3) Borst and Kelly should not
    have prevailed and were not entitled to attorney fees. The Dostal defendants
    cross-appealed and raised three more issues: (1) the payoff statements used to
    show the deficiency amounts were inadmissible hearsay and should not have
    been received in evidence; (2) FAC should not have been allowed to foreclose
    because it did not provide contractually prescribed notices of default and
    acceleration; and (3) FAC should not have been awarded the full amount of
    attorney fees it requested. We transferred the case to the court of appeals.
    The court of appeals reversed the district court on the issue of Randy
    Dostal’s personal liability. The court explained,
    11
    Randy Dostal served as “Guarantor” on the loans made by FAC to
    Dostal Developers. “Thomas Dostal Developers Inc.” was defined as
    the “Borrower.” . . . Dostal signed four of the five agreements
    individually, and the fifth listed him as guarantor and was signed
    individually by [him as] Thomas [T.] Dostal. These signatures stand
    in stark contrast to the mortgage agreements, which Randy Dostal
    signed as president of Thomas Dostal Developers. The language and
    the signatures unambiguously establish Randy Dostal’s intent to
    serve as personal guarantor of the loans extended to Dostal
    Developers.
    On all other issues, the court of appeals affirmed the district court. The
    court “[a]ssum[ed] without deciding” that the payoff statements did not fall
    within the hearsay exception. Yet it rejected the Dostal parties’ appeal on this
    point because it found that Thomas had “testified without objection to the figures
    contained in the documents before the documents were offered or admitted.” It
    found that the five notes could be accelerated by FAC without notice, and in any
    event, FAC had provided notice.
    The court also determined that the mechanics’ liens of Borst and Kelly
    were valid based on a “plain reading” of the statute. It reasoned that the statute
    doesn’t expressly require subcontractors to post notices of commencement
    within ten days as it does general contractors, and such a rule would be
    impractical:
    Section 572.13A(1) requires the general contractor/owner-
    builder—not the subcontractor—to post a notice of commencement
    of work within ten days of the commencement of work. Section
    572.13A(2) allows a subcontractor to make the posting if the general
    contractor/owner-builder does not. . . .
    In terms of a subcontractor’s timing of notices, the
    subcontractor   might    not     know     whether     the    general
    contractor/owner-builder satisfied its obligation to post the notice
    of commencement of work until after the ten-day period set forth in
    section 572A.13A(1) expires. The subcontractor’s first opportunity
    12
    to post its notice of commencement would be on the eleventh day
    after commencement of work.
    Further, based on Iowa Code section 572.18(1), the court of appeals found the
    Borst and Kelly liens had priority over FAC’s mortgages.
    FAC and the Dostal parties sought further review of this decision, which
    we granted. “On further review, we have the discretion to review all or some of
    the issues raised on appeal or in the application for further review.”
    Wermerskirchen v. Canadian Nat’l R.R., 
    955 N.W.2d 822
    , 827 (Iowa 2021)
    (quoting State v. Roby, 
    951 N.W.2d 459
    , 463 (Iowa 2020)). Here, we choose to
    review only two issues: (1) the validity and priority of the subcontractors’
    mechanics’ liens, as to which FAC seeks further review; and (2) the evidentiary
    ruling that admitted loan payoff statements as business records, as to which the
    Dostal parties seek further review. The court of appeals decision shall stand as
    the final decision on all other issues.
    III. Standard of Review.
    An action to enforce a mechanics’ lien is an action in equity. 
    Iowa Code § 572.26
    (1). Equitable proceedings are reviewed de novo. Mlady v. Dougan, 
    967 N.W.2d 328
    , 332 (Iowa 2021); see also Iowa R. App. P. 6.907 (“Review in equity
    cases shall be de novo.”). But “[w]e review questions of statutory interpretation
    for correction of errors at law.” Mlady, 967 N.W.2d at 332 (quoting Standard
    Water Control Sys., Inc. v. Jones, 
    938 N.W.2d 651
    , 656 (Iowa 2020)).
    We review evidentiary rulings on hearsay for errors at law. Buboltz v.
    Birusingh, 
    962 N.W.2d 747
    , 757 (Iowa 2021).
    13
    IV. Analysis.
    A. Validity of the Borst and Kelly Mechanics’ Liens. FAC first contends
    that Borst and Kelly don’t have valid liens because notices were not timely posted
    on the MNLR website as required by Iowa Code sections 572.13A and 572.13B.
    1. Iowa Code section 572.13A. The first of these two provisions, section
    572.13A, is titled “Notice of commencement of work — general contractor —
    owner-builder.” 
    Id.
     § 572.13A. Section 572.13A, subsection 1 requires a general
    contractor or an owner-builder (such as Dostal Developers) who has contracted
    or will contract with a subcontractor to post a notice to the MNLR website no
    later than ten days after work begins and makes the notice effective only for work
    completed after this posting. Specifically, this subsection states,
    Either a general contractor, or an owner-builder who has contracted
    or will contract with a subcontractor to provide labor or furnish
    material for the property, shall post a notice of commencement of
    work to the mechanics’ notice and lien registry internet site no later
    than ten days after the commencement of work on the property. A
    notice of commencement of work is effective only as to any labor,
    service, equipment, or material furnished to the property
    subsequent to the posting of the notice of commencement of work.
    Id. § 572.13A(1). Next, this subsection identifies the information required to be
    included in the posting. Id. § 572.13A(1)(a)–(g). However, a notice of
    commencement of work does not contain information about particular
    subcontractors. See id. It only indicates that a general contractor or
    owner-builder either has hired a subcontractor or intends to hire one in the
    future. See id.
    14
    In the following subsection—section 572.13A, subsection 2—the statute
    expressly allows a subcontractor to post a notice of commencement in the event
    that the general contractor fails to do so:
    If a general contractor or owner-builder fails to post the required
    notice of commencement of work to the mechanics’ notice and lien
    registry internet site pursuant to subsection 1, within ten days of
    commencement of the work on the property, a subcontractor may
    post the notice in conjunction with the posting of the required
    preliminary notice pursuant to section 572.13B. A notice of
    commencement of work must be posted to the mechanics’ notice
    and lien registry internet site before preliminary notices pursuant to
    section 572.13B may be posted.
    Id. § 572.13A(2).
    Whoever posts a notice of commencement of work—whether a contractor,
    an owner-builder, or a subcontractor—is required to provide written notice to
    the owner of the property (if the owner is not an owner-builder). Id. § 572.13A(3).
    Again, this notice provides no information about particular subcontractors. See
    id. Its purpose, seemingly, is to provide general notice that there are (or will be)
    subcontractors with potential lien rights working on the property. See id.
    The notice of commencement of work also results in the MNLR
    administrator (i.e., the secretary of state) assigning an MNLR number to the
    project. Id. § 572.13A(3)(a); see also id. § 572.1(1) (“ ‘Administrator’ means the
    secretary of state.”).
    Finally, section 572.13A, subsection 4 states, “A general contractor who
    fails to provide notice pursuant to this section is not entitled to a lien and remedy
    provided by this chapter.” Id. § 572.13A(4). But only a general contractor’s
    15
    noncompliance with this section forfeits the right to a lien—there is no mention
    of subcontractors here. See id.
    2. Iowa Code section 572.13B. The next Code section, 572.13B, sets forth
    the notice requirements for subcontractors like Borst and Kelly. It is titled
    “Preliminary notice—subcontractor—residential construction.” Id. § 572.13B. It
    states as follows:
    1. A subcontractor shall post a preliminary notice to the
    mechanics’ notice and lien registry internet site. A preliminary
    notice posted before the balance due is paid to the general contractor
    or the owner-builder is effective as to all labor, service, equipment,
    and material furnished to the property by the subcontractor. The
    preliminary notice shall contain all of the following information:
    ....
    b. The mechanics’ notice and lien registry number.
    c. The name, address, and telephone number of the
    subcontractor furnishing the labor, service, equipment, or material.
    ....
    2. At the time a preliminary notice is posted to the mechanics’
    notice and lien registry internet site, the administrator shall send
    notification to the owner, including the owner notice described in
    section 572.13, subsection 1, and shall post the mailing of the notice
    on the mechanics’ notice and lien registry internet site as prescribed
    by the administrator pursuant to rule. Notices under this section
    shall not be sent to owner-builders. Upon request, the administrator
    shall provide proof of service at no cost for the notice required under
    this section.
    3. a. A mechanic’s lien perfected under this chapter is
    enforceable only to the extent of the balance due the general
    contractor or the owner-builder at the time of the posting of the
    preliminary notice specified in subsection 1, and, except for
    residential construction property owned by an owner-builder, also
    is enforceable only to the extent of the balance due the general
    contractor at the time the owner actually receives the notice
    provided pursuant to subsection 2 or paragraph “b”.
    16
    Id. § 572.13B(1)–(3).
    Some differences between section 572.13B and the preceding section are
    noteworthy. First, unlike a notice of commencement of work, a preliminary notice
    can sweep backward: “A preliminary notice posted before the balance due is paid
    to the general contractor or the owner-builder is effective as to all labor, service,
    equipment, and material furnished to the property by the subcontractor.” Id.
    § 572.13B(1). Second, the preliminary notice requires different content. It must
    include the MNLR number for the project that the administrator assigned when
    the notice of commencement of work was filed. Id. § 572.13B(1)(b). And it must
    include information about the subcontractor. Id. § 572.13B(1)(c). Third, a
    subcontractor’s mechanics’ lien is only enforceable “to the extent of the balance
    due the general contractor or the owner-builder” at the time the preliminary
    notice was posted. Id. § 572.13B(3)(a). So to that extent, the preliminary notice
    doesn’t sweep backward.
    If the requirements of Iowa Code section 572.13B are not followed, that
    subcontractor is not entitled to a lien. Id. § 572.13B(4) (“A subcontractor who
    fails to post a preliminary notice pursuant to this section shall not be entitled to
    a lien and remedy provided under this chapter.”).
    Both section 572.13A and section 572.13B apply only to “residential
    construction properties.” Id. §§ 572.13A(5), .13B(5).
    3. Interpretation of these provisions. Having summarized Iowa Code
    sections 572.13A and 572.13B, we now turn to their interpretation and
    application in this case. “Our first task in interpreting a statute is to determine
    17
    whether the relevant language is ambiguous. ‘If the statutory language is plain
    and the meaning clear, we do not search for legislative intent beyond the express
    terms of the statute.’ ” United Elec., Radio & Mach. Workers of Am. v. Iowa Pub.
    Emp’t Rels. Bd., 
    928 N.W.2d 101
    , 109 (Iowa 2019) (citation omitted) (quoting
    State v. Pub. Emp. Rels. Bd., 
    744 N.W.2d 357
    , 360–61 (Iowa 2008)).
    We begin with the statute’s text. Calcaterra v. Iowa Bd. of Med., 
    965 N.W.2d 899
    , 904 (Iowa 2021) (“When interpreting the meaning of a statute, we
    start with the statute’s text.”). FAC’s primary textual argument asserts that
    section   572.13A(2)—which      allows   subcontractors    to   post   a   notice   of
    commencement—expressly sets a ten-day time limit for doing so. FAC points to
    the following language:
    If a general contractor or owner-builder fails to post the required
    notice of commencement of work . . . pursuant to subsection 1,
    within ten days of commencement of the work on the property, a
    subcontractor may post the notice in conjunction with the posting
    of the required preliminary notice pursuant to section 572.13B.
    
    Id.
     § 572.13A(2) (emphasis added). FAC insists that the italicized clause qualifies
    the clause that follows, thus placing a time limit on subcontractors’ ability to post
    a notice of commencement. Borst and Kelly disagree and argue that the italicized
    clause qualifies the preceding “if” clause, and therefore clarifies the amount of
    time general contractors or owner-builders have to post before a subcontractor is
    allowed to do so.
    Perhaps there is some ambiguity here. Given that the clause in question
    is set off by commas on both sides, it is not grammatically clear whether FAC or
    the subcontractors get the better of a debate based on punctuation alone. But a
    18
    broader look at sections 572.13A and 572.13B as a whole provides clarity. See
    Calcaterra, 965 N.W.2d at 904 (“Statutes need to be read as a whole . . . .”
    (quoting Porter v. Harden, 
    891 N.W.2d 420
    , 425 (Iowa 2017))); see also 
    Iowa Code § 4.1
    (38) (“Words and phrases shall be construed according to the context . . . .”);
    Antonin Scalia & Bryan A. Garner, Reading Law: The Interpretation of Legal Texts
    167 (2012) (“Context is a primary determinant of meaning. A legal instrument
    typically contains many interrelated parts that make up the whole. The entirety
    of the document thus provides the context for each of its parts.”). Considering
    the statute as a whole, we are convinced that the ten-day time limit in section
    572.13A    applies   only   to   general   contractors   and   owner-builders,   not
    subcontractors.
    First, timing. As Borst and Kelly point out, it would seemingly be
    impossible for a subcontractor to comply with the same ten-day deadline
    governing contractors and owner-builders that runs from the commencement of
    the overall work. How would a subcontractor know whether a contractor or
    owner-builder had failed to meet the ten-day deadline until that ten-day deadline
    had passed? And different subcontractors arrive on the jobsite at different times.
    What if the subcontractor in question didn’t show up (or wasn’t even hired) until
    more than ten days after the overall work commenced? Under FAC’s
    interpretation, the ten days a subcontractor has in which to post a notice of
    commencement of work must necessarily expire before the condition precedent
    for posting it is even satisfied. This result would be absurd, and absurd results
    should be avoided. See Iowa Ins. Inst. v. Core Grp. of the Iowa Ass’n for Just., 867
    
    19 N.W.2d 58
    , 75 (Iowa 2015) (“We have long recognized that statutes should not
    be interpreted in a manner that leads to absurd results.”); see also 
    Iowa Code § 4.4
    (3) (“In enacting a statute, it is presumed that . . . a just and reasonable
    result is intended.”).
    Also, section 572.13A contemplates one notice of commencement of work
    per project. See 
    Iowa Code §§ 572
    .13A(2) (referring to “the required notice of
    commencement of work”, .13A(3)(a) (stating that after the notice is posted, the
    administrator of the registry “shall assign” a registry number for the improved
    property). The notice of commencement of work triggers the assignment of a
    unique MNLR number for that project that subcontractors later must reference
    when they file any preliminary notices. 
    Id.
     §§ 572.13A(3)(a), .13B(1)(b).
    It would seem odd to allow the fate of all subcontractors to rise or fall based
    on whether one early-arriving subcontractor undertook the chivalrous act of
    posting a notice within ten days of commencement of the overall work for the
    benefit of all subcontractors. Borst and Kelly’s interpretation, by contrast, allows
    a subcontractor that is personally concerned about getting paid and plans to
    post a preliminary notice to protect themselves by posting any missing notice of
    commencement of work “in conjunction with the posting of the required
    preliminary notice.” Id. § 572.13A(2).
    In fact, section 572.13A anticipates that the notice of commencement
    might have to be filed before any subcontractor has even been hired. The notice
    of commencement posting requirement applies to “a general contractor, or an
    owner-builder who has contracted or will contract with a subcontractor.” Id.
    20
    § 572.13A(1) (emphasis added). That being the case, how can subcontractors be
    held to the contractor/owner-builder’s ten-day deadline?
    Further, with respect to a subcontractor, the statute says that the
    subcontractor “may” post the missing notice that the owner-builder/contractor
    has failed to post to the MNLR. Id. § 572.13A(2). It doesn’t say that the
    subcontractor “must.” The “must” language applicable to subcontractors
    surfaces in the following sentence, which provides “[a] notice of commencement
    of work must be posted to the mechanics’ notice and lien registry internet site
    [note the passive voice] before preliminary notices pursuant to section 572.13B
    may be posted.” Id. Logically, therefore, a subcontractor has an option to supply
    a missing notice of commencement of work; the only requirement is that
    somebody do so before preliminary notices may be posted.4
    FAC points out that House File 675, the bill that established these posting
    requirements, had an attached bill explanation indicating that mechanics’ liens
    are only effective for the work accomplished after a notice of commencement has
    been posted. H.F. 675, 84th G.A., 2d Sess., explanation (Iowa 2012). The
    4Itis also worth noting that the secretary of state has interpreted Iowa Code section
    572.13A(2) in the same way that we do. Its rule provides,
    Prior to the posting of a preliminary notice, a notice of commencement of
    work must be posted on the MNLR. If the general contractor or owner-builder has
    not posted a notice of commencement of work on the MNLR within ten days of
    commencement of work on the property, then the subcontractor may post a notice
    of commencement of work on the MNLR prior to posting the preliminary notice.
    
    Iowa Admin. Code r. 721
    —45.5(1)(b).
    We are not deciding today whether the secretary of state has been clearly vested with
    interpretive authority over section 572.13A(2). Iowa Code section 572.34(1) provides that the
    secretary “shall adopt rules pursuant to chapter 17A for the creation and administration of the
    registry.” We simply note that the party charged with administering the MNLR—the secretary of
    state—concurs in our interpretation of the underlying statute.
    21
    explanation stated, “A preliminary notice posted before the balance due is paid
    to the general contractor or owner-builder by the owner is effective as to all labor,
    service, equipment, or material furnished to the property subsequent to the
    posting of the notice of commencement of work.” 
    Id.
     (emphasis added).
    While we do “give weight to explanations attached to bills as indications of
    legislative intent” when a statute is ambiguous, ultimately, “[t]he legislature
    enacts the bill—not the accompanying explanation.” Iowa Ins. Inst., 867 N.W.2d
    at 76 (quoting Star Equip., Ltd. v. State, 
    843 N.W.2d 446
    , 454 & n.3 (Iowa 2014)).
    In this instance, the bill explanation cited by FAC is at odds with the actual text
    of section 572.13B(1), which provides, “A preliminary notice posted before the
    balance due is paid to the general contractor or the owner-builder is effective as
    to all labor, service, equipment, and material furnished to the property”—without
    qualification. 
    Iowa Code § 572
    .13B(1) (emphasis added).
    The bill explanation appears to have mistakenly blended section
    572.13A(1)   with   section   572.13B(1).     The   former   states,   “A   notice   of
    commencement of work is effective only as to any labor, service, equipment, or
    material furnished to the property subsequent to the posting of the notice of
    commencement of work.” 
    Id.
     § 572.13A(1). But section 572.13A, as we have
    discussed, deals with owner-builders and contractors and the validity of
    contractor liens. It is titled “Notice of commencement of work — general
    contractor — owner-builder.” Id. § 572.13A; see State v. Hall, 
    969 N.W.2d 299
    ,
    307 (Iowa 2022) (“Although the title of a statute cannot change the plain meaning
    of the statutory text, it can be considered in interpreting the text.”). By contrast,
    22
    section 572.13B is titled “Preliminary notice — subcontractor — residential
    notice.” 
    Iowa Code § 572
    .13B. It is only logical to conclude that “effective,” as
    used in section 572.13A(1), refers to the effectiveness of a contractor lien; while
    “effective,” as used in section 572.13B(1), refers to the effectiveness of a
    subcontractor lien. Otherwise, the two provisions would be in conflict. See State
    v. Iowa Dist. Ct. for Warren Cnty., 
    828 N.W.2d 607
    , 614 (Iowa 2013) (“We try to
    read statutes to avoid conflicts . . . .”).
    FAC also claims that Borst and Kelly’s interpretation is unfair to
    construction lenders and will allow “third parties [to] be surprised by mechanics’
    liens arising months or years after a subcontractor commences work.” We think
    this concern is overstated.
    Lenders are no worse off than they were before House File 675 was enacted
    in 2012. In fact, they are better off. Previous law allowed all subcontractors to
    perfect mechanics’ liens on residential projects within ninety days after the
    completion of their work without needing to worry about a notice of
    commencement of work having been posted. See 
    Iowa Code §§ 572.8
    –.9 (2011).
    Also, under current law, as under prior law, a construction lender that
    (unlike FAC) recorded its mortgage before a particular subcontractor began its
    work gets priority over that subcontractor’s mechanics’ lien. See 
    id.
     § 572.18(2)
    (2018). This can apply even to advances that the lender makes after the mortgage
    is recorded. See Blue Grass Sav. Bank v. Cmty. Bank & Tr. Co., 
    941 N.W.2d 20
    ,
    23–29 (Iowa 2020) (recognizing that a mortgage’s priority can extend to funds
    advanced after the recording of the mortgage). Additionally, with respect to
    23
    residential construction, a mechanics’ lien is enforceable only to the extent of
    the balance due the contractor or the owner-builder when the preliminary notice
    is filed. 
    Iowa Code § 572
    .13B(3)(a). A prudent lender can use self-protection
    methods such as requiring its borrower to bond the project, joint check or escrow
    arrangements, or requirements that subcontractors waive or subordinate their
    lien rights. Finally, it’s worth noting that subcontractors who work on property
    presumably enhance the value of that property, and thus enhance the value of
    the lender’s collateral—even when the lender stands in a second position behind
    them.
    The point of Iowa Code section 572.13A is to incentivize contractors and
    owner-builders to promptly post the notice of commencement of work and
    thereby activate the MNLR for the jobs they manage, not to penalize
    subcontractors that were not in a position to post that notice of commencement
    until sometime later.
    For all these reasons, we conclude that Borst and Kelly have valid
    mechanics’ liens even though no notices of commencement were posted as to
    any of the five properties until February 2018, months after work on those
    properties actually commenced. The ten-day deadline in both subsections 1 and
    2   of    section   572.13A   applies   to    contractors/owner-builders,   not   to
    subcontractors. Also, Borst’s and Kelly’s mechanics’ liens cover all work they
    performed, subject to the limits in section 572.13B(3)(a), not merely the work
    performed after the notice of commencement was posted. See 
    id.
     § 572.13B(1).
    24
    B. Priority of the Borst and Kelly Mechanics’ Liens. Chapter 572 allows
    mechanics’ liens to obtain priority over other types of liens if certain conditions
    are met. Section 572.18 describes these conditions as follows:
    1. Mechanics’ liens posted by a general contractor or
    subcontractor within ninety days after the date on which the last of
    the material was furnished or the last of the claimant’s labor was
    performed and for which notices were properly posted to the
    mechanics’ notice and lien registry internet site pursuant to sections
    572.13A and 572.13B shall be superior to all other liens which may
    attach to or upon a building or improvement and to the land upon
    which it is situated, except liens of record prior to the time of the
    original commencement of the claimant’s work or the claimant’s
    improvements, except as provided in subsection 2.
    2. Construction mortgage liens shall be preferred to all
    mechanics’ liens of claimants who commenced their particular work
    or improvement subsequent to the date of the recording of the
    construction mortgage lien.
    
    Iowa Code § 572.18
    ; see, e.g., Midland Sav. Bank FSB v. Stewart Grp., LC, 
    533 N.W.2d 191
    , 193 (Iowa 1995) (explaining that mechanics’ liens are preferred over
    all other liens except for a construction mortgage recorded before the
    subcontractor commenced their work).
    The first condition that Kelly and Borst had to satisfy to attain priority over
    other types of liens was to post their mechanics’ liens “within ninety days after
    the date on which the last of the material was furnished or the last of the
    claimant’s labor was performed.” 
    Iowa Code § 572.18
    (1). Both subcontractors
    did so. Borst’s work ended on December 19, 2017, and Borst posted its lien on
    February 2, 2018, forty-six days later. Kelly’s final day working on the property
    was January 15, 2018, and Kelly posted its liens on February 1, eighteen days
    later.
    25
    Next, Borst’s and Kelly’s notices of commencement and preliminary
    notices had to be “properly posted” to the MNLR website. 
    Id.
     We have already
    determined that this occurred.
    Finally, the subcontractors had to commence their work on the properties
    before FAC recorded its mortgages in order to get priority over FAC. See 
    id.
    §§ 572.18(1)–(2). Borst started work on July 3, 2017. Kelly started sometime in
    September 2017. FAC’s earliest mortgages were not recorded until November 13,
    2017, well after the subcontractors had begun their work. That being so, Borst’s
    and Kelly’s mechanics’ liens have priority over FAC’s inferior mortgages.5
    C. Response to the Dissent. The dissent argues that the phrase
    “commencement of the work” as used in the second sentence of Iowa Code
    section 572.13A(2), refers to commencement of that subcontractor’s work. This
    argument avoids some of the possible absurdities discussed in part IV.A above.
    No longer would the subcontractor potentially be required to file the notice of
    commencement of work before arriving at the project or even being hired. But it
    creates other problems.
    For one thing, when the same term is used repeatedly in the same statute,
    we normally give it the same meaning each time. See, e.g., State v. Paye, 
    865 N.W.2d 1
    , 7 (Iowa 2015); State v. Sewell, 
    960 N.W.2d 640
    , 643 (Iowa 2021). It
    would be very odd for every other use of “commencement of work” or
    5Mechanics’   liens have long been given this preference in Iowa. See, e.g., Nw. Nat’l Bank
    of Sioux City v. Metro Ctr., Inc., 
    303 N.W.2d 395
    , 398 (Iowa 1981) (applying the 1979 version of
    Iowa Code section 572.18 and stating that “the mechanic’s lien arises upon furnishing of labor
    or material; not upon its filing”).
    26
    “commencement of the work” to be referring to the commencement of the work
    as a whole, and this use alone to be referring to only that subcontractor’s work.
    Let us quote again Iowa Code section 572.13A(2):
    If a general contractor or owner-builder fails to post the required
    notice of commencement of work to the mechanics’ notice and lien
    registry internet site pursuant to subsection 1, within ten days of
    commencement of the work on the property, a subcontractor may
    post the notice in conjunction with the posting of the required
    preliminary notice pursuant to section 572.13B. A notice of
    commencement of work must be posted to the mechanics’ notice and
    lien registry internet site before preliminary notices pursuant to
    section 572.13B may be posted.
    (Emphasis added.) Under the dissent’s interpretation, “commencement of work”
    as used in the first and second sentences refers to something totally different
    from “commencement of the work” as used in the first sentence. That is
    implausible.
    Note also the use of the definite article, i.e., “the work,” rather than a
    possessive, i.e., “its work.” 
    Id.
     If anything, that helps clarify that the statute is
    referring to the overall work on the property, rather than a specific entity’s work.
    In section 572.18, subsection 1, when the legislature wanted to refer to the
    subcontractor’s commencement of their own work, it used the qualifying phrase
    “the claimant’s work or the claimant’s improvements.” 
    Id.
     § 572.18(1). In
    subsection 2, when the legislature again wanted to refer to a subcontractor’s
    commencement of their own work, it used the qualifying phrase “their particular
    work or improvement.” Id. § 572.18(2). No qualification here.
    Furthermore,     under    the   dissent’s   interpretation,   any   notice   of
    commencement of work has to be filed by the subcontractor within ten days of
    27
    the subcontractor’s commencement of their work. But it also has to be filed “in
    conjunction with the posting of the required preliminary notice.”               Id.
    § 572.13A(2). So subcontractors would have to regularly check the MNLR before
    furnishing anything to a residential jobsite, no matter how minor. If no notice of
    commencement of work appeared in the search, the subcontractor would need
    to file both a notice of commencement of work and a preliminary notice
    immediately. Subsequent subcontractors would not be so time-limited in their
    filing of the preliminary notice since they would not be subject to the “in
    conjunction with” requirement. That seems inequitable.
    Moreover, the dissent’s interpretation fails to harmonize and give effect to
    both Iowa Code section 572.13A(1) and section 572.13B(1). The former states, “A
    notice of commencement of work is effective only as to any labor, service,
    equipment, or material furnished to the property subsequent to the posting of
    the notice of commencement of work.” Id. § 572.13A(1). The latter states, “A
    preliminary notice posted before the balance due is paid to the general contractor
    or the owner-builder is effective as to all labor, service, equipment, and material
    furnished to the property by the subcontractor.” Id. § 572.13B(1). As we have
    already discussed, the logical way to reconcile the two provisions is to conclude
    that the former provision applies to contractors (since the preceding sentence
    talks about the contractor or owner-builder’s duty to post the notice of
    28
    commencement of work), whereas the latter provision applies to subcontractors.
    The dissent gives no effect to the latter provision.6
    Additionally, the dissent’s interpretation still leaves some of the absurdity
    in place. What if the overall work and the subcontractor’s work begin at the same
    time, as can often happen? Once again, the subcontractor won’t know if the
    contractor/owner-builder failed to do what it was supposed to do until the ten
    days have passed, at which point it would be too late for the subcontractor to
    file.
    Finally, it’s notable that the Iowa Practice treatise rejects the dissent’s
    reading of section 572.13A(2) and agrees with ours. According to that treatise:
    If a general contractor or owner-builder fails to post the
    required notice of commencement of work to the mechanics’ notice
    and lien registry internet Web site pursuant to I.C.A. § 572.13B(1)
    within 10 days of commencement of the work on the property, a
    subcontractor may post the notice in conjunction with the posting
    of the required preliminary notice. A notice of commencement of
    6The dissent worries about disparate treatment between contractors and subcontractors
    if the scope-of-the-lien provision in Iowa Code section 572.13A(1) applies only to contractors and
    not subcontractors. Again, the dissent overlooks the fact that the preceding sentence applies
    only to contractors and also overlooks the fact that its interpretation gives no effect to the
    scope-of-the-lien provision in section 572.13B(1).
    In any event, there is no disparate treatment. It is the responsibility of the contractor to
    post the notice of commencement of work. See id. § 572.13A(1) (“[A] general contractor . . . shall
    post a notice of commencement of work . . . .”). This notice doesn’t identify any particular
    subcontractors but gives notice that there are or will be subcontractors on the job. This notice
    contains information that should be readily available to the contractor—i.e., the name and
    address of the owner and the date of commencement of the overall work—but that may not be
    readily available to a subcontractor. See id. § 572.13A(1)(a), (e). Thus, it is fair for the contractor
    to have its lien potentially impacted if it doesn’t do what it is supposed to do.
    By contrast, a subcontractor “may post” the notice of commencement of work if the
    contractor fails to do so. See id. § 572.13A(2). The subcontractor’s lien also may be affected by a
    delay in the posting of the notice of commencement of work, but the effect is only indirect because
    the subcontractor can’t post a preliminary notice until there is a notice of commencement of
    work on file. See id. § 572.13B(3)(a) (stating that the subcontractor’s lien is enforceable only to
    the extent of the balance due the contractor “at the time of the posting of the preliminary notice”).
    It is fair and reasonable for the effect on the subcontractor’s rights to be secondary because the
    subcontractor’s responsibility is secondary.
    29
    work must be posted to the mechanics’ notice and lien registry
    internet website before preliminary notices pursuant to I.C.A.
    § 572.13B may be posted.
    10 Barry A. Lindahl, Iowa Practice Series: Civil Practice Forms § 61:3, at 717
    (2022 ed. 2022); see also id. § 61:3, at 718 (“A general contractor who fails to
    provide the required notice is not entitled to a lien and remedy provided by this
    chapter.”). The citation to section 572.13B(1) is a technical error; it should be
    section 572.13A(1). But substantively, the treatise agrees with our view that the
    second comma is the one that does the work. The treatise also agrees that the
    “effective” language in that section applies to the general contractor. Id. § 61:3,
    at 717.
    We respectfully decline to adopt the dissent’s views.
    D. Admissibility of FAC’s Loan Payoff Statements. We now address the
    evidentiary issue raised by the cross-appeal. Dostal Developers and Randy
    Dostal contend that the loan payoff statements created by FAC’s sub-servicer
    and offered into evidence through an FAC employee were inadmissible hearsay.
    The district court, however, admitted the payoff statements under the business
    records exception. When the court of appeals considered this issue on appeal, it
    determined that any error in admitting the records would have been harmless
    because FAC’s Mark Thomas “testified without objection to the figures contained
    in the documents before the documents were offered or admitted.”
    We question whether Thomas actually testified to the figures contained in
    the documents “without objection.” This was a trial to the court. In the course of
    attempting to lay foundation for the admission of each of the five payoff
    30
    statements, FAC’s attorney asked Thomas to describe the contents of each such
    statement, including unpaid principal and interest. This occurred without
    objection. But when FAC tried to offer the statements themselves into evidence,
    the Dostal parties objected. Although the better practice would have been to
    object to testimony about the contents of exhibits that were not yet in evidence,
    we are not prepared to accept the court of appeals’ characterization of the
    situation as a waiver, at least with a bench trial. So, we turn to the merits.
    FAC argues the payoff statements were properly admitted anyway under
    Iowa Rule of Evidence 5.803(6) as business records. In the proceedings below,
    the Dostal parties objected on the ground the statements were prepared for
    litigation purposes rather than in the ordinary course of business.
    We disagree. The record shows that FAC’s loan sub-servicer, BSI, routinely
    furnished these types of payoff statements per FAC’s request. Thomas explained,
    “It’s the standard practice for how we order payoffs when we, the lender, want to
    know what is outstanding on the loans.” He confirmed it was “the regular
    practice of FAC to get payoff statements to show the balance of a loan at any
    given time.” So while these particular statements may have been requested for
    litigation purposes, from the standpoint of the party that prepared them (BSI)
    they were ordinary business records. See, e.g., U.S. Bank Tr., N.A. v. Jones, 
    925 F.3d 534
    , 537–38 (1st Cir. 2019) (Souter, J.) (upholding the admission under the
    business records exception of a computer printout that contained an account
    summary and a list of transactions related to the loan); Deutsche Bank Nat’l Tr.
    Co. v. de Brito, 
    235 So. 3d 972
    , 975–76 (Fla. Dist. Ct. App. 2017) (finding that a
    31
    payoff printout from a third-party vendor should have been admitted into
    evidence under the business records exception); Beal Bank, SSB v. Eurich, 
    831 N.E.2d 909
    , 913 (Mass. 2005) (“Clearly, EPS, as the bank’s servicing agent, had
    a business duty accurately to maintain such records for the bank. Given EPS’s
    obligation to maintain these records, and the bank’s reliance on such records,
    the judge was warranted in finding that the two computer printouts were made
    in good faith and in the regular course of business.”).
    V. Conclusion.
    For the foregoing reasons, we affirm the decision of the court of appeals.
    We reverse the district court on the issue of Randy Dostal’s personal liability but
    affirm it in all other respects. The case is remanded for further proceedings
    consistent with this opinion.
    DECISION OF COURT OF APPEALS AFFIRMED; DISTRICT COURT
    JUDGMENT AFFIRMED IN PART AND REVERSED IN PART ON APPEAL,
    AFFIRMED ON CROSS-APPEAL.
    Christensen, C.J., and Appel and Waterman, JJ., join this opinion.
    McDermott, J., files a dissenting opinion, in which McDonald and Oxley, JJ.,
    join.
    32
    #20–0972, Borst Bros. Constr., Inc. v. Thomas Dostal Devs., Inc.
    McDERMOTT, Justice (dissenting).
    I respectfully dissent from the majority’s holding that the mechanics’ liens
    have priority over the bank’s construction mortgages in this case. I disagree with
    the majority’s interpretation of the mechanic’s lien recording statutes found in
    Iowa Code sections 572.13A and 572.13B (2018), and would hold that the
    required notices in this case weren’t properly posted and thus the
    subcontractors’ mechanics’ liens are subordinate to the bank’s construction
    mortgages.
    As the majority correctly recites, section 572.13A, subsection 1 requires a
    general contractor or owner-builder who has contracted with a subcontractor to
    post a “notice of commencement of work” to the mechanic’s notice and lien
    registry website “no later than ten days after the commencement of work on the
    property.” 
    Id.
     § 572.13A(1). The statute continues: “A notice of commencement
    of work is effective only as to any labor, service, equipment, or material furnished
    to the property subsequent to the posting of the notice of commencement of
    work.” Id.
    Dostal Developers, the owner-builder, failed to post a notice of
    commencement. Section 572.13A, subsection 2 spells out the requirements for
    subcontractors to file mechanics’ liens when the general contractor or owner-
    builder doesn’t file a notice of commencement:
    If a general contractor or owner-builder fails to post the required
    notice of commencement of work to the mechanics’ notice and lien
    registry internet site pursuant to subsection 1, within ten days of
    commencement of the work on the property, a subcontractor may
    33
    post the notice in conjunction with the posting of the required
    preliminary notice pursuant to section 572.13B.
    Id. § 572.13A(2).
    Both the majority and I read the sentence as an “if-then” statement (also
    known as a “conditional” sentence); we just disagree on where the unwritten,
    implied “then” goes. I believe the sentence must be read as follows: “If a general
    contractor or owner-builder fails to post the required notice of commencement
    . . . pursuant to subsection 1, [then] within ten days of commencement of the
    work on the property, a subcontractor may post the notice in conjunction with
    the posting of the required preliminary notice.” Id. (emphasis added). The
    majority’s reading places the implied “then” later: “If a general contractor or
    owner-builder fails to post the required notice of commencement . . . pursuant
    to subsection 1, within ten days of commencement of the work on the property,
    [then] a subcontractor may post the notice in conjunction with the posting of the
    required preliminary notice.” Id. (emphasis added).
    The phrase “within ten days of commencement of the work on the
    property” is set off by commas on both sides. Id. The majority’s reading more or
    less ignores the comma between “subsection 1” and “within ten days.” Such a
    reading thus treats the phrase set off by commas as simply providing more
    information about the requirements of subsection 1. But that’s already achieved
    by the sentence’s explicit reference to it: “pursuant to subsection 1.” Id.
    Subsection 1, as we know, requires the posting within ten days of
    commencement. Id. § 572.13A(1). The legislature had no need to repeat the
    particular detail that subsection 1 included a ten-day deadline.
    34
    Conversely, if we read the sentence in a way that gives effect to the comma,
    the phrase “within ten days of commencement of the work on the property” does
    some work in the sentence: it imposes a deadline on the subcontractor to post
    the notice of commencement if the general contractor or owner-builder didn’t
    already. The majority’s reading suggests that there’s no deadline; the
    subcontractor could post the notice of commencement months, or potentially
    years, after starting its work on the project without consequence. By reading the
    phrase “within ten days of commencement of the work on the property” as
    establishing a deadline tied to the subcontractor’s actual start of work on the
    project, the “notice of commencement” actually gives meaning to the word
    commencement.
    The majority also reads “the work” in section 572.13A, subsection 2 to
    refer only to the general contractor’s or owner-builder’s work, not the
    subcontractor’s own work. On this, too, I disagree with the majority. The word
    “work” is used over twenty-five times in chapter 572. See generally id. ch. 572.
    It’s not defined anywhere in the statute, but by context we see that it refers
    generally to furnishing labor or materials that improve the property, without
    regard to any particular person. For instance, Iowa Code section 572.2 sets forth
    the “persons entitled to lien” and refers to “work” by owners, owner-builders,
    general contractors, and subcontractors:
    Every person who furnishes any material or labor for, or performs
    any labor upon, any building or land for improvement, alteration, or
    repair thereof, including those engaged in the construction or repair
    of any work of internal or external improvement . . . by virtue of any
    35
    contract with the owner, owner-builder, general contractor, or
    subcontractor shall have a lien upon such building or improvement.
    Id. § 572.2(1) (emphasis added). The term “the work” in section 572.13A,
    subsection 2 can be, and makes most sense in context, applied with reference to
    the subcontractor’s work on the project. Id. § 572.13A(2). Such a reading also
    resolves the potential problem that the majority raises about a subcontractor
    needing to file the notice of commencement within ten days of the general
    contractor’s or owner-builder’s work on the project, which a subcontractor
    (particularly one hired for the project long after other work has started) might
    have no information about.
    A notice of commencement of work posted to the mechanic’s notice and
    lien registry website puts the world on notice that at least one subcontractor has
    performed (or is about to perform) work on the project that will trigger potential
    lien rights against the property. I disagree with the majority’s suggestion that “[a]
    prudent lender can use self-protection methods” (including, for example,
    “requiring the borrower to bond the project”) to guard against the prospect of
    unrevealed mechanic’s lien claimants. If the statutory requirements are followed,
    a lender advancing funds on a project should be able to check the mechanic’s
    notice and lien registry website to determine whether a notice has been filed and
    thus whether a mechanic’s lien claimant might exist. A “notice and lien registry”
    that provides no notice of any potential lien isn’t much of a “notice and lien
    registry.” The majority’s interpretation torpedoes an obvious benefit of the
    statute.
    36
    Perhaps more importantly, as section 572.13A, subsection 1 states, a
    notice of commencement of work is only effective for labor or material furnished
    after the notice of commencement of work is posted. The majority points out that
    this particular sentence isn’t restated in subsection 2, and from that concludes
    that the limitation applies only to general contractors and owner-builders. But I
    struggle to pull that from the text of the statute, considering that the sentence
    merely states: “A notice of commencement of work is effective only as to any
    labor, service, equipment, or material furnished to the property subsequent to
    the posting of the notice of commencement of work.” Id. § 572.13A(1). The
    limitation, by my reading of section 572.13A, attaches to the notice of
    commencement irrespective of the party that filed it.
    Besides running contrary to the text of section 572.13A, subsection 2, the
    majority’s reading that this limitation applies only to general contractors and
    owner-builders but not to subcontractors would have a strange result. The notice
    of commencement requirement has a simple function: it discloses that a general
    contractor or owner-builder “has contracted or will contract with a subcontractor
    to provide labor or furnish material for the property.” Id. § 572.13A(1). It
    announces, in other words, that as to the particular property at issue, at least
    one potential lien-exercising subcontractor exists. Under the majority’s reading,
    there’s no consequence to a subcontractor that fails to timely post the notice of
    commencement disclosing that it (a subcontractor) exists, but a general
    contractor or owner-builder that fails to timely post the same notice about a
    subcontractor suffers a consequence. Considering the subcontractor-disclosing
    37
    aim of section 572.13A, the disparate treatment strikes me as contrary to both
    text and logic.
    Iowa Code section 572.18 grants mechanic’s liens priority over other liens
    in certain circumstances. Section 572.18(1) describes those circumstances:
    Mechanics’ liens posted by a general contractor or subcontractor
    within ninety days after the date on which the last of the material
    was furnished or the last of the claimant’s labor was performed and
    for which notices were properly posted to the mechanics’ notice and
    lien registry internet site pursuant to sections 572.13A and 572.13B
    shall be superior to all other liens which may attach to or upon a
    building or improvement and to the land upon which it is situated,
    except liens of record prior to the time of the original commencement
    of the claimant’s work or the claimant’s improvements, except as
    provided in subsection 2.
    (Emphasis added.) Subsection 2 then states that construction mortgage liens
    have priority over all mechanic’s liens whose claimants commenced their
    particular work after the date that the lender recorded its construction mortgage
    lien. Id. § 572.18(2).
    For mechanics’ liens to have priority over other liens, the mechanics’ liens
    (1) must be posted within ninety days from when labor or materials were last
    provided and (2) notices must be “properly posted to the mechanics’ notice and
    lien registry internet site pursuant to sections 572.13A and 572.13B.” Id.
    § 572.18(1). Because Borst and Kelly failed to timely file a notice of
    commencement within ten days of beginning their work, notices were not
    “properly posted to the mechanics’ notice and lien registry internet site pursuant
    to sections 572.13A and 572.13B.” Id. Their mechanics’ liens thus should not
    have priority over Finance of America’s construction mortgage under section
    572.18, and I would reverse the district court’s ruling that held to the contrary.
    38
    McDonald and Oxley, JJ., join this dissent.