Troy McCormick and Lynn McCormick v. Nikkel & Associates, Inc. D/B/A NAI Electrical Contractors, a Corporation , 819 N.W.2d 368 ( 2012 )


Menu:
  •                     IN THE SUPREME COURT OF IOWA
    No. 10–1889
    Filed May 25, 2012
    TROY MCCORMICK and
    LYNN MCCORMICK,
    Appellants,
    vs.
    NIKKEL & ASSOCIATES, INC. d/b/a
    NAI ELECTRICAL CONTRACTORS,
    a Corporation,
    Appellee.
    On review from the Iowa Court of Appeals.
    Appeal from the Iowa District Court for Cherokee County, Nancy L.
    Whittenburg, Judge.
    A subcontractor seeks further review of a court of appeals decision
    reversing the summary judgment in its favor in a negligence case.
    COURT       OF   APPEALS   DECISION    VACATED;     DISTRICT     COURT
    JUDGMENT AFFIRMED.
    Steven D. Hamilton of Hamilton Law Firm, P.C., Storm Lake, for
    appellants.
    Ned A. Stockdale of Fitzgibbons Law Firm, L.L.C., Estherville, for
    appellee.
    2
    MANSFIELD, Justice.
    This case presents the question whether a subcontractor that
    properly performs electrical work on a jobsite, then locks up the work
    and transfers control to the property owner, owes a duty of care to an
    employee of the owner electrocuted six days later when the owner fails to
    deenergize the work site in contravention of various warnings and
    regulations.      We conclude that no such duty is owed under the
    circumstances. Accordingly, we affirm the summary judgment granted
    by the district court and vacate the decision of the court of appeals
    reversing that grant of summary judgment.
    I. Facts and Procedural Background.
    Little Sioux Corn Processors operates an ethanol plant located near
    Marcus, Iowa.1 In 2006, Little Sioux was expanding the capacity of that
    plant. Part of that expansion involved electrical upgrades and changes.
    Little Sioux hired Fagen Engineering, Inc. to design the new electrical
    loop and to specify the electrical equipment to be included in the loop.
    Little Sioux purchased the electrical equipment needed for the electrical
    loop from Graybar Electric. Among the items purchased from Graybar
    were several switchgears. A switchgear is a large metal cabinet mounted
    on a pad that receives and transmits high-voltage electricity and,
    through mechanically operated switches, controls the overall flow of
    electricity within the distribution system.
    Little Sioux hired a contractor, Schoon Construction Company, to
    work on the electrical loop by boring in and pulling the electrical cables
    that connected the components of the new electrical loop and placing
    and installing the switchgears on their mounting basements. Schoon in
    1Because    this case was resolved on a motion for summary judgment, we set
    forth the facts in the light most favorable to the nonmoving party, i.e., the plaintiff.
    3
    turn hired the defendant, Nikkel & Associates, Inc., to do “terminations,”
    which involved hooking up electrical cables to terminals in the
    switchgears. This work was performed by early October 2006, and the
    lines were energized through the switchgears.
    Little Sioux also purchased fault indicators from Graybar. These
    optional devices were to be mounted inside the switchgear cabinet.       A
    fault indicator signals when there is an interruption or fault in the
    electrical circuit.
    The original plan was for Nikkel to install the fault indicators
    inside the cabinets. However, it turned out the holes on the mounting
    brackets were too small. On November 7, 2006, Ken (Buford) Peterson,
    of Nikkel, spoke with Russell Konwinski, Little Sioux’s maintenance
    manager, and offered to drill out the holes in the brackets.      To save
    money, Konwinski declined the offer and said he would have his
    personnel modify the mounting brackets and install them in the
    switchgear cabinets.
    Peterson left the work site pending the completion of that task.
    When Peterson left, the switchgear cabinets were closed and secured
    with penta-head bolts that could only be removed through the use of a
    special penta-head socket wrench, which Little Sioux had ordered along
    with the electrical equipment. In addition, the switchgear cabinets bore
    signs warning of the hazard of high voltage.
    Six days later, on November 13, 2006, Little Sioux’s Konwinski
    asked fellow employee Mike Jacobson, an electrician, to remove, drill out,
    and install the fault indicator brackets. Jacobson said he needed help
    because of other things going on, so Konwinski assigned Jeff Sangwin
    and Troy McCormick, the plaintiff, to assist Jacobson.         Konwinski
    believed the switchgears were not energized and so informed the group.
    4
    Little Sioux’s general manager, Steve Roe, knew that Switchgear
    #4, where the accident occurred, was energized on November 13. In fact,
    it had to be energized in order for the plant to be running because it was
    on the line between the main panel and the plant.
    Peterson reenergized the electrical circuit from the main panel to
    Switchgear #4 before he left the site on November 6. Peterson claims he
    energized the line in the presence of Konwinski and Jacobson. However,
    in an affidavit, Konwinski denied he was present. Konwinski also stated
    in his affidavit, “I had asked Buford Peterson to tell when the power
    would be turned on but I was not told by him before November 13, 2006,
    that it was on.”
    It is undisputed that both Little Sioux’s and OSHA’s safety
    regulations required employees to deenergize and lock out or tag
    electrical equipment before beginning work.      These rules required the
    employee to assume all electrical equipment was energized until proven
    otherwise.    The lockout/tag procedures were not followed by the Little
    Sioux employees the day McCormick was injured.
    After being assigned to remove, drill out, and install the brackets,
    Jacobson used the penta-head socket wrench to open two of the
    switchgear cabinets so the brackets could be removed and the holes
    redrilled. However, when Jacobson was called away to help with another
    project at the plant, he left McCormick and Sangwin to complete the
    work.    Neither McCormick nor Sangwin had prior electrical training.
    McCormick used the wrench to open the cabinet door to Switchgear #4.
    After removing the bracket and redrilling the holes, McCormick received
    a severe electrical shock when he tried to reinstall the bracket in the
    cabinet. He survived but sustained substantial injuries.
    5
    McCormick and his spouse sued Nikkel, alleging it had control of
    the switchgear box and failed to warn him the switchgear was energized.
    Nikkel moved for summary judgment on the grounds that it owed no
    duty to McCormick because it did not have control of the switchgear box
    when McCormick was injured. Nikkel argued the relevant duties rested
    with Little Sioux, which owned and controlled the switchgear box and
    controlled the work being performed by McCormick at the time of the
    accident.
    The district court granted Nikkel’s motion for summary judgment.
    It agreed with Nikkel that it owed no duty to McCormick because Nikkel
    did not have control of the switchgear box when McCormick performed
    work on it and was injured. The court found, rather, that Little Sioux
    had retained control over the electrical work that caused McCormick’s
    injury.   As the court put it, “[T]he controlling issue is control of the
    premises.”   The court also concluded that whether Petersen warned
    anyone the switchgear was energized was not a material fact because
    “Little Sioux had a duty to provide a safe workplace to Troy McCormick,
    which includes testing electrical equipment to see if it is energized, in
    accordance with OSHA and Little Sioux policy.”
    McCormick appealed, and the court of appeals reversed the district
    court’s grant of summary judgment.       It reasoned that Nikkel was in
    control “when the alleged negligent act occurred,” i.e., when Peterson
    energized the line prior to McCormick’s injury.
    Nikkel sought, and we granted, further review.
    II. Standard of Review.
    We review a trial court’s grant of summary judgment for
    correction of errors at law.      On motion for summary
    judgment, the court must: (1) view the facts in the light most
    favorable to the nonmoving party, and (2) consider on behalf
    6
    of the nonmoving party every legitimate inference reasonably
    deduced from the record. Summary judgment is appropriate
    if “there is no genuine issue as to any material fact and . . .
    the moving party is entitled to judgment as a matter of law.”
    The existence of a legal duty is a question of law for the court
    to decide.
    Van Fossen v. MidAmerican Energy Co., 
    777 N.W.2d 689
    , 692–93 (2009)
    (citations omitted).
    III. Analysis.
    A. Duty and the Control Principle.         An actionable negligence
    claim requires “the existence of a duty to conform to a standard of
    conduct to protect others, a failure to conform to that standard,
    proximate cause, and damages.”       Thompson v. Kaczinski, 
    774 N.W.2d 829
    , 834 (Iowa 2009) (citation and internal quotation marks omitted).
    “Whether a duty arises out of a given relationship is a matter of law for
    the court’s determination.” 
    Id. Historically, the
    duty determination focused on three factors: the
    relationship between the parties, the foreseeability of harm, and public
    policy. 
    Id. at 834.
    In Thompson, we said that foreseeability should not
    enter into the duty calculus but should be considered only in
    determining whether the defendant was negligent. 
    Id. at 835.
    But we
    did not erase the remaining law of duty; rather, we reaffirmed it. 
    Id. at 834–36.
    In short, a lack of duty may be found if either the relationship
    between the parties or public considerations warrants such a conclusion.
    In Van Fossen, we made clear again that our previous law of duty
    was otherwise still alive and well.      Thus, we held that employers of
    independent contractors do not owe a general duty of due care under
    Restatement (Third) of Torts section 7, but owe only a limited duty as
    described in Restatement (Second) of Torts section 413. 
    Id. at 696–97.
    We reiterated that “[u]nder the retained control standard, one who
    7
    employs an independent contractor is not liable unless he retains control
    of the contractor’s day-to-day operations.” 
    Id. at 697.
    Van Fossen thus
    illustrated one example where the relationship between the parties
    resulted in no general duty of reasonable care. As we explained,
    The limited nature of the duty owed by employers of
    independent contractors takes into account the realities of
    the relationship between employers and their contractors.
    One of these realities is that employers often have limited, if
    any, control over the work performed by their contractors.
    Employers typically hire contractors to perform services
    beyond the employers’ knowledge, expertise, and ability. The
    contractors’ knowledge and expertise places them in the best
    position to understand the nature of the work, the risks to
    which workers will be exposed in the course of performing
    the work, and the precautions best calculated to manage
    those risks. These realities dictate that the persons in the
    best position to take precautions to manage the risks are the
    contractors. The policy of the law therefore justifies the rule
    placing the primary responsibility on the contractor for
    assuring proper precautions will be taken to manage risks
    arising in the course of the performance of the work. The
    same realities justify the well-established rules limiting the
    liability of employers of independent contractors to the
    circumstances specified in Restatement (Second) sections
    413, 416, and 427. If liability were not limited in this
    fashion, inefficiencies would result as employers would be
    required to develop the knowledge and expertise in their
    contractors’ fields so as to be prepared to understand even
    the ordinary risks involved in the work and assure that the
    precautions necessary to manage those risks are taken.
    
    Id. at 698.
    This law is of long standing in Iowa. For example, in Robinson v.
    Poured Walls of Iowa, Inc., 
    553 N.W.2d 873
    , 874 (1996), a worker was
    injured while excavating a clogged sewer pipe that had been installed by
    the defendant.   The defendant had hired the plaintiff’s firm to do the
    repair work when the sewer line malfunctioned.       
    Id. We affirmed
    the
    grant of the defendant’s motion for summary judgment based on absence
    of duty, reasoning that the plaintiff’s employer, not the defendant
    contractor, had control over the work. 
    Id. at 875–76;
    see also Hoffnagle
    8
    v. McDonald’s Corp., 
    522 N.W.2d 808
    , 813 (1994) (holding that “[w]hether
    a franchisor owes a duty of care to its franchisee’s employee . . . turns on
    the extent of the franchisor’s retained control over the property and the
    daily operation of the restaurant”); Downs v. A & H Constr., Ltd., 
    481 N.W.2d 520
    , 523–25 (Iowa 1992) (finding that a contractor owed no duty
    to the employee of a subcontractor who was injured by allegedly unsafe
    scaffolding because although the employer provided some of the
    materials for the scaffolding, the subcontractor controlled how the
    scaffolding was erected).
    In Van Essen v. McCormick Enterprises Co., we held a landlord that
    had installed a grain bin, but no longer controlled it, owed no duty to an
    employee of the lessee who was subsequently injured due to the allegedly
    hazardous condition of the bin.      
    599 N.W.2d 716
    , 720 (Iowa 1999).
    Although that case specifically involved the duties of an owner/lessor, we
    emphasized using italics, “ ‘The general rule and exceptions . . . reveal a
    common principle: liability is premised upon control.’ ”     
    Id. at 720
    n.3
    (quoting Allison by Fox v. Page, 
    545 N.W.2d 281
    , 283 (Iowa 1996)
    (emphasis added)).    We noted “ ‘the general rule that one who has
    transferred ownership and control is no longer held liable.’ ” 
    Id. at 721
    (quoting Stalter by Stalter v. Iowa Res., Inc., 
    468 N.W.2d 796
    , 798 (Iowa
    1991)).
    This case is essentially the flip side of the control principle we have
    recognized in the foregoing cases.       When Nikkel left the work site
    approximately a week before the accident, the switchgear was locked up
    and in a safe condition. Little Sioux, not Nikkel, had exclusive access to
    and control over this equipment. Just as the contractor is typically in a
    better position to manage risks when it is in control, the employer is
    typically in a better position to manage risks when the contractor left the
    9
    site a week ago and the employer is now in control.                We believe the
    reasoning in Van Fossen leads inexorably to the district court’s finding of
    no duty in this case.2 If one who has transferred ownership and control
    is no longer held liable, as in Van Essen, it follows logically that one who
    transferred control and never had ownership also should not be liable.
    Application of the control principle makes sense here from a public
    policy perspective. Consider the implications of a contrary rule that a
    party has created a nondelegable risk of harm if the electricity is on when
    it leaves the premises.      No matter that the accident occurred a week
    later, or that the facility could not operate without electricity, or that the
    owner was fully aware of the relevant risks, or that the equipment had
    been locked up.       To avoid potential liability, various parties (owners,
    landlords, repairpersons, etc.) would need to turn off utilities that involve
    any risk of hazard (e.g., gas, electricity) whenever they leave a property.
    These unnecessary shutoffs would result in burdens and inconveniences
    to businesses and the general public.
    Courts in other states have repeatedly found that in the absence of
    actual control, a property owner owes no duty to a contractor or a
    contractor’s employee who suffers injury from being electrocuted on the
    property owner’s premises.        Merritt v. Bethlehem Steel Corp., 
    875 F.2d 603
    , 605–07 (7th Cir. 1989) (rejecting the claim of a contractor’s
    employee that the premises owner had a duty to deenergize the lines
    where the contractor worked); Wells v. Gen. Elec. Co., 
    807 F. Supp. 1202
    ,
    1211 (D. Md. 1992) (finding an employer owed no duty to a contractor’s
    2The  fact that a nonemployee spouse was the plaintiff in Van Fossen added
    another degree of remoteness to the 
    claim. 777 N.W.2d at 692
    . But as the above
    quotations demonstrate, our reaffirmation of the “retained control standard” and our
    discussion of the duties of employers of independent contractors were stated in broad
    terms. The reasoning in Van Fossen applies here.
    10
    employee in the absence of “latent or concealed dangers” or “actual
    physical control over the work area”); Jackson v. Petit Jean Elec. Co-op.,
    
    606 S.W.2d 66
    , 68 (Ark. 1980) (finding a utility had no duty to deenergize
    its lines or warn an electrical contractor of “obvious hazards which are
    an integral part of the work the contractor was hired to perform”); Durbin
    v. Culberson Cnty., 
    132 S.W.3d 650
    , 660–61 (Tex. Ct. App. 2004) (finding
    that the defendant owed no duty to a contractor who was electrocuted
    while changing out light bulbs on an energized pole, despite the
    contractor’s argument that the defendant should have provided locked
    down switches); cf. Groover v. Camp Dresser & McKee Inc., 420 F. App’x
    358, 362 (5th Cir. 2011) (holding that a general contractor owed no duty
    to an employee of a subcontractor to warn of dangers of electrocution);
    Edick v. Paul de Lima Co., Inc., 
    775 N.Y.S.2d 385
    , 386 (App. Div. 2004)
    (holding a company that serviced a coffee maker owed no duty to an
    employee who received an electric shock while attempting to clean the
    coffee maker).
    As we noted above, this case is basically the other side of the same
    coin. The undisputed facts are that Nikkel was hired as a subcontractor
    to do some work on the switchgears. When the project got to a certain
    point, Little Sioux decided it would perform the next phase of the work
    itself instead of paying Nikkel to do it. So, Nikkel closed and secured the
    cabinets with penta-head bolts that could only be opened by a penta-
    head wrench in the possession of Little Sioux.       In functional terms,
    Nikkel contracted the job back to Little Sioux, left the premises, and
    transferred control to Little Sioux. Like the district court, we do not see
    a material difference between “the employee of an independent contractor
    suing the owner, rather than an employee of the owner suing the
    independent contractor as in this case.”     The duty principles are the
    11
    same whether the employer turns the job over to the contractor who has
    actual control or the contractor turns the job back over to the employer
    who has actual control. 3
    The control rule persists under the Restatement (Third) of Torts, as
    we recognized in Van Fossen. Section 7(a) states, “An actor ordinarily
    has a duty to exercise reasonable care when the actor’s conduct creates a
    risk of physical harm.” Restatement (Third) of Torts § 7(a), at 77 (2010).
    But this is also subject to “an articulated countervailing principle or
    policy,” such as the control rule. 
    Id. § 7(b);
    see also 
    id. § 7
    cmt. a, at 78
    (stating that “[t]he principle or policy that is the basis for modifying or
    eliminating the ordinary duty of care contained in § 7(a) may be reflected
    in longstanding precedent”). 4 The reason is simple: The party in control
    of the work site is best positioned to take precautions to identify risks
    and take measures to improve safety.
    This is entirely consistent with Iowa’s common law. Simply put,
    the cases involving parties that turn over control of premises to another
    party are “a category of cases” where “an articulated countervailing
    principle or policy” applies. See 
    Thompson, 774 N.W.2d at 835
    . 5
    3Again, why should it make a difference whether the landowner turns over an
    energized line to a contractor or a contractor turns over an energized line to a
    landowner? See 
    Merritt, 875 F.2d at 605
    –07; 
    Wells, 807 F. Supp. at 1211
    ; 
    Jackson, 606 S.W.2d at 68
    ; 
    Durbin, 132 S.W.3d at 660
    –61. The control principle is the same.
    4To put it another way, Nikkel did not create a “risk of physical harm” giving rise
    to a general duty under section 7(a) simply by energizing the line that it left locked
    securely to prevent unauthorized access. The risk arose only when Little Sioux used
    the penta-head wrench to gain access to the switchgear and allowed an untrained
    worker (McCormick) to work on it without first turning the power off.
    5Of course, review of specific facts may be necessary to determine that there has
    been a complete transfer of control and that the claim does not involve defective work
    performed by the contractor. Nonetheless, we are still dealing with a “category of
    cases.” 
    Thompson, 774 N.W.2d at 835
    .
    12
    The court of appeals relied on Thompson v. Burke Engineering
    Sales Co., 
    252 Iowa 146
    , 
    106 N.W.2d 351
    (1960), in finding that Nikkel
    owed a duty in this case. However, in Burke Engineering, the defendant
    installed a defective metal ceiling that later 
    collapsed. 252 Iowa at 148
    ,
    106 N.W.2d at 352–53.       The problem there was a defective product
    supplied by the defendant, where the defect was latent.              
    Id. If McCormick
    had been injured because Nikkel performed defective work
    inside the switchgear cabinets, that might be a Burke Engineering-type
    case. But the problem here was not defective work, it was an inherent
    hazard associated with an instrumentality no longer under the
    defendant’s control.
    The same observation applies to Kragel v. Wal-Mart Stores, Inc.,
    
    537 N.W.2d 699
    (Iowa 1995). This too was a “bad work” case. A snow
    removal contractor did a poor job of removing wet snow from a parking
    lot, leaving a layer of packed snow and ice behind. 
    Kragel, 537 N.W.2d at 701
    –02.    The plaintiff fell and sustained a fractured hip and a
    fractured elbow. 
    Id. at 701.
    We held “[a] failed attempt to remove snow
    and ice can create an artificial condition subjecting the one who created
    the condition to liability.” 
    Id. at 707.
    We emphasized “the evidence was
    that [the contractor] affirmatively altered the slushy snow.” 
    Id. In any
    event, Kragel did not involve a transfer of control. See generally 
    id. A key
    distinction between Burke Engineering and Kragel, on the
    one hand, and this case, on the other, is that there was nothing wrong
    with the contractor’s (Nikkel’s) work. The only duty allegedly breached
    by Nikkel was a duty to warn. The duty to warn is especially susceptible
    to the control principle.   When a party performs defective work, the
    negligence occurs at the time of performance, and the party that
    performed the work normally is in the best position to have prevented the
    13
    accident; when the allegation is a failure to warn, though, that failure
    (like any “failure”) occurs over a period of time, and other parties may be
    in a better position to warn for multiple reasons. Therefore, we recognize
    various “no duty” rules in the warning area based on principles
    analogous to the lack of control. See, e.g., Restatement (Third) of Torts:
    Prods. Liab. § 5, at 130 (1998) (limiting the liability of raw material or
    component suppliers and requiring proof that the raw material or
    component was defective in itself); 
    id. § 6(d)
    & cmt. e, at 145, 148 (1998)
    (learned intermediary rule). For the foregoing reasons, we conclude that
    the control principle means Nikkel, the subcontractor, owed no general
    duty to McCormick, the employee of the property owner that had
    reassumed control of the equipment and the site.
    Another way of looking at this case is to say that Nikkel did not
    create a “risk of physical harm” giving rise to a general duty under
    section 7(a) of the Third Restatement. See Porter v. Iowa Power & Light
    Co., 
    217 N.W.2d 221
    , 232 (Iowa 1974). There was nothing wrong with
    Nikkel’s work; any danger was the result of the inherent risks of active
    power lines.   See 
    id. at 233
    (“We believe the presence near streets of
    electric transmission and distribution lines is a matter of common
    knowledge and a paving contractor can reasonably be expected to take
    precautions against contacting them.”).     When Nikkel reenergized the
    line, it also locked up the switchgear. The danger arose only when Little
    Sioux used the penta-head wrench to gain access to the switchgear and
    allowed an untrained worker (McCormick) to work on it without first
    turning the power off.
    B. “Assumed Duty.”       Next, we turn to the question whether
    Konwinski’s affidavit changes the case. We believe it does not. Iowa and
    other jurisdictions recognize the concept of an “assumed duty.”        See
    14
    Wright v. Brooke Grp. Ltd., 
    652 N.W.2d 159
    , 177–78 (Iowa 2002); see also
    Restatement (Second) of Torts § 323, at 135 (1965). That is, a duty can
    be imposed on a defendant who “undertakes” to render a service to
    another.   See 
    Wright, 652 N.W.2d at 177
    –78 (holding that tobacco
    companies’ statements that they would report on the results of their
    research into the health effects of cigarettes were not an undertaking to
    warn customers of those effects).    But Nikkel did not undertake to do
    anything here. At most, according to Konwinski’s affidavit, it failed to do
    what someone else asked it to do.        See 
    Wells, 807 F. Supp. at 1209
    (finding that General Electric had assumed no duty to disconnect the
    electricity to panel boxes given the lack of competent evidence that a GE
    employee had made affirmative comments that the boxes were dead).
    C. Duty Under Restatement (Second) of Torts Section 384.
    Alternatively, McCormick relies in part on section 384 of the Restatement
    (Second) of Torts.
    One who on behalf of the possessor of land erects a
    structure or creates any other condition on the land is
    subject to the same liability, and enjoys the same freedom
    from liability, as though he were the possessor of the land,
    for physical harm caused to others upon and outside of the
    land by the dangerous character of the structure or other
    condition while the work is in his charge.
    Restatement (Second) of Torts § 384, at 289.
    Nikkel contends it bears no liability under section 384 because
    section 384 only imposes liability on the subcontractor for dangerous
    conditions “while the work is in his charge.” We agree. Section 384 is
    not an exception to the control principle; it is an application of it. That
    section only extends the special duty of the contractor “while the work is
    in his charge.” 
    Id. Two of
    the comments are particularly apt here:
    [T]he work entrusted to the servant or contractor may be
    such that it necessarily creates a condition which is
    15
    dangerous unless further steps are taken. In such a case
    the servant or contractor may be liable if he leaves the job in
    this dangerous condition, unless he has reason to expect
    that the necessary steps will be taken. The fact that his
    employer has retained charge of taking such steps or has
    entrusted them to another contractor is usually sufficient to
    warrant the servant or another contractor in assuming that
    they will be taken.
    
    Id. § 384
    cmt. e, at 290.
    The rule stated in this Section applies to determine the
    liability of one who is entrusted by the possessor of land with
    the erection of a structure or the creation of any other
    physical condition on the land, for only such bodily harm as
    is caused while he remains in charge and control of the
    erection or creation of the structure or condition. It does not
    apply to determine his liability for harm caused after his
    charge and control of the work and his privilege to be upon
    the land for the purpose of accomplishing it is terminated in
    any manner. His charge and control is usually terminated
    by the possessor’s acceptance of the completed work, but it
    may be terminated in a variety of other ways. For example,
    the possessor may, in pursuance or in violation of his
    contract, take the work out of the hands of the independent
    contractor before it is completed or may order a servant to
    stop the work entrusted to him. Again, the possessor
    himself may be ejected from the land by one who has a
    paramount title thereto, or an injunction may prevent the
    continuance of the work.
    
    Id. § 384
    cmt. g, at 291–92.
    Little Sioux had retained for itself the work required to prepare the
    brackets to receive the fault indicators, thus eliminating any special duty
    that might have been owed by Nikkel when it exercised control of the
    switchgears. 
    Id. § 384
    cmt. e, at 290. Even if the energized switchgears
    were deemed a dangerous condition, Nikkel owed no special duty under
    section 384 because it had “reason to expect” Little Sioux employees
    would follow mandatory company and OSHA regulations before accessing
    the locked cabinet.   
    Id. And under
    comment g, Nikkel would owe no
    special duty to protect against harm caused after its “charge and control
    of the work and [its] privilege to be upon the land . . . is terminated in
    16
    any manner.” 
    Id. § 384
    cmt. g, at 291. Little Sioux instructed Nikkel not
    to perform the work on the brackets, and Nikkel was unable to complete
    its work until the brackets were revised by Little Sioux.     Accordingly,
    Nikkel’s control of the switchgears terminated until Little Sioux
    completed its work on the brackets. On this record, we conclude as a
    matter of law the work of repositioning the brackets was not in Nikkel’s
    charge, and Nikkel therefore owed no special legal duty to McCormick
    under section 384 at the time of his injury.
    IV. Conclusion.
    For the reasons stated, we affirm the judgment of the district court
    holding that Nikkel owed no duty to McCormick in this case.
    COURT OF APPEALS DECISION VACATED; DISTRICT COURT
    JUDGMENT AFFIRMED.
    Cady, C.J., and Waterman and Zager, JJ., join this opinion.
    Hecht, J., files an opinion concurring in part and dissenting in part in
    which Wiggins and Appel, JJ., join.
    17
    #10–1889, McCormick v. Nikkel & Assocs., Inc.
    HECHT, Justice (concurring in part and dissenting in part).
    While I agree with the majority’s conclusion that Nikkel does not
    owe a special duty under the Restatement (Second) of Torts section 384,
    the majority’s analysis of the general duty question demonstrates a
    fundamental misunderstanding of the distinction between duty and
    scope of liability and results in a conflation of the two issues.
    The confusion is highlighted in the opening paragraph when the
    majority couches the issue as “whether a subcontractor that properly
    performs electrical work on a jobsite, then locks up the work and
    transfers control to the property owner, owes a duty of care to an
    employee of the owner electrocuted six days later when the owner fails to
    deenergize the work site in contravention of various warnings and
    regulations.” “When liability depends on factors specific to an individual
    case, the appropriate analytical rubric is scope of liability.” Restatement
    (Third) of Torts: Liab. for Physical and Emotional Harm § 7 cmt. a, at 78
    (2010) [hereinafter Restatement (Third)].      In this case, the majority’s
    rationale is substantially based on specific facts: that Nikkel had been
    absent from the work site for approximately a week before McCormick’s
    injury; that Nikkel had locked the switchgear cabinet before leaving; that
    a hazard decal was visible on the switchgear cabinet; that Little Sioux
    was in control of the property at the time of the injury; and that
    McCormick failed to follow safety procedures confirming that the
    switchgear was not energized before attempting to work on it.           While
    these factual considerations are, of course, relevant to the scope of
    liability issue, that issue was not raised in the district court or on appeal,
    and the majority does not purport to engage in an analysis of the scope
    18
    of Nikkel’s liability. Rather, the majority relies on these factual, case-
    specific details in its duty analysis.
    On the other hand, an appropriate duty analysis “depends on
    factors applicable to categories of actors or patterns of conduct.” 
    Id. “As a
    general rule, our law recognizes that every person owes a duty to
    exercise reasonable care to avoid causing injuries to others.”                    Feld v.
    Borkowski, 
    790 N.W.2d 72
    , 75 (Iowa 2010).                     “Thus, in most cases
    involving physical harm, courts ‘need not concern themselves with the
    existence or content of this ordinary duty,’ but instead may proceed
    directly to the elements of liability.” Thompson v. Kaczinski, 
    774 N.W.2d 829
    , 834 (Iowa 2009) (quoting Restatement (Third) of Torts: Liab. for
    Physical Harm § 7(a), at 90 (Proposed Final Draft No. 1, 2005)). Only in
    “exceptional” cases, when the court can promulgate relatively clear,
    categorical, bright-line rules of law applicable to a particular class of
    cases should the court modify or displace an actor’s general duty of
    reasonable care.         
    Id. at 835.
            The majority’s conclusion that “a
    subcontractor that properly performs electrical work on a jobsite, then
    locks up the work and transfers control to the property owner [does not
    owe] a duty to an employee of the owner electrocuted six days later when
    the owner fails to deenergize the work site in contravention of various
    warnings and regulations” is not a clear, bright-line rule of law applicable
    to a particular class of cases. 6
    6The majority’s opinion reasons in part that it would be inefficient or impractical
    to impose liability on an electrical contractor who has energized a switchgear cabinet
    and locked it before leaving the work site. Fearing “burdens and inconveniences to
    businesses and the general public” if contractors are required to turn off utilities posing
    a risk of injury before leaving a work site, the majority would excuse contractors from
    the general duty of reasonable care under section 7. I am not convinced. Why should
    we conclude it would have been burdensome for Nikkel to deenergize the switchgear box
    before leaving the work site? Such a course of action would have assured Nikkel that it
    created no risk of harm to persons it expected to work on the fault indicator brackets in
    the near future. If Little Sioux wished to energize the loop before Nikkel returned to
    19
    Long before this court adopted the Restatement (Third) formulation
    of duty in Thompson v. Kaczinski, it was well established in this
    jurisdiction that the duty of contractors to exercise reasonable care does
    not evaporate with the completion of the contractor’s work. See Kragel v.
    Wal-Mart Stores, Inc., 
    537 N.W.2d 699
    , 707 (Iowa 1995) (“Our case law
    holds that the independent contractor remains liable even after the
    contractor’s employer accepts the work.”) (citing Restatement (Second) of
    Torts, § 385 (1965)); Thompson v. Burke Eng’g Sales Co., 
    252 Iowa 146
    ,
    154–55, 
    106 N.W.2d 351
    , 356–57 (1960).                        Despite the majority’s
    characterization of the reasoning in Burke Engineering, we made quite
    clear the contractor’s duty of care does not derive from possession or
    control of land. It is instead a discrete duty arising from the creation of a
    risk of injury and extends temporally beyond the completion of the
    contractor’s work and the owner’s acceptance of it.                  Burke Eng’g, 
    252 Iowa 154
    –55, 106 N.W.2d at 356–57. 7
    This duty of a contractor to exercise reasonable care is not, as the
    majority opinion suggests, one that arises only when the contractor does
    bad or defective work. The duty arises instead whenever a risk of injury
    to others arises from the contractor’s work without regard to whether the
    work is performed badly. This principle explains why a motorist owes a
    duty of care to others while driving (not just when driving badly), and it
    explains why a surgeon owes a duty of care while performing surgery (not
    _____________________________
    finish its work, it could do so and take responsibility for any resulting risk. Of course, a
    fact finder could determine Nikkel had options other than deenergizing the switchgears
    in fulfilling its general duty of reasonable care, such as honoring Konwinski’s request
    that he be notified when the switchgears were energized.
    7It is apparent that the range of conduct engendering the general duty of care
    owed by a contractor is not limited to supplying inherently defective products posing
    latent hazards. Kragel, for example, makes clear that the duty is owed by a contractor
    who creates a risk of injury to pedestrians when clearing snow and ice from a shopping
    center’s parking lot. 
    Kragel, 537 N.W.2d at 707
    .
    20
    just when operating badly). The question of whether the driver or the
    surgeon has failed to use reasonable care under the circumstances
    addresses not whether a duty was owed in the first place, but whether
    that duty was breached.             The majority’s construct—concluding a
    contractor owes a duty of reasonable care only if he performs “defective
    work”—seems to make the existence of a duty turn on whether the
    contractor failed to exercise reasonable care. This is a novel approach to
    tort law. The majority’s finding that Nikkel’s acts or omissions did not
    constitute “defective work” is tantamount to a determination that Nikkel
    exercised reasonable care, yet it serves as the foundation for the
    majority’s conclusion that Nikkel owed McCormick no duty.                     This is
    simply wrong. The existence of Nikkel’s duty turns on whether it created
    a risk of injury when it energized the switchgear boxes before leaving the
    work site without notifying Konwinski—not on whether it connected the
    wires to the switchgears badly.
    The well-established duty of care owed by contractors noted in our
    decisions in Burke Engineering and Kragel and expressed in Restatement
    (Second) of Torts section 385 was carried forward into the Restatement
    (Third). The contractor’s general duty of care does not arise as a function
    of continuing possession and control of land, for the contractor’s
    possession and control generally cease upon completion of the work.
    Having relinquished possession and control of the land, the contractor
    nonetheless owes the ordinary duty of reasonable care for risks created
    by the contractor’s work. 8 A contractor who has completed work and is
    8This distinction is crucial to the extent it explains why cases asserting
    negligence claims against land owners, Merritt v. Bethlehem Steel Corp., 
    875 F.2d 603
    (7th Cir. 1989), and Wells v. Gen. Elec. Co., 
    807 F. Supp. 1202
    (D. Md. 1992); electric
    utilities, Jackson v. Petit Jean Elec. Co-op., 
    606 S.W.2d 66
    (Ark. 1980), and Durbin v.
    Culberson Cnty., 
    132 S.W.3d 650
    (Tex. Ct. App. 2004); contractors, Groover v. Camp
    Dresser & McKee, Inc., 420 F. App’x 358 (5th Cir. 2011), Robinson v. Poured Walls of
    21
    no longer in possession of the land is “subject to the ordinary duty for
    risks created by their work under § 7.” Restatement (Third) § 49 cmt. g,
    at 10 (Tentative Draft No. 6, 2009).
    Section 385 of the first two Restatements of Torts provide
    that an agent who has completed work that is accepted by
    the principal is subject to the same liability as a
    manufacturer of a chattel who has given up possession of
    the chattel.   This oblique way of imposing a duty of
    reasonable care on contractors whose work was completed
    reflects the waning influence of the privity doctrine, which
    limited a contractor’s liability to those with whom the
    contractor was in privity of contract. After the privity rule
    was left behind beginning with MacPherson v. Buick Motor
    Co., 
    111 N.E. 1050
    , 1053 (N.Y. 1916), the liability of a
    chattel manufacturer extended to others beyond the person
    who purchased the chattel. Similar to the privity doctrine,
    the “completion and acceptance” doctrine insulated a
    contractor who completed construction on real property and
    turned the completed work over to the owner. With the
    abrogation of privity, that rule was also replaced. . . .
    Numerous modern cases accept the rule of § 385.
    Restatement (Third) § 49 rep. note to cmt. g, at 17 (Tentative Draft No. 6,
    2009).
    Thus, this general duty of care extending beyond the completion of
    a contractor’s work is clearly not a novel or revolutionary concept of law
    in this jurisdiction. It is a rule of law recognized in prior decisions of this
    court for more than fifty years, expressed by the Restatement (Second) of
    Torts as a principle of established law, and more recently restated in the
    Restatement (Third) of Torts.
    _____________________________
    Iowa, Inc., 
    553 N.W.2d 873
    (Iowa 1996), and Downs v. A & H Constr., Ltd., 
    481 N.W.2d 520
    (Iowa 1992); a landlord, Van Essen v. McCormick Enters. Co., 
    599 N.W.2d 716
    (Iowa
    1999); and a vendor of coffee makers and coffee, Edick v. Paul de Lima Co., Inc., 
    775 N.Y.S.2d 385
    (App. Div. 2004), cited by the majority are neither dispositive of the
    general duty issue nor persuasive in this case. None of these cases asserted, as the
    McCormicks do in this case, that a subcontractor owed a general duty of care under
    section 7 as a consequence of the subcontractor’s own creation of a risk of serious
    injury or death at a construction site.
    22
    Accordingly, even if Nikkel did not owe to McCormick any special
    duties as a possessor of land, or as a contractor temporarily in control of
    the construction site, it still owed a general duty of reasonable care
    under section 7 of the Restatement (Third) because it created a risk of
    severe injury or death by energizing the switchgears and failing to notify
    Konwinski as requested. The determination of whether this duty of care
    was breached by Nikkel and whether McCormick’s injuries were within
    the applicable scope of liability are matters of foreseeability to be
    determined not by the court on summary judgment, but by a jury. 9 The
    majority opinion, emphasizing that the switchgear cabinet was adorned
    with a decal warning of the electrical hazard and locked by Peterson
    before he left the work site, and that Little Sioux’s employees failed to
    follow lock-out/tag procedures on the day of McCormick’s injury,
    confounds the duty analysis under section 7 of the Restatement (Third)
    with forseeability considerations relevant to the issues of breach of the
    general duty and scope of liability.          As I have already noted, Nikkel’s
    motion    for   summary      judgment      claimed    entitlement     to   summary
    judgment solely on the duty issue—not on the issues of breach of duty or
    scope of liability.
    The majority cites this court’s decision in Van Fossen v.
    MidAmerican Energy Co., 
    777 N.W.2d 689
    (Iowa 2009), in support of its
    position that Nikkel owed no general duty of care to McCormick under
    the facts presented in the summary judgment record. In Van Fossen, we
    decided the owner of a power plant who was not in possession of a
    construction site owed no general duty of care to the wife of an
    9Foreseeability   of the risk is no longer a part of the duty analysis and is
    allocated to the fact finder, “to be considered when the jury decides if the defendant
    failed to exercise reasonable care.” 
    Thompson, 774 N.W.2d at 835
    .
    23
    independent construction contractor’s employee who was exposed to
    asbestos and carried it home on his clothing. Van 
    Fossen, 777 N.W.2d at 696
    –97.   Nikkel argues, and the majority concludes, that the no-duty
    rule adopted in Van Fossen was based on the notion that the power plant
    owner did not retain control of the construction site and the associated
    asbestos exposure risk while the contractor performed its work.
    I believe Van Fossen is distinguishable both in terms of the facts
    presented and the legal issues decided, and it is neither controlling nor
    instructive in the resolution of the duty issue in this case. In Van Fossen
    we were asked to decide whether the owner of a power plant owed a duty
    of care to the spouse of an employee of a construction subcontractor who
    was allegedly exposed to asbestos while laundering her husband’s
    clothes at home. 
    Id. at 691.
    In sharp contrast, the parties in the case
    now before the court ask us to decide whether a construction
    subcontractor owed a duty of care to an employee of the owner as a
    consequence of a risk of severe injury or death created at the construction
    site by the subcontractor’s own work.        In short, the stark factual
    differences in the facts presented in the two cases, the asymmetry of the
    roles played by the defendant actors in the construction projects in the
    two cases, and the obvious dissimilarities in the respective defendants’
    involvement in the creation of the alleged risks of injury in the two cases
    lead us to conclude the no-duty rule enunciated in Van Fossen should
    have no application in this case.
    Beyond the fact that Van Fossen is clearly distinguishable and not
    instructive in our resolution of the general duty issue in this case, the
    majority misapprehends the reasoning in Van Fossen.          Although we
    noted that the record in that case was “devoid of evidence tending to
    prove [the plant owners] exercised control over [the work of their
    24
    contractors],” the decision to recognize a no-duty rule was based on “ ‘an
    articulated countervailing principle or policy warrant[ing] den[ial of] . . .
    liability in a particular class of cases.’ ” 
    Id. at 696
    (quoting Restatement
    (Third) § 7(b), at 90 (Proposed Final Draft No. 1, 2005)) (emphasis
    added). 10     We recognized that our determination of a no-duty rule
    reflected the “realities of the relationship between employers and their
    contractors [including the reality] that employers often have limited, if
    any, control over the work performed by their contractors.” 
    Id. at 698.
    However, our decision was also based on the remoteness of the plant
    owners from the spouse of an employee of an independent contractor.
    
    Id. at 699.
         We expressed concern that imposing a general duty of
    reasonable care on the employer of a contractor extending to the spouse
    of the contractor’s employee under the circumstances presented in Van
    Fossen “would arguably also justify a rule extending the duty to a large
    universe of other potential plaintiffs who never visited the employers’
    premises but came into contact with a contractor’s employee’s asbestos-
    tainted clothing [in various other remote settings].”                
    Id. This large
    universe of other potential plaintiffs could have included taxi drivers,
    employees of dry-cleaning establishments, and others having no
    connection whatsoever to the plant-owner’s premises.                   We concluded
    “such a dramatic expansion of liability would be incompatible with public
    10Our    holding was not merely that MidAmerican owed no duty to Mrs.
    Van Fossen, but that “[o]ne who employs an independent contractor owes no general
    duty of reasonable care to a member of the household of an employee of the
    independent contractor.” Van 
    Fossen, 777 N.W.2d at 696
    . Mrs. Van Fossen had never
    visited the defendant’s construction site. 
    Id. at 699.
    Our decision in Van Fossen was “a
    determination, a purely legal question, that no liability should be imposed on actors in
    a category of cases.” Restatement (Third), § 7 cmt. j, at 82 (emphasis added). It was not
    an individualized forseeabililty-based determination that no general duty of care was
    owed to Mrs. Van Fossen because MidAmerican lacked possession or control of the
    construction site.
    25
    policy.”   
    Id. However, I
    believe our policy concerns in Van Fossen
    militating against the imposition of a duty upon the landowner are not
    present in this case. McCormick’s claim for damages is asserted against
    a construction subcontractor whose own acts or omissions are alleged to
    have created a risk of injury to its employer’s employee at the
    construction site. As I have already noted, the existence of the duty of
    care owed by subcontractors as a consequence of risks of injury they
    create at construction sites is already well established in Iowa law.
    Accordingly, I believe this case does not present, as Van Fossen did, an
    exceptional situation in which a no-duty rule would be appropriate.
    The majority also relies on our decision in Robinson v. Poured
    Walls of Iowa, Inc., 
    553 N.W.2d 873
    (Iowa 1996), as authority for its
    conclusion that Nikkel owed no general duty to exercise reasonable care
    under the circumstances of this case. In that case, Poured Walls of Iowa
    hired an independent contractor, Jack Spaw, to excavate a sewer line.
    
    Robinson, 553 N.W.2d at 874
    .       Spaw employed Robinson who was
    injured while doing the work.    
    Id. at 874–75.
      Robinson sued Poured
    Walls of Iowa claiming the contractor violated special duties under
    Restatement (Second) of Torts sections 343 (duty owed by possessors of
    land for injuries sustained by invitees), 413 (duty owed by employer of
    independent contractor hired to perform work creating a “peculiar
    unreasonable risk of physical harm”), and 427 (duty of employer of
    independent contractor hired to perform work “involving a special danger
    to others which the employer knows or has reason to know to be
    inherent in or normal to the work”).      
    Id. at 875.
      The plaintiffs in
    Robinson did not claim that the contractor, Poured Walls of Iowa, owed a
    general duty to exercise reasonable care because it created a risk of
    injury to others through its own acts or omissions at the work site. They
    26
    instead alleged the contractor violated only special duties which were
    allocated based on possession and control under the Restatement
    (Second) of Torts.   
    Id. Simply put,
    our decision in Robinson did not
    address the general duty of care alleged by the McCormicks and is
    therefore not on point. This is also true of the other decisions of this
    court cited today by the majority opinion. See Hoffnagle v. McDonald’s
    Corp., 
    522 N.W.2d 808
    , 815 (Iowa 1994) (franchisor owed no special duty
    to provide security against assaults by third parties on franchisee’s
    property under Restatement (Second) of Torts sections 344 and 414
    because franchisor lacked control); Downs v. A & H Constr., Ltd., 
    481 N.W.2d 520
    , 524–27 (Iowa 1992) (contractor owed no special duty to an
    employee of a roofing subcontractor under Restatement (Second) sections
    328E, 343 and 414 because the contractor did not retain sufficient
    control of the subcontractor’s work).    Although these precedents are
    authority for the proposition that Nikkel owed no special duty to
    McCormick under the circumstances presented in this case, they are not
    dispositive of the general duty issue under section 7 of the Restatement
    (Third) adopted by this court in Thompson.
    We should not fear the salutary effect of the general duty of
    reasonable care adopted by this court in Thompson. It is a positive force.
    I find no articulated countervailing principle or policy that warrants
    denying or limiting the liability of electrical contractors as a class of
    actors for risks of injury created by their own acts or omissions at a
    construction site. Although Nikkel did not control the construction site
    or the particular task performed by McCormick at the time of his injury,
    the McCormicks contend Nikkel owed a general duty to exercise
    27
    reasonable care when it energized the switchgears and failed to inform
    Konwinski despite having been asked to do so. 11
    The majority’s decision today recognizes a no-duty rule for what it
    characterizes as “a class of cases” in which a contractor has effected a
    complete transfer of control of the premises to another. Acknowledging
    that there may be fact questions in certain cases about the extent of the
    transfer of control and whether the contractor has performed defective
    work, the majority effectively concedes that the existence of a duty will
    turn on fact questions in particular cases. On this point, the majority
    confuses its duty analysis with the analysis of scope of liability. “When
    liability depends on factors specific to an individual case, the appropriate
    rubric is scope of liability.” Restatement (Third) § 7 cmt. a, at 78.
    Whether Nikkel exercised reasonable care under the circumstances
    by locking the cabinet, relying on warnings posted on the cabinet, and
    expecting Little Sioux employees to follow mandatory OSHA and
    company safety policies, are matters related to foreseeability, breach of
    duty, and scope of liability—all issues properly reserved for a jury’s
    assessment. Accordingly, I would reverse and remand for trial.
    Wiggins and Appel, JJ., join this concurrence in part and dissent
    in part.
    11As  I have already noted, the question of whether the McCormicks engendered a
    fact question as to whether Nikkel breached the duty of reasonable care by failing to
    give notice to Little Sioux that the switchgears were energized or by failing to take other
    action to eliminate the risk of injury was not decided by the district court and is
    therefore not a matter before this court on appeal. Similarly, Nikkel’s motion for
    summary judgment did not raise the question whether a fact issue is engendered in the
    summary judgment record as to whether any injuries sustained by the McCormicks
    were within the scope of Nikkel’s liability.