Al Urbain Construction Management Company, Inc. v. CW Wolfe LLC ( 2022 )


Menu:
  •                    IN THE COURT OF APPEALS OF IOWA
    No. 20-1627
    Filed January 12, 2022
    AL URBAIN CONSTRUCTION MANAGEMENT COMPANY, INC.,
    Plaintiff-Appellant/Cross-Appellee,
    vs.
    CW WOLFF, LLC,
    Defendant-Appellee/Cross-Appellant.
    ________________________________________________________________
    Appeal from the Iowa District Court for Dubuque County, Alan Heavens,
    Judge.
    Plaintiff appeals and defendant cross-appeals the district court’s decision
    on their breach-of-contract claims. AFFIRMED ON BOTH APPEALS.
    Robert E. Sabers, Dubuque, for appellant.
    Darin S. Harmon and Jeremy N. Gallagher of Kintzinger, Harmon, Konrardy,
    P.L.C., Dubuque, for appellee.
    Considered by Bower, C.J. and Vaitheswaran and Schumacher, JJ.
    2
    SCHUMACHER, Judge.
    Al Urbain Construction Management Co. (AUCM) appeals and CW Wolff,
    LLC (CWW) cross-appeals the district court’s decision on their breach-of-contract
    claims. The district court awarded damages to AUCM on one project and CWW
    on another project, then offset these two amounts. We find the district court’s
    decision is supported by substantial evidence and affirm on the appeal and cross-
    appeal.
    I.     Background Facts & Proceedings
    Aloysius Urbain is the president and sole shareholder of AUCM, a
    construction management company.           AUCM works with commercial clients
    through a pre-construction phase, produces a project budget, arranges a
    sequence of construction, and ensures everything is done according to plan. A
    construction management company is different from a general contractor, who
    retains subcontractors for a job. Urbain testified, “The way management works is
    I find the contractors and I share the exact numbers with the client and historically
    the client pays those bills directly is way it’s supposed to work.”
    Clark Wolff is the owner of CWW, a real estate business. He is also the
    president of Selco, Inc., a contract traffic control company. Urbain and Wolff were
    acquainted socially. They entered into agreements that AUCM would work on two
    building projects for CWW—a new building for Selco (Selco project), and a
    barbeque restaurant called Devil’s Pit (Devil’s Pit project). There were no written
    contracts.
    During the construction process, CWW became increasingly concerned
    with what it viewed as AUCM’s lack of attention to the projects. Many problems
    3
    were caused by a lack of documentation concerning what services AUCM was
    hired to provide and communication difficulties. When AUCM presented bills to
    CWW for contractors and suppliers, CWW would not pay the full amount due, so
    AUCM paid the shortfall. AUCM also began sending some contractors directly to
    CWW, rather than CWW paying AUCM and then AUCM paying the contractors.
    These practices caused problems in determining the actual costs of the projects.
    Both projects were completed on time and lien waivers were obtained from all of
    the contractors.
    On November 22, 2017, AUCM sent a letter to CWW asking for a meeting
    to close out the projects. AUCM stated CWW owed $88,734.36 for the Devil’s Pit
    project. This included a payment of ten percent of the project costs for AUCM’s
    services, which it stated was $16,600.00.        AUCM also stated CWW owed
    $48,981.14 for the Selco project, which included a payment of $35,856.14,
    representing six percent of the project costs.       The total amount due was
    $137,715.50. CWW did not respond to the letter and AUCM sent a second letter
    on December 20, again requesting a meeting. No response was made to the
    second letter.
    On May 2, 2018, AUCM sent a letter to CWW stating it had revised its billing.
    The letter stated, “It was my intent not to charge you for services provided at your
    previous Selco operation located at 15 S. Main Street, Dubuque, Iowa, plus
    additional sites, including your personal residence as outlined in my new final
    billing in the amount of $177,827.41.” AUCM asked to be paid $120 per hour for
    looking at other locations for the new Selco building before the present location
    was selected. The revised billing asked for $89,494.36 for the Devil’s Pit project
    4
    and $58,319.75 for the Selco project, plus payment for work at other sites. CWW
    did not respond to this request for payment.
    On June 14, AUCM filed a petition claiming CWW breached their contract
    by not paying for services. In the alternative, AUCM sought relief on a theory of
    quantum meruit. CWW raised counterclaims against AUCM, asserting claims of
    breach of contract, unjust enrichment, and conversion.        A bench trial was
    conducted on October 29 and 30, 2020. Testimony was provided by Urbain; Wolff;
    Damien Miller, a general contractor; Dan Muntz, a supervisor for Selco; Roger
    Klosterman, a certified public accountant (CPA) and financial advisor; and Steve
    Ulstad, an architect.
    The district court found AUCM proved CWW breached the contract for
    construction management services for the Devil’s Pit project by failing to pay for
    AUCM’s services and the reimbursement of some of the contractors. The court
    awarded AUCM damages of $89,494.36 for the Devil’s Pit project. The court
    denied AUCM’s request to be paid $120 per hour for work scouting out other
    locations for the new Selco building, finding there was no agreement AUCM would
    be paid for the work. The court determined AUCM did not prove its other claims
    for damages related to the Selco project but CWW did prove its claims through the
    testimony of Klosterman. The court awarded CWW damages of $83,050.51 for
    the Selco project. The two awards were set off and the court entered judgment for
    AUCM in the amount of $6443.85. AUCM appealed and CWW cross-appealed.
    II.    Standard of Review
    We review breach-of-contract actions for the correction of errors at law.
    Iowa Mortg. Ctr., L.L.C. v. Baccam, 
    841 N.W.2d 107
    , 110 (Iowa 2013).           “If
    5
    substantial evidence in the record supports a district court’s finding of fact, we are
    bound by its finding. However, a district court’s conclusions of law or its application
    of legal principles do not bind us.” 
    Id.
     (citation omitted). “When a party challenges
    a district court’s ruling claiming substantial evidence does not support the decision,
    we must view the evidence in the light most favorable to support the judgment and
    liberally construe the court’s finding to uphold, rather than defeat, the result
    reached.” Papillon v. Jones, 
    892 N.W.2d 763
    , 770 (Iowa 2017), as amended
    (June 6, 2017) (quoting Iowa Beta Chapter of Phi Delta Theta Fraternity v. State,
    
    763 N.W.2d 250
    , 257 (Iowa 2017)).
    III.   Selco Project
    AUCM contends the district court erred by denying its claims for damages
    for the Selco project. In order to show a breach of contract, a party must show:
    (1) the existence of a contract; (2) the terms and conditions of the
    contract; (3) that it has performed all the terms and conditions
    required under the contract; (4) the defendant’s breach of the
    contract in some particular way; and (5) that plaintiff has suffered
    damages as a result of the breach.
    Iowa Mtg. Ctr., 841 N.W.2d at 111 (citation omitted).
    AUCM claims CWW breached the contract by not paying AUCM the total
    amount due for its services. It asserts there was not substantial evidence in the
    record to support the district court’s conclusion that AUCM was overpaid for the
    Selco project.   AUCM contends the financial exhibits show it was underpaid
    $29,061.19 for its work.1 AUCM also states that it was not paid the six percent
    1 AUCM states CWW paid $710,000.00 for the Selco project and AUCM paid
    vendors $739,061.19, which is a deficit of $29,061.19.
    6
    management fee, which it calculates to be $88,190.16. In total, AUCM claims
    CWW owes it $117,251.35 for the Selco project.
    The district court found AUCM did not adequately prove its damages,
    stating, “To put it mildly, AUCM’s damages request for the Selco project was a
    moving target.” AUCM’s request for damages kept changing over time. The court
    found:
    In the Petition the total request was $177,827.41. In the
    Amended Petition the total request was $317,207.58. During the trial
    the total request changed to $173,648.36 and then to $230,959.43
    before finally settling on $185,462.15. All of these changes were due
    to [Urbain’s] revisions to the charges for the Selco project.
    The court concluded AUCM’s claim for damages on the Selco project was
    not credible “in no small part due to the many different positions taken by AUCM
    before and during the trial . . . .” In a bench trial, the district court is the fact-finder
    and it assesses the credibility of the witnesses. City of Forest City v. Holland
    Contracting Corp., No. 11-0782, 
    2012 WL 170195
    , at *3 (Iowa Ct. App. Jan. 19,
    2012). “[T]he credibility of witnesses is peculiarly the responsibility of the fact
    finder to assess.” Est. of Hagedorn ex rel. Hagedorn v. Peterson, 
    690 N.W.2d 84
    ,
    88 (Iowa 2004).
    CWW’s claims concerning the Selco project were supported by the
    testimony of a CPA, Klosterman, who provided a detailed accounting to show
    AUCM was overpaid $83,050.51 on the Selco project.2 The district court relied on
    Klosterman’s testimony and exhibits to conclude CWW should be awarded
    damages of $83,050.51 for the Selco project.             While the district court found
    2Klosterman first stated the amount was $147,313.66 but stipulated the amount
    should be revised to $83,050.51.
    7
    AUCM’s claims for damages on the Selco project were not credible, the court found
    CWW’s claims for damages on this project were credible.
    AUCM challenges the credibility of Klosterman and disputes the
    calculations in his exhibits. We defer to the district court’s findings on credibility.
    See Tim O’Neill Chevrolet, Inc. v. Forristall, 
    551 N.W.2d 611
    , 614 (Iowa 1996)
    (“The district court has a better opportunity than we do to evaluate the credibility
    of witnesses. So we think factual disputes depending heavily on such credibility
    are best resolved by the district court.”). On appeal, we “determine whether
    substantial evidence supports the district court’s findings according to those
    witnesses whom the court believed.”        
    Id.
       Additionally, we consider “whether
    substantial evidence supports the finding actually made by the trial court, not
    whether substantial evidence would have supported a different finding.” Van Oort
    Constr. Co. v. Nuckoll’s Concrete Serv., Inc., 
    599 N.W.2d 684
    , 691 (Iowa 1999).
    We conclude there is substantial evidence in the record to support the
    district court’s decision finding AUCM did not prove it was entitled to damages for
    the Selco project. Also, there is substantial evidence to show CWW is entitled to
    damages of $83,050.51 for overpayments made to AUCM for this project. The
    exhibits provided by Klosterman provide substantial evidence to support the award
    and these are also supported by his testimony during the trial.
    IV.    Devil’s Pit Project
    In the cross-appeal, CWW claims the district court erred by awarding AUCM
    $89,494.36 for the Devil’s Pit project. It asserts the terms of the contract were not
    sufficiently definite for the contract to be enforceable. It also claims CWW did not
    approve AUCM’s management fee. CWW contends there was no meeting of the
    8
    minds that AUCM would be paid a ten percent management fee for the Devil’s Pit
    project. It claims the award to AUCM for the Devil’s Pit project is not supported by
    substantial evidence.
    The district court found:
    The Court finds that it is more likely than not that the 10% fee
    was disclosed by [Urbain] to [Wolff] through a statement of probable
    cost that was one of many documents shown to [Wolff]. Although
    the evidence shows that [Wolff] never signed anything, the Court
    does not believe that [Wolff] would let AUCM complete the entire
    Devil’s Pit project without ever looking into what the fee for doing so
    would be.
    The court also found the Devil’s Pit project was completed to CWW’s satisfaction
    and AUCM did not breach the contract.
    A statement of probable cost for the Devil’s Pit project dated March 15,
    2016, has a handwritten note by Urbain stating, “Original budget reviewed &
    approved by Clark 4/28/2016.”       The statement of probable cost includes the
    construction management fee of $21,600.00. The district court found Wolff’s
    testimony that he never approved the project or the construction management fee
    was not believable, as the project was completed by AUCM and CWW must have
    been aware AUCM would receive a fee for its work.
    The district court is in a better position to evaluate the credibility of
    witnesses. See Tim O’Neill Chevrolet, 
    551 N.W.2d at 614
    . Disputes of factual
    matters that depend on the credibility of witnesses “are best resolved by the district
    court.” 
    Id.
     We find there is substantial evidence in the record to support the district
    court’s findings that CWW agreed to the cost statement for the Devil’s Pit project
    and AUCM’s construction management fee.
    9
    CWW also claims the amount of damages awarded to AUCM for the Devil’s
    Pit project is not supported by substantial evidence. Klosterman testified CWW
    did not owe AUCM any money for the Devil’s Pit project, but he did not provide
    documentation to support his statement, unlike his testimony concerning the Selco
    project. AUCM presented exhibits to support its position that CWW had not paid
    it for some of the contractors for the project. We conclude there is substantial
    evidence in the record to support the district court’s award of $89,494.36 to AUCM
    for the Devil’s Pit project.
    The district court awarded AUCM $89,494.36 for the Devil’s Pit project and
    awarded CWW $83,050.51 for the Selco project. The court offset these amounts
    and entered judgment to AUCM for $6443.85.         We affirm the district court’s
    decision on the appeal and the cross-appeal.
    AFFIRMED ON BOTH APPEALS.