Pro Commercial, LLC v. K & L Custom Farms, Inc., D/B/A K & L Landscape & Construction, Inc. ( 2015 )


Menu:
  •                    IN THE COURT OF APPEALS OF IOWA
    No. 14-0633
    Filed May 20, 2015
    PRO COMMERCIAL, LLC,
    Plaintiff-Appellee,
    vs.
    K & L CUSTOM FARMS, INC., d/b/a
    K & L LANDSCAPE & CONSTRUCTION,
    INC.,
    Defendant-Appellant.
    ________________________________________________________________
    Appeal from the Iowa District Court for Story County, Dale E. Ruigh,
    Judge.
    A subcontractor appeals the district court’s ruling finding it breached the
    terms of the subcontract. REVERSED AND REMANDED.
    Todd W. Weidemann, Brian S. Koerwitz, and Monica L. Freeman of
    Woods & Aitken, L.L.P., Omaha, Nebraska, for appellant.
    Brenton D. Soderstrum of Brown, Winick, Graves, Gross, Baskerville &
    Schoenebaum, P.L.C., Des Moines, for appellee.
    Heard by Vaitheswaran, P.J., and Tabor and Mullins, JJ.
    2
    MULLINS, J.
    K & L Custom Farms d/b/a K & L Landscape and Construction, Inc.
    (K & L) appeals the district court’s decision concluding it breached the terms of a
    subcontract with Pro Commercial, LLC. K & L claims the district court incorrectly
    interpreted the terms of the subcontract and also should have awarded K & L
    damages in its counterclaim for breach of contract against Pro Commercial.
    Finally, K & L claims, in the event we affirm the district court’s decision regarding
    the breach of contract, the district court erred in not giving it credit for the work it
    performed under the contract with Pro Commercial.
    I. Background Facts and Proceedings.
    Pro Commercial decided to bid on a rest area construction project with the
    Iowa Department of Transportation (IDOT). It requested subcontractors submit
    bids for the project, and various subcontractors, including K & L, responded. The
    plans and specifications prepared by the architect and engineers employed by
    the IDOT were available to the subcontractors as they prepared and submitted
    their bids to Pro Commercial. K & L submitted an estimate for the dirt work and
    grading required for the project. On the estimate, K & L itemized descriptions of
    the work it proposed to do along with the price associated with the work. The
    estimate listed the following work descriptions:
    3
    The total of all this work was $74,267.50.
    Steve Aldred, estimator and project manager with Pro Commercial,
    contacted Bruce Hovey, estimator with K & L, to discuss the bid. Aldred testified
    he explained to Hovey, “I will want to make sure that you have everything in the
    dirt work and you’re a hundred percent covered.” Aldred stated that Hovey had
    to check with “Hector,” but Hovey eventually called back and said “Yes, we’re
    complete.” Hovey also testified regarding the conversation he had with Aldred
    but stated he told Aldred that “what [K & L was] doing was written out on the
    proposal.”      He then instructed Aldred to call the president of K & L, Kevin
    Alexander, if he had other questions.             Alexander testified he did have a
    conversation with Aldred, but that conversation dealt with Aldred’s request for
    K & L to remove the landscaping portion of the estimate.1                  Alexander stated
    Aldred never asked him about the scope of the dirt work.
    1
    K & L also bid to perform landscaping work for a cost of $46,851.00.
    4
    Pro Commercial took K & L’s estimate along with the estimates from the
    other subcontractors and compiled them in order to submit a final bid to the IDOT
    for consideration.    The IDOT awarded the construction contract to Pro
    Commercial, who in turn drafted contracts with the various subcontractors to do
    the work,2 including K & L. The subcontract sent to K & L stated, in relevant part:
    SECTION 1. The Subcontractor agrees to furnish all labor,
    material and equipment, necessary to perform and complete all the
    work for [the] Adair County Rest Area, . . . as described in Section 2
    hereof, and in accordance with the Drawings, General Conditions of
    the Contract, Supplementary General Conditions, Specifications,
    and Addenda No. 1. (as supplied) inclusive prepared by Yeggy
    Colby Associates.
    SECTION 2. Scope of Work: The Subcontractor agrees to
    promptly begin said work IMMEDIATELY after notification by said
    Contractor, and complete all work IN ACCORDANCE WITH THE
    SCHEDULE AS OUTLINED BY THE CONTRACTOR AND IN
    ACCORDANCE WITH OTHER TRADES in accordance with this
    Agreement upon Acceptance and notice to proceed by the Bonding
    Company.
    (Work Description)
    In accordance with the contract documents, as listed on
    Attachment “A,” furnish labor, material and equipment complete as
    described by the following Specification Sections:
    Division 1-General Requirements (as applicable to
    your work); Division 31 Complete, Section 024100.
    Supply all labor, material and equipment to provide all
    dirt work, site clearing, subsoil work, building removal,
    demolition, misc items per your quote in its entirety per plans
    and specifications.
    Work includes, but is not limited to:
    A. 1 Electronic set of Submittals per your specifications
    within 10 days.
    B. Supply a schedule of values breaking out labor and
    materials.
    C. Attach current insurance certificate specific to this project
    and naming Pro Commercial LLC as an additional
    insured.
    2
    Pro Commercial acted as a project manager only and did not perform any of the
    construction work.
    5
    D. Supply Federal ID # and list of suppliers and
    subcontractors.
    E. Work per the attached construction schedule. Project to
    begin April 19th and complete in December 2010. ALL
    subcontractors will be required to work 6 days per week
    unless approved by Pro Commercial.
    F. Work per your proposal dated 3/17/10.
    Both parties signed the subcontract, but disputes regarding the scope of
    work K & L was to perform erupted almost immediately.              K & L insisted it
    contracted to perform only the work itemized in its estimate; whereas Pro
    Commercial argued K & L was to perform all of the work described in Division 31,
    which included the specifications for dirt work for the project.         Division 31
    included items such as digging the footings for the buildings and retaining wall,
    supplying granular fill (rock) for the project, and excavating the sidewalk.
    K & L agreed to do some of the work Pro Commercial requested, but
    K & L insisted this work would be billed on a time-and-materials basis.         Pro
    Commercial asserted the cost of the work requested was included in the contract
    price. In addition to disputing the scope of the work, disputes arose regarding
    the timeliness and quality of K & L’s performance. Eventually Pro Commercial
    stopped making further payments to K & L in July 2010, and K & L stopped
    working on the project in November 2010. Construction on the rest area project
    resumed in the spring of 2011, and Pro Commercial hired other subcontractors to
    complete the dirt work on a time-and-materials basis.
    Pro Commercial filed a petition against K & L in February 2012 to recover
    the money it spent remediating K & L’s work under the subcontract. K & L filed a
    counterclaim against Pro Commercial for the work it claims it completed but for
    6
    which it was not compensated. The case proceeded to a bench trial in August
    2013. The district court issued its “Findings of Fact, Conclusions of Law, and
    Order” on March 17, 2014.
    The court concluded the subcontract between Pro Commercial and K & L
    included all the work described in Division 31. Any unilateral mistake made by
    K & L regarding the scope of work called for in the contract would not excuse
    K & L from performing the contract, the court stated.        It thus concluded Pro
    Commercial was entitled to $186,179.14 on its claim, and K & L failed to prove
    what amount of money it would have been entitled to had the court concluded it
    was entitled to payment under the counterclaim.
    K & L appeals the district court’s decision.
    II. Scope and Standard of Review.
    A breach-of-contract claim tried at law to the district court is
    reviewed by us for correction of errors at law. The district court’s
    findings of fact have the effect of a special verdict. “The trial court’s
    ‘legal conclusions and application of legal principles are not binding
    on the appellate court.’” We will reverse a district court’s judgment
    if we find the court has applied erroneous rules of law, which
    materially affected its decision. In contrast, the district court’s
    findings of fact are binding on us if they are supported by
    substantial evidence.
    NevadaCare, Inc. v. Dep’t of Human Servs., 
    783 N.W.2d 459
    , 465 (Iowa 2010)
    (citations omitted). Interpretation of a contract involves determining the meaning
    of the words in a contract; whereas construction involves determining the legal
    effect of such words. Fausel v. JRJ Enters. Inc., 
    603 N.W.2d 612
    , 618 (Iowa
    1999). We review the district court’s interpretation as a legal issue unless the
    interpretation depended on extrinsic evidence. 
    Id.
     In that case, the “question of
    7
    interpretation is left to the trier of fact unless ‘the evidence is so clear that no
    reasonable person would determine the issue in any way but one.’” 
    Id.
     (citation
    omitted). “[W]e always review construction as a legal issue.” 
    Id.
    III. Pro Commercial’s Breach-of-Contract Claim.
    K & L claims the district court failed to give proper effect to the intent of the
    parties at the time it entered into the contract when determining the scope of the
    work under the contract. K & L claims that had the district court considered the
    circumstances of the transaction, it would have noted that K & L proposed to do a
    very specific list of work for $74,268 and this work did not include supplying over
    $100,000 worth of rock, backfilling, or digging footings for the buildings and
    retaining wall.
    The intent of the parties is the cardinal principle of contract interpretation.
    NevadaCare, 
    783 N.W.2d at 466
    . “[T]he most important evidence of the parties’
    intentions at the time they entered into the contract is the words of the contract.”
    
    Id.
     The court can also consider the words and conduct of the parties along with
    extrinsic evidence such as “the situation and relations of the parties, the subject
    matter of the transaction, preliminary negotiations and statements made therein,
    usages of trade, and the course of dealing between the parties.” 
    Id.
     “Long ago
    we abandoned the rule that extrinsic evidence cannot change the plain meaning
    of a contract.    We now recognize the rule in the Restatement (Second) of
    Contracts that states the meaning of a contract ‘can almost never be plain except
    in a context.’” Pillsbury Co. v. Wells Dairy, Inc., 
    752 N.W.2d 430
    , 436 (Iowa
    8
    2008) (citations omitted). But “the words of an integrated agreement remain the
    most important evidence of intention.” 
    Id.
    “Another relevant rule of contract interpretation requires that ‘[w]herever
    reasonable, the manifestations of intention of the parties to a promise or
    agreement are interpreted as consistent with each other and with any relevant
    course of performance, course of dealing, or usage of trade.’” 
    Id.
     “The rules [of
    contract interpretation] do not depend on a determination that there is an
    ambiguity, but we use them to determine ‘what meanings are reasonably
    possible as well as in choosing among possible meanings.’” 
    Id.
    In the “scope of work” section of the contract at issue, the subcontractor
    was to “furnish labor, material and equipment complete as described by the
    following Specification Sections: Division I-General Requirements (as applied to
    your work); Division 31 Complete, Section 024100.” This section went on to
    state the subcontractor was to “supply all labor, material and equipment to
    provide all dirt work, site clearing, subsoil work, building removal, demolition,
    misc items per your quote in its entirety per plans and specifications.”        The
    section then provided the “work includes, but is not limited to: . . . Work per your
    proposal dated 3/17/10.”
    The district court acknowledged the contract was not very clear, but the
    court determined that to interpret the contract as K & L requested would require
    the court to ignore or attribute no meaning to the language of section 2 that
    required the subcontractor to provide labor, material, and equipment to complete
    Division 31.
    9
    K & L correctly argues that Division 31 and Section 024100 included work
    that Pro Commercial never intended for K & L to do, including trenching for
    utilities, surveys, traffic control, barriers, and fencing. This work was done by
    other subcontractors or by Pro Commercial itself. Since Pro Commercial never
    intended for K & L to do this work, which was included in Division 31 and Section
    024100, then K & L contends it goes to reason that “Division 31 Complete” in the
    contract cannot mean for K & L to do all the work that is described in that section.
    K & L asserts Division 31 and Section 024100 are specifications telling
    contractors how to do the work, not what work to do. The project inspector for
    the IDOT working on this project agreed with this characterization of the
    specifications.
    Testimony from Pro Commercial’s expert, Brent Thompson, also supports
    this interpretation. Thompson is an estimator and project manager for the Elder
    Corporation, and during cross-examination, he admitted he had written an email
    to Pro Commercial’s attorney after his preliminary review of the record which
    stated, “normally Division 31 specifications only clarify material and methods and
    procedure for work as it applies to scope provided by the subcontractor.”
    However, he also testified at trial that in his experience when the contract states
    “Division 31 Complete” it means the subcontractor is required to provide all of the
    sections that are listed in Division 31. Thompson went on to explain that if the
    subcontractor does not want to provide some of the work set out in that division,
    the subcontractor should have specifically excluded it from the proposal. In fact,
    another contractor on the project had excluded some of the work Pro
    10
    Commercial was seeking to have K & L do under Division 31.                No such
    exclusions were included in K & L’s estimate.
    K & L presented testimony that it is standard in the construction industry in
    the Des Moines area for concrete subcontractors to dig foundation footings,
    rather than subcontractors in charge of dirt work. We note that in interpreting
    contracts, courts can look to the usages of trade. See Peak v. Adams, 
    799 N.W.2d 535
    , 544 (Iowa 2011). However, the usages of trade and customs in
    business cannot be used to change, vary, or defeat the express terms of a
    contract. See Farmers’ & Merchants’ Bank of Ireton v. Wood Bros. & Co., 
    118 N.W. 282
    , 285-86 (Iowa 1908) (“While proof of custom may be competent to
    explain words or terms of doubtful signification, or to show a trade usage by
    which certain words or expressions are given an arbitrary or technical meaning, it
    is the well-established rule in this state that proof of custom or usage is not
    admissible to defeat a contract or to vary its express terms.”); Rindskoff Bros. v.
    Barrett, 
    14 Iowa 101
    , 105 (1862) (“It is hardly correct to say that a contract
    (express) is controlled by a custom, but that it may be affected by it is too well
    settled to now admit of doubt.”).
    The issue in this case is what does the phrase “Division 31 complete”
    mean with respect to the scope of work K & L was to perform. K & L submitted a
    very specific list of work to Pro Commercial, which included prices for each
    itemized work description. The proposed itemized price list added up to $74,268,
    the ultimate price of the contract between K & L and Pro Commercial.            The
    itemized list did not include such things as digging footings or supplying the
    11
    granular fill. K & L asserts the cost of the granular fill alone for this project was
    over $100,000, and it would be illogical for Pro Commercial to believe the
    granular fill, which was not included in the itemized list of work, would be
    included with the other work at a cost of $74,268.           In addition, the word
    “complete” cannot be logically interpreted to mean all work in Division 31 as Pro
    Commercial asserts. Pro Commercial admits there was work within Division 31
    that K & L was never expected to perform: trenching for utilities, surveys, traffic
    control, barriers, and fencing.      Other subcontractors contracted with Pro
    Commercial to perform this work, and Pro Commercial has never sought for
    K & L to do this work. Therefore “complete” cannot mean what Pro Commercial
    asserts that it should mean.3
    But the word “complete” must mean something. Iowa Fuel & Minerals,
    Inc. v. Iowa State Bd. of Regents, 
    471 N.W.2d 859
    , 863 (Iowa 1991) (“[A]n
    interpretation which gives a reasonable, lawful, and effective meaning to all terms
    is preferred to an interpretation which leaves a part unreasonable, unlawful, or of
    no effect.”). K & L asserts that Division 31 is meant only to inform the contractor
    how the work is to be performed, not what work to perform. Therefore, with that
    industry understanding of what Division 31 is, “complete” in this context would
    mean    the   dirt   work   K&L     was    to   perform   had    to   be   done    in
    compliance/conformity with all of the directions listed in Division 31. In contrast,
    the contract stated “Division 1-General Requirements (as applicable to your
    work)” which would mean under K & L’s interpretation that the specification in this
    3
    In the famous words of Inigo Montoya from the movie, The Princess Bride, “You keep
    using that word. I do not think it means what you think it means.”
    12
    section only had to be followed to the extent it applied to the work K & L was to
    perform.
    This interpretation is consistent with the following paragraph in the
    contract that directs K & L to “[S]upply all labor, material and equipment to
    provide all dirt work, site clearing, subsoil work, building removal, demolition,
    misc items per your quote in its entirety per plans and specifications.” (Emphasis
    added.) This paragraph would be redundant if we were to interpreted “Division
    31 Complete” to be a description of what work K & L was to perform rather than a
    description of how to perform the work.
    We conclude the district court erred in interpreting the contract to require
    K & L to perform all of the work described in Division 31 and Section 024100.
    Therefore, we reverse the district court’s conclusion that Pro Commercial proved
    its breach-of-contract claim against K & L. Because we conclude the contract did
    not require K & L to perform all of the work described in Division 31, we must
    address K & L’s claims of quantum meruit and unjust enrichment.          K & L is
    entitled to recover for the work it performed that was outside of its estimate
    because we conclude such work was not within the terms of the subcontract.
    IV. K & L’s Counterclaim.
    In response to Pro Commercial’s breach-of-contract petition, K & L
    asserted a counterclaim for breach of contract for Pro Commercial’s failure to pay
    K & L for the work it performed under the contract and for unjust enrichment for
    the value of the work K & L did that was outside the scope of the contract. The
    district court summarily rejected these claims after agreeing with Pro
    13
    Commercial’s interpretation of the contract. As we reverse the district court’s
    decision, we proceed to address K & L’s claims.
    K & L’s president, Kevin Alexander, testified he notified Pro Commercial
    that they would charge for work done outside the scope of their estimate on a
    time-and-materials basis. Yet, Pro Commercial insisted that K & L perform the
    work asserting that work was within the scope of the contract. In addition, Pro
    Commercial last paid K & L for work completed under the contract in July 2010,
    though K & L continued to work on the project until November 2010, submitting
    invoices to be paid. K & L asserts it is entitled to recover $43,721.20 for extra
    work performed that was outside the scope of the contract and $48,530.50 for
    work it did under the contract. Pro Commercial did pay K & L for some of the
    work performed under the contract in the amount of $26,989.31, and K & L
    acknowledged Pro Commercial should receive a credit in the amount of $3275
    for the cost to correct work that K & L performed improperly. So the total K & L is
    seeking from Pro Commercial is $61,987.39.4
    A. Unjust Enrichment. “The doctrine of unjust enrichment is based on
    the principle that a party should not be permitted to be unjustly enriched at the
    expense of another or receive property or benefits without paying just
    compensation.” State ex rel. Palmer v. Unisys Corp., 
    637 N.W.2d 142
    , 154 (Iowa
    2001).     There are three elements to unjust enrichment: “(1) defendant was
    enriched by the receipt of a benefit; (2) the enrichment was at the expense of the
    plaintiff; and (3) it is unjust to allow the defendant to retain the benefit under the
    4
    $43,721.20 + 48,530.50 – 26,989.31 – 3275.00 = $61,987.39
    14
    circumstances.” 
    Id.
     at 154–55. K & L claims it is entitled to recover for the work
    it performed on the project that was not part of the contract but that Pro
    Commercial demanded K & L perform.           See Nepstad Custom Homes Co. v.
    Krull, 
    527 N.W.2d 402
    , 407 (Iowa Ct. App. 1994) (“A builder may recover from an
    owner for extras ordered or agreed upon which were not covered by the
    contract.”); see also Maasdam v. Estate of Maasdam, 
    24 N.W.2d 316
    , 321 (Iowa
    1946) (“But there may be an implied contract on a point not covered by an
    express contract.”).
    Pro Commercial received the benefit of K & L performing work that was
    not within the scope of the contract. K & L performed the work after informing
    Pro Commercial that K & L would bill for the work on a time-and-materials basis.
    The work was performed, and it is unjust to allow Pro Commercial to benefit from
    the work, as the work in question was part of the completed project for which Pro
    Commercial was paid by the IDOT, without paying K & L for the work. We agree
    K & L has proven its claim for unjust enrichment in this case for the work
    performed that was not part of the contract.
    The record is clear regarding K & L’s damage claim for work completed
    that was not under the contract. The record discloses invoices provided to Pro
    Commercial for work including the completion of the construction entrance;
    backfilling; excavation of footings for the storage building, main building, and
    retaining wall; and over-excavation for the sidewalks. The total of the invoices
    submitted to Pro Commercial for work K & L completed but that was not part of
    the contract was $43,721.20. Pro Commercial is given a credit for $3275 to
    15
    correct work that K & L performed improperly. We conclude K & L is entitled to
    judgment entered in its favor in the amount of $40,442.20.
    B. Breach of Contract. Next, K & L claims Pro Commercial breached
    the written contact by failing to timely pay the invoices it submitted for work that
    was covered under the contract. To establish a claim for breach of contract, a
    party has to prove:
    (1) the existence of a contract, (2) the terms and conditions of the
    contract, (2) that [plaintiff] has performed all of the terms and
    conditions required under the contract, (4) the defendant’s breach
    of the contract in some particular way, and (5) that plaintiff has
    suffered damages as a result of defendant’s breach.
    Royal Indem. Co. v. Factory Mut. Ins. Co., 
    786 N.W.2d 839
    , 846 (Iowa 2010).
    The contract provided all invoices from the subcontractor must be
    submitted by the 25th day of the month to be considered for payment the
    following month, and the application for payment must be made on the approved
    form. The contract also provided that Pro Commercial will pay K & L a total of
    $74,268 in monthly payments for the work called for in the contract so long as
    K & L was in full compliance with the agreement.
    Pro Commercial claims that the obligation for it to pay K & L arose only if
    K & L was in full compliance with the agreement. Pro Commercial asserts K & L
    failed to comply with the agreement by not being present on the worksite six days
    a week when its presence was needed, and failing to do the work we concluded
    above was not part of the contract agreement. Because K & L was not in full
    compliance with the agreement, Pro Commercial asserts it did not breach the
    contract by failing to pay K & L for the work performed.
    16
    There is no question there was a contract between K & L and Pro
    Commercial, and the terms and conditions of that contract are clear.            It is
    undisputed that K & L submitted requests for payment under the contact and two
    of those requests were paid in the total amount of $26,989.31. It is undisputed
    Pro Commercial stopped paying K & L for work performed in July 2010. It is also
    undisputed K & L stopped working in November 2010, and Pro Commercial did
    not call K & L back to the job site in the spring of 2011 to complete its
    performance. Instead, Pro Commercial obtained substitute performance from
    other contractors to complete the work K & L was to perform under the contract
    and to complete work that was outside the scope of the contract.
    K & L did not complete the work required by the contract. But, “[i]t is now
    the settled doctrine in this State that a party who has failed to perform in full his
    contract may recover compensation for the part performed, less the damages
    occasioned by his failure.” Wolf, Carpenter & Angel v. Gerr, 
    43 Iowa 339
    , 341
    (1876). Thus, the issue then becomes what amount K & L can recover for its
    partial performance under the contract.
    The district court concluded that even if K & L could prove Pro
    Commercial breached the terms of the contract, “the evidentiary record was
    inadequate to establish any damages.” The court noted the record disclosed
    several billing errors and lax business practices by K & L.
    Jenna Wilson, K & L’s vice president, testified she calculated the amount
    of work completed under the contract, and in her opinion, the amount K & L was
    entitled to recover totaled $48,530.30.        Of this amount, Pro Commercial had
    17
    already paid K & L a total of $26,989.31 for the work K & L had performed up to
    July 2010 under the contract. Further requests for payment were made by K & L;
    however, the evidentiary record to support these requests was severely lacking.
    Both Jenna Wilson and Kevin Alexander testified K & L generated invoices and
    requested Pro Commercial pay for work that was not completed by K & L. Both
    testified that K & L requested payment for demolishing the rest area building, the
    vending building, and a wooden garage, and completing the grading, but this
    work was not in fact done by K & L.          It was done by other contractors Pro
    Commercial employed in the spring of 2011 to complete the work.
    The evidence presented to support K & L’s damage claim for work
    completed under the contract was convoluted at best. It was K & L’s burden to
    prove the amount of damage it suffered because of Pro Commercial’s breach.
    See Royal Indem., 
    786 N.W.2d at 846
    . We agree with the district court that
    K & L failed to provide sufficient evidence to prove its breach-of-contract claim
    against Pro Commercial because it failed to prove its claim for damages. We
    therefore award it no further amount for the work K & L claimed to have
    completed under the contract.
    V. Conclusion.
    We find the district court erred in concluding the contract at issue required
    K & L to perform work that was not included in its estimate. We reverse the
    district court’s decision holding Pro Commercial proved its breach-of-contract
    claim.    Because K & L failed to prove the amount of money it is entitled to
    recover for its partial performance of the contract, it is not entitled to recover
    18
    under its breach-of-contract counterclaim any amounts beyond those already
    paid by Pro Commercial. However, we conclude K & L it entitled to a judgment in
    the amount of $40,442.20 for work completed that was outside the terms of the
    written contract under its unjust-enrichment claim. We remand the case to the
    district court for the entry of an order of judgment consistent with this opinion.
    REVERSED AND REMANDED.