Robert McFadden v. Central Iowa Truck and Trailer, Inc. ( 2014 )


Menu:
  •                    IN THE COURT OF APPEALS OF IOWA
    No. 13-1119
    Filed June 11, 2014
    ROBERT MCFADDEN,
    Plaintiff-Appellant,
    vs.
    CENTRAL IOWA TRUCK AND
    TRAILER, INC.,
    Defendant-Appellee.
    ________________________________________________________________
    Appeal from the Iowa District Court for Boone County, Dale E. Ruigh,
    Judge.
    Robert McFadden appeals the district court’s dismissal of his claims for
    breach of an oral contract. AFFIRMED.
    Benjamin T. Doran of Doran Law Firm, Boone, for appellant.
    John D. Jordan of Jordan & Mahoney Law Firm, P.C., Boone, for appellee.
    Heard by Vaitheswaran, P.J., and Tabor and Bower, JJ.
    2
    TABOR, J.
    This appeal involves a customer who is unhappy with the engine installed
    in his classic car. The customer, Bob McFadden, sued his mechanic’s shop for
    breach of an oral contract. McFadden alleged he wanted a “totally stock” GM
    engine and received an engine containing aftermarket parts instead. He also
    expressed dissatisfaction with the engine’s warranty.     McFadden sought to
    rescind the contract.
    The district court found no breach and, alternatively, ruled McFadden was
    not entitled to rescission. McFadden challenges those conclusions on appeal.
    Because the district court did not err in ruling McFadden failed to establish a
    breach of the oral contract, we affirm.
    I.     Background Facts and Proceedings
    McFadden owns a 1970 Chevrolet SS Chevelle. When the car needed
    repairs, McFadden took his cousin’s recommendation to have the engine work
    done by Dave Shank at Central Iowa Truck and Trailer, Inc. (Central Iowa) in
    Boone. Shank worked as a mechanic for twenty-five years and was the manager
    and sole employee of Central Iowa. Shank pulled out the Chevelle’s 396-cubic-
    inch engine and delivered it to Arnold Motor Supply for an estimate on the repair
    cost. Because the Arnold machinist advised that rebuilding would cost more than
    the value of the engine, McFadden decided to replace the old engine with a new
    502-cubic-inch engine.
    McFadden found an advertisement for a “General Motors ZZ502 big block
    deluxe crate engine” in a Summit Racing Equipment catalog. He ripped out that
    3
    page and showed it to Shank. McFadden recalls telling Shank: “[T]his is the
    motor I want.”
    Shank said he could buy the engine for McFadden using his discount at
    Arnold Motor Supply to save McFadden several hundred dollars. McFadden
    agreed. Shank called Gary Kemp at Arnold and asked him to order the engine
    model requested by McFadden. Kemp did not order from Summit; he instead
    ordered the engine from Motorville, a wholesale company in Kansas City.
    McFadden gave Arnold an $8000 down payment on the engine.
    When the engine was shipped to Shank, he called McFadden to have him
    inspect it before installation.   During his inspection McFadden noticed the
    cylinder heads and high rise intake manifolds were aftermarket products
    manufactured by Edelbrock rather than “genuine GM parts.” McFadden said
    when he asked about those parts, Shank “got kind of mad” and said Chevy did
    not make their own intakes and heads. As Shank remembered the conversation,
    he told McFadden: “General Motors farms out a lot of their engine work,” and he
    was not sure whether “they possibly had Edelbrock make those heads for them.”
    McFadden testified he was “naïve” at that time and took Shank’s word that GM
    did not manufacture its own heads and manifolds.1 Despite his reservations,
    McFadden told Shank to go ahead with the installation.
    McFadden received a receipt from Central Iowa dated August 5, 2011.
    The receipt reflected his down payment of $8000 and an additional amount due
    1
    McFadden testified, after purchasing the engine, he did research and learned GM does
    manufacture its own heads and intakes.
    4
    of $4,602.94. In addition, McFadden paid Shank $500 for “after hours” labor and
    tipped Shank $300. The receipt noted at the bottom: “ENGINE HAS 24 MONTH
    WARRANTY OR 50,000 MILES, WHICHEVER COMES FIRST.”
    The engine did not run properly.2 A week or two after installation, the
    distributor gear needed to be replaced.       Then two or three weeks later,
    McFadden contacted Shank to say he thought the “motor was blown up.” Shank
    removed the engine and took it to Arnold for inspection.       Arnold employees
    shipped the engine back to Motorville for major repairs covered under the
    warranty. Before the fully assembled engine was returned to Shank, he received
    correspondence from McFadden’s attorney. At the time of the trial, the repaired
    engine was sitting in Shank’s shop. Shank testified he would install it back into
    McFadden’s car at no charge under the warranty if McFadden asked him to do
    so.
    On April 23, 2012, McFadden filed a petition at law alleging he had a
    verbal agreement with defendant Central Iowa to install a “genuine GM ZZ502
    big block engine” into his Chevelle. According to the petition, it was “important”
    to McFadden the engine contain “genuine GM parts” and carry a “GM warranty.”
    The petition alleged McFadden did not receive the engine he intended to
    purchase, and stated McFadden did not want Central Iowa to reinstall the engine
    in its possession. Plaintiff McFadden asked for “the agreement between the
    parties to be rescinded, cancelled, and terminated due to the Defendant’s
    breach,” and he sought the return of his $13,402.94 in payments.
    2
    McFadden does not allege the aftermarket parts are responsible for the engine
    problems.
    5
    On May 21, 2012, Central Iowa filed an answer and a cross-petition
    naming Arnold as a third-party defendant.         Central Iowa admitted entering a
    verbal agreement with McFadden to install the block engine but denied selling
    the engine to him. Central Iowa affirmatively alleged McFadden purchased the
    engine from Arnold. Arnold, as third-party defendant, filed an answer, stating:
    “[T]he Third Party Plaintiff [Central Iowa] purchased an engine from Arnold Motor
    Supply, LLP, for a purchase price of $8,950.00.”
    The district court held a trial on April 24, 2013. Plaintiff McFadden testified
    for himself; Shank testified for Central Iowa; and Gary Kemp testified for Arnold.
    On June 20, 2013, the district court entered its “Findings of Fact, Conclusions of
    Law, and Order.” The court determined “a preponderance of the evidence fails to
    show that any of the parts of the engine installed in Mr. McFadden’s Chevelle
    were other than ‘genuine GM parts.’” The court also concluded the record did
    not support McFadden’s allegation the agreement was to install an engine with
    only parts manufactured directly by General Motors rather than by a supplier to
    General Motors. The court pointed out McFadden accepted the engine ordered
    through Arnold3 “knowing that Edelbrock may have manufactured certain parts of
    the engine.”
    Regarding the warranty complaint, the court found it significant that the
    invoice from Central Iowa included a twenty-four month, 50,000-mile guarantee.
    3
    The court also ruled its dismissal of McFadden’s claim against Central Iowa resulted in
    Central Iowa’s claim for indemnity against Arnold becoming moot. Arnold is not a party
    to this appeal.
    6
    The court decided McFadden had not proved the warranty was inconsistent with
    the agreement of the parties. The court concluded:
    Because Mr. McFadden has failed to show Central Iowa’s
    breach of their agreement, his claim for rescission of the contract
    must be dismissed. Even if the evidence showed a breach, the
    circumstances of this case would not support the rescission of the
    entire contract and return of all monies spent by Mr. McFadden on
    the engine, as opposed to an award of damages caused by the
    breach.
    McFadden appeals.
    II.   Standard of Review
    The parties disagree on the appropriate standard of review. Citing Gouge
    v. McNamara, 
    586 N.W.2d 710
    , 712 (Iowa Ct. App. 1998), McFadden advocates
    for de novo review because his request for rescission of the contract is an
    equitable remedy. Central Iowa argues our review is for errors at law, not de
    novo, because McFadden captioned his petition “at law,” and the district court
    issued findings of fact and conclusions of law.      The parties stipulated to the
    admission of all the exhibits and no objections were made during the trial.
    Because we do not reach the question of rescission, we conclude our
    review is for errors at law. See Empl. Benefits Plus, Inc. v. Des Moines Gen.
    Hosp., 
    535 N.W.2d 149
    , 153 (Iowa Ct. App. 1995) (applying “at law” review to
    district court’s findings of fact concerning breach of oral contract). The district
    court’s findings of fact are binding on appeal if supported by substantial
    evidence. 
    Id. 7 III.
      Analysis
    McFadden advances a two-fold challenge to the district court’s ruling.
    First, he contends the court was mistaken in deciding Central Iowa did not
    breach the oral agreement to install a deluxe GM engine in his classic car.
    McFadden believes he proved broken promises concerning both the engine’s
    parts and the warranty. Second, McFadden claims the court erred in finding he
    was not entitled to the remedy of rescission for Central Iowa’s breach of contract.
    Because we affirm the district court’s ruling that Central Iowa did not breach the
    oral contract, we need not address McFadden’s second appellate claim.
    As the complaining party in this breach-of-contract case, McFadden must
    show (1) the existence of a contract, (2) its terms and conditions, (3) his own
    performance under the contract, (4) the defendant’s breach of the contract in a
    particular way, as well as (5) damages resulting from the breach. See Molo Oil
    Co. v. River City Ford Truck Sales, Inc., 
    578 N.W.2d 222
    , 224 (Iowa 1998). The
    parties agree an oral contract existed, but they disagree on the contract’s precise
    terms and the defendant’s alleged breach.
    McFadden contends their oral agreement required Shank to install a
    “genuine GM ZZ502 engine” bearing the same parts number as the engine
    shown in the Summit catalog. He asserts the engine ordered by Arnold and
    installed by Central Iowa was not “the motor he wanted or thought he was
    getting.” He alleges the Edelbrock parts affect his “desire to have a totally stock
    Chevelle Classic that would increase its value.”
    8
    McFadden also argues the engine he wanted came with a warranty “that
    would let him go to a GM dealer anywhere to get the work done and the warranty
    honored, since it came from GM.” Although the warranty from Central Iowa
    covered the same number of years and miles, McFadden was worried he would
    have to consult with Shank before having repairs completed at another shop.
    Central Iowa counters that despite the “importance” McFadden now
    places on the idea of “genuine GM parts” and “having a GM warranty”—he did
    not meet his burden to prove those terms were part of the oral agreement.
    Central Iowa argues the district court correctly found McFadden did not show the
    inclusion of Edelbrock parts meant Shank failed to install a “genuine GM ZZ502
    engine.” Defendant further argues the only mutually agreed-to warranty was the
    one prominently displayed at the bottom of its invoice, the invoice paid by
    McFadden.
    A binding contract exists if the parties reach a meeting of minds on the
    material terms. Pavone v. Kirke, 
    801 N.W.2d 477
    , 487 (Iowa 2011). Terms are
    material if they are significant to the contract.    
    Id. A binding
    contract also
    requires an offer and acceptance.      
    Id. at 488.
       “Acceptance of the offer is
    indicated by a manifestation of assent to the terms of the offer made by the party
    to whom it is addressed in a manner invited or required by the offer.”         
    Id. Importantly, mutual
    assent is based on objective evidence, not the hidden intent
    of the parties. 
    Id. A breach
    occurs when, without legal excuse, a party fails to
    perform any promise which forms a whole or a part of the contract. Molo 
    Oil, 578 N.W.2d at 224
    .
    9
    This record contains objective evidence showing the parties’ mutual
    assent to Shank’s installation of the engine ordered from Motorville.            Shank
    sought McFadden’s approval before installing the engine. Despite McFadden’s
    reservations about the aftermarket parts, it is undisputed he gave Shank the go-
    ahead.   As the district court aptly emphasized: “Mr. McFadden accepted the
    engine ordered through Arnold Motor Supply for installation in his Chevelle
    knowing that Edelbrock may have manufactured certain parts of the engine.”
    Thus, even if McFadden harbored an unspoken desire to have all GM-
    manufactured parts, he did not express that intent to Shank at the time of their
    mutual assent to proceed with the installation of the Motorville engine.4 Because
    Shank installed the engine approved by McFadden, Central Iowa did not breach
    a term of the oral contract.
    Objective evidence also supports the district court’s conclusion on the
    warranty issue.     The district court pointed to the invoice documenting the
    installation of a “GM ZZ502 big block crate engine” and accompanied by the
    statement: “Engine has 24 month warranty or 50,000 miles, whichever comes
    first.” The court noted Central Iowa “has honored that warranty by doing all of its
    repair work and securing a repaired engine through Arnold Motor Supply without
    charge” to McFadden, and stood ready to continue honoring the warranty by
    reinstalling the repaired engine. The court stated:
    Nevertheless, Mr. McFadden asserts that his warranty does not
    comply with the parties’ claimed agreement that the engine would
    have a “GM warranty.” Certainly, both Mr. McFadden and Central
    4
    We also find it significant that McFadden agreed to have the engine sent back to
    Motorville for repairs after he was aware of the aftermarket parts and Shank’s warranty.
    10
    lowa contemplated that the engine installed in the Chevelle would
    have a warranty of some type. Central Iowa’s invoice refers to the
    warranty and Mr. McFadden, after receiving the invoice, made no
    complaints about the warranty until the pending dispute arose.
    Not only did McFadden not complain, he paid the entire amount invoiced and
    voluntarily added a handsome tip for Shank’s good work.               On this record,
    McFadden did not carry his burden to prove the warranty provided by Shank was
    inconsistent with the parties’ agreement on the material terms of the contract.5
    We find no error in the district court’s conclusion Central Iowa did not
    breach any material terms of the oral contract to install the GM engine in
    McFadden’s car.
    AFFIRMED.
    5
    The district court further concluded McFadden did not prove the Central Iowa warranty
    was less convenient than a GM warranty because it required prior approval for repairs.
    We agree with the district court’s assessment that the warranty provided by Central Iowa
    did not breach a material term of its contract with McFadden.