Mark Benson d/b/a Benson Border Materials v. Boyle Built Enterprises, L.L.C. and Andrew Boyle ( 2021 )


Menu:
  •                    IN THE COURT OF APPEALS OF IOWA
    No. 19-2006
    Filed December 15, 2021
    MARK BENSON d/b/a BENSON BORDER MATERIALS,
    Plaintiff-Appellant/Cross-Appellee,
    vs.
    BOYLE BUILT ENTERPRISES, L.L.C., and ANDREW BOYLE,
    Defendants-Appellees/Cross-Appellants.
    ________________________________________________________________
    Appeal from the Iowa District Court for Van Buren County, Crystal S. Cronk,
    Judge.
    The parties to a contract for the sale of a railroad tie removal business
    appeal and cross-appeal from a district court ruling.    AFFIRMED IN PART,
    REVERSED IN PART, AND REMANDED ON APPEAL; AFFIRMED ON CROSS-
    APPEAL.
    Bryan J. Goldsmith of Gaumer, Emanuel, Carpenter & Goldsmith, P.C.,
    Ottumwa, for appellant.
    Kevin J. Caster of Shuttleworth & Ingersoll, P.C., Cedar Rapids, for
    appellees.
    Heard by May, P.J., and Greer and Schumacher, JJ.
    2
    SCHUMACHER, Judge.
    The parties, Mark Benson, doing business as Benson Border Materials
    (hereinafter “Benson”), and Boyle Built Enterprises, L.L.C. (hereinafter “Boyle
    Built”) owned by Amy Boyle (hereinafter “Amy”) and Andrew Boyle (hereinafter
    “Andrew”), entered into an agreement for the sale of Benson’s railroad-tie-removal
    business. Benson was to transfer the physical assets of the business, a contract
    with Omaha Track, and provide consulting services for two years. In exchange,
    Boyle Built agreed to pay a purchase price for the physical assets and ten percent
    of the revenues earned under the Omaha Track contract for Benson’s consulting
    services.
    Benson brought suit against Boyle Built, alleging Boyle Built breached the
    agreement by failing to pay sums owed under the contract and made other
    equitable claims.1 Boyle Built argued Benson breached the agreement, relieving
    the obligation to pay the contract balance, and also brought other counterclaims.
    A bench trial was held over a period of three days in July 2019. The district court
    denied Benson’s breach-of-contract claim and dismissed Benson’s equitable
    claims. The district court granted Boyle Built’s breach-of-contract counterclaim
    and denied its other counterclaims. The court made additional rulings on the sale
    of various equipment. Benson appeals and Boyle Built cross-appeals.
    1 Benson also brought claims against Andrew Boyle individually but dismissed the
    claims, seeking judgment against Boyle Built only.
    3
    I.     Relevant Facts
    A.     The Railroad Tie Removal Business
    The parties to this appeal are engaged in the railroad-tie-removal business.
    When a section of track or “hitch” needs to be replaced, the railroad company
    deploys crews of railroad employees or “gangs” to separate the ties from the rails.
    The discarded ties are left beside the track as the gangs work their way down the
    rails. The clean-up and removal of the ties from the railroad track is subcontracted
    through a contract service company retained by the railroad.
    Picking up and removing the ties from the railroad requires the use of
    specialized equipment and “high-rail grapple trucks.”2 Replacement parts for the
    grapple trucks are specialized and can be difficult to acquire. Grapple truck
    operators must possess knowledge of the railroad’s safety regulations and are
    required to complete safety training courses.
    B.     The Parties’ Respective Businesses
    In 1997, Benson began his railroad-tie-removal business, Benson Border.
    Around 2002, Benson Border began doing railroad-tie-removal jobs for a contract
    service company, Omaha Track. By 2009, Omaha Track was awarding consistent
    contracts to Benson Border, including all clean-up for the Union Pacific Railroad.
    During this time, Benson continued to expand his business, successfully
    completing projects across the Midwest, New Mexico, and Colorado. In 2014,
    Benson had gross income from Omaha Track in excess of one million dollars. By
    2  High-rail grapple trucks are large commercial trucks able to be driven on
    railroads. The platform bed of the trucks is equipped with a grapple crane which
    is operated to lift and move the railroad ties.
    4
    2015, Benson had a fleet of five grapple trucks and had five to eight full-time
    employees. Around this same time, Benson was considering slowing down his
    business and spending more time working on his farming operation in northern
    Minnesota.
    Andrew and Amy Boyle founded Boyle Built around 2011. The business
    began as a residential tree removal service but over time grew to include storm
    debris clean-up and other right-of-way contracting. Amy handled the bookkeeping
    and Andrew secured contracts and worked in the field. Around 2013 or 2014,
    Andrew sought to expand the business further and began exploring the railroad-
    tie-removal business. Around this time, he was introduced to Benson. In 2014,
    Andrew accompanied Benson on the railroad to learn more about Benson’s
    business. Soon after, Boyle Built entered the railroad-tie-removal business and
    began securing contracts for various individual projects.3 Eventually, the idea of
    Boyle Built purchasing Benson was introduced.
    C.     The Sale of Benson to Boyle Built
    In May or June 2015, Benson, Andrew, and Andrew’s business associate,
    Brian Newman, met in Pella, Iowa to discuss the sale of Benson’s business to
    Boyle Built.4 After the meeting, Andrew drafted a letter of intent based on the terms
    discussed. The parties acknowledge that the contract was a “rough draft.” Some
    of the contract’s terms were later modified orally by the parties.
    3Boyle Built was able to secure a few short-term contracts for single projects.
    4Boyle Built could not review the financial records prior to the sale of the business
    because of Benson’s accountant being unresponsive to Boyle Built’s requests and
    an ongoing audit.
    5
    On July 23, Benson agreed with the terms and signed the letter. On July 25, the
    Omaha Track contract was signed over to Boyle Built and the parties began
    performance of their obligations under the agreement.
    The parties stipulated and the district court found the letter of intent served
    as a valid written contract between the parties. The contract includes terms of the
    assets to be purchased, the purchase price, payment of the purchase price, and
    employee matters. However, other critical portions of the contract were left blank
    or were vague. The portions of the contract most relevant to this appeal follow.
    Additional terms are discussed where necessary.
    Purchase of the Benson Border Materials’ Omaha Track Business:
    At closing, Buyer or an affiliate will purchase Benson Border
    Materials’ business relationship with Omaha Track and the assets
    used by Benson Border Materials and selected by Buyer to conduct
    that business (the “Proposed Transaction”).            The Proposed
    Transaction will include Buyer’s acquisition of:
    (i)    2013     Kenworth,      VIN      1NKDX4EX4DJ354337;
    ($200,000)
    (ii)   2000     Kenworth,      VIN      1NKDLBEX9YS958708;
    ($160,000)
    (iii)  1998 Mack, VIN 1M2AD62C9WW005864; ($110,000)
    (iv)   1995 International, VIN 1HTGCADR1SH658910;
    ($90,000)
    (v)    Tie carts ($10,000) each serco 8500 ($25,000) poclian
    drive $12,500?
    (vi)   All of the intangible assets associated with Benson
    Border Materials’ business relationship with Omaha Track including
    but not limited to any contracts that with Omaha Track that may be
    assigned to Buyers, Seller’s brand names, customer lists, licenses,
    trade secrets, know how, etc.; and
    (vii) All of Seller’s accounts receivable associated with the
    Omaha Track.
    Buyer will not assume any of Seller’s liabilities.
    Consideration:
    The purchase price (the “Purchase Price”) would be equal to:
    (a)    $627500 (the “Closing Purchase Price”) in cash, plus
    (limited to parts or additional equipment)
    6
    (b)    Assuming (i) Mark Benson is not in breach of his
    Consulting Services Obligations; and (ii) Buyer’s monthly revenues
    with Omaha Track arising from the Proposed Transaction (measured
    for each of the 24 months following closing) equal or exceed [$ ],
    Buyer shall pay Seller [10% of such monthly revenues] up to an
    aggregate of 2 years retainage (the “Earn-Out” Payment”).
    Payment Of Purchase Price:
    The Closing Purchase Price, less the amount held in escrow
    (as provided by paragraph 9 below), will be paid in cash at Closing.
    The Earn-Out Payment will be paid each month for the 24 months
    following Closing.
    [...]
    Employee Matters:
    [...]
    Mark Benson shall use his best efforts to provide Buyer with
    at least [ ] hours/week of consulting and advisory services for the 24
    months following closing which consulting and advisory services
    shall assist Buyer with retaining and expanding business with
    Omaha Track (the “Consulting Services”). The Earn Out Payment
    shall be deemed to be compensation for the Consulting Services.
    [...]
    Escrow: not currently in effect
    [...]
    **Alternately, instead of an escrow account, Buyer will lease
    all equipment from seller for 4 months, and 100% of the lease price
    will go toward the purchase price of $627,000.               (Will be
    approximately $5,500 per truck per month for the grapple trucks). If
    for some unforeseen reason the buyer forfeits after the 4 months,
    seller retains all lease payments.
    For every project billed under the Omaha Track contract, Omaha Track
    would withhold ten percent of the invoiced amount until after the job was complete.
    The withholding was described as “retainage.”       Under the parties’ consulting
    agreement, Benson was to receive this amount for two years in exchange for his
    consulting services.
    7
    D.       Boyle Built after the Sale of the Business
    Business went well for Boyle Built during the first six months of the contract
    period.     Benson’s grapple trucks were mobilized to Boyle Built’s first project,
    Benson went out to assist and the project succeeded. During this time, Benson
    was out in the field operating a grapple truck for roughly forty days.5 After Boyle
    Built’s first two projects, Benson returned to his farm in northern Minnesota; he
    never returned to the field to assist on projects. Benson remained available only
    by telephone to offer advice and answer Boyle Built’s questions.
    After the initial six months, Boyle Built’s business and the relationship
    between Boyle Built and Benson started to sour. From January to March 2016,
    Boyle Built worked the “Gila Bend” project in Yuma, Arizona. It was the largest
    project Boyle Built had undertaken. The project was fraught with mechanical and
    logistical difficulties. Amy testified,
    [I]t was extremely stressful, that it seemed like nothing was going
    right. It was a really tough schedule, working nights. It was hot. It
    was in Arizona. We had a lot of breakdowns. I knew there was a lot
    of difficulties with coordinating things with the railroad and getting
    things to work in our favor.
    Compounding these difficulties was the concurrent Walsenburg project in
    Pueblo, Colorado, where Boyle Built was short an operator. Benson was asked to
    fill in but declined.
    The Gila Bend project ended in contention after Boyle Built incorrectly
    placed ties on a right-of-way. The difficulties with the project led Omaha Track and
    5The district court found Boyle Built agreed to pay Benson for his work as an
    operator at a rate of $300 per day. The court ordered Boyle Built to pay Benson
    $12,000 for wages, which is not an issue in this appeal.
    8
    Union Pacific to become concerned with Boyle Built’s ability to successfully
    complete projects. After the project, Omaha Track and Union Pacific arranged a
    meeting with Boyle Built to discuss their relationship going forward. Benson was
    asked to attend the meeting, but he declined.
    The performance of Boyle Built on the Gila Bend project led to a drop in
    business. The number of contracts Boyle Built could secure steadily decreased
    over the remaining contract period. In late 2017, Boyle Built lost its railroad-tie-
    contract with Omaha Track.
    II.    Arguments on Appeal
    Benson asserts that the district court erred in denying his breach-of-contract
    claim, arguing substantial evidence does not support the court’s finding that he
    breached the parties’ consulting agreement. Benson also objects to the court’s
    rulings on oral agreements between the parties for the sale of miscellaneous
    equipment.     Boyle Built cross-appeals, contending the district court erred in
    dismissing its counterclaim for “mobilization costs,” arguing substantial evidence
    does not support the court’s finding that Benson was not contractually obligated to
    deliver the grapple trucks to Boyle Built’s first project.
    III.   Standard of Review
    The issues raised on appeal arise out of a breach-of-contract claim. We
    review a breach-of-contract action for correction of errors at law. NevadaCare,
    Inc. v. Dep’t of Hum. Servs., 
    783 N.W.2d 459
    , 465 (Iowa 2010). “The trial court’s
    legal conclusions and application of legal principles are not binding on the
    appellate court.” 
    Id.
     (quotation omitted). However, if district court’s findings of fact
    9
    are supported by substantial evidence the court is bound and will affirm. Iowa
    Mortg. Ctr., L.L.C. v. Baccam, 
    841 N.W.2d 107
    , 110 (Iowa 2013).
    IV.    Consulting Agreement
    A.     Introduction
    The district court found under the consulting agreement Benson had an
    obligation to use his “best efforts” to assist Boyle Built with “retaining and
    expanding business with Omaha Track.” The court found Benson’s best efforts
    “require[d] more than telephone contact,” and Benson’s declination to go to project
    sites was a substantial breach. Therefore, the court found Boyle Built was “not
    required to make further payment for consulting services/‘Earn-Out’/retainage” and
    their “failure to make such payments is not a breach of the contract.”6
    The court found the remaining balance on the asset purchase to be
    $57,624.7 It ruled, “Upon payment of $57,624 by Boyle Built Enterprise to Mark
    Benson, Benson shall transfer the following vehicles and titles to [Boyle Built], free
    of any encumbrance: 2013 Kenworth, 1998 Mack, and 1995 International.”
    B.     Discussion and Analysis
    The contract dictates that payment of retainage to Benson turns on Benson
    not breaching his “Consulting Services Obligations.” To decide Benson’s breach-
    of-contract claim, the district court was required to determine whether Benson had
    6 Retainage under the Omaha Track contract for the two years after the sale of the
    business totaled $238,998.43. Retainage was: $68,714.07 in 2015; $145,951.58
    in 2016; and $24,332.78 in 2017. Boyle Built made retainage payments to Benson
    sporadically as it was released by Omaha Track. At the time of trial, Boyle Built
    had paid Benson $96,052.99 in retainage.
    7 This amount was calculated using the $627,500 asset purchase price less the
    $569,876.26 already paid. Boyle Built stipulated that it owed $57,624 on the
    balance of the contract.
    10
    fulfilled his obligations entitling him to payment of the retainage. The contract
    defines “Consulting Services” as “Mark Benson shall use his best efforts to provide
    . . . consulting and advisory services which [sic] shall assist Buyer with retaining
    and expanding business with Omaha Track.” The relevant provision in the contract
    contemplates a certain minimum number of hours per week of consulting services
    Benson is to provide, but the term is left blank on the contract and the parties never
    set a weekly requirement. The contract does not provide any further explanation
    of Benson’s duties and obligations under the consulting agreement.
    Resolution of the issues before it required the district court to interpret the
    contract and determine the meaning of the words used by the parties.                In
    interpreting a contract, our supreme court has explained,
    The cardinal rule of contract interpretation is to determine what the
    intent of the parties was at the time they entered into the contract.
    Words and other conduct are interpreted in the light of all the
    circumstances, and if the principal purpose of the parties is
    ascertainable it is given great weight.
    Pillsbury Co. v. Wells Dairy, Inc., 
    752 N.W.2d 430
    , 436 (Iowa 2008) (quotation
    marks and citations omitted).     Additionally, whenever reasonable, the parties’
    manifestations of intent “are interpreted as consistent with each other and with any
    relevant course of performance, course of dealing, or usage of trade.” 
    Id.
     (citation
    omitted). Finally, “When the interpretation of a contract depends on the credibility
    of extrinsic evidence or on a choice among reasonable inferences that can be
    drawn from the extrinsic evidence, the question of interpretation is determined by
    the finder of fact.” 
    Id.
    11
    1.     Intention of the Parties
    In determining the intention of the parties related to Benson’s consulting
    services, the district court found it credible that “the intention was for [Benson] to
    go to job sites to assist with the operations, assist with railroad crews (flaggers,
    dispatchers and gangs), and help train Boyle’s employees.” In support of its
    finding, the district court noted Benson’s many years of experience working with
    railroad crews and established relationship with Omaha Track allowed him to get
    rail time with local crews and complete projects promptly. Before the sale of the
    business, Benson and Boyle Built discussed these relationships and agreed the
    relationships would benefit Boyle Built in taking over the business. The court
    characterized Benson’s relationships and experience as a valuable intangible
    asset negotiated by the parties and attributed it to the “trade secrets and know-
    how” identified in the contract. Given Benson’s obligation to expand and retain the
    business, the court found it was the parties’ intent that Benson would dispense his
    experience and relationships by going out to projects, assisting with railroad crews,
    and training Boyle Built’s employees.
    Benson argues the district court’s interpretation is not supported by
    substantial evidence. He argues the parties’ conduct shows they did not intend for
    Benson to come out to the field; they intended only for Benson to be available by
    telephone. When the interpretation of a contract relies on extrinsic evidence, we
    are bound by the findings of fact unless they are not supported by substantial
    evidence. See 
    id.
     We find substantial evidence supports the district court’s
    interpretation.
    12
    Boyle Built was purchasing more than the physical assets of Benson’s
    business. Benson had established a lucrative contract with Omaha Track and
    maintained relationships with railroad employees that made his business
    successful. Before the sale of the business, Andrew accompanied Benson on the
    railroad, where Benson instructed how to perform maintenance on the grapple
    trucks and imparted tricks of the trade to Boyle Built, sharing stories about how he
    had handled local railroad gangs. Andrew testified that when he was purchasing
    the business’s intangible assets, his understanding of the terms “trade secrets”
    and “know how” included,
    Relationships with the railroad, the ability to fit in with gangs, you
    know, knowing that we weren’t union and that they were union. I
    believe that he had personal relationships with gangs, that he had
    buddies out there that were going to treat us better than just
    subcontractors. I believe that he’d been to a lot of these yards and
    jobs before and he knew the intricacies of the yards and where to
    stockpile ties—and that’s what he told me.
    Benson acknowledged that the parties intended for him to transfer these intangible
    assets through his consulting services.
    During their on-going discussions about the prospect of Boyle Built taking
    over Benson’s business, Andrew recalled that Benson “was enthusiastic that we
    were going to spawn this relationship. Me and him were going to go, you know,
    do something really good on the railroad.” It was known that Omaha Track was
    expanding their operations and new opportunities would be presented. Benson
    knew Boyle Built had other lines of business but Andrew testified that Benson told
    him “he would be there to help me fill the gaps when I had to step away.” During
    the first six months of the contract period, Benson came out on two of Boyle Built’s
    projects where he operated a grapple truck and engaged the other employees,
    13
    teaching them how to perform maintenance and instructing them on where to go
    for safety training.
    The circumstances leading up to and surrounding the execution of the
    contract indicate the primary purpose of the consulting agreement was to serve as
    a means for Benson to impart the experience and relationships he developed to
    Boyle Built. Given the contract’s terms obligating Benson to use his best efforts to
    expand and retain the business, the evidence supports that the parties intended
    for Benson to use his experience and relations in the field when requested.
    We do not determine the parties’ conduct after the sale of the business
    demands an alternative interpretation. Benson argues that because Boyle Built
    never gave Benson notice that he breached the consulting agreement, the parties’
    conduct establishes that all that was required of Benson was to be available by
    phone.
    In support of his claim, Benson points to the parties’ text messages and the
    fact “those messages do not contain a single instance of Boyle Built showing
    dissatisfaction with Benson’s consulting work.” Benson relies on Boyle Built’s
    continued acknowledgment of retainage because of Benson and his use of Benson
    as a resource over the contract period.
    While no text messages evidence Boyle Built’s dissatisfaction with
    Benson’s assistance, a majority of the parties’ communications occurred over the
    phone, and other testimony presented at trial suggests that Boyle Built did not feel
    Benson was fulfilling his obligations as the parties intended.
    Andrew testified that Benson’s assistance through the Gila Bend project
    was a “big eye-opener” for him. He stated that after the project, he told Benson,
    14
    “it wasn’t working the way that we talked about. I said it wasn’t what he told me he
    was going to do.” Amy testified that she had “an ongoing discussion” with Andrew
    about the adequacy of Benson’s consulting services. She stated that while she
    continued to keep an accounting of the retainage, by July 2017, she felt Benson
    had not done “the consulting services to earn [the retainage].” When asked why
    Boyle Built continued to pay retainage up until the last payment, Andrew explained,
    Well, for one I wanted to do what I said I was going to do. I wanted
    to take the high ground, and I wanted to ultimately work it out with
    Mark. I wanted to finish the—I wanted to finish this agreement the
    way that we intended to finish it.
    He explained that he continued to call and ask Benson’s advice because he
    wanted to get his money’s worth out of the consulting agreement, even if it was
    just through phone calls.
    While the parties’ conduct is an important factor in determining the parties’
    intent, it must be evaluated within the surrounding circumstances.             See
    Restatement (Second) of Contracts § 202 cmt. g (Am. Law Inst. 1981) (“Conduct
    must be weighed in the light of the terms of the agreement and their possible
    meanings.”). The parties’ intent as found by the district court and their following
    conduct as explained and given context at trial are reasonable and consistent. We
    find the record contains substantial evidence to support the district court’s
    conclusion.
    15
    2.     Breach of Consulting Agreement
    We turn to the district court’s conclusion that Benson breached the
    consulting agreement. Benson had a contractual duty to use his best efforts to
    provide consulting services to expand and retain the business with Omaha Track.
    Substantial evidence supports the district court’s conclusion it was the intention of
    the parties the consulting services would include going to project sites to assist
    with operations, assisting with railroad crews, and training Boyle Built’s employees.
    The parties agree Benson provided satisfactory consulting services during the first
    six months of the contract period. The parties disagree as to whether Benson’s
    performance over the rest of the two years constituted a breach.
    During the first six months, Andrew testified that Benson “came out right
    away, did more than he had to do,” and Amy testified that Benson was “helpful and
    present.” Benson went out to Boyle Built’s first project on the Minnesota-Iowa
    border and operated a grapple truck. He showed Boyle Built employees how to
    do general maintenance on the trucks and told them where to go for safety and
    other maintenance training.     He went out to Boyle Built’s second project in
    Colorado to remedy an issue with rail wheels.          He had “[s]ometimes daily.
    Sometimes weekly” phone calls with employees where he would talk them through
    fixing various equipment.     He communicated frequently with Boyle Built and
    advised on how to navigate the organizational structure of Omaha Track.
    However, after six months, Benson returned to his farm in northern
    Minnesota and never returned to the field to assist on projects, only providing his
    consulting services over the phone. Andrew explained that after the first six
    months,
    16
    [Benson] he went home and started farming, he was available like
    everybody testified via phone. And I was hopeful that he was going
    to get his farming situation under wraps and be able to come back
    out to the field and help ramp it up again. And then, you know, by
    the time Gila Bend hit, it waned. It waned, and his interest and ability
    to help started waning.
    Communication between Benson and Boyle Built declined over the contract
    period. Phone records show the time Benson spent on the phone with Boyle Built
    steadily decreased over the two years and went from roughly 120 hours the first
    six months to twenty-five, seventeen, and eight hours over the next six-month
    periods. Benson acknowledges the decline but attributes it to Boyle Built asking
    less questions “as people became more familiar with the trucks.” Boyle Built
    attributes the decline to becoming “tired of begging him to come and help.”
    In its ruling, the district court noted that Benson provided telephonic services
    over the contract period but found it reasonable that “‘best efforts’ require more
    than telephone contact in these circumstances.” To support its conclusion, the
    district court noted that because Benson did not go out to project sites as
    requested, Boyle Built’s business suffered. The court specifically pointed to the
    Gila Bend project as an example of where Benson’s experience and relationships
    could have facilitated the timely completion of project, and that after the project,
    Boyle Built experienced a significant decline in business. The court found that
    Benson’s “declination to go to a job site did not assist Boyle ‘with retaining and
    expanding business with Omaha Track’ as required under the terms of the
    contract,” and Benson therefore breached the agreement.
    In response to the court’s finding, Benson argues he could fulfill his
    obligations through the services he provided over the phone and his failure to
    17
    assist in the field when requested was not a breach because his presence was not
    actually needed or he had a legitimate reason for declining.
    The Gila Bend project was a significant turning point in Boyle Built’s
    business and the relationship between Benson and Boyle Built. Benson contends
    that he cannot be faulted for the difficulties experienced during the project because
    he offered to assist in the field, but Boyle Built declined. In support of his position,
    Benson points to a text message exchange between himself and Andrew at the
    beginning of the Gila Bend project. Andrew texted Benson, “They’re saying they’re
    [g]oing to do 7[-]8000 ti[es] a day down there.” Benson replies, “Let me know in a
    couple days if you want me to fly down, to run a truck, until Lance gets back.” The
    record of text messages has no response from Andrew. Benson asserts that this
    exchange shows he was willing to come out to the field and assist on the Gila Bend
    project but his offer was declined.
    However, other evidence shows that after this initial offer, Benson was
    asked to assist and he declined. The very next day, on January 5th, Andrew texted
    Benson and inquired, “Are you getting on the conference call?” Benson replied,
    “When is it?”     Andrew replied, “Over.”      Newman and Andrew testified that
    mandatory conference calls were scheduled between Boyle Built, Omaha Track,
    and Union Pacific and Benson’s attendance was requested, but Benson never
    joined the calls. Benson was asked to attend the meeting with upper management
    from Union Pacific and Omaha Track, but again, Benson declined, indicating he
    “was done railroading.”
    Newman testified that during the Gila Bend project, they were short an
    operator on the Walsenburg project and the need “was very urgent.” He asked
    18
    Benson to assist, but Benson texted in response, “I really need to stay home, have
    been laid up, and have cows about to start calving. Can you get by without me?”8
    Following the Gila Bend project, Boyle Built continued to seek Benson’s
    assistance. Boyle Built’s next project was in June 2016 at the “Proviso” yard. The
    yard is in the Chicago area and its proximity to the city presented unique
    challenges, including little space for stockpiling, commuter trains, and pedestrian
    crossings. Benson was familiar with yard and was asked to assist on the project.
    During the project, a new operator was hired, but he needed to be trained and no
    other qualified Boyle Built employee was available. When asked if he would come
    out to the project and train the new employee, Benson stated that he would be in
    Texas for his daughter’s high-school graduation.
    The consulting services Benson did provide during the project over the
    phone were unsatisfactory. The flag man assigned to Boyle Built was known to
    Benson and his former employees as particularly difficult to work with. Boyle Built
    struggled to coordinate rail time and Benson was asked how to handle the issue.
    Benson recommended contacting the flag man’s supervisor but it appears this
    effort led to more issues between Boyle Built and the railroad crews.         It is
    reasonable to conclude that had Benson been at the project site, he could have
    provided his consulting services in a more effective manner.
    8 Andrew responded the next day, “Weather isn’t looking good in Pueblo first part
    of this week anyway. Ya we can manage I think, just need to get that Walsenburg
    project up to snuff.” Benson argues this shows that Benson’s assistance was not
    actually needed. We disagree, Benson had been asked to come out and he
    declined. Boyle Built’s acceptance of Benson’s refusal does not show Benson was
    fulfilling his obligations.
    19
    The issues continued through Boyle Built’s next project in North Platte,
    Nebraska, in late August 2016. One of Boyle Built’s operators was unexpectedly
    called home and Boyle Built needed someone to fill in. Andrew texted Benson,
    “Mark, in a bind and need someone to run the [2000 Kenworth] . . . [a]ny way you
    can run that truck?” Benson responded, “I can’t think of any way I can. In the
    middle of harvest. Wish I could, so I could get some rest.” On other occasions,
    Benson provided responses to Boyle Built’s inquiries, such as “Come park the
    trucks,” “It ain’t gonna work,” and “Just give up.”
    Substantial evidence supports the conclusion Boyle Built sought more
    assistance by Benson during the contract period.         Benson’s experience and
    relationships with local railroad crews and Omaha Track would have proven helpful
    in addressing the issues faced by Boyle Built during the projects. Andrew testified
    that “the big thing” he needed from Benson on the Gila Bend project was where to
    put cars ad that without Benson’s assistance he was forced to “put 120, maybe,
    roughly thousand ties on the ground, which could have went in cars and ultimately
    ended up into a blowup with the railroad and Omaha Track as to why the cars
    didn’t get placed.” The evidence established that without Benson’s assistance the
    business suffered. Union Pacific and Omaha Track sent upper management to
    discuss their relationship with Boyle Built going forward. Andrew testified that
    “there was upper management on both sides [Omaha Track and Union Pacific]
    that got in big trouble over this project.” After the project, Boyle Built had “a big
    red check against us with Omaha Track. We didn’t fulfill our obligations, so it
    was—it was a downward descent for us.” Substantial evidence supports the
    20
    conclusion Benson’s consulting services did not expand and retain business with
    Omaha Track.
    We reject Benson’s argument that because replacement operators were
    eventually found or the projects were eventually completed, he did not breach his
    consulting obligations. The evidence shows that after the Gila Bend project Boyle
    Built’s business suffered and continued to suffer until the end of the contract
    period. The number of contracts Boyle Built could secure steadily declined until
    the end of the year. Boyle Built did not perform any railroad tie removal from
    January to May 2017. Finally, in September 2017, Boyle Built lost its railroad-tie-
    contract with Omaha Track.9
    Substantial evidence supports that under his obligation to use his best
    efforts to expand and retain the business with Omaha Track the parties intended
    for Benson to provide more than telephonic services. Accordingly, we affirm the
    district court’s conclusion that Benson breached the terms of the agreement and
    Boyle Built does not have to pay Benson the remaining retainage pursuant to the
    consulting agreement.
    V.    Agreements Outside of the Contract
    Benson and Boyle Built made various oral agreements not included in their
    contract for the sale of miscellaneous equipment. Benson challenges the court’s
    rulings about the sale of this equipment and requests the district court judgment
    9 The revenues earned by Boyle Built under the Omaha Track contract reflect the
    difficulties experienced by the business. In 2015, from August through December,
    revenue was $687,149.74. In 2016, revenue was $1,459,515.82. In 2017, from
    January to July, revenue was $243,327.80.
    21
    be modified concerning (1) “service trucks,” (2) a “piston pump,” (3) a “stabilizer
    leg and cylinder,” and (4) “used high-rail gear.”
    1.     Service Trucks
    The parties dispute the terms of the oral agreement in regard to the
    purchase/lease of three “service trucks.”        The district court found sufficient
    evidence “the terms of the contract were modified to include the sale of the service
    trucks for $5000 each if Boyle wanted to purchase them. Therefore, Boyle Built is
    not liable for this payment if they choose not to retain the service trucks.” The court
    also ordered, “[Boyle Built] has 30 days to notify [Benson] if they intend to purchase
    the service vehicles or return the same to [Benson]. The purchase price shall be
    $5000 per vehicle and [Benson] shall deliver the vehicle and clear title to defendant
    upon receipt of payment.”
    The parties do not dispute they had an agreement in which Boyle could
    lease the service trucks for one dollar per month and at the end of the two-year
    contract return the trucks or purchase the service trucks for $5000 each. The issue
    raised by Benson on appeal is whether their agreement included a term that if
    Boyle Built does not purchase the service trucks they must be returned in “like-
    kind or better” condition.
    Benson contends the like-kind requirement was always a part of the deal.
    In explaining the agreement, he testified that “I would like them returned in good
    working order at the end of it, at the end of the contract, or they could keep them
    and we could figure the value of $5000 each.” Boyle Built argues the service trucks
    were “a throw-in” to the deal and “I for dang sure didn’t agree to return trucks with
    three, four hundred thousand mile in better or same condition as I found them.
    22
    Every mile after that cost me money.” On September 14, 2017, Andrew texted
    Benson a picture of two of the service trucks and asked, “Do you want these back
    for farm trucks?” Benson replied, “If they are same condition or better,” and “I have
    a surplus of vehicles that need repairs.”
    Benson seeks a modification of the district court judgment concerning the
    service trucks to include a requirement that the trucks be returned to Benson in
    good working condition if Boyle Built does not purchase the trucks.
    “In order to be binding, an agreement must be definite and certain as to its
    terms to enable the court to give it an exact meaning.” Tri–States Inv. Co. v.
    Henryson, 
    179 N.W.2d 362
    , 363 (Iowa 1970) (citation omitted). Upon our review
    we do not find the record establishes the parties’ agreement included a “like-kind”
    requirement. We decline to disrupt the district court’s order in this respect.
    2.     Piston Pump–Poclian Drive Unit
    The parties also dispute the sale of a “piston pump,” which is a component
    of a “poclian drive unit.”10 The contract lists a “poclian drive” unit with a listed value
    of “$12,500 ?”. At the time the contract was entered into the parties agreed Boyle
    Built would receive a poclian drive unit. However, the parties dispute whether the
    poclian drive unit in the contract included the piston pump.
    Boyle Built argues the poclian drive unit listed in the contract represented
    parts Benson already had on hand and certain difficult to acquire parts that Benson
    had already pre-paid for, which included the piston pump. Benson contends the
    pump was not included in the contract because he did not know the value of the
    10The drive unit provides hydraulic power off of the truck’s transmission and is
    used to move the trucks on the rails down the tracks.
    23
    pump at the time, and the parties made a separate agreement outside the contract
    price for the part.
    At trial the invoice for the part was submitted into evidence. The invoice is
    dated June 18, 2015, shortly before the contract was entered into. The part
    shipped July 20 and was delivered to a workshop where Boyle Built eventually
    picked it up. The district court found the invoice undercut Benson’s claim and
    found it credible that the pump was to be included in the contract price.
    We find substantial evidence supports to support the district court’s
    conclusion that the contract included the piston pump.
    3.      Stabilizer Leg and Cylinder
    During the course of the contract, Boyle Built needed a new “stabilizer leg
    and cylinder.”11 Benson acquired the part from another individual in the railroad
    tie removal business, Bob Whitner, and one of Boyle Built’s employee’s picked it
    up.
    Benson asserts that Boyle Built agreed to pay him $1700 for the part, while
    Boyle Built contends he only agreed to “replace it or buy Bob a new one.” Andrew
    texted Benson a picture of a replacement part and stated, “Got this leg for whitner.”
    However, Andrew testified that the replacement leg went missing around the time
    Benson repossessed one of the service trucks and he “feel[s] like the dadgum leg
    was in the service truck that [Benson] took.”12
    11 A stabilizer leg “is a component on the loader that stabilizes the truck so it doesn’t
    tip over.”
    12 In June 2018, Benson repossessed the 2000 Kenworth truck and one of the
    service trucks after not receiving payment for what he believed he was owed. The
    service truck contained railroad equipment and other personal property belonging
    to Boyle Built.
    24
    The district court found that Boyle Built agreed to replace the stabilizer leg
    and noted that Boyle believed it was in the vehicle Benson repossessed. The court
    ordered Benson to return the stabilizer leg to Boyle. Benson argues the court’s
    ruling about the stabilizer leg and cylinder is unclear and it should enter judgment
    in his favor for $1700. We disagree. We find substantial evidence in the record to
    support the district court’s conclusion regarding the stabilizer leg.
    4.     Used High-rail Gear
    Boyle Built received a set of railroad wheels and attachment parts which the
    parties call “used high-rail gear.” The parties do not dispute the value of the
    equipment is $5000. Boyle Built argues the used gear was part of the equipment
    identified in the contract but agreed that if the district court found otherwise, he
    would pay Benson for the equipment.
    The district court’s order states, “At trial, Boyle agreed to make payment of
    following amounts: Used high rail gear: $5000 if the Court determined this wasn’t
    included in the equipment listed. This Court finds the gear was not included in the
    contract.” However, the $5000 amount is not included in the court’s ultimate
    calculation of what is remaining due on the contract. The apparent inconsistency
    was raised in Benson’s Rule 1.904 motion, but the court did not address it.
    Benson argues the court’s ruling about the used high-rail gear is unclear
    and it should enter judgment in his favor for $5000. We agree and modify the
    judgment in this regard.
    VI.    Cross Appeal
    Boyle Built cross-appeals from the district court’s finding that Benson did
    not have to deliver the grapple trucks to Boyle Built’s first project and Boyle Built
    25
    is not entitled to a $12,000 credit toward the purchase price of the contract for the
    expenses paid to mobilize the trucks.
    When the contract was entered into, the grapple trucks purchased from
    Benson were scattered across the country and needed to be “mobilized” to Boyle
    Built’s first project along the Minnesota-Iowa boarder. Boyle Built claims that they
    spent $12,033 to move the equipment to the project. The costs included: “labor;
    miscellaneous costs for repairs to trucks that were not drivable; hotel fees; and fuel
    expenses.”
    One of the grapple trucks was located at the Denver Airport and Boyle Built
    paid to fly an employee out to pick it up and drive it back to the project. However,
    the truck had a cracked rim that needed to be repaired. Another grapple truck, the
    2000 Kenworth, was also in Colorado. While the truck was being mobilized to the
    project site, the truck experienced engine failure making it inoperable.13 The other
    grapple trucks were closer to the project site, at various locations in the Midwest
    and were mobilized successfully. While the 2000 Kenworth truck was being
    repaired, Boyle Built leased another grapple truck from Omaha Track to ensure
    they had the capacity to finish the project.
    The contract does not state who must bear the cost of relocating the
    equipment. The district court found, “The contract is silent on the location of the
    vehicles for delivery from Benson to Boyle. As such, the Court finds that Benson
    13 The repairs cost $23,083.30, and Benson agreed to credit half the cost towards
    the purchase price of the truck, which the parties do not dispute. It does not appear
    this cost was in Amy’s accounting of the $12,033 mobilization costs.
    26
    did not have a contractual obligation to deliver the vehicles to the initial Boyle job
    site.”
    Andrew testified that Benson “was willing to cover whatever costs were his”
    and “he agreed that I’d take possession of the trucks when they got delivered, and
    then I ended up delivering the trucks to myself to—to some extent.”              Amy
    acknowledged that the mobilization costs were something to be worked out
    between Boyle Built and Benson. She acknowledged that she did not include an
    accounting of the cost in the payment records sent to Benson until an email sent
    July 11, 2017.14 Benson responded to the email, “The start-up charge of 12000.00
    is not acceptable, as I believe I paid wages and fuel to Iowa jobsite.”
    As the contract is silent on the matter and the record does not contain
    evidence establishing Benson’s obligation, we find no error in the district court’s
    conclusion.
    VII. Conclusion
    Finding no err in the district court’s determination on the contract breach,
    we affirm. We find under the oral amendments, we reverse the district court ruling
    that fails to award Benson compensation for the used high-rail gear. We remand
    for modification of the judgment by $5000.00 in Benson’s favor.
    AFFIRMED IN PART, REVERSED IN PART, AND REMANDED ON
    APPEAL; AFFIRMED ON CROSS-APPEAL.
    14 Two statements of payments and amounts due sent by Amy to Benson were
    submitted at trial. The dates of which are August 13, 2016, and July 6, 2017. The
    statements do not include a $12,000 mobilization cost.