Gary Hibbeln v. Ken Jordan ( 2021 )


Menu:
  •                      RENDERED: JULY 9, 2021; 10:00 A.M.
    NOT TO BE PUBLISHED
    Commonwealth of Kentucky
    Court of Appeals
    NO. 2020-CA-0991-MR
    GARY HIBBELN                                                         APPELLANT
    APPEAL FROM JEFFERSON CIRCUIT COURT
    v.                HONORABLE OLU A. STEVENS, JUDGE
    ACTION NO. 13-CI-04376
    KEN JORDAN; AND
    KEN JORDAN CONTRACTING, LLC                                           APPELLEES
    OPINION
    AFFIRMING
    ** ** ** ** **
    BEFORE: MAZE, TAYLOR, AND K. THOMPSON, JUDGES.
    MAZE, JUDGE: Gary Hibbeln (Hibbeln) appeals from a judgment of the
    Jefferson Circuit Court dismissing his claims against Ken Jordan and Ken Jordan
    Contractors, LLC (collectively, “Jordan”). This is the third appeal of this case,
    following two prior remands by this Court. We conclude that the “law of the case”
    doctrine precludes Hibbeln from raising issues which were not presented in the
    first appeal. We further conclude that the trial court properly applied the mandate
    of this Court on remand and did not err by denying Hibbeln’s motion to re-open
    the proof for new evidence. Hence, we affirm.
    The relevant facts of this matter were set forth in a prior appeal as
    follows:
    The property at issue is a historic residence located
    at 1308 Highland Avenue, Louisville, Kentucky. Prior to
    Ken Jordan’s involvement, the residence was ordered to
    be demolished; however, the property was spared.
    Hibbeln and his partner on the Highland Avenue project,
    Stayce McCracken, met Jordan who was performing
    insurance claim work at the property to repair a collapsed
    chimney. Based on Jordan’s work, Hibbeln and
    McCracken hired Jordan as the general contractor for
    additional renovations on the residence.
    In June 2010, Jordan submitted a proposal to
    Hibbeln listing several repairs to be made. The cost of
    the individual repairs was not listed, but the total amount
    for all repairs was estimated to be $87,290.00. The
    proposal further provided that payments for the work
    were to be made on a weekly schedule, in accordance
    with the proposal. Hibbeln signed the proposal, and
    payments were made, more or less, according to
    schedule. Hibbeln paid Ken Jordan Contractors a total of
    $85,764.00 under the June 2010 proposal.
    A second proposal was submitted by Jordan to
    Hibbeln in October 2010. The proposal listed ten repairs
    to be completed and a total estimated cost of $5,100.00.
    Hibbeln paid $4,590.00 under the second proposal. In
    all, Hibbeln paid $90,354.00 to Ken Jordan Contractors
    for reconstruction services.
    -2-
    On August 10, 2013, Hibbeln filed a complaint
    against Jordan claiming breach of contract, conversion,
    and bad faith. He sought compensatory and
    consequential damages, attorney fees, and punitive
    damages.
    The matter was set for trial on February 18,
    2016. . . .
    ...
    At trial, several witnesses testified, including Gary
    Hibbeln, Stayce McCracken, home renovation expert
    John Klienholter, architect Mark Bailey, all in addition to
    Ken Jordan.
    The renovation work was initially performed
    without incident. However, according to Hibbeln and
    McCracken, progress slowed considerably, and Jordan
    was no longer coming to the job site to supervise his
    workers. Mark Bailey was hired as the architect on the
    project, but he was terminated when Hibbeln and
    McCracken decided his services were no longer needed.
    As Jordan’s work continued, Hibbeln and McCracken
    became less satisfied. Nevertheless, payments to Jordan
    continued based upon the payment schedule called for in
    the first proposal, without presenting any quality or
    progress complaints to Jordan. Hibbeln and McCracken
    further contended they gave Jordan additional projects in
    the fall of 2010 with hopes to motivate his performance
    on the residence.
    After some attempt to work through the issues with
    Jordan, Hibbeln and McCracken decided to terminate his
    services in early 2011. Another contractor was hired to
    take over the project to fix and complete Jordan’s work.
    Hibbeln testified that he paid $87,239.51 to this other
    contractor to fix Jordan’s work on the residence.
    -3-
    John Klienholter testified as Hibbeln’s expert
    witness. He had twenty-five years’ experience as a
    contractor. He went to the residence and performed an
    inspection. He examined photographs provided by
    Hibbeln of Jordan’s work. Klienholter provided estimates
    for the costs of various line items contained in Jordan’s
    first proposal for a home similar to the subject of this
    litigation.
    At the conclusion of Hibbeln’s case, Jordan moved
    to dismiss his claim for conversion, punitive damages,
    and attorney fees. The court granted Jordan’s motion.
    Jordan followed with his proof, the trial concluded, and
    the case was submitted.
    The Jefferson Circuit Court found the following:
    The Court finds the parties had an agreement and
    that a written contract signed by both parties is
    unnecessary under the circumstances. The Court
    determines that the Defendant was paid in
    accordance with the schedule of payments,
    regardless of whether the work was actually
    performed. There is a conflict in testimony, but
    the Court further determines that the Defendant did
    not complete the work as contemplated by the
    parties’ agreement. The testimony established that
    the following work was completed: Pull building
    back and straighten building, remove existing
    footer, pour new footer/foundation wall, removal
    of existing footer along left side and a portion of
    the sheathing installation. The Court finds that the
    remaining work was not completed or was
    completed in an unsatisfactory manner. Neither
    party was able to testify as to the specific amount
    charged for each task listed on Plaintiff’s exhibits
    one and two, but Plaintiff’s expert, John
    Klienholter, testified as to the costs for each item
    listed on Plaintiff’s exhibit one (1). He
    acknowledged those figures were “ballpark”
    -4-
    estimates. In all, Plaintiff claims he paid
    Defendant about $66,000 for work that was not
    completed or completed in an unsatisfactory
    manner. Based on the testimony, the Court
    determines approximately 50% of the total
    contemplated repairs were either not completed or
    not completed in a satisfactory manner.
    Accordingly, judgment shall be entered for the
    Plaintiff in the amount of $45,000 plus court costs.
    Post-judgment interest shall accrue at 12% per
    annum.
    Jordan v. Hibbeln [Jordan I], No. 2016-CA-000406-MR, 
    2018 WL 3090442
    , at
    *1–2 (Ky. App. Jun. 22, 2018).
    In the first appeal, this Court reversed the judgment for Hibbeln,
    concluding that “Hibbeln failed to provide the court with sufficient evidence to
    determine calculable, non-speculative damages. The lack of evidence renders the
    circuit court’s award of $45,000 in damages erroneous.” 
    Id. at *5
    . Consequently,
    this Court vacated the judgment and remanded, giving the circuit court explicit
    direction to enter a new judgment explaining the non-speculative method used for
    calculating damages and the evidence supporting the award. Specifically, the
    panel directed the circuit court to determine either: “(1) that Hibbeln failed to
    carry his burden of presenting non-speculative proof of his damages, or (2) that
    Hibbeln did carry his burden of presenting non-speculative damages, but that the
    judgment failed to articulate that proof in a way that would facilitate rather than
    frustrate appellate review.” 
    Id. at *6
    .
    -5-
    On remand, the trial court entered a new judgment for Hibbeln for
    $45,000. In a subsequent appeal, this Court again reversed, finding that the trial
    court failed to comply with the Court’s mandate from the prior appeal. Ken Jordan
    & Ken Jordan Contractors, LLC v. Hibbeln [Jordan II], No. 2019-CA-000310-
    MR, 
    2019 WL 6248320
    , at *3 (Ky. App. Nov. 22, 2019). Consequently, the Court
    again remanded the matter for the findings required by Jordan I. 
    Id.
    On the second remand, the trial court entered new findings and a
    judgment. In pertinent part, the trial court found as follows:
    The Court previously determined the Defendant
    [Jordan] did not complete certain tasks as assigned, but
    the conclusion that those tasks amounted to $45,000 is
    speculative. The Plaintiff [Hibbeln] is charged with the
    burden of proving his damages. In this instance, the
    Plaintiff failed to produce evidence of the specific value
    of the various tasks that were not completed or not
    completed to his satisfaction. Plaintiff’s motion to
    supplement the proof in this case is considered and
    denied. The Court determines that the Court of Appeals
    order remanding this matter does not contemplate the
    taking and consideration of further proof, but rather
    instructs this Court [to] review the record and submit
    specific findings on Plaintiff’s claims or find the Plaintiff
    did not carry his burden. The Court finds the latter.
    Based upon this conclusion, the trial court granted a judgment for
    Jordan and dismissed Hibbeln’s complaint. Hibbeln now appeals from this
    judgment.
    -6-
    Hibbeln first argues that the trial court abused its discretion by
    limiting his counsel’s cross-examination of Ken Jordan during trial. In response,
    Jordan notes that Hibbeln’s brief fails to provide any supporting references to
    where this issue was preserved, as required by CR1 76.12(4)(c)(v). Jordan further
    argues that the law of the case doctrine precludes Hibbeln from raising the issue in
    this appeal. We find the latter argument to be dispositive.
    As discussed in Jordan II, the law of the case doctrine designates that,
    if an appellate court has passed on a legal question and remanded the case to the
    court below for further proceedings, the legal determinations may not be revisited
    on a subsequent appeal in the same case. Inman v. Inman, 
    648 S.W.2d 847
    , 849
    (Ky. 1982). An extension of this doctrine also precludes a subsequent appellate
    court from reviewing decisions of the trial court which could have been but were
    not challenged in the prior appeal. Brown v. Commonwealth, 
    313 S.W.3d 577
    , 610
    (Ky. 2010). This rule is not based on the barred issue establishing the law of the
    case, “but instead on the party’s inaction in failing to raise the issue in a manner
    consistent with the court’s general policy against piecemeal appeals. 
    Id. at 610-11
    .
    In the current case, Hibbeln had the opportunity to raise the cross-
    examination issue by means of a protective cross-appeal. However, he failed to do
    so. To the contrary, in his brief in Jordan I, Hibbeln argued that Jordan was not
    1
    Kentucky Rules of Civil Procedure.
    -7-
    prejudiced by the trial court’s limitations on its cross-examination. And this Court
    noted that both parties had agreed to the trial court’s division of time. If Hibbeln
    had some objection to that discretionary decision, he was obligated to raise it in the
    first appeal. Therefore, we agree with Jordan that Hibbeln is now barred from
    raising the same issue in this appeal.
    Hibbeln primarily argues that the trial court abused its discretion by
    denying his motion to present new evidence of damages on remand. In a
    subsequent appeal following a retrial after remand, this Court’s role is limited to
    whether the trial court properly construed and applied the mandate. Inman, 648
    S.W.2d at 849. While the rule does not preclude the taking of new evidence on
    remand in all cases, the trial court must strictly follow the mandate set out in the
    prior appellate decision. Id. See also Buckley v. Wilson, 
    177 S.W.3d 778
    , 781
    (Ky. 2005). Thus, we must look to the basis for this Court’s order of remand in the
    first appeal.
    In Jordan I, this Court found that the trial court’s award of damages to
    Hibbeln was not supported by substantial evidence and was therefore clearly
    erroneous. The Court noted that Hibbeln initially sought to recover the costs he
    had to pay to another contractor to complete the work, and he presented evidence
    at trial supporting that claim. However, he abandoned that claim at trial and only
    sought a refund of monies paid to Jordan for work he failed to perform or
    -8-
    inadequately performed under the proposals. Jordan I, 
    2018 WL 3090442
    , at *5.
    The Court also noted that Hibbeln did not provide any evidence of the specific
    costs incurred for completing any particular item of work provided in the
    proposals. 
    Id.
    In addressing the sufficiency of the evidence, this Court concluded,
    The damage award is not supported by substantial
    evidence and is, therefore, erroneous. Our review of the
    record indicates that the court’s two determinations - the
    number of repair items completed and, subsequently, the
    value of incomplete or unsatisfactory work - are
    inconsistent and neither is supported by evidence in the
    record. The cost of completing half the number of tasks
    listed on the proposals may or may not equate to half the
    amount of money paid, and there was no testimony
    whether it did or did not. The resulting award is not
    derived by assigning a value or cost to any specific tasks
    deemed compensable because they were not completed
    or were unsatisfactorily completed. Nor are such values
    readily determinable from evidence presented at trial.
    There were roughly twenty tasks contained in the first
    proposal and ten included in the second. Without an
    itemization of the costs of the tasks listed in the
    proposals, and even further, a classification of what work
    was completed in full, completed in part, completed but
    not satisfactorily, or not completed at all, damages are
    speculative at best. All damages must be proved to a
    reasonable degree of certainty. [Ford Contracting, Inc.
    v. Kentucky Transp. Cabinet, 
    429 S.W.3d 397
    , 407 (Ky.
    App. 2014)]. There remain too many undetermined
    variables; they are undeterminable on review; and that
    prevents this Court from affirming a damage award.
    
    Id. at *6
    .
    -9-
    However, the panel did not simply conclude that the judgment was
    unsupported by substantial evidence. Instead, the Court remanded, directing the
    trial court make one of two possible findings based on the proof presented. In
    particular, the latter finding permitted the trial court to find that “Hibbeln did carry
    his burden of presenting non-speculative damages, but that the judgment failed to
    articulate that proof in a way that would facilitate rather than frustrate appellate
    review.” 
    Id.
     (emphasis added). When Jordan I is read in its entirety, we conclude
    that this Court remanded the matter for specific findings on a single issue based
    solely on the evidence already in the record. Therefore, the trial court properly
    construed the Court’s mandate as not permitting the introduction of new evidence.
    Accordingly, we affirm the judgment of the Jefferson Circuit Court.
    ALL CONCUR.
    BRIEF FOR APPELLANT:                       BRIEF FOR APPELLEES:
    Robert A. Florio                           J. Fox DeMoisey
    Louisville, Kentucky                       Louisville, Kentucky
    -10-
    

Document Info

Docket Number: 2020 CA 000991

Filed Date: 7/8/2021

Precedential Status: Precedential

Modified Date: 7/16/2021