Young Electrical v. Dustin Construction , 459 Md. 356 ( 2018 )


Menu:
  • Young Electrical Contractors, Inc. v. Dustin Construction, Inc.
    No. 8, September Term 2017
    Contracts – Interpretation – Construction Contracts – Conditional Payment
    Provisions. A contract between a general contractor and a subcontractor on a construction
    project may typically contain a provision that relates the payments to be made by the
    general contractor to the subcontractor to the payments to be made by the project owner to
    the general contractor. In some instances, such provisions are interpreted to govern only
    the timing of the general contractor’s payments to the subcontractor and not the obligation
    of the general contractor to pay the subcontractor. Such provisions are sometimes referred
    to as pay-when-paid clauses. Other provisions include language making the owner’s
    payment of general contractor a condition precedent for the general contractor’s obligation
    to pay the subcontractor and shift the risk of the owner’s non-payment from the general
    contractor to the subcontractor. They are sometimes called pay-if-paid clauses.
    Civil Procedure – Summary Judgment. In a breach of contract case in a Maryland circuit
    court concerning a construction contract governed by Virginia law, the trial court erred as
    a matter of law in awarding summary judgment in favor of a general contractor against a
    subcontractor based upon a pay-if-paid clause in the subcontract because that clause did
    not necessarily apply to the damages sought in the action. Applying Maryland procedural
    law, the Court of Appeals declined to affirm the award of summary judgment on alternative
    grounds, as the trial court would not have been required to award summary judgment on
    the alternative grounds.
    Circuit Court for Montgomery County
    Case No. 381002V
    Argument: October 6, 2017
    IN THE COURT OF APPEALS
    OF MARYLAND
    No. 8
    September Term, 2017
    YOUNG ELECTRICAL CONTRACTORS, INC.
    V.
    DUSTIN CONSTRUCTION, INC.
    _____________________________________
    Barbera, C.J.,
    Greene
    Adkins
    McDonald
    Watts
    Hotten
    Getty,
    JJ.
    ______________________________________
    Opinion by McDonald, J.
    ______________________________________
    Filed: May 24, 2018
    In a typical scenario in the construction industry, the owner of a construction project
    enters into a prime contract with a general contractor to erect or renovate a building. The
    general contractor then enters into subcontracts with suppliers and trade contractors, such
    as plumbers and electricians, to provide materials or to perform portions of the work. For
    various reasons, the owner of the project may later be unable or unwilling to pay the general
    contractor under the prime contract. What this means for the subcontractor depends on the
    terms of its subcontract with the general contractor.
    A subcontract may contain a provision that relates payment of the subcontractor by
    the general contractor to the payment of the general contractor by the project owner. Some
    provisions, sometimes called pay-when-paid clauses, concern the timing of payment by the
    general contractor, but do not relieve the general contractor of its liability to the
    subcontractor under the subcontract. Other provisions, sometimes called pay-if-paid
    clauses, make the project owner’s payment of the general contractor a condition precedent
    of the general contractor’s obligation to pay the subcontractor and thus can relieve the
    general contractor of liability to the subcontractor, even though the subcontractor has fully
    performed its part of the subcontract.
    This case concerns the propriety of an award of summary judgment in favor of a
    general contractor against a subcontractor based on a pay-if-paid clause.                The
    subcontractor, Petitioner Young Electrical Contractors, Inc., sued the general contractor,
    Respondent Dustin Construction, Inc., in the Circuit Court for Montgomery County for
    breach of contract relating to a construction project in Virginia. Applying Virginia law,
    the Circuit Court held that a pay-if-paid provision in the subcontract applied to the damages
    sought in the action, determined that there was no dispute that the owner of the project had
    not paid the general contractor with respect to the matters in issue, and awarded summary
    judgment in favor of the general contractor. The Court of Special Appeals affirmed that
    decision, although for slightly different reasons.
    We hold that the pay-if-paid clause relied upon by the Circuit Court, which was
    cited by neither party in motion papers or argument concerning summary judgment, does
    not necessarily apply to the issues in this case. Moreover, consistent with Maryland law
    concerning review of awards of summary judgment, we decline to seek other reasons to
    affirm the Circuit Court’s decision. Accordingly, we vacate the judgment of the Court of
    Special Appeals and remand the matter to the Circuit Court for further factual development.
    I
    Background
    A.     “Pay - When - Paid” and “Pay - If - Paid” Clauses
    In a typical construction project, the owner of the project contracts with a general
    contractor to carry out the project. The general contractor then enters into contracts with
    various suppliers and trades – the subcontractors – to provide the materials and carry out
    the actual construction. There is no necessary linkage between a subcontractor’s or
    supplier’s entitlement to compensation for performing a subcontract and the owner’s
    performance of its obligations – primarily payment of the general contractor – under the
    prime contract. Thus, in the absence of an agreement to the contrary, a subcontractor that
    has completed its work is entitled to be paid regardless of whether the general contractor
    2
    has been paid by the project owner. See J. Acret & A.D. Perrochet, Construction Litigation
    Handbook 3rd, §4.4.
    During the latter half of the twentieth century, general contractors began to include
    contingent payment provisions in their subcontracts. Although there apparently was no
    standard language, such a clause would typically provide that the general contractor was
    not obligated to pay the subcontractor until some specified number of days after the general
    contractor received payment under the prime contract from the owner of the project. Thus,
    for example, a window distributor that entered into a subcontract to supply windows for a
    project would not necessarily receive payment upon delivery of the windows, but would
    be required to await payment of the general contractor by the owner of the project.
    Such clauses could be viewed as creating two different types of conditions. One
    interpretation of such a clause would view it simply as a timing provision – i.e., it permits
    the general contractor to delay payment of the subcontractor until after it receives payment
    from the owner or (if that does not occur) some other period deemed reasonable, but does
    not relieve the general contractor of its obligation to compensate the subcontractor for its
    work. This interpretation might be viewed as a subcontractor-friendly version of the
    clause, as it considers the provision to govern when, but not whether, the subcontractor is
    to be paid by the general contractor.
    Another interpretation of such a clause would view it as a condition precedent for
    payment of the subcontractor – i.e., if the general contractor is not paid by the project owner
    under the prime contract, then the general contractor is not obligated to pay the
    subcontractor under the subcontract. In such a view, the subcontractor has not only agreed
    3
    to provide materials or to perform work on the project, but is also providing the general
    contractor with a sort of insurance against the risk of non-payment by the owner – a risk
    usually associated with insolvency or bankruptcy of the owner. This might be viewed as a
    general contractor-friendly version of the clause.
    Although the nomenclature used in the case law and legal literature has not been
    consistent, for purposes of this opinion we shall distinguish between these two types of
    clauses by adopting the terminology used in a number of recent cases.1 We shall refer to a
    provision that creates a timing condition as a “pay-when-paid” clause. We shall refer to a
    provision that creates a condition precedent for the obligation to pay as a “pay-if-paid”
    clause.” As is often the case, when there is a dispute as to whether a particular contract
    provision falls into one category or the other, the devil is in the details.
    This case will require us to apply the law of Virginia to construe a subcontract and
    prime contract. To put that law in perspective, we review briefly the evolution of judicial
    treatment of such clauses.
    The Majority Approach
    Under what has frequently been described as the majority approach,2 a court will
    construe such a clause narrowly and interpret it to be a payment timing provision – i.e., a
    1
    See, e.g., Sloan & Co. v. Liberty Mutual Ins. Co., 
    653 F.3d 175
    , 180 (3d Cir. 2011);
    Transtar Elec., Inc. v. A.E.M. Elec. Servs. Corp., 
    16 N.E.3d 645
    , 648-49 (Ohio 2014);
    Lemoine Co. of Alabama v. HLH Constructors, Inc., 
    62 So. 3d 1020
    , 1027 (Ala. 2010); see
    also R.F. Carney & A. Cizek, Payment Provisions in Construction Contracts and
    Construction Trust Fund Statutes: A Fifty-State Survey, 24 Construc. Law. 5 (Fall 2004).
    2
    See, e.g., Galloway Corp. v. S.B. Ballard Const. Co. 
    464 S.E.2d 349
    , 354 (Va.
    1995); see also M. Alsbrook, Contracting Away an Honest Day’s Pay: An Examination of
    4
    pay-when-paid clause – unless the language of the provision clearly and necessarily creates
    a risk-shifting provision – i.e., a pay-if-paid clause.
    The leading case is Thos. J. Dyer Co. v. Bishop International Engineering Co., 
    303 F.2d 655
    (6th Cir. 1962). In that case, a general contractor entered into a subcontract with
    a plumbing subcontractor to install plumbing for a construction project at a race track. The
    plumbing subcontractor provided the services required by the subcontract, but there were
    cost overruns due to additional work requested by the owner and general contractor, some
    of which was outside the scope of the prime contract. When the plumbing subcontractor
    sought payment for the additional work, the general contractor declined because it had not
    been paid by the owner, which had become insolvent and filed for bankruptcy. The general
    contractor relied on language in the subcontract stating “no part of [payment] shall be due
    until five (5) days after Owner shall have paid Contractor[.]”
    The Sixth Circuit observed that the “crucial issue” in the case was “whether … [the
    contract provision] … is to be construed as a conditional promise to pay, enforceable only
    when and if the condition precedent has taken place [i.e., a pay-if-paid provision] … or …
    is to be construed as an unconditional promise to pay with the time of payment being
    postponed until the happening of a certain event, or for a reasonable period of time if it
    develops that such an event does not take place [i.e., a pay-when-paid 
    provision].” 303 F.2d at 659
    .
    Conditional Payment Clauses in Construction Contracts, 58 Ark. L.Rev. 353, 354, 370-72
    (2005); W.M. Hill & D.M. Evans, Pay When Paid Provisions: Still a Conundrum, 18
    Construc. Law. 16 (April 1998).
    5
    While the Dyer court conceded that the expressed intention of the parties ultimately
    governed the interpretation of a particular provision, it observed that courts had generally
    viewed such clauses as timing, rather than risk-shifting, provisions unless the contract
    language clearly indicated otherwise. After reviewing case law in Ohio and Kentucky
    concerning conditional payment clauses, the court concluded that “[t]he tendency of the
    courts is to hold that, unless the contract shows clearly that such an action is an express
    condition, the provision with reference to such act is inserted in order to fix the time of
    performance, but not to make the doing of such act or the happening of such event a
    condition precedent. If this is the intention of the parties, the fact that such act is not
    performed or that such event does not happen, does not discharge the contract, and the act
    which the parties agree to do upon the performance of such act or upon the happening of
    such event, is to be performed in at least a reasonable 
    time.” 303 F.2d at 660
    (internal
    citations and quotations omitted).
    The Dyer court rooted its analysis in its understanding of risk-sharing in the
    construction industry. The court considered it “basic in the construction business” for the
    general contractor to expect to be paid in full because it is “a fundamental concept of doing
    
    business[.]” 303 F.2d at 660
    . Although the “solvency of the owner is a credit risk
    necessarily incurred by the general contractor,” various mechanisms such as installment
    payments and liens are designed to keep those risks to a minimum. The court went on to
    explain that these issues are “even more pronounced in the case of a subcontractor, whose
    contract is with the general contractor, not with the owner.” 
    Id. The court
    observed that,
    while a subcontractor might be dependent on the solvency of the general contractor,
    6
    normally the insolvency of the owner would not defeat the subcontractor’s claim against
    the general contractor. Thus, “in order to transfer this normal credit risk [related to the
    owner] ... from the general contractor to the subcontractor, the [subcontract] should contain
    an express condition clearly showing that to be the intention of the parties.” 
    Id. at 660-61.
    In the case before it, the Sixth Circuit ultimately concluded that the language of the
    subcontract did not indicate that the plumbing subcontractor intended to bear the burden of
    the owner’s insolvency and, accordingly, the appellate court affirmed the trial court’s
    judgment in favor of the plumbing subcontractor. 
    Id. at 661.
    (“To construe [the provision]
    as requiring the subcontractor to wait to be paid for an indefinite period of time until the
    general contractor has been paid by the owner, which may never occur, is to give to it an
    unreasonable construction which the parties did not intend at the time the subcontract was
    entered into.”).
    The majority approach appears to be based, at least in part, on a general principle
    that disfavors construing a contract provision to effect a forfeiture, particularly when the
    condition precedent is outside the control of the party at risk of forfeiture. See Restatement
    (Second) of Contracts, §227(1) (March 2018 update) (“In resolving doubts as to whether
    an event is made a condition of an obligor’s duty … an interpretation is preferred that will
    reduce the obligee’s risk of forfeiture, unless the event is within the obligee’s control or
    the circumstances indicate that he has assumed the risk”). In the context of a subcontract
    for a construction project, this principle favors construing a conditional payment provision
    as a timing provision rather than a risk-shifting provision. 
    Id., illustration 1
    (describing
    example apparently based on Dyer case).
    7
    Pay-if-Paid Clause as against Public Policy
    In some jurisdictions there is more than a preference for construing conditional
    payment clauses as timing provisions. In those jurisdictions, there is a view that the transfer
    of risk effected by a pay-if-paid clause in a construction subcontract is contrary to public
    policy. At least two state courts have held that such a clause, even if explicitly set out in a
    subcontract, is void as against public policy. See West-Fair Elec. Contractors v. Aetna
    Cas. & Sur. Co., 
    661 N.E.2d 967
    , 970 (N.Y. 1995) (holding that pay-if-paid clause was
    inconsistent with state legislature’s enactment of mechanic’s lien statute to protect “those
    who furnish work, labor and services or provide materials for the improvement of real
    property”); William R. Clarke v. Safeco Ins. Co., 
    938 P.2d 372
    , 373-74 (Cal. 1997) (citing
    West-Fair and stating similar rationale); but see Superior Steel, Inc. v. Ascent at Roebling’s
    Bridge, LLC, 
    540 S.W.3d 770
    , 785-87 (Ky. 2018) (declining to adopt public policy
    rationale in light of state’s long tradition of freedom of contract).        In addition, the
    legislatures in several states have enacted statutes declaring such clauses to be void. See
    R.F. Carney & A. Cizek, Payment Provisions in Construction Contracts and Construction
    Trust Fund Statutes: A Fifty-State Survey, 24 Construc. Law. 5 (Fall 2004); M. Alsbrook,
    Contracting Away an Honest Day’s Pay: An Examination of Conditional Payment Clauses
    in Construction Contracts, 58 Ark. L.Rev. 353, 379-83 (2005).
    Maryland Case Law
    Although the contract in this case is not governed by Maryland law, the Virginia
    Supreme Court has referenced Maryland law in its own analysis of conditional payment
    8
    clauses. In order to fully understand Virginia law, it is useful to review the Maryland
    decisions on which it is partly based.
    This Court has relied upon, and quoted at length from, the Dyer decision in resolving
    a payment dispute between general contractor and a subcontractor when a project owner
    has not fully paid the general contractor. See Atl. States Const. Co. v. Drummond & Co.,
    
    251 Md. 77
    , 81-84 (1968); Fishman Constr. Co. v. Hansen, 
    238 Md. 418
    , 422-23 (1965).
    Consistent with Dyer, this Court has stated that such provisions are to be construed as
    timing provisions – pay-when-paid clauses – unless the contract language clearly indicates
    that the parties intended otherwise.
    In a decision later relied upon by the Virginia Supreme Court, the Court of Special
    Appeals considered what language would suffice to shift the risk of owner insolvency from
    the general contractor to the subcontractor. Gilbane Bldg. Co. v. Brisk Waterproofing Co.,
    
    86 Md. App. 21
    (1991). In that case, a masonry subcontractor had completed all of the
    work required under its subcontract on a residential condominium project. The general
    contractor refused to make the final payment that was due to the subcontractor because the
    general contractor had not received a payment from the project owner. After the masonry
    subcontractor’s mechanic’s lien on the property had been extinguished as a result of the
    project owner’s bankruptcy, the masonry subcontractor sued the general contractor for
    payment.
    In declining to pay the masonry subcontractor, the general contractor had relied on
    a subcontract provision which stated, in pertinent part, that “[i]t is specifically understood
    and agreed that the payment to the trade contractor is dependent, as a condition precedent,
    9
    upon the construction manager receiving contract payments, including retainer from the
    
    owner.” 86 Md. App. at 25
    (emphasis added in original). The Court of Special Appeals
    concluded that the reference in the subcontract to owner payment as a “condition
    precedent” was sufficient to shift the risk of owner insolvency to the masonry subcontractor
    as a matter of objective contract interpretation, regardless of whether the parties had
    actually discussed the risk of owner insolvency during their negotiations. 
    Id. at 28.
    Virginia Case Law
    In 1995, the Virginia Supreme Court addressed for the first time the distinction
    between pay-when-paid and pay-if-paid clauses and whether a particular subcontract
    provision shifted the risk of owner default from the general contractor to the
    subcontractors. Galloway Corp. v. S.B. Ballard Const. Co., 
    464 S.E.2d 349
    (Va. 1995).
    That case arose from the construction of a commercial office complex in downtown
    Norfolk, Virginia. The general contractor had entered into various subcontracts with
    suppliers of labor and materials, all of which contained a provision stating that “[t]he
    Contractor shall pay the Subcontractor each progress payment within three working days
    after the Contractor receives payment from the 
    Owner.” 464 S.E.2d at 352
    (emphasis
    added in original). Each subcontract contained similar language with respect to the final
    payment due to each subcontractor. 
    Id. Work had
    progressed on the project for nearly two years, when the project owner
    encountered financial difficulties in the midst of construction. After the owner failed to
    make three progress payments to the general contractor, construction stopped and lawsuits
    
    began. 464 S.E.2d at 352
    . The subcontractors recovered some of the compensation due
    10
    them through the satisfaction of mechanic’s liens on the project, and sought to recover the
    remainder through a breach of contract action against the general contractor. The general
    contractor relied on the payment clause to defend itself from the subcontractors, arguing
    that it was not liable to the subcontractors because it had not been paid by the owner. 
    Id. at 353.
    The trial court ruled in favor of the subcontractors, concluding that the payment
    clause in the subcontracts concerned the timing of payment and did not relieve the general
    contractor of its liability to the subcontractors.
    On appeal, the Virginia Supreme Court came to a more nuanced conclusion. It
    discussed the Dyer case at some length and opined that the Sixth Circuit decision was
    “sound and in concert with traditional notions of the freedom to 
    contract.” 464 S.E.2d at 354
    . It regarded the Dyer case as dealing with contract language that, on its face,
    reasonably contemplated eventual payment of the subcontractor. The Virginia court
    contrasted the contract language in Dyer with that in Court of Special Appeals’ Gilbane
    decision, which it regarded as an equally clear example of an instance in which the parties
    intended to establish a condition precedent to the general contractor’s liability. 
    Id. In the
    case before it, however, the Virginia Supreme Court concluded that the
    contract language was not as clear as in either Dyer or Gilbane. The Court said “there is
    no additional language here which would permit us to find that the parties contemplated
    payment ‘within a reasonable time[,]’” as it understood the provision in Dyer. Unlike
    Gilbane, “nothing in the contracts would permit us to find ... that the parties clearly
    understood these terms to assert a condition precedent on 
    payment.” 464 S.E.2d at 355
    .
    As a result, the Virginia Supreme Court concluded that “the phrases ‘after the Contractor
    11
    receives payment from the Owner’ and ‘has received payment from the Owner’ constitute
    latent ambiguities in the contracts.” 
    Id. Because the
    clauses were latently ambiguous, the
    court relied on parol evidence to determine the intent and understanding of the parties. It
    concluded that the general contractor had intended to create a pay-if-paid clause and then
    assessed the testimony of the various subcontractors at trial as to whether each had the
    same understanding. The court ultimately concluded that four of the five subcontractors
    shared the general contractor’s understanding of the clause and that the clause was a basis
    for the general contractor’s defense as to the claims of those subcontractors. It therefore
    reversed the trial court’s ruling as to those subcontractors and upheld the judgment in favor
    of the fifth subcontractor. 
    Id. at 356.
    Summary
    While a minority of jurisdictions regard pay-if-paid clauses as void as against public
    policy, the majority approach is to recognize both “pay-when-paid” and “pay-if-paid”
    clauses, with some preference given to construing such a clause as a timing rather than a
    risk-shifting provision. To distinguish one from the other under Virginia law, a court is to
    look first to the language of the provision. If the language appears to contemplate that the
    subcontractor will ultimately be paid, the provision will be construed as a pay-when-paid
    clause. If the contractual language clearly sets forth owner payment as a condition
    precedent to the general contractor’s liability to the subcontractor, as in Gilbane, it will be
    construed as a pay-if-paid clause. If the language contains a latent ambiguity, the court
    looks to parol evidence to determine the intent of the parties.
    12
    B.     Facts and Proceedings
    The record in this case discloses the following facts, which are in many respects
    undisputed, and the resulting legal proceedings that have led to this appeal.
    The Prime Contract
    This case arose out of a construction project undertaken by George Mason
    University (“George Mason” or “Owner”), a Virginia state university located in Fairfax,
    Virginia, to renovate a student union building (the “Project”). On July 20, 2010, George
    Mason contracted with Dustin Construction Inc. (“Dustin” or “Contractor”), a general
    contractor based in Ijamsville, Maryland, to conduct the renovation (“the Prime Contract”).
    The Prime Contract consisted of a three-page document setting out the particulars of the
    Project that was signed by representatives of George Mason and Dustin. That document
    incorporated various other documents, including a 49-page form attachment setting forth,
    in 50 multi-part sections, standard general contract terms approved by the Virginia
    Department of General Services for state government construction contracts.3
    A few days later, on July 30, 2010, George Mason issued a “Notice to Proceed” with
    the Project to Dustin. Although the Prime Contract stated a “Substantial Completion” date
    of November 15, 2010,4 the Notice to Proceed set forth a substantial completion date of
    November 30, 2010. The record does not explain this discrepancy.
    3
    While the record includes a copy of the standard Virginia procurement terms and
    conditions, it does not include the various other documents that were incorporated in the
    Prime Contract.
    4
    Under the standard Virginia state contract terms, “Substantial Completion” – as
    distinct from “Final Completion” – means “[t]he condition when the Owner agrees that the
    13
    The Electrical Subcontract
    To accomplish certain electrical work required under the Prime Contract, Dustin
    subcontracted with Young Electrical Contractors Inc. (“Young” or “Subcontractor”), an
    electrical subcontractor based in Laurel, Maryland, to perform that work. Dustin gave
    Young notice to proceed as a subcontractor on August 5, 2010, although Dustin and Young
    did not enter into a written contract until October 15, 2010 (“the Subcontract”).5 The
    Subcontract provided that Dustin would pay Young $1,148,860 for satisfactory completion
    of the work required by the Subcontract. Subcontract, §2.
    The written Subcontract included a section concerning change orders. Subcontract,
    §13. That section defined a change order as “a written order … signed by the Contractor
    … authorizing a change in the Work or an adjustment in the Subcontract Sum or
    Subcontract Time.” Among other things, that section provided that the Subcontract Sum
    or Subcontract Time could be changed only by a change order and permitted the
    Subcontractor to request an “equitable adjustment” of the Subcontract Sum or Subcontract
    Time via change order. Subcontract, §13(a), (c).
    Work, or a specific portion thereof, is sufficiently complete, in accordance with the
    Contract Documents, so that it can be utilized by the Owner for the purposes for which it
    was intended….”
    5
    The parties appear to agree that the Subcontract was entered into on October 15,
    2010 – and the Subcontract itself recites that it was “made as of October 15, 2010” –
    although a number of later dates appear on the document. The written Subcontract was
    stamped as “entered” with a date of December 29, 2010. Young’s representative
    apparently signed the written contract on December 10, 2010; Dustin’s representative
    executed it on December 22, 2010.
    14
    As we shall see, the Subcontract also contained three provisions that might be
    considered conditional payment clauses of one kind or another and that have played a
    prominent role in this litigation. Subcontract, §§2(c), 13(c), 27(f).
    Delay and Change Requests
    Young’s work on the Project was not substantially completed until March 8, 2011,
    three months beyond the substantial completion date (November 30, 2010) set by George
    Mason in the Notice to Proceed. The record is not clear on the precise cause or causes of
    the delay or the extent to which it involved only electrical work or other aspects of the
    Project.
    As permitted under the Subcontract, Young submitted change requests to Dustin
    based on increased costs. In those change requests, Young asked Dustin to issue change
    orders increasing the Subcontract Sum by specified amounts. It appears from the record
    of this case that the Subcontract Sum was increased from the original $1,148,860 for
    various reasons that Young described in one of its change requests as “owner initiated due
    to design changes, design errors, unforeseen conditions and additions/deletions of the work
    originally required.”    According to Young, these changes resulted in “excessive
    management time by the project management team, a constant interruption in the job flow,
    lower labor productivity, an excessive amount of rework of work already installed, plus a
    serious negative cash flow due to the changes needed to be negotiated but the work being
    needed as the contract work was being installed.” As a result, the Subcontract Sum was
    apparently increased by $317,193.
    15
    Two change requests submitted by Young that did not result in changes to the
    Subcontract Sum are at issue in this case: Change Request 1066 and Change Request
    1067.6
    Young submitted Change Request 1066 to Dustin on September 14, 2011. That
    change request asked Dustin to issue a change order increasing the Subcontract Sum by
    $259,034.99 for “extended overhead costs associated with [George Mason]’s extension of
    the contract” past the original substantial completion date. Attached to the change request
    was a listing of various overhead expenses comprising the change request. It is not clear
    from the record whether Dustin responded to Young contemporaneously in any way. More
    than a year later, on November 16, 2012, Dustin submitted Change Request 1066 to George
    Mason along with Dustin’s own delay claim.7         At George Mason’s request, Dustin
    subsequently separated Change Request 1066 from Dustin’s own claim, reduced the
    amount requested in Young’s Change Request 1066 to $180,010.21, and resubmitted it to
    George Mason on March 4, 2013 – denominated as Dustin’s Proposed Change Order 135.
    On February 15, 2013, Young submitted Change Request 1067 to Dustin. In that
    change request, Young asked Dustin to issue a change order increasing the Subcontract
    Sum by $274,812.33 for additional costs associated with delay and disruption, among other
    6
    A third change request, denominated Change Request 1047, was originally at issue
    in this case, but was resolved when Dustin paid Young the amount requested in February
    2014 while this case was pending in the Circuit Court.
    7
    The record does not indicate why Dustin delayed submitting this proposal to
    George Mason or whether it informed Young when it submitted the proposed change order.
    16
    reasons, which, Young said, were not attributable to Young. Attached to the change
    request was a breakdown of Young’s costs and a narrative description of the causes of
    those costs.   The narrative included the description quoted above concerning prior
    approved increases in the Subcontract Sum. The narrative went on to describe issues with
    sequencing the work, requests for information, changes to the work, excessive down time,
    and lack of negotiation. Again, it is not clear from the record whether Dustin responded
    directly to Young concerning Change Request 1067. However, approximately a month
    later, on March 19, 2013, Dustin submitted its Proposed Change Order 136 to George
    Mason, which incorporated Young’s Change Request 1067. Again, it is not clear from the
    record what, if any, information Dustin shared with Young concerning this submission.
    Young sues Dustin
    Five months later, on September 3, 2013, while the two change requests were
    apparently still pending with George Mason, Young filed a complaint against Dustin in the
    Circuit Court for Montgomery County. The complaint consisted of a single count alleging
    that Dustin had breached the Subcontract.
    Young’s complaint asserted that Dustin was responsible for “scheduling and
    sequencing of the trades” and for administration of the Prime Contract with George Mason,
    that Dustin had directed Young to perform additional work, and that Young was not
    responsible for the delay in achieving substantial completion of the work. Young further
    alleged that, because of the delays in the Project, Young had been directed to work overtime
    and had incurred additional costs. Young further contended that it had submitted its claims
    arising from the additional work to Dustin, that Dustin was required by the Subcontract to
    17
    submit the claims to George Mason “if [Dustin] considered that the claims arose due to
    [George Mason]’s actions or inactions,” that there was no indication that Dustin had
    submitted the claims to George Mason, and that Dustin had therefore waived the right to
    assert that the claims were not its own responsibility. The complaint concluded that Dustin
    had breached the Subcontract by (1) failing to coordinate and sequence the work, (2)
    directing additional work and overtime that it failed to pay for, and (3) not paying the costs
    of the extended period of contract performance.
    George Mason Rejects Change Request 1066
    On September 17, 2013, shortly after Young’s complaint had been filed, George
    Mason rejected Dustin’s Proposed Change Order 135, which incorporated Young’s
    Change Request 1066. There appears to be some dispute, or at least uncertainty, as to
    whether George Mason also rejected Change Request 1067 at the same time. In the Circuit
    Court, Dustin submitted an affidavit of its project manager stating that George Mason
    rejected Change Request 1067 at the same time it rejected Change Request 1066, but the
    documentation submitted together with the affidavit does not appear to support that
    statement.8 In any event, there appears to be no dispute that Dustin was not paid by George
    8
    At the hearing in the Circuit Court, Dustin’s counsel stated that Dustin had
    “bundled” Change Request 1066 and Change Request 1067 into one proposed change order
    – 136 – which George Mason rejected. However, from the documents submitted in
    connection with the summary judgment motion, it appears that Dustin submitted two
    separate proposed change requests to George Mason – 135 and 136 – corresponding to
    Young’s change requests and that one – 135 – was rejected by George Mason. It is perhaps
    also notable that other statements made in the project manager’s affidavit – that Young had
    not provided notice that it would submit change requests – were retracted by Dustin when
    Young submitted documentation that it had in fact given notice. For its part, Young
    contended that George Mason’s rejection – whatever it covered – did not constitute a
    18
    Mason with respect to its proposed change orders based on Young’s Change Requests 1066
    and 1067. It is also undisputed that Dustin did not pay Young the amount sought in either
    of those change requests.
    Dustin’s Motion for Summary Judgment
    On October 21, 2013, one and a half months after this action had commenced and
    one month after George Mason rejected Dustin’s proposed Change Order 135, Dustin filed
    a motion for summary judgment together with its answer to the complaint. In its summary
    judgment motion, Dustin argued that its “core, dispositive defense” was that Young had
    failed to make its claims on a timely basis. Dustin quoted §13(c)9 of the Subcontract
    concerning changes. In particular, it argued that Young had failed to comply with notice
    requirements that the Virginia Supreme Court had held were to be strictly construed.
    Dustin initially submitted a supporting affidavit attesting, in part, to a lack of notice, but
    later retracted that testimony. Ultimately, the Circuit Court did not resolve the case on the
    timeliness of notice issue raised by Dustin and that issue is not before us.
    Quoting the same provision of the Subcontract, Dustin also argued that it was not
    liable to Young for the amounts sought in the two change requests because George Mason
    “denial” under §47 of the standard Virginia government conditions incorporated in the
    Prime Contract. Given our disposition of this appeal, the questions as to whether, when,
    and how George Mason rejected the two change requests can be sorted out during
    discovery after remand.
    9
    In the memorandum accompanying its motion, Dustin repeatedly cited §13(a), but
    it is clear from its argument and the quotation in its memorandum that it was actually
    referring to §13(c) of the Subcontract.
    19
    had denied its proposed change orders based on those requests and thus a condition
    precedent for Dustin’s liability to Young – payment by George Mason – was not satisfied.
    Section 13(c) of the Subcontract states:
    In the event a change is made to this Contract as a result of the Owner’s
    change to the Prime Contract and such change causes an increase or
    decrease in the cost of and/or the time required for performance under
    this Subcontract, Subcontractor may submit to Contractor in writing in
    accordance with the requirements of the Changes Clause of the General
    Contract a request for an equitable adjustment in the Subcontract Sum
    and/or the Subcontract Time, or both, within ten (10) calendar days
    from the date of receipt by Subcontractor of notification from
    Contractor of the change or such lesser time as is required to permit
    Contractor to comply with the terms of the Prime Contract. Contractor
    shall pay to Subcontractor that amount paid by the Owner to Contractor
    on account of any such change to this Subcontract, less any markup and
    other amounts due Contractor on account of such change. Contractor
    shall have no liability to Subcontractor on account of any such Owner
    initiated change except for such amount, if any.
    Dustin pressed a similar argument under §27(f) of the Subcontract, which is entitled
    “Resolution of Disputes Involving Owner.” Section 27(f) states:
    Contractor shall have no liability to Subcontractor on account of any
    claim, suit or appeal arising under or relating to the Prime Contract or
    the Owner’s conduct thereunder except that recovered by the
    Contractor from the Owner on Subcontractor’s behalf, if any, less any
    markups and other amounts due Contractor on account of such claim,
    suit or appeal.
    Although neither clause contains the phrase “condition precedent,” in Dustin’s view, the
    two provisions of the Subcontract nevertheless functioned as risk-shifting provisions – pay-
    20
    if-paid clauses – and conditioned its liability to Young on Dustin’s receipt of payment from
    George Mason.10
    The Circuit Court Awards Summary Judgment
    On January 22, 2014, prior to any discovery in the case, the Circuit Court held a
    hearing at which it heard legal argument on Dustin’s summary judgment motion. At the
    hearing, Dustin relied primarily on its argument that Young’s claims were precluded by
    §13(c) of the Subcontract. Young countered that discovery was necessary before it could
    be said that it was undisputed that the claims were the result of changes initiated by George
    Mason.
    The Circuit Court took the matter under advisement that day, and delivered an oral
    decision at a continuation of the hearing on February 11, 2014. In its oral opinion, the
    Circuit Court explained that its review of the record demonstrated that Dustin had
    submitted both change requests to George Mason. In addition, the court held that summary
    judgment in Dustin’s favor was appropriate because George Mason had not paid Dustin
    for either request. The Circuit Court did not attempt to resolve whether George Mason had
    rejected the second proposed change order (involving Young’s Change Request 1067).
    The court said that it was irrelevant to its determination whether or not George Mason had
    actually denied both change requests as Dustin had not received payment for them from
    George Mason.
    10
    Dustin also asserted that Young had not followed the Subcontract’s dispute
    resolution process. That issue was not ruled on below, and is not before us.
    21
    The Circuit Court’s decision was based not on §13(c) or §27(f) of the Subcontract
    – the provisions on which Dustin had based its summary judgment motion – but rather on
    §2(c) of the Subcontract and §37(a)(1) of the standard Virginia terms incorporated in the
    Prime Contract between George Mason and Dustin. (Neither party had mentioned §2(c)
    of the Subcontract or §37(a)(1) of the standard conditions in their motion papers or
    addressed those provisions at oral argument.)
    Section 2(c) of the Subcontract reads, in pertinent part, as follows:
    Contractor’s obligation to pay all or any portion of the Subcontract Sum
    to Subcontractor, whether as a progress payment, retainage or final
    payment, is contingent, as a condition precedent, upon the Contractor’s
    receipt of payment from the Owner of all amounts due Contractor on
    account of the portion of the Work for which the Subcontractor is
    seeking payment.
    Subcontract, §2(c) (emphasis added). As is evident, that subsection of the Subcontract
    contains the magic phrase “condition precedent” that the Virginia Supreme Court had
    declared in Galloway to be a clear expression of a risk-shifting pay-if-paid clause.
    The other provision cited by the Circuit Court – Section 37(a)(1) of the standard
    conditions incorporated in the Prime Contract between George Mason and Dustin – is one
    of the standard terms in Virginia state government contracts. It references a Virginia
    statute11 that requires a contractor in a Virginia state contract to pay a supplier or
    subcontractor within seven days of receiving payment from the owner of a project or to
    notify the state agency and the supplier or subcontractor why payment is being withheld.
    11
    Virginia Code, §2.2-4354.
    22
    The Circuit Court signed a written order granting summary judgment in favor of
    Dustin that same day. Young moved for reconsideration, which the Circuit Court denied
    on April 3, 2014. Young timely noted its appeal.
    The Court of Special Appeals Affirms
    On October 3, 2016, the Court of Special Appeals affirmed the Circuit Court’s grant
    of summary judgment in an unreported opinion. Like the Circuit Court, the intermediate
    appellate court relied on §2(c) of the Subcontract, but also referred to §13(c) and §27(f) –
    the provisions pressed by Dustin – after it concluded that there was no dispute that George
    Mason had initiated the changes for which Young sought payment. At the request of
    Dustin, the Court of Special Appeals re-issued its decision on December 28, 2016, as a
    reported opinion. 
    231 Md. App. 353
    (2016). The reported opinion was identical to the
    original version of the opinion with the addition of a footnote that stated the Subcontract
    provided a mechanism under which Young could have pursued compensation directly from
    George Mason instead of Dustin, if it had acted within six months of the denial of its change
    
    requests. 231 Md. App. at 359
    n.4. The court cited §27 of the Subcontract and §47 of the
    standard Virginia state government contract terms in the Prime Contract in reaching this
    conclusion. Before us, both Dustin and Young agree, although for different reasons, that
    the analysis in this footnote is an incorrect interpretation of the contracts under Virginia
    law. In any event, the footnote in the Court of Special Appeals opinion appears to be dicta,
    unnecessary to its resolution of the case.12
    12
    At oral argument before us, Dustin suggested alternative ways that Young could
    have pursued claims against George Mason. The merits of Dustin’s suggestions are not
    23
    In its decision, the intermediate appellate court held that that there was no dispute
    as to any material fact, that all three payment provisions of the Subcontract were valid, and
    that they justified Dustin’s refusal to accept Young’s change requests. The intermediate
    appellate court first agreed with the Circuit Court that §2(c) was a pay-if-paid clause that
    made payment by George Mason to Dustin under the Prime Contract a condition precedent
    to payments by Dustin to Young under the 
    Subcontract. 231 Md. App. at 363-64
    .
    However, it held that §13(c) was the payment provision “most relevant” to the current
    dispute and construed the language of §13(c) and §27(f), when read alone, to be pay-when-
    paid clauses similar to the provision at issue in Dyer rather than pay-if-paid provisions. 
    Id. at 364-65.
    However, the intermediate appellate court reasoned that any payments covered
    by those provisions were also subject to the condition precedent set forth in §2(c), a pay-
    if-paid clause. 
    Id. at 365-66.
    Accordingly, the Court of Special Appeals affirmed the
    Circuit Court’s grant of summary judgment.
    Young filed a petition for a writ of certiorari, which we granted on April 4, 2017.13
    currently before us and, accordingly, we do not attempt to resolve whether Young could
    have pursued an alternative procedure under Virginia law for asserting its claims.
    13
    Young originally sought a writ of certiorari on October 28, 2016. After we denied
    that petition, Young renewed its request when the Court of Special Appeals re-issued its
    decision as a reported opinion.
    24
    II
    Discussion
    The question before us is whether the Circuit Court properly granted summary
    judgment based on its determination that there were no disputed questions of material fact
    and that Dustin was entitled to judgment as a matter of law under the court’s construction
    of the Subcontract in conjunction with the Prime Contract.14
    A.     Governing Law and Standard of Review
    1. Applicable Substantive Law
    Contract interpretation is governed by the law of the place of contract or the law
    chosen by the parties.     Cunningham v. Feinberg, 
    441 Md. 310
    , 326 (2015).             The
    Subcontract here explicitly provides that it is to be governed by Virginia law. Subcontract,
    §31. The Prime Contract also explicitly incorporates various requirements imposed by
    Virginia statutes and regulations concerning Virginia state government procurement.
    Virginia courts “review issues of contract interpretation de novo.”        Bailey v.
    Loudoun Cty. Sheriff’s Office, 
    762 S.E.2d 763
    , 766 (2014). Like Maryland law, Virginia
    law applies an objective interpretation of a contract to discern what the parties intended.
    Virginia courts assume that each provision of a contract has a purpose, and must be read in
    context harmoniously with the other provisions. See, e.g., TravCo Ins. Co. v. Ward, 736
    14
    Young raised several other issue in its petition for certiorari, which we need not
    address, in light of our decision on this question.
    
    25 S.E.2d 321
    , 325 (Va. 2012). In interpreting contracts, the Virginia Supreme Court has
    stated:
    It is the function of the court to construe the contract made by the parties,
    not to make a contract for them. The question for the court is what did the
    parties agree to as evidenced by their contract. The guiding light in the
    construction of a contract is the intention of the parties as expressed by them
    in the words they have used, and courts are bound to say that the parties
    intended what the written instrument plainly declares.
    W.F. Magann Corp. v. Virginia-Carolina Electrical Works, Inc., 
    123 S.E.2d 377
    , 381 (Va.
    1962) (citations omitted); see also Wilson v. Holyfield, 
    313 S.E.2d 396
    , 398 (Va. 1984) (“It
    is the duty of the court to construe a contract as written.”).
    2. Applicable Procedural Law
    Although we look to another state’s substantive law, the standard for summary
    judgment is governed by the law of the forum – in this case, Maryland law. Goodwich v.
    Sinai Hosp. of Baltimore, Inc., 
    343 Md. 185
    , 204-207 (1996).
    Under the Maryland Rules, a circuit court may grant summary judgment only if
    there is no genuine dispute as to any material fact, and the moving party is entitled to
    judgment as a matter of law. Maryland Rule 2–501(f). The court is to consider the record
    in the light most favorable to the non-moving party and consider any reasonable inferences
    that may be drawn from the undisputed facts against the moving party. Mathews v. Cassidy
    Turley Maryland, Inc., 
    435 Md. 584
    , 598 (2013). Because the circuit court’s decision turns
    on a question of law, not a dispute of fact, we review a circuit court’s decision to grant
    summary judgment without according deference to the circuit court’s conclusions, or those
    of the intermediate appellate court. 
    Id. 26 If
    we should reach a different conclusion than the circuit court on the basis on which
    it granted summary judgment, we ordinarily do not try to sustain the circuit court’s decision
    on a different ground. 
    Mathews, 435 Md. at 598
    . Such a course would interfere with the
    discretion that a trial court normally enjoys to deny, or defer until trial, the merits of
    summary judgment on a particular issue. 
    Id. We may
    nonetheless affirm summary
    judgment on a different ground if the trial court would have no discretion as to the particular
    issue. 
    Id. B. Whether
    Dustin was Entitled to Summary Judgment
    At the outset, we must confess that much in this case has left us scratching our head.
    To recap, Dustin initially sought summary judgment primarily on Young’s alleged failure
    to give timely notice of its claims, later switched its flagship contention to the apparent
    decision of George Mason not to accept the change requests (a decision not fully
    documented in this record), and relied on §13(c), and to a lesser extent §27(f), as risk-
    shifting pay-if-paid clauses. The Circuit Court ruled in Dustin’s favor, although not on the
    basis of the Subcontract provisions cited by Dustin, but rather on the basis of §2(c) of the
    Subcontract (a pay-if-paid clause), and §37(a)(1) of the standard Virginia conditions
    incorporated in the Prime Contract, neither of which had been mentioned by either party in
    the papers or argument on Dustin’s summary judgment motion. The Court of Special
    Appeals, attempting to bridge this gap as best it could, affirmed on the basis of the
    provisions urged by Dustin (although it construed them to be pay-when-paid provisions),
    as well as those cited by the Circuit Court, and suggested that Young should have sued
    George Mason directly under §27 of the Subcontract and §47 of the standard conditions in
    27
    the Prime Contract – a suggestion that both Dustin and Young agree is an incorrect
    interpretation of the contracts.
    And this is all in a context where we – like the trial court and intermediate appellate
    court – must not only decide the case based on Virginia (as opposed to Maryland)
    substantive law, but must decide a question that concerns Virginia state government
    procurement. It perhaps goes without saying that this is not in our wheelhouse.15 So it is
    with some trepidation that we attempt to provide some clarity and, at the very least, do no
    harm.
    We first consider whether Dustin was entitled to summary judgment for the reason
    given by the Circuit Court. We conclude that it was not and then go on to consider whether
    the Circuit Court would have been required to award summary judgment in Dustin’s favor
    for the reason originally urged by Dustin.
    1.     Whether Dustin was Entitled to Summary Judgment under §2(c)
    The Circuit Court held that Dustin was entitled to summary judgment pursuant to
    §2(c) of the Subcontract and §37(a)(1) of the standard conditions in the Prime Contract
    because George Mason had not paid Dustin with respect to its proposed change orders
    based on the two change requests submitted to Dustin by Young.
    Although Dustin itself had not raised §2(c) as a basis for summary judgment, it may
    have appeared to the Circuit Court to be a more straightforward route to that end. Section
    15
    It is perhaps worth noting that we are seldom called upon to decide matters of
    Maryland state procurement, as the General Assembly has created a special forum for that
    task. See Maryland Code, State Finance & Procurement Article, §15-201 et seq.
    28
    2(c) contains the key phrase “condition precedent” in that it made the “Contractor’s
    obligation to pay all or any portion of the Subcontract Sum to Subcontractor, whether as
    progress payment, retainage or final payment, … contingent, as a condition precedent,
    upon the Contractor’s receipt of payment from the Owner of all amounts due Contractor
    on account of the portion for the Work for which the Subcontractor is seeking payment.”
    Subcontract, §2(c) (emphasis added). Under the Galloway decision, this language clearly
    creates a pay-if-paid clause, which would appear to reduce the issue simply to whether
    George Mason had paid Dustin. The court thus would avoid having to determine whether
    the changes on which Change Request 1066 and Change Request 1067 were based were
    “owner-initiated,” whether George Mason had ever rejected Change Request 1067, 16
    whether George Mason had rejected Change Request 1066 in the appropriate manner, or
    whether Dustin was deficient in some way in seeking George Mason’s approval, among
    other issues.
    This Occam’s Razor approach – preferring a simpler resolution over a complex
    resolution of a problem – seems a generally sensible approach. However, it does not work
    in this instance. Section 2(c) concerns payment of the Subcontract Sum – originally
    $1,148,860 and later increased by $317,193 through change orders. But those costs are not
    the subject of this case. For example, Change Request 1067 requested an additional
    16
    The Circuit Court explicitly noted in its oral decision that it did not have to resolve
    this question.
    29
    $274,812.33 because of “additional costs associated with delay and disruption[,] none of
    which is attributable to Young.”
    Section 2(c) applies to “Contractor’s obligation to pay all or any portion of the
    Subcontract Sum.” Unlike the payment clauses in Gilbane and Dyer, this clause does not
    concern Dustin’s contract liability to Young generally, but specifically payments to be
    made with respect to the Subcontract Sum. Thus, in order to decide whether §2(c) applies
    to the damages sought by Young, one must first determine whether the alleged damages
    are part of the Subcontract Sum. The notion that §2(c) would be “generally applicable” to
    all contract liability of Dustin is at odds with language of that section relating it to the
    Subcontract Sum and other provisions of the Subcontract related to particular types of
    damages.
    In its complaint, Young alleged the following bases for its contention that Dustin
    had breached the subcontract: Dustin’s alleged failure to coordinate and sequence work,
    Dustin’s alleged direction to Young to perform additional work and uncompensated
    overtime, and Dustin’s alleged failure to pay for the costs of the extended period of contract
    performance. At least some of these alleged damages appear to be outside the scope of
    §2(c). For example, Young’s complaint seeks damages for delay that it attributes to Dustin
    and §39 of the Subcontract states that “Contractor [i.e., Dustin] shall be liable for any and
    all actual damages sustained as a result of delay.”17 Even assuming that George Mason
    17
    Two §39’s appear in the Subcontract. The reference above is to the second section
    with that designation.
    30
    initiated changes, what is in dispute is who is responsible for the delays and incidental costs
    of implementing those changes.
    Reading §2(c) to apply to all damages resulting from delay would establish a
    condition precedent that would bear no logical relation to those damages. For example,
    under the Prime Contract, Dustin is responsible for coordinating and sequencing the work.
    If the delay were attributable to a failure by Dustin to carry out that obligation, there is no
    reason why George Mason would pay Dustin for failing to carry out Dustin’s own
    responsibilities under the Prime Contract. The same would be true for portions of Young’s
    work that had to be redone because Dustin or one of its other subcontractors had destroyed
    Young’s work. Section 28 of the Subcontract concerns disputes that do not involve the
    conduct of the Owner and, unsurprisingly, that provision does not include a pay-if-paid
    clause.18 The general application of §2(c) to payments other than those related to the
    Subcontract Sum would transform it into a blanket waiver by a subcontractor of delay
    damages, something that appears to be contrary to the intent of the parties.
    Young seeks other damages that are not necessarily related to delay, and that might
    be governed by §2(c). In particular, the complaint alleged “Dustin breached the contract .
    . . by directing the performance of additional work which it failed and refused to pay for,
    [and] by directing overtime work which it has failed and refused to pay for[.]” The record
    18
    That provision sets forth certain alternative dispute mechanisms. Whether an
    award of such damages would be precluded by a failure to pursue those procedures is not
    before us.
    31
    before us is insufficient to say those matters are governed by a clause with a condition
    precedent, particularly where no discovery has been conducted.
    The other provision relied upon by the Circuit Court in awarding summary judgment
    was §37(a)(1) of the standard Virginia procurement terms and conditions that were
    incorporated in the Prime Contract. However, as noted earlier, that provision simply set
    forth the requirements of the Virginia “prompt payment” statute. See Virginia Code, §2.2-
    4354. That statute requires Virginia state agencies to obligate their contractors to pay
    subcontractors promptly after the agency pays the contractor, or to notify the agency and
    subcontractor why it is not doing so. It is designed to ensure that subcontractors are paid
    without delay, not to create a pre-condition to their payment.19 Thus, §37(a)(1) would not
    be a basis for awarding summary judgment in favor of Dustin in this case.
    2.   Whether the Circuit Court was Required to Award Summary Judgment for a
    Different Reason
    We consider briefly whether the Circuit Court would have been required to award
    summary judgment in Dustin’s favor on a basis other than §2(c) of the Subcontract and
    §37(a)(1) of the standard terms incorporated in the Prime Contract. The obvious basis to
    consider is the primary ground argued by Dustin before the Circuit Court: that the breach
    of contract claim made by Young was based on Owner-initiated changes and that §13(c)
    19
    In this regard it appears to be similar to the Maryland prompt payment statute
    relating to State agency construction contracts. Maryland Code, State Finance &
    Procurement Article, §15-226; see also Maryland Code, Real Property Article, §9-301 et
    seq.
    32
    and §27(f) of the Subcontract are risk-shifting pay-if-paid clauses that preclude a judgment
    in favor of Young because George Mason has not paid Dustin with respect to that claim.
    We cannot say that the Circuit Court would be required to resolve those issues in
    Dustin’s favor as a matter of law on the current state of the record, as there appear to be
    open factual issues as to both elements of Dustin’s argument. The ruling on the summary
    judgment motion in this case occurred prior to any opportunity for discovery and thus
    deprived the party opposing that motion of the opportunity to produce additional
    information relevant to the issues. See Green v. H & R Block, Inc., 
    355 Md. 488
    , 502 &
    n.3 (1999). In this case, where certain issues relate to the possible responsibility of the
    Owner for changes and delays and the Owner’s response to proposed change requests, and
    where, under the contract, Young did not deal directly with George Mason, discovery may
    well be important to determine the operative facts and whether they are undisputed.
    First, it is not at all clear, as Dustin argues, that it is undisputed that damages sought
    by Young relate to “Owner-initiated changes.” (In relying on §2(c) of the Subcontract –
    which is not addressed to Owner-initiated changes – the Circuit Court did not need to
    determine whether it was undisputed that changes were Owner-initiated because that
    question was not material to its decision.) Dustin argues that there is no dispute that
    Young’s claim is based on Owner-initiated changes, pointing to select quotations from
    Change Requests 1066 and 1067.20
    In affirming the Circuit Court, the Court of Special Appeals accepted Dustin’s
    20
    argument in this regard. For the reasons set forth in the text, we do not.
    33
    However, the Subcontract explicitly states “Nothing said or written in the
    prosecution or defense of any claim(s) against the Owner shall constitute or be regarded as
    an admission or declaration against interest of either party in any litigation or arbitration
    between Contractor and Subcontractor.”          Subcontract, §27(g).       The parties clearly
    contemplated a situation where the Owner (George Mason) would refuse to pay for certain
    costs and where the Contractor (Dustin) and Subcontractor (Young) must litigate who bears
    those costs. Neither party apparently wanted to make what was said in a change request to
    the Owner binding in future litigation between the Contractor and Subcontractor. Thus,
    placing conclusive weight on a statement made in a change request to resolve litigation
    between the Contractor and Subcontractor, particularly on a motion for summary judgment
    prior to discovery, appears to be contrary to the intent of the parties.
    Moreover, in the context of a motion for summary judgment, a court must view the
    evidence in a light most favorable to the non-moving party. 
    Mathews, 435 Md. at 598
    .
    “Even where the underlying facts are undisputed, if the undisputed facts are susceptible of
    more than one permissible factual inference, the choice between those inferences should
    not be made as a matter of law, and summary judgment should not be granted.” Heat &
    Power Corp. v. Air Prod. & Chemicals, Inc., 
    320 Md. 584
    , 591 (1990). The gravamen of
    Young’s complaint states that “[d]elays arose through no fault or negligence” of its own,
    and that “Dustin breached [its subcontract with Young] by failing to coordinate and
    sequence the work” and “not paying the costs of the extended period of contract
    performance.” Read in context, Change Requests 1066 and 1067 support this theory and
    do not necessarily seek payment for Owner-initiated changes.
    34
    For example, read in the light most favorable to Young, Change Request 1066 is
    asking for reimbursement due to the contract running behind schedule. Although this delay
    is associated with the changes George Mason made, it could also be that Dustin failed to
    implement those changes efficiently. The two are not necessarily mutually exclusive, and
    this record is not sufficient to say that Young agrees that Dustin did not contribute to the
    delays.
    Second, as the Court of Special Appeals recognized, §13(c) and §27(f) of the
    Subcontract, when considered on their own terms, are somewhat similar to the payment
    provision at issue in Dyer. They could thus be construed as pay-when-paid provisions that
    relate to the timing of payments and that do not relieve Dustin of liability to Young, even
    if George Mason declines to pay 
    Dustin. 231 Md. App. at 364-65
    .21 The intermediate
    appellate court noted that there is “no timeframe” set forth for Dustin’s payment and “no
    apparent shift in the credit risk.” 
    Id. at 365.
    These were the same reasons that the Virginia
    Supreme Court found the contract provision at issue in Galloway to have a latent
    ambiguity. 
    Galloway, 464 S.E.2d at 355
    . If the parties are unable to identify other
    language in the Subcontract (apart supplanting them with §2(c)) that indicates that these
    provisions should be construed as either a pay-when-paid or a pay-if-paid clause, a court
    could find them to be latently ambiguous.         Under Galloway, consideration of parol
    evidence concerning the parties’ intentions may thus be necessary to discern whether these
    21
    See also Richard F. Kline, Inc. v. Shook Excavating & Hauling, Inc., 165 Md.
    App. 262, 274 (2005).
    35
    provisions were intended to operate as risk-shifting pay-if-paid clauses.22       No such
    evidence has yet been submitted by either party.
    For these reasons, the Circuit Court did not lack discretion to deny summary
    judgment on the ground actually advanced by Dustin. Accordingly, we decline to affirm
    its decision based on that alternative ground.
    III
    Conclusion
    We hold that the Circuit Court erred as a matter of law when it applied §2(c) of the
    Subcontract and §37(a)(1) of the standard conditions incorporated in the Prime Contract to
    award summary judgment in favor of Dustin. Section 2(c) is a pay-if-paid clause applicable
    to the Subcontract Sum and does not necessarily apply to the costs at issue in this case;
    §37(a)(1) incorporates a prompt payment provision of Virginia statutory law and does not
    create a condition precedent for payment of subcontractors.
    We decline to affirm the Circuit Court’s decision on alternative grounds. Whether
    §13(c) or §27(f) of the Subcontract function as pay-if-paid clauses is a matter of Virginia
    law on which a court may be required to consider parol evidence. No discovery has been
    22
    In its opposition to summary judgment, Young argued that, even if §13(c) and
    §27(f) of the Subcontract were pay-if-paid clauses, the prevention doctrine would negate
    the effect of such a clause. Under the prevention doctrine, a general contractor that
    materially contributes to the failure of a condition precedent under the contract may not
    rely on the absence of the condition precedent as a defense in a breach of contract action.
    See Aarow Equipment & Services, Inc., v. Travelers Cas. & Surety Co., 417 Fed. Appx.
    366, 372 (4th Cir. 2011). Given our disposition of this appeal, we need not resolve that
    issue in this case and decline to speculate on how any facts relevant to that issue will be
    developed on remand.
    36
    conducted in this litigation and it is not at all clear on the existing record that there are no
    material facts in dispute, particularly when the record is viewed in the light most favorable
    to the non-moving party. Accordingly, we shall remand this case to the trial court for
    further factual development.
    To the extent that there may be issues of Virginia contract law that remain at issue
    after fuller factual development in the Circuit Court that are deemed worthy of appeal or
    that meet the criteria for a writ of certiorari – i.e., issues for which a resolution is “desirable
    and in the public interest”23 – we, or the Court of Special Appeals, have the option of
    certifying a question of Virginia law to the Virginia Supreme Court for an authoritative
    resolution.24
    JUDGMENT OF THE COURT OF SPECIAL APPEALS VACATED
    AND CASE REMANDED WITH INSTRUCTIONS TO REMAND
    THE CASE TO THE CIRCUIT COURT FOR MONTGOMERY
    COUNTY FOR FURTHER PROCEEDINGS CONSISTENT WITH
    THIS OPINION. COSTS TO BE PAID BY RESPONDENT.
    23
    Maryland Code, Courts & Judicial Proceedings Article, §12-203.
    24
    Maryland Code, Courts & Judicial Proceedings Article, §12-601 et seq.
    37