Barron Chiropractic & Rehabilitation, P.C. v. Norfolk & Dedham Group , 469 Mass. 800 ( 2014 )


Menu:
  • NOTICE: All slip opinions and orders are subject to formal
    revision and are superseded by the advance sheets and bound
    volumes of the Official Reports. If you find a typographical
    error or other formal error, please notify the Reporter of
    Decisions, Supreme Judicial Court, John Adams Courthouse, 1
    Pemberton Square, Suite 2500, Boston, MA, 02108-1750; (617) 557-
    1030; SJCReporter@sjc.state.ma.us
    SJC-11561
    BARRON CHIROPRACTIC & REHABILITATION, P.C.    vs.   NORFOLK &
    DEDHAM GROUP.
    Norfolk.     May 5, 2014. - October 15, 2014.
    Present:    Ireland, C.J., Spina, Cordy, Botsford, Gants, Duffly,
    & Lenk, JJ.1
    Insurance, Motor vehicle personal injury protection benefits,
    Unfair act or practice. Contract, Insurance. Practice,
    Civil, Summary judgment, Attorney's fees. Consumer
    Protection Act, Insurance.
    Civil action commenced in the Dedham Division of the
    District Court Department on November 25, 2009.
    The case was heard by James J. McGovern, J., on a motion
    for summary judgment.
    The Supreme Judicial Court granted an application for
    direct appellate review.
    Francis A. Gaimari (Robert N. Fireman & Stephen B. Byers
    with him) for the plaintiff.
    Joseph R. Ciollo (Michael L. Snyder with him) for the
    defendant.
    E. Michael Sloman, for Automobile Insurers Bureau, amicus
    curiae, submitted a brief.
    1
    Chief Justice Ireland participated in the deliberation on
    this case prior to his retirement.
    2
    Christopher M. Moutain, for American Insurance Association
    & others, amici curiae, submitted a brief.
    LENK, J.   The personal injury protection (PIP) provision of
    the automobile insurance statute permits an unpaid party to
    bring an action for breach of contract against an automobile
    insurer if the latter has not paid PIP benefits for more than
    thirty days after those benefits became due and payable.     G. L.
    c. 90, § 34M, fourth par.   If the unpaid party receives a
    judgment for any amount due and payable by the insurer, it also
    may recover its costs and reasonable attorney's fees.     The
    primary question before us is whether an unpaid party who has
    brought suit and thereafter refused the insurer's tender of
    amounts due and payable, made prior to the entry of judgment,
    may proceed with the suit and, if successful, obtain a judgment
    for those amounts as well as its costs and attorney's fees.     We
    conclude that it may proceed with the action under G. L. c. 90,
    § 34M.
    1.   Background.   The plaintiff, Barron Chiropractic &
    Rehabilitation, P.C. (Barron), provided chiropractic services to
    Nicole Jean-Pierre following her automobile accident on
    August 20, 2008.   Jean-Pierre was injured while driving a
    vehicle insured by the defendant Norfolk & Dedham Group
    (Norfolk) pursuant to G. L. c. 90, § 34A, which requires
    3
    compulsory motor vehicle liability insurance, including PIP
    benefits.2   See G. L. c. 90, §§ 34A, 34M.
    Norfolk received notice of the accident on August 22, 2008,
    and, on October 10, 2008, received Jean-Pierre's application for
    PIP benefits.3 Shortly thereafter, pursuant to its contractual
    right under the terms of Jean-Pierre's insurance policy, as well
    as language in the PIP provision, Norfolk requested that Jean-
    Pierre undergo an independent medical examination (IME)4 by Kevin
    Morgan, a licensed chiropractor of its selection.   On
    October 27, 2008, Morgan submitted his IME report to Norfolk.
    The report stated that, while treatments up to the date of the
    2
    Personal injury protection (PIP) benefits consist of "all
    reasonable expenses incurred within two years from the date of
    [the] accident for necessary medical, surgical, x-ray, and
    dental services," and, for employed persons, "any amounts
    actually lost by reason of inability to work and earn wages or
    salary or their equivalent." G. L. c. 90, § 34A.
    3
    General Laws c. 90, § 34M, third par., states that a
    "[c]laim for benefits due under the provisions of personal
    injury protection or from the insurer assigned shall be
    presented to the company providing such benefits as soon as
    practicable after the accident occurs from which such claim
    arises, and in every case, within at least two years from the
    date of the accident, and shall include a written description of
    the nature and extent of injuries sustained, treatment received
    and contemplated and such other information as may assist in
    determining the amount due and payable."
    4
    The PIP provision provides that the "insured person shall
    submit to physical examinations by physicians selected by the
    insurer as often as may be reasonably required and shall do all
    things necessary to enable the insurer to obtain medical reports
    and other needed information to assist in determining the
    amounts due." G. L. c. 90, § 34M, third par.
    4
    IME had been appropriate, Jean-Pierre had reached "maximum
    therapeutic benefit."   Based on this report, Norfolk concluded
    that treatments Barron provided Jean-Pierre after the date of
    the IME were unreasonable and unnecessary.     A few days
    thereafter, Norfolk provided Jean-Pierre's counsel with a copy
    of the report.
    Approximately nine months later, on July 27, 2009, Norfolk
    received a response to Morgan's IME report from Scott Hayden, a
    licensed chiropractor and a Barron employee.     Hayden disagreed
    with Morgan's conclusion that Jean-Pierre had reached a medical
    end result at the time of the IME, stating instead that proper
    rehabilitation had required nine treatment visits after that
    date.   On August 17, 2009, Morgan sent Norfolk an addendum to
    his initial IME report, indicating that Hayden's rebuttal had
    not altered his assessment of Jean-Pierre's care, and stating
    further that subsequent care offered by Barron, while "within
    acceptable care guidelines" and "reasonable and necessary,"
    appeared aimed largely at preexisting conditions.
    As an additional component of its investigation of Jean-
    Pierre's claim, Norfolk sent Barron's billing statements to BME
    Gateway (BME), an independent third party, for financial
    analysis.   BME uses a computer database to determine whether a
    medical provider has sought fees that are usual, customary, and
    reasonable within a particular geographic region.
    5
    Barron submitted a bill to Norfolk seeking $3,940 in
    payment for its treatment of Jean-Pierre.   Upon review, Norfolk
    concluded that it was not liable for the entirety of this
    requested amount.   Based on BME's assessment, Norfolk deducted
    $64.05 from Barron's bill, allowing only $3,875.95 on that
    ground.   In reliance on Morgan's IME report, Norfolk also
    limited its payment to service provided prior to the date of the
    IME, declining to pay a further $1,480 in charges for treatment
    occurring after October 27, 2008.   In total, Norfolk determined
    that it was liable for only $2,395.95 of Barron's submitted
    fees, resulting in a disputed amount of $1,544.05.
    On November 25, 2009, more than one year after Jean-Pierre
    had submitted her application for PIP benefits, Barron filed a
    complaint in the District Court.5   Barron sought payment of
    $1,544.05, plus interest, attorney's fees, and costs pursuant to
    G. L. c. 90, § 34M; multiple damages and attorney's fees
    pursuant to G. L. c. 93A, § 11, for alleged unfair or deceptive
    practices regarding Jean-Pierre's insurance claim; and multiple
    damages and attorney's fees pursuant to G. L. c. 93A, §§ 9 and
    5
    We have construed the term "unpaid party" in G. L. c. 90,
    § 34M, to include, as here, "an unpaid medical provider who
    treats an insured." Boehm v. Premier Ins. Co., 
    446 Mass. 689
    ,
    691 (2006). The medical provider may thus "step into the shoes
    of the insured and bring an action in contract to recover PIP
    benefits." 
    Id.
    6
    11, for violations of G. L. c. 176D, § 3 (9), which prohibits
    insurers from engaging in unfair settlement practices.
    At some point prior to trial, Norfolk learned that Morgan's
    fee to appear as an expert witness was $500 per hour, with a
    minimum of five hours to be billed.6   Although still maintaining
    that it did not owe Barron any additional payments, Norfolk
    determined that its anticipated litigation costs would exceed
    the amount of the disputed medical fees by a substantial sum.
    Accordingly, on September 28, 2010, six days prior to the second
    scheduled trial date,7 Norfolk sent Barron a check for $1,544.05
    with an attached check stub that stated "full and final
    settlement for Nicole Jean Pierre."    Norfolk included a letter
    stating that its payment was made pursuant to Fascione v. CNA
    Ins. Cos., 
    435 Mass. 88
     (2001) (Fascione); the letter requested
    that Barron sign an acknowledgment of the receipt of final
    payment and file a stipulation of dismissal in the District
    Court as to its claims under the PIP provision.    On October 12,
    2010, Barron's counsel returned the check to Norfolk's counsel
    with a letter stating, "Your client's offer of settlement is
    rejected."
    6
    In its pretrial memorandum, dated May 11, 2010, Norfolk
    indicated that Morgan was expected to testify as to the
    substance of his independent medical examination and report.
    7
    The trial initially was scheduled for August 3, 2010, but
    was rescheduled at the parties' request for October 4, 2010.
    7
    Norfolk then filed a motion for summary judgment as to both
    the G. L. c. 90, § 34M, and G. L. c. 93A claims, supported by an
    affidavit from its claims supervisor, as well as by relevant
    medical records and BME's financial analysis.     Barron filed an
    opposition, but neither alleged that any issues of material fact
    remained in dispute, nor included any counter affidavits or
    other documents indicating any factual dispute.     A District
    Court judge granted Norfolk's motion for summary judgment, and,
    on Barron's appeal, the Appellate Division of the District Court
    affirmed the judgment.     Barron filed a notice of appeal in the
    Appeals Court, and we granted Norfolk's subsequent application
    for direct appellate review.
    2.   Discussion.     Summary judgment is appropriate where
    there are no genuine issues of material fact in dispute and the
    moving party is entitled to judgment as a matter of law.
    Community Nat'l Bank v. Dawes, 
    369 Mass. 550
    , 553 (1976).        If
    the moving party, in its pleadings and supporting documentation
    pursuant to Mass. R. Civ. P. 56 (c), as amended, 
    436 Mass. 1404
    (2002), asserts the absence of any triable issue, the nonmoving
    party must respond and make specific allegations sufficient to
    establish a genuine issue of material fact.     Drakopoulos v. U.S.
    Bank Nat'l Ass'n, 
    465 Mass. 775
    , 777-778 (2013).     Pederson v.
    Time, Inc., 
    404 Mass. 14
    , 16-17 (1989).     Bare assertions made in
    the nonmoving party's opposition will not defeat a motion for
    8
    summary judgment.   O'Rourke v. Hunter, 
    446 Mass. 814
    , 821
    (2006).   Mass. R. Civ. P. 56 (e), 
    365 Mass. 824
     (1974) ("A party
    may not rest upon the mere allegations or denials of his
    pleading").   We review the disposition of a motion for summary
    judgment de novo.   Miller v. Cotter, 
    448 Mass. 671
    , 676 (2007).
    Barron contends that summary judgment was inappropriate as
    to its claim under § 34M.   Because Barron declined Norfolk's
    late tender, made on the eve of trial, it remained an "unpaid
    party" pursuant to § 34M, and was entitled to seek a judgment
    for benefits due and payable.   Relying on Fascione, supra,
    Norfolk maintains that it was entitled to summary judgment once
    it tendered a complete payment of benefits owed, notwithstanding
    Barron's rejection of that tender.   Because we conclude, for the
    reasons set forth below, that Barron was permitted to refuse
    Norfolk's tender and pursue its suit, the order granting
    Norfolk's motion for summary judgment on the G. L. c. 90, § 34M,
    claim must be vacated and the case remanded for trial.
    Barron also contests the entry of summary judgment for
    Norfolk as to the G. L. c. 93A claims.   In its opposition to
    Norfolk's motion, however, Barron did not allege the existence
    of any factual disputes and submitted no documentation that
    might reveal such disputes.   See Mass. R. Civ. P. 56 (e) ("[A]n
    adverse party [to a motion for summary judgment] . . . must set
    forth specific facts [in its affidavits and pleadings] showing
    9
    that there is a genuine issue for trial").    Accordingly, we
    affirm the order granting Norfolk's motion for summary judgment
    on the G. L. c. 93A claims.
    a.   Claim under G. L. c. 90, § 34M.    The PIP provision,
    G. L. c. 90, § 34M, specifies that an "unpaid party," that is, a
    claimant whose PIP benefits remain unpaid for more than thirty
    days after those benefits become "due and payable," shall have
    the right to bring an action in contract against an insurer to
    recover those benefits, as well as attorney's fees and costs
    should the unpaid party prevail.8   Under common-law principles of
    contract, which we have deemed applicable to "action[s] in
    contract" under § 34M, see Boehm v. Premier Ins. Co., 
    446 Mass. 689
    , 691 (2006) (Boehm), a plaintiff may reject a defendant's
    disputed tender of payment, made after the date set for payment
    has expired, and litigate its breach of contract claim to
    8
    Specifically, G. L. c. 90, § 34M, fourth par., states, in
    relevant part:
    "Personal injury protection benefits . . . shall be
    due and payable as loss accrues, upon receipt of reasonable
    proof of the fact and amount of expenses and loss
    incurred . . . . In any case where benefits due and
    payable remain unpaid for more than thirty days, any unpaid
    party shall be deemed a party to a contract with the
    insurer responsible for payment and shall therefore have a
    right to commence an action in contract for payment of
    amounts therein determined to be due in accordance with the
    provisions of this chapter . . . . If the unpaid party
    recovers a judgment for any amount due and payable by the
    insurer, the court shall assess against the insurer in
    addition thereto costs and reasonable attorney's fees."
    10
    completion.    Here, Norfolk attempted to tender the disputed
    $1,544.05 nearly one year after Barron had commenced its
    contract action, and just six days prior to trial.   We conclude
    that Barron properly could reject this tender, forgo the
    certainty it offered, and opt instead to pursue recovery not
    only of the disputed unpaid PIP benefits, but also of the
    attorney's fees and costs provided by the PIP provision.
    To construe this provision, we "look first to the text of
    the statute."   Boehm, supra at 690.   General Laws c. 90, § 34M,
    fourth par., provides that suits brought to recover PIP benefits
    shall sound in contract, noting that an unpaid claimant "shall
    be deemed a party to a contract with the insurer" and may bring
    an "action in contract" to obtain any benefits held to be due
    and payable.    Given these unambiguous statutory references to
    actions in contract, we have held that a § 34M suit brought to
    procure unpaid PIP benefits is governed generally by ordinary
    contract principles.9   In Boehm, supra at 689, we considered
    whether G. L. c. 90, § 34M, conferred the right to a jury trial.
    In concluding that PIP claimants were so entitled, we emphasized
    that an unpaid claimant "has a 'right' to seek recovery through
    9
    Barron contends also that it was entitled to reject
    Norfolk's efforts at late tender pursuant to the tender statute,
    G. L. c. 232A, § 1. Since we conclude that common-law contract
    principles govern here, we do not address this argument. See
    Fascione v. CNA Ins. Cos., 
    435 Mass. 88
    , 90 n.1 (2001).
    11
    'an action in contract,'" deeming this text "determinative of
    the issue at bar."   Boehm, supra at 691, quoting G. L. c. 90,
    § 34M, fourth par.   At common law, we noted, parties to contract
    actions "enjoyed the right to a jury trial," and "the
    Legislature is presumed 'to know the preexisting law and the
    decisions of this court.'"    Boehm, supra, quoting Selectmen of
    Topsfield v. State Racing Comm'n, 
    324 Mass. 309
    , 313 (1949).
    "Had the Legislature intended to treat contract
    actions brought pursuant to § 34M, fourth par., differently
    from the ordinary contract action, it could have said so
    explicitly as it did in the very next paragraph, which
    directs insurers to resolve disagreements concerning
    subrogation through arbitration."
    Boehm, supra.   "That § 34M does not explicitly refer to the
    right to a jury trial," we concluded, "is of no consequence."
    Boehm, supra at 691-692.     The Legislature's explicit
    determination that an unpaid PIP claimant may file a contract
    suit "carries with it the principle[s]" of the common law of
    contracts.   Id. at 692.   See Commonwealth v. Burke, 
    392 Mass. 688
    , 690 (1984) (statute must be construed as consistent with
    common law absent clear contrary legislative intent).
    Principles of contract law are "dispositive" of the present
    case, just as they were of the question addressed in Boehm.       At
    common law, tender of a sum owed under a contract is valid only
    when made prior to the parties' agreed-upon date for payment,
    12
    even if that tender is for the entire disputed sum.10   There can
    "be no 'tender' in the legal meaning of the word if the offer
    was made after the day fixed for payment had passed and the
    contract to pay had been broken."   Levin v. Wall, 
    290 Mass. 423
    ,
    426 (1935).   See City Bank v. Cutter, 
    3 Pick. 414
    , 418 (1826)
    ("the plea of tender is bad, the tender not having been made
    until the day after the debt became due against the
    defendants"); 17B C.J.S. Contracts, Tender of Performance § 729
    (2011) ("In order to be valid, a tender of payment on a contract
    must be timely . . ."); M.G. Perlin & S.H. Blum, Procedural
    Forms Annotated § 54:230, Tender (6th ed. 2009) (tender invalid
    if made after payment date).
    A party who receives an invalid late tender is not obliged
    to accept it.   See Levin v. Wall, supra at 427 (plaintiff
    permitted to reject tender made on first day of trial for breach
    of contract and pursue his claim to judgment); Davis v.
    Harrington, 
    160 Mass. 278
    , 280 (1894) (plaintiff who accepted
    complete tender after filing breach of contract suit "could have
    preserved his right to interest by way of damages, and also to
    10
    Norfolk never conceded its liability for $1,544.05 of
    Barron's requested fees. Nevertheless, in light of the
    litigation costs it might incur should the case proceed to
    trial, Norfolk contends that it made a business decision to
    tender this disputed amount. In conjunction with payments
    already made, the tendered payment, if accepted, would have
    compensated Barron for all of the PIP benefits it sought, not
    including interest.
    13
    costs, by declining to accept the payment"); Loitherstein v.
    International Business Machs. Corp., 
    11 Mass. App. Ct. 91
    , 92
    (1980) (defendant's late tender, which plaintiff rejected, did
    not extinguish plaintiff's claim for damages due to breach).
    Where a defendant attempts to tender payment after it has
    already breached the contract, "the rights of the parties
    depend, not on a tender, but on the acceptance of a payment
    which discharged the cause of action."     Davis v. Harrington,
    supra at 280.   Even if a plaintiff receives a tender of payment
    in full for a disputed sum, as here, "an underlying debt may not
    be discharged unless payment is accepted."     First Nat'l Bank v.
    Commonwealth, 
    391 Mass. 321
    , 326 (1984).     Late tender alone
    therefore does not preclude a plaintiff from filing a claim for
    breach or pursuing a then-pending suit.11
    Here, Norfolk's tender of $1,544.05 was made past the
    deadline set forth in the PIP provision.     General Laws c. 90,
    11
    To be sure, a plaintiff is also entitled to accept and
    thereby validate an otherwise improper late tender. Such
    acceptance removes the "foundation of [a potential contract]
    suit" and necessitates the dismissal of a suit already
    commenced. Davis v. Harrington, 
    160 Mass. 278
    , 280 (1894)
    (plaintiff who accepted tender made after suit had commenced not
    entitled to damages in form of interest and costs). See Hamlen
    v. Rednalloh Co., 
    291 Mass. 119
    , 126-127 (1935) (plaintiff could
    not recover costs after accepting late payment in full with
    interest); Paul Revere Trust Co. v. Castle, 
    231 Mass. 129
    , 132
    (1918) ("when the plaintiff accepted the principal in full
    payment the right to recover the interest . . . was
    extinguished").
    14
    § 34M, establishes the date of breach relevant to unpaid PIP
    benefits, providing that, where "benefits due and payable remain
    unpaid for more than thirty days, any unpaid party . . . shall
    therefore have a right to commence an action in contract."
    After the expiration of that thirty-day period, Barron had yet
    to receive $1,544.05 in medical fees which it maintains were
    "due and payable."   Norfolk sent its check for that amount to
    Barron on September 28, 2010, nearly two years after Jean-Pierre
    first notified Norfolk of her claim for PIP benefits, and nearly
    one year after Barron filed suit seeking payment of the disputed
    balance.   The "day fixed for payment had passed," Levin v. Wall,
    supra at 426, and, after that point, "a tender cannot be
    effectual to bar the action for damages."    Suffolk Bank v.
    Worcester Bank, 
    5 Pick. 106
    , 108 (1827) (where there had been no
    tender at time contract suit commenced, "the tender afterwards
    cannot avail in defence of the action").    Norfolk's tender
    therefore was improper under principles of common law, and
    Barron was permitted to reject it and seek an award of the PIP
    benefits it maintained were "due and payable," as well as its
    attorney's fees, costs, and interest.
    Norfolk maintains nonetheless that, under our decision in
    Fascione, its tender of payment was sufficient to discharge all
    of its obligations to Barron, and that the allowance of its
    15
    motion for summary judgment was proper.12     This argument
    misapprehends the relevance of Fascione to the circumstances
    here.     In Fascione, supra at 89, an insurer inadvertently failed
    to pay the full amount of a PIP claimant's benefits, and
    tendered the remaining payment after the claimant had filed suit
    under G. L. c. 90, § 34M, to recover the amounts due.      We held
    that the claimant, who had accepted the insurer's tender and was
    fully compensated for her medical expenses, was not thereafter
    permitted to seek costs, attorney's fees, and interest under
    § 34M.    Fascione, supra at 89-90, 92-94.    A claimant may only
    receive costs and attorney's fees upon obtaining "a judgment for
    any amount due and payable."     Id. at 92.   The phrase "any amount
    12
    The parties' disagreement as to the import of Fascione,
    supra, reflects differences in decisions of the Appellate
    Division of the District Court. Certain of those decisions have
    interpreted Fascione to mean that an insurer's tender of a full
    PIP payment, made after a claimant filed suit but before
    judgment has entered, will extinguish the G. L. c. 90, § 34M,
    claim even where the claimant rejects such tender. See, e.g.,
    Essex Chiropractic Office, LLC vs. Plymouth Rock Assur. Corp.,
    Mass. Dist. Ct. App. Div., No. 08-ADMS-10032 (Dec. 17, 2008)
    ("it would be an absurd result if a medical provider were able
    to defeat the holding of Fascione merely by rejecting the tender
    of full payment of a PIP claim"); Kratzer vs. Liberty Mut. Ins.
    Co., Mass. Dist. Ct. App. Div., No. 9834 (May 28, 2003).
    Other Appellate Division decisions, however, have concluded
    that "[n]othing in Fascione dictates that a tender of the
    balance due under the § 34M claim must necessarily stop that
    part of the litigation in its tracks and require a judgment of
    zero damages." Metro West Med. Assocs., Inc. vs. Amica Mut.
    Ins. Co., Mass. Dist. Ct. App. Div., No. 10-ADMS-10009 (June 29,
    2010). See Olympic Physical Therapy vs. ELCO Admin. Servs.,
    Mass. Dist. Ct. App. Div., 10-ADMS-10017 (Aug. 17, 2010).
    16
    due and payable," we concluded, encompassed only PIP benefits
    themselves, and did not include interest.      Id. at 92-93.
    Because the claimant had accepted the insurer's full payment of
    her PIP expenses, she could not recover a judgment for costs and
    attorney's fees.   Id. at 94.
    Fascione affords no basis upon which to conclude that a PIP
    claimant, having filed an action in contract against an insurer
    for its delayed payment of benefits, is obliged to accept late
    tender and thus relinquish its suit.     We held in that case that
    G. L. c. 90, § 34M, provides no further remedy to a claimant who
    has accepted an insurer's late, but complete, tender of payment;
    this in no way was intended to suggest that a claimant may not
    reject such tender in an effort to obtain the attorney's fees
    and costs mandated by § 34M.     Indeed, our analysis relied on the
    claimant's acceptance of the insurer's reimbursement, which
    removed any basis for a judgment in favor of the claimant by
    compensating her for all "amount[s] due and payable."
    Moreover, to interpret Fascione as Norfolk suggests would
    contravene the fee-shifting provision of G. L. c. 90, § 34M,
    thereby enabling insurers to delay their payment of benefits
    without consequence.   The Legislature was "aware of the long
    delays in getting financial aid to the injured person" when it
    enacted the PIP provision.      Pinnick v. Cleary, 
    360 Mass. 1
    , 20
    (1971).   Accordingly, the thirty-day payment period, in
    17
    conjunction with the provision for attorney's fees and costs,
    together protect "the right and need of all accident victims to
    simple and speedy justice."   
    Id. at 21
    .   Since a cause of action
    lies against an insurer who fails to pay PIP benefits within the
    statutory period, and since the insurer will be liable for
    attorney's fees and costs if a claimant obtains a judgment for
    the unpaid amount, G. L. c. 90, § 34M, encourages the prompt
    payment of benefits.13
    But these incentives would diminish if an insurer could
    disregard the thirty-day deadline yet nevertheless evade
    liability for attorney's fees and costs by tendering benefits at
    will after a suit has commenced.   Under Norfolk's approach, the
    timeframe for prompt payment established by the Legislature
    would have little effect, since an insurer's delay would
    engender no more serious consequence than the payment of the
    very benefits sought from it at the outset.    See Insurance
    Rating Bd. v. Commissioner of Ins., 
    356 Mass. 184
    , 189 (1969)
    13
    This, in turn, is intended to lessen the expense of
    compulsory automobile insurance for all Massachusetts drivers,
    by reducing the number of claims that insurers will choose to
    litigate. See Fascione, supra at 94, citing Pinnick v. Cleary,
    
    360 Mass. 1
    , 16-20 (1971) ("[T]he main objectives of the
    automobile insurance law, of which § 34M is a critical part,
    were to reduce the amount of motor vehicle tort litigation,
    control the costs of automobile insurance, and ensure prompt
    payment of claimants' medical and out-of-pocket expenses"). See
    also Dominguez v. Liberty Mut. Ins. Co., 
    429 Mass. 112
    , 115
    (1999).
    18
    ("An intention to enact a barren and ineffective provision is
    not lightly to be imputed to the Legislature").
    The provision for payment of attorney's fees and costs
    would be similarly toothless.    When an insurer's payment of PIP
    benefits, as here, is made on the eve of trial, a claimant may
    well have incurred substantial expenses.    If, as Norfolk
    suggests, a claimant were required to accept such late tender,
    she would be bound to forgo the recovery of those expenses
    whenever an insurer offered belated reimbursement of a disputed
    sum.   See Pine v. Rust, 
    404 Mass. 411
    , 416 (1989) ("If an offer
    of the statutory minimum amount of damages were all that could
    be expected by plaintiffs, there would be no need for provision
    in the law for the award of attorney's fees").    Moreover, a
    contract suit under § 34M is only necessary, in the first
    instance, if an insurer fails to reimburse a claimant by the
    statutory deadline.   Under Norfolk's approach, far from reducing
    the amount of litigation, § 34M would provide incentives for
    insurers to delay payment until their insureds filed suit to
    collect amounts owed; on a date of its choosing, an insurer then
    unilaterally could terminate litigation prompted only by its own
    delay.   "[E]quity will not permit" such a result, which would
    allow an insurer to "defeat a remedy which except for his
    misconduct would not be available."    Lamb v. Rent Control Bd. of
    19
    Cambridge, 
    17 Mass. App. Ct. 1038
    , 1039 (1984), quoting Deitrick
    v. Greaney, 
    309 U.S. 190
    , 196 (1940).
    In sum, an insurer's late tender of PIP benefits, made
    after a claimant has filed suit and which the claimant declines
    to accept, does not entitle an insurer to summary judgment.     To
    be sure, an insurer may opt to tender payment of outstanding PIP
    benefits after the filing of a suit, and, if a claimant accepts
    that tender, the action under G. L. c. 90, § 34M, will be
    extinguished.   See Fascione, supra at 91.   But the mere tender
    of such late payment will not, in itself, innoculate an insurer
    against liability for attorney's fees and costs if the claimant
    opts to refuse tender and subsequently obtains a judgment for
    PIP benefits.   Here, because Barron rejected Norfolk's tendered
    check for $1,544.05, it remained an "unpaid party," and
    Norfolk's motion for summary judgment on its G. L. c. 90, § 34M,
    claim should have been denied.
    b.   Claims under G. L. c. 93A, §§ 9, 11.   Barron contends
    also that the judge erred in allowing Norfolk's motion for
    summary judgment on the G. L. c. 93A claims.14   To determine
    whether a business practice is unfair under G. L. c. 93A, § 11,
    14
    In its complaint, Barron set forth two separate claims
    for violations of G. L. c. 93A, one based on Norfolk's asserted
    failure to adhere to G. L. c. 90, § 34M, and one stemming from
    Norfolk's purported unfair claim settlement practices as defined
    by G. L. c. 176D, § 3 (9) (b), (d), (e), (f), (g), and (n). As
    did the Appellate Division, we assess both claims together.
    20
    we assess "(1) whether the practice . . . is within at least the
    penumbra of some common-law, statutory, or other established
    concept of unfairness; (2) whether it is immoral, unethical,
    oppressive, or unscrupulous; [and] (3) whether it causes
    substantial injury to consumers (or competitors or other
    businessmen)."   PMP Assocs., Inc. v. Globe Newspaper Co., 
    366 Mass. 593
    , 596 (1975).
    In the circumstances of this case, there was no error in
    allowing Norfolk's motion for summary judgment on the G. L.
    c. 93A claims.   Norfolk's motion stated that there were no
    genuine issues of material fact as to the propriety of Norfolk's
    dealings under G. L. c. 93A, and indicated that Norfolk acted,
    at all times, in accordance with appropriate business judgments.
    In support of its motion, Norfolk included a detailed affidavit
    by one of its senior claims supervisors outlining its conduct in
    handling Jean-Pierre's claim for PIP benefits.   According to the
    affidavit, Norfolk relied in good faith on the IME report in
    deciding to limit payment to dates of medical service prior to
    October 27, 2008, and relied similarly on BME's fee analysis in
    reducing Barron's submitted bills by $64.05.   See Duclersaint v.
    Federal Nat'l Mtge. Ass'n, 
    427 Mass. 809
    , 814 (1998); Lumbermens
    Mut. Cas. Co. v. Y.C.N. Transp. Co., 
    46 Mass. App. Ct. 209
    , 215
    (1999).
    21
    In its opposition to Norfolk's motion for summary judgment,
    Barron did not allege that material facts were in dispute,
    stating only that "[n]othing in Norfolk's submission
    demonstrates that no genuine issue of fact remains on the G. L.
    c. 93A claims.    Thus, the plaintiff has no burden of rebuttal."
    Nor did the opposition include counter affidavits or any other
    countervailing documentation that might have demonstrated the
    existence of genuine issues of material fact.     Although Barron
    had alluded in its initial complaint to Norfolk's purported bad
    faith,    a party opposing a motion for summary judgment may not
    "simply rest on his pleadings."     Community Nat'l Bank v. Dawes,
    
    369 Mass. 550
    , 554 (1976). See LaLonde v. Eissner, 
    405 Mass. 207
    , 209-210 (1989) (granting summary judgment for defendant
    where plaintiffs did not dispute any relevant material fact).
    Cf. Rule 9A(a)(2) of the Rules of the Superior Court (2014)
    ("Affidavits and other documents setting forth or offering
    evidence of facts on which the opposition is based shall be
    served with the memorandum in opposition [to a motion for
    summary judgment]").     Having failed to "set forth specific facts
    showing that there is a genuine issue for trial," Mass. R. Civ.
    P. 56 (e), Barron was not entitled to trial on its G. L. c. 93A
    claims.
    3.     Conclusion.   The order allowing judgment for Norfolk on
    count 1, the G. L. c. 90, § 34M, claim, is vacated and set
    22
    aside, and the matter is remanded to the District Court for
    further proceedings on that claim.   The entry of judgment for
    Norfolk on counts two and three, the claims under G. L. c. 93A,
    is affirmed.
    So ordered.