G4S Technology LLC v. Massachusetts Technology Park Corp. , 479 Mass. 721 ( 2018 )


Menu:
  • NOTICE: All slip opinions and orders are subject to formal
    revision and are superseded by the advance sheets and bound
    volumes of the Official Reports. If you find a typographical
    error or other formal error, please notify the Reporter of
    Decisions, Supreme Judicial Court, John Adams Courthouse, 1
    Pemberton Square, Suite 2500, Boston, MA, 02108-1750; (617) 557-
    1030; SJCReporter@sjc.state.ma.us
    SJC-12397
    G4S TECHNOLOGY LLC vs. MASSACHUSETTS
    TECHNOLOGY PARK CORPORATION.
    Suffolk.    March 5, 2018. - June 13, 2018.
    Present:    Gants, C.J., Gaziano, Lowy, Budd, Cypher,
    & Kafker, JJ.
    Contract, Public works, Construction contract, Performance and
    breach, Subcontractor, Damages. Public Works, Delay, Extra
    work. Damages, Breach of contract, Quantum meruit, Fraud.
    Practice, Civil, Summary judgment, Damages. Fraud.
    Civil action commenced in the Superior Court Department on
    September 22, 2014.
    The case was heard by Janet L. Sanders, J., on motions for
    summary judgment, and entry of separate and final judgment was
    ordered by her.
    The Supreme Judicial Court granted an application for
    direct appellate review.
    Christopher Weld, Jr. (Megan C. Deluhery & Joel Lewin also
    present) for the plaintiff.
    Robert J. Kaler (Edwin L. Hall also present) for the
    defendant.
    Carol Chandler, Brendan Carter, David E. Wilson, Shannon A.
    Reilly, & Mark Keough Molloy, for Associated Builders and
    Contractors, Massachusetts Chapter, & others, amici curiae,
    submitted a brief.
    2
    Maura Healey, Attorney General, & James A. Sweeney &
    Cassandra H. Arriaza, Assistant Attorneys General, for the
    Attorney General, amicus curiae, submitted a brief.
    KAFKER, J.   At issue is a construction contract dispute
    between G4S Technology LLC (G4S) and Massachusetts Technology
    Park Corporation (MTPC) arising out of a State- and federally
    funded project to design and build a fiber optic network in
    western and north central Massachusetts.   On summary judgment, a
    judge in the Superior Court concluded that G4S was barred from
    seeking recovery on the contract or under quantum meruit because
    it intentionally filed false certifications of timely payments
    to subcontractors.   The judge also concluded that MTPC could not
    maintain a fraud action against G4S, in which it sought damages
    in addition to the $4 million payment MTPC already had withheld
    from G4S, because any recovery would be duplicative.
    On appeal, G4S argues that MTPC was not damaged by the
    false certifications, and that the Commonwealth should replace
    the common-law rule that "in relation to building contracts,
    . . . a contractor cannot recover on the contract itself without
    showing complete and strict performance of all its terms," Andre
    v. Maguire, 
    305 Mass. 515
    , 516 (1940), with a materiality rule
    as provided in the Restatement (Second) of Contracts §§ 237, 241
    (1981).   Alternatively, G4S contends that, even if recovery on
    the contract is disallowed, it should be able to pursue an
    3
    equitable recovery under the doctrine of quantum meruit.     G4S
    argues that MTPC, and not G4S, was responsible for the delays in
    construction and the $10 million in increased costs G4S assumed.
    MTPC cross-appealed from the dismissal of its claim of fraud
    against G4S.
    We conclude that complete and strict performance is still
    required for all construction contract terms relating to the
    design and construction itself.   We also conclude, however, that
    ordinary contract principles, including the traditional
    Massachusetts materiality rule, apply for breaches of other
    provisions, such as the one at issue governing payment
    certifications.   We hold that G4S's numerous false
    certifications and intentional subcontractor payment delays
    constitute a material breach of the contract and, standing
    alone, preclude recovery for breach of contract.
    Summary judgment was not, however, properly granted on
    G4S's quantum meruit theory of recovery.   A party seeking to
    recover under quantum meruit must prove both substantial
    performance and good faith.   Substantial performance is not at
    issue here, as the project was completed as specified, albeit
    delayed.   The issue is whether a party that has intentionally
    committed a breach of a provision in the contract can still have
    acted in good faith for quantum meruit purposes and whether
    there has been a windfall for the other party.   Overruling an
    4
    older line of cases, we now hold that good faith applies to the
    contract as a whole, and that the intentional commission of
    breaches of individual contract provisions must be considered in
    the over-all context, including the value of the uncompensated
    work, the damage caused by the breach, the total performance of
    both parties, and the balancing of equities to accomplish a just
    result.     Here, there are material disputed facts regarding which
    party caused the delays, whether G4S performed $10 million of
    uncompensated work, and whether there is any causal connection
    between the intentional misrepresentations regarding payments to
    subcontractors and the damages assessed against G4S.    We thus
    reverse the award of summary judgment on the quantum meruit
    claim for further fact finding.
    We further conclude that the dismissal of MTPC's fraud
    claim against G4S was error.    The undisputed facts establish
    fraudulent certifications.     The motion judge dismissed the count
    as duplicative, concluding that the fraudulent certifications
    provided the basis for damages under all the different claims
    presented and recovery under the fraud claim would be far less
    than the amount MTPC was allowed to retain for breach of
    contract.    Where separate recoveries are based on the same act
    and injury, duplicative recovery is precluded.    Here, however,
    further fact finding is required to discern whether there could
    be factually separable and distinguishable acts resulting in
    5
    separable quantifiable injuries.    We therefore reverse the
    allowance of summary judgment on the fraud claim.1
    1.   Background.   MTPC is a State development agency created
    and organized under G. L. c. 40J.   In 2010, MTPC received
    funding from both the Commonwealth and the Federal government to
    build a 1,200-mile fiber optic network connecting 123
    communities in western and north central Massachusetts to high-
    speed Internet (project).   An approximately $89.7 million
    construction project, it connects "[o]ver 1,100+ public safety
    entities, schools, libraries, medical facilities, and town
    halls[,] . . . serve[s] as a backbone for over 400,000
    households and businesses over a geographic area covering over
    one-third of Massachusetts, with more than one million
    residents[,] . . . [and] [p]rovides necessary broadband
    infrastructure to foster economic growth, improve health care
    and education, and strengthen public safety."   Of the $89.7
    million project, $45.4 million was funded by the American
    Recovery and Reinvestment Act of 2009, 111th Cong., Pub. L. No.
    111-5, 123 Stat. 115 (2009) (Recovery Act).   In the wake of the
    "Great Recession," the funds were to be used "in a manner that
    1 We acknowledge the amicus briefs submitted by Associated
    Builders and Contractors, Massachusetts Chapter; Associated
    General Contractors of Massachusetts; Associated Subcontractors
    of Massachusetts, Inc.; Construction Industries of
    Massachusetts, Inc.; and Utility Contractors' Association of New
    England, Inc.; and by the Attorney General.
    6
    maximize[d] job creation and economic benefit" and was intended
    to "provide a one-time injection of funds for the purpose of
    stimulating the American economy."
    Time was of the essence with respect to the dates for
    substantial completion and final completion of the project.2
    According to the initial procurement documents, the Recovery Act
    award placed "significant time constraints on the construction
    of the Project."    The design-builder thus was contractually
    2   The contract provided that "substantial completion" was
    "the date on which either (a) the Work required by the
    Contract Documents has been completed except for Work
    having a Contract Price of less than one per cent (1%) of
    the then adjusted total Contract Price, or (b) the Network,
    or an agreed upon segment of the Network, is sufficiently
    complete and connected to the Internet that Owner can use
    it for its intended purposes except for minor incomplete or
    unsatisfactory Work items that do not materially impair the
    usefulness of the Work required by the Contract Documents.
    To meet these conditions, all fiber optic cable and all
    equipment must have been installed and tested successfully
    and passed pre- and post-construction testing and ready to
    begin the conditional Network acceptance testing period,
    and all operating manuals, warranties, and as-built
    documents pertaining to that portion of the Work have been
    delivered to the Owner."
    "Final Completion" was
    "the date on which the Network, and all equipment and fiber
    supplied by or made available to the Design-Builder for
    installation in the Network, all Work is successfully
    completed, has been handed over to and accepted by Owner,
    no Work items required by the Contract Documents remain
    incomplete or unsatisfactory, and Owner has received and
    accepted all documentation and Project close-out
    deliverables required under the Contract Documents."
    7
    obligated to meet mandatory milestones:   complete fifty-five per
    cent of the value of the work by June 30, 2012; achieve
    substantial completion by April 15, 2013; and achieve final
    completion by June 30, 2013.
    MTPC put the project out to public bid, and a design-build
    contract with G4S was executed on June 30, 2011.   After
    adjustments, the total contract value was $45.5 million.     G4S
    agreed to the mandatory milestones and acknowledged that if "any
    Date for a Mandatory Milestone, after adjustment for any
    extensions of time . . . is not attained as a result of any
    failure of [G4S] to perform, then [G4S] shall pay [MTPC], as
    part of compensatory delay damages . . . for each Day . . . that
    achievement of the Mandatory Milestone" is not met as damages
    are "difficult to determine and specify accurately."3
    Damages for failure to attain substantial completion by
    April 15, 2013, was $7,500 per day and escalated to $9,500 per
    day after June 30, 2013.   Failure to attain final completion by
    June 30, 2013, was $3,000 per day; daily rates additive for any
    periods of overlap.   The contract, however, also contemplated a
    remedy should there be excused delays to the project.      Articles
    8.2.1 and 8.2.2 provided that, "[i]f [G4S] is delayed in the
    3 The contract provided that "[t]he compensatory delay
    damages . . . shall be [MTPC's] sole remedy for any failure of
    [G4S] to meet the above dates."
    8
    performance of the Work due to acts, omissions, conditions,
    events, or circumstances beyond its control and due to no fault
    of its own, . . . the Contract Time(s) for performance shall be
    reasonably extended by Change Order . . . [and G4S] shall also
    be entitled to an appropriate adjustment of the Contract Price."
    MTPC's contract with G4S set forth additional provisions,
    at issue here.   They included (1) procedures for obtaining a
    change order to adjust the contract price and time in the event
    of delay to the work; (2) MTPC's right to stop and suspend the
    work and terminate G4S for cause should G4S, among other
    reasons, fail to "timely pay, without cause . . .
    subcontractors"; (3) MTPC's obligation to facilitate timely and
    efficient performance of the work, submit conduit and pole
    attachment applications for licenses and leases, and perform any
    "Make-Ready work" necessary to permit G4S to perform its
    construction and installation work; and (4) G4S's right to,
    within ten working days of awareness of excused work delay,
    request an equitable adjustment to the contract price or an
    equitable extension of time for the reasonable costs of excused
    delays or differing site conditions.
    Following the June 30, 2011, execution of the design-build
    contract and the subsequent notice to proceed, G4S commenced the
    work.   On September 21, 2012, MTPC notified G4S of nonconforming
    9
    work and requested corrective action.4    On December 10, 2012,
    MTPC notified G4S a second time of nonconforming work and gave
    notice that G4S had failed to cure the prior nonconforming work.5
    At various times, change orders were executed throughout the
    performance of the work.   The dates to achieve substantial and
    final completion of the project were adjusted to July 31, 2013,
    and October 31, 2013, respectively.     The parties reserved their
    respective rights, stating that "[n]othing in . . . Change
    Order[s] shall be taken as a waiver of any rights or defense of
    [MTPC] and [G4S] with respect to any other request for change,
    equitable adjustment or other claim."
    On March 7, 2014, over seven months past the contractual
    substantial completion date, substantial completion of the
    4 Among other things, the notice of nonconforming work that
    Massachusetts Technology Park Corporation (MTPC) sent to G4S
    Technology LLC (G4S) alleged that G4S had been performing work
    with insufficiently skilled labor, resulting in poor
    workmanship; that G4S failed to follow industry standards with
    the installation of certain project parts; and that G4S's work
    generally suffered from a lack of planning, poor leadership, and
    poor quality. The notice acknowledges that G4S had made
    improvements over time, but it stated that more corrective
    action on behalf of G4S was needed. The notice requested a
    conference between G4S and MTPC as well as a plan of action to
    resolve the issues.
    5 MTPC sent G4S a second notice. This notice alleged that
    G4S failed to take corrective action in accordance with the plan
    laid out by the parties following the first notice. The notice
    also restated several of the issues MTPC had with G4S, including
    a general lack of planning, poor performance, and poor
    leadership.
    10
    network was achieved.   On March 21, 2014, G4S submitted a
    request for equitable adjustment (REA) seeking additional
    compensation and an extension of time for the dates of
    substantial completion and final completion.   On April 1, 2014,
    MTPC responded to G4S's REA and asserted that G4S was not
    entitled to additional time or money and that G4S was the reason
    for the delay.6   On August 15, 2014, MTPC issued a "Notice of
    Withholding" to G4S claiming damages in the amount of
    approximately $4 million resulting from the delays and failure
    to perform required tasks.7
    On September 10, 2014, G4S submitted an amended REA to MTPC
    for approximately $10 million.   G4S asserted that, because of
    MTPC's "failure to timely complete the necessary predecessor
    Make-Ready work," G4S incurred substantial additional time and
    6 Neither G4S's March 21, 2014, request for equitable
    adjustment nor MTPC's April 1, 2014, letter was in the submitted
    record.
    7 In accordance with the August 15, 2014, notice of
    withholding, MTPC withheld approximately $2 million, based on
    the liquidated damage rate of $9,500 per day for 219 days, on
    account of G4S's failure to achieve substantial completion of
    the project by July 31, 2013, the date established for
    substantial completion. Additionally, MTPC withheld $864,000,
    based on the liquidated damages rate of $3,000 per day for 288
    days, on account of G4S's failure to achieve final completion by
    October 31, 2013, the date established for final completion.
    Lastly, MTPC withheld the additional sum of approximately $1.3
    million for reimbursements due and extra cost and expenses
    incurred on account of G4S's failure to perform or complete
    required tasks.
    11
    costs in completing the project.   It explained, "The failure of
    [MTPC] to timely complete the predecessor activities to G4S
    installation work resulted in the work often being performed
    with different crew configurations, out-of-sequence, in smaller
    non-contiguous distances, utilizing premium time/extended work
    days, and often in different climatic conditions than what was
    contemplated under the baseline schedule."   The amended REA
    referenced provisions in the contract that permitted G4S to
    recover increased costs due to circumstances that were no fault
    of the design-builder.   G4S also stated that it had filed the
    necessary change orders required by article 8.2.1 and that the
    parties had reserved their rights regarding those change orders.8
    Contending that MTPC's failure was thus the "root cause of
    delays and impacts to the Project," G4S also requested another
    adjustment to the dates to achieve substantial and final
    completion of the project.   The response, if any, to the REA, is
    not in the submitted record.
    On January 20, 2015, MTPC issued a Certificate of Final
    Completion of the Work, over one year after the contractual
    final completion date.   On February 11, 2015, MTPC issued a
    recalculated and updated "Notice of Withholding" of
    approximately $4 million, to account for subsequent delays,
    7 The change orders referenced in G4S's amended REA were not
    in the submitted record.
    12
    costs, and expenses.
    G4S brought an action in the Superior Court against MTPC
    for breach of contract, breach of warranty, and quantum meruit.
    G4S asserted that MTPC's withholding of $4 million was improper
    and contended that MTPC wrongfully denied its $10 million REA.
    MTPC, in turn, brought counterclaims against G4S alleging fraud
    and violations of G. L. c. 93A.   By the start of litigation,
    MTPC had paid G4S approximately $41 million of the original $45
    million total contract value.
    During discovery, evidence revealed that, unbeknownst to
    MTPC, G4S engaged in a pattern of submitting inaccurate
    "progress payment releases" (certifications) when sending its
    applications for payment.9   As previously explained, the contract
    expressly stated that subcontractors were to be paid on time and
    that a failure to do so, without cause, was grounds for
    terminating the contract with G4S.   G4S certified to MTPC that
    it had timely paid its subcontractors, but this was not true.
    9 Through the "progress payment releases" (certifications),
    G4S represented and warranted that
    "all subcontractors, suppliers and equipment providers of
    the undersigned have been paid in full all amounts due to
    them up to the date of this Certification, and that the
    sums received in payment for the Amount Requested shall be
    used to forthwith pay in full all amounts due to such
    subcontractors, suppliers and equipment providers up to the
    date hereof."
    13
    Spanning more than one year, G4S, a publicly traded company,
    repeatedly and continuously delayed payments to its
    subcontractors until after its fiscal quarters closed, so it
    could show a more favorable cash flow in its quarterly reports.10
    In sum, G4S received $38.6 million in progress payments
    through sixty false certifications.   The work had been
    performed, but the subcontractors had not been paid prior to the
    certifications.
    The delayed payments did not go unnoticed by the
    subcontractors.   At various times, subcontractors strongly
    objected and threatened to shut down work or remove crews from
    the project if G4S continued to withhold payments, even as G4S
    was getting paid by MTPC.11   Despite such protests, there was no
    10G4S's contract manager, who was responsible for paying
    subcontractors, acknowledged in contemporaneous electronic mail
    (e-mail) messages as well as in her later deposition that there
    remained past due invoices for significant sums that were
    outstanding at the time the certifications were executed. The
    certifications were nevertheless submitted to MTPC. One
    internal e-mail message from a G4S project manager criticized
    this practice stating, "How can we tell sub[contractors] that
    they aren't getting paid so our books look better? There's
    something wrong with that."
    11For example, in an e-mail message to G4S, one
    subcontractor wrote, "I think it is extremely unfair that you
    are not honoring our contract. . . . The issue that bothers me
    the most is that you are not making payment [in order] to better
    your books but don't care about the books of the companies that
    support you." Another subcontractor wrote to G4S that they were
    owed $358,275, which presented a "significant problem" for the
    subcontractor as it sought to pay its work crews.
    14
    indication from the submitted record that any of the
    subcontractors demanded direct payment of balances due from
    MTPC, as was the subcontractors' statutory right under G. L.
    c. 30, § 39F,12 nor did they shut down work or remove crews.
    MTPC moved for summary judgment, and in March, 2016, the
    judge granted summary judgment to MTPC as to G4S's complaint.
    The judge concluded that G4S intentionally committed a breach of
    the contract and thus, without complete and strict performance
    of all of the contract's terms, could not recover on the
    contract.   The judge, relying on an older line of cases that we
    overrule today, also concluded that G4S could not recover under
    a theory of quantum meruit because an intentional violation of a
    contract provision was inconsistent with a finding of good faith
    and barred all such recovery unless the violation was deemed "so
    trifling as to fall within the rule de minimis."     See 
    Andre, 305 Mass. at 516
    .   G4S's payment delays and false certifications
    were inconsistent with the good faith requirement.    In January,
    2017, in a subsequent decision, the judge dismissed MTPC's
    counterclaims of fraud and G. L. c. 93A.   The judge reasoned
    12General Laws c. 30, § 39F (d), provides: "If, within
    seventy days after the subcontractor has substantially completed
    the subcontract work, the subcontractor has not received from
    the general contractor the balance due under the subcontract
    . . . , the subcontractor may demand direct payment of that
    balance from the awarding authority."
    15
    that permitting additional compensation to MTPC under a theory
    of fraud would be improperly duplicative because the underlying
    conduct forming the basis of MTPC's fraud claim was the same as
    the contract claim.     The judge also noted that MTPC, as a public
    entity acting pursuant to a legislative mandate, was not acting
    in a business context and therefore was not engaged in trade or
    commerce for the purposes of G. L. c. 93A.     G4S appealed from
    the Superior Court decision, and we granted its application for
    direct appellate review.
    2.    Discussion.    "Our review of a motion judge's decision
    on summary judgment is de novo, because we examine the same
    record and decide the same questions of law."     Kiribati Seafood
    Co. v. Dechert LLP, 
    478 Mass. 111
    , 116 (2017).     "The standard of
    review of a grant of summary judgment is whether, viewing the
    evidence in the light most favorable to the nonmoving party, all
    material facts have been established and the moving party is
    entitled to judgment as a matter of law" (citation omitted).
    Casseus v. Eastern Bus Co., 
    478 Mass. 786
    , 792 (2018).     Here, we
    affirm the decision to grant summary judgment on the contract
    claim, but conclude that there are material disputed facts
    precluding summary judgment on the quantum meruit and fraud
    claims.
    a.    Complete and strict performance of all construction
    contract terms.   "The law has long been settled in this
    16
    Commonwealth, in relation to building contracts, that a
    contractor cannot recover on the contract itself without showing
    complete and strict performance of all its terms . . . ."
    
    Andre, 305 Mass. at 516
    .   See Peabody N.E., Inc. v. Marshfield,
    
    426 Mass. 436
    , 441 (1998); United States Steel v. M. DeMatteo
    Constr. Co., 
    315 F.3d 43
    , 50 (1st Cir. 2002).   G4S claims that
    the complete and strict performance requirement is outdated and
    asks us to adopt instead the "materiality rule" set forth in
    Restatement (Second) of 
    Contracts, supra
    at §§ 237, 241.13    We
    13Restatement (Second) of Contracts § 237 (1981) provides:
    "[I]t is a condition of each party's remaining duties to render
    performances to be exchanged under an exchange of promises that
    there be no uncured material failure by the other party to
    render any such performance due at an earlier time."
    Section 241 presents five factors to consider whether a
    failure is material:
    "In determining whether a failure to render or to offer
    performance is material, the following circumstances are
    significant:
    "(a) the extent to which the injured party will be
    deprived of the benefit which he reasonably expected;
    "(b) the extent to which the injured party can be
    adequately compensated for the part of that benefit of
    which he will be deprived;
    "(c) the extent to which the party failing to perform
    or to offer to perform will suffer forfeiture;
    "(d) the likelihood that the party failing to perform
    or to offer to perform will cure his failure, taking
    account of all the circumstances including any reasonable
    assurances;
    17
    decline this invitation.   We do, however, interpret the complete
    and strict performance requirements in construction contracts as
    being limited to the design and construction itself, as
    explained infra.   All of our previous holdings imposing complete
    and strict performance have concerned breaches of the actual
    design and construction of the project.
    Our construction law cases have emphasized the importance
    and need for strict compliance with construction law contracts
    to ensure that the construction itself is done safely and
    correctly according to design specifications.   See, e.g., Russo
    v. Charles I. Hosmer, Inc., 
    312 Mass. 231
    , 233-234 (1942)
    (failure to follow design requirements in guard rails posed
    public safety problems).   This is particularly true as defects
    are difficult to identify and expensive to fix in a finished
    project.   See 
    id. at 233
    (deviation from number of steel rods
    cast in concrete to provide support for highway guard rail
    unknown to owner); Bowen v. Kimbell, 
    203 Mass. 364
    , 368 (1909)
    (cost to cure deviation from building specification after
    building's construction disproportionately high).   Thus, we have
    not tolerated any breaches that relate to whether the
    "(e) the extent to which the behavior of the party
    failing to perform or to offer to perform comports with
    standards of good faith and fair dealing."
    18
    construction was completed according to design specifications.
    See Peabody N.E., 
    Inc., 426 Mass. at 437
    , 441 (failure to
    substantially complete construction of septage and grease waste
    facility by terms of agreement not complete and strict
    performance); J.A. Sullivan Corp. v. Commonwealth, 
    397 Mass. 789
    , 790 (1986) (failure to complete itemized list of finish
    work, corrections, repairs, and services for construction of
    public college building not complete and strict performance);
    Albre Marble & Tile Co. v. Governman, 
    353 Mass. 546
    , 549-550
    (1968) (failure to ensure satisfactory surfaces before tile
    installation not complete and strict performance); 
    Russo, supra
    (failure to install highway guard rail in accordance with terms
    specifying number of steel rods not complete and strict
    performance); 
    Andre, 305 Mass. at 516
    -517 (failure to comply
    with plans and specifications of house construction not complete
    and strict performance); 
    Bowen, supra
    (failure to use correct
    ratio as provided in specifications for making plaster not
    complete and strict performance); Hayward v. Leonard, 
    7 Pick. 181
    , 185 (1828) (failure to build house to specifications not
    complete and strict performance).
    In the instant case, design and construction provisions
    that would require strict and complete performance would
    include, for example, the following:
    "The fiber optic cable and infrastructure system shall be
    19
    designed and installed for a minimum life expectancy of 30
    years[.]"
    "All fiber strands and buffer tubes shall be color coded
    with highly distinguishable, vibrant colors[.]"
    "The fiber cable shall have a circular cross section so
    that aerial installation can be done with standard sheaves
    and tensioning equipment[.]"
    "The . . .Fiber Optic Network will consist of a core fiber
    backbone with extensions to two (2) major . . . regional
    network centers located at One Summer Street in Boston, MA
    and One Federal Street in Springfield, MA."
    We recognize, however, that construction contracts can be
    thousands of pages long, containing all types of different
    provisions.14   We have not considered in our cases the
    consequences of breaches of construction contract provisions
    that are subsidiary to or supportive of the design and
    construction, but do not directly involve the design and
    construction itself.   We clarify today that the complete and
    14Here, the 1,400-page contract between MTPC and G4S
    provided many provisions unrelated to the actual construction
    work. Examples of such provisions include (1) G4S was to submit
    printed copies of required manuals in "heavy-duty, commercial-
    quality, durable, 3-ring, vinyl covered, loose-leaf binders, in
    thickness necessary to accommodate contents, sized to receive 8-
    1/2" by 11" paper. The binder spine shall provide a clear
    plastic sleeve to hold labels identifying the contents"; (2) G4S
    was to ensure that the Recovery and Reinvestment Act of 2009
    logo emblem was at least six inches or larger in diameter and
    ensure clear space surrounding the logo equal to one-half of the
    logo's radius; and (3) G4S was required to provide, for MTPC
    field inspectors, offices with a "minimum of 200 square feet of
    usable space with . . . a [d]esk, desk chair, visitor chair and
    plan table[,] . . . [p]ortable radio with contractor frequencies
    and charger[,] . . . [and] [w]eekly office cleaning services."
    20
    strict performance requirements in construction contracts apply
    only to the design and construction work itself.   Other
    provisions should be analyzed pursuant to ordinary contract
    principles, including the materiality standard applied under
    Massachusetts contract law.    See EventMonitor, Inc. v. Leness,
    
    473 Mass. 540
    , 546 (2016), quoting Anthony's Pier Four, Inc. v.
    HBC Assocs., 
    411 Mass. 451
    , 470 (1991); Buchholz v. Green Bros.,
    
    272 Mass. 49
    , 52 (1930), S.C., 
    290 Mass. 350
    (1935).15
    The question then becomes what is the legal status of the
    contractual violations here.   The construction contract at issue
    was to "design, furnish, build and equip a complete fiber optic
    network system . . . for a fully implemented, functional and
    tested system" in accordance with the project construction
    schedule.   The "Work" was defined broadly as comprising
    "all Design-Builder's design, construction and other
    services required by the Contract Documents, including
    procuring and furnishing all materials, equipment, services
    and labor specified by or reasonably inferable from the
    Contract Documents, to develop, install, and test the
    Network, and including the submission and delivery of all
    documents and other things as required or reasonably
    inferable from the Contract Documents."
    The contractual violations at issue did not concern the actual
    15We decline to adopt the materiality standard of the
    Restatement (Second) as argued by G4S. We recognize, however,
    that many of the different elements of the Restatement
    materiality standard are considered in either our contract or
    our quantum meruit analysis.
    21
    design and construction of the project.   Instead, they were
    about the timing of payments to subcontractors and the
    documentation concerning those payments.16   G4S delayed payments
    and filed false certifications to allow it, a public company, to
    report inflated revenues for its quarterly reports.    We thus
    analyze these violations under a materiality standard, not
    complete and strict performance.
    In the Commonwealth, a material breach of a contract occurs
    when the breach concerns an "essential and inducing feature of
    the contract."   See EventMonitor, 
    Inc., 473 Mass. at 546
    ,
    quoting Anthony's Pier Four, 
    Inc., 411 Mass. at 470
    .   Essential
    and inducing features of a contract are provisions that are "so
    serious and so intimately connected with the substance of the
    contract[]" that a failure to uphold the provision would justify
    16Contract terms defining payment or reporting requirements
    may have an impact on construction but they are not design and
    construction contract terms analyzed pursuant to the complete
    and strict performance requirement. Rather they are analyzed
    according to the materiality standard. For example, payment
    delays or disputes may cause subcontractors to stop or slow down
    work by temporarily pulling crews or reducing the number of
    workers. That would result in delays in the construction, but
    even delays in the construction are different from the design
    and construction itself. If, however a subcontractor, having
    not received timely payments, installs an insufficient amount of
    highway guard rails, uses plastering of inferior quality, or
    does not complete the project, such breaches would be analyzed
    under complete and strict performance. See Peabody N.E., Inc.
    v. Marshfield, 
    426 Mass. 436
    , 441 (1998); Russo v. Charles I.
    Hosmer, Inc., 
    312 Mass. 231
    , 233-234 (1942); Bowen v. Kimbell,
    
    203 Mass. 364
    , 368 (1909).
    22
    the other party walking away from the contract and no longer
    being bound by it.   See 
    Buchholz, 272 Mass. at 52
    (failure to
    make monthly payments as agreed to in contract material breach
    because payments "essential and inducing feature").
    There can be little doubt that paying subcontractors on
    time was an essential and inducing feature of the contract
    between MTPC and G4S.   See 
    Buchholz, 272 Mass. at 52
    (in
    contract to paint and maintain signs, payment of wage "essential
    and inducing feature").   The "[p]rompt payment of subcontractors
    on public works is a consistent legislative purpose."       Manganaro
    Drywall, Inc. v. White Constr. Co., 
    372 Mass. 661
    , 664 (1977).
    This is particularly true here, where a significant portion of
    the project funding came from the Recovery Act, the purpose of
    which was to "maximize[] job creation and economic benefit" and
    "provide a one-time injection of funds for the purpose of
    stimulating the American economy."
    The contract itself also stressed the importance of timely
    payments to subcontractors.   As provided in article 10.2 of the
    contract's general conditions, MTPC could walk away from the
    contract and no longer be bound by its terms if G4S failed to
    timely pay subcontractors.    G4S's repeated instances of
    intentionally failing to timely pay subcontractors in accordance
    with the agreed-upon contract was therefore a material breach of
    the contract, barring G4S from recovering breach of contract
    23
    damages.   See 
    Buchholz, 272 Mass. at 55
    .17
    G4S not only delayed the payments but also falsely
    certified that it had made the payments, thereby magnifying and
    multiplying the number of material breaches.     The contract here
    independently required proper certification of payments.       Those
    provisions were intentionally violated.    Intentional
    misrepresentations to the government for financial gain are
    significant breaches of contract in and of themselves and can be
    serious civil and criminal offenses.18    In the words of Justice
    Holmes, contractors "must turn square corners when they deal
    with the Government."   Rock Island, Ark. & Louisiana R.R. v.
    United States, 
    254 U.S. 141
    , 143 (1920).      G4S did the opposite,
    cutting those corners for improper purposes.     In sum, the
    delayed payments and the false certifications here were material
    17G4S argues that the subcontractors were eventually paid
    and thus the breach was cured. Given the importance of timely
    payment, we do not consider the delayed payments a cure for the
    contractual violation. They do, however, have an impact on the
    equities and the quantum meruit analysis.
    18We note that persons or corporations who make a
    fraudulent claim for payment to a State government entity are
    subject to civil penalties under the Massachusetts False Claims
    Act, G. L. c. 12, §§ 5A-5O. When any funding for a public
    contract is provided by the Federal government, civil and
    criminal sanctions may also be pursued under the civil or
    criminal False Claims Act. See 31 U.S.C. §§ 3729-3733 (civil);
    18 U.S.C. § 287 (1986) (criminal). Additionally, the Division
    of Capital Asset Management and Maintenance may suspend or debar
    persons who wilfully supply materially false information while
    performing a public contract. G. L. c. 29, § 29F.
    24
    breaches of the contract precluding recovery on G4S's contract
    claim.
    b.   Recovery under quantum meruit.   G4S contends that even
    if it is not entitled to pursue its contract claim, it should be
    allowed to recover under a quantum meruit theory.     We conclude
    that there are genuine issues of material fact in dispute on the
    quantum meruit claim.     To recover under quantum meruit in a
    construction case, a contractor must prove both substantial
    performance of the contract and an endeavor in good faith to
    perform the work fully.     J.A. Sullivan 
    Corp., 397 Mass. at 796
    ;
    Albre Marble & Tile 
    Co., 353 Mass. at 550
    ; 
    Andre, 305 Mass. at 516
    .   "The underlying basis for [recovery under quantum meruit]
    is derived from principles of equity and fairness, to prevent
    unjust enrichment of one party . . . at the expense of another
    . . . ."    Malonis v. Harrington, 
    442 Mass. 692
    , 697 (2004).
    Although "clean hands" are important in determining equitable
    relief, we also have recognized that this is not an absolute
    proposition, as the purpose of the doctrine is to allow courts
    to produce a just result.    Walsh v. Atlantic Research Assocs.,
    
    321 Mass. 57
    , 62 (1947).     The proper focus is on the value of
    the benefit conferred.     In a construction contract, "[t]he
    amount of recovery on a claim based in quantum meruit is the
    fair and reasonable value of material and labor supplied to the
    benefiting party."     J.A. Sullivan Corp., supra at 797.   "It is
    25
    not the policy of our law to award damages which would put [the
    nonbreaching party] in a better position than if the [breaching
    party] had carried out [its] contract."     Ficara v. Belleau, 
    331 Mass. 80
    , 82 (1954).   The nonbreaching party is "entitled to be
    made whole and no more."    
    Id. See J.A.
    Sullivan Corp., supra at
    794 (principle of equity and fairness cautions against
    "produc[ing] a windfall").
    In the instant case there was, without dispute, substantial
    performance by the contractor.    A critical and complex project
    providing a fiber optic network for western and north central
    Massachusetts has been completed according to its design.     The
    project was, however, delayed.    The cause of those delays is
    bitterly disputed in the record.    G4S has raised a genuine issue
    of material fact that MTPC is responsible for those delays due
    to its failure to complete the make-ready work on time.
    More complicated is the good faith requirement.     The motion
    judge concluded that it was undisputed that G4S did not act in
    good faith given its numerous delayed payments to contractors
    and false certifications.    She held that intentional violation
    of these contract provisions precluded a finding of good faith
    fully to perform.   Support for this holding and the short-
    circuiting of the rest of the equitable analysis certainly
    exists, in a line of older cases that the judge properly cited.
    For example, in J.A. Sullivan 
    Corp., 397 Mass. at 797
    , quoting
    26
    
    Andre, 305 Mass. at 516
    , we reiterated that "[g]enerally, '[i]n
    the absence of special exculpating circumstances an intentional
    departure from the precise requirements of the contract is not
    consistent with good faith in the endeavor fully to perform it,
    and unless such departure is so trifling as to fall within the
    rule de minimis, it bars all recovery."   The simplicity and
    severity of this approach, which dates back to Sipley v.
    Stickney, 
    190 Mass. 43
    , 46 (1906), and Homer v. Shaw, 
    177 Mass. 1
    , 5 (1900), has, however, been criticized in leading treatises
    on contract law.   See 8 C.M.A. McCauliff, Corbin on Contracts
    § 36.8, at 354 (J.M. Perillo ed., rev. ed. 1999); S. Williston,
    Contracts § 842, at 2364 n.4 (rev. ed. 1936).   This rule also
    has been questioned, and even distinguished by this court, but
    this older line of cases has not been overruled.   See 
    Walsh, 321 Mass. at 62
    (describing Sipley doctrine as rigid rule of law
    that has been criticized as "too severe").   We expressly
    overrule this line of cases and rearticulate the doctrine of
    quantum meruit today.
    We conclude that intentional breaches, even those involving
    material breaches, alone are not dispositive of the right to
    equitable relief, at least when such breaches do not relate to
    the construction work itself.   Good faith is a requirement for
    recovery under quantum meruit, but ruling in equity, this
    requirement is not one that is "too rigid and unyielding for the
    27
    practical accomplishment of justice."    J.A. Sullivan 
    Corp., 397 Mass. at 797
    , quoting Morello v. Levakis, 
    293 Mass. 450
    , 453
    (1936).    We have emphasized that "[t]he doctrine of clean hands
    is not one of absolutes and should be so applied as to
    accomplish its purpose of promoting public policy and the
    integrity of the courts."    
    Walsh, 321 Mass. at 66
    (allowing
    recovery in quantum meruit even for plaintiff who intentionally
    committed breach of employment contract provision).   There is no
    simple formula to apply here, but rather numerous factors to
    analyze.   We thus conclude that in evaluating the contractor's
    good faith and right to recover under quantum meruit, we must
    consider the contract performance as a whole, taking into
    account both parties' actions, the different contractual
    breaches and the damages they caused, and most importantly the
    value of the project provided as compared to the amount paid for
    that work.    We must, in the end, balance the equities and
    produce a just result.    See 
    id. (in quantum
    meruit case, court
    declined to deprive plaintiff of all earnings during employment
    despite bad faith material breach of employment contract).      See
    also Meehan v. Shaughnessy, 
    404 Mass. 419
    , 438-439 (1989)
    (departing law firm partner did not forfeit accrued profits
    despite intentional breach of partnership contract and fiduciary
    duties because there was no causal connection between law firm's
    claimed losses and breaches).
    28
    Here, G4S completed the project as specified, albeit with
    delays.   MTPC deducted $4 million, of which a significant sum
    was damages for delay.   Whether one party or the other or both
    were responsible for the delays remains disputed on this record.
    Resolution of this issue has an impact on the over-all balancing
    of the equities in the instant case.    If MTPC was responsible
    for some or all of those delays and nevertheless withheld the
    amount, MTPC's own contractual violations would need to be
    considered in the equitable analysis.   If those violations were
    intentional, that would also be a factor in the balancing of
    equities.   Furthermore, G4S has introduced evidence to support
    its claim that it has performed $10 million in uncompensated
    work because of MTPC's failure to perform make-ready work.     If
    G4S's $10 million REA has merit, this represents a significant
    amount of value supplied to MTPC without cost and may constitute
    a windfall.   See J.A. Sullivan 
    Corp., 397 Mass. at 794
    ; 
    Ficara, 331 Mass. at 82
    .    It would thus "work great hardship to deprive"
    G4S of compensation for extra work conferred over the three-year
    project given that the design and construction of the network
    was satisfactory.   See 
    Walsh, 321 Mass. at 66
    .
    Finally, although there was not good faith and clean hands
    in the context of prompt payments to subcontractors or truthful
    certifications to MTPC, it is unclear from the submitted record
    whether there is any causal connection between these contractual
    29
    violations and any damages to MTPC.   It is undisputed that the
    work had been done prior to the certifications.   It also appears
    from this record that the subcontractors, not MTPC, suffered the
    consequences of the delayed payments by continuing to work
    despite the payment delays.   The record before us, as the motion
    judge recognized, contains no evidence that the delayed payments
    or false certifications had an impact on or affected the
    construction, the delays in the completion of the project
    resulting in the withholding of liquidated damages, or the $10
    million of extra work alleged in the REA.19   See 
    Meehan, 404 Mass. at 438-439
    (no causal connection between breach and
    damages claimed).
    We conclude that resolution of these disputed factual
    questions is necessary to determine whether equitable relief is
    appropriate in the instant case.   The responsibility for the
    delay, the amount of extra uncompensated work, and the presence
    or absence of any causal connection between the intentional
    breaches and any damage to MTPC are all relevant to a just
    resolution of the quantum meruit claim.   If the delays were
    caused by MTPC, G4S has performed and paid for $10 million in
    19The lack of impact on the construction appears to be
    because of the patience and accommodation of the subcontractors
    that put up with, and even suffered from, G4S's misconduct,
    without complaining to MTPC or demanding direct payment as was
    their right.
    30
    extra work to complete the project, and the payment delays to
    subcontractors and false certifications had no impact on the
    project's construction or completion date, it would be
    inequitable for MTPC to withhold compensation from G4S for the
    reasonable value of its labor and materials in excess of the
    amounts already paid to G4S.   
    Meehan, 404 Mass. at 447
    .   See
    Harness Tracks Sec., Inc., v. Bay State Raceway, Inc., 
    374 Mass. 362
    , 367-368 (1978).
    c.   Fraud.   MTPC contends that its counterclaim against G4S
    for fraud was improperly dismissed.   The motion judge sua sponte
    dismissed MTPC's fraud claim against G4S.   She relied on Szalla
    v. Locke, 
    421 Mass. 448
    , 454 (1995), in which this court held:
    "Where the same acts cause the same injury under more than one
    theory, duplicative damage recoveries will not be permitted."
    Applying Szalla, the motion judge reasoned that "the conduct
    that forms the basis of MTPC's fraud claim is precisely the same
    as that which caused this Court to conclude that G4S had
    necessarily forfeited its affirmative claims against MTPC.     As a
    consequence . . . , [MTPC] no longer had to justify the $4
    million it retained of the Contract balance; the upshot was that
    it was effectively provided with an award that more than covered
    any loss that it suffered as a result of paying G4S
    prematurely."
    We agree that summary judgment on the fraud claim may be
    31
    appropriate only under a duplicative damages analysis.     However,
    "where the acts complained of . . . are factually separable and
    distinguishable . . . , there is no error in permitting separate
    recoveries for separable injuries."   Calimlim v. Foreign Car
    Ctr., Inc., 
    392 Mass. 228
    , 236 (1984).   "Permitting awards under
    several counts where claims and injuries are factually
    distinguishable, but disallowing such recovery where they are
    not, will serve to avoid over or under compensation."     
    Id. Here, there
    may be separable and distinguishable acts
    forming the basis of recovery under the breach of contract and
    fraud claims.   A fact finder could determine that the delayed
    completion of the project could be the basis for the breach of
    contract claim and the false certifications that subcontractors
    were timely paid could be the basis for the fraud claim.     MTPC
    withheld $4 million as separable recovery for the breach of
    contract because of the delay, using the liquidated damages
    provision to calculate the amount of the withholding.20    MTPC
    additionally claims that the false certifications caused it to
    20The fact that the fraudulent certifications and delayed
    payments to subcontractors also provide a basis for breach of
    contract is not dispositive. If G4S was responsible for the
    delays, an issue that cannot be decided on summary judgment,
    those delays provided a much more straightforward basis for
    calculating damages for breach of contract than the false
    certifications.
    32
    pay G4S prematurely, resulting in the loss of $1.67 million,
    which it asserts is another injury for which it thus is entitled
    to separable recovery.21   Whether this claim has merit and
    whether such calculations of damages are correct require further
    fact finding, but some recovery, at least for the loss of the
    time value of money, may be justified.
    Whether the monetary loss for MTPC due to fraud is less
    than the monetary loss due to breach of contract also should be
    determined.   This appears to depend on who was responsible for
    the delays; G4S's recovery, if any, under quantum meruit; and
    whether the losses due to fraud claimed by MTPC have been
    grossly inflated.   Whether the damages, if any, caused by the
    false certifications are duplicative thus cannot be determined
    on this record.   We therefore reverse the allowance of summary
    judgment on the fraud claim.
    3.   Conclusion.   For the reasons discussed, we affirm the
    summary judgment decision on the breach of contract claim and
    reverse the summary judgment decision on the quantum meruit and
    21MTPC and G4S also dispute the amount of loss, asserting
    it to be $1.67 million and $1,757.48, respectively. MTPC
    calculated $1.67 million based on lost interest accrued at the
    prime rate of 3.25 per cent per annum interest from the date of
    each payment until June, 2, 2014, the date of MTPC's last
    payment to G4S. G4S, in turn, asserts that lost interest based
    on alleged late subcontractor payments would result only in
    $1,757.48 based on a thirty-day yield of 0.22 per cent interest
    calculated for only the period that the payment was late.
    33
    fraud claims.   We remand the matter to the Superior Court for
    proceedings consistent with this opinion.
    So ordered.