Nantasket Beachfront Condominiums, LLC v. Hull Redevelopment Authority , 87 Mass. App. Ct. 455 ( 2015 )


Menu:
  • NOTICE: All slip opinions and orders are subject to formal
    revision and are superseded by the advance sheets and bound
    volumes of the Official Reports. If you find a typographical
    error or other formal error, please notify the Reporter of
    Decisions, Supreme Judicial Court, John Adams Courthouse, 1
    Pemberton Square, Suite 2500, Boston, MA, 02108-1750; (617) 557-
    1030; SJCReporter@sjc.state.ma.us
    14-P-222                                               Appeals Court
    NANTASKET BEACHFRONT CONDOMINIUMS, LLC      vs.   HULL REDEVELOPMENT
    AUTHORITY.
    No. 14-P-222.
    Plymouth.     November 7, 2014. - June 5, 2015.
    Present:   Rapoza, C.J., Milkey, & Hanlon, JJ.
    Contract, Performance and breach, Implied covenant of good faith
    and fair dealing, Damages, Provision for liquidated
    damages, Termination. Practice, Civil, Summary judgment,
    Damages, Waiver. Redevelopment Authority. Administrative
    Law, Conflict of interest. Conflict of Interest. Public
    Employment, Unethical conduct. State Ethics Commission.
    Waiver. Damages, Breach of contract, Liquidated damages.
    Civil action commenced in the Superior Court Department on
    February 8, 2012.
    The case was heard by Robert C. Cosgrove, J., on motions
    for summary judgment.
    Brian K. Bowen for the plaintiff.
    Denise A. Chicoine (Edward S. Englander with her) for the
    defendant.
    MILKEY, J.     In 2004, plaintiff Nantasket Beachfront
    Condominiums, LLC (Nantasket) and defendant Hull Redevelopment
    2
    Authority (authority) entered into a contract for the purchase
    and development of certain land in Hull.    Under that "LAND
    DISPOSITION AGREEMENT" (LDA), Nantasket was to purchase the
    land, construct seventy-two units of housing, and develop a new
    public park.   Subsequently, the proposed project encountered
    robust neighborhood opposition, and this in turn led to
    significant delays in the anticipated closing.     Eventually, the
    authority terminated the LDA and notified Nantasket that it was
    retaining as liquidated damages $857,500 in deposits that
    Nantasket had made.   This action ensued.
    In a comprehensive and thoughtful decision, a Superior
    Court judge ruled in the authority's favor on summary judgment.
    He concluded that Nantasket indisputably stood in breach of the
    LDA, and that the authority was within its rights to terminate
    the agreement and to retain the deposits.   On Nantasket's
    appeal, we affirm, albeit on somewhat different grounds.
    Background.1    The parties execute the LDA.   In order to spur
    the development of twelve acres of land that it owned, the
    authority in October of 2003 issued a detailed "Request for
    Proposals" (RFP).   According to the RFP, the property "provides
    the transition between the [State-owned] . . . Nantasket Beach
    1
    The facts, which are largely uncontested, are drawn from
    the summary judgment record. We view the facts in a light most
    favorable to Nantasket, the nonmoving party. See Godfrey v.
    Globe Newspaper Co., Inc., 
    457 Mass. 113
    , 118-119 (2010).
    3
    Reservation and a major residential area of the Town of Hull
    along Nantasket Avenue."   The RFP set forth a preferred
    development scenario in which approximately three-quarters of
    the land would be developed into "primarily passive public open
    space," with the rest (approximately three acres) developed as
    "residential dwelling units, or other uses, as may be acceptable
    to the [authority]."   In a section entitled "Site Constraints
    and Issues," the RFP discussed the applicability of various
    environmental and land use requirements.
    Only two developers submitted proposals.    One was from
    Nantasket's parent company, which emphasized that, based on its
    thirty years of experience in developing residential and
    commercial projects, it was "well versed in overcoming a
    multitude of tough regulatory issues and environmental
    concerns."   On July 9, 2004, Nantasket and the authority
    executed the LDA, which spelled out their respective rights and
    obligations in thirty-three single-spaced pages (not including
    voluminous attachments).
    Under the LDA, Nantasket would purchase the land for three
    and one-half million dollars (subject to various potential
    adjustments).   Nantasket would then build seventy-two units of
    housing, develop the open space, and eventually return the park
    land to public ownership and control.   Nantasket's specific
    development plans were subject to its completing the authority's
    4
    design review process and obtaining -- at its expense -- all
    necessary permits and other approvals (collectively termed
    "Approvals") from other State and local agencies.    The closing
    date was set for thirty days after Nantasket obtained the
    Approvals, but not later than July 9, 2006 (termed the "Outside
    Closing Date").   Thus, as originally executed, the LDA
    contemplated that all necessary permitting and the closing would
    be completed within two years.
    Deposits.     Nantasket paid a $97,000 deposit to the
    authority at the execution of the LDA, in addition to a $25,500
    deposit it had previously paid.    An additional deposit of
    $122,500 was due on August 17, 2004, bringing the total deposit
    due by that point to $245,000.    Until the closing actually took
    place, additional deposit payments of $122,500 each would be due
    at the six month anniversary of the date of the LDA and the one
    year anniversary, and then "Extension Deposits" of $122,500 each
    would be due every three months after that.    The LDA stated that
    if Nantasket missed any deposit payment, this "shall constitute
    a default."
    Termination rights.     The LDA gave each party the right to
    terminate the agreement in certain situations.    In the event
    that Nantasket defaulted on its obligations and did not achieve
    a cure of that default within thirty days of receiving written
    notice from the authority, the authority could terminate the LDA
    5
    and retain all deposits paid.2    For its part, Nantasket could
    terminate the LDA and secure a return of its deposits in three
    different types of scenarios.    First, Nantasket was given until
    August 4, 2004, to inspect the property, and until August 16,
    2004, to inspect the title.     If such inspections revealed a
    defect in either, then it could terminate the LDA within those
    respective deadlines.    Second, Nantasket could terminate the LDA
    in the event that a local permitting agency prevented the
    project from going forward as planned and adjustments to the
    project or purchase price could not be agreed upon to
    accommodate the potential loss in value (this scenario was
    termed a "Local Permit Problem").     Third, if a third party
    challenged the issuance of one or more of the approvals that the
    project needed, Nantasket could terminate the LDA in lieu of
    defending the action.
    Project delays.     Almost immediately, the project sparked
    significant opposition from local residents.     In 2004,
    Jacqueline Chase, a direct abutter, cofounded a group to try to
    stop it.   At Chase's suggestion, the group called itself "No Way
    HRA!"    The project opponents used every opportunity to attempt
    to derail the project.    Chase herself attended seventy local
    2
    The thirty-day cure period could be extended if the
    default could not be cured within thirty days even with the
    exercise of due diligence. Nantasket has never argued that this
    provision applies here.
    6
    board meetings on the topic.    After the Hull zoning board of
    appeal (ZBA) issued a special permit for the project on March
    30, 2006, six project opponents filed an action in Superior
    Court appealing the special permit pursuant to G. L. c. 40A,
    § 17.    The lead plaintiffs in that action (zoning appeal) were
    Chase and Phyllis Aucoin, another leading member of No Way HRA!.
    First amendment to the LDA.    Nantasket did not use the
    filing of the zoning appeal as an occasion to terminate the LDA,
    but instead elected to defend it.    However, with it becoming
    increasingly obvious that Nantasket could not obtain all
    approvals by July 9, 2006 (the original Outside Closing Date),
    Nantasket requested and secured an amendment to the LDA.     This
    amendment dated May 10, 2006, set a new closing date of forty
    days after Nantasket received all approvals, but in no event
    later than the earlier of:     (1) ninety days after the "Appeals
    Termination Date" (set as the date that the zoning appeal and
    any other appeals of project approvals eventually were resolved
    in Nantasket's favor),3 or (2) July 9, 2012 (the amended Outside
    3
    The "Appeals Termination Date" was defined in full as the
    date "of the final disposition, in favor of the validity of the
    Approvals, of all appeals challenging or appealing the issuance
    of any Approval, including without limitation the Zoning Appeal,
    including the exhausting of all further appeals or the
    expiration of the time for bringing any further appeal."
    7
    Closing Date).4   The parties also agreed that after Nantasket
    paid the additional Extension Deposits due on July 9, 2006, and
    October 9, 2006 (bringing the total deposits held by the
    authority to $857,500), further Extension Deposits would be
    waived until the Appeals Termination Date.5
    Chase and Aucoin join the authority's board.    In 2007,
    Chase and Aucoin ran for, and were elected to, the authority's
    board.    Even after that, they continued their active opposition
    to the project in their personal capacity.    Thus, for example,
    after a Superior Court judge in 2008 ruled in Nantasket's favor
    on summary judgment in the zoning appeal, Chase and Aucoin
    joined in appealing that decision to this court.
    Second amendment to the LDA.    With the continued delays,
    Nantasket requested a further extension of the Outside Closing
    Date, and also requested that Chase and Aucoin recuse themselves
    from participating in matters concerning the project.      On August
    3, 2009, by a vote of three to one (with one abstention), the
    authority's board extended the Outside Closing Date to July 9,
    2015.    Chase voted against the extension, while Aucoin
    abstained.
    4
    As part of the first amendment, Nantasket expressly waived
    its right to terminate the LDA based on the filing of the zoning
    appeal.
    5
    The parties also agreed to reduce the purchase price of
    the land by $125,000, because of a reduction in the scope of the
    project required by the special permit.
    8
    The end of the zoning appeal.      The zoning appeal was
    finally resolved on May 3, 2010, when a stipulation of dismissal
    was filed in this court.    This removed a significant obstacle to
    the project's moving forward, but others remained.    Indeed,
    changes to the project that resulted from review by the State
    Department of Environmental Protection pursuant to the Wetlands
    Protection Act, G. L. c. 131, § 40, meant that Nantasket would
    have to resubmit the project for various additional local
    approvals.   Meanwhile, changes to the real estate market in the
    interim called into question the financial viability of the
    project.   In fact, as Nantasket acknowledged in a letter to the
    authority dated September 10, 2010, "[t]here exists no bank
    financing available for this project, and there are no equity
    partners willing to invest in it."
    Nantasket's efforts to renegotiate the deal.      Under the
    express terms of the LDA, Nantasket's inability to obtain
    financing did not constitute a force majeure event excusing its
    performance.   In light of the new circumstances it faced,
    Nantasket sought to renegotiate the terms of the original deal.
    In its September 10, 2010, letter, Nantasket proposed to
    construct the park improvements immediately using a portion of
    the deposit funds, with the remainder of the funds to be
    returned to Nantasket.     Also, the housing would be developed in
    phases on a more long-term basis (with the hope that the housing
    9
    market would improve in the interim), with Nantasket to pay a
    pro rata share of the original purchase price for each phase.
    The authority flatly rejected this proposal, and stated its view
    that "[g]iven that there is no longer any appeal pending, the
    payment of the Extension Deposits must resume."   At the same
    time, the authority indicated flexibility in three areas.
    First, instead of insisting that the closing take place within
    forty days of Nantasket's receiving the approvals,6 the authority
    expressed a willingness to extend the closing until November 9,
    2014.    Second, the authority indicated it was open to allowing
    the postclosing construction to be completed in phases (so long
    as Nantasket purchased all of the property at the closing).
    Third, the authority indicated that if a new agreement were
    reached, it would agree to have new Extension Deposits due every
    six months rather than every three.
    By letter dated November 1, 2010, Nantasket countered that
    it would not agree to pay any new Extension Deposits before the
    closing.    As to the existing deposit monies, Nantasket stated
    that it needed the return of $250,000 "plus the cost of
    designing and permitting the park."    Nantasket also indicated
    that it could only purchase all of the property at the closing
    if market rate financing was available.
    6
    The second amendment had not modified this provision but
    instead had changed only the Outside Closing Date.
    10
    The authority demands payment.    As a result of this back
    and forth, the parties remained far apart.   The authority's
    further response on November 19, 2010, brought them no closer.
    That letter rejected Nantasket's last proposal, offered no new
    proposal, and instead merely sharpened the authority's position
    that Nantasket had to resume payment of the Extension Deposits.
    In fact, the letter declared that Nantasket was already in
    default for not making additional Extension Deposit payments of
    $122,500 each on August 3, 2010, and November 3, 2010, and for
    not actively pursuing the remaining approvals for the project.
    According to the authority, if these problems were not cured
    within thirty days, this "will leave the Authority no choice but
    to declare [Nantasket] to be in default of its obligations under
    the LDA [which] . . . would allow the Authority to exercise all
    of its rights and remedies under Section 10.2 of the LDA,
    including, without limitation, the termination of the LDA and
    the retention of the deposit as liquidated damages under the
    LDA."
    In its response dated December 30, 2010, Nantasket
    underscored its continued unwillingness to resume payment of any
    additional Extension Deposits.   Nantasket also stated its view
    that there were outstanding title problems that the authority
    had not cured and that this both excused Nantasket's failure to
    pay additional Extension Deposits and provided Nantasket its own
    11
    basis for terminating the LDA and demanding return of the
    deposits paid to date.7   The authority responded on January 11,
    2011, by explaining its view that the title problems had been
    cured and that Nantasket had no grounds for refusing to resume
    making the Extension Deposits.   It also reiterated its demand
    that such sums be paid.   In a short and extremely pointed letter
    dated February 14, 2011, the authority once again demanded
    payment.
    The termination of the LDA.   After the demanded additional
    Extension Deposit payments were not made, the authority's board
    on April 19, 2011, voted to send Nantasket a letter terminating
    the LDA.   Four of the five board members were present (including
    Chase and Aucoin), and the vote apparently was unanimous.    The
    record reflects that before the vote was taken, the board's
    chairman, Bartley Kelly, purported to invoke the "rule of
    necessity" and that Chase and Aucoin "follow[ed]."8   No further
    7
    Nantasket had raised some of these title issues in a 2004
    letter that was sent to the authority prior to the relevant
    deadline set forth in the LDA. The letter stated a view that
    the problems could be resolved and requested "an extension of
    the 'Title Inspection Period' for the period of time necessary
    for the parties to address these issues." It further stated
    that "[i]n the event that the Authority is unable or unwilling
    to address these issues then, most reluctantly, kindly consider
    this written notice of termination pursuant to [the relevant
    provision in the LDA]." Other of the title issues arose only
    later.
    8
    The "rule of necessity" is a doctrine that recognizes that
    in some circumstances, public officials who otherwise have an
    12
    explanation was given.       The authority sent Nantasket a letter
    formally terminating the LDA that same day.
    Discussion.    Nantasket's five-count complaint relies on
    various overlapping contract-related theories.      However,
    permeating Nantasket's legal claims is its overarching
    contention that the authority's actions were tainted by serious
    conflicts of interests among two or three of its five board
    members.   In addition, Nantasket argues that the authority's
    proceeding to terminate the LDA in the face of those issues
    violated the covenant of good faith and fair dealing implied in
    every Massachusetts contract.      See Uno Restaurants, Inc. v.
    Boston Kenmore Realty Corp., 
    441 Mass. 376
    , 385 (2004).        We
    begin with addressing these ethical considerations.
    1.     Ethical issues.    As noted, Chase and Aucoin led the
    opposition to the project, and they continued that opposition
    after they joined the authority's board.      Based on the
    allegations they raised in the zoning appeal and the deposition
    ethical duty to recuse themselves from participating in a
    particular matter nevertheless may do so if necessary for the
    public entity to act. See Boston Retirement Bd. v. Contributory
    Retirement Appeal Bd., 
    441 Mass. 78
    , 85 (2004), citing Moran v.
    School Comm. of Littleton, 
    317 Mass. 591
    , 593 (1945), and cases
    cited. By letter dated July 26, 2010, town counsel had sent a
    letter to the authority's board that generally explained how the
    rule of necessity worked, and that cautioned that the rule
    should be invoked only as a "last resort" (and then only in
    accordance with certain specified procedures). The letter did
    not analyze whether any members of the authority's board in fact
    had a disqualifying conflict of interest.
    13
    of Chase taken in that case, Nantasket argues -- with
    significant force -- that Chase and Aucoin had a direct and
    substantial economic stake in whether this particular project
    succeeded or failed.   If so, then Chase and Aucoin had a
    "financial interest" in the authority's consideration of the
    project.9   This means that unless one of the recognized
    exceptions applied, they could not participate as board members
    in matters concerning the project.   See G. L. c. 268A, § 19.
    The judge noted that Chase and Aucoin had an "undisputed
    conflict of interest."   Nevertheless, he seems to have concluded
    that they satisfied their ethical obligations and that they, in
    any event, did not act in bad faith.   With regard to their
    failure to follow the procedures for invoking the rule of
    necessity outlined in town counsel's letter (see note 
    8, supra
    ),
    the judge concluded that this did "not evidence bad faith, where
    their participation in the abutter litigation and opposition to
    the Project was [already] well known."   Finally, he ruled that
    even if the vote to terminate was taken in bad faith, this was
    immaterial, because Nantasket itself was in breach of the
    contract before the vote was taken and the authority therefore
    had an express contractual right to terminate.
    9
    Whether Kelly also had a disqualifying financial interest
    is less clear because the record reveals little about his
    situation.
    14
    Although we agree with the motion judge that the ethical
    issues Nantasket sought to raise ultimately do not aid its
    cause, we arrive at that conclusion by a somewhat different
    path.     Without resolving whether his analysis of the rule of
    necessity was correct, we note that the issues do not appear to
    be as straightforward as he suggested.      As the State Ethics
    Commission (commission) has emphasized, and the authority
    acknowledges, the rule of necessity is to be invoked only "as a
    last resort."     State Ethics Commission Advisory 05-05, at 841
    (2005).    Under the commission's interpretation of that rule, if
    in fact there was no need for Kelly to recuse himself, then
    Chase and Aucoin could not have invoked the rule because their
    participation would not have been necessary to achieve a quorum
    (assuming the absent member could have attended a subsequent
    meeting).     See Ibid.10   Thus, any premise that Chase and Aucoin
    satisfied their G. L. c. 268A, obligations lies in at least some
    doubt.
    We also question the judge's conclusion that Nantasket's
    being in default necessarily rendered any bad faith by authority
    officials beside the point.      To be sure, we agree that the
    10
    Compare Attorney Gen. v. Department of Pub. Util., 
    390 Mass. 208
    , 215-216 (1983) (approving use of rule to avoid
    deadlock even where presence of a quorum was not an issue);
    Boston Retirement 
    Bd., 441 Mass. at 85
    (approving use of rule
    even though filling vacant board seat by the governor could have
    provided a quorum).
    15
    authority had no obligation to renegotiate the terms of the
    contract or to sit idly by once Nantasket defaulted (especially
    where Nantasket conceded that it could not bring itself in
    compliance due to the collapse of the housing market).     At the
    same time, the authority's decision to terminate the LDA was a
    discretionary one, and parties to a contract cannot exercise
    such discretion based on improper motives.11   See Anthony's Pier
    Four, Inc. v. HBC Assocs., 
    411 Mass. 451
    , 473 (1991).     It is of
    course axiomatic that public officials should not be exercising
    their authority to promote their own financial interests.
    Our recognition of these principles creates a potential
    conundrum about how to proceed.    On one hand, the case law
    teaches that courts are to apply a markedly strong presumption
    that public officials act in good faith, and it casts a
    jaundiced eye toward judicial inquiries into what really
    motivated the official action.12   See, e.g., LaPointe v. License
    11
    Put differently, the authority's right to terminate the
    LDA (based on Nantasket's breach) does not necessarily immunize
    its exercise of that right from any scrutiny.
    12
    This is a case where the plaintiff is challenging the
    motives behind otherwise valid government action; it is not one
    where the government actions themselves were improper. Compare
    Judge Rotenberg Educ. Center, Inc. v. Commissioner of the Dept.
    of Mental Retardation (No. 1), 
    424 Mass. 430
    , 451-459 (1997).
    In that vein, it cannot be said that the authority unfairly
    terminated the LDA in order to put itself in a better position
    than had both parties performed. Instead of receiving a total
    purchase price of $3,375,000 and the housing and park
    development that it desired, the authority was left with only
    16
    Bd. of Worcester, 
    389 Mass. 454
    , 459 (1983); Brennan v. The
    Governor, 
    405 Mass. 390
    , 397-398 (1989).   Such presumptions
    serve to avoid interference with the democratic process.13      In
    this regard, we note that the voters of Hull may have elected
    Chase and Aucoin to the authority's board precisely because of
    their opposition to the project.   On the other hand, the
    presumption that public officials act in good faith is not
    irrebuttable, and there are exceptional cases where courts have
    invalidated an otherwise valid public action based on proof that
    the "dominant reason" the action was undertaken was an improper
    one.    See, e.g., Pheasant Ridge Assocs. Ltd. Partnership v.
    Burlington, 
    399 Mass. 771
    , 777-780 (1987) (invalidating the
    taking of land for a public park, done pursuant to a town
    meeting vote, where the manifest purpose behind this was to
    block low or moderate housing at the site).   Nantasket argues
    that because the summary judgment record allows the inference
    that the board members made their decision to terminate the LDA
    $857,000 as liquidated damages while having to restart the
    development process from scratch in the midst of an anemic
    housing market.
    13
    In one case, we commented that a court would not set
    aside a legislative act even upon proof that all of the
    affirmative votes were induced by bribery. See Knowles v. Codex
    Corp., 
    12 Mass. App. Ct. 493
    , 498 (1981). The Supreme Judicial
    Court has cited this dicta, although in a manner that leaves in
    some doubt its own views of the principle. See Pheasant Ridge
    Assocs. Ltd. Partnership v. Burlington, 
    399 Mass. 771
    , 776-778
    (1987).
    17
    for an improper reason, the ethical issues could not be resolved
    as a matter of law.
    For purposes of resolving Nantasket's contract-based
    claims, it is important to keep in mind that it is the authority
    that was the party to the LDA, not individual board members.
    Municipal redevelopment authorities are liable in contract and
    tort "in the same manner as . . . private corporation[s]," and
    their officers and agents are, in the same fashion as those of
    private corporations, generally not personally liable in tort or
    contract.    G. L. c. 121B, § 13, inserted by St. 1969, c. 751,
    § 1.   As the Supreme Judicial Court has held in the context of a
    private corporation, individual board members' conflicts of
    interest are not imputed to actions taken pursuant to a valid
    vote of the board.    See Estate of Moulton v. Puopolo, 
    467 Mass. 478
    , 482, 488-489 (2014) (noting that the acts of the
    corporation's board by valid vote and those of the corporation
    are "one and the same" even where individual board members face
    conflicts of interest).    Absent evidence of bad faith on the
    part of the authority as a contracting entity, Nantasket cannot
    be heard to claim that the termination amounted to a bad faith
    breach warranting damages.
    This did not leave Nantasket without a potential remedy for
    any ethical breaches by individual board members.   However, to
    follow such remedies, Nantasket would have had to file a
    18
    complaint with the commission alleging violations of G. L.
    c. 268A.   See G. L. c. 268B, § 4(a) (governing the filing of
    verified administrative complaints with the commission).
    Compliance with State ethical rules is now overseen by the
    commission.   See Doe v. State Ethics Commn., 
    444 Mass. 269
    , 271
    (2005) (referring to the commission as "the primary civil
    enforcement agency for violations of the conflict of interest
    law, G. L. c. 268A," and noting that the commission is
    authorized "to identify and seek redress for ethics violations
    by public officials in the Commonwealth").   Thus, the commission
    regulates the conduct of municipal officials, provides guidance
    to them, and investigates whether they have violated their
    obligations under G. L. c. 268A.   
    Doe, supra
    .   If the commission
    determines that ethical breaches "substantially influenced the
    action taken by any municipality in any particular matter," the
    commission may order that the municipal action be "avoid[ed],
    rescind[ed] or cancel[ed]. . . upon request by said municipal
    agency."   Leder v. Superintendent of Schs. of Concord & Concord-
    Carlisle Regional Sch. Dist., 
    465 Mass. 305
    , 311 (2013), quoting
    from G. L. c. 268A, § 21(a).14   Nantasket could have raised its
    14
    Granted, invalidation of the municipal action is
    available only when the municipal entity requests such relief.
    However, the statute also authorizes alternative relief for a
    party who has suffered damages from an ethical breach. If the
    commission determines that a municipal official has "acted to
    his economic advantage in violation of" certain sections under
    19
    ethical concerns with the commission,15 but did not do so.16   In
    the circumstances of this case, Nantasket's failure to follow
    the statutorily prescribed procedures prevents it from now
    asking a court to invalidate the LDA termination vote (or to
    seek damages from individual board members).   See Leder, supra
    at 313.   Although the remedies provided for in G. L. c. 268A,
    are not exclusive, the statute "contemplates a primary role for
    G. L. c. 268A, it may award damages to the municipality and
    restitution to injured third parties (subject to various
    conditions and limitations). Leder, supra at 311 & n.10. In
    the event that the commission determines that damages exceed the
    amount it is authorized to order through administrative action
    ($25,000), the commission "may bring a civil action against the
    violator to recover such damages." G. L. c. 268A, § 21(b),
    inserted by St. 2009, c. 28, § 80. Municipal officials are
    protected from enforcement by the commission if they rely upon a
    formal opinion from municipal counsel issued pursuant to G. L.
    c. 268A, § 22, so long as certain procedures are followed. See
    930 Code Mass. Regs. 1.03(3) (2012).
    15
    The filing of a verified complaint triggers a
    "preliminary inquiry" into any alleged violations. G. L.
    c. 268B, § 4(a), inserted by St. 1978, c. 210, § 20. If there
    is "reasonable cause for belief" that a violation has occurred,
    the commission may, upon a majority vote, initiate an
    adjudicatory proceeding. G. L. c. 268B, § 4(c), inserted by St.
    1978, c. 210, § 20.
    16
    Nantasket did not raise its ethical concerns with the
    commission after the 2011 termination vote. Nor did Nantasket
    prior to that vote ever seek any judicial or administrative
    adjudication whether the potentially conflicted board members
    could participate in matters related to the project. Compare
    Graham v. McGrail, 
    370 Mass. 133
    , 136-137 (1976) (concluding --
    in a case that arose before the commission was created -- that a
    declaratory judgment action was available for one member of a
    school committee to address the application of G. L. c. 268A,
    § 19). The extent to which Nantasket could have obtained such
    relief here is not before us.
    20
    the commission."   Leahy v. Local 1526, Am. Fedn. of State,
    County, & Mun. Employees, 
    399 Mass. 341
    , 378 (1987).   In the
    case before us, there are numerous unresolved issues surrounding
    whether, and to what extent, individual board members violated
    the governing statute by participating in the board's vote.
    Resolution of those issues "requires the application of the
    [commission's] expertise."   
    Id. at 350.
      To the extent Nantasket
    wanted to rely on the alleged ethical breaches to make out its
    contract claim, it should have brought the issues to the
    commission in the first instance.
    2.   Merits of Nantasket's other contract-related claims.
    Stripped of this ethical overlay, resolution of Nantasket's
    underlying contract claims is relatively straightforward, at
    least based on the arguments that Nantasket raised.
    a.   Nantasket's obligation to renew the Extension Deposit
    payments.17   Once the zoning appeal was dismissed, the authority
    took the position that the Appeals Termination Date had been
    reached (there being at that moment no pending appeals) and that
    Nantasket's duty to pay additional Extension Deposits resumed
    17
    As noted, the authority also terminated the LDA on the
    grounds that Nantasket was not diligently pursuing remaining
    permit approvals. The motion judge correctly concluded that
    there was a dispute of material fact regarding that issue.
    Therefore, like the motion judge, we will focus on Nantasket's
    compliance with the obligation to resume paying the Extension
    Deposits.
    21
    ninety days later (August 3, 2010).18   Nantasket never argued in
    the trial court, nor does it argue on appeal, that this
    interpretation was incorrect.19   To the contrary, Nantasket
    itself stated in its appellate brief that "[u]nder the LDA, as
    then amended, additional $122,500 deposits were due every three
    months beginning on August 3, 2010."    Therefore, any argument
    that the Appeals Termination Date did not run when the zoning
    appeal was dismissed has been waived.
    b.   Whether Nantasket's failure to pay the Extension
    Deposits was excused.   It is undisputed that Nantasket did not
    make the Extension Deposit payments due on August 3, 2010,
    November 3, 2010, and February 3, 2011.   Nantasket nevertheless
    maintains that it was not in breach, because its conduct was
    excused by the authority's own material breach of the contract.
    See Prozinski v. Northeast Real Estate Servs., LLC, 59 Mass.
    App. Ct. 599, 610 (2003).   Specifically, Nantasket points to the
    fact that although the authority's board approved a second
    18
    Strictly speaking, ninety days after the dismissal of the
    zoning appeal on May 3, 2010, would have been August 1, 2010,
    but the record reflects that both parties consistently treated
    "ninety days" as meaning three months.
    19
    As noted, the term Appeals Termination Date was defined
    by reference to "the final disposition . . . of all appeals
    challenging or appealing the issuance of any Approval." See
    note 
    3, supra
    , for full text. Even after the zoning appeal was
    dismissed, various approvals remained outstanding, thus allowing
    opportunities for additional appeals to be filed.
    22
    amendment to the LDA on August 3, 2009, it subsequently failed
    to execute a formal amendment to the LDA memorializing that
    vote.20   To be sure, the authority's actions in this regard lie
    unexplained in the summary judgment record.21   However, also
    missing is any proof that the authority's failure to execute the
    second amendment played any material role in Nantasket's
    unwillingness or inability to resume making the required
    Extension Deposits.   In fact, nowhere in the pointed exchanges
    between the parties leading up to the termination of the LDA is
    there any reference whatsoever to the authority's refusal to
    execute a formal second amendment; the parties' discussion
    instead had turned to a potential third amendment to overhaul
    the original agreement.   Under these circumstances, Nantasket
    20
    Nantasket also argues that that the authority directly
    repudiated the second amendment to the LDA. Its evidence of
    this is that in its letter of October 4, 2010, the authority
    offered to extend the closing until November 9, 2014 (which fell
    eight months before the July 9, 2015, Outside Closing Date
    already approved by the board in its vote on the second
    amendment). However, there is no direct conflict between the
    authority's offer and the second amendment, which modified only
    the Outside Closing Date, not the actual date that the closing
    was supposed to take place.
    21
    Because Nantasket did not conduct any discovery before
    the discovery deadline lapsed, it largely has itself to blame
    for the relatively thin state of the summary judgment record.
    The judge did not abuse his discretion in declining Nantasket's
    request to extend the discovery deadline.
    23
    has failed to offer sufficient proof -- even for purposes of
    summary judgment -- that its nonperformance was excused.22
    c.   Whether the parties suspended their termination rights.
    Nantasket also argues that even if its own breach allowed the
    authority to terminate the LDA and retain the deposit, the
    authority implicitly suspended its right to do so while it was
    negotiating a third amendment to the LDA.   Once the authority
    engaged in such negotiations, Nantasket maintains, it owed
    unequivocal notice that negotiations had ended and a reasonable
    time to cure any deficiencies before terminating the LDA.     See,
    e.g., Church of God in Christ, Inc. v. Congregation Kehillath
    Jacob, 
    370 Mass. 828
    , 833-834 (1976).   According to Nantasket,
    such notice was critical because at the time, it had its own
    right to terminate the LDA and to have all its deposits
    returned.
    Nantasket's arguments are not without some force.    Once the
    zoning appeal was dismissed, the parties did engage in some
    substantive negotiations about remaking their original
    22
    Nantasket also argues that because Chase and Aucoin
    should have recused themselves from participation, the authority
    violated the contractual requirement that its execution of all
    documents related to the LDA be duly authorized, valid, and
    enforceable. However, on their face, the relevant documents
    executed by the authority in relation to the termination of the
    LDA were authorized, valid, and enforceable, and, as noted,
    Nantasket has forsworn seeking to invalidate the authority's
    actions based on any alleged ethical breaches by its board
    members.
    24
    agreement, and in that context, the authority specifically
    showed some flexibility about the frequency with which further
    Extension Deposits would be due.    In addition, Nantasket has
    some argument that -- at least at the beginning of the
    negotiations over a third amendment to the LDA -- it possessed
    its own right to terminate the LDA, even if that argument could
    not be characterized as strong.23
    However, the authority's position on the resumption of the
    Extension Deposits hardened over time, with the authority making
    it increasingly clear that it would terminate the LDA if the
    Extension Deposits were not paid as previously agreed.     At least
    by the authority's January 11, 2011, letter, it had taken that
    issue off the table.   To the extent that the authority had an
    obligation to provide unequivocal notice that Nantasket was in
    default and faced forfeiture of its deposit, the authority
    satisfied that obligation.   If Nantasket felt it still retained
    its own right to terminate the LDA, this was the time to
    23
    In the relevant time period, no permit appeals were
    pending (Nantasket having elected to defend and having
    successfully defended the zoning appeal), and there does not
    appear to have been a pending "Local Permit Problem" (as that
    term was defined in the LDA) even though Nantasket still had to
    secure some additional local approvals. Nantasket's strongest
    argument appears to be that the title issues it identified had
    not fully been cured. Because Nantasket did not terminate the
    LDA within the relevant Title Inspection Period, its ability to
    make such an argument depends on its related contention that the
    authority, by its conduct, had implicitly agreed to extend that
    period. Compare McCarthy v. Tobin, 
    429 Mass. 84
    , 88-89 (1999).
    25
    exercise it.   Alternatively, Nantasket could have tried to
    negotiate a standstill agreement to let negotiations continue.
    It chose to pursue neither option, and cannot now be heard to
    claim that the authority's actions were procedurally unfair.
    d.   Liquidated damages.   Finally, Nantasket argues that the
    authority's retaining the $857,500 as liquidated damages cannot
    stand because the sum is so disproportionate to the authority's
    actual damages that it amounts to an unenforceable penalty.      See
    NPS, LLC v. Minihane, 
    451 Mass. 417
    , 419-420 (2008).   A
    contractual liquidated damages provision is entitled to a
    presumption of validity, especially where, as here, it was
    negotiated between two sophisticated parties.   The party seeking
    to invalidate a liquidated damages provision bears the burden of
    proving that it is unenforceable, and "we resolve reasonable
    doubts in favor of the aggrieved party" (here, the authority).
    
    Ibid. "A liquidated damages
    provision will usually be enforced,
    provided two criteria are satisfied:   first, that at the time of
    contracting the actual damages flowing from a breach were
    difficult to ascertain; and second, that the sum agreed on as
    liquidated damages represents a 'reasonable forecast of damages
    expected to occur in the event of a breach.'"   Ibid., quoting
    from Cummings Properties, LLC v. National Communications Corp.,
    
    449 Mass. 490
    , 494 (2007).
    26
    At the time the parties executed the LDA, trying to
    calculate the amount of damages that the authority would suffer
    from a breach by Nantasket was inherently difficult, as a matter
    of both theory and practice.   Therefore, the first criterion of
    the two-part test is easily satisfied.   The difficulty in
    predicting such damages makes the second prong challenging to
    apply.   Without attempting to demarcate the boundaries of what
    forecast would be reasonable in these circumstances, we agree
    with the motion judge that Nantasket has not met its burden of
    showing that the liquidated damages due here (which in this
    case, amounted to some twenty-five percent of the purchase price
    of the land) were so disproportionate to predictable actual
    damages as to amount to an illegal penalty.
    Nantasket emphasizes that under the LDA, additional
    Extension Deposits of $122,500 were to accrue every three
    months, which allowed rapid escalation of potential liquidated
    damages as any delays mounted.   However, passing over the
    foreseeability of such delays (especially by a developer that
    sold itself as being experienced in overcoming regulatory
    hurdles), we note that the authority reasonably agreed to
    suspend the payment of additional Extension Deposits for over
    three-and-one-half years while the zoning appeal was pending.
    In fact, the last deposit payment that Nantasket ever made came
    on October 9, 2006 (just three months after the originally
    27
    contemplated closing date).   Moreover, the record makes plain
    that the dominant problem that caused Nantasket to default on
    its obligations was not the delay per se, but the intervening
    collapse of the real estate market.     In sum, Nantasket cannot
    claim any substantive unfairness in the enforcement of the
    liquidated damages provision to which it freely agreed.
    Conclusion.   For the reasons set forth above, we affirm the
    judgment.
    So ordered.