N.E. Bridge Contractors, Inc. v. City of Lawrence. ( 2023 )


Menu:
  • NOTICE: Summary decisions issued by the Appeals Court pursuant to M.A.C. Rule
    23.0, as appearing in 
    97 Mass. App. Ct. 1017
     (2020) (formerly known as rule 1:28,
    as amended by 
    73 Mass. App. Ct. 1001
     [2009]), are primarily directed to the parties
    and, therefore, may not fully address the facts of the case or the panel's
    decisional rationale. Moreover, such decisions are not circulated to the entire
    court and, therefore, represent only the views of the panel that decided the case.
    A summary decision pursuant to rule 23.0 or rule 1:28 issued after February 25,
    2008, may be cited for its persuasive value but, because of the limitations noted
    above, not as binding precedent. See Chace v. Curran, 
    71 Mass. App. Ct. 258
    , 260
    n.4 (2008).
    COMMONWEALTH OF MASSACHUSETTS
    APPEALS COURT
    22-P-283
    N.E. BRIDGE CONTRACTORS, INC.
    vs.
    CITY OF LAWRENCE.
    MEMORANDUM AND ORDER PURSUANT TO RULE 23.0
    The plaintiff, N.E. Bridge Contractors, Inc. (NEB), brought
    this action against the defendant, the city of Lawrence (city),
    alleging that NEB had a contract with the city to complete
    bridge repairs and NEB fulfilled its obligations under the
    contract, but that the city refused to pay NEB for all materials
    and labor.     NEB sought damages for (1) $324,177.50 for
    additional materials not included in the stated contract price,
    and (2) $18,441.38, which reflected the difference between the
    stated contract price of $326,410 and the amount the city paid
    NEB, $307,968.62.      In an amended order on cross motions for
    summary judgment, a Superior Court judge (motion judge) granted
    summary judgment in the city's favor on the $324,177.50 for
    additional materials but concluded that there were genuine
    issues of material fact as to the $18,441.38 balance.               After a
    jury-waived trial, a different Superior Court judge (trial
    judge) concluded that the city committed a breach of contract by
    not paying NEB the $18,441.38 balance.       Both parties appealed.
    We affirm, but remand for recalculation of prejudgment interest.
    Background.      This appeal arises out of the city's
    invitation for bids "to make some scour repairs" around the base
    of a bridge pier.    The invitation to bid included both detailed
    drawings of the project and estimated quantities of materials
    needed to perform the work.    Bidders were asked to provide
    prices for clearing the site, mobilization, and the following
    estimated quantities of materials:       eleven cubic yards of
    concrete, nine hundred tons of riprap, and one thousand tons of
    modified rockfill.    Before the bid deadline of November 30,
    2006, NEB submitted a bid of $286,410.       On May 7, 2008, the city
    entered into a contract with NEB to perform the work.
    The contract included several provisions regarding the
    scope of NEB's services and how the parties would handle changes
    to the scope of those services.       Under the scope of services
    provisions, NEB's work "consist[ed] of straightening out a
    section of steel sheeting and filling a void . . . underwater in
    the Merrimack River with modified fill, riprap and tremie
    concrete" using "[t]he quantities of material . . . estimated in
    the [s]chedule of [p]rices."    Paragraph 3 of the contract stated
    that "[t]he above tasks and items [were] not intended to be all
    2
    inclusive" and included the following provisions for additions
    or deletions to NEB's scope of services:
    "The [c]ity may add to or delete any items, provided that
    any added items are of a similar nature, and provided that
    the total cost of such work does not exceed the total cost
    as specified in [p]aragraph 8 hereof. [NEB] shall
    undertake such work only upon the direction of the [c]ity.
    All directives and changes thereof in conformance with this
    [a]greement shall be in written form, prepared and signed
    by the [c]ity and accepted and countersigned by [NEB] or
    his authorized representatives. Any added tasks or items
    which are not agreed to be within the [s]cope of [s]ervices
    by both the [c]ity and [NEB], or which will incur costs
    beyond the total cost specified in [p]aragraph 8, shall be
    handled in accordance with [p]aragraph 13 hereof."1
    Paragraph 13 stated that if NEB provided services "not to the
    satisfaction of the [c]ity, the [c]ity [could] request that
    [NEB] refurnish services at no additional cost" or "purchase
    services in substitution," and that the city could deduct the
    cost of substituted services or the nonperformance of services
    from the contract price.   In addition, the contract incorporated
    by reference the Massachusetts Highway Department's Standard
    Specifications for Highways and Bridges, and those
    specifications recited the requirements of G. L. c. 30, § 39N.
    Under G. L. c. 30, § 39N, all contracts subject to G. L. c. 149,
    § 44A, or G. L. c. 30, § 39M, must set forth the procedure for
    1 Likewise, paragraph 12 provided that any changes in the scope
    of services, "including any increase or decrease in the amount
    of [NEB's] compensation or any change in the work schedule,
    which are mutually agreed upon by and between the [c]ity and
    [NEB], shall be incorporated in written amendments to this
    [a]greement."
    3
    addressing differing subsurface or latent physical conditions
    and specify that requests for equitable adjustments due to those
    conditions be made in writing.
    The contract also included several provisions regarding
    compensation.   "The [c]ity agree[d] to pay [NEB] the
    compensation specified in Schedule B, Compensation and Method of
    Payment, . . . which shall constitute complete compensation for
    all services rendered and for such reimbursable expenses as
    authorized per paragraph 9."    By paragraph 9, "[t]he [c]ity
    agree[d] to reimburse [NEB] only for those direct costs incurred
    by [NEB] pursuant to the performance of work under this
    [a]greement as set forth and authorized within Schedule B."
    Schedule B provided that payment was "not to exceed $286,410."
    Around the time the parties entered into the contract, NEB
    requested a price increase of $40,000, noting that there had
    been a significant increase in the cost of supplies, materials,
    and fuel since it bid on the project over one year prior.       The
    city approved the $40,000 increase, bringing the contract price
    to $326,410.    The increase was memorialized in a written change
    order signed by the parties at various times in May through July
    of 2008.
    Thereafter, two disputes arose between the parties.     The
    first dispute, which concerned NEB's claim that it used
    4
    $324,177.50 in additional materials,2 was resolved on summary
    judgment.   We recite the facts pertinent to that dispute in the
    light most favorable to NEB.    See HSBC Bank USA, N.A. v. Morris,
    
    490 Mass. 322
    , 326-327 (2022).   When NEB began its work, its
    divers encountered a larger void than the one depicted on the
    detailed project drawings, and it "became apparent" to NEB that
    "additional quantities of certain materials specified in the
    [c]ontract would be required in order to perform the work."      On
    or around July 22, 2008, NEB filled the void using 154 cubic
    yards of cement, an overrun of 143 cubic yards of cement,
    without obtaining a written change order.     NEB also used an
    additional 170.54 tons of riprap.    NEB's president, John
    Waitkus, submitted an affidavit stating that a city engineer and
    a representative of the city's authorized field engineer, Fay,
    Spofford & Thorndike, LLC (FST), told him that they had
    authority to approve NEB's use of additional materials, and that
    they did approve of that use.    On August 6, 2008, the city held
    a meeting to discuss the material overruns.    At the meeting, NEB
    was asked to submit a written change order request for the
    2 In its complaint, NEB alleged that it was owed $324,177.50 for
    additional materials and labor, but NEB later asserted on
    summary judgment that it was owed $299,734.24 for additional
    materials. While the difference between the amounts could,
    perhaps, be attributable to labor, NEB also stated at another
    point that "[n]one of the amount claimed due [was] for
    additional labor or services." Regardless, nothing in our
    analysis turns on the difference between the amounts.
    5
    additional materials.    NEB submitted the written change order
    request, which was denied.3
    The second dispute concerned the fact that the city paid
    NEB $307,968.62 of the $326,410 contract price, leaving an
    $18,441.38 balance.     At trial, the city argued that it was
    excused from paying NEB the balance on the basis that NEB did
    not straighten the steel sheeting or install modified rockfill
    and riprap along the outer side of the sheeting.    As we discuss
    infra, the city has not shown that any of the trial judge's
    findings are clearly erroneous, and we therefore describe the
    material facts as the trial judge found them.    See Kendall v.
    Selvaggio, 
    413 Mass. 619
    , 620 (1992).    Waitkus inspected the
    underwater work site before work commenced and suggested leaving
    the steel sheeting in place.    The city agreed to that
    suggestion.   An expert witness called by the city also agreed
    that (1) "the better decision was . . . to not re-bend the steel
    sheeting" into a straight position and (2) not re-bending the
    steel sheeting "was proper."    The city "accepted [NEB's] work as
    finished," "never complained about [NEB's] work or issued a
    3 While we view the facts in the light most favorable to NEB, we
    note the following for context, to explain the dispute between
    the parties. The city has taken the position that (1) "[its]
    engineers did not approve" NEB's use of additional materials,
    (2) once NEB filled the void, "a substantive investigation was
    impossible," and (3) NEB's claim for $324,177.50 for additional
    materials was "immediately circumspect, and summarily rejected."
    6
    demand for performance,"4 and "did not offer anyone who testified
    to the reasons for partially paying [NEB] and denying the
    balance."   "[N]o work has been performed on the site since
    [then]."    Based on these findings, the trial judge concluded
    that NEB performed under the contract, and that the city
    committed a breach of contract by not paying NEB the $18,441.38
    balance.
    Discussion.   1.   Summary judgment.   On summary judgment,
    the motion judge concluded that, where NEB did not obtain a
    written change order for the $324,177.50 in additional
    materials, the city was not required to pay NEB for those
    additional materials.    NEB argues error in the motion judge's
    conclusion.   NEB asserts that its use of additional materials
    was contemplated and compensable under the terms of the contract
    without a written change order, and that the contract described
    the required quantities of materials as estimates "for no other
    purpose but to allow for adjustment once the [w]ork had
    commenced and a better understanding of what materials were
    necessary to complete the [w]ork was ascertained."    NEB also
    4 In fact, the city engineer sent a letter "[o]n behalf of the
    [city's] Department of Public Works" to the conservation
    commission requesting that the conservation commission issue a
    certificate of compliance for the pier, noting that "the
    [Mass]achusetts Highway Underwater Inspection Team inspected the
    work and gave [its] approval that the work performed was
    satisfactory to solve the problem."
    7
    asserts that its use of additional materials was compensable as
    a reimbursable expense.    We disagree.
    "The interpretation of a contract . . . presents a question
    of law for the court, subject on appeal to de novo review."
    Biewald v. Seven Ten Storage Software, Inc., 
    94 Mass. App. Ct. 376
    , 380 (2018).     We construe the words of a contract "according
    to their plain meaning, in the context of the contract as a
    whole."   Lieber v. President & Fellows of Harvard College, 
    488 Mass. 816
    , 823 (2022).     "When the words of a contract are clear,
    they control."   
    Id.
    As a whole, the contract did contemplate the possibility
    that NEB would need to use additional materials, but the
    contract also required NEB to obtain a written change order
    before doing so.     Paragraph 3 provided that the city could "add
    to or delete any items," but that any such changes had to "be in
    written form."     Paragraph 12 provided that the city could
    "increase or decrease . . . the amount of [NEB's] compensation,"
    but that any such increase or decrease had to "be incorporated
    in written amendments to this [a]greement."     NEB plainly
    understood the requirement for a writing because it prepared one
    for the $40,000 change order.     Where the contract required a
    written amendment and it was undisputed that NEB never submitted
    one for the additional materials, the judge correctly concluded
    that the city was not required to pay for them.     Moreover, NEB's
    8
    use of $324,177.50 in additional materials, an amount that would
    have nearly doubled the contract price, was not compensable as a
    reimbursable expense, because "[t]he [c]ity agree[d] to
    reimburse [NEB] only for those direct costs incurred by [NEB]
    pursuant to the performance of work under this [a]greement as
    set forth and authorized within Schedule B."   Schedule B did not
    authorize any costs in excess of the stated contract price.
    Our interpretation is consistent with the requirements of
    G. L. c. 30, § 39N, which were incorporated in the contract
    through the Massachusetts Highway Department's Standard
    Specifications for Highways and Bridges.   The requirements of
    G. L. c. 30, § 39N, specify that requests for equitable
    adjustments due to differing subsurface or latent physical
    conditions be made in writing.   This allows a contracting
    authority to investigate the physical conditions and "monitor
    the additional expenses incurred by the contractor."     Sutton
    Corp. v. Metropolitan Dist. Comm'n, 
    423 Mass. 200
    , 208 (1996).
    NEB's interpretation, that $324,177.50 in additional materials
    was compensable as a reimbursable expense, would run counter to
    the statutory requirements.   See G. L. c. 30, § 39N.5
    5 Furthermore, the Supreme Judicial Court has interpreted G. L.
    c. 44, § 31, to prohibit "a contractor [from] recover[ing] for
    work not contemplated by a contract" but allow the contractor to
    "recover for damages suffered as a result of the municipality's
    breach of contract." Perseus of N.E., MA, Inc. v. Commonwealth,
    
    429 Mass. 163
    , 166 (1999). Here, NEB seeks payment for
    9
    We are unpersuaded by NEB's alternative argument that the
    city engineer and the FST representative had apparent authority
    to waive the written change order requirement.6    "[T]he doctrine
    of apparent authority does not apply to the government, its
    agencies, or its officials."   Dagastino v. Commissioner of
    Correction, 
    52 Mass. App. Ct. 456
    , 458 (2001).7    Even if that
    were not true, the summary judgment record does not support an
    inference of apparent authority.     "Apparent authority exists
    additional materials not contemplated by the contract, not
    damages suffered as a result of the city's breach of contract.
    Given the statutory limitations at issue, NEB's equitable claims
    also fail. "[A] party cannot evade the statutory limitations on
    a municipality's contracting power by rendering services and
    subsequently seeking recovery based on alternative theories"
    (citation omitted). Celco Constr. Corp. v. Avon, 
    87 Mass. App. Ct. 132
    , 136 (2015).
    6 Relatedly, NEB argues that the city waived the requirement of a
    written change order for the additional materials by accepting
    NEB's work as finished. This argument is meritless. Regardless
    of whether the city accepted NEB's work as finished, a question
    we address infra, the city promptly questioned NEB's use of the
    additional materials, required NEB to submit a written change
    order request for the additional materials, and did not waive
    the requirement of a written change order for the additional
    materials.
    7 Costonis v. Medford Hous. Auth., 
    343 Mass. 108
     (1961), on which
    NEB relies, is not to the contrary. That case involved a
    housing authority, which is "a public body politic and
    corporate" and is "liable in contract or in tort in the same
    manner as a private corporation" (citations omitted). Ryan v.
    Boston Hous. Auth., 
    322 Mass. 299
    , 300 (1948). Thus,
    "Massachusetts courts have permitted the presentation of
    evidence to demonstrate that an agent of a housing authority had
    implied or apparent authority to enter a contract on the housing
    authority's behalf and have at times found such implied or
    apparent authority to exist." Lowell Hous. Auth. v. PSC Int'l,
    Inc., 
    692 F. Supp. 2d 180
    , 189 (D. Mass. 2010).
    10
    when the principal, by his or her words or conduct, causes a
    third person to reasonably believe that the principal consents
    to the agent acting on the principal's behalf."     Fergus v. Ross,
    
    477 Mass. 563
    , 567 (2017).    "[O]nly the words and conduct of the
    principal, . . . and not those of the agent, are considered in
    determining the existence of apparent authority" (citation
    omitted).   
    Id.
        On summary judgment, NEB relied on conclusory
    statements that the city engineer and the FST representative
    "supervised and directed" the project and that they purported to
    be the city's "authorized agents and representatives," and not
    on any words or conduct of the city.     This was insufficient to
    support an inference that the city engineer or the FST
    representative had apparent authority to waive the written
    change order requirement, especially for a change that would
    have effectively doubled the contract price.8
    2.   Trial.   Following a jury-waived trial, the trial judge
    concluded that NEB performed under the contract and that the
    8 We note that NEB also argues that the law of the case doctrine
    required the motion judge to defer to a motion to dismiss ruling
    in which another Superior Court judge stated that NEB's use of
    additional materials did not require a written change order.
    This argument is unavailing. The dispositive question before us
    -- how to interpret the contract language using the materials
    described in Mass. R. Civ. P. 56 (c), as amended, 
    436 Mass. 1404
    (2002) -- is a question of law that we review de novo and is
    fundamentally different from the question posed by a motion to
    dismiss -- whether the allegations of the complaint, if true,
    plausibly suggest an entitlement to relief. Iannacchino v. Ford
    Motor Co., 
    451 Mass. 623
    , 636 (2008).
    11
    city committed a breach of contract by not paying NEB the
    $18,441.38 balance.   The city argues that (1) NEB waived its
    claim for the $18,441.38 balance, (2) some of the trial judge's
    findings are clearly erroneous, and (3) NEB may not recover
    under the contract where NEB did not straighten the steel
    sheeting or install riprap along the outer side of the sheeting.
    On the last point, the city argues that separate and apart from
    the contractual provisions requiring written change orders,
    G. L. c. 30, § 39I, bars NEB from recovering under the contract
    where NEB did not obtain written authorization.    We disagree.
    First, the city argues that NEB waived its claim for the
    $18,441.38 balance.   By way of background, the motion judge
    initially allowed the city's motion for summary judgment on
    NEB's claims in their entirety.    NEB moved for relief from that
    summary judgment order, arguing that there were genuine issues
    of material fact with respect to the $18,441.38 balance.     The
    motion judge agreed, and an amended order so entered.   The city
    contends that this was the first time NEB asserted a claim for
    the $18,441.38 balance, but that is not correct.   NEB's
    complaint alleged that the city agreed to pay NEB the undisputed
    amount of $326,410, that NEB incurred $324,177.50 in disputed
    costs for additional materials, and that the city paid NEB
    $307,968.62.   NEB went on to allege that the sum of the
    undisputed and disputed amounts was $629,117.46, which we note
    12
    is not the sum of $324,177.50 and $326,410, and that the city
    therefore owed NEB $321,148.84.    Despite the apparent
    mathematical error, NEB's complaint plainly set forth a claim
    for the balance on the undisputed amount.    The city also
    contends that, early in the litigation, NEB explicitly stated
    that it was seeking reimbursement solely for the additional
    materials, but the city reads NEB's statement out of context.
    NEB's statement was made in the context of clarifying that it
    was seeking reimbursement for the additional materials, not any
    extra labor, and did not affect a waiver of its claims for the
    $18,441.38 balance.
    Second, the city challenges the trial judge's finding that
    the city's expert witness agreed that (1) "the better decision
    was . . . not to re-bend the steel sheeting" into a straight
    position and (2) not re-bending the steel sheeting "was proper."
    The city also challenges the trial judge's finding that the city
    "did not offer anyone who testified to the reasons for partially
    paying [NEB] and denying the balance," contending that the
    city's expert witness provided this testimony.   We review for
    clear error, and discern none.    See T.W. Nickerson, Inc. v.
    Fleet Nat'l Bank, 
    456 Mass. 562
    , 569 (2010).9
    9 In addition, the city asserts that the trial judge "failed" to
    find that no riprap was present on the outer side of the metal
    sheeting. However, that finding is implicit in the trial
    judge's analysis. The trial judge noted two deviations:
    13
    The city's expert witness testified that he agreed with
    "Waitkus in the sense that that was too hard to do that," i.e.,
    straighten the steel sheeting.   It is true, as the city notes,
    that the expert went on to testify that the "best thing" would
    have been to "cut [the bent part] and make a new steel
    sheeting," but that does not alter the fact that, on the key
    issue of whether NEB should have straightened the steel
    sheeting, the expert testified that it would have been "too
    hard" to do so.   Regarding whether the expert testified to the
    city's reasons for partially paying NEB and denying the balance,
    the expert agreed that, in his opinion, NEB was "not entitled to
    payment for work [it] did not complete."   However, the expert
    did not testify to any firsthand knowledge regarding the city's
    specific reasons for partially paying NEB and denying the
    balance, or why the city decided to pay NEB the precise amount
    of $307,968.62.   In sum, the trial judge's findings are not
    clearly erroneous.
    Third, the city argues that NEB may not recover under the
    contract where NEB did not straighten the steel sheeting or
    install riprap along the outer side of the sheeting as called
    for by the contract.   In resolving this question, we are bound
    by the trial judge's factual findings.   The trial judge's
    keeping the metal sheeting in place and the "placement of
    riprap."
    14
    analysis turned in part on the idea that the city waived the
    contractual requirement of a written change order for the
    deviations at issue.   That finding is supported by subsidiary
    findings that the city "accepted [NEB's] work as finished" --
    which included not re-bending the sheeting or installing riprap
    along its outer side -- and "never complained about [NEB's] work
    or issued a demand for performance," which findings are
    supported by the evidence.10   See Parks v. Johnson, 
    46 Mass. App. Ct. 905
    , 906 (1998) (appellate court does not retry facts).
    The question remains whether G. L. c. 30, § 39I,
    nonetheless bars NEB from recovering under the contract for
    steel sheeting it did not straighten and riprap it did not
    install.   That statute requires every contractor having a
    contract for the repair of any public works to "perform all the
    work required by such contract in conformity with the plans and
    specifications contained therein," and that "[n]o wilful and
    substantial deviation from said plans and specifications shall
    be made unless authorized in writing."   In arguing that G. L.
    c. 30, § 39I, bars NEB from recovering, the city relies on this
    court's statement in Glynn v. Gloucester, 
    9 Mass. App. Ct. 454
    ,
    461 (1980), that "[i]f any claim arises from the contractor's
    10In contrast, with respect to NEB's use of additional
    materials, the city promptly questioned the overruns and
    required NEB to submit a written change order request.
    15
    wilful and substantial deviation from the plans and
    specifications, there can be no recovery without a showing of
    compliance with the requirements of G. L. c. 30, § 39I."    The
    city reads this statement too broadly.   In the same paragraph,
    id. at 460, the court stated that if a contractor must "perform
    extra work or incur added expense," the contractor must follow
    proper procedures "before unilaterally accruing expenses to be
    pursued later," and that public authorities are expected to
    address legitimate problems in good faith and to compensate
    contractors "for bona fide extras."   In Glynn, supra at 455,
    460-461, a contractor asserted a claim for extra expenses
    incurred in connection with a municipal construction contract,
    and the court's statement, that "there can be no recovery
    without a showing of compliance with the requirements of G. L.
    c. 30, § 39I," specifically pertained to claims for extra
    expenses.
    This case presents a different question:    whether NEB may
    recover the stated contract price where the city accepted NEB's
    work as finished but did not provide written authorization for
    certain contract deviations.   We note that the city had ample
    opportunities to challenge whether NEB should have straightened
    the steel sheeting and installed riprap along the outer side of
    the sheeting.   If NEB provided services "not to the satisfaction
    of the [c]ity," the contract permitted the city to "request that
    16
    [NEB] refurnish services at no additional cost" or "purchase
    services in substitution."   Having chosen instead to accept
    NEB's work as finished, the city may not avoid its contractual
    payment obligations solely on the basis that it did not provide
    written authorization for deviations it approved.
    3.   Prejudgment interest.   Lastly, the parties dispute the
    date from which prejudgment interest should have begun to
    accrue.   General Laws c. 231, § 6C, provides that "[i]n all
    actions based on contractual obligations, . . . interest shall
    be added by the clerk of the court to the amount of damages, at
    the contract rate, if established, or at the rate of twelve per
    cent per annum from the date of the breach or demand."    However,
    "[i]f the date of the breach or demand is not established, such
    interest shall be added . . . from the date of the commencement
    of the action."   G. L. c. 231, § 6C.   Here, interest was added
    from the date of the commencement of the action.    Both parties
    argue that this was error.   NEB argues that interest should have
    been added from August 15, 2008, the date it sent a letter
    requesting full payment on the stated contract price.    That
    letter was introduced in evidence, and the city does not dispute
    its authenticity or offer any other reason why it could not be
    relied on to establish the date of demand.11   The city instead
    11The city does suggest that we are bound by the trial judge's
    finding that there was no "credible evidence" of the date of
    17
    argues that NEB did not assert a claim for the $18,441.38
    balance until March 8, 2017, when NEB filed its motion for
    relief from the original summary judgment order, and that
    interest should have been added from that date.     As we have
    explained, the city's argument that NEB did not assert a claim
    for the $18,441.38 balance until moving for relief from the
    original summary judgment order is without merit.    In light of
    the August 15, 2008 letter establishing the date of NEB's
    demand, we conclude that interest should have been added from
    that date.
    Conclusion.    So much of the judgment as awarded prejudgment
    interest from the date of the commencement of the action is
    vacated, and the matter is remanded for recalculation of
    prejudgment interest running from August 15, 2008.    In all other
    respects, the judgment is affirmed.
    So ordered.
    By the Court (Meade, Blake &
    Brennan, JJ.12),
    Clerk
    Entered:   July 24, 2023.
    demand. Given the undisputed documentary evidence and the lack
    of further explanation by the judge, we do not find this
    argument persuasive.
    12 The panelists are listed in order of seniority.
    18