Balfour Beatty v. Rummel Klepper & Kahl , 226 Md. App. 420 ( 2016 )


Menu:
  •              REPORTED
    IN THE COURT OF SPECIAL APPEALS
    OF MARYLAND
    No. 496
    September Term, 2014
    BALFOUR BEATTY
    INFRASTRUCTURE, INC.
    v.
    RUMMEL KLEPPER & KAHL, LLP
    Leahy,
    Reed,
    Eyler, James. R.,
    (Retired, Specially Assigned)
    JJ.
    Opinion by Leahy, J.
    Filed: January 28, 2016
    In this appeal we consider whether the economic loss doctrine applies to shield an
    engineering firm from tort claims brought by a contractor seeking damages for economic
    losses suffered in consequence of relying on the firm’s allegedly defective designs and
    projections. Our holding is framed by the fact that, while the engineering firm and the
    contractor each had separate contracts with the government to perform work on the same
    design-bid-build construction project, there was no contract between the parties.
    The City of Baltimore entered into a contract with Rummel Klepper & Kahl, LLP
    (“RK&K” or “Appellee”), a design engineering firm, to produce construction designs and
    associated documents for use by the successful bidder(s) on succeeding proposals for
    construction of the Patapsco Wastewater Treatment Plant.            Fru-Con Construction
    Corporation, predecessor to Balfour Beatty Infrastructure, Inc. (“BBII” or “Appellant”),1
    was the successful bidder on the plant upgrade projects, and entered into Sanitary Contract
    852R with the City in November 2009.
    Just over four years later, BBII filed a complaint in the Circuit Court for Baltimore
    City against RK&K, claiming that, during construction, BBII ran into costly delays and
    complications in reliance on RK&K’s allegedly defective designs and negligent
    misrepresentations concerning project timeline projections.     The complaint sounded in
    tort, supported by the theory that RK&K had a duty to BBII based on the “intimate nexus”
    between them, and asserted three causes of action: 1) professional negligence, 2)
    1
    BBII is a construction company organized under Delaware law and authorized to
    do business in Maryland.
    1
    information negligently supplied for the guidance of others under Restatement (Second) of
    Torts § 552, and, 3) negligent misrepresentation.
    RK&K filed a motion to dismiss the complaint for failure to state a claim. RK&K’s
    central argument was that the complaint sought recovery for purely economic losses, and,
    because there was no contractual privity or its equivalent between BBII and RK&K, the
    economic loss doctrine barred BBII’s tort claims. The circuit court granted the motion to
    dismiss in an order entered on April 10, 2014.
    We affirm. We hold that BBII failed to state a claim because, as a matter of law, in
    the absence of privity, death, personal injury, property damage, or the risk of death or
    serious personal injury, no duty of care in tort runs from an engineer or architect to a
    contractor for purely economic losses on a public construction project. In reaching this
    holding, we determine that Maryland does not expand the “intimate nexus” test to include
    extra-contractual concepts of duty for the recovery of solely economic losses in public
    construction cases.
    BACKGROUND
    Design-bid-build contracts
    Under the “design-bid-build” project delivery method utilized by the City in this
    case, the owner first enters into a contract with an architect and/or engineer (“A/E” or
    “design professional”) to design the project. Typically, the engineering and design is
    completed before the owner releases a request for proposals for a general contractor to
    2
    perform the work.2 1 Bruner & O’Connor Construction Law § 2:11 (2015). Under this
    method:
    (1) the design is fully developed and completed before the pricing of the
    work, thus, presumably resulting in lowest cost, and (2) selection among
    responsible and responsive bidders can be made on the basis of price alone.
    . . the contractor is excluded from contributing to the design process. . .
    Id. The A/E and the contractor each have a contract with the owner, but they have no
    contractual relationship with each other.
    In contrast, integrated delivery methods, such as “design-build,” create a single
    point of responsibility because the A/E and the contractor are bound under a single contract
    with the owner. Id. at § 2:12. Typically the contractor who is part of a design-build team
    is involved in aspects of the design of a project from the beginning, and the A/E remains
    involved—normally in an oversight and advisory role—during the construction phase. Id.;
    5 Bruner & O’Connor Construction Law § 17:52 (2015) (explaining the modern trend to
    minimize the A/E’s previous “substantial involvement in the construction process” to a
    lesser obligation to “observe the work and determine in general if the work is being
    performed in accordance with the contract documents.”).3
    2
    The owner may, in addition to hiring a general contractor to perform the work
    according to the A/E’s design specifications, enter into a separate contract with the A/E
    firm, or a construction manager (“CM”), or a “CM-at-Risk” to oversee the work. Robert
    F. Cushman et al., Proving & Pricing Construction Claims § 9.03[A][1] (3d ed. 2015).
    3
    We recognize the current trend in the construction industry to move away from the
    traditional design-bid-build project delivery method toward more integrated delivery
    methods that embrace a direct contractual relationship between the A/E and the contractor.
    See 1 Bruner & O’Connor Construction Law § 2:12 (2015) (acknowledging the dramatic
    increase in public use of the design-build project delivery method that “maximizes the
    cooperative and early involvement of design and construction professionals working
    3
    The traditional design-bid-build model often engenders tensions between the A/E
    and the construction contractor, as explained in one treatise on the subject:
    A fundamental difficulty in allocating liability under the design-bid-build
    model is the inherent tension between the interests of the architect and
    contractor. Some contractors believe they can increase profits through
    change orders that are based on ambiguities, errors, or omissions in the
    architect’s design. Architects have an interest in protecting their designs, and
    frequently serve as the owner’s representative during construction. In these
    situations, it benefits the architect to resist any suggestion that the design is
    flawed and deny change order requests based on defective plans and
    specifications.
    Because of these competing interests, it can be difficult for the owner to
    determine whether the architect or contractor is responsible for a delay. . . .
    To complicate matters further, it may not be possible to join the architect and
    contractor in a single action[.]
    Robert F. Cushman et al., Proving & Pricing Construction Claims § 9.03[A][1] (3d ed.
    2015). As discussed further infra, under traditional design-bid-build contracts, especially
    in the public sector, the contractor normally has a contractual entitlement to recover against
    the owner for construction delays and other benefit-of-the-bargain damages caused by the
    A/E’s defective specifications and designs.
    together as part of a project team.”); see also Patrick M. Miller, 2011 Construction Review:
    Design-Build, 3 Construction Briefings (March 2012) (acknowledging the intensifying
    debate surrounding design and construction delivery methods and the gaining popularity
    of “integrated project delivery,” including design-build, which contemplates designers and
    constructors working together from the project’s conception); see also Sean Devenney and
    Gregg Bundschuh, Is the Line Blurring Between General and Professional Liability, 29
    ABA Construction Lawyer 15 (Spring 2009) (noting that the “blurred lines between
    constructor duties and design duties raise significant questions in the construction
    insurance market given the traditional line between professional liability coverage for
    designers and commercial general liability for different aspects of work on a construction
    project.”).
    4
    RK&K’s Professional Engineering Services Contract
    According to the complaint,4 sometime prior to October 2009,5 the City entered into
    a contract with RK&K for the design of two interrelated projects to upgrade the plant,
    termed the “Enhanced Nutrient Removal Facilities.” According to BBII, the City’s
    contract with RK&K specified that RK&K was to produce accurate, complete, and correct
    construction designs and drawings for use by the successful bidder(s) who would construct
    the plant upgrades. RK&K’s duties and responsibilities allegedly included, but were not
    limited to:
    ▪      Development of the design for the two interrelated projects;
    ▪      Development and preparation of drawings and specifications for use
    by prospective contractors for preparing and submitting bids and
    ultimately for use by the successful contractor for the construction of
    the projects;
    ▪      Development of timelines for construction of the projects;
    ▪      Development and preparation of responses to questions regarding the
    design raised by prospective contractors during the bid phase;
    ▪      Review, evaluation, and comment on the proposals submitted by
    bidders/prospective contractors;
    4
    As this appeal is from the grant of a motion to dismiss a complaint for failure to
    state a claim upon which relief can be granted, the evidentiary background will assume the
    truth of all well-pleaded facts and allegations in the complaint. Lloyd v. Gen. Motors Corp.,
    
    397 Md. 108
    , 121 (2007) (citing Morris v. Osmose Wood Preserving, 
    340 Md. 519
    , 531
    (1995)).
    5
    Neither BBII nor RK&K attached to the complaint or motion to dismiss any of
    the bid or contract documents (including Sanitary Contract 852R) for the Patapsco
    Wastewater Treatment Plant.
    5
    ▪      Review, evaluation, and approval of various submittals from the
    successful contractor during construction related to the Work and
    RK&K’s design;
    ▪      Review, evaluation, and inspection of the successful contractor’s
    Work during construction to assure conformance with RK&K’s
    design intent and design; and
    ▪      Review, evaluation, and acceptance of the successful contractor’s Work and
    certification to the City regarding the same.
    Thus, in addition to its pre-construction/design phase responsibilities, RK&K was
    allegedly assigned several construction-phase responsibilities, including: 1) evaluating and
    approving “various submittals” from the contractor related to the work and RK&K’s
    design; 2) inspecting the contractor’s work during construction to assure conformance with
    RK&K’s design intent and design; and, 3) review, evaluation, and, if acceptable,
    certification of the contractor’s work to the City.
    Sanitary Contract 852R
    Construction work for the projects under Sanitary Contract 852R (“SC 852”) and
    Sanitary Contract 845R (“SC 845”)6 was to be completed at the same time, although SC
    852 was let out for bid prior to SC 845. After it was pre-qualified by the City as capable
    6
    To the extent one can glean something more about these projects from their titles,
    we note that SC 852 is identified as “Denitrification and Related Work for the
    Enhancement Nutrient Removal Facilities at Patapsco Wastewater Treatment Plant.” SC
    845 is identified as “Nitrification Filters and Related Work for the Enhanced Nutrient
    Removal Facilities at Patapsco Wastewater Treatment Plant.”
    6
    of performing the work, Fru-Con Construction Corporation (predecessor in interest to
    BBII) bid on the SC 852 project, directly relying upon RK&K’s documents and designs.7
    On November 20, 2009, Fru-Con Construction Corporation and the City entered
    into a contract for the SC 852 project (“Contract”). Several years later, on January 1, 2014,
    the City agreed to an assignment of the Contract from Fru-Con Construction, LLC, to
    BBII.8 Under the Contract, BBII was to, “among other things,” construct thirty-four
    “[d]enitrification filter cells (‘DNF cells’) adjacent to the existing wastewater facility.”
    DNF cells are “enormous, concrete tubs that hold massive amounts of wastewater to be
    treated.” The Contract also required BBII to construct pipes and pipe support systems for
    the SC 852 project.
    BBII’s Complaint
    In its complaint filed on January 6, 2014, BBII related that RK&K designed the
    DNF cells to expand or contract at keyed joints located in their concrete walls to
    accommodate fluctuating water pressure. BBII constructed the DNF cells in accordance
    with RK&K’s designs, but, when the water retention integrity of the DNF cells was tested,
    7
    RK&K, in its memorandum of points and authorities, alleges that BBII has
    contracts with the City for both projects—SC 852 and SC 845. RK&K states further that
    “[f]or reasons known only to the pleader, [BBII] has declined to allege that it holds the
    contracts with the City for both of the projects.”
    8
    The Contract was initially assigned on May 24, 2011, with the City’s consent, from
    Fru-Con Construction Corporation to Fru-Con Construction, LLC. BBII then acquired all
    membership interests in Fru-Con Construction, LLC, and by January 1, 2014, BBII had
    fully absorbed Fru-Con Construction, LLC as a division of BBII. The record before us is
    not sufficient to discern which events discussed in the complaint occurred before BBII
    assumed the Contract, but, given that such distinction has no obvious legal significance in
    this appeal, we refer only to BBII throughout this opinion.
    7
    BBII learned that the cells were leaking due to cracks in the expansion and contraction
    joints.     BBII alleged that these cracks and the associated leaks were a direct result of
    deficiencies in RK&K’s design and that it cost BBII substantial additional time and
    expense to remediate the problems. BBII also claimed that, once construction was
    underway, it discovered RK&K’s design for the pipe support system was defective, and
    again, suffered substantial additional time and cost remedying RK&K’s allegedly defective
    pipe system design.
    Finally, BBII contended that RK&K delayed completion of its design of the
    companion project, SC 845, and that RK&K knew that any delays in the design of SC 845
    would delay BBII’s ability to complete work on SC 852 and expose BBII to substantial
    costs and expenses. BBII alleged RK&K failed to properly establish a reasonable contract
    duration or project timeline for SC 852, and, instead, supplied false information to
    prospective contractors who were developing their estimates and competitive bids for the
    projects.
    Predicated on these factual allegations, BBII asserted a claim for Professional
    Negligence (Count I), Restatement (Second) of Torts § 552 (Court II), and Negligent
    Misrepresentation (Count III). In Count I, BBII claimed that it was a forseeable party that
    would directly rely upon RK&K’s professional services and designs, and, that “based upon
    the intimate nexus between [RK&K’s] design and [BBII’s] work as well as the contractual
    privity equivalent that exists between [RK&K] and [BBII], [RK&K] owed [BBII] a duty
    to act with a reasonable degree of care, knowledge, diligence and skill ordinarily possessed
    and exercised by similarly situated design professionals.” BBII demanded an estimated
    8
    $10 million in damages for “increased and additional labor, materials, equipment and
    subcontractor costs, investigative costs, consultant fees, remediation costs, and delay
    costs.” In Count II (Restatement § 552 for “Information Negligently Supplied for the
    Guidance of Others”), BBII contended that it suffered damages “[a]s a direct and proximate
    result of [RK&K’s] failure to exercise reasonable care in preparing, supplying and
    communicating the design, including plans and specifications, for the Project.”
    Finally, in its third count for negligent misrepresentation, BBII posited that, as a
    result of the overlapping responsibilities of RK&K in both the design and construction
    phases of the project, and, because RK&K knew that BBII would rely on RK&K’s design
    and project duration schedule, “an intimate nexus and contractual privity equivalent exists
    between [RK&K] and [BBII].” According to BBII, RK&K knew that the design of SC
    845 was not sufficiently complete so as to allow SC 582 to be constructed within the
    contract schedule, and RK&K failed to warn BBII that the prices and ultimate costs of
    completing SC 852 would far exceed estimates.
    Motions Before the Circuit Court
    After it was served with a copy of the complaint, on January 29, 2014, RK&K filed
    a motion to dismiss for failure to state a claim in the circuit court. In its memorandum of
    points and authorities, RK&K argued that BBII failed to plead any facts that would support
    finding the existence of a legally cognizable duty in tort running from RK&K to BBII.
    Invoking the “economic loss rule,” RK&K argued that, in the construction industry,
    in the absence of privity or death, injury or a genuine risk of death or serious personal
    injury or property damage, no duty is owed by an architect or engineer to a contractor
    9
    where the loss or damage alleged is economic in nature. RK&K asserted that there was no
    contract between the parties, and argued that the “intimate nexus” and Restatement
    (Second) of Torts § 522 concepts of extra-contractual duty have never been applied in
    Maryland to design professionals in the construction field. Nonetheless, RK&K contended
    that BBII failed to allege facts that would allow a court to find the parties shared an
    “intimate nexus” or “professional/client relationship.” RK&K asserted that, for example,
    there were no allegations in the complaint regarding any specific communications between
    RK&K and BBII before or during construction, or consultations between BBII and RK&K
    on BBII’s bid or schedule assumptions.
    RK&K advanced the principles that support the economic loss rule as applied in the
    construction industry; namely, that common variables and “unknowns”—such as hidden
    site conditions, owner-directed changes, material and labor shortages, price escalations,
    defective materials, change orders and errors—are addressed through contracts that
    allocate risks and provide mechanisms for the assertion of claims and resolution of
    disputes. RK&K asserted that “[w]hen considered in the construction industry context,”
    BBII’s “pitch to apply tort principles in order to bypass its bargained-for rights . . . [is] a
    disruptive tactic that only can undermine public confidence in public procurement.”
    In its response filed February 20, 2014, BBII argued that RK&K misconstrued
    Maryland case law because the “economic loss rule” applies to products liability claims
    and was not meant to be a shield for professional malpractice. BBII defended its failure
    to allege facts detailing the provisions of BBII’s contract(s) with the City because the
    causes of action alleged in the complaint were separate from any claims BBII may have
    10
    had against the City. BBII challenged RK&K’s assertion that the complaint failed to allege
    facts showing a relationship between RK&K and BBII on the ground that the complaint
    alleged that BBII was one of a limited group of pre-qualified, prospective contractors and
    that RK&K knew the City’s prospective contractors would directly rely upon RK&K’s
    design in preparing their bids. Finally, BBII argued that under Maryland law, a plaintiff
    seeking purely economic losses is not foreclosed from bringing an action for negligent
    misrepresentation.
    RK&K replied, adding that tort liability should not be extended in this case because
    the “Spearin Doctrine” should have sheltered BBII from the risk of suffering the benefit-
    of-the-bargain type economic damages alleged in the complaint.9 The doctrine, as
    enunciated in United States v. Spearin, applies specifically to construction projects and
    provides that “if the contractor is bound to build according to plans and specifications
    9
    RK&K also noted that BBII failed to include anything in the complaint concerning
    BBII’s responsibilities as they relate to the construction and administration of the projects
    under its contract with the City, or the costs therefor; or mention the City’s procurement
    and administrative dispute resolution procedures, or the status of BBII’s claims, if any,
    under the City’s administrative dispute resolution process. RK&K cites to Baltimore City’s
    comprehensive and detailed “Green Book,” which defines the rights, roles and
    responsibilities of the City and its contractors. City of Baltimore Department of Public
    Works, Specifications: Materials, Highways, Bridges, Utilities, and Incidental Structures
    (2006)             (the           “Green            Book”)            available            at
    http://archive.baltimorecity.gov/Portals/0/agencies/general%20srvcs/public%20download
    s/City%20of%20Baltimore%20Specifications%20(Green%20Book).pdf. The Green Book
    specifications, which generally apply to City construction projects, include provisions that
    allow a contractor to assert claims against the City for “damages, losses, time, costs and/or
    expenses, alleged to have been sustained, suffered or incurred by [contractor] in connection
    with the Project.” Green Book § 00.73.84 (1)(a). The Green Book also sets out the claims
    processes and procedures for contractors. See Green Book at § 00.73.84 Claims or
    Disputes.
    11
    prepared by the owner, the contractor will not be responsible for the consequences of
    defects in the plans and specifications.” 
    248 U.S. 132
    , 136 (1918) (citations omitted); see
    also Dewey Jordan, Inc. v. Maryland-Nat'l Capital Park & Planning Comm'n, 
    258 Md. 490
    , 498 (1970) (“the contracting authority impliedly warrants that the plans and
    specifications are adequate and sufficient for the purpose intended and that the contractor
    is entitled to be compensated for delays in work occasioned by faulty plans and
    specifications.”). Thus, RK&K argued, that if its designs were indeed defective, and if
    BBII had a right to rely on them (as BBII alleged in the complaint), then BBII would have
    been entitled to reimbursement from the City for any extra costs incurred under its contract
    with the City under the Spearin doctrine. On the other hand, if BBII could not establish
    that RK&K’s designs were defective, or if it was determined that BBII failed to follow or
    properly interpret the designs, then BBII’s tort claims would fail as well.
    On March 14, 2014, BBII filed a motion for leave to file a sur-reply. BBII argued
    that RK&K misapplied the Spearin Doctrine because, although courts have held that the
    contracting authority impliedly warrants that plans and specifications supplied under the
    contract are adequate, and that the contractor is entitled to be compensated for certain costs
    and delays, those courts have never held that the implied warranty was a “limitation on a
    contractor’s ability to pursue another, viable cause of action.”
    On April 2, 2014, the Circuit Court for Baltimore City heard argument from counsel
    on the pending motion to dismiss. At the close of the hearing, the circuit court orally
    granted RK&K’s motion, finding that there was no privity between the parties giving rise
    to a tort duty under the current law in Maryland.
    12
    BBII filed a motion to reconsider on April 7, 2014, along with a memorandum of
    law, arguing (1) that privity is not a requirement for a claim under Restatement (Second)
    Torts § 552, or negligent misrepresentation, and (2) the circuit court did not consider the
    “equivalent of privity” between BBII and RK&K to support BBII’s professional negligence
    claim. On May 6, 2014, the circuit court denied BBII’s motion for reconsideration, and,
    on May 15, 2014, BBII noticed a timely appeal.
    BBII presents three questions:
    I.      Does an engineer owe a duty to a contractor when the engineer is aware
    that the contractor will rely upon the engineer's services to the contractor's
    detriment if the engineer's services are negligently performed, even
    though no contract exists between the engineer and contractor?
    II.      Does a contractor have a cause of action under Restatement of Torts
    (Second) § 552 against an engineer for negligently supplied information
    when the design professional knew the contractor would rely upon the
    information supplied and be harmed by the engineer's negligence?
    III.      Does a contractor have an action for negligent misrepresentation against
    an engineer when the engineer: (a) intended the contractor to rely upon
    the representations (i.e., design); (b) knew that the contractor would rely
    upon the design; and (c) knew that the contractor would be harmed if the
    design was negligently performed?
    DISCUSSION
    Standard of Review
    Appellate courts “review[] the grant of a motion to dismiss for legal correctness.”
    Rounds v. Maryland-Nat. Capital Park and Planning Comm’n, 
    441 Md. 621
    , 635 (2015)
    (citing Patton v. Wells Fargo Financial Maryland, Inc., 
    437 Md. 83
    , 95 (2014); Heavenly
    Days Crematorium, LLC v. Harris, Smariga & Assocs., Inc., 
    433 Md. 558
    , 568 (2013)).
    13
    The circuit court, when considering a motion to dismiss a complaint for failure to state a
    claim upon which relief can be granted, must view all well-pleaded facts and allegations in
    the complaint as true. Lloyd, 
    supra,
     
    397 Md. at
    121 (citing Morris, supra, 340 Md. at 531;
    Sharrow v. State Farm Mutual Ins. Co., 
    306 Md. 754
    , 768 (1986)). The court may grant
    the motion only if the allegations and inferences, assumed to be true, do not state a cause
    of action. State Center, LLC v. Lexington Charles Ltd. P’ship, 
    438 Md. 451
    , 496-97 (2014)
    (quoting RRC Ne., LLC v. BAA Maryland, Inc., 
    413 Md. 638
    , 643-44 (2010)). When the
    claim at issue is in tort, the court “merely determines [the plaintiff’s] right to bring the
    action,” and does not decide whether the claims are meritorious. Figueiredo-Torres v.
    Nickel, 
    321 Md. 642
    , 647 (1991). We apply the same standards and determine only
    whether the circuit court’s decision was legally correct, according no special deference to
    the circuit court’s legal conclusions. Heavenly Days Crematorium, 433 Md. at 568
    (citations omitted).
    I.
    Professional Negligence
    BBII asserts that RK&K is liable under a professional negligence theory for the
    economic losses BBII sustained performing construction work under BBII’s contract with
    the City in reliance upon RK&K’s allegedly defective designs. According to BBII, RK&K
    breached a duty to BBII to act with the reasonable care of a design professional in creating
    designs for the SC 852 project, and in “failing to establish a reasonable duration” for the
    construction of the project.
    14
    The elements required to establish a cause of action for professional negligence are
    equivalent to the elements required in a standard negligence action; the professional,
    however, is held to the standard of care that prevails in his or her profession. See Crockett
    v. Crothers, 
    264 Md. 222
    , 224-25 (1972). “[O]ne who undertakes to render services in the
    practice of a profession or trade is required to exercise the skill and knowledge normally
    possessed by members of that profession or trade in good standing in similar communities.”
    Restatement (Second) of Torts § 299A (1965). To sustain a cause of action for negligence,
    a complaint must allege facts sufficient to support a finding of: 1) a duty to the plaintiff (or
    to a class of which the plaintiff is a part), 2) a breach of that duty, and 3) a causal
    relationship between the breach and the harm, and 4) damages suffered. See Walpert,
    Smullian & Blumenthal, P.A. v. Katz, 
    361 Md. 645
    , 655 (2000) (citing Jacques v. First
    Nat'l Bank, 
    307 Md. 527
    , 531 (1986); Cramer v. Hous. Opportunities Comm'n, 
    304 Md. 705
    , 712 (1985); Scott v. Watson, 
    278 Md. 160
    , 165 (1976); Peroti v. Williams, 
    258 Md. 663
    , 669 (1970)). “Absent a duty of care, there can be no liability in negligence.” 
    Id.
    (citing W. Va. Cent. v. Fuller, 
    96 Md. 652
    , 666 (1903)). The Walpert Court further
    clarified:
    “[T]here can be no negligence where there is no duty that is due; for
    negligence is the breach of some duty that one person owes to another. . . .
    As the duty owed varies with circumstances and with the relation to each
    other of the individuals concerned, so the alleged negligence varies, and the
    act complained of never amounts to negligence in law or fact, if there has
    been no breach of duty.”
    Walpert, 
    361 Md. at 655
     (quoting W. Va. Cent., 
    96 Md. at 666
    ). In Jacques, the Court of
    Appeals instructed that two major considerations in determining whether a tort duty should
    15
    be recognized in a particular context are “the nature of the harm likely to result from a
    failure to exercise due care, and the relationship that exists between the parties.” 
    307 Md. at 534
    .
    A. The Economic Loss Doctrine
    Most states recognize that lack of privity between the parties is not, alone, a bar to
    a negligence claim. See Council of Co-Owners Atlantis Condo., Inc. v. Whiting-Turner
    Contracting Co., 
    308 Md. 18
    , 32 (1986) (“In following the modern trend, we hold that
    privity is not an absolute prerequisite to the existence of a tort duty.”); Adams v. Buffalo
    Forge       Co.,    
    443 A.2d 932
    ,    939        (Me.   1982)   (“We    hold,   therefore,
    that lack of privity does not constitute a bar to an action alleging negligence on the part of
    the manufacturer”); Barni v. Kutner, 
    76 A.2d 801
    , 803 (Del. Super. Ct., 1950) (stating
    that “lack of privity is no defense in a negligence case under certain conditions.”) (citation
    omitted)). But in cases such as the one presented here, in which a contractor sustains higher
    than anticipated costs based on the allegedly defective designs of an engineering firm with
    which it has no contract, states are divided over whether and in what circumstances a
    negligence claim to recover the costs is barred by the “economic loss doctrine.”
    The general rule is that a party cannot recover against another in tort where the
    resulting harm is purely economic loss and the parties have no contract between them. See
    Robins Dry Dock & Repair Co. v. Flint, 
    275 U.S. 303
     (1927); see also U.S. Gypsum Co. v.
    Mayor and City Council of Baltimore, 
    336 Md. 145
    , 156 (1994). The recovery of purely
    economic, benefit-of-the-bargain-type damages has long been limited in the United States.
    In Robins, Justice Holmes addressed the issue in a suit brought by the charterers of a
    16
    steamship against a dry dock for damages for loss of the use of the vessel. Id. at 307. The
    dry dock company was contractually responsible to the vessel owner to perform periodic
    servicing. Id. When the dry dock company negligently broke a propeller, the Supreme
    Court held that the charterers could not recover their economic damages from the dry dock,
    either as third-party beneficiaries to the owner’s service contract, nor for the dry dock
    company’s negligence. Id. at 308-09. Justice Holmes explained:
    [The charterer’s] loss arose only through their contract with the owners—and
    while intentionally to bring about a breach of contract may give rise to a
    cause of action, no authority need be cited to show that, as a general rule, at
    least, a tort to the person or property of one man does not make the tort-feasor
    liable to another merely because the injured person was under a contract with
    that other unknown to the doer of the wrong. The law does not spread its
    protection so far.
    Id. at 308-09 (internal citations omitted).
    In Maryland, we acknowledge that “‘the first obstacle which arises [to imposition
    of a duty] is the fact that there has been no direct transaction between the plaintiff and the
    defendant, which usually is expressed by saying that they are not in ‘privity’ of contract.’”
    Whiting-Turner, 
    308 Md. at 26
     (quoting Prosser and Keeton on the Law of Torts § 18.5, at
    708-10 (2d ed. 1986). The rationale supporting the requirement of privity (or, as we shall
    explain infra, a “privity equivalent”) as a condition to the recovery of economic damages
    for negligent conduct is “to avoid ‘liability in an indeterminate amount for an indeterminate
    time to an indeterminate class.’” Walpert, 
    361 Md. at 671
     (quoting Chief Judge Cardozo
    in Ultramares Corp. v. Touche, 
    174 N.E. 441
    , 444 (N.Y. 1931)). Still, Maryland courts
    have established that the economic loss doctrine does not always apply to bar recovery of
    economic damages. See, e.g., Lloyd, 
    397 Md. at 121
     (stating that the economic loss
    17
    doctrine will not bar a claim for products liability where the product at issue [defective car
    seats that collapse rearward in rear-impact collisions] creates a dangerous condition that
    “gives rise to a clear danger of death or personal injury.” (citation omitted)); A.J. Decoster
    Co. v. Westinghouse Elec. Corp., 
    333 Md. 245
    , 254-60 (1994) (stating that economic loss
    can be recovered for property damage through strict products liability claims where the
    damage is caused by “unreasonably dangerous products.”); Cash & Carry America, Inc. v.
    Roof Solutions, Inc., 
    223 Md. App. 451
    , 468-470 (2015) (holding that the economic loss
    doctrine did not bar a negligence claim against a contractor by a third party where the risk
    of harm was personal injury and property damage).10
    In construction matters, the law in Maryland contours more narrow circumstances
    under which the economic loss doctrine does not bar tort claims for purely economic loss.
    As explored further below, a construction contractor’s ability to recover for economic
    losses against a design professional where there is no contractual privity is generally
    limited to situations involving death, personal injury, property damage, or the risk of death
    or serious personal injury. See Whiting-Turner, 
    308 Md. at 35
    .
    i.     Privity, Property Damage, Death, Injury, or the Risk of Death or Serious
    Personal Injury
    10
    In Cash & Carry America, we observed that the economic loss doctrine has been
    expanded in some states, limited in others, and given way to “‘vast confusion over this area
    of law.’” 223 Md. App. at 466, n.6 (quoting David v. Hett, 
    270 P.3d 1102
    , 1105 (2011));
    see also LAN/STV v. Martin K. Eby Const. Co., 
    435 S.W.3d 234
    , 242, n.32 (Tex. 2014)
    (“‘The confusing mass of precedent relating to tort liability for economic loss has yet to be
    disentangled and expressed with the clarity commonly found with respect to other tort law
    topics.’”) (quoting Vincent R. Johnson, The Boundary-Line Function of the Economic Loss
    Rule, 
    66 Wash. & Lee L. Rev. 523
    , 546 (2009)).
    18
    In Whiting-Turner, the Court of Appeals held that builders and architects have a
    duty, even where no privity exists between the parties, to use due care in the design,
    inspection, and construction of a project that extends to “persons foreseeably subjected to
    the risk of personal injury because of a latent and unreasonably dangerous condition
    resulting from that negligence.” 
    308 Md. at 22
    . In Whiting-Turner, a condominium
    owners’ association brought a negligence action against the general contractor, developer,
    and architects of a building, alleging that their negligence had resulted in the deficient
    construction of the building and created a fire hazard that “present[ed] a threat to the safety
    and welfare of the owners and occupants. . . .” 
    Id. at 22-23
    . The unit owners also alleged,
    inter alia, that, in advertising and selling the units, the developer negligently
    misrepresented “the building’s suitability for occupancy.” 
    Id. at 23
    .
    The builder and certifying architects filed motions to dismiss, contending that the
    complaint failed to allege facts sufficient to show they owed a duty of care to the unit
    owners. 
    Id.
     The defendants argued that a duty should not be recognized because the unit
    owners had only suffered economic loss, not personal injury or property damage. 
    Id. at 23-24
    . The trial court concluded it was bound by the Court of Appeals’ statement in
    Marlboro Shirt, that “‘a contractor owes no duty to the general public for which it may be
    made responsible in an action in tort for negligence if it does not perform its contract.’” 
    Id. at 29
     (quoting Marlboro Shirt Co., v. Am. Dist. Tel. Co., 
    196 Md. 565
    , 571-72 (1951)).
    The Court of Appeals distinguished Marlboro Shirt because it involved an action
    solely for injury to personal property and the plaintiffs did not allege the contractor created
    any risk of personal injury. 
    Id.
     The Court then turned to the question of whether a
    19
    negligence action may be maintained against a builder or architect in a situation in which
    the risk of personal injury existed but no personal injury occurred. Id. at 30-31. The Court
    concluded that
    the determination of whether a duty will be imposed in this type of case
    should depend upon the risk generated by the negligent conduct, rather than
    upon the fortuitous circumstance of the nature of the resultant damage.
    Where the risk is of death or personal injury the action will lie for recovery
    of the reasonable cost of correcting the dangerous condition.[11]
    Id. at 35 (footnote omitted).
    Eight years later in Chambco, Div. of Chamberlin Waterproofing & Roofing System,
    Inc. v. Urban Masonry Corporation, 
    101 Md. App. 664
     (1994), vacated on other grounds,
    
    338 Md. 417
     (1995), this Court reviewed the development and application of Whiting-
    Turner since its publication. Chambco addressed a claim of negligence asserted by a
    roofing subcontractor against a masonry subcontractor, both of whom had contracts with
    the general contractor but not each other. 101 Md. App. at 667-68. The Court held that
    Whiting-Turner was a “narrowly drawn opinion,” concluding that, “in Maryland, there
    have been no substantive expansions of the Whiting-Turner theory of negligence actions
    in building construction cases.” Id. at 672, 680. Because the appellant only suffered
    economic losses, was not in privity of contract with the appellee, and did not allege that
    11
    The Court explained the nature of the risk intended by its holding:
    It is the serious nature of the risk that persuades us to recognize the cause of
    action in the absence of actual injury. Accordingly, conditions that present
    a risk to general health, welfare, or comfort but fall short of presenting a clear
    danger of death or personal injury will not suffice.
    Whiting-Turner, 
    308 Md. at
    35 n.5.
    20
    the negligence created a risk of death or personal injury, this Court determined in Chambco
    that the cause of action did not fit within Whiting-Turner and there was no cause of action
    absent privity of contract. Id. at 680-81.
    In Heritage Harbour, L.L.C. v. John J. Reynolds, Inc., developers brought an action
    seeking indemnification and contribution from the original developers, contractors, and
    architects of a condominium in relation to an underlying action brought against the
    developer by the owners of the condominium for “numerous structural and non-structural
    defects in the buildings . . . .” 
    143 Md. App. 698
    , 702-03 (2002). This Court clarified that
    the appellees must have had an original duty to the condominium owners in the underlying
    suit in order to be liable to appellants for contribution and/or indemnity. Id. at 706. The
    appellants needed to “plead clear facts that would support a finding of extreme danger and
    an imminent risk of severe personal injury,” to circumvent the economic loss doctrine in
    order to find tort liability. Id. at 708 (citing Morris, supra, 340 Md. at 536). Because the
    appellants “failed to allege the existence of any substantial risk to persons or property,”
    this Court, relying on Whiting-Turner, concluded that “their claims are precluded by the
    Economic Loss Doctrine.” Id.
    We recently held that the economic loss doctrine did not apply to bar a third party’s
    negligence claim against a contractor for damage to property where the risk of harm
    (personal injury and property damage from misuse of a torch and resulting fire) was not
    solely economic in Cash & Carry America, 223 Md. App. at 468-470. After reviewing
    established principles governing application of the doctrine, we explained that “the
    economic loss doctrine serves as a boundary between contract law, the purpose of which
    21
    is to enforce the expectations of the parties to an agreement, and tort law, the purpose of
    which is to protect people and property from foreseeable risks of harm by imposing upon
    others a duty of reasonable care.” Id. at 466 (citing East River S.S. Corp. v. Transamerica
    Delaval, Inc., 
    476 U.S. 858
    , 866 (1986)).
    Here, BBII’s complaint does not allege any facts that would support a finding that
    there was any risk of serious injury or death, nor does BBII argue that the alleged negligent
    actions of RK&K created such a risk. BBII also made no claim of damage to property.
    Therefore, the economic loss doctrine bars BBII’s claim of professional negligence against
    RK&K for purely economic losses. See Whiting-Turner, 
    308 Md. at 35
    ; Chambco, 101
    Md. App. at 680-81; Heritage Harbour, 143 Md. App. at 708.
    ii.    The “Privity Equivalent” Analysis Does Not Apply
    BBII asks this Court to hold for the first time, that where there is no contract between
    a construction contractor and a design professional in a negligence action for the recovery
    of purely economic losses, an intimate nexus, and therefore a duty in tort, can be established
    by demonstrating a “privity equivalent” between the parties. BBII argues that, as stated in
    the complaint, its relationship with RK&K satisfies the intimate nexus test because BBII
    was not a member of an “indeterminate class,” but, rather, as bidder on the contract with
    the City, was known to RK&K as an entity that would rely on RK&K’s schematics after
    winning the bid for the contract. Thus, RK&K owed a duty to BBII to act with reasonable
    care.
    In riposte, RK&K states that no Maryland appellate court has recognized a tort claim
    by a contractor against a not-in-privity design professional for the type of damages
    22
    allegedly suffered by BBII. RK&K’s principal argument relies on policy—that Maryland
    contract law allows government contractors to recover against the owner in negligent
    design cases under the Spearin Doctrine, and that many state supreme courts have
    expressly denied recovery for contractors against architects, engineers, and designers.
    RK&K contends that the intimate nexus analysis does not apply to this case at all, but that
    even if it did, RK&K owed no duty to BBII because the circumstances alleged in the
    complaint do not rise to the level of privity or its equivalent. RK&K maintains that no
    facts were alleged in BBII’s complaint concerning “any design-phase interactions”
    between RK&K and BBII.
    As we next explain, although we agree that the law does not impose a duty of care
    that would sustain an action for professional negligence against RK&K on the complaint
    filed in this case, we do not adopt RK&K’s blanket contention that the intimate nexus
    analysis does not apply in construction contract cases. Rather, we hold that in government
    construction matters such as the case on appeal,12 the intimate nexus analysis is not
    expanded to include “privity equivalent” concepts of extra-contractual duty for the
    recovery of solely economic losses.
    Generally, “when the failure to exercise due care creates a risk of economic loss
    only, and not the risk of personal injury, we have required an ‘intimate nexus’ between the
    parties as a condition to the imposition of tort liability.” Swinson v. Lords Landing Vill.
    12
    We limit our holding to cases involving government construction cases and do
    not reach whether or not intimate nexus concepts of extra-contractual duty may be applied
    in a private-sector construction case.
    23
    Condo., 
    360 Md. 462
    , 477 (2000) (citing Jacques, 
    supra,
     
    307 Md. at 534
    ; Village of Cross
    Keys v. U.S. Gypsum Co., 
    315 Md. 741
    , 753 (1989)).13 We trace the term to Chief Judge
    Cardozo’s landmark opinion in Ultramares Corp., supra, wherein he described the kinds
    of relationships that may form a tort duty where the “intimacy of the resulting nexus”
    formed by transactions between the parties are “so close as to approach that of privity, if
    not completely one with it.” Ultramares Corp., 
    255 N.Y. 170
    , 182-83. An “intimate
    nexus,” therefore, “is satisfied by demonstrating contractual privity or its equivalent.”
    Premium of Am., LLC v. Sanchez, 
    213 Md. App. 91
    , 108 (2013) (some internal quotations
    omitted) (quoting Walpert, 
    supra,
     
    361 Md. at 658
    ).
    The intimate nexus analysis has been applied in Maryland to permit recovery of
    economic loss in suits between: a bank and its client, see Jacques, 
    307 Md. at 534-35
    ; a
    title company and a purchaser of real property, see 100 Inv. Ltd. P’ship v. Columbia Town
    Center Title Co., 
    430 Md. 197
    , 225 (2013); and an accounting firm and a third-party
    investor, see Walpert, 
    361 Md. at 693-94
    . See also Sanchez, 213 Md. App. at 95, 108-15
    (2013) (applying the intimate nexus analysis to the marketing of viatical settlements, an
    “unusual context”).
    In Jacques, the Court held a bank liable for the economic losses of its customer
    where the bank expressly agreed to process an application for a loan, accepted
    consideration for the processing, and promised a guaranteed rate of interest as an
    13
    Accordingly, when the risk created is one of personal injury, “no such direct
    relationship need be shown, and the principal determinant of duty becomes foreseeability.”
    Jacques, 
    307 Md. at 535
     (citations omitted).
    24
    enticement to the customer to deal with the bank. 
    307 Md. at 528, 537-38
    . The court found
    that the relationship and dealings between the parties amounted to a contract and that the
    contract contained an implied promise to use reasonable care. 
    Id. at 540
    . The court further
    noted that the customers were “particularly vulnerable and dependent” on the Bank
    exercising due care and that the Bank “had knowledge” and was “well aware” that its
    customers would be legally obligated to proceed to settlement with the loan determined by
    the Bank or forfeit their deposit. 
    Id. at 540-41
    .
    In Walpert, the Court of Appeals held that accountants may be held liable for
    negligence to a non-contractual party when there exists a connection equivalent to privity
    between the parties. 
    361 Md. 645
    . There, the Court found that an accounting firm that had
    prepared a financial report for a business in a negligent manner was liable to a third party
    who relied on the report in deciding whether to loan the business money and then suffered
    economic damages. 
    Id. at 692-94
    . The Court applied the three-prong test for “privity
    equivalent” developed in Credit Alliance Corp. v. Arthur Anderson, 
    483 N.E.2d 110
     (N.Y.
    1985), which requires that the plaintiff show “(1) the accountants must have been aware
    that the financial reports were to be used for a particular purpose or purposes; (2) in the
    furtherance of which a known party or parties was intended to rely; and (3) there must have
    been some conduct on the part of the accountants linking to that party or parties, which
    evinces the accountants' understanding of that party or parties' reliance.” Walpert, 
    361 Md. at 674, 692
    . The Court of Appeals concluded that this approach reflected the same policy
    reported in prior Maryland cases involving negligence claims brought by non-contractual
    third parties, and it “limit[ed] the unpredictable and unlimited nature of economic
    25
    damages.” 
    Id. at 675
     (citation omitted). The Court supported this approach as it “[sought]
    to recognize and give effect to the current commercial reality in which the certified public
    accountant plays a major role in assuring the reliability of financial statements.” 
    Id. at 676
    .
    In reaching its holding, the Walpert Court focused on the third prong of the testthe
    requirement for conduct linking the parties—and concluded that the accountant’s proven
    knowledge that the third party would rely on the report satisfied the legal privity equivalent.
    
    Id. at 684-92
    .
    Maryland state appellate courts have not applied the “privity equivalent” test in a
    construction case sounding in tort for economic damages against a design professional.
    Indeed, a number of cases have emerged in other states discouraging the application of any
    exception to the economic loss rule in a case involving the construction industry. See
    Berchauer/Phillips Construction Co. v. Seattle School District, 
    881 P.2d 986
     (Wash. 1994)
    (holding that, under the economic loss rule, a contractor was not allowed to recover purely
    economic damages from a design professional in tort and recovery was limited to remedies
    provided by the construction contract); BRW, Inc. v. Dufficy & Sons, Inc., 
    99 P.3d 66
     (Colo.
    2004) (holding that the economic loss rule barred the subcontractor’s negligence and
    negligent misrepresentation claims against an engineering firm and inspector), declined to
    extend by S K Peightal Engineers, LTD v. Mid Valley Real Estate Solutions V, LLC, 
    342 P.3d 868
     (Colo. 2015); LAN/STV v. Martin K. Eby Const. Co., 
    435 S.W.3d 234
     (Tex. 2014)
    (holding that a contractor could not recover the increased costs of performing its
    construction contract with the owner in a tort action against the project architect for alleged
    errors in the plans and specifications); see also William Powers, Jr. & Margaret Niver,
    26
    Negligence, Breach of Contract, and the “Economic Loss” Rule, 
    23 Tex. Tech L. Rev. 477
    (1992). These cases, some of them cited by RK&K in its brief, view construction as a
    distinctive industry which relies on “a network of contracts to allocate [] risks, duties, and
    remedies. . . .” BRW, 99 P.3d at 72. These courts caution that “certainty and predictability
    in allocating risk would decrease and impede future business activity” if courts allowed
    parties working on a construction project to recover in tort for economic loss against A/E
    firms where there is no privity. Berchauer/Phillips, 881 P.2d. at 992.
    There are, however, states that have extended extra-contractual concepts of the
    “intimate nexus” analysis in construction industry cases. For example, the Ohio Eighth
    District Court of Appeals held that lack of privity is not an absolute bar to a design
    professional's malpractice action when there is a nexus that can serve as a substitute for
    privity. Clevecon, Inc. v. Northeast Ohio Regional Sewer Dist. 
    628 N.E.2d 143
    , 146 (Ohio
    Ct. App. 1993). In Clevecon, the court of appeals upheld the lower court’s denial of a
    design professional’s motions for summary judgment and for directed verdict where the
    design professional was “extensively involved in supervision and administration . . . [and]
    reasonable minds could find that a sufficient nexus existed between the parties to substitute
    for privity of contract.” 
    Id. at 147
    . See also Nicholson v. Turner/Cargile, 
    669 N.E.2d 529
    ,
    535 (Ohio Ct. App. 1995) (concluding that “a design professional who exercises ‘excessive
    control over the contractor’ through the power to stop the work and give orders about the
    project is liable for such economic damages.” (citing Clevecon, 
    628 N.E.2d at 147
    )).
    Similarly, the Supreme Court of Appeals of West Virginia held that the lack of
    privity was not an absolute bar to recovery for economic damages in tort against a design
    27
    professional where there was a “special relationship” between the parties.          E. Steel
    Constructors, Inc. v. City of Salem, 
    549 S.E.2d 266
    , 275 (2001). In E. Steel, the appellate
    court reversed the circuit court’s grant of summary judgment to a design professional in a
    professional negligence action where the design professional and contractor were
    separately employed by the same project owner. 
    Id.
     The court held that “a design
    professional (e.g. an architect or engineer) owes a duty of care to a contractor, who has
    been employed by the same project owner as the design professional and who has relied
    upon the design professional's work product in carrying out his or her obligations to the
    owner, notwithstanding the absence of privity of contract between the contractor and the
    design professional, due to the special relationship that exists between the two.
    Consequently, the contractor may, upon proper proof, recover purely economic damages
    in an action alleging professional negligence on the part of the design professional.” 
    Id. at 275
    .
    We return to the threshold considerations presented at the beginning of this
    discussion to determine whether, in Maryland, we should extend the “privity equivalent”
    concept of extra-contractual duty in an action for professional negligence in a public
    construction industry case that does not involve a risk of death, serious injury, or property
    damage. Accordingly, whether to find a duty in tort, we must examine “the nature of the
    harm likely to result from a failure to exercise due care, and the relationship that exists
    between the parties.” Jacques, 
    307 Md. at 534
    . The Jacques Court observed:
    We discern from our review of the development of the law of tort duty that
    an inverse correlation exists between the nature of the risk on one hand, and
    the relationship of the parties on the other. As the magnitude of the risk
    28
    increases, the requirement of privity is relaxed-thus justifying the imposition
    of a duty in favor of a large class of persons where the risk is of death or
    personal injury. Conversely, as the magnitude of the risk decreases, a closer
    relationship between the parties must be shown to support a tort duty.
    Jacques, 
    307 Md. at 537
     (emphasis supplied). “[D]uty is not sacrosanct in itself, but is
    only an expression of the sum total of those considerations of policy which lead the law to
    say that the plaintiff is entitled to protection.’” Sanchez, 213 Md. App. at 110 (some internal
    quotations omitted) (citing Prosser and Keeton on the Law of Torts § 53 at 358.) “In other
    words, ‘the determination of whether a duty exists represents a policy question of whether
    the specific plaintiff is entitled to protection from the acts of the defendant.” Id. at 108
    (citing Gourdine v. Crews, 
    405 Md. 722
    , 745 (2008)).
    A contractor performing work on a government design-bid-build contract is
    typically covered by its contract with the government, and protected under the Spearin
    doctrine as well, against the risk of loss arising from defective engineering designs.14 Thus,
    14
    As we have noted, supra at n.5, the record does not contain any documents
    detailing the contract between BBII and the City. But even accounting for the possibility
    that the contract contained a “no-damage-for-delay” or similar clause, BBII would
    arguably have been entitled, under the Spearin Doctrine, to recover damages from the City
    for its reliance on the designs provided by the City, if those designs were in fact defective.
    Dewey Jordan, Inc., 
    supra
     258 Md. at 499 (1970). In Dewey Jordan, Inc., the Court of
    Appeals concluded, following an examination of United States v. Spearin, that it would not
    enforce the public owner’s no-damage-for-delay clause, reasoning that “‘[t]he defendant
    cannot, by errors in the specifications, cause delay in plaintiff’s completion of the work
    and then compensate plaintiff merely by extending its performance time and by payment
    of any added direct cost occasioned by changes to correct those errors.’” Id. at 499 (quoting
    Laburnum Constr. Corp. v. United States, 
    325 F.2d 451
    ,457 (1963)). In Raymond Int’l,
    Inc. v. Baltimore County, 
    45 Md. App. 247
    , 258 (1980), this Court declined to relieve the
    Government of responsibility for inaccurate representations contained in specifications
    provided by County’s engineer, despite “extensive and direct exculpatory clauses intended
    to place the responsibility and risk of inaccurate information upon the contractor.” (quoting
    Maryland Dept. of Public Safety & Correctional Servs. v. PHP Healthcare Corp., 
    151 Md. 29
    a government building contractor can normally recover costs from the government for its
    reliance on defective designs supplied by the government; whereas, a property owner or
    accounting client, for example, typically cannot recover their expectation-type damages
    from anyone other than the title examiner or accounting professional. Compare Raymond,
    45 Md. App. at 257-58 (concluding that Baltimore County was liable to the general
    contractor for “materially wrong and substantially inaccurate” specifications provided to
    the general contractor by the project engineer retained by the County), with Walpert, 
    supra,
    361 Md. 645
    , 692-94 (concluding that an accountant may be held liable for negligence to
    a non-contractual party where the specific purpose of retaining the accountant was to rely
    on the financial reports created to determine whether to loan money to the business).
    We conclude that Maryland decisional law countenances a distinction between the
    duty owed by design professionals to construction contractors under government contracts,
    and the duty owed by accountants and other professionals to third parties who can establish
    reliance and the elements of an intimate nexus. See Jacques, 
    307 Md. at 540
    ; Walpert, 
    361 Md. at 674, 692
    . In the construction industry, parties can delimit their economic risk by
    defining their respective rights and liabilities contractually. We read our precedent,
    App., 182, 202 (2003)). Notably, however, where delay damages are not caused by a
    contractor’s reliance on the public owner’s faulty plan specifications, the Spearin Doctrine
    does not apply and this Court has determined that “no-damage-for-delay” clauses are
    enforceable, even for delays not contemplated by the parties. See State Highway Admin.
    v. Greiner Engineering Sciences, Inc., 
    83 Md. App. 621
    , 638-39 (1990) (enforcing a “no-
    damages-for-delay” clause in a state highway contract where the engineer suffered delay
    damages resulting from the SHA’s numerous changes in the scope of the design work and
    funding uncertainties).
    30
    embracing the Spearin doctrine, to encourage, rather than discourage, design professionals
    and contractors to communicate with each other on public works projects where necessary
    in the interest of public safety. Especially in situations where the design professional is
    hired as a neutral agent of the owner, expanding Maryland law to permit exposure to tort
    liability for economic loss would create a chilling effect on the design professional’s
    neutrality and ability to communicate effectively. We agree with the observations of the
    Supreme Court of Washington that
    [t]here is a beneficial effect to society when contractual agreements are
    enforced and expectancy interests are not frustrated. . . . The preservation of
    the contract represents the most efficient and fair manner in which to limit
    liability and govern economic expectations in the construction business.
    Berschauer/Phillips, supra, 881 P.2d at 992-92. Accordingly, we hold that the “privity
    equivalent” concept of extra-contractual duty does not apply in an action for professional
    negligence against a design professional by a contractor seeking purely economic damages
    on a public construction project where there is no death, personal injury, property damage,
    or the risk of death or serious personal injury.
    II.
    Restatement (Second) Torts § 552
    BBII also argues that the Restatement (Second) of Torts § 552 provides plaintiffs in
    Maryland with a cause of action for harm stemming from information negligently supplied
    for the guidance of others and that it was error for the circuit court to dismiss this claim
    presented in Count II of the complaint. BBII states that this tort is independent of its other
    two claims. RK&K maintains in response that Restatement § 552 has not been applied in
    31
    Maryland in cases involving architects, engineers, or contractors not in privity with the
    plaintiff.
    Maryland courts have adopted the Restatement § 552 as an alternative means of
    satisfying the intimate nexus test. Swinson, 
    supra,
     
    360 Md. at 477
    ; see also Sanchez, 213
    Md. App. at 115 (citing 100 Inv. Ltd. P'ship, supra, 430 Md. at 230).15 In lieu of
    demonstrating the equivalent of contractual privity under the three-prong test developed in
    Credit Alliance Corp., supra, a plaintiff can demonstrate a privity equivalent under
    15
    The Restatement provides:
    § 552. Information Negligently Supplied for the Guidance of Others.
    (1) One who, in the course of his business, profession or employment, or in
    any other transaction in which he has a pecuniary interest, supplies false
    information for the guidance of others in their business transactions, is
    subject to liability for pecuniary loss caused to them by their justifiable
    reliance upon the information, if he fails to exercise reasonable care or
    competence in obtaining or communicating the information.
    (2) Except as stated in Subsection (3), the liability stated in Subsection (1) is
    limited to loss suffered
    (a) by the person or one of a limited group of persons for whose
    benefit and guidance he intends to supply the information or knows
    that the recipient intends to supply it; and
    (b) through reliance upon it in a transaction that he intends the
    information to influence or knows that the recipient so intends or in a
    substantially similar transaction.
    (3) The liability of one who is under a public duty to give the information
    extends to loss suffered by any of the class of persons for whose benefit the
    duty is created, in any of the transactions in which it is intended to protect
    them.
    32
    Restatement § 552. Id.      However, for the same reasons that we declined to apply the
    “privity equivalent” analysis of the Credit Alliance and Walpert line of cases to satisfy the
    intimate nexus test, we also decline to apply the Restatement (Second) of Torts § 552 in
    this case.
    In Sanchez, we examined the application of § 522 as an alternative to contractual
    privity in a case in which a physician, who provided life expectancy estimates to an
    insurance provider for viatical policies, was sued by investors for negligence in
    underestimating life expectancies.       Sanchez 213 Md. App. at 97-100.            There, we
    determined that § 552 was not a basis for imposing a tort duty on the physician. Id. at 118.
    We noted that the “undisputed evidence shows that Sanchez had no inkling of [the
    insurer’s] actual role in the purchase of the viatical policies. . . . The mere possibility that
    [the insurer] might disclose the evaluation to others [the investors] is an insufficient basis
    to expand the scope of Sanchez’s duty.” Id.
    BBII maintains that, because RK&K should have known that BBII was among the
    entities that would bid on the SC 852 contract with the City, § 552 permits recovery against
    RK&K “by the person or one of a limited group of persons for whose benefit and guidance
    [RK&K] intends to supply the information or knows that the recipient intends to supply
    it.” Restatement § 552(2)(a). BBII underscores in its briefing that we also said in Sanchez,
    that “had [the insurer] told Sanchez that it was not purchasing viatical policies for its own
    benefit but was instead doing so as an agent for investors, Sanchez might owe a duty to
    those investors even if he did not know their specific identities.” Id. Although this dicta
    lends some support to BBII’s argument, it does not translate to the imposition of a tort duty
    33
    under these facts where there was no pre-determined set of bidders for the project.
    Moreover, this case involves two sophisticated businesses working on the same
    construction project. They each negotiated their independent contracts with the owner in
    what they understood was a “design-bid-build” construction project with the City of
    Baltimore. The relationship between BBII and RK&K—two veteran business entities in
    the construction field—is not at all similar to the relationship between the physician and
    the investors in Sanchez. The investors in Sanchez are more comparable to the client in
    Jacques, or the third-party investor in Walpert—parties who typically cannot recover their
    expectation-type damages from anyone other than the professional on whom they relied
    for advice. See Jacques, 
    supra,
     
    307 Md. at 540
    ; Walpert, 
    361 Md. at 692-94
    .
    But even if the Restatement § 552 analysis had application in the present context,
    BBII failed to allege facts sufficient to support this alternative intimate nexus equivalent.
    Under Restatement § 552(1), BBII must plead facts that establish RK&K provided false
    information and failed to exercise reasonable care or competence. The Court of Appeals
    explained in Walpert:
    For liability to attach under § 552, the plaintiff must be a member of
    a limited class to whom the accountant intends to supply the information or
    to whom the accountant knows the recipient intends to supply it, who suffers
    loss through reliance on the information for substantially the same purpose
    as the bona fide client.[16]
    
    361 Md. at 677
     (citation omitted) (emphasis supplied).
    16
    The Court of Appeals ultimately decided not to apply Restatement § 552 in
    Walpert, 
    361 Md. at 681
    .
    34
    Here, the complaint states simply that “RK&K failed to exercise reasonable care
    and competence in preparing, supplying and communicating the design to [BBII] and in
    failing to timely design the 845R project so that it would not impact the completion of the
    [SC 852] Project.” There is no allegation in the complaint that RK&K made a false
    statement other than the allegedly flawed designs, or that RK&K told BBII that the 845R
    project would be completed on a certain date. BBII does not allege any facts to demonstrate
    that RK&K did not exercise reasonable care or competence, other than making a
    conclusory statement that they did not. Therefore, we concluded that the utility of
    Restatement § 552 as an alternative means to establishing an intimate nexus is not
    applicable to this case, and even if it were, BBII failed to allege facts sufficient to meet the
    elements of § 552. We affirm the judgment of the circuit court.
    III.   Negligent Misrepresentation
    BBII presents another alternate theory for recovery in Count III, alleging that
    RK&K is liable under the tort of negligent misrepresentation. Relying on Whiting-Turner,
    
    supra,
     
    308 Md. at 41
    , BBII asserts that Maryland has recognized a cause of action for
    negligent misrepresentation seeking only economic loss that does not require contractual
    privity. BBII argues that it specifically pled in its complaint the elements of negligent
    misrepresentation, including that “RK&K made a false statement; i.e., RKK’s design was
    flawed” and that RK&K intended that its design be relied upon by a “distinct class of
    persons—prospective contractors bidding on the Project, including BBII.”
    RK&K relies on its general contention that, in Maryland, the economic loss doctrine
    bars design professionals in the construction field from liability for purely economic loss
    35
    suffered by a contractor, “in the absence of privity, death, injury or a risk of death or serious
    personal injury, or property damage. . . .” RK&K maintains that its position is supported
    by sound policy, citing to LAN/STV, supra, wherein the Supreme Court of Texas
    considered whether a contractor could recover for negligent misrepresentation against the
    project architect. 
    435 S.W.3d 234
    .         The contractor alleged that, “[i]n the course of
    providing the referenced plans, drawings, and specifications, LAN/STV made
    representations, in a transaction for which it was compensated, where those representations
    were false, misleading and/or inaccurate and were made with the knowledge that
    contractors such as EBY would rely upon them.” 
    Id.
     at 237 n.10. The Supreme Court
    held that the contractor was barred from bringing a negligent misrepresentation claim by
    the economic loss rule because the construction industry has the “freedom to allocate
    economic risk through contract.”
    As stated in Whiting-Turner, “[t]he tort of negligent misrepresentation has been
    recognized in this State.” 
    308 Md. at
    41-2 (citing Flaherty v. Weinberg, 
    303 Md. 116
    , 135
    (1985); Martens Chevrolet, Inc. v. Seney, 
    292 Md. 328
     (1982)). In Maryland, common law
    negligent misrepresentation is comprised of the following elements:
    (1) The defendant, owing a duty of care to the plaintiff, negligently asserts a
    false statement;
    (2) The defendant intends that his statement will be acted upon by the
    plaintiff;
    (3) The defendant has knowledge that the plaintiff will probably rely on the
    statement, which, if erroneous, will cause loss or injury;
    (4) The plaintiff, justifiably, takes action in reliance on the statement; and
    (5) The plaintiff suffers damage proximately caused by the defendant's
    negligence.
    36
    Flaherty, 
    303 Md. at 135
     (emphasis in Flaherty) (citing Martens Chevrolet, 
    292 Md. at 337
    ); see also Walpert, 
    361 Md. at 656-57
    . To recover damages in a tort action for
    fraudulent misrepresentation, “a plaintiff must prove that a false representation was made,
    that its falsity was either known to the maker or that the representation was made with such
    reckless indifference to the truth as to be equivalent to actual knowledge of falsity, that the
    representation was made for the purpose of defrauding the plaintiff, that the plaintiff not
    only relied on the representation but had a right to rely on it and would not have done the
    thing from which the injury arose had the misrepresentation not been made, and that the
    plaintiff actually suffered damage directly resulting from the misrepresentation.” Swinson,
    supra, 
    360 Md. at
    476 (citing Gittings v. Von Dorn, 
    136 Md. 10
    , 15–16 (1920); Martens
    Chevrolet, 
    292 Md. at 333
    ).
    For claims of economic loss based on negligent misrepresentation, the injured party
    must demonstrate it had an “intimate nexus” relationship with the defendant in order to
    establish that the defendant owed a duty to the injured party. See Jacques, 
    supra,
     
    307 Md. at 534-35
    . In Walpert, the Court of Appeals determined that a duty could be imposed on
    accountants to a non-contractual plaintiff if the plaintiff could establish an intimate nexus
    through the privity equivalent test developed in Credit Alliance. 
    361 Md. at 681, 689-93
    ;
    see also Sanchez, supra, 213 Md. App. at 107-109 (explaining that negligent
    misrepresentation’s duty element requires satisfaction of the intimate nexus test as stated
    in Walpert).
    The cases surveyed above and throughout this opinion make plain that the
    prerequisites for establishing the duty element are the same for negligent misrepresentation
    37
    and professional negligence claims in Maryland.17 Because, in this case, there was no
    contract between the parties, to impose a duty for negligent misrepresentation would
    require that we apply the “privity equivalent” test, or Restatement § 552, to determine
    whether there was an intimate nexus between the parties. Just as we did with respect to
    BBII’s claim of professional negligence, we reject the argument that extra-contractual
    concepts of duty permit the recovery of solely economic losses in the construction industry
    in a cause of action for negligent misrepresentation.18     The parties, both sophisticated
    17
    For example, in Prudential Securities, Inc. v. E-Net, Inc., this Court considered
    whether a corporation and transfer agent had a duty in tort to a stock broker under theories
    of negligence and negligent misrepresentation. 
    140 Md. App. 194
    , 200-206 (2001). First,
    this Court acknowledged that, to establish a duty in tort where the risk of loss is purely
    economic, the parties must share an intimate nexus, satisfied by contractual privity or its
    equivalent. Id. at 213-14. This Court then determined that the parties did not share a
    “meaningful link” to support a cause of action for negligence. Id. at 221 (quoting Jacques,
    
    307 Md. at 535
    ). Later in the opinion, in considering the appellant’s negligent
    misrepresentation claim, this court acknowledged that negligent misrepresentation is “one
    variety of a negligence action.” Id. at 230 (quoting Walpert, 
    361 Md. at 654
    ). After setting
    out the elements of a negligent misrepresentation claim, however, this Court summarily
    dismissed the claim, explaining, “[a]s we discussed above . . . neither [appellees] owed a
    duty to [appellant] in this situation.” Id.; see also Village of Cross Keys, 
    supra,
     
    315 Md. at 752-755
     (determining whether a duty in tort for purely economic loss existed prior to
    determining whether to treat the claim as one for negligent misrepresentation or one for
    negligent conduct).
    18
    We are not persuaded that BBII’s contention that RK&K should have known
    BBII would be among the entities that would bid on the SC 852 contract establishes the
    kind of reliance required to sustain a cause of action for negligent misrepresentation. In
    Raymond, supra, this court explained why it found no error in the trial court's granting of
    Greiner's motion to dismiss Raymond International’s suit against Greiner on the grounds
    of misrepresentation at the conclusion of Raymond's case:
    It would serve no useful purpose to again restate the five prerequisites
    of proof required to sustain an action for misrepresentation or deceit. It is
    sufficient to state that the appellant failed to produce evidence from which
    could be found or inferred that Greiner intended to defraud by reason of the
    38
    businesses with experience in construction projects and contracts, were free to allocate
    their duties and risks in their contracts with the City.   BBII’s claims against RK&K for
    benefit-of-the-bargain economic damages under theories of professional negligence and
    negligent misrepresentation based on allegedly inaccurate timelines and flawed
    specifications that belonged to the City are barred by the economic loss doctrine.
    For the foregoing reasons, we affirm the circuit court’s dismissal of BBII’s negligent
    misrepresentation claim.
    JUDGMENT OF THE CIRCUIT
    COURT FOR BALTIMORE CITY
    AFFIRMED; COSTS TO BE PAID BY
    THE APPELLANT.
    allegedly incorrect information it furnished to Raymond. Even assuming that
    Greiner was negligent in preparing the information it furnished to the
    bidders, that would not be sufficient to satisfy the plaintiff's burden as a
    misrepresentation induced by negligence or ignorance will not sustain an
    action for fraud. . . . There was no testimony establishing clear and
    convincing evidence that Greiner's representations in this case were made for
    the specific purpose of defrauding the plaintiff. This is particularly so when
    we note that at the time the information was supplied to the prospective
    bidders no one had any knowledge as to who the successful bidder would be.
    
    45 Md. App. 247
    , 261-62 (internal citations omitted) (emphasis supplied).
    39
    40