29 McKown LLC v. Town of Boothbay Harbor , 2022 ME 38 ( 2022 )


Menu:
  • MAINE SUPREME JUDICIAL COURT                                              Reporter of Decisions
    Decision: 
    2022 ME 38
    Docket:   Lin-21-306
    Argued:   May 9, 2022
    Decided:  June 28, 2022
    Panel:       STANFILL, C.J., and MEAD, HORTON, CONNORS, and LAWRENCE, JJ.*
    29 MCKOWN LLC et al.
    v.
    TOWN OF BOOTHBAY HARBOR et al.
    MEAD, J.
    [¶1] This case concerns a real estate office building constructed by
    party-in-interest Harbor Crossing, LLC, in Boothbay Harbor. The project is
    being challenged by two abutters, 29 McKown LLC and Chandler Wright
    (collectively 29 McKown). After the Town’s Board of Appeals (BOA) denied
    29 McKown’s administrative appeal from the Code Enforcement Officer’s
    (CEO’s) decision to lift a stop work order he had issued to Harbor Crossing
    during the building’s construction, 29 McKown sought review of the BOA’s
    decision in the Superior Court pursuant to M.R. Civ. P. 80B. 29 McKown now
    appeals from a judgment of the court (Lincoln County, Billings, J.) affirming the
    *    Although Justice Humphrey participated in the appeal, he retired before this opinion was
    certified.
    2
    BOA’s decision. We vacate the judgment and remand for further proceedings
    before the CEO.
    I. BACKGROUND
    [¶2] The factual background is drawn from the undisputed facts and the
    procedural record. See LaMarre v. Town of China, 
    2021 ME 45
    , ¶ 1 n.1,
    
    259 A.3d 764
    . The following timeline traces Harbor Crossing’s project:
    • March 2020: Harbor Crossing purchased the property.
    • March 26, 2020: Harbor Crossing applied for a building permit to
    renovate the existing building with a “new roof, exterior doors, siding,
    trim, new flooring, interior doors, paint, [and a] heat pump” and
    concurrently applied to the Planning Board for permission to operate a
    branch real estate office in the renovated building.
    • May 13, 2020:       The Planning Board approved Harbor Crossing’s
    application.
    • June 2, 2020:     The CEO issued building permit #20-37 to Harbor
    Crossing.
    • June 5, 2020: Harbor Crossing advised the CEO that it had discovered
    that the existing building was in “very poor condition” and asked whether
    a new building permit would be required to demolish and rebuild the
    building with a two-foot extension of one wall. The CEO responded that
    a new building permit would be required for that project.
    Harbor Crossing submitted a new application seeking to demolish the
    existing building; pour a new foundation; expand the main portion of the
    building from 20’x22’ to 22’x22’; change the roof pitch; and change the
    height of the building to 16’.
    3
    • June 8, 2020: The CEO issued building permit #20-41 to Harbor
    Crossing. No notice was published or given to the abutters.
    • September 17, 2020: After receiving a complaint,1 the CEO issued a stop
    work order to Harbor Crossing, citing “a deviation from the building
    design permitted by this office on June 8, 2020, under building
    permit 20-41.” The order stated that it would remain in effect until
    Harbor Crossing “provide[d] the [CEO with] a revised plan.” By email, the
    CEO advised Harbor Crossing that the building actually being constructed
    “may have triggered a reason for you to have to go before the Planning
    Board for approval.”
    • September 25, 2020: After Harbor Crossing submitted new building
    plans, the CEO lifted the stop work order; he did not issue a new building
    permit. The notification lifting the stop work order said only that the CEO
    had “received the information requested” and that “[t]he information
    satisfies this office.”
    • October 22, 2020: Contending that Harbor Crossing’s new building
    required Planning Board approval pursuant to the Town’s Land Use
    Ordinance, 29 McKown appealed to the BOA from the CEO’s action lifting
    the stop work order. See Boothbay Harbor, Me., Land Use Ordinance
    § 170-61(A)-(B) (May 8, 2010).
    • November 24, 2020: Following a hearing on November 19, 2020, the
    BOA denied the appeal in a written decision that summarized the parties’
    arguments and the CEO’s explanation of his findings. In reaching its
    decision, the BOA “relied upon the CEO’s statements” at the hearing.
    [¶3] On December 11, 2020, 29 McKown appealed the BOA’s decision to
    the Superior Court pursuant to M.R. Civ. P. 80B. Its complaint asserted that in
    lifting the stop work order, the CEO effectively issued a new building permit
    1  Although the Superior Court found that 29 McKown complained, Harbor Crossing asserts there
    is no record evidence of that.
    4
    without Planning Board approval as required by the Land Use Ordinance.2 See
    Boothbay Harbor, Me., Land Use Ordinance §§ 170-11 (May 3, 2013), 170-61
    (May 8, 2010). On August 30, 2021, the court affirmed the BOA’s decision.
    Harbor Crossing timely appealed from the Superior Court’s judgment. See M.R.
    App. P. 2B(c)(1); M.R. Civ. P. 80B(n).
    II. DISCUSSION
    [¶4] “When the Superior Court has acted in its intermediate appellate
    capacity to adjudicate an appeal from a municipal zoning board decision, we
    review the operative decision of the municipality directly.” Zappia v. Town of
    Old Orchard Beach, 
    2022 ME 15
    , ¶ 5, 
    271 A.3d 753
    . In identifying the operative
    decision to be reviewed, if “the ordinance explicitly calls for the [BOA’s] review
    to be appellate, the operative decision is that of the CEO.” Id.; see LaMarre,
    
    2021 ME 45
    , ¶ 4, 
    259 A.3d 764
     (“[I]f . . . the scope of the Board’s review is
    appellate, we review the CEO’s decision directly.”); 30-A M.R.S. § 2691(3)(C)
    (2022) (“If a[n] . . . ordinance establishes an appellate review process for the
    board [of appeals], the board shall limit its review on appeal to the record
    established by the board or official whose decision is the subject of the appeal
    2The complaint also requested declaratory judgment relief; that count was dismissed by the court
    as duplicative.
    5
    and to the arguments of the parties” and “may not accept new evidence as part
    of an appellate review.”).
    [¶5] The Boothbay Harbor Ordinance governing the BOA explicitly
    provides that
    [a]dministrative appeals shall be an appellate hearing. If new facts
    or evidence are available, the matter shall be referred back to the
    Planning Board or Code Enforcement Officer for a new decision
    based on the additional information.
    Boothbay Harbor, Me., Land Use Ordinance § 170-108(D)(2)(a) (May 3, 2008).
    The BOA recognized that it had only appellate jurisdiction. Accordingly, we will
    review the decision of the CEO and not that of the BOA or the Superior Court.
    See Zappia, 
    2022 ME 15
    , ¶ 5, 
    271 A.3d 753
    ; LaMarre, 
    2021 ME 45
    , ¶¶ 4-5,
    
    259 A.3d 764
    .
    [¶6] In LaMarre, we cautioned municipalities about the frequently
    occurring pitfalls of an ordinance that, like Boothbay Harbor’s, provides for
    appellate review by a board of appeals. 
    2021 ME 45
    , ¶¶ 11-15, 
    259 A.3d 764
    .
    The inherent problems of appellate-only review identified in LaMarre are
    present here, and they lead to the same result. For that reason, we again
    “strongly urge municipalities to provide for de novo review of CEO decisions by
    boards of appeals.” Id. ¶ 15.
    6
    [¶7] First, because there is no evidence in the record that any notice of
    the June 8, 2020, demolish-and-rebuild permit was published as required by
    the Ordinance,3 by the time 29 McKown learned of the extent of the project “the
    decision [to grant the permit had] already been made by the CEO based on
    whatever information [Harbor Crossing] submitted.” Id. ¶ 13. The failure to
    give the required notice, coupled with the absence of de novo review by the
    BOA, meant that 29 McKown could not submit opposing evidence it may have
    wished to present to the Town at any point in Harbor Crossing’s construction
    process, thus “depriv[ing] [29 McKown] of a critical component of
    administrative due process.”4 Id.; see Zappia, 
    2022 ME 15
    , ¶ 7, 
    271 A.3d 753
    3 Boothbay Harbor, Me., Land Use Ordinance § 170-11(A)(6) (May 5, 2003) (“All applications for
    building permits must be advertised by the Code Enforcement Officer for seven days in the local
    newspaper to allow for public comment.”). Harbor Crossing argues that 29 McKown had notice of
    the Planning Board proceeding that resulted in the approval of its building for use as a real estate
    office, but that process concerned only the building’s prospective use, not changes to its design, and
    it preceded the building permits issued by the CEO.
    4The BOA found that 29 McKown’s appeal from the CEO’s decision to lift the stop work order on
    September 25, 2020, was timely. To the extent that Harbor Crossing contends that 29 McKown’s
    appeal is not properly before us because it was not taken from the CEO’s issuance of the June 8, 2020,
    building permit that was the subject of the stop work order, we have held that a regulatory decision
    finding that original permitting standards were not violated is itself an enforcement action that is
    judicially reviewable. See Fox Islands Wind Neighbors v. Dep’t of Env’t Prot., 
    2015 ME 53
    , ¶¶ 5, 17,
    19-20, 
    116 A.3d 940
    .
    In any event, were it necessary for 29 McKown to take a late appeal from the original building
    permit, the CEO’s failure to give notice of the permit as required by the Ordinance would likely call
    for application of a good cause exception to the Ordinance’s deadlines. See supra n.3; Viles v. Town of
    Embden, 
    2006 ME 107
    , ¶¶ 12-13, 
    905 A.2d 298
     (“The need for a good cause exception primarily stems
    from the lack of notice of the issuance of the building permit to abutting landowners or other persons
    who may be aggrieved by its issuance. . . . The good cause exception was designed because the lack of
    a notice requirement may mean that an abutting landowner does not learn of a permit until the time
    7
    (stating that when the BOA is limited to appellate review, it is “preclud[ed] . . .
    from taking additional evidence or adopting its own findings of fact”).
    [¶8] The second problem identified by LaMarre is that
    adjudication is not a usual CEO task. Unsurprisingly, when an
    objection by an interested person comes to the attention of a CEO
    during the permitting process, the CEO is unfamiliar with the
    minimum requirements of due process and the prerequisites for
    preparing a record and a decision sufficient for meaningful
    appellate review.
    
    2021 ME 45
    , ¶ 14, 
    259 A.3d 764
    .
    [¶9] As LaMarre anticipated, the factual record created by the CEO in this
    case is sparse. Both the original renovation permit and the demolish-and-
    rebuild permit were issued to Harbor Crossing with no remarks by the CEO.
    When the CEO issued the stop work order some three months later, he cited
    “a deviation from the building design permitted by this office on June 8, 2020,
    under building permit 20-41.” The order made no finding reviewable on appeal
    identifying the nature of the deviation or what corrections would be necessary,
    saying only that Harbor Crossing was required to submit “a revised plan”
    showing the building’s specifications.
    period for appeal has expired.”); Brackett v. Town of Rangeley, 
    2003 ME 109
    , ¶ 24, 
    831 A.2d 422
    (“When a town violates its own ordinance as to process and on the merits, equity will infer a good
    cause exception to an ordinance that requires a party to appeal within thirty days of the issuance of
    a building permit.”); Boothbay Harbor, Me., Land Use Ordinance § 170-109(A)(1) (May 3, 1999)
    (requiring that decisions of the CEO be appealed “within 30 days of the action complained of”).
    8
    [¶10] Private email correspondence from the CEO to Harbor Crossing
    was somewhat more detailed in identifying the problem, but neither it nor
    Harbor Crossing’s private response by email was readily available to
    29 McKown or any other potential objector. When the CEO lifted the stop work
    order, his decision officially found only that the information he had received
    from Harbor Crossing “satisfies this office.” Precisely what led to the stop work
    order and how the “deviation” had been remedied was again left unspecified,
    and there is no indication that the CEO invited input from 29 McKown or
    anyone else before lifting the order.
    [¶11] The CEO’s reviewable record leading to 29 McKown’s appeal to the
    BOA consists of nothing more than the barebones entries noted above.
    Although the Board’s written order denying 29 McKown’s appeal provided a
    summary of the CEO’s recitation at the hearing of his factual findings that led to
    the stop work order being lifted, because the BOA did not have de novo
    jurisdiction we are limited to reviewing the CEO’s findings directly.5 LaMarre,
    
    2021 ME 45
    , ¶ 4, 
    259 A.3d 764
    .
    [¶12] For a CEO’s decision to be judicially reviewable, the CEO must
    render a decision “based on substantial evidence in the record” that “contain[s]
    5   At oral argument, Harbor Crossing agreed that we cannot review the record before the BOA.
    9
    findings of fact sufficient to apprise the reviewing court of the decision’s basis.”
    Id. ¶ 6. The mere issuance of a building permit—or the lifting of a stop work
    order concerning that permit based only on unspecified “information [that]
    satisfies [the CEO’s] office”—is, absent findings of fact or conclusions of law,
    “insufficient to allow for meaningful appellate review.” Id. ¶ 7 (quotation marks
    omitted); see id. ¶ 9 (“There is no identification of what [the potentially
    relevant] ‘new information’ was, or what other material the CEO reviewed in
    his investigation of the facts. This is not sufficient to provide a record for
    appellate review.”).
    [¶13] For the reasons we have discussed, we conclude that 29 McKown
    was deprived of administrative due process and that the CEO did not issue a
    judicially reviewable decision in lifting the stop work order. Accordingly, we
    reach the same result as we did in LaMarre and
    remand for the CEO to issue a reviewable decision. The evidence
    upon which the CEO makes his decision must be identified and
    contained in the record. [The parties] must be permitted to submit
    their evidence and rebut each other’s evidence, no substantive
    ex parte communications with the CEO should take place, and the
    CEO’s decision must include findings of fact and conclusions of law
    sufficient to understand the basis for that decision.
    Id. ¶ 15 (citations omitted).
    10
    The entry is:
    Judgment vacated. Remanded to the Superior
    Court with instructions to remand the matter to
    the Board of Appeals with instructions to
    remand to the Code Enforcement Officer for
    proceedings consistent with this opinion.
    Kristin M. Collins, Esq. (orally), and Stephen E.F. Langsdorf, Esq., Preti Flaherty
    Beliveau & Pachios LLP, Augusta, for appellants 29 McKown LLC and Chandler
    Wright
    Scott D. Anderson, Esq. (orally), Verrill Dana, LLP, Portland, for appellee Harbor
    Crossing, LLC
    John A. Cunningham, Esq., Eaton Peabody, Brunswick, for appellee Town of
    Boothbay Harbor
    Lincoln County Superior Court docket number AP-2020-06
    FOR CLERK REFERENCE ONLY