Passadumkeag Mountain Friends v. Board of Environmental Protection , 102 A.3d 1181 ( 2014 )


Menu:
  • MAINE SUPREME JUDICIAL COURT                                              Reporter of Decisions
    Decision: 
    2014 ME 116
    Docket:   BEP-13-413
    Argued:   September 4, 2014
    Decided:  October 21, 2014
    Panel:          SAUFLEY, C.J., and SILVER, MEAD, GORMAN, and JABAR, JJ.
    PASSADUMKEAG MOUNTAIN FRIENDS et al.
    v.
    BOARD OF ENVIRONMENTAL PROTECTION et al.
    JABAR, J.
    [¶1]      Passadumkeag Mountain Friends (PMF), a Maine nonprofit
    corporation, Alexander F. Cuprak, and Rhonda Cuprak appeal from a decision by
    the Board of Environmental Protection (the Board) granting Passadumkeag
    Windpark, LLC, (PW) a permit to develop a wind farm on property owned by
    Penobscot Forest, LLC, (PF) located on Passadumkeag Ridge in Grand Falls
    Township. The Board’s decision followed PW and PF’s appeal from the decision
    of the Department of Environmental Protection (the Department) denying the
    requested permit. PMF and the Cupraks contend that we should treat the decision
    of the Department, rather than the decision of the Board, as operative for purposes
    of appellate review. The Cupraks also contend that, even if the Board’s decision is
    reviewed on appeal, the record does not support that decision, and that they were
    denied due process because of ex parte communications between the Board, PW,
    2
    and PF during the application process. We disagree with these contentions and
    affirm the Board’s decision.
    I. ADMINISTRATIVE PROCESS
    [¶2] In February 2012, PW applied to the Department for an expedited wind
    energy development permit pursuant to the Natural Resources Protection Act, 38
    M.R.S. §§ 480-A to 480-HH (2012). See 35-A M.R.S. § 3451(4) (2013); 38
    M.R.S. § 480-C. It also applied for the Department’s approval of the project
    pursuant to the site location of development statute. See 38 M.R.S. §§ 482(2)(A),
    483-A (2013). Through these applications, PW sought approval to construct a
    wind farm on Passadumkeag Ridge in Grand Falls Township. The project features
    fourteen 140-meter-high turbines, access roads, a crane path, a meteorological
    tower, and electrical collection infrastructure including an electrical substation, an
    operations and maintenance building in Greenbush, and a 17-mile transmission
    line.
    [¶3] While considering PW’s application, the Department’s staff made two
    site visits and held two public meetings. The Department did not hold a public
    hearing, concluding that there was insufficient “credible conflicting technical
    information” that would warrant a public hearing. See 38 M.R.S. § 345-A(1-A)
    (2013); 2 C.M.R. 06 096 002-3 § 7(B) (2013).             During the meetings, the
    Department heard concerns from numerous members of the public, whom it
    3
    labeled “interested persons,” including the Cupraks, and several individual
    members of PMF. See 2 C.M.R. 06 096 002-1 § 1(J) (2013).
    [¶4]    The Department ultimately denied the application, finding that
    construction on Passadumkeag Ridge would dramatically change the undeveloped
    view of Passadumkeag Mountain from Saponac Pond, and concluding that the
    project would have an unreasonable adverse impact on the scenic character and
    existing uses related to the scenic character of Saponac Pond, a scenic resource of
    state or national significance (SRSNS). The Department also concluded that, with
    the exception of an unreasonable adverse impact on the scenic character and
    existing uses of Saponac Pond, the applicant had met all permit criteria. After
    denial of the application, PW, the applicant, and PF, the owner of the land on
    which the wind park would be built, both filed timely notices of appeal to the
    Board. See 38 M.R.S. § 344(2-A) (2013). The Cupraks then filed a letter with the
    Board stating their objections to the application and the appeal.
    [¶5] While it was reviewing the Department’s decision, the Board sent
    several letters to PW regarding the issues and evidence that it would consider,
    without sending copies to the Cupraks or other interested parties. At its March 21,
    2013, meeting, the Board heard arguments from PW, PF, the Department’s staff,
    and the Cupraks, but it did not take any additional evidence or augment the
    administrative record.
    4
    [¶6] On August 20, 2013, the Board issued “Findings of Fact and Order on
    Appeal.” In it, the Board stated that the scenic consultants hired by PW and the
    Department “agree that the project will not have an unreasonable adverse impact
    on the scenic character of Saponac Pond,” and that it found these assessments
    credible. Based on this determination, the Board granted the permit. Both PMF
    and the Cupraks timely appealed. See 38 M.R.S. § 346(4) (2013); M.R. App. P.
    2(b)(3).
    II. DISCUSSION
    [¶7] Appellants raise three fundamental issues on appeal: (1) whether the
    decision of the Department, rather than the Board, is the operative decision on
    appeal; (2) whether there is sufficient evidence to support the Board’s decision;
    and (3) whether the Cupraks were denied due process as a result of ex parte
    communications between the Board, PW, and PF during the application process.1
    A.       Operative Decision
    [¶8] PMF and the Cupraks argue that the Board erred in reviewing the
    Department’s decision de novo, and that the Department, as fact-finder, issues the
    operative decision for appellate review. Appellants base their arguments on the
    language of 38 M.R.S. § 341-D (2013), which details the Board’s responsibilities
    1
    Although PF challenges PMF’s standing to seek review of the Board’s decision, we decline to
    address this issue because PMF has not raised any issues that were not raised by the Cupraks, for whom
    standing is uncontested.
    5
    and duties in reviewing permit applications. Pursuant to section 341-D(4)(D),
    which applies specifically to “[l]icense or permit decisions regarding an expedited
    wind energy development,” the Board may supplement the record with additional
    information at its discretion. Section 341-D(4)(D) does not expressly provide that
    the Board is not bound by the Department’s findings, unlike section 341-D(4)(A),
    which pertains to other permit and license appeals. PMF and the Cupraks argue
    that this omission is an indication of the Legislature’s intent to have the Board give
    deference to the Department’s findings.
    [¶9]    However, in Concerned Citizens to Save Roxbury v. Board of
    Environmental Protection, we determined that the Board had engaged in an
    independent review of the record, which included not only the administrative
    record before the Department, but also some supplemental evidence presented by
    the parties. 
    2011 ME 39
    ¶ 17, 
    15 A.3d 1263
    . Based on that determination, we
    concluded that the Board’s decision was the operative decision for our appellate
    review. 
    Id. In our
    discussion, we noted that the Department’s rules for processing
    appeals provided that the Board, “is not bound by the [Department’s] findings of
    fact or conclusions of law.” 
    Id. ¶ 16
    (quoting 2 C.M.R. 06 096 002-12 § 24(B)(7)
    (2003)).
    [¶10] Although the Board in this case did not supplement the administrative
    record in the course of its review, it engaged in an independent analysis of the
    6
    record, made factual findings regarding the credibility of various experts, and
    concluded that the proposed development would not have an unreasonable adverse
    impact on Saponac Pond. See 2 C.M.R. 06 096 002-12 § 24(G) (2013) (providing
    that the “Board is not bound by the [Department’s] findings of fact or conclusions
    of law”). The Board acted as both fact-finder and decision-maker pursuant to
    agency rules, and did not err in so doing. The Board’s decision is the operative
    decision for purposes of this appeal.
    B.    The Board’s Findings and Conclusions
    [¶11] The Cupraks argue that the Board’s findings regarding the visual
    impact of the proposed project were based upon “statistically flawed” evidence.
    They also contend that the Board erred as a matter of law in weighing the relevant
    criteria for determining whether the proposed project would have an unreasonable
    adverse impact on the scenic character and related uses of Saponac Pond.
    [¶12] Our review of administrative agency decisions is “deferential and
    limited.” Friends of Lincoln Lakes v. Bd. of Envtl. Prot., 
    2010 ME 18
    , ¶ 12,
    
    989 A.2d 1128
    . When reviewing an agency’s interpretation of a statute that it
    administers, we defer to the agency’s construction unless the statute plainly
    compels a contrary result. FPL Energy Me. Hydro LLC v. Dep’t of Envtl. Prot.,
    
    2007 ME 97
    , ¶ 11, 
    926 A.2d 1197
    . When reviewing an agency’s factual findings,
    we examine the record in its entirety. Concerned Citizens to Save Roxbury, 2011
    
    7 ME 39
    , ¶ 24, 
    15 A.3d 1263
    .         “‘We must affirm findings of fact if they are
    supported by substantial evidence in the record, even if the record contains
    inconsistent evidence . . . .’” 
    Id. (quoting Friends
    of Lincoln Lakes, 
    2010 ME 18
    , ¶
    13, 
    989 A.2d 1128
    ). We will vacate an agency’s factual findings only if the record
    contains no competent evidence to support them. 
    Id. [¶13] The
    statute guiding the Board’s determination of a grid-scale wind
    project’s impact on the character and uses of a SRSNS requires the Board to
    consider six criteria but does not require it to assign more or less weight to any one
    criterion. 35-A M.R.S. § 3452(3) (2013). Because this statute does not compel a
    result contrary to that reached by the Board, we defer to the Board’s evaluation.
    [¶14] Although the Cupraks challenge the credibility and significance of
    some of the evidence in the record, the Board was free to make its own credibility
    determinations with respect to the conflicting evidence before it. See Stewart v.
    Town of Sedgwick, 
    2000 ME 157
    , ¶ 7, 
    757 A.2d 773
    (explaining that a
    decision-maker makes its own credibility determinations when conducting a de
    novo review). Its findings regarding the project’s visual impact are supported by
    evidence that Saponac Pond is lightly used, that the surrounding area is developed,
    and that the project would not have an unreasonable adverse impact on the
    viewshed of the pond. The Board’s findings and conclusion are supported by
    substantial evidence in the record. We therefore uphold the Board’s decision.
    8
    C.    Ex Parte Communications
    [¶15] Finally, the Cupraks contend that the Board violated their due process
    rights by communicating with PW and PF without including them or giving them
    an opportunity to comment on the materials communicated. The Board counters
    that 5 M.R.S. § 9055 (2013) prohibits ex parte communications only in an
    “adjudicatory proceeding,” which is defined as “any proceeding before an agency
    in which the legal rights, duties or privileges of specific persons are required by
    constitutional law or statute to be determined after an opportunity for hearing,” 5
    M.R.S. § 8002(1) (2013). Because the decision to hold an adjudicatory hearing
    was within the Board’s discretion pursuant to 38 M.R.S. § 341-D(4), the Board
    argues that the opportunity for a hearing in this case was not a matter of
    constitutional or statutory law, and that 5 M.R.S. § 9055 therefore does not prohibit
    ex parte communications.
    [¶16]     Although section 9055 provides that “[i]n any adjudicatory
    proceeding, no agency members . . . may communicate directly or indirectly in
    connection with any issue of fact, law or procedure, with any party or other
    persons legally interested in the outcome of the proceeding, except upon notice and
    opportunity for all parties to participate,” 5 M.R.S. § 9055(1) (emphasis added), we
    have not held that there is a bright-line rule that permits ex parte communications
    in all nonadjudicatory proceedings. We have instead concluded that the contours
    9
    of due process in an administrative proceeding, particularly a nonadjudicatory,
    fact-gathering proceeding, depend upon the nature of the proceeding, the nature of
    the alleged right involved, and the possible burden that additional procedures
    would place on the proceeding. Cunningham v. Kittery Planning Bd., 
    400 A.2d 1070
    , 1079 (Me. 1979); Duffy v. Town of Berwick, 
    2013 ME 105
    , ¶ 16, 
    82 A.3d 148
    . Other factors that we take into account include
    the gravity of the ex parte communications; whether the contacts may
    have influenced the . . . ultimate decision; whether the party making
    the improper contacts benefited from the . . . ultimate decision;
    whether the contents of the communications were unknown to
    opposing parties, who therefore had no opportunity to respond; and
    whether vacation of the . . . decision and remand for new proceedings
    would serve a useful purpose.
    Duffy, 
    2013 ME 105
    , ¶ 19, 
    82 A.3d 148
    (quotation marks omitted).
    [¶17]    The Cupraks have challenged as ex parte the following
    communications: (1) a letter sent from PW to the Board chair seeking to exclude
    the Cupraks’ responses to PW and PF’s notice of appeal; (2) materials sent by PF
    to the Board in preparation for the March 21, 2013, public meeting; and (3) three
    letters from the Board to PW, all of which advised PW that it could not supplement
    the administrative record with the additional evidence that it sought to proffer on
    10
    appeal.2 The Cupraks have not argued that these communications between PF,
    PW, and the Board harmed them in any substantial way, and there is no evidence
    suggesting that the communications resulted in “‘procedural unfairness.’” 
    Id. ¶ 18
    (quoting Lane Constr. Corp. v. Town of Washington, 
    2008 ME 45
    , ¶ 32, 
    942 A.2d 1202
    ).
    [¶18] Although the Board did not hold a formal hearing, it gave the Cupraks
    the opportunity to participate and the Cupraks have not argued that the proceedings
    before the Board were fundamentally unfair. See 
    id. ¶¶ 20-21;
    Cunningham, 400
    A.2d at 1079
    . We therefore conclude that the communications at issue did not
    affect the Cupraks’ due process rights.3
    [¶19] For the reasons stated above, we affirm the decision of the Board.
    The entry is:
    Judgment affirmed.
    2
    The Cupraks also refer to “numerous other communications” occurring ex parte between the Board
    and the PW. However, of the approximately ten separate communications referred to in the Cupraks’
    appellate brief, only the three letters are actually included in the administrative record that the parties
    provided to us.
    3
    Although it may be good practice for state agencies to send copies of all correspondence to all
    parties involved in the application process, it is up to the Legislature to mandate that such practice be
    undertaken during the application process.
    11
    On the briefs:
    Alexander F. Cuprak and Rhonda Cuprak, pro se appellants
    Rufus E. Brown, Esq., Brown & Burke, for appellants
    Passadumkeag Mountain Friends et al.
    Janet T. Mills, Attorney General, and Margaret A. Bensinger,
    Asst. Atty. Gen., Office of the Attorney General, Augusta, for
    appellee Board of Environmental Protection
    P. Andrew Hamilton, Esq., Jonathan A. Pottle, Esq., and Ryan
    P. Dumais, Esq., Eaton Peabody, for appellee Penobscot Forest,
    LLC
    Katherine A. Joyce, Esq., and Mary E. Costigan, Esq.,
    Bernstein Shur, for appellee Passadumkeag Windpark LLC
    At oral argument:
    Alexander F. Cuprak and Rhonda Cuprak, pro se appellants
    Rufus E. Brown, Esq., for appellants Passadumkeag Mountain
    Friends et al.
    Margaret A. Bensinger, Asst. Atty. Gen., for appellee Board of
    Environmental Protection
    Katherine A. Joyce, Esq., for appellee Passadumkeag Windpark
    LLC
    Board of Environmental Protection number BEP L-25597
    FOR CLERK REFERENCE ONLY