in Re App of Mich Electric Transmission Co for Transmission Line , 309 Mich. App. 1 ( 2014 )


Menu:
  •                           STATE OF MICHIGAN
    COURT OF APPEALS
    HAR COMPANY, LLC, KEN IRISH,                   UNPUBLISHED
    MARGARET IRISH, JACK KUIPERS, JANE             November 18, 2014
    KUIPERS, Individually and as Trustee of JANE
    KUIPERS TRUST, JMK HOLDINGS, LLC,
    DOUG MAXWELL, Individually and as Trustee
    of the DOUGLAS E. MAXWELL 2000 TRUST,
    MICKI MAXWELL, Individually and as Trustee
    of the MICKI MAXWELL 2000 TRUST, WARD
    SQUIRES and HENRIETTA SQUIRES,
    Appellants,
    v                                              No. 317872
    MPSC
    MICHIGAN ELECTRIC TRANSMISSION                 LC No. 00-017041
    COMPANY,
    Petitioner-Appellee,
    and
    MICHIGAN PUBLIC SERVICE COMMISSION,
    Appellee.
    CHARTER TOWNSHIP OF OSHTEMO,
    Appellant,
    v                                              No. 317893
    MPSC
    MICHIGAN ELECTRIC TRANSMISSION                 LC No. 00-017041
    COMPANY LLC,
    Petitioner-Appellee,
    and
    MICHIGAN PUBLIC SERVICE COMMISSION,
    -1-
    Appellee,
    and
    MICHIGAN TOWNSHIPS ASSOCIATION,
    MICHIGAN MUNICIPAL LEAGUE, PUBLIC
    CORPORATION LAW OF THE STATE BAR OF
    MICHIGAN, MICHIGAN COALITION TO
    PROTECT PUBLIC RIGHTS-OF-WAY,
    MICHIGAN CABLE TELECOMMUNICATIONS
    ASSOCIATION, and MICHIGAN ENERGY
    PROVIDERS GROUP,
    Amici Curiae.
    Before: OWENS, P.J., and MARKEY and SERVITTO, JJ.
    PER CURIAM.
    In these consolidated cases appellants Landowners1 and Charter Township of Oshtemo
    appeal as of right an order of the Michigan Public Service Commission (PSC) approving the
    application of Michigan Electric Transmission Company, LLC (METC) for a certificate of
    public convenience and necessity (CPCN) for construction of an overhead transmission line. We
    affirm in both cases and lift the stay imposed pending appeal of these cases.
    I. Background
    The Legislature enacted the Electric Transmission Line Certification Act (Act 30), 
    1995 PA 30
    , effective May 17, 1995, to regulate the construction and location of certain electric
    transmission lines. Act 30 provides that if an electric utility with 50,000 or more residential
    customers plans to construct a major transmission line,2 the utility must submit a plan to the PSC
    and may not begin construction on the line until the PSC has issued a CPCN. MCL 460.565. A
    1
    Appellants in Docket No. 317872, Har Company, LLC, Ken Irish, Margaret Irish, Jack
    Kuipers, Jane Kuipers, Individually and as Trustee of the Jane Kuipers Trust, JMK Holdings,
    LLC, Doug Maxwell, Individually and as Trustee of the Douglas E. Maxwell 2000 Trust, Micki
    Maxwell, Individually and as Trustee of the Micki A. Maxwell 2000 Trust, Ward Squires, and
    Henrietta Squires, will be referred to collectively as the Landowners.
    2
    A major transmission line is “a transmission line of 5 miles or more in length wholly or
    partially owned by an electric utility, affiliated transmission company, or independent
    transmission company through which electricity is transferred at system bulk voltage of 345
    kilovolts or more.” MCL 460.562(g).
    -2-
    utility that wishes to construct a transmission line3 other than a major transmission line may, but
    is not required to, submit an application for a CPCN to the PSC. If the utility applies for a
    CPCN, the utility may not begin construction on the transmission line until the PSC has issued a
    CPCN. MCL 460.569(1). With one exception, “the provisions of this act that apply to
    applications and certificates for major transmission lines apply in the same manner to
    applications and certificates issued under this section.” MCL 460.569(2). The PSC proceeds in
    the same manner on both mandatory and voluntary applications. MCL 460.569(2). A CPCN
    takes “precedence over a conflicting local ordinance, law, rule, regulation, policy, or practice that
    prohibits or regulates the location or construction of a transmission line for which the
    commission has issued a certificate.” MCL 460.570(1). In addition, Act 30 controls “in any
    conflict between this act and any other law of this state.” MCL 460.563(2).
    II. Underlying Facts and Proceedings
    METC proposed the construction of a new transmission line; however, Oshtemo
    Township amended its utility control ordinance to require METC to prove the necessity of the
    proposed line and receive Township approval before beginning construction of the line. In
    addition, the ordinance required METC to locate the proposed line underground in any area in
    which the line would come within 250 feet of a public right-of-way. METC filed an application
    with the PSC seeking a CPCN “for the construction of two double-circuit 138 kilovolt (“kV”)
    transmission lines on a 220-foot right-of-way running through Oshtemo Township, Kalamazoo
    County, and an electrical transmission substation in Almena Township, Van Buren County.
    METC asserted that the issuance of a CPCN would take precedence over any conflicting local
    ordinance.
    Evidence produced at the evidentiary hearing showed that the parties had conflicting
    views regarding the efficacy of METC’s proposed project. A witness for METC testified that the
    Kalamazoo area was served by three 345/138 kV transformers located at the Argenta substation.
    METC’s proposal to add additional lines and a new substation at Weeds Lake would enable
    METC to comply with national mandatory planning criteria.
    METC’s witness stated that METC considered two alternative routes for the lines, but
    rejected them because they failed to meet planning criteria. METC considered the option of
    adding a fourth transformer at the Argenta substation, but rejected that option because it would
    not protect against the risk that the entire substation could be disconnected from the 345kV
    power source or the 138kV transmission lines that served an area that included Kalamazoo and
    Battle Creek.
    A witness for Oshtemo Township testified that the Township preferred two identified
    alternative routes over METC’s preferred route because the alternative routes relied in part on
    public lands and an existing corridor and would impose less of a burden on private property
    owners.
    3
    A transmission line is “all structures, equipment, and real property necessary to transfer
    electricity at system bulk supply voltage of 100 kilovolts or more.” MCL 460.562(k).
    -3-
    A witness for the Landowners testified that the quantifiable and nonquantifiable benefits
    of the proposed project did not offset the detriments, including the cost of the project, the adverse
    impact caused by locating the project close to private residences, and the loss of woodlands and
    croplands. The witness maintained that the installation of a fourth transformer at the Argenta
    substation would cost less but would achieve results comparable to METC’s proposed project.
    The witness also asserted that an alternative referred to as B Avenue was preferable to METC’s
    Weeds Lake proposal because it required only one transmission line and power flow control
    protectors could guard against unbalanced power flows.
    The PSC issued an order granting METC a CPCN for the construction of METC’s
    proposed transmission line along METC’s preferred route. The PSC noted that the “most
    contentious issue in this case is whether METC sufficiently demonstrated that the quantifiable
    and nonquantifiable public benefits of the project justify its construction.” The PSC found that
    “a formal benefit/cost analysis of the project is not strictly required; however, it appears that the
    most straightforward way to demonstrate that a project’s benefits justify its construction, as the
    Commission must find under section 8(5)(a), is through the submission of at least some
    reasonable estimate of the value of benefits of the project.”
    The PSC found that the record established that two realistic proposals existed to address
    the contingency issue: 1) the Weeds Lake proposal, estimated by METC to cost $45 million, and
    (2) the B Avenue proposal put forth by the Landowners, and estimated to cost $37 to $47
    million. The PSC stated:
    . . . The Landowners presented evidence that the value of the benefit of increased
    efficiency resulting from the Weeds Lake Project was $1.3 million per year, thus
    offsetting the difference in cost between the two proposals by that amount. In
    addition, METC identified, but did not quantify, the benefits of 500 MW of
    additional capacity and the establishment of a geographically separate and distinct
    source of power for the Kalamazoo area, thus resulting in a more robust system
    and addressing a NERC Category D contingency. As the Staff pointed out, while
    a NERC Category D contingency is unlikely, the costs to businesses, industry,
    and residents in the event of the loss of the lines to the Argenta station are
    potentially catastrophic. The Commission notes that the costs to Kalamazoo and
    Battle Creek area customers, in the event of a loss of the lines to the Argenta
    station, are certainly higher that the minor cost difference between the Weeds
    Lake project, which would provide a geographically distinct source of power, and
    the B Avenue alternative, which would not.
    The Commission recognizes that transmission infrastructure can provide a
    host of benefits, both in economic and reliability terms, some of which are more
    easily quantified than others. The Commission also sees value in planning for the
    longer term and designing projects that provide comprehensive system benefits,
    even if there are incremental costs for a more robust transmission solution. In this
    case, the proposed project is clearly needed and the alternatives proposed by
    Landowners, while potentially feasible, do not provide comparable benefits.
    Moreover, the associated cost savings are not entirely clear or less costly than the
    proposed project after including the ancillary upgrades.            Therefore, the
    -4-
    Commission finds it appropriate to approve the CPCN because the overall
    benefits justify construction and there is a clear need to proceed with construction
    to maintain reliability.
    The PSC agreed with METC’s assertion that MCL 460.568(5)(b) did not require the
    finding of the best or most reasonable route. The PSC also found that METC presented ample
    evidence that the I-94 route was not a realistic alternative to the Weeds Lake Project.
    The PSC found that under MCL 460.563 and MCL 460.570, the grant of a CPCN to
    METC preempted Oshtemo’s ordinance. In addition, the PSC found that Oshtemo Township,
    not METC, had the burden of demonstrating the cost and practicality of placing a portion of the
    transmission line underground and that the Township failed to carry its burden.
    III. Standard of Review
    The standard of review for PSC orders is narrow and well defined. Pursuant to MCL
    462.25, all rates, fares, charges, classification and joint rates, regulations, practices, and services
    prescribed by the PSC are presumed, prima facie, to be lawful and reasonable. Michigan
    Consolidated Gas Co v Public Service Comm, 
    389 Mich 624
    , 635-636; 209 NW2d 210 (1973).
    A party aggrieved by an order of the PSC has the burden of proving by clear and convincing
    evidence that the order is unlawful or unreasonable. MCL 462.26(8). To establish that a PSC
    order is unlawful, the appellant must show that the PSC failed to follow a mandatory statute or
    abused its discretion in the exercise of its judgment. In re MCI Telecommunications Complaint,
    
    460 Mich 396
    , 427; 596 NW2d 164 (1999). An order is unreasonable if it is not supported by
    the evidence. Associated Truck Lines, Inc v Public Service Comm, 
    377 Mich 259
    , 279; 140
    NW2d 515 (1966).
    A final order of the PSC must be authorized by law and be supported by competent,
    material, and substantial evidence on the whole record. Const 1963, art 6, § 28; Attorney
    General v Public Service Comm, 
    165 Mich App 230
    , 235; 418 NW2d 660 (1987).
    The court gives due deference to the PSC’s administrative expertise and does not
    substitute its judgment for that of the PSC. Attorney General v Public Service Comm No 2, 
    237 Mich App 82
    , 88; 602 NW2d 225 (1999). We give respectful consideration to the PSC’s
    construction of a statute that the PSC is empowered to execute, and we will not overrule that
    construction absent cogent reasons. If the language of a statute is vague or obscure, the PSC’s
    construction serves as an aid to determining the legislative intent and will be given weight if it
    does not conflict with the language of the statute or the purpose of the Legislature. However, the
    construction given to a statute by the PSC is not binding on us. In re Complaint of Rovas
    Against SBC Michigan, 
    482 Mich 90
    , 103-109; 754 NW2d 259 (2008). Whether the PSC
    exceeded the scope of its authority is a question of law that we review de novo. In re Complaint
    of Pelland Against Ameritech Michigan, 
    254 Mich App 675
    , 682; 658 NW2d 849 (2003).
    “Issues of constitutional and statutory construction are questions of law that [this Court
    reviews] de novo.” Lansing v Detroit Edison Co, 
    475 Mich 109
    , 115; 715 NW2d 28 (2006).
    IV. Analysis
    -5-
    A. Docket No. 317872
    On appeal, the Landowners argue that the PSC did not follow the requirements of Act 30,
    and in particular MCL 466.568, in making its decision. METC was required to prove that the
    quantifiable and nonquantifiable benefits of its proposed Weeds Lake Project justified the
    construction of the project. METC was required to prove that a new transmission line was
    needed; however, METC stated only that the line was needed to address a reliability issue that
    could arise if two of the three transformers at the Argenta substation became unavailable at the
    same time. The PSC erred by granting METC’s application for a CPCN. We disagree.
    The PSC is required to issue a CPCN if it makes certain determinations.               MCL
    460.568(5) provides:
    (5) The commission shall grant the application and issue a certificate if it
    determines all of the following:
    (a) The quantifiable and nonquantifiable public benefits of the proposed
    major transmission line justify its construction.
    (b) The proposed or alternative route is feasible and reasonable.
    (c) The proposed major transmission line does not present an unreasonable
    threat to public health or safety.
    The Landowners argued that METC did not prove that the proposed transmission line
    was needed. However, MCL 460.568(5) does not specifically state that an applicant for a
    proposed transmission line must prove that the line is needed.4 Nevertheless, the PSC found that
    METC’s proposed transmission line was needed to address a reliability issue.
    The PSC’s finding that the Landowners’ alternative plan of installing a fourth transformer
    at the Argenta substation was not a viable solution was supported by the requisite evidence. The
    Landowners countered METC’s assertion that installing a fourth transformer would increase
    loads on other circuits by demonstrating the installation of power flow control reactors would
    address this issue. The PSC, however concluded that the addition of a fourth transformer at the
    Argenta substation would not solve the reliability issue. Most of the power for the Kalamazoo
    area would continue to originate from a single substation; therefore, if two or three transformers
    ceased to be operational, the overload on other circuits could cause blackouts. Both METC and
    the Landowners presented expert testimony on the viability of the fourth generator plan. The
    PSC was entitled to choose to accept the testimony of METC’s expert even though the
    Landowners’ expert gave contradictory testimony. ABATE v Public Service Comm, 
    192 Mich 4
    MCL 460.567(2)(f) states that the applicant for a CPCN must include in the application
    information “supporting the need for the proposed major transmission line[.]” MCL 460.568(5)
    contains no such language.
    -6-
    App 19, 27; 480 NW2d 585 (1991). The testimony of one expert constitutes substantial evidence
    in PSC cases. 
    Id.
    The PSC correctly found that METC was not required to do a cost/benefit analysis of the
    Weeds Lake project, even though that project was estimated to cost $32 million more than the
    fourth transformer project. No statute required the METC to perform a cost/benefit analysis, and
    the PSC was not required to make its judgment based solely on cost. The reliability issue was
    the primary reason for METC seeking a CPCN to install a transformation line, and the evidence
    showed that the fourth transformer project would not solve the reliability issue. The PSC was
    entitled to accept METC’s evidence on this issue. ABATE v Public Service Comm, 192 Mich
    App at 27.
    The PSC correctly found that METC’s proposed route for the transmission line was
    feasible and reasonable, in spite of the fact that METC’s proposed route did not get the highest
    score using METC’s own scoring methods. MCL 460.568(5)(b) required only that the PSC find
    that METC’s proposed route was feasible and reasonable, not that it was more feasible and more
    reasonable than any other route proposed by any party. The Landowners suggested that METC
    could have used alternatives such as a quad circuit or a tapping variant to address right-of-way
    concerns; the PSC correctly concluded that those alternatives were not as reliable as METC’s
    Weeds Lake project.
    Next, the Landowners argue that the PSC’s approval of METC’s application for a CPCN
    allowed METC to violate municipal zoning ordinances and to take private property from
    landowners without due process. We disagree.
    A person cannot be deprived of property without due process of law. US Const, Am V;
    Const 1963, art 1, § 17. A person must be afforded notice, an opportunity to heard, and a written
    statement of findings. Michigan Elec Coop Ass’n v Public Service Comm, 
    267 Mich App 608
    ,
    622; 705 NW2d 709 (2005).
    The METC applied for a CPCN under MCL 460.569, and held public meetings on its
    proposal as required by MCL 460.566(1). Moreover, the PSC conducted a contested case
    hearing on the METC’s application; the Landowners intervened in the proceeding, as was their
    right under MCL 460.568(2). The Landowners fully participated in the case and were not
    deprived of due process during the proceedings before the PSC. Michigan Elec Coop Ass’n, 267
    Mich App at 622.
    Furthermore, we reject the Landowners’ argument that the PSC’s act of granting a CPCN
    is not subject to review and therefore denies them due process. A PSC order granting a CPCN is
    appealable as of right to this Court. MCL 460.575(1). A CPCN is “binding as to the public
    convenience and necessity for that transmission line” in “an eminent domain or other related
    proceeding arising out of or related to a transmission line for which a certificate is issued[.]”
    MCL 460.570(3). This Court does not conduct eminent domain proceedings; a CPCN is not
    binding on this Court.
    In order to grant a CPCN to the METC, the PSC was required to find that “[t]
    quantifiable and nonquantifiable public benefits of the proposed major transmission line justify
    -7-
    its construction.” MCL 460.568(5)(a). Logically, to make such a finding, the PSC would have
    to conclude that the proposed transmission line would fulfill a public purpose. As noted, a
    CPCN is “binding as to the public convenience and necessity for that transmission line” in an
    eminent domain case. MCL 460.570(3). Thus, the requisite showing of a public purpose would
    have been made before the commencement of any subsequent condemnation proceeding.
    The Separation of Powers clause of the Michigan Constitution states: “The powers of
    government are divided into three branches: legislative, executive and judicial. No person
    exercising powers of one branch shall exercise powers properly belonging to another branch
    except as expressly provided in this constitution.” Const 1963, art 3, § 2. The Landowners’
    argument that the PSC’s decision violates the Separation of Powers clause because it allows the
    METC to ignore Oshtemo Township’s ordinance that a portion of the transmission line be placed
    underground is without merit. The Legislature enacted statutes providing that a CPCN granted
    by the PSC preempts the Township’s ordinance regarding the placement underground of
    transmission lines, MCL 460.570(1), and that Act 30 controls if it conflicts with any other law of
    this state. MCL 460.563(2). The PSC’s actions were authorized by statute so they did not
    violate the Separation of Powers doctrine.
    The Landowners have not demonstrated that the PSC erred or abused its discretion by
    granting METC’s application for a CPCN.
    B. Docket No. 317893
    The appeal by Oshtemo Township and the amici brief filed by Michigan Townships
    Association, et al,5 present the question whether a local ordinance can prevail over a conflicting
    CPCN issued by the PSC under Act 30.
    The Michigan Constitution grants a municipality the right to control its public places.
    Const 1963, art 7, § 29 provides:
    No person, partnership, association or corporation, public or private,
    operating a public utility shall have a right to the use of the highways, streets,
    alleys or other public places of any county, township, city or village for wires,
    poles, pipes, tracks, conduits or other utility facilities, without the consent of the
    duly constituted authority of the county, township, city or village; or to transact
    local business therein without first obtaining a franchise from the township, city
    or village. Except as otherwise provided in this constitution the right of all
    counties, townships, cities and villages to the reasonable control of their
    highways, streets, alleys and public places is hereby reserved to such local units
    of government.
    5
    The amici represented in the brief are American Transmission Company, DTE Electric
    Company, DTE Gas Company, Enbridge Energy Limited Partnership, Michigan Electric and Gas
    Association, Michigan Electric Cooperative Association, and Wolverine Power Supply
    Cooperative.
    -8-
    The provisions of the Michigan Constitution and state laws concerning municipalities are
    to be liberally construed in favor of those municipalities. Const 1963, art 7, § 34. But, the grant
    of authority in Const 1963, art 7, § 29 is not absolute. Const 1963, art 7, § 22 provides:
    Under general laws the electors of each city and village shall have the
    power and authority to frame, adopt and amend its charter, and to amend an
    existing charter of the city or village heretofore granted or enacted by the
    legislature for the government of the city or village. Each such city and village
    shall have power to adopt resolutions and ordinances relating to its municipal
    concerns, property and government, subject to the constitution and law. No
    enumeration of powers granted to cities and villages in this constitution shall limit
    or restrict the general grant of authority conferred by this section.
    In City of Taylor v Detroit Edison Co, 
    475 Mich 109
    ; 715 NW2d 28 (2006), our Supreme
    Court considered whether the plaintiff’s ordinance requiring the defendant to bear the cost of
    relocating the defendant’s transmission lines underground conflicted with the PSC’s authority
    over cost allocation in this area. The Taylor Court, citing Const 1963, art 7, § 29, stated that “the
    authority reserved to local units of government to exercise reasonable control over the
    enumerated subject areas is explicitly made subject to the other provisions of the Constitution.”
    Taylor, 
    475 Mich at 116
    . The Taylor Court pointed to Const 1963, art 7, § 22 as one such
    provision to which a local unit of government’s authority was subject. Id. The Taylor Court
    reasoned that a local unit of government could exercise reasonable control “to regulate matters of
    local concern, but only in a manner and to the degree that the regulation does not conflict with
    state law.” Taylor, 
    475 Mich at 117-118
    , citing People v McGraw, 
    184 Mich 233
    ; 
    150 NW 836
    (1915).6
    In Lansing v State of Michigan, 
    275 Mich App 423
    ; 737 NW2d 818 (2007), this Court
    considered whether MCL 247.183(2), which permits a utility to construct transmission lines
    “longitudinally within limited access highway rights-of-way and under any public road, street, or
    other subsurface that intersects any limited access highway” without obtaining the consent of the
    governing municipality, was unconstitutional because it eliminated the requirement in Const
    1963, art 7, § 29 that a utility must first obtain such consent. The plaintiff asserted that Const
    1963, art 7, § 29 gave a municipality “the absolute right to refuse to consent to the use of” its
    streets by a utility. Lansing, 275 Mich App at 429. This Court disagreed, finding that the grant
    of authority in Const 1963, art 7, § 29 “is not absolute.” Id. at 432. In addition, this Court found
    that because, as stated in Const 1963, art 7, § 22,
    . . . a city’s authority to grant or withhold consent to use its highways, streets,
    alleys, and other public places can only be exercised through an ordinance or
    resolution, it follows that a city’s ability to grant or withhold consent is also
    subject to the constitution and laws. Consequently, when Const 1963, art 7, §§ 22
    6
    The Taylor Court concluded that the plaintiff’s ordinance might conflict with PSC rules, and if
    so, that portion of the ordinance was invalid. In addition, the Taylor Court concluded that the
    PSC had primary jurisdiction over the issue. Taylor, 
    475 Mich at 123-124
    .
    -9-
    and 29 are read in conjunction, the Legislature has the authority to limit the
    manner and circumstances under which a city may grant or withhold consent
    under § 29. [Id. at 433.]
    This Court found that because MCL 247.183(2) limited a local government’s authority in a
    narrow manner, the statute was “a proper exercise of the Legislature’s authority to limit the
    manner and circumstances under which a city may grant or withhold consent under § 29. Id. at
    433-434.
    Oshtemo Township enacted Ordinance No. 114 that required a utility seeking to construct
    a transmission line to place the line and all related facilities “underground within the public road
    right-of-way and to a point within 250 feet either side of said public right-of-way.” The CPCN
    issued by the PSC allowed METC to construct an overhead transmission line. The PSC found
    that the CPCN preempted the ordinance.
    Oshtemo Township argues that the PSC erred as a matter of law by failing to determine if
    the ordinance conflicted with state law. Oshtemo Township asserts that the ordinance does not
    conflict with any state law or regulations7 because it does not regulate the construction or
    location of the proposed line, even though it might impose additional requirements (i.e., location
    of a portion of the proposed line underground).
    Contrary to arguments made by Oshtemo Township and amici Michigan Townships
    Association, et al, the PSC did not hold that Act 30 preempted all local regulation by the
    Township, and did not eliminate the authority granted to Oshtemo Township by Const 1963, art
    7, § 29 to control its roads and rights-of-way. The arguments that Act 30 preempted Oshtemo
    Township’s ordinance and is unconstitutional ignores the clear language of constitutional
    provisions, MCL 460.570(1), and binding precedent.
    Const 1963, art 7, § 29 makes a utility’s use of public places and rights of way subject to
    local approval. A local government is authorized to enact resolutions and ordinances relating to
    such matters; however, those enactments are “subject to the constitution and law.” Const 1963,
    art 7, § 22.
    METC used Act 30 to apply for a CPCN to build a new transmission line. In making its
    application, METC was required to include any zoning ordinance that would affect, i.e., regulate
    the location or construction of, the proposed route. MCL 460.567(2)(d). Oshtemo Township’s
    relevant ordinance, if applicable, would require METC to locate a portion of its proposed
    transmission line underground. The ordinance did not provide for any exceptions to this
    requirement. METC determined that locating a portion of the proposed line underground would
    be prohibitively expensive, and so sought a CPCN for a line to be constructed entirely above
    7
    Regulations dealing with underground electric facilities are located at AC R 460.511 through
    460.519. However, these regulations refer specifically to “electric distribution facilities”
    operated at 15,000 or 20,000 volts or less. These regulations do not apply to the proposed
    transmission line at issue in these cases.
    -10-
    ground. The PSC was entitled to accept METC’s evidence regarding the cost and preferability of
    constructing a line above ground, notwithstanding the fact that the record also contained
    contradictory evidence. See Great Lakes Steel Div of Nat’l Steel Co v Public Service Comm, 
    130 Mich App 470
    , 481-482; 344 NW2d 321 (1983). The PSC issued a CPCN allowing METC to
    construct a transmission line that was entirely above ground. The PSC was entitled to find that
    METC was not required to comply with Oshtemo Township’s ordinance, but was not required to
    do so. However, once the PSC issued CPCN allowing METC to build such a line, Oshtemo
    Township’s ordinance conflicted with the CPCN. Under the plain language of MCL 460.570(1),
    that certificate took precedence over Oshtemo Township’s conflicting ordinance that required
    that a portion of the transmission line be constructed underground. MCL 460.570(1) is not an
    unconstitutional blanket usurpation of Oshtemo Township’s ability to pass regulations and
    ordinances regarding its municipal affairs. The Legislature has the authority to enact laws that
    limit the way in which a local government can exercise the power granted to it under Const 1963,
    art 7, § 29. See Lansing, 275 Mich App at 433; see also Const 1963, art 7, § 22. The argument
    that the PSC’s analysis was required to expand beyond the conclusion that the CPCN took
    precedence over Oshtemo Township’s conflicting local ordinance, and that the PSC was required
    to determine if the ordinance conflicted with some state law other than the CPCN, finds no
    support in the language of any portion of Act 30, particularly not in MCL 460.570(1), or in any
    case law.
    “The legislative power of the State of Michigan is vested in a senate and a house of
    representatives.” Const 1963, art 4, § 1. In Michigan Elec Coop Ass’n this Court stated:
    The Legislature cannot delegate its power to make a law; however, it can
    enact a law that delegates a power to determine a fact or status upon which the
    law makes, or intends to make, its own action depend. Such a statute must be
    sufficiently broad to permit efficient administration designed to carry out
    legislative policy, but not so broad as to leave an administrative body with
    uncontrolled and arbitrary power. The guiding principles in determining whether
    a statute provides sufficient standards for the exercise of administrative discretion
    are: (1) the provision in question should be read with reference to the act as a
    whole; (2) the standard should be as reasonably precise as the subject matter
    requires or permits; and (3) if possible, the statute must be construed in such a
    way as to render it valid rather than invalid, i.e., as conferring administrative, not
    legislative power, and as vesting discretionary, not arbitrary, authority. Dep’t of
    Natural Resources v Seaman, 
    396 Mich 299
    , 308-309; 240 NW2d 206 (1976).
    [Michigan Elec Coop Ass’n, 267 Mich App at 622-623.]
    Act 30 is not an unconstitutional delegation of power. The evaluation of an application
    for a CPCN requires the PSC to consider a multitude of factors, including any conflicting local
    zoning ordinances. MCL 460.567(2)(d). Each application presents its own unique facts and
    circumstances. The Legislature could not have specified with any practicality or feasibility what
    routes or configurations the PSC would be required to consider in each case. The standards set
    out in MCL 460.568(5) are as reasonably precise as the subject matter permits. See, e.g., Kent
    Co Aeronautics Bd v Dep’t of State Police, 
    239 Mich App 563
    , 588; 609 NW2d 593 (2000).
    Moreover, the PSC can grant a CPCN only if it finds that the applicant has made the required
    showings set out in MCL 460.568(5). Neither Oshtemo Township nor amici Michigan
    -11-
    Townships Association, et al, has established that Act 30 is an unconstitutional delegation of
    power from the Legislature to the PSC.
    V. Conclusion
    The issues raised by appellants and amici in these consolidated cases are without merit
    and do not warrant reversal of the PSC’s order granting METC’s application for a CPCN.
    We affirm and lift the stay. No taxable costs pursuant to MCR 7.219, a question of
    public policy involved.
    /s/ Donald S. Owens
    /s/ Jane E. Markey
    /s/ Deborah A. Servitto
    -12-