20230202_C359420_68_359420.Opn.Pdf ( 2023 )


Menu:
  •              If this opinion indicates that it is “FOR PUBLICATION,” it is subject to
    revision until final publication in the Michigan Appeals Reports.
    STATE OF MICHIGAN
    COURT OF APPEALS
    NORFOLK SOUTHERN RAILWAY COMPANY,                                       UNPUBLISHED
    February 2, 2023
    Plaintiff-Appellant
    v                                                                       No. 359420
    Ingham Circuit Court
    METRO FIBERNET LLC,                                                     LC No. 21-000332-CB
    Defendant-Appellee.
    Before: GLEICHER, C.J., and K. F. KELLY and LETICA, JJ.
    PER CURIAM.
    The issue presented is whether a utility company must comply with a railroad company’s
    approval process before installing a utility line 15 feet under a railroad track at its intersection with
    a public roadway. Despite obvious safety concerns, no statute requires the utility company to
    secure permission or even provide notice. The railroad company could not force the utility
    company to comply with its work application process. We affirm the circuit court’s summary
    dismissal of its lawsuit.
    I. BACKGROUND
    Norfolk Southern Railway Company (NSRC) owns several miles of railroad track in
    Ingham County. Metro Fibernet, LLC (Metronet) is a telecommunications company. On
    November 22, 2019, Metronet notified NSRC’s lessee—Jackson & Lansing Railroad Company—
    that it intended to bore under the railroad tracks at a crossing over St. Joseph Street and install fiber
    optic cable. The notice included “[d]etailed designs and construction plans for this crossing” and
    a copy of the insurance policy covering the project. Metronet got a permit from the city of Lansing
    to install the cables. The permit required Metronet “to secure any and all other authorizations from
    impacted utilities,” contact MISS DIG, and secure “any other applicable permits from other
    governing agencies,” such as the county and the Michigan Department of Transportation (MDOT).
    In return, NSRC informed Metronet that the written notice permitted under MCL 462.265
    only applies to wires strung over and across the railroad right-of-way, not below. NSRC advised
    Metronet to follow the railroad’s established procedure for approval of such underground projects.
    Metronet continued with its plans, insisting that it was required only to provide 30 days written
    -1-
    notice. It also provided similar notice of intent to install underground cables under other railroad
    track/highway crossings in the county.
    NSRC filed a petition with MDOT to “settle [this] dispute.” NSRC argued that MCL
    462.265 does not apply and therefore Metronet was required to seek permission to install the
    underground cable. Despite stating its belief that the statute does not apply, NSRC “invoke[d]
    MDOT’s explicit jurisdiction under MCL 462.265(3) to resolve this dispute.” NSRC filed
    additional petitions when Metronet provided written notices of intent to bore under other railroad
    crossings.
    MCL 462.265 is part of the railroad code of 1993 and provides:
    (1) A corporation or person shall not string any wire, electrical or other, over and
    across a railroad or street railway right-of-way unless 1 of the following procedures
    is followed:
    (a) For crossings within the right-of-way of a public street, highway, road,
    or alley, notification shall first be given to the railroad company and railroad
    authority of the place and the manner in which the corporation or person desires
    to string any wire 30 calendar days prior to performance of the work unless the
    parties otherwise agree.
    (b) For crossings at any other location not within the right-of-way of a
    public street, highway, road, or alley, notification shall first be given to the railroad
    company and railroad authority in writing of the place and the manner in which the
    corporation or person desires to string the wire and written or telegraphic
    permission shall be received from the railroad company and railroad authority prior
    to performance of the work. The railroad company shall respond positively or
    negatively to the request within 90 calendar days after the receipt of the request.
    (2) Any aerial crossings shall be constructed in accordance with specifications of
    the Michigan public service commission and all applicable codes and laws.
    (3) In case of a dispute emanating from subsections (1) and (2) which the parties
    cannot resolve within a reasonable time, either party may petition the department
    for a hearing. The department shall have jurisdiction to settle the dispute between
    the parties.
    (4) Upon proof of violation of or failure to comply with subsections (1) and (2), a
    court of competent jurisdiction may issue an order immediately enjoining the
    violation. [Emphasis added.]
    MDOT referred the petitions to the Michigan Office of Administrative Hearings and Rules.
    An administrative law judge (ALJ) was assigned to consider the petitions. Metronet moved for
    summary disposition, arguing that MDOT and the ALJ lacked subject matter jurisdiction to hear
    the case under MCL 462.265. NSRC filed a brief opposing the summary disposition motion, but
    it is not part of the current record.
    -2-
    The ALJ determined that MDOT lacked jurisdiction to resolve a dispute regarding
    underground wires as they are not mentioned in the statute. But the ALJ went on to state that he
    agrees with NSRC’s assertion that MCL 462.265 does not allow Metro[n]et to
    unilaterally proceed with installing underground wires under the crossings in this
    case. Similarly, the [ALJ] agrees with NSRC’s concerns raised over safety and
    costs. However, in order to resolve this particular dispute, MDOT, and, this
    tribunal by extension, would need to exercise equitable power that [has] not been
    provided. Unless expressly authorized by a statute, an administrative agency does
    not have equitable jurisdiction. . . .
    NSRC fails to cite authority that specifically vests MDOT with the requisite
    power to resolve a dispute involving a railway company and a utility company
    concerning the installation of underground fiber optic cables. In this regard, NSRC,
    on page 7 of its Brief in Opposition, correctly points out that, “The statute does not
    purport to discuss underground wiring at all.” The [ALJ] also cannot find support
    to show how this tribunal has the requisite authority to determine whether MCL
    462.265 applies to underground crossings. Unlike the circuit court, this tribunal
    cannot issue a declaratory judgment, a preliminary injunction or grant other
    equitable relief. For these reasons, this tribunal lacks jurisdiction and this matter
    should be dismissed.
    The MDOT Chief Administrative Officer adopted the ALJ’s decision after reviewing the parties’
    exceptions and summarily dismissed the petition for lack of subject matter jurisdiction.
    NSRC then filed this case in the Ingham Circuit Court. NSRC recounted that “[o]n
    numerous occasions,” Metronet had asserted its right under MCL 462.265 to install fiber optic
    cable under the railroad’s right-of-way where it crosses the public highway without the railroad’s
    approval, “based on mere written notice.” NSRC asserted that it had advised Metronet that
    “pursuant to its clear terms,” MCL 462.265 applies to wires “strung over railroad rights-of-way,”
    not under. Although the statutory notice provision did not apply, NSRC asserted that Metronet
    was required “to comply with NSRC’s established procedures for underground utility crossings.”
    NSRC sought a declaratory judgment that Metronet did “not have legal authority pursuant
    to MCL 462.265 to install underground cable . . . underneath NSRC’s right-of-way without the
    permission of NSRC.” NSRC sought a permanent injunction against the installation of any further
    cable underneath NSRC rights-of-way without permission, as well as any relief the court deemed
    just.
    In lieu of an answer, Metronet filed a motion for summary disposition pursuant to MCR
    2.116(C)(8). Metronet contended that NSRC had no authority to preclude a utility from installing
    underground cable under a public highway. Metronet accused NSRC and other railroad owners
    of illegally “attempt[ing] to collect exorbitant fees from anyone attempting to string cable, lay
    conduit, etc. along a public right-of-way if, in the process, it crosses a set of railroad tracks.”
    NSRC improperly forces the crossing party to obtain the railroad’s approval through a lengthy
    permit process that costs “tens of thousands of dollars,” Metronet asserted. Yet, NSRC had not
    cited any legal authority permitting it to require participation in this expensive process.
    -3-
    Turning to an analysis of MCL 462.265, Metronet argued that the statute “makes clear that
    crossings with wire only require the railroad’s permission if the crossing is ‘not within the right-
    of-way of a public street, highway, road, or alley.’ ” As Metronet sought to cross the tracks in a
    public street, it was required only to notify NSRC 30 days in advance under MCL 462.265(1)(a).
    Citing a different statute, MCL 247.183, Metronet contended that it was the municipality’s duty to
    grant permission, not the railroad’s. A railroad’s permission is required only when the utility
    company seeks to cross the rail line on private property under MCL 462.265(1)(b). Metronet
    emphasized that NSRC took contrary positions in relation to the statute. NSRC stated in the
    complaint that MCL 462.265 only applies to wires strung “over and across” the track. After
    deeming the statute inapplicable, NSRC then relied on the statute to claim that Metronet required
    permission to bore under the tracks.
    Ultimately, Metronet relied on MCL 247.183(1) of the Highway Code, which provides:
    Except as otherwise provided under subsection (2), telegraph, telephone, power,
    and other public utility companies, cable television companies, broadband
    companies, and municipalities may enter upon, construct, and maintain telegraph,
    telephone, or power lines, pipelines, wires, cables, poles, conduits, sewers or
    similar structures upon, over, across, or under any public road, bridge, street, or
    public place, including, longitudinally within limited access highway rights-of-
    way, and across or under any of the waters in this state, with all necessary erections
    and fixtures for that purpose. A telegraph, telephone, power, and other public utility
    company, cable television company, broadband company, and municipality, before
    any of this work is commenced, shall first obtain the consent of the governing body
    of the city, village, or township through or along which these lines and poles are to
    be constructed and maintained.
    Under this statute, Metronet required only the municipality’s permission to install its fiber optic
    cables under the roadway, even where the roadway intersected with a railroad track. Metronet
    further cited MCL 484.3105, which requires telecommunication companies to seek permission
    only from the municipality when installing cables along a public right-of-way.
    NSRC retorted that Metronet had “pepper[ed] its motion for requests for sanctions and
    other claims while completely ignoring or glossing over the issues that have already been decided
    by” MDOT. It complained that Metronet had “continued to assert ‘rights’ under MCL 462.265,
    rights that [MDOT] in previous litigation ha[d] stated do not exist.” NSRC asserted that railroads
    bear a statutory duty to maintain the roadway as well as their tracks where the tracks cross a public
    road. Citing MCL 462.307, NSRC emphasized that even municipalities require railroad
    permission before modifying the roadway at a rail crossing. NSRC also relied upon MCL 462.309,
    which provides in relevant part:
    (1) A railroad owning tracks across a public street or highway at grade shall at its
    sole cost and expense construct and thereafter maintain, renew, and repair all
    railroad roadbed, track, and railroad culverts within the confines of the street or
    highway, and the streets or sidewalks lying between the rails and for a distance
    outside the rails of 1 foot beyond the end of the ties. The road authority at its sole
    -4-
    cost and expense shall construct or improve if necessary and thereafter maintain,
    renew, and repair the remainder of the street or highway.
    * * *
    (3) The full cost of maintaining and repairing all existing crossings shall be borne
    by the respective parties responsible for the work as provided in this act. The cost
    of improving an existing crossing, where improvement is necessary, shall be borne
    in the same manner as provided in this act for maintenance and repair.
    “In the end, the roadbed that Metronet wishes to drill holes into to install its cable is NSRC property
    and Metronet cannot trespass on [that property] without the authority to do so and no such authority
    exists.”
    NSRC admitted that MCL 462.265 does not apply as the statute refers only to wires “over
    and across” the railway line. While the word “across” is “less restrictive” than “over,” the statute
    uses the conjunctive “and,” indicating that both terms must be met. Underground wires do not
    meet that definition.
    NSRC also filed a motion for a preliminary injunction. NSRC asserted that Metronet had
    installed underground fiber optic cable on NSRC property without permission and planned to
    repeat these actions at other crossings. NSRC sought to enjoin those installations pending
    resolution of its lawsuit.
    The court conducted a hearing to consider the parties’ motion and ruled in Metronet’s
    favor. The court began by noting that its review was de novo; “[i]t is not a review as an appeal
    from the MDOT ruling.” Before the court was a purely legal issue. And the court found NSRC’s
    request to be “somewhat . . . puzzling”: NSRC claimed that MCL 462.625 does not give Metronet
    the legal authority to install underground cables without the railroad’s authority, but also claimed
    that MCL 462.265 does not apply to underground cable. If the statute does not apply to
    underground cable installation, “the next step would be to determine by what authority can [NSRC]
    require [Metronet] to get [NSRC’s] permission to install the underground cable.”
    The court determined that MCL 462.265 applies “only to wires strung both over and
    across.” It “does not apply to wires or cables buried beneath the surface.” As the statute does not
    apply, Metronet could not be required to seek permission under that statute. NSRC also cited MCL
    462.309, which provides that a railroad that owns tracks crossing a public street bears the sole cost
    of maintaining “all railroad, roadbed, track, and railroad culverts” spanning one foot beyond the
    ties on each side. The court defined the roadbed as “the bed on which the tires, rails, and ballast
    of a railroad rest.” Ballast in turn “is defined as gravel or broken stone laid in a railroad bed.” The
    court noted that NSRC did not “even suggest[] that ballast could extend to 15 feet underground,”
    the depth at which Metronet proposed to install the cable. The court described:
    [NSRC] makes a huge leap in logic from saying it has a duty to maintain, renew,
    and repair the railroad roadbed to concluding that quote, “It is imperative that any
    proposed underground installations are subject to prior review and approval by the
    railroad.”
    -5-
    I can’t make that leap in logic, unless there’s legal authority for it, and
    [NSRC] points to none. [MCL 462.309] doesn’t give [NSRC] ownership or a duty
    to maintain anything deeper than the ballast, and certainly not 15 feet underground.
    NSRC doesn’t own or control all of the earth under the ballast all the way
    to the center of the earth. In fact, MCL 247.183 addressed the authority to bury
    cable where railroads are not the owners of land and where railroads have no duty
    to maintain anything.
    MCL 247.183 permits broadband companies to install wires and cables under a public road if they
    secure the consent of the municipality alone, not any railroad company, the court concluded, ruling
    that Metronet had not trespassed on NSRC’s property and was not required to seek NSRC’s
    consent for the proposed work. The court dismissed the action, and NSRC appeals.
    II. STANDARDS OF REVIEW
    We review de novo a lower court’s resolution of a summary disposition motion. Zaher v
    Miotke, 
    300 Mich App 132
    , 139; 
    832 NW2d 266
     (2013). “[M]otions under MCR 2.116(C)(8) test
    the legal sufficiency of a claim based on the factual allegations in the complaint. When considering
    such a motion, a trial court must accept all factual allegations as true, deciding the motion on the
    pleadings alone.” Encompass Healthcare PLLC v Citizens Ins Co, ___ Mich App ___; ___ NW2d
    ___ (2022) (Docket No. 357225), slip op at 3 (cleaned up).
    The crux of this case is the interpretation of various statutes.
    The primary goal of statutory interpretation is to identify and give effect to
    the intent of the Legislature. We first look to the specific language of the statute in
    determining the intent of the Legislature. We accord to every word or phrase of a
    statute its plain and ordinary meaning, unless a term has a special, technical
    meaning or is defined in the statute. [Id., slip op at 4 (cleaned up).]
    Although NSRC complained that the parties were bound by the ALJ’s ruling, that ruling
    was based on the ALJ’s interpretation of MCL 462.265.
    [A]gency interpretations are entitled to respectful consideration, but they are not
    binding on courts and cannot conflict with the plain meaning of the statute. While
    the agency’s interpretation may be helpful in ascertaining the legislative intent,
    courts may not abdicate to administrative agencies the constitutional responsibility
    to construe statutes. Giving uncritical deference to an administrative agency would
    be such an improper abdication of duty. [In re Complaint of Rovas Against SBC
    Mich, 
    482 Mich 90
    , 117-118; 
    754 NW2d 259
     (2008).]
    Accordingly, if the ALJ improperly interpreted the plain language of the relevant statutes, we must
    conduct a de novo review and reach an independent conclusion.
    -6-
    II. PROPERTY INTEREST
    NSRC asserts that it owns the land under its railroad tracks in fee simple, including where
    those tracks cross public roadways. This ownership interest entitles it to prevent others from
    trespassing under the surface, NSRC contends. With its appellate reply brief, NSRC presented
    documents from its “real estate file” on this rail line. Although this was an expansion of the record,
    we will consider those documents as this is a legal rather than factual question and the circuit court
    summarily dismissed the action before discovery could be conducted, essentially precluding the
    presentation of these essential records.
    NSRC’s real estate file includes a 1966 quit-claim deed from the Michigan Central
    Railroad Company and New York Central Railroad Company to NSRC’s predecessor-in-interest.
    This deed describes the subject land, but otherwise is vague. It does not describe the property
    interest in any detail; indeed, the terms “fee,” “fee simple,” “right-of-way,” and “easement” are
    never mentioned. Schedule A to the deed indicates that the rail line already existed and required
    the grantee to erect and maintain “a suitable barricade along the track side of” the land. Overall,
    the omission of the nature of the property interest is concerning, as “[i]t is settled law in this State
    that a quitclaim deed transfers any interest the grantor may have in the lands, whatever its nature,”
    no more and no less. Roddy v Roddy, 
    342 Mich 66
    , 69; 
    68 NW2d 762
     (1955). See also Doelle v
    Read, 
    329 Mich 655
    , 657; 
    46 NW2d 422
     (1951) (quotation marks and citation omitted) (“The
    grantee in a quitclaim deed acquires the right and title which his grantor had, and no other.”).
    However, the file includes letters connected with a 1946 legal action in which the railroad
    companies refer to their “right-of-way.” A March 25, 1946 letter indicates that “attached papers
    show that title to this portion of the right-of-way was acquired in 1865, by condemnation
    proceedings.” A handwritten, 1865 probate court judgment was attached as well. Although much
    of this document is illegible, the caption indicates that it pertains to “proceedings” regarding a
    “right of way.” The judgment states, “the west side of the line established for the route of the said
    Rail Road over and across the undivided two fifths of the [indecipherable],” and reiterates that the
    interest pertains to “the west side of the line established for the route of the Said Rail Road over
    and across the” northwest section of a certain plot. We could not locate the terms “fee,” “fee
    simple,” “right-of-way,” or “easement” within the body of this document. However, the 1946
    legal correspondence and the heading of the 1865 judgment clearly used the term “right-of-way.”
    In Quinn v Pere Marquette R Co, 
    256 Mich 143
    , 150; 
    239 NW 376
     (1931), the Michigan
    Supreme Court explained:
    “Right of way” has two meanings in railroad parlance: the strip of land upon
    which the track is laid, and the legal right to use such strip. In the latter sense it
    may mean an easement. But in this State and others the character of the title taken
    to the strip depends upon the language of the conveyance.
    “Where the land itself is conveyed, although for railroad purposes only, without specific
    designation of a right of way, the conveyance is in fee and not of an easement.” 
    Id. at 150-151
    .
    On the other hand, “[w]here the grant is not of the land but is merely of the use or of the right of
    way, or, in some cases, of the land specifically for a right of way, it is held to convey an easement
    only.” 
    Id. at 150
    . In Dep’t of Natural Resources v Carmody-Lahti Real Estate, Inc, 472 Mich
    -7-
    359, 370; 
    699 NW2d 272
     (2005), the Supreme Court again held that “the precise contours of the
    property interest conferred upon” a railroad company must come from the deed creating the
    interest.
    Given that the 1865 judgment and 1966 quit-claim deed describe the parameters of certain
    real estate and the 1865 judgment cites the property’s use for a rail line, NSRC likely does hold
    the railroad right-of-way in fee. But does an unlimited fee ownership exist even where the rail line
    crosses a public roadway?
    MCL 462.273(1) of the Railroad Code provides that “a person shall not walk, ride, drive,
    or be upon or along the right-of-way or yard of a railroad company operating its lines within this
    state, or go upon or cross the right-of-way or yard at a place other than a public or private crossing,
    unless having first obtained written permission from the owner or occupant railroad, its agent or
    servant.” (Emphasis added.) For purposes of this statute, the “right-of-way” is defined as “the
    track or roadbed owned by a railroad and that property owned by a railroad which is located on
    either side of its tracks and which is readily recognizable to a reasonable person as being railroad
    property or is reasonably identified as such by fencing, the existence of railroad tracks, or
    appropriate signs.” MCL 462.273(2). This provision of the Railroad Code makes clear that the
    section of the right-of-way that crosses a roadway is not entitled to the same protection of privacy
    as the remainder of the track.
    Public highways can be created in several ways and we cannot discern from this record
    how the subject highway came to be. Even assuming, however, that NSRC, as an abutting
    landowner, retained fee simple interest to the land underlying this public road,1 NSRC could not
    assert the unfettered control it proposes. The Michigan Supreme Court has held that even where
    the public only has an easement in the public highway, the government may approve the
    installation of underground utilities without the consent of or compensation to the fee holder. Eyde
    Bros Development Co v Eaton Co Drain Comm, 
    427 Mich 271
    , 285-286; 
    398 NW2d 297
     (1986).
    This is commensurate with the many statutes cited by the parties regarding the installation of
    utilities underneath public highways. Absent a statute giving railroads increased rights at these
    intersections, we cannot find that NSRC’s property rights were invaded.
    III. NOTICE PROVISION
    By its plain language, MCL 462.265 does not apply in this situation. As noted, MCL
    462.265 provides, in relevant part:
    (1) A corporation or person shall not string any wire, electrical or other, over and
    across a railroad or street railway right-of-way unless 1 of the following procedures
    is followed:
    1
    When a public highway is dedicated by user rather than by statute, the public roadway is a public
    easement not owned in fee by the municipality. See Eyde Bros Development Co v Eaton Co Drain
    Comm, 
    427 Mich 271
    , 282; 
    398 NW2d 297
     (1986).
    -8-
    (a) For crossings within the right-of-way of a public street, highway, road,
    or alley, notification shall first be given to the railroad company and railroad
    authority of the place and the manner in which the corporation or person desires to
    string any wire 30 calendar days prior to performance of the work unless the parties
    otherwise agree.
    (b) For crossings at any other location not within the right-of-way of a
    public street, highway, road, or alley, notification shall first be given to the railroad
    company and railroad authority in writing of the place and the manner in which the
    corporation or person desires to string the wire and written or telegraphic
    permission shall be received from the railroad company and railroad authority prior
    to performance of the work. The railroad company shall respond positively or
    negatively to the request within 90 calendar days after the receipt of the request.
    (2) Any aerial crossings shall be constructed in accordance with specifications of
    the Michigan public service commission and all applicable codes and laws.
    According to this statute, if a corporation wants to string wire over and across a railway at a public
    roadway crossing, it must provide 30 days’ notice to the railway. If it wants to string wire over
    and across a railway at any other location, it must secure the railroad’s permission. If MCL
    462.265 applies in this matter, Metronet would be required to provide notice, which it did, but
    would not be required to secure permission as its proposed installations are all within public
    railways.
    But MCL 462.265 does not apply in this case because Metronet does not intend to “string
    any wire . . . over and across a . . . street railway right-of-way.” This undefined phrase must be
    given its “plain and ordinary meaning.” Mantei v Mich Pub Sch Employees Retirement Sys, 
    256 Mich App 64
    , 72; 
    663 NW2d 486
     (2003).
    The phrase “over and across” is an adverbial modifier adding more information about the
    verb “string.” To “string [a] wire . . . over and across” something is generally understood to
    inherently encompass a wire’s aerial placement. Stringing wire means connecting the ends of a
    wire to a pole, such that the wire runs above ground level.
    Employing dictionary definitions does not alter the outcome because, string as a verb is
    defined, in relevant part, as “to tie, hang, or fasten with string.” Merriam-Webster’s Collegiate
    Dictionary (11th ed). The adverb “over” is defined as “across a barrier or intervening space,”
    “across,” and “above.” Merriam-Webster’s Collegiate Dictionary (11th ed). “Across” is defined
    as “in a position reaching from one side to the other” and “to or on the opposite side.” Merriam-
    Webster’s Collegiate Dictionary (11th ed). Further, the words “over” and “across” are joined with
    the conjunctive “and,” meaning that both terms must apply. See Mich Pub Serv Comm v
    Cheboygan, 
    324 Mich 309
    , 341; 
    37 NW2d 116
     (1949) (“ ‘And’ is a conjunctive, used to denote a
    joinder, a union. ‘Or’ is the opposite, a disjunctive, used to indicate a disunion, a separation, an
    alternative.”). Read together, these terms in MCL 462.265(1) refer to wire or cable hung above
    and across a rail line.
    -9-
    As underground wires and cables are not contemplated in MCL 462.265, that statute did
    not require Metronet to either provide notice or seek permission from NSRC before beginning its
    planned work. This is a potentially problematic omission. After all, rail companies that install
    track across a public street or highway bear the full cost of construction, repair, and maintenance
    of that crossing. MCL 462.307(6); MCL 462.309(1). Notice of the installation of wires or cables
    underneath a rail line is an easy and inexpensive way to protect the interests and investments of
    the railroad companies and protect public safety. But we are not permitted to read these terms into
    the statute. If NSRC and other railroad owners want a change in the law, they must lobby the
    Legislature.2
    NSRC contends that MCL 462.309 gives it an ownership interest in the ground underneath
    its tracks, making Metronet’s proposed drilling a trespass. MCL 462.309(1) provides:
    A railroad owning tracks across a public street or highway at grade shall at its sole
    cost and expense construct and thereafter maintain, renew, and repair all railroad
    roadbed, track, and railroad culverts within the confines of the street or highway,
    and the streets or sidewalks lying between the rails and for a distance outside the
    rails of 1 foot beyond the end of the ties. The road authority at its sole cost and
    expense shall construct or improve if necessary and thereafter maintain, renew, and
    repair the remainder of the street or highway.
    NSRC’s duty to “maintain, renew, and repair” extends to one foot beyond the rail ties. Metronet
    proposes to begin its boring process outside that boundary. NSRC’s duty also extends to the
    “railroad roadbed, track, and railroad culverts.”
    NSRC asserts that the ground extending beneath the track is the “roadbed.” “Roadbed” is
    not defined in the statutes. This is a “technical term[] of art” and must be defined as used in the
    industry. West Bloomfield Charter Twp v Karchon, 
    209 Mich App 43
    , 51; 
    530 NW2d 99
     (1995).
    We first look to federal law governing railroads. 49 USC 213.31 provides safety standards for the
    “roadbed and areas immediately adjacent to roadbed.” The federal statutes also do not define the
    “roadbed.” However, a study of the United States Department of Transportation (USDOT) Federal
    Railroad Administration describes, “A major component of the railroad rack system is the track
    substructure (i.e., the ballast, subballast, subgrade, and foundation). DiPilato et al, Railroad Track
    Substructure-Design and Performance Evaluation Practices, June 1983, p 1, available at
     (accessed December 16, 2022). Ballast is stone spread
    under and around the rails to absorb and distribute the weight and vibration from train traffic. Id.
    at 3. Subballast is sand and gravel mixed with “crushed natural aggregates or slags” laid
    underneath the ballast. It serves the same purpose as the ballast. Id. at 5. Subgrade soils are
    “natural earth materials lying under the ballast and subballast” that support the track system, absorb
    stress from the upper layers, and provide stability during the changing seasons. Id. This study
    found that any increased benefit beyond a ballast thickness of 21 inches was “questionable.” Id.
    43. The recommended thickness of subballast is six to 12 inches. Id. at 56. The deepest total
    2
    An example of a statutory scheme that requires the application process proposed by NSRC can
    be found in Minnesota. See Minn Stat 237.045 (2022).
    -10-
    ballast, subballast, and subgrade cited in the report was five feet and the author noted that such
    depth is not necessarily required. Id. at 70. See also Missouri Pacific R Co v R Comm of Texas,
    948 F2d 179, 182 n 2 (CA 5, 1991), quoting Hay, Railroad Engineering, 393 (2d ed. 1982) (“The
    roadbed is the area of soil that supports the ballast, which is the ‘permeable, granular materials
    such as sand, gravel, crushed rock or slag, chat, cinders, and so on placed around and under the
    ties to promote track stability.’ ”). The USDOT study never suggests that the subgrade of a rail
    line extends 15 feet underground, the depth at which Metronet proposes to install its underground
    cables. Given this scientific study by the federal department tasked with railroad safety and the
    absence of any evidence provided by NSRC regarding the technical meaning of “roadbed,” we
    decline to define roadbed as extending 15 feet beneath the roadway surface. NSRC cannot claim
    ownership to that depth simply because its tracks cross it.
    Neither party cites any other statute referring to a utility company’s duty to provide notice
    or seek permission from a railroad company before installing underground cables. MCL
    247.183(1) of the highway code governs utility companies installing structures “upon, over, across,
    or under any public road, bridge, street, or public place.” A private railroad track is not included
    in this list. The metropolitan extension telecommunications rights-of-way oversight act (METRO)
    governs the installation of broadband cables in public rights-of-way, but again does not refer to
    any duty in relation to railroad crossings. See MCL 484.3101 et seq.
    Ultimately, NSRC has not established its entitlement to force Metronet through its
    application process. The circuit court properly denied NSRC’s motion for injunctive relief and
    dismissed its lawsuit.
    We affirm.
    /s/ Elizabeth L. Gleicher
    /s/ Kirsten Frank Kelly
    /s/ Anica Letica
    -11-