Rodney Woods v. City of Saginaw ( 2021 )


Menu:
  •             If this opinion indicates that it is “FOR PUBLICATION,” it is subject to
    revision until final publication in the Michigan Appeals Reports.
    STATE OF MICHIGAN
    COURT OF APPEALS
    RODNEY WOODS, doing business as RODNEY                                UNPUBLISHED
    WOODS BUILDER,                                                        January 7, 2021
    Plaintiff-Appellant,
    v                                                                     No. 344025
    Saginaw Circuit Court
    CITY OF SAGINAW,                                                      LC No. 16-029129-CB
    Defendant-Appellee.
    ON REMAND
    Before: REDFORD, P.J., and JANSEN and LETICA, JJ.
    PER CURIAM.
    In an order dated October 21, 2020, the Michigan Supreme Court reversed, in part, the
    portion of this Court’s prior opinion in Woods v City of Saginaw, unpublished per curiam opinion
    of the Court of Appeals, issued October 15, 2019 (Docket No. 344025) (Woods I), where we held
    that “the trial court properly granted summary disposition of the plaintiff’s quantum meruit claim
    under MCR 2.116(C)(8).” Woods v City of Saginaw, ___ Mich ___; 949 NW2d 456 (2020)
    (Woods II). Our Supreme Court further held that:
    The plaintiff’s amended complaint and attached exhibits were legally sufficient to
    plead his claim that the defendant was unjustly enriched by extra-contractual work
    completed by the plaintiff. See El-Khalil v Oakwood Healthcare, Inc, 
    504 Mich 152
    , 159-160; 934 NW2d 665 (2019); Wright v Genesee County, 
    504 Mich 410
    ;
    934 NW2d 805 (2019). Moreover, the Court of Appeals clearly erred by engaging
    in appellate fact-finding when it stated that the plaintiff had been “fairly
    compensated.” We REMAND this case to the Court of Appeals for consideration
    of the plaintiff’s arguments regarding the trial court’s alternative ruling that granted
    summary disposition to the defendant under MCR 2.116(C)(10). The plaintiff’s
    motion to disqualify the trial judge is DENIED, without prejudice to the plaintiff
    seeking such relief on remand. In all other respects, leave to appeal is DENIED,
    -1-
    because we are not persuaded that the remaining question presented should be
    reviewed by this Court. [Woods II, __ Mich ___.]
    Accordingly, we now consider whether defendant, the City of Saginaw, was entitled to summary
    disposition under MCR 2.116(C)(10). Again, we affirm.
    I. FACTUAL AND PROCEDURAL BACKGROUND
    In Woods I, we previously articulated that:
    This case involved blight demolition efforts in the Saginaw area under the
    Troubled Asset Relief Program (“TARP”). Defendant and the Saginaw County
    Land Bank Authority (“SCLBA”) secured over $11,000,000 in TARP funds from
    the Michigan State Housing Development Authority for blight elimination.
    Defendant and the SCLBA entered into a partnership to demolish up to 950 blighted
    properties. The SCLBA would be responsible for acquiring, owning, and
    maintaining properties slated for demolition, and defendant would be responsible
    for hiring demolition contractors and overseeing their work. In 2013, defendant
    began soliciting bids from numerous demolition contractors to take on the role of
    demolishing the blighted properties. One of these contractors was plaintiff, a sole
    proprietor.
    Defendant created a procedure in which each contractor submitted a “per
    unit costs” for various services related to demolition. Such services included
    foundation removal, tree removal, and asbestos removal. Each of these services
    was assigned a particular number of points. Defendant would award demolition
    work to the “highest qualified contractor with the lowest accepted and approved
    bids” for a period of two years, and defendant had the option to extend this period
    for a third year. . . .
    Plaintiff submitted his bid proposal and “won” the bidding process. As the
    highest ranked contractor, plaintiff had first pick of the demolition properties and
    received 240 out of a total 480 initial properties. In total, plaintiff demolished
    approximately 600 houses over the life of the contract. . . .
    Plaintiff filed a three-count complaint. In Count I, a breach of contract
    claim, plaintiff claimed that defendant increased the scope of the contract, and then
    was not adequately compensated for the extra work performed. In Count II,
    plaintiff sought relief under a quantum meruit theory for the extra work performed.
    The extra work relevant to Count I and Count II was primarily related to grading
    and seeding of the properties after demolition, which plaintiff claimed was not
    included in the parties’ original contract. In support of his claim for additional
    compensation, plaintiff attached a letter from John C. Stemple, Chief Inspector for
    defendant, in which Stemple issued a change order acknowledging that plaintiff,
    and other contractors, had been performing work beyond the original contract and
    would receive additional compensation for prospective demolitions. Finally, in
    Count III, plaintiff made a second claim for breach of contract, this time claiming
    -2-
    that defendant allocated demolitions to other contractors, thereby breaching an
    implied covenant of good faith.
    Defendant filed its first motion for summary disposition in October 2017,
    which the trial court granted in part as to Count I, and denied in part as to Count II
    and Count III. . . .
    In March 2018, defendant filed a renewed motion for summary disposition
    of Count II and Count III. The trial court granted summary disposition in favor of
    defendant of Count II, plaintiff’s quantum meruit claim, under MCR 2.116(C)(8)
    and (C)(10), and of Count III under MCR 2.116(C)(10) for the implied warranty of
    good faith claim. [Woods I, unpub op at 1-2.]
    Plaintiff appealed to this Court, and we affirmed. Woods I, unpub op at 1. Plaintiff again
    appealed to our Supreme Court, and our Supreme Court reversed in part, concluding that the trial
    court erroneously granted summary disposition of Count II under MCR 2.116(C)(8), and remanded
    this matter back to this Court with the instructions to further evaluate whether defendant was
    entitled to summary disposition of plaintiff’s quantum meruit claim under MCR 2.116(C)(10).
    Woods II, ___ Mich ___. Additionally, our Supreme Court again affirmed the trial court’s
    dismissal of plaintiff’s implied warranty of good faith claim under MCL 2.116(C)(10). 
    Id.
    II. STANDARD OF REVIEW
    On remand, we now consider whether defendant was entitled to summary disposition of
    plaintiff’s quantum meruit claim under MCR 2.116(C)(10). A trial court’s ruling regarding a
    motion for summary disposition is reviewed de novo. Heaton v Benton Constr Co, 
    286 Mich App 528
    , 531; 780 NW2d 618 (2009).
    A motion under MCR 2.116(C)(10) tests the factual support of a plaintiff’s claim.
    Summary disposition is appropriate under MCR 2.116(C)(10) if there is no genuine
    issue regarding any material fact and the moving party is entitled to judgment as a
    matter of law. In reviewing a motion under MCR 2.116(C)(10), this Court
    considers the pleadings, admissions, affidavits, and other relevant documentary
    evidence of record in the light most favorable to the nonmoving party to determine
    whether any genuine issue of material fact exists to warrant a trial. A genuine issue
    of material fact exists when the record, giving the benefit of reasonable doubt to
    the opposing party, leaves open an issue upon which reasonable minds might differ.
    [Zaher v Miotke, 
    300 Mich App 132
    , 139-140; 832 NW2d 266 (2013) (quotations
    marks and citations omitted).]
    “Circumstantial evidence can be sufficient to establish a genuine issue of material fact, but mere
    conjecture or speculation is insufficient.” McNeill-Marks v Midmichigan Med Ctr-Gratiot, 
    316 Mich App 1
    , 16; 891 NW2d 528 (2016). “This Court is liberal in finding genuine issues of material
    fact.” Jimkoski v Shupe, 
    282 Mich App 1
    , 5; 763 NW2d 1 (2008). However, “this Court’s review
    is limited to review of the evidence properly presented to the trial court.” Barnard Mfg Co, Inc v
    Gates Performance Engineering, Inc, 
    285 Mich App 362
    , 380; 775 NW2d 618 (2009).
    -3-
    The moving party bears the initial burden of production, which may be satisfied “in one of
    two ways.” Quinto v Cross & Peters Co, 
    451 Mich 358
    , 361; 547 NW2d 314 (1996). “First, the
    moving party may submit affirmative evidence that negates an essential element of the nonmoving
    party’s claim. Second, the moving party may demonstrate to the court that the nonmoving party’s
    evidence is insufficient to establish an essential element of the nonmoving party’s claim.” 
    Id. at 362
     (quotation marks and citation omitted). Once the moving party satisfies its burden in one
    of those two ways, “[t]he burden then shifts to the opposing party to establish that a genuine issue
    of disputed fact exists.” 
    Id.
    III. ANALYSIS
    Although the trial court erroneously granted summary disposition of plaintiff’s quantum
    meruit claim under MCR 2.116(C)(8), we conclude that there were two distinct basis to grant
    summary disposition in favor of defendants under MCR 2.116(C)(10).
    A. EXISTENCE OF AN EXPRESS CONTRACT COVERING THE SAME SUBJECT
    MATTER
    As we noted in our prior opinion:
    “The theory underlying quantum meruit recovery is that the law will imply
    a contract in order to prevent unjust enrichment when one party inequitably receives
    and retains a benefit from another.” [Morris Pumps v Centerline Piping, Inc, 
    273 Mich App 187
    , 194; 729 NW2d 898 (2006).] However, a party may not recover in
    quantum meruit if an express contract between the parties covers the same subject
    matter. 
    Id.
    In this case, plaintiff seeks additional compensation for extra work
    performed. Plaintiff relies heavily on the change order from Stemple to support his
    claim that he should receive additional compensation for extra work performed on
    demolition jobs before the change order was issued. However, based on the record
    before us, the change order only applied to prospective demolitions; it was not to
    have retroactive effect. [Woods I, unpub op at 3-4.]
    Examining each of the specific claims contained within plaintiff’s complaint, we conclude
    that the contract undoubtedly covered the alleged extra work. In his amended complaint, plaintiff
    alleged the extra work performed was:
    (1) prompt backfilling of soil following a structural demolition, (2)
    bringing in, at the contractor’s expense, a minimum of three inches
    of fresh topsoil, (3) uniformly grading all surfaces; (4) excavating
    surfaces to encourage water runoff, and (5) seeding the topsoil with
    clover and watering, if necessary.
    Additionally, the contract provided: “Upon removal of below grade materials all excavations and
    cavities in the earth shall be filled with clean yellow sand or clay materials and covered with a
    minimum, after compaction, of four inches organic top soil approved in advance by the Chief
    -4-
    Inspector.” Included in this contractual obligation was (1) backfilling of soil and (2) bringing in
    fresh topsoil, as alleged in plaintiff’s complaint.
    The contract further provided:
    In some cases the contractor may be directed by the City of
    Saginaw to prepare the site for the application of grass seed and
    apply seed. The site shall be graded smooth and seed applied using
    the hydro-seed method of application. Application shall be made in
    accordance with the seed supplier’s recommendations. Grass seed
    shall be of a type that does not grow more than six inches in height
    and shall be acceptable to the City for this application. The cost of
    this service shall be determined on a cost per square foot basis.
    This covered (3) the grading of all surfaces, (4) excavating surfaces to encourage water runoff, and
    (5) seeding the topsoil with clover and watering alleged in plaintiff’s complaint. Moreover, the
    bid included plaintiff’s proposed costs for a number of services, which explicitly included “Lot
    Grading and Seeding.” Therefore, we conclude that the alleged extra work was explicitly covered
    by the contract.
    In short, because the relevant contents of the parties’ contractual agreement are undisputed,
    there is no genuine issue of material fact for resolution at trial. See Calhoun Co v Blue Cross Blue
    Shield Mich, 
    297 Mich App 1
    , 12; 824 NW2d 202 (2012) (“Construction and interpretation of a
    contract are questions of law”). As a matter of law, because the parties had a written agreement
    expressly governing the compensation to which plaintiff was entitled for the demolition work that
    is the subject of this lawsuit, plaintiff cannot seek additional compensation for such work under a
    quantum meruit theory. See Morris Pumps, 273 Mich App at 194, quoting Belle Isle Grill Corp v
    Detroit, 
    256 Mich App 463
    , 478; 666 NW2d 271 (2003) (“a contract will be implied only if there
    is no express contract covering the same subject matter”). See also Rory v Continental Ins Co,
    
    473 Mich 457
    , 461; 703 NW2d 23 (2005) (“the judiciary is without authority to modify
    unambiguous contracts or rebalance the contractual equities struck by the contracting parties”).
    B. THE CITY CHARTER
    Additionally, the City Charter prevents plaintiff from recovering under a quantum meruit
    theory. Defendant’s Charter contains a section relevant to this appeal, Section 33, which provides:
    Competitive bids for all purchases and public improvements shall be obtained
    where practicable and contracts awarded to the lowest and best bidders. Sealed
    bids shall be asked for in all transactions involving the expenditure of two thousand
    dollars ($2,000) or more and the transaction evidenced by written contract
    submitted to and approved by the council; provided that, in cases where it is clearly
    to the city’s advantage to contract without competitive bidding, the council upon
    recommendation of the manager may so authorize. Detailed purchasing and
    contracting procedure shall be established by ordinance. The council may authorize
    the making of public improvements by day labor.
    -5-
    In granting defendant summary disposition of plaintiff’s quantum meruit claim under MCR
    2.116(C)(10), the trial court relied on the above-quoted portion of the Charter and, among other
    authorities, Black v Common Council of City of Detroit, 
    119 Mich 571
    , 576-577; 
    78 NW 660
    (1899), in which our Supreme Court held:
    Of every municipal corporation, the charter or statute by which it is created is its
    organic act. Neither the corporation nor its officers can do any act, or make any
    contract, or incur any liability not authorized thereby. . . . All acts beyond the scope
    of the powers granted are void.
    * * *
    [A]s said in Spitzer v. Village of Blanchard, 82 Mich. [234, 246; 
    46 NW 400
    (1890)], “the limitation of power upon the common council appears in the public
    statute, and is presumed to be known by all dealing with corporate authorities.”
    Those who deal with the agents of municipal corporations must take notice
    of the restrictions in their charters in respect to the powers of the corporation and
    its agents, and the mode in which such powers may be exercised, and must see to it
    that the contracts on which they rely are authorized by the charter.
    In Hodges v. City of Buffalo, [
    2 Denio 110
     (NY Sup Ct, 1846)], the plaintiff
    insisted that, though the city had no express authority to make the expenditure, yet
    the claim could be satisfied on the ground that, the plaintiff having furnished the
    entertainment, the corporation had received the consideration, and was bound to
    pay, although the engagement was made without legal authority. The court said in
    that case:
    “It is said to be analogous to a subsequent ratification by a corporation of
    the unauthorized act of its agent. I cannot concur in this view of the case. The
    doctrine referred to assumes that the principal had power to confer the requisite
    authority in the first instance. It cannot be maintained that a corporation can by a
    subsequent ratification make good an act of its agent which it could not have
    directly empowered him to do.”
    Where the contract is void, the contractor cannot recover of the corporation
    in any form,–neither under the contract nor quantum meruit. All who deal with a
    municipal corporation must see that the contract upon which they rely is within its
    powers. Halstead v. [City of New York, 3 NY 430 (1850)]; Brady v. [City of New
    York, 20 NY 312 (1859)]; Cowen v. Village of West Troy, 43 Barb 48 [NY Sup Ct,
    1864]. [Some quotation marks and citations omitted; some emphases added.1]
    1
    Notably, neither the formatting nor all of substance of this block quote are accurately reflected
    on Westlaw—the passage is quoted here as it appears in the official reporter.
    -6-
    Applying Black to this case, the trial court reasoned that because it “is undisputed that there is no
    Council-approved written contract for [plaintiff’s] ‘extra work’ ” in this case (i.e., the allegedly
    uncontracted-for work for which plaintiff sought a recovery in quantum meruit), it followed, as a
    matter of law, that plaintiff could not recover in quantum meruit. On that basis, the trial court held
    that defendant was entitled to summary disposition of the quantum meruit claim under MCR
    2.116(C)(10).
    In this Court, plaintiff argues that Black was wrongly decided, contending that it is contrary
    to “the modern rule that an agent having apparent power can bind its principal.” However, plaintiff
    concedes that he only raised that argument in this Court “for the purpose of issue preservation,”
    and that whether Black was wrongly decided “is not a question for this Court to decide[.]” We
    agree. Under the doctrine of vertical stare decisis, only our Supreme Court has the authority to
    overrule Black, which remains binding on this Court unless and until the Supreme Court does so.
    See generally In re AGD, 
    327 Mich App 332
    , 340; 933 NW2d 751 (2019) (discussing vertical stare
    decisis and noting that until our Supreme Court overrules one of its earlier decisions, “all lower
    courts and tribunals are bound by that prior decision and must follow it even if they believe that it
    was wrongly decided or has become obsolete”) (quotation marks, citation, and emphasis omitted).
    Recognizing that Black is both binding on this Court and seemingly fatal to his position,
    plaintiff argued that Black is not dispositive because, in this case, the defendant city “wasn’t going
    to pay any amount of money for demolition services—instead, it was going to procure and contract
    for such services with the attendant costs being paid wholly by the [Saginaw County] Land Bank,”
    by way of TARP grants. In other words, because the alleged extracontractual work in this case
    “did not require the expenditure of any City funds, whether raised by tax, grant, or otherwise,”
    plaintiff argued that his claim was not contrary to § 33 of the Charter, unlike the claim at issue in
    Black.
    In rejecting that same argument below, the trial court reasoned:
    [Plaintiff] has provided no authority for this proposition and, on its face, the Charter
    does not distinguish between transactions funded by locally raised tax revenues and
    funds originating elsewhere. Rather, the Charter limitation applies to “all” City
    transactions involving $2,000 or more. In any event, even assuming the City used
    none of its own tax revenue but, rather, wholly relied on a state or federal grant, the
    funds would presumably be the City’s upon acceptance of the “grant”.
    In the end, [plaintiff] is suing the City for upwards of $232,000 of “extra
    work”. For the City to be obligated for such a large expenditure, its Charter requires
    that “the transaction [be] evidenced by written contract submitted to and approved
    by the council”. It is undisputed that there is no Council-approved written contract
    for [plaintiff’s] “extra work”.
    We concur with the trial court’s analysis fully. “When reviewing the provisions of a home
    rule city charter, we apply the same rules that we apply to the construction of statutes.” Barrow v
    City of Detroit Election Comm, 
    301 Mich App 404
    , 413; 836 NW2d 498 (2013). Section 33 of
    the Charter expressly applies to “all transactions involving the expenditure of two thousand dollars
    ($2,000) or more[.]” Because nothing in such language is ambiguous, it should be applied as
    -7-
    written. See id. at 414 (“Courts apply unambiguous statutes as written.”). Moreover, § 33 does
    not specify that it is inapplicable when defendant anticipates that a given expenditure will be paid
    for by grant funding or any other source of noncity funds. Therefore, it would be inappropriate to
    construe the Charter as if it did, in fact, contain such language. See Johnson v USA Underwriters,
    
    328 Mich App 223
    ; 936 NW2d 834 (2019) (“we cannot read into the statute something that is not
    there”). Finally, as the trial court aptly recognized, plaintiff has not sued the Saginaw County Land
    Bank here—he has asserted his claims in this action against the defendant city. In other words, he
    seeks a judgment that defendant—not the Land Bank—is liable to him in quantum meruit for in
    excess of $2,000.
    On the basis of the foregoing, we conclude that § 33 of the Charter precludes plaintiff from
    recovering under a quantum meruit theory, and according, defendant was entitled to summary
    disposition as a matter of law under MCR 2.116(C)(10).
    Affirmed.
    /s/ James Robert Redford
    /s/ Kathleen Jansen
    /s/ Anica Letica
    -8-
    

Document Info

Docket Number: 344025

Filed Date: 1/7/2021

Precedential Status: Non-Precedential

Modified Date: 1/8/2021