Matthew Leczel v. Intrust Building Inc ( 2023 )


Menu:
  •              If this opinion indicates that it is “FOR PUBLICATION,” it is subject to
    revision until final publication in the Michigan Appeals Reports.
    STATE OF MICHIGAN
    COURT OF APPEALS
    MATTHEW LECZEL and FADY CHOLAGH,                                       UNPUBLISHED
    June 15, 2023
    Plaintiffs-Appellees,
    v                                                                      No. 362855
    Oakland Circuit Court
    INTRUST BUILDING, INC.,                                                LC No. 2021-187558-CK
    Defendant-Appellant.
    Before: REDFORD, P.J., and O’BRIEN and FEENEY, JJ.
    PER CURIAM.
    In this action to compel arbitration pursuant to a residential construction contract,
    defendant appeals as of right the trial court’s judgment confirming the June 27, 2022 arbitration
    award in favor of plaintiffs. We affirm.
    I. BACKGROUND
    On September 26, 2019, plaintiffs and defendant entered into an agreement for the
    construction of a single-family residence on property purchased by plaintiffs. Defendant agreed
    to build the residence in accordance with plans and specifications attached to the agreement and
    to comply with all applicable laws, ordinances, regulations, and codes, and plaintiffs agreed to
    purchase the completed home for the price stated in the agreement. The agreement required that
    construction be completed within 14 months and assessed liquidated damages of $100 a day for
    delays caused by either party. Plaintiffs and defendant agreed to settle any claim, controversy, or
    dispute arising between them related to the agreement through arbitration pursuant to the
    Commercial Arbitration Rules of the American Arbitration Association. The arbitrator’s decision
    would be the parties’ exclusive remedy, and the decision would be final and binding.
    On April 21, 2021, plaintiffs filed a complaint in the Oakland Circuit Court asserting that,
    although the agreement required completion of the project no later than December 1, 2020, the
    project was far from completion and did not conform to the specifications stated in the agreement.
    Plaintiffs alleged that defendant had ignored plaintiffs’ requests for updates and clarifications, that
    they would be responsible for interest payments due to the delay, and that they were forced to rent
    -1-
    space in which to store their furniture and personal property. Plaintiffs requested that the trial
    court enter an order compelling arbitration pursuant to the parties’ agreement.
    One month later, the trial court entered a stipulated order referring the dispute to arbitration
    under the Uniform Arbitration Act (UAA), MCL 691.1681 et seq. The parties agreed to the
    appointment of the arbitrator, agreed to general procedures for conducting the arbitration, and
    agreed that the decision of the arbitrator would be issued through a written opinion. The court
    dismissed the case without prejudice, but retained jurisdiction to enter a final judgment on the
    arbitrator’s award.
    The arbitrator conducted hearings on May 16, 17, and 26, 2022, and held a closing
    conference on June 7, 2022. The parties submitted final briefs on June 24, 2022. Three days later,
    the arbitrator issued an award in favor of plaintiffs. The arbitrator found that construction had not
    been completed and a balance of $43,850 remained on the contract. He also found reasonable the
    contracts terms that specified the 14-month construction period, that the residence should have
    been completed by August 26, 2021, that defendant caused 306 days of delay, and that plaintiffs
    were entitled to liquidated damages in the amount of $30,600. The arbitrator noted that defendant
    acknowledged that completion of the work specified in the agreement would cost $12,000; but he
    concluded, based upon his 45 years’ experience, that defendant understated its estimate and that
    the cost to complete construction “would more likely be $18,000, especially in light of the current
    market conditions.” The arbitrator also awarded plaintiffs an additional $5,000 for “time,
    inconvenience, and uncertainty” and “escalation costs in obtaining a completion of the Residence,”
    as well as, “the unavailability of a builder’s warranty, which is released by this Award.” After
    subtracting the amounts awarded to plaintiffs from the contract balance due, the arbitrator
    calculated the net award to plaintiffs at $14,750.
    On July 1, 2022, plaintiffs moved in the trial court for confirmation of the arbitration award
    and entry of a judgment reflecting the arbitrator’s decision. Ten days later, defendant moved to
    set aside or modify the arbitration award. Defendant contended that the award was “grossly
    disproportionate” and contrary to the terms of the parties’ agreement, asserting that while the
    arbitrator awarded plaintiffs $30,600 in liquidated damages for defendant’s delays, he failed to
    award defendant any liquidated damages for the 25 days of delay attributable to plaintiffs.
    Defendant also asserted that the arbitrator had exceeded his authority by increasing the cost of
    completion from $12,000 to $18,000 based on his 45 years of experience. Defendant argued
    further that the arbitrator exceeded his authority by awarding plaintiffs $5,000 in damages for
    “aesthetics,” because plaintiffs failed to mitigate those damages. Defendant asserted that the
    arbitrator’s award of $5,000 for time, inconvenience, uncertainty, costs of completion, and in lieu
    of a warranty duplicated damages already awarded and also contended that the arbitration award
    violated Michigan law regarding the apportionment of delay damages under a construction
    contract.
    Plaintiffs countered that the arbitrator “clearly understood the issues, listened to the
    testimony, read the exhibits, and made a ruling based on the evidence presented and consistent
    with the contract documents.” Plaintiffs contended that the award was consistent with Michigan
    caselaw, the agreement of the parties, and the evidence submitted at the arbitration hearing.
    Plaintiffs denied that the arbitrator improperly relied on his experience, asserting that defendant’s
    -2-
    estimation of the cost of completion was unrealistic and refuted by the evidence presented, and
    contended that the agreement and Michigan law permitted the award of damages.
    Waiving oral argument pursuant to MCR 2.119(E)(3), the trial court entered an opinion
    and order on September 2, 2022. Interpreting defendant’s motion as contending that the arbitrator
    exceeded his authority by awarding liquidated damages for delay, the court explained that
    liquidated-damages clauses are generally enforceable, a court cannot substitute its interpretation
    of a contract for that of the arbitrator, and the parties’ agreement provided for liquidated damages
    in the event of defendant’s failure to complete the project within the time provided in the
    agreement. The court disagreed that the award of an additional $5,000 for warranty issues was
    outside the scope of the arbitrator’s authority. Thus, the trial court granted plaintiff’s motion and
    confirmed the arbitration award. Six days later, the court entered a judgment reflecting the
    arbitration award.
    II. STANDARD OF REVIEW
    A trial court’s decision on a motion to set aside, vacate, or modify an arbitration award is
    reviewed de novo, without extending any deference to the trial court’s ruling on legal issues.
    Radwan v Ameriprise Ins Co, 
    327 Mich App 159
    , 164; 
    933 NW2d 385
     (2018). “Whether an
    arbitrator exceeded his or her authority is also reviewed de novo.” 
    Id.
     (citation and quotation
    marks omitted).
    III. ANALYSIS
    On appeal, defendant contends that the arbitrator exceeded his authority by improperly
    apportioning liquidated damages, awarding a form of damages other than liquidated damages, and
    injecting his opinion as an expert witness for plaintiffs. We disagree.
    Arbitration in Michigan is governed by the UAA. MCL 691.1703(1) provides in relevant
    part:
    On motion to the court by a party to an arbitration proceeding, the court
    shall vacate an award made in the arbitration proceeding if any of the following
    apply:
    (a) The award was procured by corruption, fraud, or other undue means.
    (b) There was any of the following:
    (i) Evident partiality by an arbitrator appointed as a neutral arbitrator.
    (ii) Corruption by an arbitrator.
    (iii) Misconduct by an arbitrator prejudicing the rights of a party to the
    arbitration proceeding.
    * * *
    -3-
    (d) An arbitrator exceeded the arbitrator’s powers.
    Under Michigan law, “ ‘[a]rbitrators exceed their powers whenever they act beyond the material
    terms of the contract from which they draw their authority or in contravention of controlling law.’ ”
    Radwan, 327 Mich App at 165, quoting Miller v Miller, 
    474 Mich 27
    , 30; 
    707 NW2d 341
     (2005).
    In this case, the arbitrator determined that construction should have commenced on
    May 25, 2020, and found that “[n]o more than 25 days are attributable to, concurrent, or Owner-
    caused delays and therefore the Residence should have been completed by August 26, 2021.” The
    arbitrator found that the construction had still not been completed as of the date of the arbitration
    proceedings. The arbitrator’s 14-month completion calculation provided for defendants a 14-
    month period to complete the project adjusted by the amount of owner caused delays. The
    arbitrator found that defendant caused 306 days of delays entitling plaintiff to apportioned
    liquidated damages of $30,600 as plaintiffs’ sole remedy for the delay in completion. Defendant
    contends that because the arbitrator found that plaintiffs were responsible for a portion of the delay
    in completion, the arbitrator exceeded his authority by awarding liquidated damages to plaintiffs,
    contrary to Michigan law. We disagree.
    Defendant relies on the decision of the United States Court of Appeals for the Sixth Circuit
    in Great American Ins Co v EL Bailey & Co, Inc, 841 F3d 439 (CA 6, 2016). Great American
    involved mediation and extensive litigation in both state and federal courts related to bonds issued
    by the plaintiff guaranteeing the defendant’s performance of a contract with the state of Michigan
    for the construction of a kitchen at the Huron Valley Women’s Correctional Facility. In return,
    the defendant agreed to indemnify the plaintiff for all payments or other expenses incurred due to
    the bonds. The defendant’s contract with the state included a provision allowing the state to
    withhold liquidated damages of $1,000 a day for delays in completing the project. Mediation of
    various disputes regarding the project resulted in a finding that the state was responsible for delays
    of 89.5 days, while the defendant caused 278.5 days’ delay. After agreeing to a settlement of
    various claims related to the construction contract, the plaintiff filed an action in the United States
    District Court for the Eastern District of Michigan seeking in part a declaratory judgment
    recognizing its right to settle the claims. After the district court granted summary judgment in
    favor of the plaintiff, the defendant appealed to the Sixth Circuit. Id. at 440-443.
    On appeal, the defendant asserted that the plaintiff had failed to sufficiently investigate
    Michigan law regarding liquidated damages, contending that because the mediator had found the
    state responsible for some delay, the state was not entitled to any liquated damages. Id. at 448.
    Addressing this argument, the Sixth Circuit explained that “a series of century-old rulings by the
    Michigan Supreme Court clearly establish that ‘where the delay is due to the fault of both parties
    the court will not attempt to apportion [liquidated] damages.’ ” Id. at 448, quoting Bd of Ed of
    City of Sault Ste Marie v Chaussee, 
    211 Mich 61
    , 68; 
    177 NW 975
     (1920). The Sixth Circuit also
    noted that this Court applied the rule in Grand Rapids Asphalt Paving Co v City of Wyoming, 
    29 Mich App 474
    ; 
    185 NW2d 591
     (1971). Great American, 841 F3d at 448.
    The Sixth Circuit, however, did not apply the rule against apportionment of liquidated
    damages in Great American. Recognizing the potential unfairness of the rule, the court noted that
    “federal and other state courts . . . have been shifting away from strict application of this rule.” Id.
    at 448. Citing a bankruptcy court decision, In re Constr Diversification, Inc, 
    36 BR 434
     (ED Mich,
    -4-
    1983), the Sixth Circuit explained that the rule may not apply where a contract provides for per
    diem liquidated damages. The court noted that a majority of courts have allowed the
    apportionment of liquidated damages where the damages are divisible. It stated that “it is unclear,
    however, whether the Michigan Supreme Court, if faced with the issue today, would maintain the
    strict non-apportionment rule in light of the modern view . . . .” Great American, 841 F3d at 449.
    Thus, the Sixth Circuit declined to apply the rule against apportionment of liquidated damages,
    and its decision does not support defendant’s argument here.
    Although there is scant caselaw on this issue, in three published decisions, Michigan
    appellate courts have addressed the apportionment of liquidated damages where delay is the fault
    of both parties. In Early v Tussing, 
    182 Mich 314
    , 316; 
    148 NW 678
     (1914), the parties agreed to
    a construction contract requiring completion of the project by March 1, 1910, and provided for the
    plaintiffs’ contractors’ payment of liquidated damages of $25 a day to the defendant owner for
    each day construction remained incomplete after that date. Following completion of construction,
    a dispute arose regarding the balance due under the contract, with the defendant claiming that the
    plaintiffs owed liquidated damages for delayed completion, as provided in the agreement. The
    parties agreed to arbitration, resulting in an arbitration award that found that completion had been
    delayed 150 days and charged two-thirds of the delay against the plaintiffs. After confirmation of
    the award, the plaintiffs appealed. Id. at 324-327.
    On appeal, our Supreme Court examined commentaries on English law, as well as two
    American decisions, Jefferson Hotel Co v Brumbaugh, 168 F 867, 871 (CA 4, 1909), and Mosler
    Safe Co v Maiden Lane Safe Deposit Co, 199 NY 479; 
    93 NE 81
     (1910). Early, 
    182 Mich at
    327-
    329. Noting the paucity of caselaw on point, the Court, nevertheless, concluded that “the great
    weight of the authorities are in favor of the proposition that such damages for delays cannot be
    apportioned, and this rule has been applied both in courts of law and in equity.” 
    Id. at 327
    . The
    Court vacated the arbitration award as a mistake of law, finding that the defendant’s own delays
    “amounted to a breach of contract on his part, and by reason thereof defendant lost all right to
    recover liquidated damages for delays.” 
    Id. at 329
    .
    Six years later, in Bd of Ed of City of Sault Ste Marie, 
    211 Mich at 68
    , another case where
    the contractor alone contractually agreed to pay the owner liquidated damages for delayed
    completion, our Supreme Court, citing Early, agreed that “where the delay is due to the fault of
    both parties the court will not attempt to apportion such [liquidated] damages.” The Court found
    that the delay in construction did not occur due to the fault of either party, the parties had agreed
    to a reasonable extension of time for the contractor to complete construction, and any delay beyond
    the extension was “due solely to the conduct and neglect of the contractor.” 
    Id. at 69
    . Thus, the
    Court affirmed the award of liquidated damages. 
    Id. at 63, 70
    .
    More than 50 years later, this Court addressed the issue in Grand Rapids Asphalt, 
    29 Mich App 474
    . In that case, the plaintiffs sued the defendant city to recover liquidated damages withheld
    by the defendant for the plaintiffs’ failure to timely complete performance of a road construction
    contract. The contract provided that the city could withhold as liquidated damages $25 for each
    day plaintiffs delayed completion but also provided for extension of the completion date because
    of the city’s acts, neglect, or default. After the trial court entered a judgment for the plaintiffs, the
    defendant appealed. Id. at 475-476. Citing both Early and Bd of Ed of Sault Ste Marie, this Court
    affirmed the trial court, and explained that, “[b]ecause of delays occasioned by the actions of both
    -5-
    plaintiffs and defendant, as revealed by the record, the conclusion by the court that liquidated
    damages were not recoverable by defendant city was, based upon the foregoing authority, not
    clearly erroneous.” Grand Rapids Asphalt, 
    29 Mich App at 484
    .
    Michigan caselaw regarding apportionment of liquidated damages does not support
    reversal of the trial court’s judgment in this case. In Early, 
    182 Mich at 316
    , our Supreme Court
    observed that the only provision for liquidated damages contractually bound the contractor to pay
    liquidated damages for delay in completion but no provision provided for liquidated damages for
    delays caused by the owner. Similarly, in Bd of Ed of City of Sault Ste Marie, 
    211 Mich at 67-68
    ,
    the parties’ contract required the contractor to pay liquidated damages to the owner in the event of
    delay. Likewise, in Grand Rapids Asphalt, 
    29 Mich App at 477
    , the agreement allowed the city
    to withhold liquidated damages from the payment due in the event of a delay by the contractor,
    but no provision awarded liquidated damages to the contractor for delay caused by the city. By
    contrast, in this case, the parties’ agreement provided both the right to recover liquidated damages
    for the other party’s delays.
    The bedrock of contract law is that the “parties are free to contract as they see fit, and the
    courts are to enforce the agreement as written absent some unusual circumstances, such as a
    contract in violation of law or public policy.” Wilkie v Auto-Owners Ins Co, 
    469 Mich 41
    , 51; 
    664 NW2d 776
     (2003).
    When interpreting a contract, the examining court must ascertain the intent of the
    parties by evaluating the language of the contract in accordance with its plain and
    ordinary meaning. In re Egbert R Smith Trust, 
    480 Mich 19
    , 24; 
    745 NW2d 754
    (2008). If the language of the contract is clear and unambiguous, it must be
    enforced as written. 
    Id.
     A contract is unambiguous, even if inartfully worded or
    clumsily arranged, when it fairly admits of but one interpretation. Holmes v
    
    Holmes, 281
     Mich App 575, 594; 
    760 NW2d 300
     (2008). Every word, phrase, and
    clause in a contract must be given effect, and contract interpretation that would
    render any part of the contract surplusage or nugatory must be avoided. Woodington
    v Shokoohi, 
    288 Mich App 352
    , 374; 
    792 NW2d 63
     (2010). [McCoig Materials,
    LLC v Galui Constr, Inc, 
    295 Mich App 684
    , 694; 
    818 NW2d 410
     (2012).]
    “Michigan law presumes that one who signs a written agreement knows the nature of the
    instrument so executed and understands its contents.” Galea v FCA US LLC, 
    323 Mich App 360
    ,
    369; 
    917 NW2d 694
     (2018) (citation omitted).
    In this case, the parties contractually agreed that each would pay liquidated damages of
    $100 a day for delays occasioned by the other as follows:
    Builder agrees to complete construction no later than fourteen (14) months from
    date of this Agreement, subject to acts of God, events over which Builder has no
    reasonable control, Purchaser’s failure to comply with selection deadlines, or
    delays caused by Change Orders. If home is not completed by that date and the
    delay was the result of the Builder, Builder will pay a $100.00 a day fee as
    liquidated damages. If Purchaser delays the progress of construction such as late
    -6-
    selections or change orders, the Purchaser agrees to pay Builder $100.00 per day
    for his delays.
    Thus, the agreement expressly provided a remedy to each party for delays attributable to the other
    party. The record indicates that the arbitrator properly interpreted and applied the parties’ contract
    terms and correctly apportioned the liquidated damages. The trial court, therefore, correctly
    affirmed the arbitration award in this regard.
    Defendant next contends that the arbitrator exceeded his authority by injecting his personal,
    expert opinion in support of a higher award to plaintiffs for the project’s completion cost.
    Defendant, however, devotes a total of three paragraphs to this issue with no citation to caselaw,
    the UAA, or any other authority to support its argument. An appellant is required to support its
    position with citation to authority, and may not simply announce a position or assert an error and
    expect this Court to search for authority to support its position. Where an appellant fails to properly
    support an argument, this Court may reject it as abandoned. Mettler Walloon, LLC v Melrose Twp,
    
    281 Mich App 184
    , 220; 
    761 NW2d 293
     (2008). “This Court is not required to search for authority
    to sustain or reject a position raised by a party without citation of authority.” 
    Id.
     (citations omitted).
    “It is not enough for an appellant in his brief simply to . . . assert an error and then leave it up to
    this Court to . . . unravel and elaborate for him his arguments, and then search for authority either
    to sustain or reject his position.” 
    Id.
     (citations omitted). Defendant having failed to properly
    support its claim of error has abandoned this issue and we decline to consider it.
    Defendant also objects to the award of $5,000 to compensate plaintiffs for time,
    inconvenience, uncertainty, costs for completion of the project, and lack of a warranty. Defendant,
    however, devotes a total of three paragraphs to this issue, with no citation to caselaw or any other
    authority to support its argument. Where an appellant fails to properly support an argument, this
    Court may reject it as abandoned. Mettler Walloon, LLC, 
    281 Mich App at 220
    . Defendant having
    failed to properly support its claim of error has abandoned this issue and we decline to consider it.
    Affirmed.
    /s/ James Robert Redford
    /s/ Colleen A. O’Brien
    /s/ Kathleen A. Feeney
    -7-