Montaplast of North America Inc v. Proper Tooling LLC ( 2023 )


Menu:
  •               If this opinion indicates that it is “FOR PUBLICATION,” it is subject to
    revision until final publication in the Michigan Appeals Reports.
    STATE OF MICHIGAN
    COURT OF APPEALS
    MONTAPLAST OF NORTH AMERICA, INC.,                                     UNPUBLISHED
    August 17, 2023
    Plaintiff-Appellant/Cross-Appellee,
    v                                                                      No. 363217
    Macomb Circuit Court
    PROPER TOOLING, LLC,                                                   LC No. 2021-004171-CB
    Defendant-Appellee/Cross-Appellant.
    Before: GADOLA, P.J., and MURRAY and MALDONADO, JJ.
    PER CURIAM.
    Montaplast of North America (hereinafter Montaplast) appeals by right the trial court’s
    order granting in part Proper Tooling’s motion for an order to show cause. Montaplast argues that
    the trial court erred by ordering it to pay damages for its purported breach of contract because
    Proper Tooling was required to file a new complaint rather than a motion for an order to show
    cause and because Montaplast did not owe any damages for the outstanding balance sought by
    Proper Tooling. Proper Tooling cross-appeals, arguing that it was entitled to the entire contested
    amount, not the amount offset by the speculative costs offered by Montaplast. We affirm.
    I. FACTUAL AND PROCEDURAL BACKGROUND
    This case arises out of a dispute regarding the cost of “tuning”1 services for two tools
    Montaplast purchased from Proper Tooling. The tools in question are identified as Tool #10424-
    1
    According to Proper Tooling’s Chief Financial Officer, Blaise Flack:
    “Tuning” is part of the normal manufacturing process for plastic injection molding
    tools. It consists of making post-fabrication adjustments to the tool so that the tool
    produces parts consistent with the customer’s specifications. Following the
    fabrication of a tool, the tool will be tested to determine whether tuning is
    necessary. Tuning does not include modifications to the tool beyond the design
    -1-
    000 (Tool 000) and Tool #10424-100 (Tool 100). This case consists of two phases, with only the
    second phase being at issue on appeal. The first phase began when Montaplast filed suit alleging
    two counts: (1) replevin/claim and delivery, and (2) breach-of-contract. Montaplast purchased
    various tools from Proper Tooling, but conflicts arose between the parties concerning payment and
    delivery. The parties ultimately settled on schedules for payment and delivery, which the trial
    court incorporated into a stipulated order of dismissal without prejudice.
    Montaplast took delivery of the tools but after what Montaplast alleges were multiple
    untimely deliveries, which allegedly violated the stipulated order, Montaplast terminated the
    remainder of the contract under the original contract’s terms and conditions. The remainder of the
    contract only consisted of Proper Tooling tuning the tools. Montaplast sought a discount on the
    final contract price of $539,600 which Montaplast calculated was the value of the tuning services.
    Montaplast based the discount on the two sets of quotes Montaplast received from Proper Tooling.
    The first quote did not include tuning as a line item. The subsequent quote stated that it included
    tuning and increased the price of the contract by $539,600. Proper Tooling moved for an order to
    show cause why Montaplast should not be held in contempt for violating the trial court’s order by
    failing to pay the amount owed under the payment schedule. In response, Montaplast argued that
    the order was essentially a settlement agreement subject to contractual interpretation, that Proper
    Tooling was required to file a new lawsuit alleging breach-of-contract, and that even if Proper
    Tooling adhered to the proper procedural requirements, there was a genuine issue of material fact
    regarding whether Montaplast owed the contested amount. After various hearings and
    supplemental briefings, the trial court granted Proper Tooling’s motion in part, ordering
    Montaplast to pay Proper Tooling the difference between the amount outstanding and the amount
    that the trial court found that the tuning would cost Proper Tooling. Montaplast now appeals,
    arguing that the trial court deprived it of its procedural due-process rights by adjudicating a motion
    for an order to show cause, which had fewer procedural safeguards, when the correct course of
    action for Proper Tooling would have been filing a new complaint alleging breach of contract.
    Additionally, there were genuine issues of material fact regarding whether Montaplast owed
    Proper Tooling any money at all. Proper Tooling cross-appeals, arguing the trial court erred by
    subtracting Montaplast’s estimated costs to procure tuning of the tools from an alternative vendor
    because it did not properly reflect Proper Tooling’s cost savings from not having to perform the
    tuning.
    II. ANALYSIS
    A. CONTEMPT
    Montaplast argues that the trial court violated its procedural due-process rights by
    adjudicating what was actually a breach-of-contract claim as a motion for an order to show cause.
    We disagree.
    specifications or to address design modifications, such as texturing, to the parts
    intended to be produced.
    -2-
    “This Court reviews a trial court’s decision regarding a contempt motion for an abuse of
    discretion.” DeGeorge v Warheit, 
    276 Mich App 587
    , 591; 
    741 NW2d 384
     (2007). “An abuse of
    discretion occurs when the trial court’s decision is outside the range of reasonable and principled
    outcomes.” Pirgu v United Servs Auto Ass’n, 
    499 Mich 269
    , 274; 
    884 NW2d 257
     (2016) (footnote
    and citation omitted). “A trial court necessarily abuses its discretion when it makes an error of
    law.” 
    Id.
     (footnote and citation omitted). “Whether due process has been afforded is a
    constitutional issue that is reviewed de novo.” Elba Twp v Gratiot Co Drain Comm’r, 
    493 Mich 265
    , 277; 
    831 NW2d 204
     (2013).
    The order Proper Tooling sought to enforce was titled: “Stipulated Order of Dismissal
    Without Prejudice.” While Proper Tooling’s motion was labeled as one seeking contempt, this
    was not what it actually was, or how the trial court handled the matter. “Courts are not bound by
    the labels that parties attach to their claims.” Buhalis v Trinity Continuing Care Servs, 
    296 Mich App 685
    , 691; 
    822 NW2d 254
     (2012). The order was entered to embody the parties’ agreement
    regarding a schedule for delivery and payment. However, the trial court incorporated the parties’
    agreement into its order, and reserved the power to enforce the order in the future. “A trial court
    has inherent and statutory authority to enforce its orders.” In re Moroun, 
    295 Mich App 312
    , 331;
    
    814 NW2d 319
     (2012). The dispute giving rise to this portion of the case directly concerned the
    schedule incorporated into the order and, therefore, the trial court had inherent authority to enforce
    the schedule. Id.; See also MCL 600.611 (“Circuit courts have jurisdiction and power to make any
    order proper to fully effectuate the circuit courts' jurisdiction and judgments.”). Indeed,
    Montaplast does not dispute that it never actually was held in contempt. In sum, Proper Tooling’s
    motion sought to enforce the schedules provided in the trial court’s order, and the trial court’s
    order granting Proper Tooling’s motion merely awarded damages; it did not hold Montaplast in
    contempt.
    Montaplast argues that the trial court lacked enforcement powers because a stipulated order
    of dismissal is a settlement agreement, and a settlement agreement is enforced by filing a complaint
    for breach of contract. For support, Montaplast relies on Acorn Investment Co v Michigan Basic
    Prop Ins Ass’n, 
    495 Mich 338
    , 355-356; 
    852 NW2d 22
     (2014), in which our Supreme Court said,
    “A stipulated order of dismissal based on a settlement agreement is not a ‘judgment’ in the sense
    that it is not a final determination by the court of the rights and obligations of the parties.”
    However, Montaplast has taken this quotation out of context. In Acorn, the Supreme Court was
    determining whether a stipulated order of dismissal could be considered a “verdict” for the
    purposes of since-repealed MCR 2.403(O), which provided for sanctions if a party rejected a case
    evaluation then did not obtain a verdict that was more favorable. Id. at 355. Accordingly, we
    disagree with Montaplast’s contention that Acorn can be construed to suggest that courts do not
    have the authority to enforce a stipulated order of dismissal.2
    Further, it is unclear to us how Montaplast would have been better off if the court had
    required Proper Tooling to file a complaint rather than proceeding as it did. While it is true civil
    contempt proceedings are “only entitled to ‘rudimentary’ due process protections,” In re Contempt
    2
    We agree with Montaplast that a stipulated order of dismissal ought to be treated as a contract to
    the extent that such an order is interpreted with the end goal of ascertaining the intent of the parties.
    -3-
    of Pavlos-Hackney, ___ Mich App ___, ___; ___ NW2d ___ (2022) (Docket No 357407); slip op
    at 14, Montaplast was given multiple opportunities to present its defense and argue its case. The
    trial court ordered multiple briefings and the submission of proofs, and it held multiple hearings.
    Montaplast has failed to identify any additional procedural right, besides discovery, which was
    lacking during this phase of the case. Further, Montaplast has not identified anything useful that
    discovery would have yielded. Montaplast was given numerous opportunities to present
    documentary evidence, and it expressly declined an opportunity to present testimony at an
    evidentiary hearing.
    In conclusion, whether the trial court had the power to hold Montaplast in contempt on the
    basis of the stipulated order is irrelevant, because that is not what happened. The trial court merely
    enforced its own order, as it was entitled to do. Therefore, the trial court acted within the scope of
    its authority.
    B. AMOUNT OWED AND DAMAGES
    In this case, Montaplast viewed the purchase of the tools and the purchase of the tuning
    services as two separate transactions. Montaplast argued that, pursuant to the terms of the
    agreement, that it would not need to pay for the tuning if it canceled the transaction after acceptance
    of the tools but before the tuning services were performed. Thus, Montaplast did not believe it
    was obligated to pay the $539,600 that it viewed as having been allocated for the tuning services.3
    Montaplast reached this figure by determining the difference in price between a quote that did not
    include the tuning services and a subsequent quote that did. The trial court, however, did not agree
    with Montaplast’s position that the purchase of the tools and the tuning services were two separate
    transactions. The court found that the parties negotiated the cost of tuning as part of the cost of
    purchasing the tools and that “[t]he inclusion of tuning services in the quote, followed by an
    increased price, does not divide the tool from the tuning regarding the payment obligation.”
    Nevertheless, the trial court determined that it would constitute a windfall for Proper Tools
    if it could recover the entire contract price without performing the tuning services. Thus, the trial
    court concluded that “Proper Tooling is entitled to $539,600 less any of its savings from not having
    to perform the tuning and coating work” because it “will clearly save money by not performing
    the tuning and coating services.” Proper Tooling argued that it would only save $131,000, but the
    court was persuaded that the services were actually worth $308,731 because that is the figure
    Montaplast claimed to have paid a third party to have the tuning completed after it canceled the
    contract. Thus, Montaplast was ordered to pay Proper Tooling $230,869 to satisfy its outstanding
    debt.
    3
    Montaplast received quotes for the pair of tools on January 19, 2021 and again on January 20.
    The January 20 quotes listed tuning services as “INCLUDED” in the purchase price while the
    January 19 quotes did not; this was the only difference between the two sets of quotes. The January
    19 quotes indicated prices of $735,500 for Tool 000 and $650,000 for Tool 100 while the January
    20 quotes indicated prices of $1,021,950 and $903,150, respectively. Thus, Montaplast deduced
    that the price for tuning must have been $286,450 for Tool 000 and $253,150 for Tool 100.
    -4-
    Neither party agrees with the trial court’s decision that Montaplast pay Proper Tooling
    $230,869. On appeal, Montaplast argues that the unperformed tuning services were worth
    $539,600 and that the trial court erred by finding the services to only be worth $308,371.
    Montaplast argues that it is “entitled to a credit in the full amount of the unperformed tuning
    services.” Montaplast disagrees with the trial court’s conclusion that tuning could not be separated
    from the purchase of the tools because such a separation was made in Proper Tooling’s quotes.
    On cross appeal, Proper Tooling argues that the trial court erred by reducing the purchase price to
    prevent a “windfall” and that Montaplast should have been ordered to pay the full $539,600
    remaining on the contract because that was the figure provided in the stipulated order of dismissal.
    Proper Tooling argues that if a modification for these savings was warranted then the trial court
    nonetheless erred by relying on Montaplast’s estimated market costs. Proper Tooling submits that
    damages must be ascertained with reasonable certainty, that Montaplast did not prove its estimates
    with reasonable certainty, and that it was inappropriate to use market costs to calculate the offset
    because market costs include profits.
    1. SEVERABILITY OF TUNING FROM PURCHASE PRICE
    The trial court did not err by interpreting the sale and tuning of the tools as a single
    transaction that could not be severed.
    This Court reviews questions of contractual interpretation de novo. Cadillac Rubber &
    Plastics, Inc v Tubular Metal Sys, LLC, 
    331 Mich App 416
    , 422; 
    952 NW2d 576
     (2020). “The
    cardinal rule in the interpretation of contracts is to ascertain the intention of the parties; to this rule
    all others are subordinate.” Joseph & Anita Russell Trust v Russell, 
    338 Mich App 170
    , 179; 
    979 NW2d 672
     (2021) (quotation marks and citation omitted). To accomplish this, a court must
    “examine the language of the contract according to its plain and ordinary meaning.” Ingham Co v
    Mich Co Rd Comm Self-Ins Pool, 
    508 Mich 461
    , 477; 
    975 NW2d 826
     (2021). “If the contractual
    language is unambiguous, courts must interpret and enforce the contract as written, because an
    unambiguous contract reflects the parties’ intent as a matter of law.” Cadillac Rubber & Plastics,
    331 Mich App at 422 (quotation marks and citation omitted).
    The record supports the trial court’s conclusion that the parties’ intent was that the tuning
    services be included as part of the purchase of the tools. First, while the quotes list the items and
    services included in the price, the price is not itemized. Rather, there is only one total price for
    everything included in the transaction. Moreover, Proper Tooling’s Chief Financial Officer, Blaise
    Flack, stated in an affidavit that tuning was “part of the normal manufacturing process” for the
    tools Montaplast purchased, and this further suggests that the parties intended that the purchase
    and tuning be one transaction. Flack explained that Montaplast was not charged “separately for
    the tuning because the service was included in the price of each tool.” Finally, this interpretation
    is consistent with the parties’ course of dealing as the record suggests that they had never
    previously separated the sale of the tools from the tuning.
    Therefore, the trial court properly concluded that the sale and tuning of the tools was
    intended by the parties to be a single, nonseverable transaction.
    2. REDUCTION OF PURCHASE PRICE
    -5-
    Proper Tooling takes exception with the trial court’s decision to reduce the amount owed
    to it by the amount of money it would save by not having to perform tuning services. Proper
    Tooling submits that Montaplast should have been ordered to pay the entire outstanding balance
    of $539,600 because that was the amount specified in the stipulated order of dismissal. However,
    we agree with the trial court that declining to reduce the payout would have resulted in a windfall
    for Proper Tooling. Damages available pursuant to the Uniform Commercial Code (UCC), MCL
    440.1101 et seq., “are intended to place the injured party in as good a position as he would have
    been in had the promised performance been rendered.” Sullivan Indus, Inc v Double Seal Glass
    Co, Inc, 
    192 Mich App 333
    , 346; 
    480 NW2d 623
     (1991), quoting S C Gray, Inc v Ford Motor Co,
    
    92 Mich App 789
    , 810; 
    286 NW2d 34
     (1979). The parties’ intent was that Proper Tooling would
    spend money to complete the tuning process and that Montaplast would pay Proper Tooling the
    additional $539,600. If the court did not reduce the amount owed to Proper Tooling then it would
    receive the $539,600 without also spending money to complete the tuning process. Thus, such a
    remedy would have placed Proper Tooling in a better position rather than as good a position.
    Therefore, the court did not err by reducing the outstanding balance in order to avoid such a
    windfall.
    3. VALUE OF TUNING AND COATING SERVICES
    The trial court’s finding that Proper Tooling saved $308,731 by not performing tuning
    services was supported by the record and, thus, not a clear error.
    “The trial court’s factual findings are reviewed for clear error.” DeGeorge, 
    276 Mich App at 591
    . “Clear error exists when the reviewing court is left with a definite and firm conviction that
    a mistake has been made.” 
    Id.
    The record supported the court’s finding that Proper Tooling saved $308,731 by not
    performing the tuning services. The evidence available to the court regarding the cost of
    performing the tuning was scarce. The court could have found that the cost of tuning was $539,600
    as this was the difference between the prices of the quotes that did and did not list tuning. However,
    it was not a clear error for the court to have been unconvinced that this represented the cost that
    would be incurred by Proper Tooling if it performed the tuning because the evidence regarding the
    difference in the prices of these quotes was ambiguous, and this price likely included profits Proper
    Tooling would earn in addition to the actual expense of performing the service. Proper Tooling
    asserted in its July 8, 2022 supplemental brief that the actual cost of tuning was $131,000, but there
    was no evidence supporting this assertion. Thus, the trial court was correct not to rely on that
    figure. The only evidence Proper Tooling produced regarding the cost of the tuning services came
    from the affidavit of its Chief Financial Officer, Blaise Flack. Flack explained that “it took one or
    two Proper employees a total of approximately 30-40 hours at a cost of approximately $3,000-
    $10,000 for tuning each of the tools.” Flack estimated “that the actual cost to Proper Tooling for
    tuning the Tools [sic] . . . will range from $25,000 to $35,000 each.” Based on Flack’s testimony,
    the total cost to Proper Tooling for tuning Tool 100 and Tool 000 would have been between
    $50,000 and $70,000. However, given that even Proper Tooling itself argued that the cost would
    be significantly higher, the court cannot be faulted for declining to rely on this affidavit for its
    calculation of the cost of the tuning.
    -6-
    The amount the court settled on was $308,731. The court reasoned that it was “persuaded
    that Montaplast’s calculations more accurately represent the market costs of tuning services, and
    therefore by extension, are a reasonable approximation of the amount Proper Tooling will save.”
    The $308,731 figure was obtained from an exhibit that Montaplast attached to its May 10, 2022
    supplemental brief. The two-page exhibit listed the work that had been done, the work still needed
    to be done, and the price for each. The exhibit was far from perfect as it was not dated and it was
    not clear how the figures were obtained. Nevertheless, the trial court found that this was the most
    credible representation of the costs to perform tuning services, and we will not disturb this finding.
    See Luna v Regnier, 
    326 Mich App 173
    , 182-183; 
    930 NW2d 410
     (2018).
    Affirmed.
    /s/ Michael F. Gadola
    /s/ Christopher M. Murray
    /s/ Allie Greenleaf Maldonado
    -7-