Seagate Technology, LLC v. Western Digital Corporation, Sining Mao ( 2016 )


Menu:
  •                         This opinion will be unpublished and
    may not be cited except as provided by
    Minn. Stat. § 480A.08, subd. 3 (2014).
    STATE OF MINNESOTA
    IN COURT OF APPEALS
    A15-0760
    Seagate Technology, LLC,
    Appellant,
    vs.
    Western Digital Corporation, et al.,
    Respondents,
    Sining Mao,
    Respondent.
    Filed January 25, 2016
    Reversed and remanded
    Rodenberg, Judge
    Hennepin County District Court
    File No. 27-CV-06-19000
    Lewis A. Remele, Jr., Mark R. Bradford, Jeffrey R. Mulder, Frederick E. Finch, Bassford
    Remele, P.A., Minneapolis, Minnesota (for appellant)
    Michael D. Schissel (pro hac vice), Arnold & Porter LLP, New York, New York; and
    Clifford M. Greene, Larry D. Espel, Sybil L. Dunlop, Greene Espel PLLP, Minneapolis,
    Minnesota (for respondents Western Digital Corporation and Western Digital
    Technologies, Inc.)
    George W. Soule, Soule & Stull LLC, Minneapolis, Minnesota (for respondent Sining
    Mao)
    Considered and decided by Rodenberg, Presiding Judge; Schellhas, Judge; and
    Reilly, Judge.
    UNPUBLISHED OPINION
    RODENBERG, Judge
    Appellant Seagate Technology, LLC (Seagate) challenges the district court’s
    denial of its request for an award of post-arbitration-award interest, arguing that the
    district court erred in interpreting the underlying arbitration award as having determined
    post-award interest. Because we conclude that the arbitrator did not decide the issue of
    post-award interest, and because the plain language of 
    Minn. Stat. § 549.09
     (2014)
    mandates post-award interest on the amount of the entire award, we reverse and remand.
    FACTS
    The lengthy procedural history of this case, which we do not recite here, is
    included in the previous opinions of this court and the Minnesota Supreme Court. See
    Seagate Tech., LLC v. W. Digital Corp., 
    854 N.W.2d 750
    , 753-57 (Minn. 2014), aff’g
    
    834 N.W.2d 555
     (Minn. App. 2013). Those opinions, collectively “Seagate I,” generally
    concern the arbitrator’s authority.
    The supreme court issued its opinion in Seagate I on October 8, 2014, affirming
    this court’s reinstatement of the arbitrator’s final award.     
    854 N.W.2d 750
    .       On
    October 13, 2014, respondents Western Digital Corporation and Western Digital
    Technologies, Inc. (together, Western) offered to satisfy what Western considered to be
    the full award amount, $773,404,103.74.         Seagate accepted that amount as partial
    payment, but maintained that Western owed a balance of $28,884,751.64, because the
    total award amount as of December 24, 2014, including post-award interest, was
    $802,288,855.38. The discrepancy in the parties’ calculations results from disagreement
    2
    over whether the arbitrator’s final award provided the method for calculating post-award
    interest.
    Seagate sought a declaratory judgment concerning the correct computation of
    interest. The parties brought cross-motions in the district court: Western sought a
    declaration that it had fully satisfied its liability, and Seagate sought judgment for what it
    claimed was the unpaid balance of the award, with interest. The narrow issue before the
    district court was the correct computation of interest owing on the arbitrator’s award.
    Western based its interest calculation on the principal amount of the arbitrator’s interim
    award, $525,000,000. Seagate based its interest calculation on a principal amount of
    $630,431,501, the sum of the arbitrator’s compensatory-damages award plus the interest
    included in the final award.
    The district court ruled for Western, construing the final award as having
    addressed both pre- and post-award interest. This appeal followed.
    DECISION
    I.     Standard of review.
    We review a district court’s interpretation of legal documents, such as arbitration
    awards, de novo. See Halla Nursery, Inc. v. City of Chanhassen, 
    781 N.W.2d 880
    , 884
    (Minn. 2010) (“[W]e review de novo the district court’s interpretation of [a] stipulation
    and judgment.”); Star Windshield Repair, Inc. v. Western Nat. Ins. Co., 768 N.W2d 346,
    348 (Minn. 2009) (“[W]e independently review a lower court’s interpretation of [an]
    insurance policy.”); Alpha Real Estate Co. of Rochester v. Delta Dental Plan of Minn.,
    
    671 N.W.2d 213
    , 221 (Minn. App. 2003) (“[T]he construction of [an unambiguous
    3
    contract provision] is a question of law for the court to resolve, and this court need not
    defer to the district court’s findings.”), review denied (Minn. Jan. 20, 2004) (quotations
    omitted). Western argues in a footnote in its brief that Ray v. City of Maple Grove, 
    519 N.W.2d 466
     (Minn. App. 1994), review denied (Minn. Sept. 16, 1994) and Johnson v.
    Newbold, No. A06-760, 
    2007 WL 583332
     (Minn. App. Feb. 27, 2007), when read
    together, suggest that we should review the district court’s interpretation of the
    arbitrator’s award for clear error.     The narrow issue here, however, concerns the
    availability of prejudgment interest, which both parties agree that we review de novo.
    Duxbury v. Spex Feeds, Inc., 
    681 N.W.2d 380
    , 390 (Minn. App. 2004), review denied
    (Minn. Aug. 25, 2006). Our de novo review requires us to consider the four corners of
    the arbitrator’s final award and 
    Minn. Stat. § 549.09
    . We do not evaluate the merits of
    the underlying dispute between the parties. The issue before us is one of law concerning
    which we do not defer to the district court. De novo review is appropriate.
    II.    Our opinion and the Minnesota Supreme Court’s opinion in Seagate I did not
    resolve the issue of post-award interest.
    Western argues that the recitation of this case’s procedural history in our opinion
    and in the supreme court’s opinion in Seagate I should guide our interpretation of the
    arbitrator’s final award.   The district court relied on language in those opinions to
    conclude that the arbitrator decided the issue of post-award interest.
    The references to “post-award interest” in the Seagate I opinions are contained in
    each court’s recitation of background information. The issue then on appeal was whether
    the arbitrator exceeded his authority in imposing sanctions. Seagate I, 854 N.W.2d at
    4
    760. Neither we nor the supreme court considered the question of the proper interest
    calculation because the question in Seagate I was binary: should or should not the
    arbitrator’s final award be vacated for having exceeded the arbitrator’s authority? Id. at
    765. The characterizations of interest are not necessary to the holdings in Seagate I, and
    are therefore dicta. See State v. Naftalin, 
    246 Minn. 181
    , 208, 
    74 N.W.2d 249
    , 266
    (1956) (defining “dicta” as “expressions in a court’s opinion which go beyond the facts
    before the court and therefore are . . . not binding on subsequent cases”).
    It is worth noting in this context that the statements of the appellate courts
    concerning interest in Seagate I arose from the parties’ and the district court’s
    characterizations of the magnitude of the arbitrator’s final award. Both parties have taken
    a mercurial approach to the issue of post-award interest. In Seagate I, each advanced a
    position concerning post-award interest exactly opposed to that party’s present
    arguments. Western argued then, attempting to demonstrate the claimed outrageousness
    of the award, that the arbitrator’s final award included compensatory damages and pre-
    award interest for a total of approximately $630 million, with interest accruing at the rate
    of $173,000 per day. The $173,000 per day figure can only be replicated by using a
    principal amount of $630,431,501.1 Conversely, Seagate argued in Seagate I that interest
    was accruing at $143,835.61 per day. That figure can only be arrived at by computing
    1
    $630,431,501 principal x 0.10 interest rate = $63,043,150.10 annual interest.
    $63,043,150.10 ÷ 365 days = $172,720.95 daily interest. $172,720.95 x 7 days =
    $1,209.046.65 weekly interest. This calculation, and that which follows in note 2 infra,
    are for illustration only. The parties appear to have “rounded” to the next-lowest cent.
    Our present purpose does not involve focusing on the parties’ rounding standards.
    5
    10% interest on a principal amount of $525,000,000.2 Each now takes the position
    formerly advanced by the other, and each claims that its position in this appeal is
    unquestionably correct.
    Despite the parties’ characterizations of the magnitude of interest in Seagate I, that
    earlier appeal did not involve, and neither this court nor the supreme court considered, the
    question presented in this appeal: should post-award interest on these facts be computed
    on the principal amount of the award ($525,000,000) or on the entire final award
    ($630,431,501)?
    III.   The arbitrator did not decide the availability or calculation of post-award
    interest.
    If an arbitrator’s final award includes post-award interest and establishes how it
    must be computed, then the arbitrator’s decision is final and binding on the parties,
    regardless of whether it is legally correct. See Seagate I, 854 N.W.2d at 760-61 (noting
    that an arbitration award is final unless the arbitrator clearly acts beyond the scope of his
    or her authority); State v. Minn. Ass’n of Prof’l Emps., 
    504 N.W.2d 751
    , 754 (Minn.
    1993) (“[An arbitrator’s] award will not be reviewed or set aside for mistake of either law
    or fact in the absence of fraud, mistake in applying his own theory, misconduct, or other
    disregard of duty.”) (citation omitted).      Therefore, we first consider whether the
    arbitrator’s final award resolved the issue of post-award interest.
    2
    $525,000,000 principal x 0.10 interest rate = $52,500,000 annual interest. $52,500,000
    ÷ 365 days = $143,835.61 daily interest. $143,835.61 x 7 days = $1,006,849.27 weekly
    interest.
    6
    The district court concluded that the final award addressed both pre- and post-
    award interest and provided a mechanism for calculating post-award interest because the
    arbitrator made two interest calculations: (1) “pre-award interest” from January 21, 2010
    to November 18, 2011, and (2) “interest” from November 19, 2011 to January 23, 2012.
    Both calculations apply 10% interest to the underlying compensatory-damage award,
    $525,000,000. The day that separates the two calculations, November 18, 2011, is the
    date of the arbitrator’s interim award. Therefore, the district court interpreted the final
    award as having determined that all future interest would be computed based on the
    principal amount of the interim award.
    The final award stated:
    Seagate is entitled to recover compensatory damages from
    Western Digital and Dr. Mao in the amount of Five Hundred
    Twenty-Five Million Dollars ($525,000,000). Seagate is
    entitled to recover pre-award interest from Western Digital
    and Dr. Mao from January 21, 2010 to November 18, 2011,
    the date of the Interim Award, on the award of $525,000,000
    at the rate of 10% per annum in the amount of
    $95,938,351.00. Seagate is entitled to recover interest from
    Western Digital and Dr. Mao on the award of $525,000,000 at
    the rate of 10% per annum from November 19, 2011 to
    January 23, 2012, the date of the Final Award, in the amount
    of $9,493,150.00.
    (Emphasis added). The arbitrator introduced this section by recapping the arbitration
    proceedings to that point.       Specifically, the arbitrator noted that the interim award
    provided for “pre-award interest on the compensatory damage award” and requested that
    the parties brief the issue of pre-award interest. The final award made no reference to
    “post-award” interest, and provides no indication that the arbitrator considered or decided
    7
    the issue of post-award interest. In the arbitrator’s memorandum that accompanied the
    final award, he based his conclusions on 
    Minn. Stat. § 549.09
    , subd. 1(b), which governs
    pre-award interest. And neither party appears to have requested that the arbitrator clarify
    whether the final award intended to resolve the issue of post-award interest.
    In determining that all future interest would be calculated on the principal amount
    of the interim award, the district court erred in considering the interim award as one
    susceptible of confirmation. Under 
    Minn. Stat. § 572.15
    (a) (2010), an “award must
    include interest.”3 Once a party receives notice of an award, the party may file a motion
    with the district court to confirm the award. 
    Minn. Stat. § 572.19
     (2010). Minnesota
    courts consider an arbitration award to be a “final judgment,” one allowing the prevailing
    party to confirm and collect the award. Aufderhar v. Data Dispatch, Inc., 
    452 N.W.2d 648
    , 651 (Minn. 1990) (affording “an arbitration award finality as to both facts and the
    law” for the purposes of triggering collateral estoppel). And the Minnesota Supreme
    Court has held that “[a]n award of arbitrators must be final and certain, and so determine
    the matter submitted that an action between the same parties will not afterwards lie in
    regard to it, or the award is void.” Hoit v. Berger-Crittenden Co., 
    81 Minn. 356
    , 358, 
    84 N.W. 48
    , 49 (1900).
    3
    Effective August 1, 2011, 
    Minn. Stat. § 572.08
    -.30 (2010) were repealed and replaced
    by substantially similar provisions in Minn. Stat. § 572B.01-.30 (2012). Act of April 22,
    2010, ch. 264, art. 1, §§ 7, 15, 23, 32-33, 
    2010 Minn. Laws 499
    , 501-02, 505, 508-09. As
    the supreme court noted in Seagate I, however, the repealed provisions continue to
    govern this case because this arbitration began in October 2006. 854 N.W.2d at 754 n.1
    (citing Minn. Stat. § 572B.30 (2012), which provides that the provisions in section 572B
    are inapplicable to an arbitration that began before August 1, 2011).
    8
    Here, the arbitrator’s interim award reserved and sought the parties’ briefing on
    the issue of pre-award interest. Until the arbitrator issued the final award, neither party
    could have sought confirmation of the award.
    We conclude that the arbitrator did not decide the issue of post-award interest.
    IV.    
    Minn. Stat. § 549.09
     provides for post-award interest on the amount of the
    entire final award.
    Because we conclude that the arbitrator did not decide post-award interest, we
    next consider whether Seagate is entitled to post-award interest and, if so, how interest is
    properly calculated on these facts.
    Seagate argues that it is entitled to post-award interest on the sum of the
    compensatory-damages award plus the interest awarded by the arbitrator’s final award.
    Western argues that Seagate is not entitled to “interest on interest” under 
    Minn. Stat. § 549.09
    , that the final award determined post-award interest, and that the final award has
    been paid in full.
    
    Minn. Stat. § 549.09
    , subd. 1(a) provides, in relevant part: “When a judgment or
    award is for the recovery of money . . . interest from the time of the . . . award . . . until
    judgment is finally entered shall be computed by the court administrator or arbitrator . . .
    and added to the judgment or award.” Subdivision 1(c)(2) provides: “For a judgment or
    award over $50,000 . . . the interest rate shall be ten percent per year until paid.” Under
    the plain language of the statute, post-award interest is mandatory (“shall”) and must be
    calculated at a rate of ten percent. The remaining issue is what constitutes the “award” to
    which the post-award interest should be added.
    9
    Under Minnesota law, an award includes damages and pre-award interest. The
    Minnesota Supreme Court has held that preverdict interest “is an element of damages
    awarded to provide full compensation by converting time-of-demand . . . damages into
    time-of-verdict damages.” Lienhard v. State, 
    431 N.W.2d 861
    , 865 (Minn. 1988). The
    supreme court has also held that prejudgment interest is an element of compensatory
    damages in the context of underinsured motorist coverage policy limits. Lessard v.
    Milwaukee Ins. Co., 
    514 N.W.2d 556
    , 558 (Minn. 1994). And we have held the same
    concerning statutory limits on tort-damages awards. Myers v. Hearth Techs., Inc., 
    621 N.W.2d 787
    , 794 (Minn. App. 2001), review denied (Minn. Mar. 13, 2001). Just last
    year, we held that “[b]ecause preverdict interest is part of compensatory damages, it is
    part of a prevailing party’s judgment or award” under the language of 
    Minn. Stat. § 549.09
    , subd. 1(a). Hogenson v. Hogenson, 
    852 N.W.2d 266
    , 276 (Minn. App. 2014).
    These cases establish that Minnesota courts have long considered an award to include
    damages plus pre-award interest, consistent with the plain language of 
    Minn. Stat. § 549.09
    .
    Western argues that Hogenson is inapplicable because it involved a judicial
    proceeding, rather than arbitration.    Reliance on Hogenson is not necessary to our
    conclusion here, but we note that 
    Minn. Stat. § 549.09
     applies equally to awards and
    judgments. See 
    Minn. Stat. § 549.09
    , subd. 1(a) (“When a judgment or award is for the
    recovery of money. . . .”); 
    id.,
     subd. 1(b) (“[P]reverdict, preaward, or prereport interest
    . . . shall be computed.”). We rely on the plain language of the statute.
    10
    We note that the district court’s October 12, 2012 order accepted the approach we
    now adopt concerning the proper computation of interest. The figures in the district
    court’s footnote 2 of its October 12, 2012 memorandum of law cannot be replicated any
    other way. Footnote 2 reads: “The $525 Million award, plus the interest calculation of
    approximately $106 million, plus the interest accruing at more than $1.2 million per
    week, makes this award the largest ever in the U.S., according to defense counsel.” The
    $1.2 million per week interest figure can only be arrived at by using a principal amount
    of $630,431,501. See supra note 1. The dicta in our opinion and in the supreme court’s
    opinion in Seagate I apparently referred to this ongoing post-award interest, premised on
    the arbitrator not having determined post-award interest.          Closely examined, the
    procedural history, and even the reference to interest in the earlier decisions of all three
    courts in Seagate I, support our conclusion that the plain language of 
    Minn. Stat. § 549.09
    , as applied to the arbitrator’s final award, requires post-award interest to be
    calculated on the total amount of the arbitrator’s final award, including the computed pre-
    award interest.
    In sum, we conclude that the arbitrator did not decide the issue of post-award
    interest and that, under 
    Minn. Stat. § 549.09
    , Seagate is entitled to interest on the entire
    amount of the arbitrator’s award, $630,431,501, which is the sum of the compensatory-
    damages award plus pre-award interest. We therefore reverse the district court and
    remand for the entry of judgment consistent with this opinion.
    Reversed and remanded.
    11