in-the-matter-of-xcels-request-to-issue-renewable-development-fund-cycle-4 ( 2015 )


Menu:
  •                          This opinion will be unpublished and
    may not be cited except as provided by
    Minn. Stat. § 480A.08, subd. 3 (2014).
    STATE OF MINNESOTA
    IN COURT OF APPEALS
    A14-1006
    In the Matter of Xcel's Request to Issue Renewable
    Development Fund Cycle 4 Requests for Proposals and
    Petition for Approval of a Standard Grant Contract.
    Filed May 18, 2015
    Affirmed
    Hudson, Judge
    Minnesota Public Utilities Commission
    File No. E-002/M-12-1278
    David J. Zoll, Charles N. Nauen, Kristen G. Marttila, Lockridge Grindal Nauen, P.L.L.P.,
    Minneapolis, Minnesota; and
    Thomas Melone (pro hac vice), Ecos Energy LLC, Minneapolis, Minnesota (for relator
    Minnesota Go Solar, LLC)
    Michael C. Krikava, Thomas Erik Bailey, Kodi Jean Church, Briggs and Morgan, PA,
    Minneapolis, Minnesota; and
    Mara N. Koeller, Xcel Energy Inc., Minneapolis, Minnesota (for respondent Northern
    States Power Company, d/b/a Xcel Energy, Inc.)
    Lori Swanson, Attorney General, Anjali V. Shankar, Assistant Attorney General,
    St. Paul, Minnesota (for respondent Minnesota Public Utilities Commission)
    Considered and decided by Reyes, Presiding Judge; Hudson, Judge; and
    Stoneburner, Judge. ∗
    ∗
    Retired judge of the Minnesota Court of Appeals, serving by appointment pursuant to
    Minn. Const. art. VI, § 10.
    UNPUBLISHED OPINION
    HUDSON, Judge
    In this certiorari appeal, relator challenges respondent public utility commission’s
    denial, based on the recommendations of respondent utility, of relator’s application for a
    renewable-development-fund (RDF) grant. Relator argues that respondent commission
    (1) failed to follow the statutory funding directives of giving preference to the most cost-
    effective proposals and strongly considering the benefits to Minnesotans, (2) failed to
    address record evidence supporting relator’s application, and (3) did not accord relator
    due process. We affirm.
    FACTS
    In 1994, to promote renewable energy, the Minnesota legislature established the
    RDF to administer and distribute funds collected from the ratepayers of respondent
    Northern States Power Company, d/b/a Xcel Energy. See Minn. Stat. § 116C.779 (2014).
    The legislation requires Xcel to deposit funds into the RDF based on the volume of spent
    nuclear fuel maintained in Xcel’s nuclear-power plants.        Id., subd. 1.   Respondent
    Minnesota Public Utilities Commission (MPUC) approves grants for RDF funding after
    recommendations by Xcel, which consults with an advisory board on those
    recommendations. See id.
    In 2012, after a legislative audit report recommended changes to the RDF
    program, the Minnesota legislature amended the program’s governing statute. See 2012
    Minn. laws. ch. 196, § 1, at 276–77; Minn. Stat. § 116C.779. The amended statute
    provides that “[a] request for proposal [RFP] for renewable energy generation projects
    2
    must, when feasible and reasonable, give preference to projects that are most cost-
    effective for a particular energy source.” Minn. Stat. § 116C.779, subd. 1(h). It also
    provides that, in selecting projects for proposed funding, Xcel “must strongly consider,
    where reasonable, potential benefit to Minnesota citizens and the utility’s ratepayers.”
    Id., subd. 1(f). Xcel must use an independent third-party expert, along with the advisory
    board, to evaluate proposals submitted in response to an RFP. Id. The MPUC may
    disapprove recommended projects, but it cannot modify those selections without Xcel’s
    agreement. Id., subd. 1(e).
    In 2013, in response to Xcel’s RFP for the fourth RDF funding cycle, relator Go
    Solar, LLC, submitted a $7.4-million proposal for 20 one-megawatt solar projects at
    separate locations on the electrical grid in southeast and southwest Minnesota. The
    proposed project contemplated a long-term power purchase agreement (PPA) at Xcel’s
    project-avoided cost, with a fixed production incentive from solar renewable-energy
    credits over a 25-year term. It had stated goals of doubling Xcel’s solar generating
    capacity and creating a template for a solar renewable-energy-credit program.
    In the fourth funding cycle, Xcel received 46 proposals for energy-production
    projects, including Go Solar’s project, and 18 proposals for research-and-development
    (R&D) projects. The independent expert first reviewed and rated the proposals. The
    independent expert gave Go Solar’s proposal the highest total overall score, ranking it
    highest in terms of total jobs created and highest among energy-production projects for
    potential benefit to Minnesota and ratepayers, which was weighted 10% for energy-
    production projects and 40% for R&D projects. Go Solar asserts that it should have also
    3
    been ranked first in cost-effectiveness because it provided the best value per RDF grant
    dollar and was priced at avoided costs, which was lower than other solar-energy
    proposals, which were priced at net-metering, or retail, prices. But the independent
    expert used a different metric, total resource cost (TRC), and ranked Go Solar’s project in
    the midrange of energy-production proposals for cost effectiveness.
    The advisory board then reviewed a list of proposals, considering the independent
    expert’s evaluation as well as qualitative factors, including diversity in location, project
    types, and technology. Advisory board members noted that the independent expert rated
    Go Solar’s proposal high in every area; that it was a large project; that its “[p]rice was
    good”; and that its 25-year PPA was longer than typical 15-20 year PPAs. But advisory
    group members also expressed concerns that the proposed four-month timeline to
    negotiate PPAs was too short; that Go Solar was capable, but wished to negotiate one
    PPA for the entire project; that its site locations were open, which added uncertainty; that
    it was a “[g]ood, but very expensive project” and not suitable for RDF funding; and that
    the solar renewable-energy-credit proposal was “interesting, but . . . need[ed] more
    perspective.” The advisory group did not recommend Go Solar’s proposal to Xcel for
    funding.
    Xcel submitted an initial project selection report and two later supplemental
    reports to the MPUC, noting its agreement with the advisory group’s concerns. Go Solar
    filed a petition to intervene and requested a contested-case hearing, arguing that
    significant issues not addressed in the selection process could be resolved only through a
    contested-case hearing. The Minnesota Department of Commerce and other stakeholders
    4
    also filed comments. After an audit corrected technical scoring errors, which did not
    affect Go Solar’s proposal, Xcel filed reply comments with a selection-report summary
    and supplements for the MPUC review. Those comments observed that Go Solar had
    received the highest technical score of EP proposals, but also that
    [the project w]as disfavored by the advisory group as it would
    require too large of a portion of the funds anticipated to be
    awarded to EP projects (over a third of available funds). The
    energy price per kWh was high relative to other proposals and
    the locations for constructing the facilities were still open,
    which adds uncertainty.        From prior experience, RDF
    proposals that do not have specific sites identified or a very
    clear plan to identify sites have significant project delays.
    Further, the overall timeline proposed for the project was not
    long enough based on the Company’s prior experiences
    negotiating power purchase agreements for projects of the
    scale proposed.
    Xcel recommended funding for 13 EP projects, in amounts ranging from $310,310
    to $5,000,000. It recommended reserve funding for nine EP projects and no funding for
    24 EP projects, including Go Solar’s project.
    The MPUC issued a decision approving Xcel’s recommended projects and some
    of the reserve projects and denying Go Solar’s contested-case-hearing request. The
    MPUC found that the RFP had notified bidders that selections would be based both on
    the independent expert’s technical score and the advisory group’s subjective
    recommendations, which it deemed a reasonable approach “because it gave Xcel the
    necessary leeway to select a diverse mix of unique and innovative projects.” The MPUC
    found that the selected projects were likely to further RDF statutory goals by increasing
    the renewable-energy market penetration at reasonable costs; promoting the startup,
    5
    expansion, and attraction of renewable companies and projects in Minnesota; stimulating
    research and development in renewable technology; and developing demonstration-scale
    and near-commercial renewable electric generation projects. See Minn. Stat. § 116C.779,
    subd. 1(d) (stating those goals). However, based on comments and lessons learned in the
    RFP and selection process, the MPUC also required Xcel to make a “compliance filing”
    with proposals for improving transparency in the selection process. Go Solar requested
    reconsideration, which was denied. This certiorari appeal follows.
    DECISION
    This court may reverse, remand, or modify an administrative agency decision if
    that decision is, among other deficiencies, affected by legal error, unsupported by
    substantial evidence in the record as a whole, or arbitrary and capricious. 
    Minn. Stat. § 14.69
     (2014). Go Solar argues that the MPUC committed legal error by failing to
    properly follow the statutory directives for awarding RDF funds under Minn. Stat.
    § 116C.779, subd. 1(f), (h) (2014), and that the decision not to grant Go Solar RDF
    funding was arbitrary and capricious and unsupported by substantial evidence.
    I
    Consideration of factors not in statute
    Go Solar argues that in selecting RDF projects based on Xcel’s recommendations,
    Xcel and the MPUC impermissibly considered factors not specifically listed in Minn.
    Stat. § 116C.779. Generally, an agency’s decision is presumed correct, and this court
    affords deference to an agency in its field of expertise. Reserve Mining Co. v. Herbst,
    
    256 N.W.2d 808
    , 824 (Minn. 1977). But we review matters of statutory interpretation
    6
    de novo. In re Application of N. State Power Co. for Approval of its 1998 Res. Plan, 
    604 N.W.2d 386
    , 390 (Minn. App. 2000), review denied (Minn. Mar. 28, 2000). Nonetheless,
    “when a statute is couched in general terms, the agency is left the duty of determining
    precisely what standards will fulfill the . . . policy enunciated by the legislature.” 
    Id.
    (quotation omitted).
    If a statute’s plain language is clear, this court applies that language.      In re
    Application of Minn. Power, 
    838 N.W.2d 747
    , 754 (Minn. 2013). We construe the
    statute as a whole, giving effect to all of its provisions, and consider its words and
    sentences in light of their context. Id.; see also 
    Minn. Stat. § 645.16
     (2014). We apply
    canons of construction to discern a statute’s meaning only if the statute is ambiguous,
    which occurs if the text is subject to more than one reasonable interpretation. Billion v.
    Comm’r of Revenue, 
    827 N.W.2d 773
    , 777 (Minn. 2013); Brayton v. Pawlenty, 
    781 N.W.2d 357
    , 363 (Minn. 2010).
    By statute, “[an RFP] for renewable energy generation projects must, when
    feasible and reasonable, give preference to projects that are most cost-effective for a
    particular energy source.” Minn. Stat. § 116C.779, subd. 1(h). And “in evaluating
    responses to [RFPs], the public utility must strongly consider, where reasonable, potential
    benefit to Minnesota citizens and businesses and the utility’s ratepayers.” Id., subd. 1(f).
    Go Solar argues that under the principle of expressio unius est exclusio alterius, the
    statutory expression of preferences for cost-effective projects and projects providing the
    most benefits to Minnesotans indicates that the legislature meant to exclude other non-
    enumerated factors in awarding RFP grants.
    7
    The canon of statutory construction, expressio unius est exclusio alterius, means
    that “the expression of one thing is the exclusion of another.” State v. Caldwell, 
    803 N.W.2d 373
    , 383 (Minn. 2011). “Expressio unius generally reflects an inference that any
    omissions in a statute are intentional.” 
    Id.
     Go Solar notes this court’s decision affirming
    the exclusion of fair-market value evidence in an eminent-domain damages award, in
    which we concluded that statutory language stating that the district court “must include”
    four specific damages factors limited the court’s consideration to only those factors. City
    of Moorhead v. Red River Valley Coop. Power Ass’n, 
    811 N.W.2d 151
    , 160 (Minn. App.
    2012) (quotation omitted), aff’d, 830 N.W.2d. 32 (Minn. 2013). But the Minnesota
    Supreme Court, although affirming our decision, concluded that, because the statute
    listed “other appropriate factors” as one of the four enumerated factors, it did not support
    an inference that the district court was to limit consideration of relevant evidence. City of
    Moorhead, 830 N.W.2d at 39 (quotation omitted). Similarly, here, we conclude that the
    statutory language, “when feasible and reasonable” and “where reasonable” modifies the
    enumerated preferences and indicates unambiguously that those preferences are not
    exclusive, so that the doctrine of expressio unius does not apply.         See Minn. Stat.
    § 116C.779, subd. 1(h), (f); see also In re PERA Police & Fire Plan Line of Duty
    Disability Benefits of Brittain, 
    724 N.W.2d 512
    , 516 (Minn. 2006) (“If the statute is not
    ambiguous, the inquiry ends there.”) Therefore, Xcel and the MPUC did not err by
    considering additional factors in the RDF decision-making process.
    8
    Failure to sufficiently address statutory preferences
    Go Solar argues that, even if the statute permits the MPUC to consider additional
    factors, its decision was arbitrary and capricious because it failed to “strongly consider”
    benefits to Minnesotans and “give preference” to the most cost-effective project for a
    particular energy source. See Minn. Stat. § 116C.779, subd. 1(h), (f); see also In re
    Petition of S.G., 
    828 N.W.2d 118
    , 124 (Minn. 2013) (defining to “consider” as “to think
    carefully and form an opinion about,” and “preference,” as “[the] select[ion of] . . .
    someone or something over another or others”) (quotation omitted).
    An agency decision is arbitrary and capricious “if the agency (a) relied on factors
    not intended by the legislature; (b) entirely failed to consider an important aspect of the
    problem; (c) offered an explanation that runs counter to the evidence; or (d) [made a]
    decision [that] is so implausible that it could not be explained as a difference in view or
    the result of the agency’s expertise.” Citizens Advocating Responsible Dev. v. Kandiyohi
    Cnty. Bd. of Comm’rs, 
    713 N.W.2d 817
    , 832 (Minn. 2006). But “[i]f there is room for
    two opinions on a matter, the [agency] decision is not arbitrary and capricious, even
    though the court may believe that an erroneous conclusion was reached.” In re Review of
    2005 Annual Automatic Adjustment of Charges for All Elec. & Gas Utils., 
    768 N.W.2d 112
    , 120 (Minn. 2009).
    Go Solar first argues that the MPUC’s decision is arbitrary and capricious because
    it failed to refer to the cost-effectiveness preference.       See Minn. Stat. § 116C.779,
    subd. 1(h). But the MPUC’s failure to articulate that preference in its decision does not
    mean that the agency did not consider it in the decision-making process. Cf. Save Mille
    9
    Lacs Sportfishing, Inc., v. Minn. Dep’t of Natural Res. 
    859 N.W.2d 845
    , 851 (Minn. App.
    2015) (holding that the absence of a citation to or analysis of a relevant constitutional or
    common-law principle by an administrative agency in rulemaking does not provide
    grounds for declaring the rule invalid in a pre-enforcement challenge). As Xcel points
    out, the RFP required a cost-effectiveness assessment of all projects, which evaluated
    consideration of cost effectiveness at 30% in scoring EP projects, such as Go Solar’s.
    And Go Solar’s assertion that it was ranked first in cost-effectiveness is inaccurate
    because it used a standard different from that outlined in the RFP and used by the
    independent expert. In fact, Go Solar was not ranked first in cost-effectiveness and
    would not have been entitled to a statutory preference based on that criterion.
    Go Solar also argues that the RFP decision-making process did not independently
    address and “strongly consider” whether the selected projects maximized benefits to
    Minnesotans, Minn. Stat. § 116C.779, subd. 1(f), but instead placed too much weight on
    “other ad hoc factors,” such as a developer’s financial and technical credibility and a
    project’s location in a diverse community. Go Solar argues that allowing unquantifiable
    criteria to trump this stated statutory criterion, which relates mainly to economic benefits,
    effectively renders the 2012 statutory changes meaningless.         But the current statute
    provides that RDF funds may be used for “any of the following purposes,” including the
    broad purpose of “promot[ing] the start-up, expansion, and attraction of renewable
    electric energy projects and companies within the state.”         Minn. Stat. § 116C.779,
    subd. 1(d)(2).   It also provides that the MPUC may disapprove any proposed
    expenditures that it finds “to [not be] in compliance with [the RDF] statute or otherwise
    10
    not in the public interest.” Id., subd. 1(e). Therefore, read as a whole, the RDF statutory
    framework affirmatively allows public-interest factors to weigh in the selection process.
    Further, we defer to the agency’s interpretation of general statutory standards
    enunciated by the legislature. Application of N. States Power Co., 604 N.W.2d at 390.
    To that end, the RFP specifies broad criteria for assessing a project’s potential benefits to
    Minnesota and ratepayers, including job creation and fiscal benefits, in addition to
    addressing barriers to market development, such as issues of utility integration, location
    constraints, socioeconomic constraints, and the novelty of the proposal.           Thus, in
    selecting projects for RDF funding, Xcel and the MPUC properly considered qualitative
    factors such as diversity of project type, location, and technology; innovation; benefit to
    increasing renewable market penetration; cost; practicality; and value to ratepayers in
    Minnesota and Wisconsin. Consideration of these factors was appropriate and does not
    render the MPUC’s decision arbitrary and capricious.
    Conflicts of interest
    Go Solar maintains that, because individual advisory-group members were
    allowed to consider recommendations relating to their own projects, the MPUC’s
    decision was arbitrary. Go Solar argues that, although several advisory-group members
    were recused from assigned review of their sponsored projects, disclosure of conflicts is
    meaningless if an interested person is not entirely recused from the decision-making
    process.
    We recognize Go Solar’s concern. But the structure of the RDF selection process
    requires Xcel to consult with an advisory group that includes ratepayer representatives
    11
    and may also include representatives of “other interests.”       Minn. Stat. § 116C.779,
    subd. 1(f). To obtain the required expertise for project review, Xcel necessarily recruited
    advisory-group members with experience in the emerging renewable-energy field.
    Moreover, the advisory board operated by consensus, which minimized the role of
    possible conflicts of interest. Further, because Xcel “has . . . sole authority to determine
    which expenditures shall be submitted . . . for commission approval,” id., Xcel was free
    to reject advisory-board input with which it disagreed. Go Solar points out that Xcel
    requested a substantial award for its own proposal. But the statute expressly designates
    Xcel eligible to apply for RDF funding. Id., subd. 1(d). We also note that the MPUC
    ordered verification of the independent expert’s scoring and required Xcel to explain in
    reply comments why its selections deviated from the independent expert’s project
    rankings. We therefore conclude that advisory-group conflicts of interest did not render
    the MPUC’s decision arbitrary and capricious.
    II
    Go Solar argues that the MPUC’s decision on funding allocations was
    unsupported by substantial evidence because it is unreasonable based on the record. An
    agency decision is supported by substantial evidence if it “is supported by such relevant
    evidence as a reasonable mind might accept as adequate to support the conclusion.”
    Minn. Ctr. for Envtl. Advocacy v. Minn. Pollution Control Agency, 
    644 N.W.2d 457
    , 468
    (Minn. 2002). Substantial evidence has been defined as “(1) such relevant evidence as a
    reasonable mind might accept as adequate to support a conclusion; (2) more than a
    scintilla of evidence; (3) more than some evidence; (4) more than any evidence; or (5) the
    12
    evidence considered in its entirety.” 
    Id. at 466
    . The objecting party has the burden to
    show that the agency’s findings are not supported by evidence on the record. Herbst, 256
    N.W.2d at 825. In assessing whether the substantial-evidence standard has been met, we
    “determine whether the agency has adequately explained how it derived its conclusion
    and whether that conclusion is reasonable on the basis of the record.” Application of
    Minn. Power, 838 N.W.2d at 757 (quotation omitted).
    Timeline and site selection
    Go Solar argues that the record lacks a basis for Xcel’s articulated concerns
    relating to Go Solar’s inability to negotiate a PPA within its four-month stated timeline
    and to secure site locations. But Xcel’s reply comments note the proposal’s large scale
    and Go Solar’s prior experience in negotiating PPAs for projects of that scale. The
    advisory board also indicated that Go Solar wished to negotiate one PPA for the entire
    20-site project. And although Go Solar points out that its proposal contained designated
    site locations, it acknowledges that no specific leases or purchases had been negotiated at
    those locations. The record thus provides a reasonable basis for rejecting Go Solar’s
    proposal, based on concerns about its ability to execute the project as proposed.
    Cost effectiveness
    Go Solar challenges Xcel’s reply comment that Go Solar’s “energy price per kWh
    was high relative to other EP proposals.” The independent expert ranked Go Solar’s
    proposal in the mid-range for cost effectiveness, based on a metric of total resource cost,
    which was calculated using information on initial capital costs, a PPA negotiated with
    Xcel, and projected energy production. Go Solar argues that the TRC metric did not
    13
    properly measure its project’s cost-effectiveness because electricity from the solar
    projects could be sold at Xcel’s avoided costs. Xcel acknowledges that the TRC metric
    omits some projected factors; we defer, however, to the independent expert’s use of that
    measurement to evaluate a project’s cost-effectiveness. See Herbst, 256 N.W.2d at 824
    (stating that “deference should be shown by courts to the agencies’ expertise and their
    special knowledge in the field of their technical training, education, and experience”).
    And we reject Go Solar’s argument that the TRC for its project was inaccurate because
    Go Solar could have entered a PPA at Xcel’s avoided cost, rather than at higher preferred
    rates. The RFP notified Go Solar, like all grant applicants, that its project would be
    evaluated using a uniform measurement, and the record does not support a reasonable
    inference that its costs were measured unfairly relative to those of other projects. We
    also reject Go Solar’s contention that Xcel was required to evaluate cost effectiveness in
    proportion to the amount of grant funds Go Solar requested, rather than the total cost of
    its project.
    Additional criteria
    Go Solar points out that the independent expert scored its proposal highest in jobs
    created and local economic impact; it also contends that its proposal lacks many of the
    negative features of projects selected for funding. But Go Solar’s ability to identify some
    qualities that distinguish its project from approved projects, and some qualities that it
    shares with approved projects, does not alone determine whether the MPUC’s decision is
    arbitrary and capricious or unsupported by substantial evidence. See Review of 2005
    14
    Annual Automatic Adjustment of Charges, 768 N.W.2d at 120 (stating that an agency
    decision is not arbitrary if room exists “for two opinions on a matter”).
    Xcel articulated specific reasons for not recommending Go Solar’s proposal for
    funding: its overall project cost, which would require over a third of the funds available
    for EP projects; its high price relative to other EP proposals; uncertainty about securing
    site locations; and the overall proposed timeline for negotiating PPAs. The MPUC
    recognized that Xcel considered a “voluminous selection record” that fully explained its
    evaluation process, which used technical scores as a baseline and then applied other
    qualitative criteria. The MPUC found that “[w]here Xcel’s recommendations deviated
    from the Independent Evaluator’s rankings, Xcel explained its choices in sufficient
    detail,” and that the approach of selecting projects based on both technical scores and
    subjective recommendations “was reasonable because it gave Xcel the necessary leeway
    to select a diverse mix of unique and innovative projects.” Xcel and the MPUC fully
    explained the decision not to recommend or fund Go Solar’s project, and based on the
    record, substantial evidence supports that decision. See Application of Minn. Power, 838
    N.W.2d at 757 (noting that an agency must “adequately explain[] how it derived its
    conclusion,” which must be “reasonable on the basis of the record” (quotation omitted)).
    III
    Go Solar argues that it should have been afforded a contested-case hearing or
    similar due process to address material disputed facts. The MPUC must hold a contested-
    case hearing if a matter “involves contested material facts and there is a right to a hearing
    under statute or rule, or if the commission finds that all significant issues have not been
    15
    resolved to its satisfaction.” 
    Minn. R. 7829
    .1000 (2013). A relator who requests a
    contested-case hearing has the burden to show the existence of material facts that would
    assist the agency in making its decision. In re Petition of N. States Power Co., 
    676 N.W.2d 326
    , 335 (Minn. App. 2004). The MPUC denied Go Solar’s request for a
    contested-case hearing, finding that no disputed material facts warranted a contested case
    and that further factual development would not assist the agency in making its decision.
    No statute entitled Go Solar to a contested-case hearing on its RDF proposal. And
    absent statutory authority, an agency hearing is “a necessary prerequisite to determining
    [a party’s] legal rights, duties, and privileges only if it is required by the due process
    provisions of the State and Federal Constitutions.” Indep. Sch. Dist. No. 581 v. Mattheis,
    
    275 Minn. 383
    , 386, 
    147 N.W.2d 374
    , 376 (1966). Go Solar cannot demonstrate a
    property interest in obtaining RDF funding and therefore cannot assert a due-process
    right to a contested-case hearing. See In re Implementation of Util. Energy Conservation
    Improvement Programs, 
    368 N.W.2d 308
    , 313 (Minn. App. 1985) (holding that a utility
    customer had no property right in existing utility rates and thus no right to a contested-
    case proceeding).
    Go Solar argues that it should have been afforded the opportunity to challenge
    Xcel’s recommendation through discovery and cross-examination because the MPUC
    failed to consider relevant and probative information that could have affected the
    outcome of the proceeding.     In particular, Go Solar challenges the rejection of the
    independent expert’s top ranking of its proposal. But the record shows that Go Solar had
    sufficient notice of the RDF process and ample opportunity to present evidence
    16
    supporting its project. 1 The MPUC reasonably determined that it could address the
    proposals based on the extensive record, which included numerous comments and Go
    Solar’s objections to the advisory board’s and Xcel’s recommendations. The MPUC did
    not err by declining to order a contested-case hearing.
    Affirmed.
    1
    On September 12, 2013, Go Solar filed a petition to intervene, initial comments and
    request for a contested-case proceeding. Go Solar filed additional comments on
    December 12, 2013, and December 31, 2013, respectively. The matter came before the
    MPUC on January 23, 2014, and Go Solar made an oral presentation.
    17