Bertram Hill v. City of Horn Lake, Mississippi , 160 So. 3d 671 ( 2015 )


Menu:
  •                     IN THE SUPREME COURT OF MISSISSIPPI
    NO. 2012-CA-01748-SCT
    BERTRAM HILL, INDIVIDUALLY, JENANNE
    MOONEYHAN AND RACHAEL PHILLIPS, AS
    WRONGFUL DEATH BENEFICIARIES OF
    DAVID MOONEYHAN
    v.
    CITY OF HORN LAKE, MISSISSIPPI
    DATE OF JUDGMENT:                          10/04/2012
    TRIAL JUDGE:                               HON. ROBERT P. CHAMBERLIN
    COURT FROM WHICH APPEALED:                 DESOTO COUNTY CIRCUIT COURT
    ATTORNEYS FOR APPELLANTS:                  JOHN THOMAS LAMAR, III
    JOHN THOMAS LAMAR, JR.
    JOSEPH HARLAND WEBSTER
    RALPH EDWIN CHAPMAN
    ATTORNEY FOR APPELLEE:                     ROY JEFFERSON ALLEN
    NATURE OF THE CASE:                        CIVIL - PERSONAL INJURY
    DISPOSITION:                               AFFIRMED - 01/15/2015
    MOTION FOR REHEARING FILED:
    MANDATE ISSUED:
    EN BANC.
    COLEMAN, JUSTICE, FOR THE COURT:
    ¶1.    The City of Horn Lake (“the City”) contracted with Phillips Construction Company
    and its owner Michael Phillips (collectively “Phillips”) to work on a sewer project. Two
    employees of Phillips, Bertram Hill and David Mooneyhan, were working near the bottom
    of a trench that was seventeen feet deep when the walls of the trench suddenly collapsed.
    Mooneyhan was killed, and Hill was injured. Mooneyhan’s beneficiaries and Hill
    (collectively “Plaintiffs”) sued the City for Phillips’s negligence under respondeat superior
    and also alleged that the City had negligently hired Phillips. The circuit court properly
    granted summary judgment in favor of the City, and we affirm.
    Facts and Procedural History
    ¶2.    On October 28, 2008, a trench being constructed in connection with the City’s Chapel
    Hill Sewer Installation Project (“project”) collapsed on itself, causing serious injury to
    Bertram Hill and death to David Mooneyhan. Two city employees who were at the site to
    deliver supplies witnessed the event. Hill and Mooneyhan had been performing work near
    the bottom of the trench as part of their employment with Phillips. Phillips did not have
    general liability insurance coverage at the time of the trench collapse. Since that time, OSHA
    has investigated Phillips for possibly violating federal regulations in connection with its work
    on the project.
    ¶3.    Phillips and the City never reduced to writing the agreement for the project’s
    completion, but the record provides ample information about the agreement. The project was
    to be completed on a cost-plus basis, and Phillips ultimately requested $9,678 for its work.1
    Interrogatory responses from Phillips and depositions of Calvin Shields, the City’s Director
    of Operations, shed additional light on the nature of the agreement. Via interrogatory
    responses, Phillips testified that his company was an independent contractor for the City and
    1
    The fact that the contract was “cost-plus” indicates that, had Phillips determined
    additional materials were needed, it would have been able to purchase the materials and then
    bill the City for them. The invoice Phillips submitted to the City stated that the price
    included “all material for complete job, all equipment and labor on what part was completed
    including time and equipment on engineering part.” However, in the aftermath of the
    collapse, the City hired another construction company to complete the project. While the
    City paid Phillips only $9,678, the total cost of the project was approximately $34,000 once
    the second construction company was paid.
    2
    that the City did not participate in the construction or direct the manner or means by which
    the work was done. Shields testified that the City would inspect the site only if the contractor
    requested an inspection. Shields testified that city employees had visited the site only twice
    during the course of the project.
    ¶4.    Plaintiffs filed a complaint against the City on August 4, 2009, alleging that the City
    was liable for Phillips’s negligence on the basis of respondeat superior and also for its own
    negligence in maintaining the site. On February 9, 2012, the City moved for summary
    judgment on the following grounds: (1) Plaintiffs contended that Hill and Mooneyhan were
    employees of the City, thus rendering their claims subject to the exclusive remedy provision
    found in the Mississippi Workers’ Compensation Act; (2) Phillips was an independent
    contractor, not an agent, so the City could not be liable to Plaintiffs under respondeat
    superior; and (3) the discretionary function exemption of the Mississippi Tort Claims Act
    (“MTCA”) rendered the City immune from liability for maintenance of a sewer system.
    ¶5.    In response to the City’s motion for summary judgment, Plaintiffs admitted that Hill
    and Mooneyhan were not employees of the City, thus rendering the City’s defense under the
    Mississippi Workers’ Compensation Act moot. Plaintiffs argued that the City was not
    immune from liability under the discretionary function exemption because the City still had
    a duty to warn of dangerous conditions. Finally, they added that the City was liable under
    Mississippi Code Section 31-5-51(7), which requires any person entering into a formal
    contract with a city that exceeds $25,000 to furnish proof of general liability insurance
    coverage. Miss. Code Ann. § 31-5-51(7) (Rev. 2010). The City argued that the statute was
    inapplicable because the contract amount was only $9,678, well below the $25,000 threshold.
    3
    ¶6.    The circuit court granted the City’s motion for summary judgment on all issues,
    holding that Plaintiffs had not established the City had more than a supervisory role over the
    project, that the City’s maintenance of a sewer system is a discretionary function, and that
    the burden under Mississippi Code Section 31-5-51(7) is placed on the contractor, not the
    City. Plaintiffs appealed.
    ¶7.    We requested supplemental briefing from the parties on the following issues: (1)
    whether the contract, if any, between Horn Lake and Phillips was void and unenforceable as
    a matter of public policy because it was formed in violation of Mississippi Code Section 31-
    7-13; (2) whether the existence of an enforceable contract is a prerequisite for the existence
    of independent-contractor status for the purposes of determining whether Horn Lake is
    vicariously liable for the negligence, if any, of Phillips; and (3) whether the Court’s opinion
    in Little v. Mississippi Department of Transportation, 
    129 So. 3d 132
    (Miss. 2013), has any
    effect on whether Horn Lake enjoyed discretionary immunity.
    Standard of Review
    ¶8.    The standard of review for a grant or denial of summary judgment is de novo.
    Ladnier v. Hester, 
    98 So. 3d 1025
    , 1027-28 (¶ 9) (Miss. 2012). Courts determine whether
    summary judgment is proper by considering whether “the pleadings, depositions, answers
    to interrogatories and admissions on file, together with the affidavits, if any, show that there
    is no genuine issue as to any material fact and that the moving party is entitled to judgment
    as a matter of law.” Miss. R. Civ. P. 56(c). A fact is material if it “tends to resolve any of
    the issues properly raised by the parties.” Moss v. Batesville Casket Co., 
    935 So. 2d 393
    ,
    398 (¶ 16) (Miss. 2006). Issues of fact exist when one can draw more than one reasonable
    4
    inference from uncontradicted facts. 
    Ladnier, 98 So. 3d at 1029
    (¶ 14). The moving party
    has the burden of demonstrating the absence of a genuine issue of material fact. 
    Id. at 1028
    (¶ 10). If there is any doubt as to the existence of a genuine issue of material fact, the benefit
    goes to the nonmoving party. 
    Id. at (¶
    9). However, the nonmoving party may not rest on
    mere allegations or denials in the pleadings, but must set forth specific facts showing that
    there are genuine issues for trial. Pigg v. Express Hotel Partners, LLC, 
    991 So. 2d 1197
    ,
    1199 (¶ 4) (Miss. 2008).
    Discussion
    ¶9.    The DeSoto County Circuit Court granted the City’s motion for summary judgment
    on the following grounds: the City had no liability under respondeat superior; the City was
    exempt from liability because the maintenance of a sewer is a discretionary function; and the
    City was not liable for negligence in hiring Phillips. Plaintiffs raise the following issues on
    appeal: (1) whether the circuit court erred by holding that the City cannot be vicariously
    liable for the actions of Phillips because Phillips was an independent contractor; (2) whether
    the circuit court erred by dismissing Plaintiffs’ negligent hiring and per se negligence claims
    by ruling that the City has no liability under Mississippi Code Section 31-5-51(7); and (3)
    whether the circuit erred by dismissing the City as a defendant based on the discretionary
    function of the MTCA. Additionally, in response to the parties’ supplemental briefs, the
    Court finds it appropriate to discuss whether the contract, if any, between Horn Lake and
    Phillips was void and unenforceable as a matter of public policy because it was formed in
    violation of Mississippi Code Section 31-7-13.
    5
    I. Whether the circuit court erred by holding that the City cannot be
    vicariously liable for the actions of Phillips because Phillips was an
    independent contractor.
    ¶10.   The City may be vicariously liable for Phillips’s negligence if there was a master-
    servant relationship between the two entities when the trench collapsed. See Richardson v.
    APAC-Miss., Inc., 
    631 So. 2d 143
    , 151 (Miss. 1994). However, the City may not be
    vicariously liable for Phillips’s negligence if Phillips was merely an independent contractor
    of the City. See Hodges v. Attala County, 
    42 So. 3d 624
    , 626 (¶ 6) (Miss. Ct. App. 2010).
    Plaintiffs would bear the burden at trial of proving the City vicariously liable for Phillips’s
    negligence, if any, and accordingly bear the burden here of producing evidence to
    demonstrate the existence of a disputed material fact on the issue. Webster v. Miss.
    Publishers Corp., 
    571 So. 2d 946
    , 949 (Miss. 1990); Fruchter v. Lynch Oil Co., 
    522 So. 2d 195
    , 198 (Miss. 1988).
    ¶11.   A servant is “a person employed by a master to perform service in his affairs whose
    physical conduct in the performance of the service is controlled or is subject to the right to
    control by the master.” 
    Richardson, 631 So. 2d at 148
    . An independent contractor is
    defined as “a person who contracts with another to do something for him but who is not
    controlled by the other nor subject to the other’s right to control with respect to his physical
    conduct in the performance of the undertaking.” 
    Id. In short,
    the difference between a
    master-servant relationship and an independent-contractor relationship is that an employer
    in a master-servant relationship has control of, or the right to control, the employee in the
    details of the work. See Miller v. R.B. Wall Oil Co., Inc., 
    970 So. 2d 127
    , 132 (¶ 15) (Miss.
    2007); Stewart v. Lofton Timber Co., LLC, 
    943 So. 2d 729
    , 734 (¶ 15) (Miss. 2006). In
    6
    determining whether an employer has the right of control over the employee, the Court
    should consider what the employer was entitled to do under the contract, as opposed to what
    the employer actually did. 
    Richardson, 631 So. 2d at 150
    (quoting Kisner v. Jackson, 
    159 Miss. 424
    , 
    132 So. 90
    , 92 (1931)).
    ¶12.   That Phillips and the City understood their relationship to be that of an independent
    contractor is not controlling. An employer may not escape liability to adversely affected
    third parties by drafting a contract that labels its employee an independent contractor.
    McCary v. Wade, 
    861 So. 2d 358
    , 363 (¶ 12) (Miss. Ct. App. 2003) (quoting McKee v.
    Brimmer, 
    39 F.3d 94
    , 98 (5th Cir. 1994)). Therefore, the Court must consider whether the
    facts of the case – taken in a light most favorable to Plaintiffs – trigger a master-servant
    relationship.
    ¶13.   The distinction between a servant and an independent contractor is a difficult one to
    make and has been described by the Court as “elusive.” 
    Richardson, 631 So. 2d at 148
    (citation omitted)). However, the Court has provided the following factors to consider in
    determining whether a person is an independent contractor:
    [(1)] Whether the principal master has the power to terminate the contract at
    will; [(2)] whether he has the power to fix the price in payment for the work,
    or vitally controls the manner and time of payment; [(3)] whether he furnishes
    the means and appliances for the work; [(4)] whether he has control of the
    premises; [(5)] whether he furnishes the materials upon which the work is done
    and receives the output thereof, the contractor dealing with no other person in
    respect to the output; [(6)] whether he has the right to prescribe and furnish the
    details of the kind and character of the work to be done; [(7)] whether he has
    the right to supervise and inspect the work during the course of the
    employment; [(8)] whether he has the right to direct the details of the manner
    in which the work is to be done; [(9)] whether he has the right to employ and
    discharge the subemployees and to fix their compensation; and [(10)] whether
    he is obliged to pay the wages of said employee.
    7
    
    Richardson, 631 So. 2d at 148
    -49 (quoting 
    Kisner, 132 So. at 91
    ); see also Heirs &
    Wrongful Beneficiaries of Branning ex rel. Tucker v. Hinds Cmty. Coll. Dist., 
    743 So. 2d 311
    , 316-17 (¶ 29) (Miss. 1999).
    ¶14.   Plaintiffs have not produced evidence sufficient to create an issue of material fact as
    to whether the City is vicariously liable for Phillips. Plaintiffs and the City agree that the
    workers on the project were Phillips’s employees, not the City’s. Further, Phillips was
    responsible for obtaining its own equipment to complete the project. Even though the City
    reimbursed Phillips for the expense of renting the equipment, the record does not indicate
    that Phillips had anything but full discretion in choosing the equipment used for the project.
    In response to the City’s request for admission, Phillips also admitted that the City did not
    assist in construction. The City’s Director of Operations testified that city employees made
    only two visits to the site before the trench collapsed and that it was Phillips’s responsibility
    to request inspections.
    ¶15.   While the City may have had the right to inspect the site more frequently than it did,
    the right to inspect, in itself, is not sufficient to trigger a master-servant relationship. See
    Chisolm v. Miss. Dep’t of Transp., 
    942 So. 2d 136
    , 141 (¶ 8) (Miss. 2006) (holding that the
    parties had an independent-contractor relationship even though the contract authorized the
    defendant to inspect all work and materials); see also Casement v. Brown, 
    148 U.S. 615
    , 662
    (1893) (finding that the status of independent contractor was not affected by the fact that “the
    contract provided for their daily supervision and approval of both material and work”).
    ¶16.   However, Plaintiffs argue that the City was involved in the planning stage of the
    project. They point out that Phillips denied the City’s request to admit that the City did not
    8
    assist in the engineering, the “design and repair,” and the “preparation of specifications or
    drawings” of the project. Phillips also denied the request to admit that the City did not assist
    in decisions concerning the methods, dimensions, procedures, and depths of the project.
    However, involvement at the planning stage is not enough to trigger a master-servant
    relationship. See, e.g., 
    Chisolm, 942 So. 2d at 141-42
    (¶ 9) (“While the construction work
    had to comply with MDOT’s specifications and the traffic control plan . . . . [b]ased on the
    clear language of the contract, we agree . . . that Great River was an independent
    contractor.”).
    ¶17.   Further, denials of requests for admission do not have the same probative value as
    admissions. See Miss. R. Civ. P. 36(b) (“Any matter admitted under this rule is conclusively
    established unless the court on motion permits withdrawal or amendment of the admission.”).
    See also Young v. Smith, 
    67 So. 3d 732
    , 742-43 (¶ 22) (Miss. 2011); Shell Oil Co. v.
    Murrah, 
    493 So. 2d 1274
    , 1276-77 (Miss. 1986). Unlike admissions, denials in response to
    a request for admission are not competent summary judgment evidence. See Barragan v.
    Mosler, 
    872 S.W.2d 20
    , 22 (Tex. App. 1994); City of Richland Hills v. Bertelsen, 
    724 S.W.2d 428
    , 431 (Tex. App. 1987).
    ¶18.   In Chisolm v. Mississippi Department of Transportation, we held that an
    independent-contractor relationship existed, and the governmental body in that case exercised
    a greater amount of control than the City did here. See Chisolm, 
    942 So. 2d 136
    . In
    Chisolm, survivors of a driver killed in an automobile accident brought an action against the
    Mississippi Department of Transportation (“MDOT”) and the contractor hired by MDOT to
    replace a bridge with an underground box culvert. 
    Chisolm, 942 So. 2d at 139
    (¶ 2). The
    9
    contract between MDOT and the contractor allowed inspectors employed by MDOT to
    inspect all work done and the materials used, although they were not “to act as foreman for
    the contractor.” 
    Id. at 141
    (¶ 8). The contract also provided that the contractor’s work
    “consists of complying with the contract requirements of the Department’s Traffic Control
    Plan.” 
    Id. at 141
    (¶ 8). Nevertheless, the Court found the contractor in Chisolm to be an
    independent contractor, and not an employee, of MDOT. 
    Id. at 141
    (¶ 8).
    ¶19.   The Court of Appeals reached the same decision in Hodges v. Attala County. That
    case also involved a car accident in which the decedent crashed into a culvert at a
    construction site. 
    Hodges, 42 So. 3d at 624
    (¶ 1). The Court of Appeals found the contract
    language in Hodges to be substantially similar to the contract language in Chisolm. 
    Id. at 627
    (¶ 9). The contract, however, went further to state that the county engineer was to
    “insure the Contractor constructs, installs, and maintains the devices called for on the Traffic
    Control Plan.” 
    Id. at 627
    (¶ 9). The Court of Appeals found no Mississippi case regarding
    whether a general contractor obtains liability through the oversight of safety standards. 
    Id. at 627
    (¶ 11). However, the court noted that, in some cases, it “can look beyond the contract
    to determine whether public policy requires recharacterization of the relationship to allow
    the injured party to recover.” 
    Id. at 628
    (¶ 13) (quoting 
    Chisolm, 942 So. 2d at 142
    (¶ 10)).
    It went on to find that it would not serve public policy to impose liability on the county for
    addressing the issue of safety in its construction contracts. 
    Id. at 629
    (¶ 14). The court cited
    various cases to the same effect from foreign jurisdictions. See Koch Ref. Co. v. Chapa, 
    11 S.W.3d 153
    , 155 (Tex. 1999); LaChance v. Michael Baker Corp., 
    869 A.2d 1054
    , 1058 (Pa.
    10
    Commw. Ct. 2005); Ross v. Dae Julie, Inc., 
    793 N.E.2d 68
    , 72 (Ill. App. Ct. 2003); Jevons
    v. State, 
    2003 WL 1986977
    , 
    116 Wash. App. 1056
    (Wash. Ct. App. 2003).
    ¶20.   Chisolm and Hodges both evidence a stronger amount of control on the part of the
    governmental body over the respective contractors than is present in the instant case.
    However, both cases concluded that the relationship in question was that of an independent
    contractor. Therefore, as to the instant case, the amount of control demonstrated by
    Plaintiffs, standing alone, is insufficient to trigger the master-servant relationship.
    ¶21.   Additionally, we find it appropriate to discuss two sub-issues, which we asked the
    parties to address in their supplemental briefs: (1) whether the existence of an enforceable
    contract is a prerequisite for the existence of independent-contractor status and (2) whether
    the contract, if any, between the City and Phillips was void and unenforceable as a matter of
    public policy because it was formed in violation of Mississippi Code Section 31-7-13. These
    two sub-issues dovetail each other, because, as the Richardson factors quoted above
    demonstrate, the existence of a formal contract is but one factor in establishing independent-
    contractor status. 
    Richardson, 631 So. 2d at 148
    -49. In other words, though an important
    factor, the existence of a formal contract is not a prerequisite for a finding of independent-
    contractor status.
    ¶22.   As to any potential violation of the bidding requirements, Phillips correctly notes that
    judicial precedent in Mississippi has long held that “public boards speak only through their
    minutes and their actions are evidenced solely by entries on the minutes.” Thompson v.
    Jones County Cmty. Hosp., 
    352 So. 2d 795
    , 796 (Miss. 1977). Because the potential bidding
    requirements cited by Phillips require an examination as to what is and is not contained in
    11
    the City’s board minutes, the Court is unable to hold that a violation even occurred, as the
    board minutes are not in the record before the Court. See Miss. Code Ann. § 31-7-13 (Supp.
    2014).     Even considering, arguendo, that Phillips conclusively established a bidding
    violation, such a violation does not necessarily render the resulting contract void: “Any
    failure by the Board in this case to comply with the requirements of the bid purchase statutes
    constitutes at most a technical defect in the bid-letting process which did not render the
    resulting contract to [the defendant] void.” Huey Stockstill, Inc. v. Hales, 
    730 So. 2d 539
    ,
    543 (¶ 16) (Miss. 1998). Moreover, even assuming, again arguendo, that the resulting
    contract was made void by the bidding statutes, the existence of a contract is but one factor
    to consider in establishing independent-contractor status. 
    Richardson, 631 So. 2d at 148
    -49.
    Thus, the issue of any potential violation of the bidding statutes is moot for the purposes of
    the case sub judice.
    ¶23.     The dissent would rely upon a single factor, originally announced in Richardson v.
    APAC-Mississippi, Inc., 
    631 So. 2d 143
    , 150 (Miss. 1994), to hold that, despite otherwise
    being an independent contractor, Phillips should be treated as an employee. In Richardson,
    we announced a new factor in the balancing test we employ to determine the nature of an
    employment relationship for respondeat superior purposes.
    When a contract is made between two parties that as between themselves
    creates an independent contractor relationship and involves employment
    generally performed under a simple master/servant or employer/employee
    relationship, it will be upheld as between the parties. When, however, third
    parties are adversely affected, this Court will carefully scrutinize the contract
    to see if public policy should permit the transformation of an ordinarily
    employer/employee relationship into that of an independent contractor. A
    necessary condition precedent for the application of this factor, however, is
    that the party challenging the claimed relationship will be adversely affected,
    12
    and denied an adequate legal remedy. In the absence of this, the right of parties
    to contract as they please is a constitutionally-protected right.
    
    Id. We decline
    to apply the Richardson factor to convert Phillips’s independent-contractor
    status because Plaintiffs never presented the argument to the trial court for consideration.
    “[A] trial court will not be put in error on appeal for a matter not presented to it for decision.”
    Harrington v. Office of Miss. Sec’y of State, 
    129 So. 3d 153
    , 169 (¶ 40) (Miss. 2013).
    ¶24.   The grant of summary judgment was appropriate as to the issue of whether a master-
    servant relationship was formed in this case.          Phillips hired and supervised its own
    employees, rented its own equipment, and performed its work on the project without much
    supervision from city employees. The evidence relied upon by Plaintiffs to infer that the City
    was involved at the planning stage is not competent summary judgment evidence, nor is that
    sufficient involvement to infer a master-servant relationship. Therefore, we affirm the trial
    court’s grant of summary judgment on the vicarious liability issue.
    II. Whether the circuit court erred by dismissing Plaintiffs’ negligent hiring and
    per se negligence claims by ruling that the City has no liability under
    Mississippi Code Section 31-5-51(7).
    ¶25.   Plaintiffs assert that the City was per se negligent because it violated Mississippi Code
    Section 31-5-51(7). To prevail on a negligence per se claim, “a party must prove that he was
    a member of the class sought to be protected under the statute, that his injuries were of a type
    sought to be avoided, and that violation of the statute proximately caused his injuries.”
    Snapp v. Harrison, 
    699 So. 2d 567
    , 571 (¶ 22) (Miss. 1997) (citing Thomas v. McDonald,
    
    667 So. 2d 594
    , 597 (Miss. 1995)). Section 31-5-51(7) requires parties entering into a
    construction or public works contract with a municipality to furnish proof of general liability
    13
    insurance coverage if the contract exceeds $25,000. Miss. Code Ann. § 31-5-51(7) (Rev.
    2010).
    ¶26.     The contract between the City and Phillips for the completion of the project did not
    exceed $25,000. The City’s Director of Operations testified that, at the time of contracting,
    he estimated the cost of the project to be approximately $6,000, which is well below the
    $25,000 threshold. The invoice Phillips submitted to the City was for $9,678, also well
    below the amount needed for the statute to apply. The amount that the City ultimately paid
    another construction company, which has no relation to Phillips, is irrelevant. Because Hill
    cannot show he was a member of the class sought to be protected by Section 31-5-51(7), we
    affirm the trial court’s finding that the City was not liable under this statute.
    ¶27.     To address Plaintiffs’ arguments in full, we note that, even if the statute applied to this
    agreement, the City would not be liable because the statute places the burden on the
    contractor to furnish the insurance, not on the City to make sure that the insurer does so.
    Pidgeon Thomas Iron Co. v. Leflore County, 
    135 Miss. 155
    , 
    99 So. 677
    , 679 (1924).
    Plaintiffs suggest that the Court should not apply Pidgeon Thomas because that judgment
    was rendered in 1924 and did not involve a death, unlike the instant case. However, Pidgeon
    Thomas is still controlling precedent, and even though the instant case involved a death,
    there is no reason the Court should make an exception.
    ¶28.     Further, Plaintiffs have not established that there was legislative intent to create a
    private cause of action under which they may sue the City under Section 31-5-51. The Court
    will not find a private cause of action when there is no apparent legislative intent to establish
    one. Tunica County v. Gray, 
    13 So. 3d 826
    , 829 (¶¶ 16-17) (Miss. 2009) (“Unless the
    14
    legislative intent can be inferred from the language of the statute, the statutory structure, or
    some other source, the essential predicate for implication of a private remedy simply does
    not exist.”). As the party asserting a right of action, Plaintiffs have the burden of establishing
    the required legislative intent. 
    Id. at 829
    (¶ 16). Plaintiffs claim that the legislative intent
    behind Section 31-5-51(7) was to prevent physical injuries of the kind they suffered, but they
    cite no authority to support that claim.
    Conclusion
    ¶29.   The trial court correctly granted the City’s motion for summary judgment. Regarding
    vicarious liability, there is no genuine issue of material fact because Plaintiffs have not
    shown that the City exercised more than a supervisory role over the project, which is not
    sufficient to trigger a master-servant relationship. As to Mississippi Code Section 31-5-
    51(7), the City provided proof that the contract was for less than $25,000, so the statute does
    not apply. The Court’s finding that the trial court’s grant of summary judgment was proper
    on the aforementioned issues is dispositive, and we decline to address the discretionary
    function immunity issue.      Accordingly, we affirm the trial court’s grant of summary
    judgment in favor of the City.
    ¶30.   AFFIRMED.
    WALLER, C.J., DICKINSON AND RANDOLPH, P.JJ., CHANDLER AND
    PIERCE, JJ., CONCUR. KITCHENS, J., DISSENTS WITH SEPARATE WRITTEN
    OPINION JOINED BY KING, J. LAMAR, J., NOT PARTICIPATING.
    KITCHENS, JUSTICE, DISSENTING:
    ¶31.   Under the majority’s holding, an injured worker and a bereaved wife and daughter are
    denied any possibility of relief. Because I believe that our law ought to, and does, grant relief
    15
    in this unusual situation, and because the ramifications of the majority’s decision would tend
    to encourage reckless and irresponsible dealings between governmental entities and their
    contractors, I respectfully dissent.
    ¶32.   It is undisputed that, without their being able to sue the City, David Mooneyhan’s
    surviving wife and daughter, along with Bertram Hill, will be barred from compensatory
    relief of any kind. Phillips, the contractor, did not have workers’ compensation insurance2
    or general liability insurance, and is, effectively, judgment proof. Nevertheless, the majority
    holds that Phillips was an independent contractor of the City of Horn Lake (“the City”),
    without consideration of an important element of a legitimate, and, I believe, appropriate,
    common law analysis of such a relationship which would allow this Court to recharacterize
    the relationship between Phillips and the City. “Even if a contract clearly evinces the parties’
    settled intent to create a principal-independent contractor relationship, when a third party is
    adversely affected, this Court can look beyond the contract to determine whether public
    policy requires recharacterization of the relationship to allow the injured party to recover.”
    Chisolm v. Miss. Dep’t of Transp., 
    942 So. 2d 136
    , 142 (¶ 10) (Miss. 2006). While such a
    power initially may seem extreme, the Court was careful to note that it could do so only
    where “the party challenging the claimed relationship will be adversely affected, and denied
    an adequate legal remedy.” Richardson v. APAC-Mississippi, Inc., 
    631 So. 2d 143
    , 150
    (Miss. 1994) (emphasis added).
    2
    The appellants’ brief informs us that Hill and Mooneyhan were “the only two (2)
    employees of Phillips” when the accident occurred. Phillips, the contractor, employed fewer
    than five people, and thus was not required by law to carry workers’ compensation
    insurance. See Miss. Code Ann. § 71-3-5 (Rev. 2011).
    16
    ¶33.   The majority’s unwillingness to analyze the Richardson public policy factor due to
    the plaintiffs’ failure to present the argument to the trial court3 is incorrect in light of the fact
    that the factor is but one of several implicit in the balancing test used to determine
    independent-contractor status. The Court in Richardson clearly explained that the policy
    consideration factor, which I find dispositive in the case before us, was “another factor in the
    balancing test. . . .” 
    Richardson, 631 So. 2d at 150
    . Accordingly, when the trial court
    determined that Phillips was an independent contractor of the City without analyzing an
    important factor in the balancing test, the trial court committed error. This was not some
    extra consideration that the plaintiffs were required to argue before the trial court, but a factor
    implicit in the consideration of independent-contractor status that the trial court was bound
    to consider. The trial court erred as a matter of law, and we are well within our purview to
    review that error.
    ¶34.   The availability of other avenues for relief to a plaintiff has been a factor that this
    Court often has considered in finding an independent-contractor relationship. In Richardson,
    the Court found that the plaintiff never claimed that relief was unavailable from the
    independent contractor and, in fact, had entered into a settlement with the independent
    contractor’s insurance carrier. 
    Id. at 151.
    In Chisolm, we held that “[a]pplication of the
    ‘public policy’ factor [was] unwarranted[,]” because the plaintiffs, after being denied relief
    3
    This itself is debatable. In the hearing on the motion for summary judgment, while
    arguing about Phillips’s failure to provide proof of insurance, counsel for the plaintiffs
    stated, “Phillips had no insurance, and these Plaintiffs had absolutely no remedy for the
    wrongs that have occurred to them if this is allowed to proceed otherwise.” (Emphasis
    added.)
    17
    against the Mississippi Department of Transportation, settled with the independent contractor
    involved and dismissed it from the case. 
    Chisolm, 942 So. 2d at 142
    (¶ 11). Therefore, the
    plaintiffs in that case had an adequate remedy at law. The Court noted that the public policy
    factor “contemplates a situation where the plaintiff cannot get any recovery based on the
    principal-independent contractor shield.” 
    Id. As the
    plaintiff did obtain at least some relief
    in that case, the factor was irrelevant.
    ¶35.   The facts of this case, on the other hand, cry out for its application. One man is dead,
    leaving behind a wife and minor child, and another man is seriously injured. The only party
    who can be sued directly is, effectively, judgment proof, to say nothing of the fact that
    Phillips indisputably was egregiously negligent in digging this trench.4 If the plaintiffs are
    prevented from pursuing civil actions against the City, they will have no hope of relief. This
    is “a situation where the plaintiff[s] cannot get any recovery based on the principal-
    independent contractor shield.” 
    Id. The majority
    pays lip service to this concept, but goes no
    further. Indeed, in this case, the callous indifference of the City in its failure to hire an
    insured contractor is the reason the plaintiffs have no viable path to relief. I would find that
    the complete lack of availability or even the possibility of a legal remedy to the plaintiffs
    allows this Court to recharacterize the relationship between Phillips and the City.
    4
    It is undisputed that Phillips was found to have violated several federal regulations,
    including having his employees work without hardhats, failing to provide cave-in protection
    for the trench, failing to train his employees to recognize the dangers of a cave-in, failing to
    secure the large tree next to the excavation which actually caused the cave-in, keeping the
    excavated dirt pile directly adjacent to the excavation, failing to place a ramp or ladder inside
    the hole for the workmen to use, and failing to shore up the walls of this seventeen-foot deep
    trench .
    18
    ¶36.   Moreover, the history of the City’s dealings with Phillips reveals a lackadaisical
    approach to maintenance and construction contracts, with little oversight, or, it would seem,
    little motivation or effort on the City’s part to see that Phillips conducted his business in a
    safe and responsible manner. In response to requests for admission, Phillips answered,
    “Phillips had no written contracts with [Horn Lake] for any projects performed by Phillips[.]
    Any projects were performed on a cost plus basis and invoiced when the project was
    completed.” (Emphasis added.) One of those past projects was valued at $100,000. The
    history of slipshod contracting between Phillips and the City suggests that their interaction
    in the circumstances before us may be but one component of an established pattern of very
    informal conduct. Although the majority finds that the issue of any potential violation of the
    bidding statutes is moot, I believe that the City’s potential violation of the bidding statutes,
    in light of its history with Phillips, weighs against a finding that there existed an independent-
    contractor relationship. If the City can be allowed to relax its compliance with the laws
    regarding contracts for public works projects, then the law’s treatment of its relationship with
    its contractors ought to be relaxed as well.
    ¶37.   Further, it must be noted that the very nature of “cost-plus” contracting renders any
    protections offered by Mississippi Code Section 31-5-51(7) meaningless. As stated by the
    majority, that section requires construction or public works contractors to provide proof of
    general liability insurance to the contracting municipality when the contract between the two
    exceeds $25,000. Miss. Code Ann. § 31-5-51(7) (Rev. 2010). Under a cost-plus contract, the
    two parties may contract for any amount they choose, and once costs have gone over that
    amount, the contractor may simply submit invoices to the municipality for any additional
    19
    costs. It is obvious that savvy contracting parties can sign a contract for an amount below the
    threshold value of $25,000, and thus avoid the requirements of Section 31-5-51(7), even
    where the actual cost of the work may greatly exceed that amount. Thus, municipalities and
    contractors can enter into a convenient “don’t ask, don’t tell” arrangement that shields both
    from liability under the statute, that ensures that contractors without insurance still get work,
    and that permits municipalities to give contracts to the lowest bidder without having to ask
    why the contractor can do his work so cheaply.5
    ¶38.    By forbidding the plaintiffs’ suit in this case, the majority–unintentionally, I am sure–
    incentivizes municipalities and other governmental entities to hire fly-by-night, uninsured
    contractors, knowing that the governmental entity, clothed with immunity, will bear no legal
    responsibility for injury or death caused by such a contractor’s negligence, no matter how
    egregious or how devastating. As such operations often are the cheapest, there is little or no
    motivation for local governments to determine whether their contractors are solvent, insured,
    or competent. In fact, the incentive lies in the other direction. As such, uninsured contractors
    may remain more or less judgment proof, the only parties left bearing losses not of their own
    making are those injured by the negligent activities of such contractors. To put it simply, this
    is not fair.
    5
    Of course, all of this is rendered moot by the majority’s determination that the burden
    lies upon the contractor to provide proof of insurance, and not on the municipality to require
    that the contractor be insured. I reject that proposition as well. I can think of no reason why
    any principal should not have the burden of ensuring that any contractor it hires has
    sufficient general liability insurance, especially if the contractor is small enough not to be
    required to carry workers’ compensation insurance.
    20
    ¶39.   This Court should not ignore or be oblivious to the repercussions of the majority’s
    decision. If it stands, the bereaved wife and daughter of David Mooneyhan will have no
    chance for a legal remedy for the grievous injury done them.6 The injured Bertram Hill has
    no means of remediation of his injury. This factor should outweigh the other aspects utilized
    by this Court to determine the relationship between Phillips and the City. When a principal
    hires an independent contractor to do dangerous work, without determining whether that
    contractor has the ability to compensate persons who may be injured, and doing so
    completely denies relief to injured parties, this Court should recharacterize the relationship
    to allow relief. The language of our precedent, as enshrined in Chisolm and Richardson, and
    justice itself, demand such a process.
    ¶40.   Let us not forget: this was a terrible tragedy. A family was destroyed. David
    Mooneyhan, a working husband and father, was buried alive and crushed to death at the
    bottom of a sewage pit. His wife and daughter will receive no compensation for their loss.
    Bertram Hill was buried alongside Mooneyhan, close enough to touch his head with his hand.
    He heard Mooneyhan gasping for breath until he died. Hill remained buried for several hours
    until rescuers reached him. He will receive no compensation for his injuries. The City of
    Horn Lake had orally contracted with an uninsured contractor to perform dangerous sewage
    system work. Phillips, the contractor, did not have to account for either workers’
    compensation insurance or general liability insurance in his overhead costs, and so was able
    6
    Mooneyhan was being paid ten dollars per hour for his work for Phillips. Without
    his income, where are his wife and daughter to turn? Will it be the taxpayers of this State
    who help to support them?
    21
    to perform this work relatively cheaply. The City of Horn Lake either did not know or did
    not care that Phillips was uninsured. A husband and father is dead, another man is seriously
    injured, and the city that hired an uninsured, negligent contractor without regard to the
    contractor’s insurance coverage won’t have to pay a dime. The majority’s conclusion is
    utterly devoid of justice.
    ¶41.   I would reverse the trial court’s grant of summary judgment and remand for a trial
    against the City of Horn Lake. The majority ignores a vital component of our common law
    jurisprudence on the principal-independent contractor relationship. This Court has stated
    plainly that, where the plaintiff cannot obtain relief due to “the principal-independent
    contractor shield,” then we may recharacterize the relationship in the interest of public
    policy. 
    Chisolm, 942 So. 2d at 142
    (¶ 11). I find this factor to be dispositive. The City hired
    someone who violated federal regulations and failed to maintain insurance against the
    possibility of his conduct’s hurting someone. The majority would incentivize the repeat of
    such behavior, as there is no liability for the City of Horn Lake for acting as it did.
    ¶42.   The justices who comprise the majority are honorable and dedicated public servants
    who did not set out to create such an untoward and malevolent outcome in the lives of the
    innocent victims of this tragedy. Nevertheless, the outcome, in my view, is unnecessarily
    harsh and it is altogether unjust, so much so that I am unable to concur in it, especially when
    Mississippi law, as outlined above, provides a path toward a legitimate legal remedy for the
    victims. I therefore respectfully dissent.
    KING, J., JOINS THIS OPINION.
    22