In the Matter of: Trenton Farms RE, LLC Permit No. MOGS10500 v. Missouri Department of Natural Resources, Hickory Neighbors United, Inc. , 504 S.W.3d 157 ( 2016 )


Menu:
  •                                         In the
    Missouri Court of Appeals
    Western District
    IN THE MATTER OF: TRENTON                  )
    FARMS RE, LLC                              )
    Permit No. MOGS10500,                      )   WD79527
    )
    Appellant,                  )   OPINION FILED:
    )   November 22, 2016
    v.                                         )
    )
    MISSOURI DEPARTMENT OF                     )
    NATURAL RESOURCES, HICKORY                 )
    NEIGHBORS UNITED, INC.,                    )
    )
    Respondent.                  )
    Appeal from the Clean Water Commission
    Before Division Four: Mark D. Pfeiffer, Chief Judge, Presiding, Karen King Mitchell,
    Judge and Gary D. Witt, Judge
    Trenton Farms RE, LLC ("Trenton Farms") appeals the decision of the Missouri
    Clean Water Commission ("CWC") to deny Trenton Farms' permit application for a swine
    concentrated animal feeding operation ("CAFO") to be operated in Grundy County,
    Missouri. Trenton Farms raises five points of error on appeal, four alleging that the CWC
    erred in its denial because it misinterpreted the permit requirements of 10 CSR 20-
    6.010(3)1 causing the regulation to be misapplied and resulting in violations of Trenton
    Farms' constitutional rights. Trenton Farms' final point alleges that the CWC erred in
    finding that Trenton Farms' application did not adequately prove that the CAFO operation
    was protected from a one hundred-year flood as required by 10 CSR 20-8.300(5)(A).2 We
    affirm.
    Factual and Procedural Background
    In Missouri, the Clean Water Act ("CWA") is implemented by two administrative
    agencies: the Missouri Department of Natural Resources ("DNR") and the CWC. The
    DNR is Missouri's "general environmental agency charged with administering the
    programs assigned to the Department relating to environmental control and the
    conservation and management of natural resources." Mo. Soybean Ass'n v. Mo. Clean
    Water Comm'n, 
    102 S.W.3d 10
    , 19 (Mo. banc 2003) (internal quotation omitted). The
    CWC is charged by statute with a number of duties and granted numerous powers
    including:
    (1) the "general supervision of the administration and enforcement" of the
    Missouri Clean Water Law, sec. 644.026.1(1); (2) developing
    "comprehensive plans and programs for the prevention, control and
    abatement of new or existing pollution of the waters of the state."
    sec.644.026.1(2); (3) identifying waters of the state and prescribing water
    quality standards for them, sec.644.026.1(7); (4) the power to promulgate
    rules and regulations to enforce and implement Missouri's Clean Water Law,
    and the duties imposed on the state by the CWA, sec.644.026.1(8); and (5)
    the power to exercise all incidental powers necessary to carry out the
    purposes of Missouri's Clean Water Law, and to assure that the State of
    Missouri complies with the CWA, sec.644.026.1(16).
    1
    All regulatory references to 10 CSR 20-6 are to the Missouri Code of State Regulations (2014) unless
    otherwise indicated.
    2
    All regulatory references to 10 CSR 20-8 are to the Missouri Code of State Regulations (2012) unless
    otherwise indicated.
    2
    Id. at 19 n.15. The CWC's "domicile" is within the DNR. Section 644.021.1. DNR reviews
    all applications for CAFOs and determines eligibility for permits. 10 CSR 20-6.010(2).
    Such decisions, however, are reviewed by the CWC and the CWC acts as the final deciding
    agency regarding whether an applicant will or will not receive a permit. Section 644.026.1.
    On April 6, 2015, Trenton Farms applied to the DNR3 for a state no-discharge
    operating permit for a swine CAFO ("Permit Application"). The Permit Application was
    reviewed by DNR employee Greg Caldwell ("Caldwell"). Caldwell determined that the
    Permit Application met all statutory and regulatory requirements and, on August 12, 2015,
    DNR issued Permit MOGS10500 ("Permit") to Trenton Farms to operate the requested
    swine CAFO.
    Hickory Neighbors United, Inc. ("Hickory Neighbors") filed a Petition for Appeal
    of the Permit to the Administrative Hearing Commission ("AHC") on August 28, 2015,
    and a subsequent Amended Petition for Appeal ("Amended Petition") on September 22,
    2015. Trenton Farms intervened in the AHC action, and the AHC held a hearing on
    Hickory Neighbors' Amended Petition on October 23, 2015. The AHC found that DNR
    met its burden of showing that the operating permit was issued in accordance with
    applicable laws and recommended that the grant of the Permit be upheld ("Recommended
    Decision"). The Recommended Decision was transmitted to the CWC on January 4, 2016.
    The CWC heard additional oral argument from the parties on February 17, 2016, issuing
    3
    The DNR staff in the Division of Environmental Quality, Water Protection Program, are responsible for
    administering the Missouri Clean Water Law, including issuing CAFO permits. 10 CSR 20-1.010(3). The CWC,
    which is ultimately charged with conserving Missouri's waterways, maintains oversight over the permits and is the
    agency ultimately responsible for the final granting or denying of a CAFO permit. 10 CSR 20-1.020.
    3
    its Final Decision on February 24, 2016 ("Final Decision"). The CWC disagreed with the
    ultimate findings of the AHC, instead finding that the Permit was not appropriately and
    lawfully issued to Trenton Farms because DNR failed to determine that Trenton Farms was
    a "continuing authority," as required by 10 CSR 20-6.010(3), and further that DNR failed
    to adequately determine that the swine CAFO would be protected in the event of a one
    hundred-year flood in accordance with 10 CSR 20-8.300(5)(A). The Final Decision by the
    CWC overruled the DNR's grant of the Permit to Trenton Farms. This appeal followed.
    Standard of Review
    Section 644.051.6 provides that decisions by the CWC shall be subject to appellate
    review pursuant to chapter 536 of the Missouri Administrative Procedure Act. Section
    536.140.2 provides that, on review, this Court may determine whether the action of the
    agency: (1) violates a constitutional provision; (2) is in excess of statutory authority or
    jurisdiction of the agency; (3) is unsupported by competent and substantial evidence upon
    the whole record; (4) is unauthorized by law; (5) is made upon unlawful procedure or
    without a fair trial; (6) is arbitrary capricious or unreasonable; or (7) involves an abuse of
    discretion.
    We give deference to the agency's findings of fact so long as they are supported by
    competent and substantial evidence. Bd. of Educ. of City of St. Louis v. Mo. State Bd. of
    Educ., 
    271 S.W.3d 1
    , 7, 12 (Mo. banc 2008). As to questions of law, this Court conducts
    its review de novo. Albanna v. State Bd. of Registration for Healing Arts, 
    293 S.W.3d 423
    ,
    428 (Mo. banc 2009); ITT Commercial Fin. Corp. v. Mid-America Marine Supply Corp.,
    
    854 S.W.2d 371
    , 376 (Mo. banc 1993).
    4
    Discussion
    I.
    As it is dispositive of this appeal, we will first discuss Trenton Farms' final Point
    Relied On. In Point Relied On V, Trenton Farms alleges that the CWC erred in denying
    the Permit in that "there was no evidence in the record that the barns were not protected
    from inundation by the 100-year flood."4
    The Manure Storage Design Regulations, which apply to this type of CAFO
    operation, require that "[m]anure storage structures, confinement buildings, open lots,
    composting pads, and other manure storage areas in the production area shall be protected
    from inundation or damage due to the one hundred-year flood." 10 CSR 20-8.300(5)(A).
    This protection may be accomplished by constructing all listed sites above the one hundred-
    year flood plain or by including with the permit application certification from an engineer
    that all relevant sites are protected.
    Trenton Farms argues that there was sufficient evidence presented to the CWC to
    support a conclusion that the manure management barns of the CAFO were adequately
    4
    We agree with Hickory Neighbors that, as drafted, the Point Relied On incorrectly states the burden of
    proof. It was not the burden of Hickory Neighbors or the CWC to show that there was "no evidence" that the barns
    were "not protected" but rather the regulations require that a permit applicant and the DNR bear the burden of
    affirmatively proving that certain portions of the CAFO facility are protected against a one hundred-year flood. See
    10 CSR 20-8.300(5)(A). Despite the wording of the Point Relied On, Trenton Farms is ultimately raising a
    challenge to the CWC's finding that the engineer's certificate filed with the Permit Application was insufficient to
    meet the burden of Trenton Farms and the DNR in demonstrating that the CAFO operation was adequately
    protected. Thus, we need not enter into a detailed discussion of the burden of proof applicable to each of the parties.
    We further note that Hickory Neighbors' Amended Petition challenged the validity of the Permit because
    Trenton Farms failed to comply with the requirements of Executive Order 98-03, as opposed to 10 CSR 20-
    8.300(5)(A). The AHC's Recommended Decision held that 10 CSR 20-8.300(5)(A) was promulgated for the
    purposes of implementing Executive Order 98-03 to CAFOs. As such, the AHC interpreted Hickory Neighbors'
    allegation that Trenton Farms failed to meet the requirements of Executive Order 98-03 as an allegation that Trenton
    Farms failed to meet the requirements of 10 CSR 20-8.300(5)(A). The CWC appears to have adopted this
    interpretation and Trenton Farms does not raise the issue on appeal. Thus, we too review the parties arguments as
    they relate to the properly adopted rule 10 CSR 20-8.300(5)(A).
    5
    protected from a one hundred-year flood. First, Trenton Farms relies on the testimony of
    Caldwell who reviewed the Permit Application on behalf of DNR. Caldwell testified that
    Trenton Farms submitted a map with the application showing the flood plain but it was
    difficult to determine where the buildings would be placed on that map. He also noted that
    the flood boundary map crossed topographical lines, which prevented him from
    determining whether the CAFO was located within flood boundary lines based strictly on
    the map submitted. As a result, he obtained a FEMA map and a soil data map to determine
    that the CAFO was not actually located within the one hundred-year flood plain. He
    testified that his determination was based solely on the three additional maps that he
    obtained and which were entered into evidence by DNR. Unfortunately, as noted by
    Hickory Neighbors, the maps identified and entered into evidence by the DNR and
    allegedly relied upon by Caldwell are from counties other than Grundy.5 Ultimately,
    although the AHC found that Caldwell was credible, it found that his conclusions merely
    went to the issue of flooding of the soil and were not actually dispositive of the issue of
    whether the CAFO project was located in a FEMA Zone A floodplain.
    5
    It appears that these maps are wholly unrelated to the Grundy CAFO site and call into question Caldwell's
    testimony. When the discrepancy was pointed out to Caldwell he responded that he did not know why the maps
    were from different counties and that the "map unit [he] clicked on in there was in Grundy County." It was possible
    that map was part of a series that included multiple counties. Caldwell testified that he used topographic lines as
    well as the "identify tool" that was part of the map to confirm that it was in Grundy County as well as the map
    numbers which corresponded to Grundy County. It is not clear whether Caldwell incorrectly relied on maps from
    surrounding counties or the wrong maps were printed and submitted as exhibits. The AHC accepted the map
    exhibits as offered subject to objection from Hickory Neighbors noting that "[the Commission's] initial thought is
    that he has testified that he relied on those documents and, therefore, for what they are worth," they are admitted.
    We find that we need not resolve the discrepancy between the locations of the maps, however, because the AHC
    found--and the CWC agreed--that Caldwell's testimony was not dispositive of the ultimate issue of floodplain
    location.
    6
    Grundy County Emergency Management Director, Glen Briggs ("Briggs"),
    submitted an affidavit in support of Trenton Farms stating that he concluded that the CAFO
    building site is not located in the FEMA Zone A floodplain--also known as a one hundred-
    year floodplain. The AHC, however, noted that the orientation of the buildings on the map
    examined by Briggs did not match the building site plan submitted by Trenton Farms and,
    thus, found his conclusions to be irrelevant.
    The final source of evidence that the CAFO was adequately protected from a one
    hundred-year flood came from the certification of the Permit Application. As part of the
    application, Todd Van Maanen ("Van Maanen"), a Missouri licensed civil engineer,
    certified that, to the best of his knowledge, information and belief, "the manure
    management and containment system is designed in general conformance with applicable
    laws, codes, and regulations as of the date of signing." The AHC found that Caldwell and
    DNR were entitled to rely on this certification to find that the CAFO complied with 10
    CSR 20-8.300(5)(A) and ultimately found this certification was sufficient evidence for
    DNR to conclude that Trenton Farms complied with the regulation.
    The CWC agreed with the AHC's findings as to the testimony of Caldwell and
    Briggs6 but disagreed as to the AHC's conclusions regarding the engineer's certification.
    While the AHC interpreted the certification to mean that Van Maanen certified the CAFO
    buildings were protected from inundation or damage due to a one hundred-year flood, the
    6
    The CWC also agreed with the AHC's finding that the testimony of Hickory Neighbors' engineer, Kathy
    Martin, did not conclusively establish that the proposed CAFO buildings were located in the one hundred-year
    floodplain. Since the CWC ultimately found that Trenton Farms had no evidence to show compliance with 10 CSR
    20-8.300(5)(A), and it bore the burden of showing compliance, we need not discuss Martin's testimony.
    7
    CWC found that his certification did not go nearly so far. The CWC found that the
    engineer's certification and seal were attached only to the documents titled "Gestation
    Facility Manure Productions & Storage Calculations, Farrowing Facility Manure
    Production & Storage Calculations, and Gilt Development Facility Manure Production &
    Storage Calculations." Thus, the engineer's certification could only be interpreted to state
    that Van Maanen certified that the Production and Storage Calculations of the manure
    management and containment system complied with the applicable laws, codes and
    regulations. There was no evidence to suggest that Van Maanen intended to certify the
    compliance of all CAFO buildings and operations location as to the one hundred-year
    floodplain.
    Further, as Hickory Neighbors notes in its brief, the certification only states that the
    certification applies to "the manure management and containment system." 10 CSR 20-
    8.300(5)(A) requires evidence that the manure storage structures be protected, but also that
    there be protection for "confinement buildings, open lots, composting pads, and other
    manure storage areas in the production area." Even were we not mandated to give
    deference to the CWC's findings of fact regarding the breadth of the certification, we note
    that there is no evidence in the Petition Application to support a finding that Trenton Farms
    complied with the flood protection for these other areas or, in the alternative, evidence that
    this particular swine CAFO did not include such other areas and thus no certification of
    protection was needed. Trenton Farms repeatedly argues that there is nothing in the record
    that would indicate that the certification did not apply to the design of the entire facility,
    thus the CWC was erroneous in deciding that it did not meet the requirements of 10 CSR
    8
    20-8.300(5)(A). This argument ignores the plain language of the engineer's certification,
    which states it only applies to the "manure management and containment system," making
    no mention of the other sites required to be protected under the regulation. Without some
    evidence or testimony that these other sites were similarly protected or not part of the
    CAFO, the CWC, as the finder of fact, was free to find the engineer's certification did not
    fully comply with the regulations.
    We give deference to the CWC's findings of fact and will overturn their judgment
    only if it is unsupported by competent and substantial evidence; is arbitrary, capricious,
    unreasonable, or involves an abuse of discretion; or the decision is unauthorized by law.
    M.A.H. v. Mo. Dept. of Soc. Servs., 
    447 S.W.3d 694
    , 697 (Mo. App. E.D. 2014). It was
    not unreasonable for the CWC to make the same findings as the AHC that the testimony
    presented regarding the floodplain was insufficient to establish that the CAFO would be
    adequately protected. The maps relied on by Caldwell were suspect because they were
    identified as representing other irrelevant counties, and the map relied on by Briggs had
    the buildings oriented differently than the site plan submitted by Trenton Farms. Further,
    although Trenton Farms interprets the engineer's certification by Van Maanen differently,
    the CWC's interpretation was not arbitrary, capricious or unreasonable. The clear language
    of the certification states that "manure management and containment system" conforms to
    applicable laws, codes and regulations, but makes no mention of the other areas and
    structures listed in 10 CSR 20-8.300(5)(A). It was also reasonable for the CWC to question
    why the certification was only attached to the manure containment calculations and not the
    Permit Application as a whole, if it was indeed intended to apply to the entire Permit--
    9
    including areas beyond the manure containment system. Under section 327.411.1, the
    professional seal only applies to "all documents sealed by the licensee." Given that the
    seal was only affixed to a certain subset of documents, it is reasonable for the fact finder
    to believe it was not intended to provide a certification to the entire permit. Further,
    subsection 3 of 327.411 states that a professional licensee may affix his seal "specifying
    the particular technical submissions, or portions thereof, intended to be authenticated by
    the seal, and disclaiming any responsibility for all other technical submissions relating to
    or intended to be used for any part or part of the [project]." In this case, the seal specifically
    stated it applied to the "manure management and containment center." While it did not
    expressly disclaim the rest of the Permit Application, it was reasonable for the CWC to
    interpret this language as an intent by the engineer to limit his certification pursuant to
    section 327.411.3. How to interpret the certification was soundly within the CWC's
    discretion. Under these circumstances, this Court cannot overturn the factual determination
    of the CWC.
    Because we find that the CWC did not err in determining that Trenton Farms' Permit
    Application failed to adequately establish that it was in compliance with 10 CSR 20-
    8.300(5)(A), whether the CWC properly interpreted the requirements for being a
    "continuing authority" is immaterial. However, because the record indicates that Trenton
    Farms may still retain the right to seek a CAFO permit from the DNR, we briefly address
    the issues raised in the first four points of Trenton Farms' brief.
    10
    II.
    Trenton Farms' first four points on appeal challenge the finding by the CWC that
    Trenton Farms did not present evidence in its Permit Application that it was a "continuing
    authority" as required by 10 CSR 20-6.010(3). It argues that this finding was arbitrary,
    capricious, unreasonable, and an abuse of discretion; was contrary to the law; was
    constitutionally invalid because it was void for vagueness as applied to Trenton Farms; and
    was constitutionally invalid because it violated Trenton Farms' right to due process.
    "Administrative rules and regulations are interpreted under the same principles of
    construction as statutes." McGough v. Dir. of Revenue, 
    462 S.W.3d 459
    , 462 (Mo. App.
    E.D. 2015). Statutory interpretation is a matter of law which this Court reviews de novo.
    Albanna, 293 S.W.3d at 428.
    Section 10 CSR 20-6.010(3) provides:
    All applicants for construction permits or operating permits shall show, as
    part of their application, that a permanent organization exists which will
    serve as the continuing authority for the operation, maintenance, and
    modernization of the facility for which the application is made. Construction
    and first-time operating permits shall not be issued unless the applicant
    provides such proof to the department and the continuing authority has
    submitted a statement indicating acceptance of the facility.
    "Continuing authority" is not a defined term in the regulations. See 10 CSR 20-2.010. Nor
    does it appear that the term has ever been interpreted by a Missouri court. In the absence
    of a given definition in a regulation, the word or term will be given its plain and ordinary
    meaning as derived from a dictionary. Teague v. Mo. Gaming Comm'n, 
    127 S.W.3d 679
    ,
    686 (Mo. App. W.D. 2003). "The interpretation and construction of a statute by an agency
    charged with its administration is entitled to great weight." Beverly Enters.-Mo. Inc. v.
    11
    Dept. of Soc. Servs., Div. of Med. Servs., 
    349 S.W.3d 337
    , 352 (Mo. App. W.D. 2008).
    "However, it is inappropriate to defer to an agency's interpretation of its own regulation
    that in any way expanded upon, narrowed, or was otherwise inconsistent with the plain and
    ordinary meaning of the words used in the regulation." Id. Regulations should be
    interpreted reasonably, and absurd interpretations should not be adopted. Dep't of Soc.
    Servs. v. Senior Citizens Nursing Home Dist. of Ray Cty., 
    224 S.W.3d 1
    , 9 (Mo. App. W.D.
    2007).
    The testimony regarding this Permit revealed that, historically, DNR interpreted the
    regulations to require only a showing that an entity was a permanent organization to satisfy
    the "continuing authority" requirements. Financial information has never been required.
    This was true for both new permits and permit renewals. At the Permit hearing before the
    AHC, Caldwell testified as follows:
    [Trenton Farms]. Mr. Caldwell, let's talk about the application and the
    Department's interpretation of the continuing authority regulations and
    whether or not the finances of each applicant for a permit are relevant. I
    believe it's your testimony that the Department does not look at the financial
    wherewithal of any applicants?
    [Caldwell]. No.
    Q. So all industrial applicants that submit applications for construction
    permits or operating permits, the Department has never looked at the
    financial wherewithal or investigated it or asked them to submit any
    information concerning their finances to the Department of Natural
    Resources.
    A. Not that I'm aware of.
    Q. And they never asked any Concentrated Animal Feeding Operation or
    CAFO to submit any of their balance sheets or other financial information to
    qualify as a continuing authority?
    12
    A. Not that I'm aware of.
    Q. Even if they did, there are no regulations in the Missouri Clean Water
    Commission regulations that would instruct you or any other person at the
    Department of Natural Resources how to evaluate any financial information
    that's been submitted?
    A. No.
    Q. And would it be fair to say that any permit that comes up for reissuance
    after a five-year permit has expired and somebody has to apply to renew a
    permit, the Department has never asked any industrial or CAFO for any
    financial information when they renew a permit?
    A. No.
    Given its historical application, interpreting "continuing authority" to require financial
    disclosures was arbitrary as applied to Trenton Farms. CWC cannot change interpretations
    of "continuing authority" without some notice or other action. See section 536.010(4).7
    There is no evidence to suggest that this was an erroneous interpretation on behalf of the
    DNR or a particular employee of the DNR. To the contrary, recent discussion of changes
    to the regulations reveals a continued acceptance by the DNR and, therefore, the CWC that
    financial documents are not required submissions to prove "continuing authority." On
    September 15, 2016, DNR issued an Order of Rulemaking for 10 CSR 20-6.300 on behalf
    of the CWC and DNR which included comments to the rulemaking. Comment four stated:
    Mr. Stephen Jeffery proposed additional language to 10 CSR 20-6.300(3)(E)
    that reads, "Balance sheet and income statement for the applicant prepared
    7
    The required filings to prove "continuing authority" may not rise to the level of a rule under section
    536.010(6), because there is no evidence that the interpretation was a printed or published. All evidence, however,
    indicates that prior to the Final Judgment in this case, all permit seekers attempting to prove they were a "continuing
    authority" only needed to show proof that they were a permanent entity. The CWC cannot abandon this
    interpretation and require substantially more and different documentation of Trenton Farms without going through
    proper procedures to amend its rules. Section 536.021.
    13
    by a certified public accountant showing the applicant has sufficient assets
    to serve as a continuing authority in accordance with 10 CSR 20-6.010(3)."
    This would require that any applicant for a CAFO operating permit submit a
    balance sheet and an income statement prepared by a certified public
    accountant as part of its application package. The purpose of requiring these
    commonly utilized financial documents is for the applicant to provide
    "proof" that it is financial viable to operate, maintain, and modernize its
    proposed CAFO facility, as required by the continuing authority rule, 10 CSR
    20-6.010(3).
    Orders of Rulemaking from Department of Natural Resources, 2016 MO REG TEXT 418316
    (NS) (Sept. 15, 2016). In response, the DNR stated:
    No changes were made as a result of this comment. Continuing authority
    requirements are contained in 10 CSR 20-6.010. Discussion of any proposed
    revisions to continuing authority requirements would need to be addressed
    during stakeholder meeting(s) for the revision of that regulation.
    Id. Had a requirement for such balance sheets or financial information already existed in
    10 CSR 20-6.010(3), one would have expected the DNR to acknowledge such. Instead,
    the DNR recognized that this would be a revision to the existing requirements, requiring
    time for comment and revision of that particular regulation. While it appears that these
    comments were made by the DNR, they were done on behalf of the CWC, just as the DNR
    has been responsible for the interpretation of the submission requirements of 10 CSR 20-
    6.010(3) on behalf of the CWC. Hickory Neighbors asks us to give deference to the CWC's
    new interpretation of the filing requirements to prove "continuing authority," arguing that
    the prior interpretation was given by DNR not CWC. This, however, ignores the actual
    agency structure of DNR and CWC, in which DNR has been given the authority by CWC
    to both review and issue permits and promulgate rules and regulations governing permits,
    both on behalf of the CWC. See Mo. Soybean Ass'n, 102 S.W.3d at 19. The CWC
    14
    maintains oversight of these functions but it cannot choose to allow rules and regulations
    to be promulgated, issued, and implemented for extended periods of time until the CWC
    chooses to arbitrarily overturn the DNR's interpretation with no warning to the public or
    DNR and DNR agents, which the CWC has tasked with reviewing permits. Further, it
    would be disingenuous to then publish the original interpretation of the regulation even
    after it supposedly decided on a new and expanded interpretation.
    Further, to interpret the statute to require a permit applicant to submit the financial
    records of the "continuing authority" entity reads an additional requirement into the
    regulation that is not currently present. As written, 10 CSR 20-6.010(3) requires that a
    permit application "show, as part of their application, that a permanent organization exists
    which will serve as the continuing authority for the operation, maintenance, and
    modernization of the facility for which the application is made." (emphasis added). "For"
    has a number of accepted definitions but it is generally a function word used to indicate
    actions such as "preparation toward;" "in order to be, become or serve as;" "in order to
    bring about or further;" "with the purpose or object of;" "prerequisite to." WEBSTER'S
    THIRD NEW INTERNATIONAL DICTIONARY UNABRIDGED 886 (1993). In this case, it merely
    identifies the purpose that the continuing authority will serve. While having positive
    financials may ultimately be required to fulfil that function, evidence of such is not required
    to identify the entity which will serve the function--which is all the regulation requires.
    Hickory Neighbors and the CWC's interpretation asks this Court to transform "for" into
    "and" to require not only the identification of the "continuing authority" entity but also
    evidence that such entity also has the current financial ability to fulfill its future purpose.
    15
    The CWC did not have the authority to simply reinterpret 10 CSR 20-6.010(3) in a way
    that would effectively drastically modify its terms. See Matteson v. Dir. of Revenue, 
    909 S.W.2d 356
    , 360 (Mo. banc 1995). An agency cannot change the plain meaning of a term
    used simply because it does not reflect the intent of the regulation. See Stiers v. Dir. of
    Revenue, 
    477 S.W.3d 611
    , 615-16 (Mo. banc 2016) (giving plain meaning to the word
    "and" despite agency's claim that doing so did not reflect the intent behind the regulation).
    If an agency desires such a change, it must be done through amending the regulation. Id.
    at 616.
    Because we find that CWC's interpretation of "continuing authority" is arbitrary and
    contrary to the plain and ordinary meaning of the regulation, we need not enter into a
    review of Trenton Farms' constitutional challenges to CWC's interpretation to finally
    decide this point.
    As noted above, however, because Trenton Farms failed to adequately demonstrate
    that the entire swine CAFO operation was protected from a one hundred-year flood, as
    required by 10 CSR 20-8.300(5)(A), the CWC did not err in denying Trenton Farms' Permit
    Application.
    Motion for Attorneys' Fees on Appeal
    Pursuant to Local Rule XXIX, Trenton Farms filed with this Court a Motion for
    Attorney's Fees and Expenses on appeal. We elected to take the motion with the case. The
    motion requested that, in the event Trenton Farms prevailed on appeal, this Court award
    Trenton Farms reasonable attorneys' fees and expenses. Given this Court's affirmance of
    the Final Decision, Trenton Farms' Motion for Attorney's Fees and Expenses is denied.
    16
    Conclusion
    We find that the CWC did not err in finding that Trenton Farms' Permit Application
    did not meet the requirements of 10 CSR 20-8.300(5)(A) and, therefore, Trenton Farms
    was not entitled to receive a permit for its purposed swine CAFO. We affirm.
    __________________________________
    Gary D. Witt, Judge
    All concur