In the Matter of the Application of Laclede Gas Company to Change its Infrastructure System Replacement Surcharge in its Missouri Gas Energy Service Territory In the Matter of the Application of Laclede Gas Company to Change its Infrastructure System Replacement Surcharge in its Laclede Gas Service Territory The Office of Public Counsel Spire Missouri, Inc. v. The Missouri Public Service Commission ( 2019 )


Menu:
  •                  MISSOURI COURT OF APPEALS
    WESTERN DISTRICT
    IN THE M ATTER OF THE              )
    A PPLICATION OF L ACLEDE G AS      )   WD82200 and
    C OMPANY TO CHANGE ITS             )   WD82297
    INFRASTRUCTURE SYSTEM              )
    REPLACEMENT SURCHARGE IN ITS       )   O PINION FILED :
    M ISSOURI G AS E NERGY S ERVICE    )
    T ERRITORY ; IN THE MATTER OF      )   November 19, 2019
    THE APPLICATION OF L ECLEDE        )
    G AS C OMPANY TO CHANGE ITS        )
    INFRASTRUCTURE SYSTEM              )
    REPLACEMENT SURCHARGE IN ITS       )
    L ACLEDE G AS S ERVICE             )
    T ERRITORY ; THE O FFICE OF        )
    PUBLIC C OUNSEL ;                  )
    )
    Appellant,      )
    )
    S PIRE MISSOURI , INC .,           )
    )
    Appellant,      )
    v.                              )
    )
    T HE MISSOURI P UBLIC S ERVICE     )
    C OMMISSION ,                      )
    )
    Respondent.     )
    APPEAL FROM THE PUBLIC SERVICE COMMISSION
    Before Division Two: Thomas H. Newton, Presiding Judge,
    Anthony Rex Gabbert, and Thomas N. Chapman, Judges
    The Office of Public Counsel (OPC) 1 and Spire Missouri, Inc., a gas
    corporation       and    public      utility,   appeal      a   Public      Service      Commission 2
    determination that it lacked the authority to require that Spire refund, or return
    to, ratepayers excess infrastructure surcharges 3 related to the company’s 2017
    neighborhood-replacement program after this Court found the same surcharges
    ineligible as to the company’s 2016 infrastructure surcharges, reversing as
    unlawful a Commission ruling to the contrary. In re Laclede Gas Co. v. Office
    of Pub. Counsel, 
    539 S.W.3d 835
    (Mo. App. W.D. 2017). 4 Having found the
    OPC’s request for a ratepayer refund under a 2017 stipulation and agreement
    moot, the Commission also seeks to dismiss the appeal as moot, arguing that the
    company’s 2017 general rate cases, which are currently pending before the
    Missouri Supreme Court, reset Spire’s 2017 surcharges to zero and thus the
    1
    The Office of Public Counsel (OPC) is the Missouri state agency responsible for representing
    consumers in cases before the Public Service Commission and on appeals of Commission orders. In
    re Kansas City Power & Light Co. v. Midwest Energy Consumers' Grp ., 
    425 S.W.3d 142
    , 144 n.2 (Mo.
    App. W.D. 2014) (citing sections 386.700 and 386.710).
    2
    The Public Service Commission regulates public utilities, such as gas companies, in Missouri under
    Chapters 386 and 393 of the Missouri Revised Statutes. In re Kansas City Power & Light 
    Co., 425 S.W.3d at 143
    n.1.
    3
    The “infrastructure system replacement surcharge” is commonly referred to as an ISRS. See, e.g., §
    393.1015, RSMo (2016). We will refer to it as an infrastructure surcharge to avoid the overuse of
    acronyms and any resulting confusion. We also refer to the gas company, variously known during the
    relevant time period as Laclede Gas Co., Missouri Gas Energy, and subsequently Spire Missouri, Inc.,
    as Spire for the reader’s convenience.
    4
    Spire has an eastern and a western territory in Missouri, and, when Spire has sought a surcharge or a
    new general base rate, it has done so by bringing two cases, one for each territory. This appeal involves
    two surcharge cases filed for the company’s infrastructure projec ts in each of its territories in 2017 and
    analyzes their relation to two general rate cases filed in 2017 —that took effect in 2018—for each of
    Spire’s territories. No other general rate cases are at issue or discussed. The related appeals argued
    with this appeal similarly involve two infrastructure -surcharge cases from 2016 (WD82199, WD82299)
    and two infrastructure-surcharge cases from 2018 (WD82302, WD82373).
    2
    excess surcharges are no longer eligible for recovery. We overrule the motion
    and have considered the matter on the merits. We reverse and remand for further
    proceedings.
    The Commission issued three separate orders following a consolidated
    hearing in August 2018 intended to allow the parties to introduce evidence on
    the methodology the Commission would use to determine how to place a value
    on those components of the neighborhood infrastructure Spire replaced—plastic
    mains and service lines—and which this Court determined were ineligible for
    recovery as infrastructure surcharges because the components were not worn out
    or deteriorated and no obligation had been placed on Spire to replace them by a
    government-mandated safety requirement. 
    Id. at 840.
    5 The consolidated hearing
    pertained to Spire’s infrastructure surcharges for projects in 2016, 2017, and
    2018, each of which arises in different proceedings that are procedurally
    distinguishable. This appeal focuses on the 2017 cases.
    When Spire sought surcharges for its 2017 infrastructure projects, the 2016
    surcharge cases were pending before this Court. The OPC opposed some of the
    2017 project costs for the same reason that it had opposed costs in the 2016 cases.
    The parties entered a stipulation and agreement as to the 2017 cases believing
    5
    Note that section 393.1012.1 permits a gas corporation to petition the Commission to increase its
    infrastructure surcharge to recover the costs of “certain government -mandated infrastructure
    replacement projects outside a general ratemaking case.” In re Laclede Gas Co. v. Office of Pub.
    Counsel, 
    539 S.W.3d 835
    , 838 (Mo. App. W.D. 2017) (citation omitted). The infrastructure-surcharge
    mechanism is more streamlined than a public utility’s general rate proceeding and is of more limited
    duration. Compare sections 393.1015.2 and .5(2) with section 393.270.
    3
    that a court ruling on the matter would be dispositive and that it would not be a
    productive use of the Commission’s or the parties’ resources “to litigate the
    Plastics Issue before the Commission again.” 6 Under the agreement, which the
    Commission approved in April 2017, if this Court reversed the Commission ’s
    ruling on infrastructure cost-recovery eligibility as unlawful or unreasonable,
    “then the court’s final decision shall be applied to the [2017 cases] in the same
    manner as it is applied to the [2016 cases], as applicable.” Spire and Commission
    staff agreed not to challenge the OPC’s right to request that the Commission
    determine the amount of the infrastructure-surcharge refund for the 2017 projects
    under the Court’s ruling, but all signatories agreed “to make any argument they
    wish regarding the methodology, propriety, and quantification of such refund, if
    any.” 7 After the Missouri Supreme Court denied transfer in March 2018 and our
    mandate issued in the 2016 cases, the Commission asked the parties to file
    recommendations about moving forward with the 2016 cases; the OPC addressed
    both the 2016 and 2017 cases in a single recommendation given the stipulation
    6
    During oral argument, the Commission contended that OPC should not have entered a stipulation as
    to the 2017 infrastructure surcharges that Spire sought, but instead should have allowed the surcharges
    to be imposed and then litigated the matter to get its challenge properly before this Court. We would
    not encourage parties to avoid reaching agreements that have the potential to conserve agency and
    judicial resources.
    7
    The Commission subsequently approved tariffs for the 2017 infrastructure surcharges of $3,000,749
    and $3,044.481 for Spire’s separate territories on Staff’s recommendation in May 2017. According to
    Staff, the recommended tariffs complied with the unanimous stipulation and agreement of the parties
    and thus included the costs for replaced plastic mains and service lines later fo und ineligible by this
    Court with respect to the 2016 cases and due to be refunded under the parties’ agreement in the 2017
    cases.
    4
    and agreement that related the 2017 cases to the outcome of the court appeal in
    the 2016 cases.
    Because Spire’s 2017 general rate cases were not finalized until
    compliance tariffs were approved on April 4, 2018, the OPC requested in a March
    2018 pleading titled “Public Counsel’s Recommendation” that the Commission
    determine which infrastructure surcharges from Spire’s 2016 and 2017 cases
    were ineligible for recovery and suggested that the Commission apply any over-
    collection to the rate base set in the 2017 general rate cases. 8 The OPC calculated
    those excess surcharges in the total amount of $4.9 million. Spire opposed the
    OPC’s recommendation on procedural and evidentiary grounds. Commission
    Staff recommended that costs associated with the ineligible infrastructure
    surcharges be refunded to Spire’s ratepayers in the company’s 2018
    infrastructure-surcharge cases.             Staff calculated the excess surcharges at
    $3,634,344.
    The record does not show whether the refunds that OPC requested for the
    2017 infrastructure surcharges were accounted for or incorporated in the 2017
    general rate cases. We assume that the refunds were not accounted for because,
    8
    As to the 2017 general rate cases, appealed by Spire, the Southern District affirmed the Commission
    order, and the Missouri Supreme Court granted Spire’s motion to transfer on September 3, 2019, at No.
    SC97834. Spire Mo., Inc. v. Pub. Serv. Comm’n, No. SD35485 (Mo. App. S.D. Mar. 15, 2019). It
    does not appear that any infrastructure -surcharge issues are part of the matters challenged in this
    appeal. As noted above, because Spire serves customers in the eastern and western parts of Missouri
    at different rates, its rate cases came before the Commission as two separate matters, but were
    consolidated on appeal. 
    Id. slip op.
    at 3. The OPC later argued in the proceedings leading to the case
    currently before this Court that the 2017 surcharge refunds c ould be provided through a line item on
    customers’ bills or through a separate and independent temporary rate adjustment under section
    386.520.2(2).
    5
    as indicated above, after Spire’s 2017 general base rates went into effect, the
    Commission ordered an August 2018 evidentiary hearing on the appropriate
    methodology for valuing the ineligible surcharges as to the 2016, 2017, and 2018
    infrastructure-surcharge cases and thus would have had no basis to account for
    the ineligible surcharges in the 2017 general rate cases until after the hearing
    took place. The Commission then issued an “Order Denying Request to Modify
    Commission Order” on September 20, 2018, as to the 2017 surcharge cases at
    issue in this appeal.      In that order, the Commission deemed the OPC’s
    pleading—the “Recommendation”—a request to modify the 2017 final
    Commission order, which had approved the stipulation and agreement, and
    determined that it lacked the legal authority to order refunds of ineligible
    infrastructure-surcharge costs in the 2017 cases, citing statutes that it claimed do
    not allow the retroactive correction of superseded infrastructure-surcharge tariffs
    after a general rate case includes those infrastructure costs in the base rates. The
    Commission concluded that the “OPC’s request to modify the final order
    approving the stipulation and agreement is moot and will be denied.” The OPC
    filed an application for rehearing, which the Commission denied, and timely filed
    this appeal. Spire also filed an application for rehearing, which the Commission
    denied, and timely filed an appeal to argue that the Commission erred to the
    extent, if any, that it determined that any of the costs in the company ’s 2017
    infrastructure-surcharge cases were ineligible for recovery due to the
    Commission’s failure to issue findings of fact and conclusions of law to support
    6
    that determination.   We consolidated the appeals of the 2017 infrastructure-
    surcharge cases.
    MOOTNESS
    We have taken with the case the Commission’s motion to dismiss for
    mootness and the motion to strike the OPC’s brief for failure to comply with
    Rule 84.04. Spire has joined the Commission’s motion to dismiss but only with
    the understanding that the Commission’s disposition of the 2016 infrastructure-
    surcharge cases does not apply to the Commission order denying for mootness
    the OPC’s request for refund in the 2017 infrastructure-surcharge cases. The
    company suggests that its right to challenge the Commission’s decisions
    regarding ineligible infrastructure-surcharge costs in the 2016 cases will not be
    waived by a dismissal of the consolidated appeal here as the Commission did not
    rule on the merits of the infrastructure-surcharge costs in the 2017 cases and
    made no finding on the eligibility or amount of those costs, which would have to
    be determined on remand, if that occurs. We address the Commission’s mootness
    argument first.
    According to the Commission, under In re Missouri-American Water Co.
    v. Office of Public Counsel, 
    516 S.W.3d 823
    (Mo. banc 2017), once it granted
    Spire general base rate increases for 2017, it lost the authority to order a
    correction to the superseded 2017 infrastructure surcharges, which were required
    by statute to be reset to zero. 
    Id. at 828
    (citing section 393.1006.6(1) and stating,
    7
    “superseded tariffs cannot be corrected retroactively.”). 9 In that case, the OPC
    had challenged the Commission’s authority to grant a petition for infrastructure
    surcharges, and the matter was pending on appeal when the water company filed
    a separate rate case. 
    Id. at 826-27.
    Commission Staff and the water company
    “reached a stipulation and agreement establishing a new base rate that
    incorporated the costs of the [water company’s] projects for all then-existing
    surcharges, including the surcharge at issue in this case.” 
    Id. at 827.
    Because
    the surcharge was reset to zero “once the new base rates went into effect[,] . . .
    the surcharges that were the subject of the underlying interim rate case were no
    longer in effect by the time the appellate court issued its opinion.” 
    Id. According to
    our supreme court, the legal question underlying the infrastructure surcharges
    was therefore moot and did not fit within the public-interest exception to the
    mootness doctrine. 
    Id. at 828
    -29.
    9
    The equivalent statutory subsection applicable to gas utilities is found in section 393.1015, which
    states the following:
    A gas corporation that has implemented an ISRS [infrastructure system replacement
    surcharge] pursuant to the provisions of sections 393.1009 to 303.1015 shall file
    revised rate schedules to reset the ISRS to zero when new base rates and c harges
    become effective for the gas corporation following a commission order establishing
    customer rates in a general rate proceeding that incorporates in the utility’s base rates
    subject to subsections 8 and 9 of this section eligible costs previously ref lected in an
    ISRS.
    § 393.1015.6(1). Because the Missouri Supreme Court cited this Court’s decision in State ex rel.
    Praxair, Inc. v. Public Service Commission, 
    328 S.W.3d 329
    (Mo. App. W.D. 2010), the legal principle
    is better stated as “superseded tariffs are generally considered moot and therefore not subject to
    consideration because superseded tariffs cannot be corrected retroactively.” 
    Id. at 334
    (emphasis
    added) (citations omitted).
    8
    We do not find the water company case applicable to the matter at hand.
    Here, when our decision finding the costs to replace plastic mains and service
    lines ineligible for recovery in the 2016 infrastructure-surcharge cases became
    final, Spire’s 2017 general base rates had not yet gone into effect. The Missouri
    Supreme Court denied transfer in the 2016 infrastructure-surcharge cases on
    March 6, 2018; our mandate issued on March 7, 2018, and the parties knew as
    early as November 21, 2017, when we issued the opinion, that the costs for
    plastic mains and service lines had been ruled ineligible for recovery as
    infrastructure surcharges. The Commission approved Spire’s 2017 general rate
    cases on March 7, 2018, with an effective date of March 17, 2018, and
    compliance tariffs for those rate cases were approved April 4, 2018. Under
    section 393.1015.6(1), an infrastructure surcharge incorporated into a general
    rate case is reset to zero when the new base rates “become effective.” Because
    the rates in the 2017 general rate cases did not go into effect until March 17,
    2018, at the earliest, the 2016 and 2017 infrastructure surcharges had not been
    reset to zero when our eligible-costs decision and order for proceedings
    consistent with our opinion became final. 10 Further, the parties had signed a
    stipulation and agreement, approved by the Commission, that the final
    determination as to the appeal of the 2016 cases would be applied to the 2017
    10
    The Commission’s September 20, 2018, report and order on remand i n the 2016 infrastructure-
    surcharge cases, states, in fact, that Spire’s 2017 general rates became effective on April 19, 2018, or
    more than one month after our mandate issued in In re Laclede Gas Co., and the existing infrastructure
    surcharges were then reset to zero.
    9
    infrastructure-surcharge cases, subject only to a calculation of the refunds o wed
    to Spire’s ratepayers. While it may not be possible at this late date under the law
    to “correct” the 2017 infrastructure surcharges, which have now been reset to
    zero, excess charges may flow through and be returned to ratepayers by means
    of temporary rate adjustments. § 386.520.2. The matter is not moot.
    The Commission also argues that we should grant its motion to dismiss
    because the OPC and Spire “seek relief that is unauthorized under the exclusive
    and jurisdictional procedures of Sections 386.500 and 386.510.” In its view, the
    OPC should have appealed the Commission order approving the stipulation and
    agreement to which OPC was a party because the Commission approved the 2017
    infrastructure surcharge, including the costs of replaced plastic, in that order and
    it has deemed the OPC’s “Recommendation” following our ruling in the 2016
    infrastructure-surcharge cases as a request to modify that order. The Commission
    also contends that it cannot reach back and modify the order approving the
    stipulation to establish a 2017 infrastructure surcharge for an amount other than
    what was approved in that order, i.e., an amount that included the cost to replace
    plastic mains and service lines. Essentially, the Commission asks this Court to
    overlook our ruling that the Commission’s approval of Spire’s recovery of costs
    for the replacement of plastic components in 2016 was not permitted under the
    infrastructure-surcharge statute and that the Commission approved a stipulation
    under which the parties agreed that ratepayers could be refunded, or recover
    excess charges, in the 2017 cases if the courts finally ruled these costs ineligible
    10
    in the 2016 cases. We do not believe that the law allows the Commission to
    move forward, particularly under the circumstances of this case, as if we had not
    spoken to the issue before the new base rates went into effect. We feel compelled
    to observe, as well, that the law does not contemplate the incorporation of
    ineligible costs previously reflected in an infrastructure surcharge into a utility
    company’s base rates. § 393.1015.6(1) (pertaining to the incorporation in new
    base rates of “eligible costs previously reflected in an [infrastructure surcharge]”
    (emphasis added)). We overrule the motion to dismiss.
    As to the Commission’s contention that the OPC’s point is multifarious,
    even if we were to agree, we may still, in the exercise of our discretion, “attempt
    to resolve the issue on the merits.” LaBarca v. LaBarca, 
    534 S.W.3d 329
    , 335
    n.4 (Mo. App. W.D. 2017) (citation omitted); see also State ex re. Mo. Office of
    Pub. Counsel v. Pub. Serv. Comm'n, 
    293 S.W.3d 63
    , 70 (Mo. App. S.D. 2009)
    (declining to dismiss appeal for briefing deficiencies, court references the
    “substantial business and private interests and investments” at stake in a case of
    this nature). Accordingly, we will not strike the OPC’s brief.
    2017 INFRASTRUCTURE-SURCHARGE REFUNDS
    After the Commission issued the September 20, 2018, order, which it
    unilaterally denominated a denial of a request to modify its April 2017 order, the
    OPC sought a rehearing under section 386.500 and, when that request was
    denied, filed an appeal under section 386.510. Accordingly, the Commission’s
    order finding moot OPC’s recommended disposition following our remand in
    11
    Laclede and the stipulation the Commission approved, is properly before this
    Court. In the sole point relied on, the OPC argues that the Commission erred by
    declining to enforce its April 2017 order “because the enforcement of that prior
    order does not require separate statutory authority to independently issue refunds
    as suggested by the Commission and would not result in a remedy that is moot. ”
    According to the OPC, the Commission’s order required Spire to adhere to its
    agreement that a court ruling in the 2016 infrastructure-surcharge cases would
    be applied to the 2017 cases; by remanding the Commission’s decision in the
    2016 cases for further proceedings consistent with our opinion, this Court
    implicitly instructed the Commission to comply with section 386.520.2;
    determination of the amount of the required refunds would not challenge the
    validity of Spire’s infrastructure surcharges or its ability to use the surcharge
    statute; and the refunds would only affect money that Spire collected before its
    rates were reset in the 2017 general rate cases.
    The Commission determined that it lacked statutory authority to correct
    the 2017 infrastructure surcharges under section 393.1015.6(1), and In re
    Missouri-American Water Co. Because this raises an issue of law, we must
    determine whether the Commission’s order is lawful.            State ex rel. AG
    Processing, Inc. v. Pub. Serv. Comm'n, 
    120 S.W.3d 732
    , 734 (Mo. banc 2003).
    “The lawfulness of a [Commission] order is determined by whether statutory
    authority for its issuance exists, and all legal issues are reviewed de novo.” 
    Id. 12 In
    our view, the principal error the Commission made was in deeming the
    OPC’s Recommendation following our remand of the 2016 infrastructure-
    surcharge cases a request to modify the Commission’s April 2017 order, which
    approved the OPC/Spire stipulation and agreement to apply the Court’s ruling in
    In re Laclede Gas Co. to the 2017 infrastructure surcharges. The OPC made the
    Recommendation at the Commission’s request after we remanded in In re
    Laclede Gas Co. and under a stipulation that allowed the OPC to seek refunds
    for ratepayers of ineligible surcharges that the Commission included in the
    infrastructure surcharges imposed under the April 2017 order. No modification
    of the Commission’s 2017 order was called for; rather, the OPC, in its
    Recommendation, sought a “resolution of the outstanding issues related to the
    plastic portion of the main and service lines which were approved for [the 2017
    infrastructure-surcharge cases].”               This would require that the Commission
    enforce the stipulation and agreement that was still in force, the Commission
    approved, and allowed a refund, or return of excess surcharges to ratepayers. 11
    Thus, the Commission erred in deeming the OPC’s Recommendation a request
    to modify the 2017 order.
    11
    The Commission states in the September 20, 2018, order that the signatories to the stipulation and
    agreement “did not agree on a specific mechanism to effectuate such refunds. Even if they had so
    agreed, however, the Commission cannot orde r a refund of [infrastructure-surcharge] costs without
    statutory authority.” If the Commission is correct, then it lacked the authority to approve the stipulation
    and agreement and, under section 386.490.2, its April 2017 order is a nullity. That issue i s not,
    however, before this Court.
    13
    Also, as indicated above, nothing in In re Missouri-American Water Co.,
    precludes the Commission in this case from ordering adjustments for ratepayers
    who have paid in excess of what Spire “would have received had the commission
    not erred.” § 386.520.2(2). We decided that Spire’s costs for replacing plastic
    mains and services lines were ineligible for recovery as infrastructure surcharges
    before the 2017 general base rates went into effect and before the 2017
    infrastructure surcharges were reset to zero. As well, Spire agreed to issue
    refunds to ratepayers in this case, therefore obviating the need for the
    Commission to do anything more than enforce the stipulation and determine the
    appropriate amount of the refund/adjustment as requested by the OPC.                                 We
    recognize that the surcharges have now been reset to zero, but this does not mean
    that the Commission lacks any authority to order Spire to adjust for excess
    surcharges or that ratepayers cannot recover refunds by means of temporary rate
    adjustments or prospective rate adjustments for excess surcharges.
    Section 386.520 authorizes the Commission to make “temporary rate
    adjustments” or “prospective rate adjustments” after a final judicial decision
    “determines that a commission order or decision unlawfully or unreasonably
    decided an issue or issues in a manner affecting rates.” § 386.520.2. 12 In this
    regard, the statute states the following:
    12
    Under section 393.1012, a gas corporation may seek the establishment of infrastructure surcharges
    “that will allow for the adjustment of the gas corporation’s rates and charges to provide for the recovery
    of costs for eligible infrastructure system replacements.” § 393.1012.1. Accordingly, an infrastructure
    surcharge comes within the ambit of an issue “affecting rates.”
    14
    2. With respect to orders or decisions issued on and after July 1,
    2011, that involve the establishment of new rates or charges for
    public utilities that are not classified as price-cap or competitive
    companies, there shall be no stay or suspension of the commission’s
    order or decision, however:
    (1) In the event a final and unappealable judicial decision
    determines that a commission order or decision unlawfully
    or unreasonably decided an issue or issues in a manner
    affecting rates, then the court shall instruct the commission
    to provide temporary rate adjustments and, if new rates and
    charges have not been approved by the commission before
    the judicial decision becomes final and unappealable,
    prospective rate adjustments. Such adjustments shall be
    calculated based on the record evidence in the proceeding
    under review and the information contained in the
    reconciliation and billing determinants provided by the
    commission under subsection 4 of section 386.420 and in
    accordance with the procedures set forth in subdivisions
    (2) and (5) of this subsection;
    (2) If the effect of the unlawful or unreasonable commission
    decision issued on or after July 1, 2011, was to increase the
    public utility’s rates and charges in excess of what the
    public utility would have received had the commission not
    erred or to decrease the public utility’s rates and charges in
    a lesser amount than would have occurred had the
    commission not erred, then the commission shall be
    instructed on remand to approve temporary rate
    adjustments designed to flow through to the public utility’s
    then-existing customers the excess amounts that were
    collected by the utility plus interest at the higher of the
    prime bank lending rate minus two percentage points or
    zero. Such amounts shall be calculated for the period
    commencing with the date the rate increase or decrease
    took effect until the earlier of the date when the new rates
    and charges consistent with the court’s opinion became
    effective or when new rates or charges otherwise approved
    by the commission as a result of a general rate case filing
    or complaint became effective. Such amounts shall then be
    reflected as a rate adjustment over a like period of time.
    The commission shall issue its order on remand within
    sixty days unless the commission determines that
    15
    additional time is necessary to properly calculate the
    temporary or any prospective rate adjustment, in which
    case the commission shall issue its order within one
    hundred twenty days.
    § 386.520.2.
    The Commission erred in determining that it lacked statutory authority to
    allow ratepayers to recover for the excess 2017 infrastructure surcharges. We
    will grant this point, but we recognize that the amount of the adjustments in the
    2017 infrastructure surcharge cases is still in question, because the Commission
    did not calculate what percent of the work orders involved in the 2017 surcharge
    cases involved ineligible plastic mains and service lines.
    SPIRE’S APPEAL
    Spire argues in its appeal that the Commission erred to the extent, if any,
    that its September 20, 2018, order determined that any of the costs in the
    company’s 2017 infrastructure-surcharge cases were ineligible “because such
    decision was void of findings of fact, conclusions of law, or any other language
    in the Order that would support such a determination.” Spire makes the same
    assertions here as it does in its suggestions regarding the Commission’s motion
    to dismiss, i.e., that the Commission has indicated that it did not rule on the
    merits of the 2017 infrastructure-surcharge cases as it “could not issue a refund
    in any event.” Accordingly, Spire is assured that “appealing the Order is not
    necessary to preserve its rights to later argue the merits of any future
    [Commission] case on ineligible [infrastructure surcharge] costs in the 2017
    16
    Cases.” The company asks this Court to find that the Commission’s order “did
    not reach the issue of the eligibility or cost of plastic replacements in the 2017
    Cases, did not quantify or order refunds or any replacement costs, and therefore
    the Order in the 2017 Cases should not be vacated or reversed.” The only law
    that Spire cites is a case giving the Commission the authority “to interpret its
    own orders and to ascribe to them a proper meaning.” While we agree that the
    Commission did not decide the merits of the 2017 infrastructure surcharges after
    we remanded the 2016 infrastructure surcharge cases in In re Laclede Gas Co.,
    there was no need for it to do so. Spire agreed that the final decision in that case
    would be applied in the same manner to the costs for plastic mains and service
    lines imposed on ratepayers for the 2017 projects. Once a final judicial opinion
    held that the 2016 infrastructure surcharges were unlawful, no further
    Commission rulings on eligibility were necessary in the 2017 cases. This point
    is denied.
    Conclusion
    We deny the Commission’s motion to dismiss this appeal, having
    concluded that it is not moot. Because the Commission erred in finding moot
    and denying the OPC’s request that the excess 2017 infrastructure surcharges
    contemplated in a stipulation and agreement between Spire and the OPC be
    returned to ratepayers, we reverse and remand for further proceedings consistent
    with this opinion. The Commission shall calculate the amount of the excess
    surcharges using the method adopted and affirmed in the 2016 (WD82199,
    17
    WD82299) infrastructure-surcharge appeals, and shall approve temporary rate
    adjustments in that amount.
    /s/   Thomas H. Newton
    Thomas H. Newton, Presiding Judge
    Anthony Rex Gabbert and Thomas N. Chapman, JJ. concur.
    18
    

Document Info

Docket Number: WD82200, WD82297

Judges: Thomas H. Newton, Presiding Judge

Filed Date: 11/19/2019

Precedential Status: Precedential

Modified Date: 11/19/2019