In the Matter of the Application of Laclede Gas Company to Change its Infrastructure System Replacement Surcharge in its Missouri Gas Energy Service Territory In the Matter of the Application of Laclede Gas Company to Change its Infrastructure System Replacement Surcharge in its Laclede Gas Service Territory The Office of Public Counsel Spire Missouri, Inc. v. Missouri Public Service Commission ( 2019 )


Menu:
  •                                            In the
    Missouri Court of Appeals
    Western District
    
    IN THE MATTER OF THE                           
    APPLICATION OF LACLEDE GAS                        WD82199 and WD82299
    COMPANY TO CHANGE ITS
    INFRASTRUCTURE SYSTEM                             OPINION FILED:
    REPLACEMENT SURCHARGE IN ITS                   
    MISSOURI GAS ENERGY SERVICE                       November 19, 2019
    TERRITORY; IN THE MATTER OF                    
    THE APPLICATION OF LACLEDE GAS                 
    COMPANY TO CHANGE ITS                          
    INFRASTRUCTURE SYSTEM                          
    REPLACEMENT SURCHARGE IN ITS                   
    LACLEDE GAS SERVICE TERRITORY;                 
    THE OFFICE OF PUBLIC COUNSEL;                  
    
    Appellant-Respondent,       
    
    SPIRE MISSOURI, INC.,                          
    
    Respondent-Appellant,       
    v.                                             
    
    MISSOURI PUBLIC SERVICE                        
    COMMISSION,                                    
    
    RESPONDENT.             
    
    APPEAL FROM THE PUBLIC SERVICE COMMISSION
    Before Division Two:
    Thomas H. Newton, P.J. Anthony Rex Gabbert, and Thomas N. Chapman, JJ.
    The Office of Public Counsel and Spire Missouri, Inc. appeal from the Report and Order
    on Remand entered by the Public Service Commission. In its sole point on appeal, the Office of
    Public Counsel argues that the Public Service Commission erred in finding that it did not have
    statutory authority to order Spire Missouri, Inc. to issue refunds of ineligible infrastructure
    system replacement surcharges. In its three points on appeal, Spire Missouri, Inc. argues that the
    Public Service Commission erred in disallowing $3,110,787 in infrastructure system replacement
    surcharges. We affirm in part, reverse in part, and remand for further proceedings.
    Parties & Regulatory Background
    The Public Service Commission (PSC) is a Missouri agency responsible for regulating
    the conduct of utility providers. See § 386.250.1 “The Commission employs technical experts
    [Staff] who are responsible for representing the Commission and the State of Missouri in all
    Commission investigations, contested cases, and other proceeding unless PSC Staff timely files a
    notice of its intention not to participate.” Missouri-Am. Water Co.'s Request for Auth. to
    Implement a Gen. Rate Increase for Water & Sewer Serv. Provided in Missouri Serv. Areas v.
    Office of Pub. Counsel, 
    526 S.W.3d 253
    , 256 (Mo. App. W.D. 2017). The Office of Public
    Counsel (OPC) is separate from the PSC and Staff; it is authorized by statute to “represent and
    protect the interests of the public in any proceeding before or appeal from the public service
    commission[.]” See § 386.710. Spire Missouri, Inc. (Spire) is a “gas corporation” and “public
    utility” as those terms are statutorily defined. See § 386.020(18), (43). Spire provides gas
    services to two service areas, Spire East and Spire West.2
    At issue in this case is Spire’s collection of certain infrastructure system replacement
    surcharges (ISRS). In 2003, “[t]he Legislature created ISRS to allow for single-issue ratemaking
    so that gas corporations could recover the costs associated with certain government-mandated
    1
    Statutory references are to RSMo 2016 unless otherwise indicated.
    2
    Spire East was formerly known as “Laclede Gas Co.” and Spire West was formerly known as “Missouri Gas
    Energy” or “MGE.”
    2
    infrastructure replacement projects outside a general ratemaking case.” Laclede Gas Co. to
    Change its Infrastructure Sys. Replacement Surcharge in its Laclede Gas Serv. Territory v. Office
    of the Pub. Counsel, 
    523 S.W.3d 27
    , 30 (Mo. App. W.D. 2017) (citing §§ 393.1009, 393.1012,
    393.1015). Under § 393.1012.1,
    a gas corporation providing gas service may file a petition and proposed rate
    schedules with the commission to establish or change ISRS rate schedules that
    will allow for the adjustment of the gas corporation's rates and charges to provide
    for the recovery of costs for eligible infrastructure system replacements.… An
    ISRS and any future changes thereto shall be calculated and implemented in
    accordance with the provisions of sections 393.1009 to 393.1015. ISRS revenues
    shall be subject to a refund based upon a finding and order of the commission to
    the extent provided in subsections 5 and 8 of section 393.1009.
    Section 393.1009(5)(a) allows for ISRS recovery of costs associated with “[g]as utility plant
    projects,” consisting of “[m]ains, valves, service lines, regulator stations, vaults, and other
    pipeline system components installed to comply with state or federal safety requirements as
    replacements for existing facilities that have worn out or are in deteriorated condition[.]” Thus,
    the ISRS statutes “provide a method, outside of a formal rate case, for a gas corporation to
    recover the cost of certain government-mandated infrastructure system replacement projects via
    a petition to establish or change an ISRS.” In re Laclede Gas Co., 
    417 S.W.3d 815
    , 818 (Mo.
    App. W.D. 2014); see also § 393.1009, et seq.
    Procedural & Factual Background
    The case presently before us was the subject of a previous appeal. See Matter of
    Application of Laclede Gas Co. to Change Its Infrastructure Sys. Replacement Surcharge in Its
    Missouri Gas Energy Serv. Territory v. Office of Pub. Counsel, 
    539 S.W.3d 835
    (Mo. App. W.D.
    3
    2017).3 There, we summarized the factual background of that appeal (and the present one) as
    follows:
    This case arises from [Spire’s] current programs for replacing cast iron and
    unprotected steel gas mains and service lines. Beginning in 2011, [Spire]
    abandoned a previous strategy of replacing only impaired gas mains and service
    lines and implemented a new approach focused on replacing entire neighborhood
    systems at one time, which in this case also involved moving its main lines to
    more convenient locations, changing system pressure, and moving or replacing
    service lines. On September 30, 2016, [Spire] filed petitions with the Commission
    to recover costs associated with the replacement of these neighborhood systems
    through an increase to existing ISRS surcharges. The Commission Staff proposed
    particular adjustments, which were accepted by [Spire]. Relevant to this appeal,
    the OPC objected to [Spire’s] effort to secure cost recovery through ISRS
    surcharges for costs associated with the replacement of plastic mains and service
    lines that were not in a worn out or deteriorated condition.
    Spire 
    I, 539 S.W.3d at 837
    .
    In Spire I, we began by noting that Spire was attempting to recover (through ISRS
    surcharges) the costs of replacing plastic mains and service lines that were not in a worn out or
    deteriorated condition. 
    Id. at 839.
    We held that the costs of replacing plastic components that
    were not worn out or deteriorated were not eligible for ISRS recovery. 
    Id. at 841.
    The Court
    therefore “reverse[d] the Commission’s Report and Order as it relate[d] to the inclusion of the
    replacement costs of the plastic components in the ISRS rate schedules,” and “remanded [the
    case] for further proceedings consistent with this opinion.” 
    Id. The parties’
    motions for
    rehearing and transfer to the Missouri Supreme Court were denied, and our mandate issued on
    March 7, 2018. Before conducting any hearings on remand, the PSC approved new general rates
    for Spire and the previously effective ISRS that formed the basis of the first appeal was reset to
    zero. The new rates went into effect on April 19, 2018.
    3
    To avoid confusion with other cases cited in this opinion involving Laclede Gas Co., we refer to the earlier appeal
    in this case as Spire I.
    4
    On remand, the PSC directed the parties to file briefing as to how to proceed in light of
    this Court’s opinion and mandate in Spire I. After initial briefing by the parties, the PSC held
    oral arguments on August 9, 2018. At the hearing, Spire argued that its method of entirely
    replacing neighborhood systems (including the plastic portions that were not worn out or
    deteriorated) resulted in a cost savings to ratepayers as compared with a program that would
    replace only steel and cast iron facilities while attempting to reuse the existing plastic
    components. In other words, because its replacement of ISRS-ineligible plastic components did
    not generate any added costs, no refund was warranted. Staff argued that Spire had over-
    collected millions of dollars through its replacement of ISRS-ineligible plastic components and
    that a refund of those amounts was appropriate under both Missouri statutory law and the PSC’s
    own rules. The OPC similarly argued that Spire should be required to issue a refund (although
    its calculation of the refund amount differed slightly from Staff’s).
    On August 15, 2018, the PSC entered an Order providing that additional evidence would
    be necessary to resolve the issues raised by this Court’s first opinion and mandate. It scheduled
    an evidentiary hearing for August 27 and August 28, 2018. At the hearing, Spire presented
    expert testimony from its own employees. Spire’s witnesses testified that the company’s practice
    of replacing existing plastic pipe (rather than incorporating it into new systems) had the effect of
    saving its customers money. Specifically, Spire’s Vice President of Operations and Services,
    Craig Hoeferlin, testified that the company analyzed nine replacement projects selected by OPC
    itself (and another project chosen by Spire) and determined that the company’s method of
    replacing existing plastic facilities resulted in a net savings of $230,000 to ratepayers when
    compared with a method that attempted to reuse those components. Spire’s Director of Health,
    Safety, and Environment, Mark Lauber, testified “that the retirement of plastic facilities as part of
    5
    the Company's cast iron and bare steel main replacement programs served to reduce rather than
    increase the costs incurred for these programs and thus the amounts included in the Company's
    ISRS filings.” He opined that the company’s replacement of plastic components (as opposed to
    an approach that sought to reuse those components) had saved its customers millions of dollars.
    The OPC and Staff proffered evidence from their own experts indicating that Spire had
    improperly charged ratepayers for the cost of removing plastic components that were not
    deteriorated or worn out and contended that, in accordance with our opinion in the first appeal,
    the company should be required to issue a refund. Kim Bolin, a Utility Regulatory Auditor for
    the PSC, testified that after this Court issued its opinion in the first appeal, Spire Missouri
    provided Staff with all work order authorizations for projects totaling over $25,000 (except for
    blanket work orders). After analyzing these projects, Staff decided the refund amount owed to
    Spire’s customers using the following methodology: for each project (1) Staff calculated the feet
    of main and service lines replaced and retired, (2) determined the percentage of retired pipe that
    consisted of plastic, and (3) multiplied that percentage times the total cost of the project. Using
    this calculus, PSC Staff concluded that Spire had over-collected $3,110,787 in 2016 and owed its
    ratepayers a refund in that amount.
    Bolin maintained that the percentage-based model was the only method Staff could
    devise to adhere to this Court’s earlier holding that Spire could not legally recover ISRS
    surcharges attributable to removing plastics that were not worn out or deteriorated. Staff elicited
    further testimony from David Sommerer, Manager of the PSC’s Procurement Analysis
    Department. Sommerer acknowledged that Staff’s percentage-based method was “imperfect,”
    but did not fully accept Spire’s position that it had, in the aggregate, saved its customers money
    by virtue of its practice of bypassing and replacing plastic components instead of incorporating
    6
    them into the new systems. He testified to further complications occasioned by Spire’s
    systematic replacement program:
    Q. Is it conceivable that the Company's "systematic" replacement approach has
    ended up replacing main that had already been replaced under its previous
    "piecemeal" or block by block approach?
    A. Yes. It is possible that the Company has previously requested ISRS recovery
    of the cost of inserting this relatively new plastic main under the "piecemeal"
    approach 10 years ago, while re-replacing it in its post-2012 entire cast iron
    system replacement approach. This is important to know to understand whether
    the replacement program is actually incorporating many incidental patches or
    what is being replaced includes much longer segments of previously "replaced"
    cast iron using plastic inserts.
    …
    [A]lthough I am not an attorney, my understanding of the Court of Appeals'
    direction is to establish instances where plastic mains and services were not worn
    out or deteriorated. Upon identifying those situations, the ISRS would then need
    to be reduced by those replacement costs.
    The OPC’s experts testified that insofar as Spire’s ISRS application sought recovery of
    costs attributable to removing and replacing ineligible plastic facilities, the entire application was
    non-compliant with the ISRS statute and thus the entire ISRS amount would need to be refunded.
    Alternatively, the OPC calculated Spire’s ISRS costs attributable to replacing ineligible plastics
    using the same percentage-based method utilized by Staff, albeit while relying upon far fewer
    work orders. In its post-hearing brief, the OPC acknowledged that Staff’s calculation was based
    upon more extensive data and conceded that the PSC would be justified in ordering Spire to
    refund the amount calculated by Staff.
    Following the evidentiary hearing and briefing by the parties, the PSC issued its Report
    and Order on Remand (Remand Order). In its Remand Order, the PSC found that “Staff’s
    witnesses provided credible testimony on the correct methodology for determining the costs of
    7
    ineligible plastic pipe replacements, and Staff’s evidence on this issue was the best evidence
    presented at the hearing.” The PSC observed that Spire had not determined whether any of the
    pipe it was replacing was worn out or deteriorated and concluded that it was attempting to
    recover ISRS costs for the replacement of ineligible components. In addition, it found Spire did
    not provide information necessary “to determine whether any plastic pipe being replaced was
    incidental to and required to be replaced in conjunction with the replacement of other worn out
    or deteriorated components.” The PSC acknowledged Spire’s argument that its neighborhood
    replacement program saved its customers money when compared with a piecemeal approach that
    sought to reuse existing plastic components, but found that Spire had adduced insufficient
    evidence to support this contention. Specifically, it referred to Spire’s analysis of ten work
    orders which purported to show a net cost savings produced by its systematic neighborhood
    replacement program. It ruled that Spire had submitted “far too few work orders” to support its
    position that analysis of all of the relevant projects would have yielded the same result (no added
    costs). It therefore accepted Staff’s calculation and determined that Spire had collected ineligible
    ISRS costs in the amount of $3,110,787.
    The PSC concluded, however, that it did not have authority to order Spire to issue a
    refund to its customers because this Court had not specifically instructed it to do so in Spire I. It
    noted that the Court had not issued such a specific directive even though the OPC had requested
    a refund instruction multiple times in its appellate briefing. It further ruled that the challenged
    ISRS was no longer in effect (because of an intervening general rate case commenced by Spire)
    and that ISRS tariffs generally cannot be corrected retroactively.
    The OPC filed a timely appeal and Spire also appeals.
    8
    Discussion
    Pursuant to § 386.510, we review the PSC’s Remand Order solely to determine whether it
    is lawful and reasonable. “Where ratemaking is at issue, determinations by the Commission are
    favored by a presumption of validity.” In Matter of Kansas City Power & Light Co.'s Request
    for Auth. to Implement a Gen. Rate Increase for Elec. Serv. v. Missouri Pub. Serv. Comm'n, 
    509 S.W.3d 757
    , 765 (Mo. App. W.D. 2016).
    “The lawfulness of the [Commission's] order is determined by ‘whether statutory
    authority for its issuance exists, and all legal issues are reviewed de novo.’ ” In re
    Verified Application & Petition of Liberty Energy (Midstates) Corp., 
    464 S.W.3d 520
    , 524 (Mo. banc 2015). If we find the Commission's order is unlawful, we
    need not reach the issue of the reasonableness of the Commission's order. 
    Id. If we
    find the Commission's order is lawful, then we must determine whether the
    Commission's order is reasonable. 
    Id. “The [Commission's]
    order is determined to
    be reasonable when ‘the order is supported by substantial, competent evidence on
    the whole record; the decision is not arbitrary or capricious[;] or where the
    [Commission] has not abused its discretion.’ ” 
    Id. Laclede Gas
    Co., 523 S.W.3d at 32 
    (citation omitted).
    OPC Appeal
    In its sole point on appeal, the OPC argues that the PSC erred in its determination that it
    lacked statutory authority to order Spire to issue refunds to its customers.4 Both Spire and the
    PSC argue that this issue has been rendered moot because the disputed ISRS has been reset to
    zero.5 Because it presents a threshold issue, we begin by addressing whether the present
    controversy is moot. State, ex rel. Pub. Counsel v. Pub. Serv. Comm'n of the State of Missouri,
    4
    We understand this to be a challenge to the lawfulness of the PSC’s Remand Order, which we review de novo.
    5
    The PSC also asks us to dismiss OPC’s appeal, citing a number of alleged deficiencies in OPC’s brief. Even were
    we to agree that OPC’s brief is defective, the Court has “discretion to review non-compliant briefs ex gratia where
    the argument is readily understandable.” Scott v. King, 
    510 S.W.3d 887
    , 892 (Mo. App. E.D. 2017). Because we
    can easily discern OPC’s arguments, we deny the PSC’s request to dismiss OPC’s appeal.
    9
    
    328 S.W.3d 347
    , 352 (Mo. App. W.D. 2010) (noting that “[a] threshold question in any appellate
    review of a controversy is the mootness of the controversy.”). “A case becomes moot when the
    matter presented for review seeks a decision ‘upon some matter which, if the judgment was
    rendered, would not have any practical effect upon any then existing controversy[.]’” 
    Id. (quoting Precision
    Invs., L.L.C. v. Cornerstone Propane, L.P., 
    220 S.W.3d 301
    , 304 (Mo. banc
    2007)).
    Spire and the PSC cite Matter of Missouri-Am. Water Co., 
    516 S.W.3d 823
    (Mo. banc
    2017) for the proposition that this case is moot.6 In that case, a water utility received approval to
    collect surcharges for certain infrastructure system replacement costs undertaken in St. Louis
    County. Missouri-Am. 
    Water, 516 S.W.3d at 826
    . The OPC filed an application for rehearing,
    arguing that the utility could not recover ISRS costs in St. Louis County because the county’s
    population had fallen below one million inhabitants (a benchmark for ISRS eligibility under §
    393.1003). 
    Id. The PSC
    denied the OPC’s application, and the OPC appealed. 
    Id. While the
    appeal was pending, the utility and “PSC staff reached a stipulation and agreement establishing a
    new base rate that incorporated the costs of the MAWC projects for all then-existing surcharges,
    including the surcharge at issue in this case.” 
    Id. at 826-27.
    The Missouri Supreme Court observed that after the ISRS charges were approved, and
    while their validity was pending appeal, they had been reset to zero and incorporated in the
    utility’s general rate base. 
    Id. at 828.
    It stated that the disputed tariffs had been superseded and
    noted the general rule that “superseded tariffs cannot be corrected retroactively.” 
    Id. The 6
     While the PSC’s Remand Order did not explicitly state that it was precluded from issuing refunds because the case
    had become moot, it quoted extensively from Missouri-Am. Water in support of its conclusion that it could not
    correct superseded “tariffs retroactively by applying a refund prospectively in future ISRS cases.”
    10
    Supreme Court then concluded by holding that the OPC’s challenge to the validity of the
    surcharge had become moot because the surcharge was “no longer in effect” and the Court was
    therefore precluded from granting relief. 
    Id. at 830.
    Missouri-Am. Water is distinguishable from the present case for at least two reasons.
    First, Missouri-Am. Water involved an ISRS surcharge that had been superseded and reset to zero
    during the pendency of the appeal, and before the Missouri Supreme Court handed down its
    opinion and mandate. By contrast, our mandate in Spire I issued on March 7, 2018, while,
    according to the PSC’s Remand Order, Spire’s new general rates went into effect on April 19,
    2018. See § 393.1015.6(1) (“A gas corporation that has implemented an ISRS pursuant to the
    provisions of sections 393.1009 to 393.1015 shall file revised rate schedules to reset the ISRS to
    zero when new base rates and charges become effective[.]”) (emphasis added). Thus, this case
    did not involve a retroactive correction of invalid ISRS surcharges; rather, the challenged
    surcharges were still in effect when our mandate issued.
    Secondly, Missouri-Am. Water addressed only the “propriety” of an ISRS surcharge that
    had been incorporated into the utility’s rate base following a general rate 
    case. 516 S.W.3d at 825
    . The Supreme Court held only that it could not adjudicate the validity of an ISRS surcharge
    that no longer existed. 
    Id. Once the
    surcharge had been reset to zero, the OPC’s challenge to the
    surcharge was rendered moot. 
    Id. at 828.
    The OPC presents a distinct issue in this appeal. It is
    not now challenging the propriety of Spire’s attempts at collecting ISRS surcharges for the costs
    of replacing plastic piping not in a worn out or deteriorated condition. We determined that issue
    in Spire I when we held that those costs are not eligible for ISRS recovery. OPC is instead
    requesting an order that Spire refund the previously collected ISRS-ineligible surcharges to its
    customers.
    11
    Having determined that the OPC’s point on appeal presents an issue that is still ripe for
    review, we turn to the consideration of whether statutory or other authority exists for the PSC to
    order Spire to issue refunds. We conclude that the PSC is so authorized pursuant to §
    386.520.2(1)-(2), which provides as follows:
    In the event a final and unappealable judicial decision determines that a
    commission order or decision unlawfully or unreasonably decided an issue or
    issues in a manner affecting rates, then the court shall instruct the commission
    to provide temporary rate adjustments and, if new rates and charges have not
    been approved by the commission before the judicial decision becomes final and
    unappealable, prospective rate adjustments. Such adjustments shall be calculated
    based on the record evidence in the proceeding under review and the information
    contained in the reconciliation and billing determinants provided by the
    commission under subsection 4 of section 386.420 and in accordance with the
    procedures set forth in subdivisions (2) to (5) of this subsection;
    (2) If the effect of the unlawful or unreasonable commission decision issued on or
    after July 1, 2011, was to increase the public utility's rates and charges in excess
    of what the public utility would have received had the commission not erred or to
    decrease the public utility's rates and charges in a lesser amount than would have
    occurred had the commission not erred, then the commission shall be instructed
    on remand to approve temporary rate adjustments designed to flow through to the
    public utility's then-existing customers the excess amounts that were collected by
    the utility plus interest at the higher of the prime bank lending rate minus two
    percentage points or zero….
    (Emphasis added).7 The PSC found that this statute did not authorize it to order a refund. It
    reasoned that although this Court held in the first appeal that Spire was not permitted to collect
    ISRS costs attributable to the replacement of plastic components that were not worn out or
    deteriorated, the Court did not “instruct the commission to provide temporary rate adjustments”
    7
    The PSC contends on appeal that § 386.520 does not support the issuance of a refund because the statute is
    directory, rather than mandatory. See Frye v. Levy, 
    440 S.W.3d 405
    , 409 (Mo. banc 2014) (“[T]he distinction
    between ‘mandatory statutes’ and ‘directory statutes’ is whether the legislature intended to make all actions that fail
    to comply with that obligation void or ineffective.”). However, the PSC ruled in its Remand Order that a refund was
    not authorized because this Court had not included a refund instruction in Spire I; it did not refuse to order a refund
    because § 386.520 is directory (rather than mandatory) with respect to the Court or the PSC. Thus, we do not need
    to decide whether § 386.520 is “mandatory” or “directory” since that distinction has no bearing on whether Spire I
    contained an instruction to order a refund.
    12
    or otherwise order a refund. The OPC argues, and we agree, that our opinion in Spire I implicitly
    contained such an instruction.
    In the first appeal, we remanded the case for further proceedings consistent with our
    opinion in Spire I. Gerken v. Missouri Dep't of Soc. Servs., Family Support Div., 
    415 S.W.3d 734
    , 738 (Mo. App. W.D. 2013) (“‘It is well settled that the mandate is not to be read and applied
    in a vacuum. The opinion is part of the mandate and must be used to interpret the mandate.’”)
    (quoting Frost v. Liberty Mut. Ins. Co., 
    813 S.W.2d 302
    , 305 (Mo. banc 1991)). In our opinion,
    we concluded that “recovery of the costs for replacement of plastic components that are not worn
    out or in a deteriorated condition is not available under ISRS[.]” Spire 
    I, 539 S.W.3d at 831
    .
    Our mandate required the PSC to conduct proceedings consistent with our opinion, which
    would address its error in allowing interim ISRS surcharges for the replacement of plastic
    components that are not worn out or in a deteriorated condition. In such circumstances, where it
    has been determined “that a commission order or decision unlawfully or unreasonably decided
    an issue or issues in a manner affecting rates” the commission “shall be instructed to provide
    temporary rate adjustments…” § 386.520.2(1). Disallowing such refund not only ignored what
    our mandate clearly entailed (to conduct proceedings necessary to correct the error in over-
    collection of ISRS surcharges) but also ignored what § 386.520.2(1) clearly requires – temporary
    rate adjustments (refunds) to correct the PSC’s error. Additionally, had we concluded that Spire
    was not legally allowed to collect ISRS costs attributable to ineligible replacements, but that it
    nevertheless could keep the costs it collected for such ISRS-ineligible replacements, our opinion
    would have had a negligible impact on the controversy between the parties.8 See State ex rel.
    8
    In the instant case, the OPC seeks the refund of ISRS costs attributable to Spire’s replacement of ineligible plastics
    in 2016. In a separate appeal, the OPC has raised the very same issue for ISRS costs collected by Spire in 2017.
    13
    Missouri Parks Ass'n v. Missouri Dep't of Nat. Res., 
    316 S.W.3d 375
    , 384 (Mo. App. W.D. 2010)
    (“Missouri courts do not issue opinions that have no practical effect and that are only advisory as
    to future, hypothetical situations.”).
    “On remand, proceedings in the trial court should be in accordance with both the mandate
    and the result contemplated in the opinion.” 
    Frost, 813 S.W.2d at 304
    . “What is contemplated in
    an opinion by necessary implication is equivalent to that which is clearly and expressly stated.”
    
    Id. at 305.
    Our opinion in the first appeal held that Spire cannot collect ISRS costs attributable to
    ineligible plastic; by necessary implication, this meant that Spire could not retain (and was
    therefore required to refund) the improperly collected costs.9
    While the 2017 cases were pending before the PSC and before we issued our opinion in Spire I, the parties stipulated
    that our decision in the first appeal would govern both the 2016 and 2017 ISRS cases, where applicable. It is
    noteworthy that in that stipulation, Spire and Staff agreed “not to challenge OPC’s right” “to request that the
    Commission determine the amount of refund, if any, that shall be made in both the [2016 cases] and the [2017
    cases],” in the event that our decision in Spire I held that Spire could not use ISRS to recover the costs of replacing
    plastics that were not worn out or deteriorated.
    9
    In support of its contention that no refunds should be ordered, Spire cites § 386.420.4, which states as follows:
    A full and complete record shall be made of all proceedings before the commission or any
    commissioner on any formal hearing had, and all testimony shall be taken down by a reporter
    appointed by the commission, and the parties shall be entitled to be heard in person or by
    attorney…. In any proceeding resulting in the establishment of new rates for a public utility …,
    the commission shall cause to be prepared, with the assistance of the parties to such proceeding,
    and shall approve, after allowing the parties a reasonable opportunity to provide written input, a
    detailed reconciliation containing the dollar value and rate or charge impact of each contested
    issue decided by the commission, and the customer class billing determinants used by the
    commission to calculate the rates and charges approved by the commission in such
    proceeding. Such information shall be sufficient to permit a reviewing court and the
    commission on remand from a reviewing court to determine how the public utility's rates and
    charges, including the rates and charges for each customer class, would need to be temporarily
    and, if applicable, permanently adjusted to provide customers or the public utility with any
    monetary relief that may be due in accordance with the procedures set forth in section 386.520.
    In the event there is any dispute over the value of a particular issue or the correctness of a
    billing determinant, the commission shall also include in the reconciliation a quantification of
    the dollar value and rate or charge impact associated with the dispute.
    (Emphasis added). While the first appeal was pending, the parties attempted to comply with § 386.420.4 by
    submitting reconciliations to the PSC setting forth the dollar value of the ineligible plastic replacements. However,
    the parties did not agree on the value of the ineligible plastic parts. At the initial post-remand oral argument, Spire’s
    counsel conceded: “I don't believe that there is a legal barrier to having additional proceedings if you believe that
    14
    We find that the PSC has the authority and the duty to order refunds of ISRS over-
    collections.10 The portion of the PSC’s Remand Order finding that it was not statutorily
    authorized to issue a refund was unlawful. The OPC’s sole point on appeal is granted.
    Spire Appeal
    Spire has also filed an appeal. In its second point on appeal, Spire argues that the PSC’s
    Remand Order disallowing ISRS recovery for the costs of replacing plastic facilities in
    connection with its systematic neighborhood replacement program (approximately $3.1 million)
    was unsupported by substantial and competent evidence and was therefore arbitrary and
    unreasonable.11 Spire cites the testimony of its own experts, who opined generally that there
    was appropriate.” However, Spire now contends that, because the calculated disallowance was based on evidence
    adduced at the remand hearing, rather than a reconciliation figure previously approved by the PSC, “this was simply
    not a case that lent itself to an adjustment as contemplated by §386.520.2(1) and §386.420.4.” We reject this
    argument. While § 386.420.4 provides a mechanism for calculating temporary or permanent rate adjustments in
    accordance with § 386.520.2(1), it does not prohibit the PSC from conducting further evidentiary proceedings to
    determine the rate adjustments that may be required to provide customers with monetary relief.
    10
    The PSC also argues that § 386.520 does not support the issuance of a refund because such relief is separately
    provided for under § 393.1015.8, which states, in relevant part:
    In the event the commission disallows, during a subsequent general rate proceeding, recovery of
    costs associated with eligible infrastructure system replacements previously included in an ISRS,
    the gas corporation shall offset its ISRS in the future as necessary to recognize and account for any
    such overcollections.
    See also § 393.1015.5(2) (prescribing a reconciliation process where it has been determined that a gas corporation
    over or under-collected ISRS revenues). The PSC argues that the specific provisions of § 393.1015 “prevail over
    the general rate adjustment provisions of Section 386.520.” Assuming arguendo that § 393.1015 is more specific
    than § 386.520, the principle that a more specific statute prevails over a less specific one “applies only in situations
    where there is a ‘necessary repugnancy’ between the statutes.” Greenbriar Hills Country Club v. Dir. of Revenue, 
    47 S.W.3d 346
    , 352 (Mo. banc 2001). Discerning no conflict between §§ 386.520 and 393.1015, we find the principle
    inapposite in this case.
    11
    Spire’s first point on appeal contends that the PSC’s Remand Order was unlawful in that the PSC failed to follow
    our directive in Spire I to calculate the costs incurred to replace ineligible plastic. The gist of Spire’s argument is
    that the percentage method adopted by the PSC did not accurately capture the costs of replacing ineligible plastic
    and that the PSC therefore failed to calculate those costs in violation of our previous opinion and mandate. As
    discussed more fully in our analysis of Spire’s second point, we affirm the PSC’s factual determination that Staff’s
    percentage-based methodology constituted the “best evidence…to calculate the costs of th[e] ineligible plastic pipe
    replacements.” This holding is dispositive of Spire’s first point, which is denied.
    15
    were no incremental costs of replacing and retiring plastic facilities when compared with a
    system that attempted to reuse those components. Because its systematic replacement of plastic
    components did not incur additional costs, Spire contends, no refunds are warranted.
    As the party that filed the ISRS applications, Spire bore the burden of proof in this matter.
    § 393.150.2 (“At any hearing involving a rate sought to be increased, the burden of proof to
    show that the increased rate or proposed increased rate is just and reasonable shall be upon the
    gas corporation[.]”).12 “The party having the burden of proof carries ‘the risk of
    nonpersuasion.’ Therefore, if the evidence is ‘equally balanced and the [fact-finder] is left in
    doubt, the litigant having the burden of proof loses; he must sustain his case by the greater
    weight of the evidence.’” In re Request for an Increase in Sewer Operating Revenues of
    Emerald Pointe Util. Co., 
    438 S.W.3d 482
    , 490–91 (Mo. App. W.D. 2014) (citations omitted).
    Additionally, the PSC’s Remand Order “has a presumption of validity” on appeal and the burden
    is on Spire “to prove by clear and satisfactory evidence that the order was unlawful or
    unreasonable.” 
    Id. at 489-90.
    Spire alleges that the PSC erred in that it “disregarded and ignored the undisputed and
    unimpeached evidence presented by the Company’s expert engineering witnesses[.]” This
    contention ignores our standard of review under which we recognize that the PSC “is free to
    believe none, part, or all of the testimony” presented at the hearing. State Ex rel. Praxair, Inc. v.
    Pub. Serv. Comm'n of the State of Missouri, 
    328 S.W.3d 329
    , 342 (Mo. App. W.D. 2010).13 “If
    12
    See also Clapper v. Lakin, 
    343 Mo. 710
    , 723, 
    123 S.W.2d 27
    , 33 (Mo. 1938) (“The burden of proof, meaning the
    obligation to establish the truth of the claim by preponderance of the evidence, rests throughout upon the party
    asserting the affirmative of the issue[.]”).
    13
    Spire cites Cardwell v. Treasurer of State of Missouri, 
    249 S.W.3d 902
    (Mo. App. E.D. 2008) for the proposition
    that the PSC may not “arbitrarily disregard and ignore competent, substantial and undisputed evidence of witnesses
    who were not impeached[.]” See 
    id. at 907
    (“The Commission may not arbitrarily disregard and ignore competent,
    16
    the trier of fact does not believe the evidence of the party bearing the burden, it properly can find
    for the other party.” White v. Dir. of Revenue, 
    321 S.W.3d 298
    , 305 (Mo. banc 2010). To the
    extent that Spire assigns error to the PSC for not crediting the testimony of the company’s
    witnesses, the claim is unavailing.
    Furthermore, the Remand Order does not suggest that the PSC “disregarded” or
    “ignored” Spire’s expert testimony. The PSC stated that Spire had not conducted a review to
    determine whether the plastic piping it replaced was in a worn out or deteriorated condition and
    noted the acknowledgement of Spire’s own witness (Craig Hoeferlin) that the plastic facilities
    “should last indefinitely.” It found further that Spire had not presented evidence to determine
    whether some of the plastic components it was replacing were incidental to and required to be
    replaced in conjunction with the replacement of nearby pipe that was worn out or deteriorated.
    See Spire 
    I, 539 S.W. at 839
    n.5 (“We recognize that the replacement of worn out or deteriorated
    components will, at times, necessarily impact and require the replacement of nearby components
    that are not in a similar condition. Our conclusion here should not be construed to be a bar to
    ISRS eligibility for such replacement work that is truly incidental and specifically required to
    complete replacement of the worn out or deteriorated components.”). The PSC ruled that Spire
    had not attempted to quantify the amount of pipe it replaced that was ISRS-eligible or the
    amount of pipe it replaced that was not. The Remand Order made note of the report Spire
    substantial, and undisputed evidence of witnesses who are not shown by the record to have been impeached[.]”).
    But Cardwell recognized that an agency “is free to disbelieve uncontradicted and unimpeached testimony[,]”
    particularly where “the record is not wholly silent on the issue of credibility.” 
    Id. at 907-08
    (emphasis added). In its
    Remand Order, the PSC specifically stated: “Any finding of fact for which it appears that the Commission has made
    a determination between conflicting evidence is indicative that the Commission attributed greater weight to that
    evidence and found the source of that evidence more credible and more persuasive than that of the conflicting
    evidence.” The PSC’s adoption of Staff’s percentage model as against a different approach proposed by Spire
    reflects the PSC’s belief that Staff’s evidence was more credible and carried greater weight.
    17
    presented at the hearing purporting to show that the company reduced, rather than increased, its
    replacement costs in nine out of the ten work orders that its expert analyzed. However, it
    concluded that this sample size was far too small “to extrapolate…and reach a similar result in
    the hundreds of work orders that Spire Missouri did not analyze.”
    In sum, the PSC found that Spire had not presented evidence sufficient to support its
    claim that its replacement of plastic components (without regard to whether they were worn out
    or deteriorated) reduced its ISRS costs. It found also that Spire had not even attempted to
    quantify its ISRS costs attributable to the replacement of plastic components that were not worn
    out or deteriorated, despite our previous holding that those costs were not ISRS-eligible. Spire
    bore the burden of proving that the costs it was attempting to recover were ISRS-eligible and the
    PSC found that it had not adduced sufficient evidence to carry that burden. The PSC did not err
    in rejecting Spire’s argument that it incurred no incremental costs by replacing rather than
    reusing ISRS-ineligible plastic facilities.
    We next consider whether the PSC’s chosen methodology for calculating a disallowance
    was lawful and supported by substantial evidence. On this point, the PSC made the following
    findings:
    Here, Staff provided the best evidence of a methodology to calculate the costs of
    those ineligible plastic pipe replacements. Staff reviewed all of the work order
    authorizations provided by the company to determine the feet of main and service
    lines replaced and retired by the type of pipe, and then applied the actual
    individual plastic main and services line percentages to the work order cost to
    determine the value of the replacement pipe for the work order.
    “This court will not substitute its judgment for that of the Commission.” State ex rel. GS
    Techs. Operating Co. v. Pub. Serv. Comm'n of State of Mo., 
    116 S.W.3d 680
    , 687 (Mo. App. W.D.
    2003). Further, “[w]e must defer to the Commission's decisions regarding the credibility of
    18
    witnesses and not second-guess issues that are within the PSC's area of expertise.” In Matter of
    Kansas City Power & Light Co.'s Request for Auth. to Implement a Gen. Rate Increase for Elec.
    
    Serv., 509 S.W.3d at 770
    . Accordingly, we afford deference to the PSC’s chosen methodology
    for calculating an ISRS disallowance. 
    Id. Staff’s witness,
    David Sommerer, acknowledged that the percentage methodology did not
    perfectly reflect the costs of ineligible plastic pipe replacements. At the evidentiary hearing, a
    PSC Chairman observed, “There clearly are problems with the methodology and they’ve been
    aired publicly all day today. I’m struggling with any other methodology that makes more sense.”
    Kim Bolin similarly testified that Staff’s percentage-based model “was the only method [Staff]
    could come up with.”
    We again stress that it was Spire’s burden to prove that some or all of its plastic
    replacements were eligible for ISRS recovery. Spire chose to rest on its theory that no ISRS
    collections should have been disallowed because its replacement of ineligible plastics did not
    increase ISRS costs. The PSC found that this theory was not supported by sufficient data. Spire
    did not conduct a case-by-case review to determine exactly which of its plastic replacements
    involved components that were in fact worn out or deteriorated. The PSC was therefore
    precluded from taking a more nuanced approach to the disallowance issue than the percentage-
    based method advocated by the OPC and Staff. We cannot conclude that the PSC erred in
    determining that the percentage model constituted “the best evidence of a methodology to
    calculate the costs of th[e] ineligible plastic pipe replacements.” Given the lack of evidence
    adduced by Spire, the percentage-based model was the only method the PSC could employ to
    calculate the cost of ISRS-ineligible replacements, and thereby calculate a disallowance in
    accordance with our opinion and mandate in Spire I. The PSC’s calculation of Spire’s ISRS
    19
    disallowance was supported by substantial competent evidence and is not arbitrary or
    unreasonable.
    In its third point on appeal, Spire argues that it was deprived of a fair trial and that its due
    process rights were violated in that, inter alia, it had “only five business days to prepare and file
    testimony.”14 This claim is unpersuasive. The issue of Spire’s replacement of ISRS-ineligible
    plastic components was litigated in the first evidentiary hearing held on January 3, 2017.
    Following that hearing, the PSC entered an order finding that Spire could recover ISRS costs
    associated with the incidental replacement of plastic facilities undertaken in conjunction with the
    replacement of worn out and deteriorated cast iron and steel pipe. We reversed this finding in
    Spire I, holding that Spire could not legally recover the cost of plastic replacements that were not
    worn out or deteriorated. Our opinion was handed down in November 2017 and our mandate
    issued in March 2018. As the hearing on remand was held in August 2018, Spire had been on
    notice for approximately nine months that the PSC would be considering a disallowance
    reflecting Spire’s replacement of ineligible plastics. In addition, Spire (along with the other
    parties) submitted initial post-remand briefing and participated in oral arguments held prior to the
    August 2018 evidentiary hearing. The parties participated in another round of briefing
    immediately before the evidentiary hearing, and then also submitted post-hearing briefing. We
    are satisfied that Spire was afforded a full and fair opportunity to be heard on the issue of the
    ineligible plastic replacements. State ex rel. Fischer v. Pub. Serv. Comm'n of Missouri, 
    645 S.W.2d 39
    , 43 (Mo. App. W.D. 1982) (“Due process requires that administrative hearings be fair
    and consistent with rudimentary elements of fair play. One component of this due process
    14
    The PSC issued an order on August 17, 2018, requiring the parties to submit the written direct testimony of their
    witnesses on August 22, 2018.
    20
    requirement is that parties be afforded a full and fair hearing at a meaningful time and in a
    meaningful manner.”) (internal citation omitted).
    Spire also complains that the PSC applied the percentage-based method to “blanket work
    orders,” which Spire’s expert (Glenn Buck) described as unplanned projects (undertaken, for
    example, in response to “leak surveys” or “leak crawls”) where the company discovers and
    rectifies leaks or other defects in its facilities. Spire contends that all of the costs incurred in
    completing these blanket work orders are ISRS-eligible, and that the PSC therefore erred in
    disallowing a percentage of those costs. In making this argument, Spire simply assumes that any
    time a pipe is leaking or damaged in some way it is worn out or deteriorated within the meaning
    of section 393.1009.5(a) and that the costs of replacing such infrastructure are recoverable under
    ISRS.15 This is incorrect. In Matter of Verified Application & Petition of Liberty Energy
    (Midstates) Corp., 
    464 S.W.3d 520
    , 525 (Mo. banc 2015) (clarifying that a replacement project is
    only ISRS-eligible under section 393.1009.5(a) when the replaced infrastructure has become
    deteriorated through “a gradual process that happens over a period of time rather than an
    immediate event.”).
    15
    Spire’s expert testimony conflicted on this issue. Spire’s expert, Craig Hoeferlin, initially testified in response to
    questions posed by the PSC:
    Q. So are you essentially saying that whenever there's a leak then that, by definition, makes it
    worn out and deteriorated?
    A. If it's on the bare steel or the cast iron, yes. If it's on a plastic main, no, it would not be worn
    and deteriorated. If we find a leak on a plastic fitting, that would not be covered under the ISRS
    blanket work orders.
    However, Spire then elicited testimony from another expert witness (Glenn Buck) as follows:
    Q. Okay. Let me ask you another direct question about the blanket work order issue. Are the
    facilities that are included in the blanket work orders worn out or in deteriorated condition?
    A. For the blankets I would believe so, yes.
    Q. And that would include the plastic that's in the blankets?
    A. That's correct.
    21
    Finally, Spire asserts that the PSC’s rejection of the company’s analysis of ten work
    orders (purporting to show a net savings occasioned by its wholesale replacement program when
    compared with a piecemeal replacement program) was arbitrary and capricious. In essence,
    Spire argues that the PSC commonly accepts and relies upon representative samples “when
    evaluating large databases like those involved in an ISRS filing.” Spire therefore challenges the
    PSC’s finding in this case that the company had submitted “far too few work orders” to treat the
    sampling as truly representative and conclude that Spire’s neighborhood replacement program
    produced no net costs for its ratepayers. However, even if Spire’s contention is true, we will not
    fault the PSC for departing from a practice it has followed in other rate cases. “An
    administrative agency is not bound by stare decisis. Courts are not concerned with alleged
    inconsistency between current and prior decisions of an administrative agency so long as the
    action taken is not otherwise arbitrary or unreasonable.” State ex rel. GTE N., Inc. v. Missouri
    Pub. Serv. Comm'n, 
    835 S.W.2d 356
    , 371 (Mo. App. W.D. 1992) (citations and quotation marks
    omitted). As we have explained more fully above, the PSC’s chosen methodology for
    calculating a refund to Spire’s customers was not arbitrary or unreasonable.16
    16
    Spire relatedly contends that its due process rights were violated because the PSC “ignor[ed]” its statistical studies
    purporting to “demonstrate[] the impact of plastic replacements on ISRS costs and charges.” Spire argues that this
    was in violation of § 536.070(11), which provides:
    The results of statistical examinations or studies, or of audits, compilations of figures, or surveys,
    involving interviews with many persons, or examination of many records, or of long or
    complicated accounts, or of a large number of figures, or involving the ascertainment of many
    related facts, shall be admissible as evidence of such results, if it shall appear that such
    examination, study, audit, compilation of figures, or survey was made by or under the supervision
    of a witness, who is present at the hearing, who testifies to the accuracy of such results, and who is
    subject to cross-examination, and if it shall further appear by evidence adduced that the witness
    making or under whose supervision such examination, study, audit, compilation of figures, or
    survey was made was basically qualified to make it. All the circumstances relating to the making
    of such an examination, study, audit, compilation of figures or survey, including the nature and
    extent of the qualifications of the maker, may be shown to affect the weight of such evidence but
    22
    Spire has not met its burden of rebutting the presumption of validity we grant to the
    PSC’s decision. It has not demonstrated that the PSC’s calculation of disallowed ISRS
    surcharges was unlawful, unreasonable, arbitrary or capricious, undertaken without a fair
    hearing, or unsupported by substantial and competent evidence. Laclede Gas 
    Co., 523 S.W.3d at 32
    .
    Spire’s first, second, and third points on appeal are denied.
    Conclusion
    The PSC’s decision is affirmed in part, reversed in part, and remanded for further
    proceedings consistent with this opinion.
    Thomas N. Chapman
    /s/
    Thomas N. Chapman, Judge
    All concur.
    such showing shall not affect its admissibility[.]
    The PSC responds that the requirements prescribed in § 536.070(11) did not apply in this case because the PSC was
    not obligated to hold an evidentiary hearing on remand. See § 393.1015.2(3). We need not resolve this issue, as
    nothing in the PSC’s Remand Order indicates that it ignored the analyses submitted by Spire; it simply found Staff’s
    expert evidence more credible and persuasive than Spire’s. The PSC’s determinations are presumptively valid. In re
    Request for an Increase in Sewer Operating Revenues of Emerald Pointe Util. 
    Co., 438 S.W.3d at 490
    –91. Thus,
    absent some evidence to the contrary, we must presume that it considered all relevant evidence in reaching its
    decision.
    23