Lake Ozark-Osage Beach Joint Sewer Board v. Missouri Department of Natural Resources, Land Reclamation Commission and Magruder Limestone Co., Inc. , 491 S.W.3d 667 ( 2016 )


Menu:
  •                                                  In the
    Missouri Court of Appeals
    Western District
    
    LAKE OZARK-OSAGE BEACH JOINT                          
    SEWER BOARD, ET AL.,                                     WD78869
    Appellants,                           OPINION FILED:
    
    v.                                                       June 14, 2016
    
    MISSOURI DEPARTMENT OF                                
    NATURAL RESOURCES, LAND                               
    RECLAMATION COMMISSION AND                            
    MAGRUDER LIMESTONE CO., INC.,                         
    
    Respondents.                         
    
    Appeal from the Circuit Court of Miller County, Missouri
    The Honorable Sanford Francis Conley, IV, Judge
    Before Division Three:
    Gary D. Witt, P.J., James Edward Welsh, and Anthony Rex Gabbert, JJ.
    The Lake Ozark-Osage Beach Joint Sewer Board and Larry and Vicky Stockman
    ("Appellants") appeal the Missouri Land Reclamation Commission's decision to grant Magruder
    Limestone Co., Inc., ("Magruder") a permit to operate a limestone quarry on a site adjacent to a
    wastewater treatment plant owned and operated by the Lake Ozark-Osage Beach Joint Sewer
    Board ("Sewer Board").1 We affirm.
    1
    This case comes before this Court following our remand in Lake Ozark/Osage Beach Joint Sewer Board v.
    Missouri Department of Natural Resources, 
    326 S.W.3d 38
    , 39 (Mo. App. 2010). Portions of the facts and
    procedural history are adopted from that opinion without further attribution.
    Statutory Framework
    Missouri's Land Reclamation Act ("the Act"), §§ 444.760-.790,2 is administered by the
    Director of the Department of Natural Resources ("Department"). § 640.010.6. The stated
    purpose of the Act is to "strike a balance" between the surface mining of minerals and the
    reclamation of land subjected to surface disturbance by that mining. § 444.762. To that end, the
    Act grants the Land Reclamation Commission ("Commission") the power to "[e]xamine and pass
    on all applications and plans and specifications submitted . . . for the method of operation and for
    the reclamation and conservation of the area of land affected by the operation." § 444.767(3).
    The Act requires any operator desiring to engage in surface mining to "make written
    application to the director for a permit." § 444.772.1. Once the Director deems the application
    complete, there is a period of public notice and comment. Saxony Lutheran High Sch., Inc. v.
    Mo. Dep't of Nat. Res., 
    404 S.W.3d 902
    , 906 (Mo. App. 2013) (citing § 444.772.10). The
    Director must promptly investigate the application and then make a recommendation to the
    Commission as to whether the permit should be issued or denied. § 444.773.1. If the Director's
    recommendation is to issue the permit, the Commission is authorized to grant a formal hearing
    "to formally resolve concerns of the public" before passing on the application. § 444.773.3.
    Factual and Procedural Background
    Magruder operates several quarries under a permit from the Commission. This case
    originated in April 2007, when Magruder filed an application to expand its permit to operate a
    limestone quarry on a 212-acre site in Miller County. Magruder sought permission from the
    Commission to engage in surface mining on 205 of those acres. The new quarry site is adjacent
    to a wastewater treatment plant operated by the Sewer Board. Magruder's application proposed
    2
    Statutory references are to the Revised Statutes of Missouri (RSMo) 2000, as updated by the 2013
    Cumulative Supplement, except where otherwise noted.
    2
    quarry activity approximately 700 feet from that plant. In addition, two force main sewer lines
    transverse through the center of the proposed quarry site and transmit all the sewage from the
    City of Osage Beach to the sewer treatment plant.3
    Magruder's application was deemed complete, and it published the required notice. Both
    Magruder and opponents of its permit application then made presentations at the Commission’s
    next public meeting. The Sewer Board and several citizens thereafter requested a formal public
    hearing, which the Commission granted. The Commission appointed a hearing officer, who
    conducted seven days of hearings. The hearing officer ultimately recommended that Magruder's
    expansion permit be approved, with special conditions,4 for the area west of the sewer line
    easement. The approved mining area was limited to approximately fifty-two acres. On July 29,
    2008, the Commission approved the hearing officer's recommended order and adopted the
    hearing officer's findings of fact and conclusions of law as its final decision.
    The Miller County Circuit Court reversed the Commission's decision to grant the permit.
    On appeal, this Court found that the decision was made upon unlawful procedure because the
    Commission incorrectly imposed the burden of persuasion on the petitioners in contravention of
    § 444.773 and 10 C.S.R. 40-10.80(3). Lake Ozark/Osage Beach Joint Sewer Bd. v. Mo. Dep't of
    Nat. Res., 
    326 S.W.3d 38
    , 45 (Mo. App. 2010). Consequently, we reversed the Commission's
    decision to grant the permit and remanded with instructions to apply the correct burden of proof
    in a new hearing. 
    Id. On remand,
    the Commission designated Commissioner Winn from the Administrative
    Hearing Commission to take evidence and make recommendations. Following a five-day
    3
    The City of Osage Beach owns the sewer lines but is not a party to this litigation.
    4
    The conditions concerned restricting the days, times, and location of the blasting with regard to the sewer
    line easement; using seismographs to monitor the sewer plant and sewer lines; and restricting the elevation of the
    mine floor to run at or above the grade of the sewer line easement. Lake Ozark/Osage 
    Beach, 326 S.W.3d at 40
    n.4.
    3
    hearing, the Commissioner issued a Recommended Decision. She found that the Sewer Board
    met its burden of production by "establishing issues of fact regarding the impact, if any, of the
    permitted activity on [its] health, safety, or livelihood" but the individual petitioners (including
    the Stockmans5) did not. See § 444.773. The Commissioner also found, however, that Magruder
    met its burden of persuasion that the expanded permit, subject to certain conditions, "will not
    unduly impair the health, safety or livelihood of the petitioners." She recommended, therefore,
    that Magruder's application for permit expansion be granted with eight specific conditions.
    The Commission took up the matter at its next public meeting. It voted unanimously to
    adopt the recommendations and findings of Commissioner Winn and to grant Magruder's permit,
    but it incorporated only the first five of the recommended conditions. The Commission also
    modified Condition 4 to make it easier to understand.
    The Appellants filed a petition for judicial review, claiming that the Commission erred in
    failing to accept all of the hearing officer's suggested conditions, and that the Commission lacked
    the authority to impose any conditions that were not in Magruder's application. The circuit court
    rejected those arguments, stating that it had reviewed the Commission's reasons for removing
    Conditions 6, 7, and 8 and found no basis for rejecting the Commission's findings. The court
    also found that the "Commission had the authority to impose or reject conditions when issuing a
    permit" and affirmed the Commission's decision to grant the permit with conditions.
    The Sewer Board and the Stockmans appeal.
    Standard of Review
    On appeal from the circuit court's review of an agency's decision, we review the agency's
    actions and not those of the circuit court. Albanna v. State Bd. of Registration for Healing Arts,
    5
    The Stockmans own and operate an RV park that is approximately a mile from the proposed mine site and
    is serviced by the Lake Ozark/Osage Beach sewer system. Their concern is with the impact that the proposed
    mining activity will have on their business.
    4
    
    293 S.W.3d 423
    , 428 (Mo. banc 2009). Our review is limited to determining whether the
    agency's decision was constitutional; was within the agency's statutory authority and jurisdiction;
    was supported by competent and substantial evidence upon the whole record; was authorized by
    law; was made upon lawful procedure with a fair trial; was not arbitrary, capricious or
    unreasonable; and was a proper exercise of discretion. Lagud v. Kansas City Bd. of Police
    Comm'rs, 
    136 S.W.3d 786
    , 791 (Mo. banc 2004); § 536.140.2. In reviewing the agency's
    decision, we must consider the entire record and not simply the evidence that supports the
    agency's decision. Coffer v. Wasson-Hunt, 
    281 S.W.3d 308
    , 310 (Mo. banc 2009). "If the
    evidence permits either of two opposing findings, deference is afforded to the administrative
    decision." 
    Id. We review
    questions of law de novo. 
    Saxony, 404 S.W.3d at 906
    .
    Point I
    The Appellants first contend that the Commission erred in granting Magruder's permit
    because the Commissioner's Order is not supported by competent and substantial evidence and is
    arbitrary and capricious, in that the Commission removed Conditions 6, 7, and 8, which
    Commissioner Winn deemed necessary to the grant of the permit.
    Section 444.773.3 of the Act provides that, where the Director recommends issuing a
    permit, a formal hearing may be held upon a timely petition from "any person whose health,
    safety or livelihood will be unduly impaired by the issuance of this permit." Lake Ozark/Osage
    
    Beach, 326 S.W.3d at 43
    . Following the formal hearing, if the Commission finds, "based on
    competent and substantial scientific evidence on the record, that an interested party's health,
    safety or livelihood will be unduly impaired by the issuance of the permit," then the Commission
    may deny the permit application. § 444.773.4; 10 C.S.R. 40-10.080(3)(D). At least four of the
    Commission members must approve any "final action by the commission." § 444.787.4.
    5
    Pursuant to section 444.789.3, the Commission may designate a hearing officer to hold a
    hearing and make recommendations to the Commission. Here, the Commission designated
    Commissioner Winn to do so. In the course of the hearing, the Commissioner accepted portions
    of the evidence from the 2008 hearing that the parties designated and heard additional testimony.
    As noted, the Commissioner ultimately found that the Sewer Board "met its burden of
    production" but that the individual petitioners did not. The Commissioner also found, however,
    "that Magruder met its burden of persuasion."6 She recommended that Magruder's application
    for permit expansion be granted subject to these Conditions:
    1) Magruder must adhere to its blast plan. . . . Any significant alterations to the blast
    plan should be filed with the LRC and a copy provided to the Sewer Board. If
    smaller blast, smaller holes or lesser bench height is warranted because of concerns
    about safety or proximity to the sewer system, such "downward departures" should
    be allowed without notice.
    2) The conditions set forth in the blast plan shall apply to the entire 205-acre mine
    plan.
    3) Blasting shall be confined to weekdays between 8:00 a.m. and 5:00 p.m. Magruder
    shall notify sewer plant staff prior to each blast. The Sewer Board shall provide the
    name of the appropriate contact person to [Magruder].
    4) The elevation of the mine floor at the quarry shall be maintained above the sewer
    lines to reduce the possibility of ground shifting or block movement in the pipeline
    area from blasting.
    5) Magruder shall not stockpile rock on or within 150 feet of the sewer line easement.
    6) Trucks or other heavy equipment shall not travel over the sewer line easement. If
    that necessity arises, Magruder shall consult with the Sewer Board and the City of
    Osage Beach to engineer and build a safe crossing over the sewer lines.
    7) Magruder shall employ the best available technology for dust suppression and
    control.
    6
    As explained in Lake Ozark/Osage 
    Beach, 326 S.W.3d at 43
    , the burden of proof for parties before the
    Commission is set forth in 10 C.S.R. 40-10.080(3)(B), which provides that "[t]he burden of establishing an issue of
    fact regarding the impact, if any, of the permitted activity on a hearing petitioner's health, safety or livelihood shall
    be on that petitioner by competent and substantial scientific evidence on the record," and "[o]nce such issues of fact
    have been established, the burden of proof for those issues is upon the applicant for the permit." (Emphasis added.)
    6
    8) If the Sewer Board documents a correlation between blasting at the quarry site and
    disruption to [its] UV [ultraviolet treatment] system, Magruder shall pay the cost of
    repairs and shall adjust its blasts to eliminate or minimize any such disruption.
    At the Commission's next public meeting, a member of the Land Reclamation Program
    Staff presented the Staff's recommendations for modifications to the conditions recommended by
    Commissioner Winn. The Staff's recommendations pertinent to this appeal are as follows:
    4. Condition 4 was modified slightly from the original recommendation staff had
    prepared and placed in the packets for the meeting, and was altered to match the
    original recommendation of Hearing Officer Tichenor, from the first hearing. The
    condition deals with the elevation of the mine floor. The elevation of the floor of
    the mine (quarry) shall run at or above the grade of the City of Osage Beach's
    sewer line easement as it crosses the Magruder property, so that no blasting holes
    will be drilled to a depth that would be below the elevation of that grade.
    Permittee shall submit an annual report prepared by a Missouri registered
    Professional Engineer to verify compliance with this requirement.
    Justification for the above modification is that the proposed language is easier
    to understand for all parties and meets the intent of the Administrative Hearing
    Commission's recommendation.
    ....
    6. Trucks or other heavy equipment shall not travel over the sewer easement line.
    If that necessity arises, Magruder shall consult with the Sewer Board and the City
    of Osage Beach to engineer and build a safe crossing over the sewer line.
    Staff recommendation is not to include this as a condition of the permit because
    this condition is between the company and the Sewer Board.
    7. Magruder shall employ the best available technology for dust suppression and
    control.
    Staff recommendation is not to include this as a condition of the permit because
    this activity will be regulated and enforceable under the Missouri Clean Air
    Conservation Law.
    8. If the Sewer Board documents a correlation between blasting at the quarry site
    and disruption to the UV system, Magruder shall pay the cost of repairs and shall
    adjust its blasts to eliminate or minimize such disruption.
    Staff recommendation is not to include this as a condition of the permit because
    it's not feasible for Land Reclamation Program staff to make a determination
    as to a cause of UV system disruption and nearly impossible to enforce.
    7
    Following the Staff recommendations, each side was allowed five minutes to address the
    Commission. One of the Commissioners then moved "to adopt the findings of the hearing
    officer with the changes presented by staff and the further change for Condition 4 to include the
    words 'at the surface' following 'the Magruder property.'" Another Commissioner seconded the
    motion, and a third Commissioner commented "that these conditions narrowed the aspects to the
    things that are under the jurisdiction of the Land Reclamation Program while other issues are
    enforced in different ways but they are addressed."
    The Commission voted unanimously to adopt the recommendations and findings of
    Commissioner Winn and to grant Magruder's permit. Pursuant to Staff recommendations, the
    Commission rejected Conditions 6, 7, and 8. The Commission also modified Condition 4 to
    make it easier to understand. In a letter dated January 13, 2014, the Commission issued "formal
    notice" of its decision, stating that it had adopted the Commissioner's recommended decision,
    including the permit conditions as modified by the Commission.
    The evidence supported the Commission's decision to incorporate these modifications.
    As to Condition 6, Magruder's representative testified at the formal hearing that Magruder would
    use a conveyor system to transport material at the mine and would engineer and build a proper
    crossing if it needs to use trucks to convey the material over the sewer lines. The Commission,
    as the finder of fact, was free to believe this testimony, Dierks v. Kraft Foods, 
    471 S.W.3d 726
    ,
    737 (Mo. App. 2015), and to conclude from it that Condition 6 was unnecessary and that
    engineering a crossing, if needed, is "between [Magruder] and the Sewer Board."
    As to Condition 7, requiring Magruder to "employ the best available technology for dust
    suppression," the Staff pointed out that it was unnecessary because Magruder is subject to
    Missouri's Clean Air Conservation Law dust emission limits. §§ 643.010-.620.
    8
    In rejecting Condition 8, requiring Magruder to pay for repairs if Magruder's blasting
    causes a disruption of the UV system, the Staff noted that it would be "nearly impossible to
    enforce," in that it would not be "feasible" for the Staff to determine the cause of a UV system
    disruption. Moreover, the evidence showed that the treatment plant's alert system recently had
    been upgraded so that personnel are notified within 90 seconds of any failure in the UV system;
    that resetting the system takes about five minutes; that if the UV system is offline only for a few
    minutes, the quality of the plant's effluent will not be impaired; and that Condition 3 requires
    Magruder to provide advance notice of blasting, after which plant personnel can inspect the UV
    system. In light of all this, it is not surprising that the Commission determined that Condition 8
    was not needed.
    Finally, the decision to modify Condition 4 was based on the Staff's advice that the new
    language would make the provision more understandable.7
    The Appellants contend that the Commission's decision to accept Commissioner Winn's
    recommendation to grant the permit while modifying her suggested conditions was "outside the
    Commission's authority" and thus "arbitrary and capricious." This argument, which suggests that
    the Commission was bound by the Commissioner's recommendations, is without merit.
    As noted, the Commission may designate a hearing officer to conduct a hearing and make
    recommendations to the Commission. § 444.789.3. Those recommendations have no binding
    effect, however, because the Commission "shall make the final decision" on a permit application,
    and all Commission members participating in the decision must "review the record before
    making the decision." See 
    id. The Act
    clearly leaves the decision to grant or deny the permit
    7
    As modified, Condition 4 stated:
    The elevation of the floor of the mine (quarry) shall run at or above the grade of the City of Osage
    Beach's sewer line easement as it crosses the Magruder property at the surface, so that no blasting
    holes will be drilled to a depth that would be below the elevation of that grade.
    9
    "solely to the discretion of the Commission," which "retains the ultimate authority" to make the
    decision following the public hearing. 
    Saxony, 404 S.W.3d at 908
    , 911 (citing § 444.773.1-2 &
    § 444.789.3).
    The Appellants' suggestion that the Commission must either accept or reject the
    Recommended Decision in its entirety is simply incorrect. The legislature gave the Commission,
    not the hearing officer, the power to "examine and pass on" mining-permit applications. See §
    444.767(3). Accordingly, the Commission acted within its statutory authority in determining
    whether or not to adopt any of the hearing officer's conditions.
    The Appellants clarify in their reply brief that they are not claiming that the Commission
    does not have the authority to make its own decision on the merits or modify recommendations.
    Rather, they are arguing that if the Commission does modify the recommendations, it must issue
    its own findings of fact and conclusions of law. Specifically, they contend that Magruder
    eliminates the requirement that the [Commission] make "findings" to support its
    decision. See RSMo. 444.773 (If the commission changes or modifies the decision
    recommended by the administrative hearing officer, it shall issue its own decision,
    which shall include findings of fact and conclusions of law).
    The Appellants assert, in other words, that the Commission may not grant the permit and then
    reject some of the required conditions, but must reject some or all of the factual findings and then
    make its own findings. Absent new findings, they argue, "the decision to grant a permit was
    arbitrary and capricious."
    This claim, however, also is without merit. The portion of section 444.773 on which the
    Appellants rely was not in effect at the time of the Commission's decision here. That provision
    was first added to section 444.773 in 2014. Here, the Commission issued its final decision letter
    10
    on January 13, 2014 (seven months prior to the new provision's effective date).8 At that time, the
    Commission was not statutorily required to issue its own decision with findings of fact and
    conclusions of law if it changed or modified the recommended decision. See § 444.773, RSMo,
    Cum. Supp. 2013.
    In addition, the Appellants fail to show how they were prejudiced by the Commission's
    failure to issue findings of fact and conclusions of law. "Only prejudicial error is reversible
    error." 
    Saxony, 404 S.W.3d at 912
    . Here, the Commission's formal notice of its decision, with
    attached minutes from the hearing on the Recommended Decision, explained the Staff's
    reasoning for its recommended modifications, which the Commission adopted.
    We also disagree with the Appellants' (rather convoluted) claim that the Commission's
    decision to eliminate some of the recommended conditions somehow rendered the entire decision
    unsupported by competent and substantial evidence. Our review of the record reveals that the
    Commission's decision was "supported by competent and substantial evidence upon the whole
    record." See § 536.140.2; 
    Coffer, 281 S.W.3d at 310
    .
    Finally, to the extent that the Appellants argue that the Commission was required to adopt
    all eight of the suggested conditions in order for Magruder to satisfy its burden of proof, we
    again disagree.9 As discussed above, the hearing officer is not the ultimate decision maker on
    mining permits; that role is the Commission's alone. 
    Saxony, 404 S.W.3d at 908
    -09; § 444.767.
    8
    See L.2014, H.B. No. 1201, § A, eff. Aug. 28, 2014; L.2014, S.B. No. 642, § A, eff. Aug. 28, 2014. As
    amended, § 444.773.2, RSMo, Cum. Supp. 2015, now provides:
    The commission shall issue its own decision, based on the appeal, for permit issuance, denial,
    suspension, or revocation. If the commission changes a finding of fact or conclusion of law
    made by the administrative hearing commission, or modifies or vacates the decision
    recommended by the administrative hearing commission, it shall issue its own decision, which
    shall include findings of fact and conclusions of law. [Emphasis added.]
    9
    We also reject the Appellants' complaint that the language added to Condition 4 came directly from the
    2008 decision which incorrectly applied the burden of proof. They do not show that this specific language was in
    any way defective, and the evidence shows that the language was employed solely to make Condition 4 easier to
    understand. The Commission did not err in employing the clearest, most effective language, regardless of its origin.
    11
    Here, the Commission ultimately decided, based on the evidence, that Magruder met its burden
    of proof even without three of the conditions proposed by the hearing officer. We find no error
    in that decision. Point I is denied.
    Point II
    The Appellants next argue that the Commission erred in granting Magruder's permit
    because its Order is made "upon unlawful procedure and without a fair trial," in that
    Commissioner Winn's act of sua sponte adding conditions to the permit carried the burden of
    proof for Magruder. As the Commission appoints a hearing officer only for the limited purpose
    of conducting a hearing and making recommendations, the issue is whether the Commission has
    authority to attach conditions to a permit. §§ 444.767(3) & .765(4); see also § 536.140.2
    (allowing judicial inquiry into whether the agency's action was in excess of its authority).
    We find that the Commission does have such authority. We note, first, that section
    444.773 was amended in 2014 to include language explicitly permitting the Director to impose
    conditions. The revised version of the statute now states: "In issuing a permit, the director may
    impose reasonable conditions consistent with the provisions of sections 444.760 to 444.790."
    § 444.773.1, RSMo, Cum. Supp. 2015. The Commission decided this case prior to the addition
    of that sentence, however; thus, we look to the case law to assist with the interpretation of the
    Act as it existed at the time.
    In Saxony, the Southern District of this Court determined that the Commission had the
    authority to impose a condition on a permit to operate a limestone mine before it approved the
    
    application. 404 S.W.3d at 906-11
    . While the quarry's application was pending in that case, a
    newly enacted law took effect requiring a 1,000-foot buffer between a mining area and a school.
    
    Id. at 905.
    The quarry's application had specified a 55-foot buffer. 
    Id. The school
    tried to stop
    12
    the public hearing and to strike the application after the law passed. 
    Id. The applicant
    responded
    by offering to revise the plan to reflect a boundary at least 1,000 feet from the school. 
    Id. As in
    this case, the school argued that the Commission lacked the authority to impose conditions on the
    approval of a permit, but, rather, had authority only to approve or deny the application as filed.
    
    Id. The hearing
    officer recommended granting the permit subject to the revision, however, and
    the Commission adopted the recommendation. 
    Id. Following review
    in the circuit court, which
    vacated the decision, the appeals court upheld the Commission's decision. 
    Id. at 905,
    911.
    In examining section 444.767(3), which grants the Commission the power to "[e]xamine
    and pass on all applications," the Saxony Court reasoned that the plain meaning of pass "suggests
    the Commission is empowered to consider the evidence in front of it and render its decision." 
    Id. at 909.
    It further noted that, by stating that the Act's purpose is to "strike a balance" between the
    various interests, the legislature intended for "the Commission [to] exercise [its] judgment and
    craft a decision that would balance those interests." 
    Id. To read
    the Act to "suggest [that] the
    Commission's role is limited essentially to just checking one of two boxes on a form," the Court
    stated, "would limit the Commission's ability to balance and resolve [the relevant] concerns" and
    would disregard the plain meaning of "pass on" in the Act. 
    Id. Citing other
    Department of Natural Resources agencies which have provisions for issuing
    conditional permits, the Saxony Court stated, "we have no reason to believe [that] the legislature
    intended [the Commission] to be the only permit-granting entity without power to impose
    conditions on such permits during the process." 
    Id. at 910.
    The Court held that "the only logical
    conclusion is that the Commission's power to 'pass on' applications under the Act includes the
    ability to conditionally approve permit applications in ways that align with the Act and fulfill the
    Commission's purpose to balance interests" of operators and the public. 
    Id. at 911.
    13
    The Court also noted that section 444.787.2 of the Act empowers the Director to
    eliminate "violation[s] of any provision of [the Act] or any rule or regulation . . . or any condition
    imposed on the permit." 
    Id. at 909-10.
    The Court also opined that the Act must be read in
    conjunction with the Surface Coal Mining Law, which expressly allows the Director and the
    Commission to modify a permit application as an alternative to outright denial. 
    Id. at 910.
    The Saxony Court concluded, in light of the foregoing, "that the Commission had the
    authority to approve [the] permit subject to the condition that [the applicant] relocate its mine
    plan boundary." 
    Id. at 912.
    Although the Saxony Court at times framed the issue more narrowly,
    nothing in its reasoning is limited to the specific circumstances of that case; rather, its reasoning
    necessarily decides the broader question of whether the Commission has the authority to attach
    conditions generally.10
    In light of the compelling reasoning in Saxony, we conclude that the Commission had the
    authority to impose conditions on Magruder's permit at that time. We also believe that the 2014
    revision of the statute to now specifically authorize the Director to impose conditions on a permit
    supports this. Consequently, Point II also is denied.
    Conclusion
    Based on the foregoing, we affirm the circuit court's judgment which upheld the
    Commission's decision to grant Magruder its permit subject to the conditions cited.
    /s/ JAMES EDWARD WELSH
    James Edward Welsh, Judge
    All concur.
    10
    The Appellants' claim that adding conditions deprived them of the opportunity to present evidence
    regarding their impact is refuted by the fact that most of the conditions appear in Magruder's blasting plan, and they
    were, in fact, discussed at the hearing.
    14
    

Document Info

Docket Number: WD78869

Citation Numbers: 491 S.W.3d 667

Judges: James E. Welsh, Judge

Filed Date: 6/14/2016

Precedential Status: Precedential

Modified Date: 1/12/2023