Northern Lights, Inc. v. State , 51 State Rptr. 394 ( 1994 )


Menu:
  •                                        No.    93-554
    IN THE SUPREME COURT OF THE STATE OF MONTANA
    1994
    NORTHERN LIGHTS, INC.,
    an Idaho corporation,
    Plaintiff and Respondent,
    THE STATE OF MONTANA,
    DEPARTMENT OF HIGHWAYS,
    Defendant and Appellant.
    APPEAL FROM:               District Court of the First Judicial District,
    In and for the County of Lewis and Clark,
    The Honorable Dorothy McCarter, Judge presiding.
    COUNSEL OF RECORD:
    For Appellant:
    Nick A. Rotering and James R. Beck, Department of
    Transportation, Helena, Montana
    For Respondent:
    Larry D. Epstein and Thane P. Johnson, Werner,
    Epstein & Johnson, Cut Bank, Montana
    ~F?wd; '"
    73
    .
    :            ...
    7   : : ,.-'
    Submitted on Briefs:     April
    P.   I
    L- r .J
    , ,A 6 '
    I
    ?3    1994                       Decided:   May 3
    Chief Justice J. A. Turnage delivered the Opinion of the Court.
    The State of Montana, Department of Highways, now the Depart-
    ment   of Transportation    (Department), appeals   from a   summary
    judgment order of the First Judicial District Court, Lewis and
    Clark County.     The court ordered the Department to reimburse
    Northern ~ights,
    Inc. (Northern), an Idaho utility company, for 75
    percent of expenses incurred in relocating its utility facilities
    which were situated near a federal-aid secondary road in rural
    Lincoln County, Montana.    We affirm.
    The Department questions whether the District Court erred in
    determining that 3 60-4-403, MCA, required the State to reimburse
    Northern for 75 percent of its relocation expenses and whether
    Northern's claim for reimbursement was barred by 5 27-2-211, MCA.
    Northern owns certain utility facilities located in Lincoln
    County.    Portions of the facilities are located on United States
    Forest Service land and portions are located on private properties.
    Prior to 1986, the Federal Highway Administration       (FHWA)
    decided to finance and construct a forest highway on Montana's
    federal-aid secondary road located in Lincoln County. By agreement
    With FHWA, the Department purchased necessary rights-of-way and
    administered the road project for the FHWA.
    Part of the Department's administration of the project
    entailed asking Northern to relocate its utility facilities which
    were located on Forest Service land.      Northern complied.     The
    District Court specifically noted:
    2
    Northern Lights began the process of moving its utilities
    in November of 1987 and completed the principal portion
    of its work by April of 1988.       However, the entire
    relocation project was not completed until March 1989.
    The Department and Northern did not operate pursuant to any written
    contract; the Department did, however, prepare and offer Northern
    a utility relocation agreement, which Northern refused to sign.
    In January 1989, Northern requested a hearing pursuant to
    5 60-4-402, MCA, and the Department declined to grant the request.
    This declaratory judgment action followed that denial and the
    Department's refusal to reimburse Northern for a portion of the
    cost of relocating its utility facilities.
    ISSUE 1
    Did the District Court err in determining that the Department
    must reimburse Northern for 75 percent of relocation expenses as
    set forth in 9 60-4-403, MCA?
    This Court reviews a district court's decision for or against
    summary judgment by utilizing the same criteria the court used in
    its deliberations.    Knight v. City of Missoula (1992), 
    252 Mont. 232
    , 
    827 P.2d 1270
    . Summary judgment is appropriate when there are
    no disputed issues of material fact and one party is entitled to
    judgment as a matter of law.    Rule 56(c), M.R.Civ.P.   Here, where
    both parties agree there are no disputed issues of material fact,
    we review whether Northern is entitled to judgment as a matter of
    law.
    The Department asserts that judgment in favor of Northern is
    improper because it believes that the provisions of 5 60-4-403,
    MCA, do not apply when federal funds are used to construct a
    highway in Montana and when the utility company involved has a
    Forest Service permit to be on the land.       We disagree.
    When interpreting statutes, courts are to "simply        . . .
    ascertain and declare what is in terms or in substance contained
    therein, not to insert what has been omitted or to omit what has
    been inserted."      Section 1-2-101, MCA; see also State ex rel.
    Neuhausen v. Nachtsheim (1992), 
    253 Mont. 296
    , 299, 
    833 P.2d 201
    ,
    203-04.     Section 60-4-403, MCA, provides:
    Seventy-five percent of all costs of relocation, includ-
    ing the costs of acquisition of new right-of-way, of
    dismantling and of removal, shall be paid by the depart-
    ment as a cost of highway construction.
    The section does not list any prerequisites for payment, contrary
    to the Department's assertions.     It does not contemplate, mention
    or refer to federal or state ownership of the highway. Cf. 5 60-4-
    401, MCA.     It does not require that the utility company own, rent
    or lease the land. Nor does it require that the Department and the
    utility   company have a written      contract, specifying payment
    provisions.
    The only requirement before 75 percent of relocation costs
    must be paid by the Department under 5 60-4-403, MCA, is that a
    utility company relocate its utility facilities in order for the
    Department to further highway construction. Northern did relocate
    its facilities. We therefore conclude that the District Court did
    not err in determining that the Department must pay 75 percent of
    Northern's relocation costs.
    ISSUE 2
    Was Northern's claim for reimbursement of relocation expenses
    barred by 5 27-2-211, MCA?
    The Department argues that Northern's claim for reimbursement
    was barred by the statute of limitations set forth at 5 27-2-211,
    MCA, because it alleges that Northern completed relocation of the
    utility   facilities during April    1988.    While we agree that
    Northern's claim for reimbursement was a statutory claim with a
    two-year statute of limitations pursuant to P 27-2-211, MCA, we
    disagree with the Department's allegation that the relocation was
    completed during April of 1988.
    The Department bases its allegation on answers it received
    during the discovery phase of this litigation, which were filed in
    connection with the Department's June 1991 motion for summary
    judgment. Specifically, when the Department asked Michael Fox, the
    general manager of Northern, whether the relocation project was
    completed during April, 1988, Fox said yes.    Fox later clarified
    his response by stating:
    As indicated in [the answer to the Department's ques-
    tion],  ...  the major portion of the relocation work for
    which reimbursement is sought in this action, was
    completed by the latter part of April, 1988. It was this
    work to which affiant referred in response to Defendant s
    counsel's question at deposition herein, indicating that
    this portion of the work was, in fact, completed in April
    of 1988.
    Plaintiff corporation utilized the services of an
    independent contractor in the major portion of this
    relocation project and it was that work, referred to as
    "primary utility relocationv1 which affiant referred in
    to
    his response to deposition questioning by counsel for
    defendant and in response to Interrogatories from
    Defendant.   This contractorvs work was substantially
    completed in April of 1988.
    Plaintiff Is claim upon which this action is based
    includes various items of work that were conducted in
    relocation of facilities for this project in the months
    following April of 1988 including work done directly by
    Plaintiff in November of 1988 and relocation of poles as
    recently as March, 1989. Work Orders Nos. 88-865, 88-822
    and 89-820 (referred to in affiant's deposition and
    Defendant s brief) were completed after the main project
    was completed and are a part of Plaintiff Is claim herein.
    In its November 4, 1991, Order, the court stated:
    In this claim for payment under Section 60-4-403, the
    utility is entitled to recover a percentage of all costs
    of relocation. Thus, the full demand for payment cannot
    be made until the entire relocation project is completed.
    On this basis, Northern Light's cause of action accrued
    upon completion of its relocation project, in March of
    1989. Since the complaint was filed in July of 1990,
    less than two years later, the action is not barred.
    After reviewing the record, we conclude that the court did not err
    in determining that Northern's claim was not barred by 1 27-2-211,
    MCA.   Affirmed.
    We concur:
    

Document Info

Docket Number: 93-554

Citation Numbers: 265 Mont. 47, 51 State Rptr. 394

Judges: Harrison, Hunt, Trieweiler, Turnage, Weber

Filed Date: 5/3/1994

Precedential Status: Precedential

Modified Date: 8/6/2023