Tri-County Atlas, Inc. v. Brummer , 238 Mont. 331 ( 1989 )


Menu:
  •                                                                                        No.       88-531
    I N THE SUPREME COURT OF THE STATE O F MONTANA
    1989
    TRI-COUNTY ATLAS,                                             INC.,
    P l a i n t i f f and R e s p o n d e n t ,
    -vs-
    JAMES BRUMMER, d / b / a BRUMMER E N T E R P R I S E S ,
    D e f e n d a n t and A p p e l l a n t .
    APPEAL FROM:                                           D i s t r i c t C o u r t of t h e F i r s t J u d i c i a l D i s t r i c t ,
    I n and f o r t h e C o u n t y o f L e w i s & C l a r k ,
    The H o n o r a b l e Henry L o b l e , J u d g e presiding.
    COUNSEL O F RECORD:
    For Appellant:
    C h a r l e s E. P e t a j a , H e l e n a , M o n t a n a
    T h o m a s H. C l a r y ; C l a r y & C l a r y , G r e a t F a l l s ,           Montana
    For Respondent:
    P. K e i t h K e l l e r ; K e l l e r , R e y n o l d s , D r a k e ,        Sternhagen
    & Johnson, H e l e n a , M o n t a n a
    S u b m i t t e d on B r i e f s :   J u n e 1, 1 9 8 9
    t -.
    oi                   -._.
    -,
    i-3
    I                                              Decided:
    e            ~ u g u s t3 , 1 9 8 9
    ..,
    -I_-
    Filed:                            -
    C .
    -   * -
    1-                                           i,   "-
    -
    -
    i                    3
    ? .
    7   *     i
    ,-
    -. 3                                                             "    Clerk
    - a                 ..--
    *'
    .I                      3     Ci
    *4    I-.
    6-        3
    '    .I
    4"
    c_r
    -..--
    Mr. Justice John Conway Harrison delivered the Opinion of the
    Court.
    This appeal arises from an action to foreclose a
    mechanics' lien filed by Tri-County Atlas, Inc. for work and
    materials supplied to a construction project owned by James
    Brummer. The District Court for the First Judicial District,
    Lewis and Clark County, entered judgment in favor of
    Tri-County. We affirm and remand for correction of costs.
    James Brummer is a general contractor who conceived and
    developed the construction of a professional office building
    located   in Helena, Montana.         Brummer, through his
    corporation, Brummer     Enterprises,   Inc.,  designed   and
    constructed the building, and utilized subcontractors for
    electrical, plumbing, heating, air conditioning and other
    aspects of the construction. Tri-County was hired by Brummer
    to install the heating, ventilation, and air conditioning
    (HVAC) system, and the domestic plumbing in the building.
    The parties had no written contract but merely discussed
    their agreements orally.
    Tri-County began work on the building in early February
    of 1987, and continued installation of both the HVAC system
    and the domestic plumbing until August, when it walked off
    the job because of nonpayment.      In September, Tri-County
    filed its lien and brought this action to foreclose. Brummer
    counterclaimed   for    alleged   defects   in   Tri-County's
    workmanship.
    The District Court entered judgment for Tri-County, and
    awarded damages, attorney's fees and costs. Brummer raises
    the following issues for our review:
    1. Was the District Court's award of damages to
    Tri-County supported by substantial evidence?
    2. Was it error for the District Court to award
    attorney's fees and costs?
    The standard of review is clear. We must affirm the
    trial court if its findings are supported by substantial
    evidence and are not clearly erroneous.          We will not
    substitute our judgment for that of the District Court.
    Hammerquist v. Employment Sec. Div. of Montana Dept. of Labor
    and Industry (Mont. 1988), 
    749 P.2d 535
    , 536, 45 St.Rep. 261,
    262; Meridian Minerals Co. v. Nicor Minerals, Inc. (Mont.
    1987), 
    742 P.2d 456
    , 461, 44 St.Rep. 1516, 1523.
    At trial, Tri-County alleged it was hired on a
    not-to-exceed basis, plus specific amounts to be paid for
    additional constant air volume (CAV) and variable air volume
    (VAV) units. Brummer claimed Tri-County had given a flat bid
    of $112,000 for the entire HVAC system.      The evidence was
    clear, however, that no final plans were submitted to
    Tri-County on which it could make a firm flat bid because the
    plans were evolving as the project developed. Additionally,
    there was evidence that other subcontractors were hired by
    Brummer on similar time-and-materials, or price-not-to-exceed
    bases.
    Although Brummer's counterclaim alleged the work
    performed by Tri-County was not done in a workmanlike manner,
    no evidence was produced at trial that Tri-County's
    workmanship was deficient. Tri-County admitted some work was
    not completed, because it pulled off the job.      Tri-County
    also admitted there were some product defects which would
    have been covered by the manufacturer's warranty, had Rrurnrner
    not failed to pay.       However, there was no evidence the
    workmanship was poor. Tri-County's witnesses and even one of
    Brummer's witnesses testified that Tri-County's workmanship
    was very good.
    The evidence was extensive and complicated. During the
    four day trial, the District Court heard testimony from
    eleven witnesses, examined all of the exhibits and determined
    that Tri-County was entitled to judgment. In its Opinion,
    Memorandum of Decision, and Order, the District Court made
    the following conclusions:
    The evidence of each party was
    diametrically opposed to the evidence of
    the opposing party. The matter resolved
    itself into a question of which party
    presented the most credible evidence. If
    the version of the Plaintiff is accepted,
    the version of the Defendant must be
    rejected, and vice versa. As the trial
    progressed, it became very clear to the
    Court that Plaintiff presented the most
    credible    witnesses    and    evidence.
    Defendant, on the other hand, lacked
    credibility to a pronounced degree. His
    version of the events is wholly rejected
    by the Court.
    We find no abuse of discretion.      The findings were
    supported by substantial evidence in the record.          The
    judgment of the District Court is affirmed.
    Brumrner's final issue alleges the District Court erred
    in its award of attorney's fees and costs to Tri-County. The
    first basis of the alleged error, which Tri-County admits,
    involves the inclusion of expert witness fees and deposition
    costs within the award of attorney's fees and costs. Section
    26-2-505, MCA. We remand this matter to the District Court
    to deduct these costs from the award.
    The second basis of alleged error involved settlement
    negotiations between the parties. Brummer apparently offered
    to pay Tri-County the amount of its lien as settlement of
    Tri-County's claims.     Tri-County refused because it had
    already invested substantial amounts of money in attorney's
    fees in its attempt to recover. The District Court refused
    to hear the evidence because it involved settlement
    negotiations.
    Brummer cites Schillinger v. Brewer (1985), 
    215 Mont. 333
    , 
    697 P.2d 919
    , to support his claim that because
    Tri-County refused to accept his settlement offer, it is not
    entitled     to   attorney's   fees.       However,   the   facts   of
    Schillinger differ from those of this case, and do not
    support Brumrner's theory. In Schillinger, the District Court.
    awarded the defendant attorney's fees when judgment was
    entered for an amount less than that offered in settlement by
    the defendant.     We reversed the award of attorney's fees
    because the defendant was only entitled to costs, not
    attorney's fees. If Schillinger has any application to this
    case, it supports Tri-County's claim for attorney's fees.
    Donnes v. Orlando (1986), 
    221 Mont. 356
    , 
    720 P.2d 233
    .
    Tri-County prevailed in its action and was therefore entitled
    to recover attorney's fees and costs.
    Affirmed and remanded for reduction of costs awarded to
    Tri-County in accordance with this opinion.
    We concur:                             U
    

Document Info

Docket Number: 88-531

Citation Numbers: 238 Mont. 331, 779 P.2d 46

Judges: Gulbrandson, Harrison, Hunt, McDONOUGH, Sheehy

Filed Date: 8/3/1989

Precedential Status: Precedential

Modified Date: 8/6/2023