Anderson v. Hobbs ( 1981 )


Menu:
  •                                  No. 81-97
    IN THE SUPREME COURT OF THE STATE OF MONTANA
    1981
    LEN ANDERSON, d/b/a LEN ANDERSON
    CONSTRUCTION COMPANY,
    Plaintiff and Respondent,
    NORMAN D. HOBBS, individually and NORMAN
    D. HOBBS, d/b/a C. D. VENTURES,
    Defendant and Appellant.
    Appeal from:          District Court of the Fifth Judicial District,
    In and for the County of Beaverhead.
    Honorable Frank Blair, Judge presiding.
    Counsel of Record:
    For Appellant:
    Harrison, Loendorf and Poston, Helena, Montana
    For Respondent:
    Drysdale, McLean, Screnar        &   Cok, Bozeman, Montana
    Submitted on briefs: August 27, 1981
    Filed: gkc. -   'T   [h!8;i
    Clerk
    Mr. Justice John Conway Harrison delivered the Opinion of
    the Court.
    This appeal arises from a contract for construction
    on appellant's nursing home in Dillon, Montana.                 The parties
    entered into the written agreement in January 1977, and the
    work was completed sometime in the late summer of 1977.
    Respondent filed a mechanics' lien against appellant's
    property on October 19, 1977.          After trial without a jury,
    the District Court of the Fifth Judicial District upheld the
    lien and issued a judgment for $15,687.92 plus interest and
    attorney fees.      This appeal followed.
    In December       1976, at the request of appellant,
    respondent,       a general     contractor    doing   business      as   Len
    Anderson Construction Co., a sole proprietorship, began work
    on Park View Acres in Dillon, Montana, a nursing home owned
    by   appellant, Norman D. Hobbs, doing business as C. D.
    Ventures.
    In January 1977 the parties entered into a written
    contract    whereby     respondent would       renovate    the    existing
    fifty-four-bed facility of Park View Acres and add a fifty-
    four-bed wing to the building.         The contract provided appel-
    lant would pay respondent all costs plus an eight percent
    contractor's fee.         Costs    included all costs necessarily
    incurred in the proper performance of work paid by the con-
    tractor; all wages paid for labor in the direct employ of
    the contractor; all salaries of contractor's employees; a
    portion of reasonable transportation, traveling and hotel
    expenses    of    the   contractor, its officers          and    employees
    incurred in the discharge of their duties; the cost of all
    materials,       supplies and     equipment    incorporated       into   the
    work; all payments made by the contractor to subcontractors
    for work performed      according to      subcontracts under          this
    agreement; and costs, including transportation and main-
    tenance, of all materials, supplies, equipment, temporary
    facilities and hand tools not owned by the workmen, which
    are consumed in the performance of the work, and the costs
    less salvage value on such items used but not consumed which
    remained property of the contractor.
    Respondent concluded construction on the project in
    the summer of 1977.     On October 19, 1977, respondent filed a
    lien in the amount of $31,218.27.         On the lien application
    respondent    stated   his    final day   of   performance       on   the
    project was July 21, 1977.        At trial respondent testified
    his last full-time work on the project was in the middle of
    August   1977.    Respondent also introduced a "punch list"
    prepared by appellant's employees and dated September 23,
    1977.    Respondent argued the "punch list" established the
    last day     respondent spent any      time    on   the     job was    in
    September.    The costs claimed by respondent were supported
    almost exclusively at trial by cancelled checks.
    The District Court found the lien was filed within
    the ninety-day period        required by Montana         statute.     The
    court also found respondent's lien valid and enforceable and
    made the following determination of the amount owing:
    Costs for Anderson's
    out-of-pocket expenses.       . . . . .    .$150,362.72
    Defendant's payments
    to date for expenses.      .......              139,633.00
    $    10,729.72
    Due Plaintiff for costs.      .......           .$    10,729.72
    Contractor's fee as a portion
    of 8% of contract and
    total costs on contract .        ....      .$366,977.56
    Contractor's fee equals 8%
    of $366,977.56, for a
    total of.     .. .
    . .      ..
    .       .....           29,358.28
    Defendant's payment to date
    for contractor's fee. . .     . . . . .     12,600.00
    Due Plaintiff for contractor's
    fee     ...............                . $ 16,758.28
    Total due to Plaintiff by
    Defendant for costs     ........            10,729.72
    Total due to Plaintiff by
    Defendant for fees. .     . . . . . . .     16,758.20
    TOTAL.    . . . . . . . . . . . . . . . .   .$   27,487.92
    LESS THE FOLLOWING OFFSETS:
    Liquidated damages. . . . .     . . . .      8,000.00
    Lumber from personal stock.      . . . . 3,800.00
    TOTALOFFSETS.      .     .    .     .     . .$11,800.00
    TOTAL DUE TO     PLAINTIFF . . . . . . . . . $ 15,687.92
    Four issues are before this Court:
    1.    Was   the lien filed by    respondent within         the
    statutory ninety-day period?
    2.   Are there gross and substantial exaggerations in
    claims made which constitute fraud and void the filed lien?
    3.   Did the District Court err in failing to make
    certain deductions to the amount of the lien?
    4.   Did the District Court err in determining in the
    memorandum supporting its findings of fact and conclusions
    of law that Exhibit K was inadmissible as hearsay?
    To perfect a mechanics' lien it must be filed within
    ninety days after material or machinery is furnished or work
    or labor performed.       Section 7-3-511(1), MCA.         Appellant
    argues   there   is no    credible evidence on       the   record   to
    support the District Court's finding that the lien was filed
    within the statutory period.       Respondent filed the lien on
    October 19, 1977, and on the lien stated the last work had
    been done on July 21, 1977.      Appellant claims that the last
    work was performed by respondent on July 15, 1977, which was
    when the nursing home opened. At trial, respondent testified
    the date listed on the lien was incorrect and that, in fact,
    h i s l a s t f u l l t i m e o n t h e j o b was i n t h e m i d d l e o f A u g u s t
    and t h a t he r e t u r n e d i n S e p t e m b e r t o c o m p l e t e t h e p r o j e c t .
    Respondent a l s o s u b m i t t e d i n t o e v i d e n c e a "punch l i s t " p r e -
    p a r e d by a p p e l l a n t ' s employee c o n t a i n i n g t h e d a t e S e p t e m b e r
    23.
    The          District      Court     found     the     lien      had        been       filed
    w i t h i n t h e n i n e t y - d a y p e r i o d and s p e c i f i e d r e s p o n d e n t ' s work
    was c o m p l e t e d on A u g u s t 1 9 , 1 9 7 7 .
    The s t a n d a r d of        t h i s C o u r t on r e v i e w i s w h e t h e r t h e
    D i s t r i c t C o u r t ' s f i n d i n g s and c o n c l u s i o n s a r e s u p p o r t e d by
    s u b s t a n t i a l c r e d i b l e evidence.         T o e c k e s v . Baker ( 1 9 8 0 ) ,          -
    Mont   .             ,    6 1 
    1 P.2d 609
    ,    37 S t . R e p .   948.          If    substantial
    evidence e x i s t s ,           t h i s Court w i l l n o t o v e r t u r n t h e D i s t r i c t
    C o u r t . Schuman v . S t u d y Comm'n o f Y e l l o w s t o n e County ( 1 9 7 8 ) ,
    
    176 Mont. 3
    1 3 , 578 P . 2 d 291.
    It       is     apparent       from     the     record         and        the    District
    C o u r t ' s f i n d i n g s t h a t t h e c o u r t gave c o n s i d e r a b l e weight t o
    r e s p o n d e n t ' s t e s t i m o n y a t t r i a l t h a t h i s l a s t f u l l - t i m e work
    on t h e p r o j e c t was             i n mid-August       1977.          In its supporting
    memorandum, t h e D i s t r i c t C o u r t c h o s e A u g u s t 1 9 , 1 9 7 7 , a s t h e
    final date.                The r e c o r d makes no m e n t i o n o f             that specific
    d a t e i n August.              T h e r e f o r e , t h e f i n d i n g of August 19 c a n n o t
    be a f f i r n e d .       T h i s C o u r t w i l l , however, g i v e c r e d e n c e t o t h e
    weight t h e D i s t r i c t Court obviously gave r e s p o n d e n t ' s t e s t i -
    mony.
    "The c r e d i b i l i t y and w e i g h t g i v e n t h e w i t n e s s e s           ...
    is n o t f o r t h i s Court t o determine.                    T h i s is a p r i m a r y func-
    tion       of    a       trial    judge    sitting        without      a    jury;           it    is   of
    special          consequence            where     the     evidence         is     conflicting."
    Hellickson           v.     B a r r e t t M o b i l e Home T r a n s p o r t ,        Inc.       (1973),
    
    161 Mont. 455
    , 459, 
    507 P.2d 523
    , 525.           Where the evidence
    indicates reasonable grounds for different conclusions, the
    findings of the District Court will not be disturbed. Morgen
    &   Oswood Const. Co. v. Big Sky of Mont. (1976), 
    171 Mont. 268
    , 274, 
    557 P.2d 1017
    , 1021; Morrison v. City of Butte
    (1967), 
    150 Mont. 106
    , 112, 
    431 P.2d 79
    , 83.
    If respondent's last work on the project occurred any
    time in August or September, the filing of the lien was
    within the statutory ninety-day period.           An exact date in
    August or September, however, is necessary for an accurate
    accounting of the $100-a-day offset allowed for late comple-
    tion of the job.        We therefore remand this matter for a
    hearing to establish the exact date in August or September
    on which respondent completed his full-time work on the job.
    The next issue before us is appellant's contention
    that respondent's claim contained such gross and substantial
    exaggerations as to constitute         fraud    and   invalidate the
    lien.
    Fraud must be plead affirmatively to be relied on as
    a defense.       Rule   8(c),   M.R.Civ.P.;    Ekestrand   v.   Wunder
    (1933), 
    94 Mont. 57
    , 
    20 P.2d 622
    .             In the case before us
    fraud was not plead in either the original or the amended
    answer.     Therefore, it cannot now be argued as a defense to
    the lien.
    Appellant also claims the District Court erred             in
    failing to make     reductions in the lien amount for three
    items.
    The first item appellant claims was erroneously
    allowed by the District Court is $2,558.60 of the $7,000
    claimed paid     to Simkins-Hallin.       Respondent    submitted a
    c a n c e l l e d check f o r $7,000 i n s u p p o r t of t h e S i m k i n s - H a l l i n
    claim.         However, t h e s t a t e m e n t on S i m k i n s - H a l l i n I n v o i c e No.
    6988 i n d i c a t e s t h a t o f             t h e $7,000,           $4,441.40        was a p p r o p r i -
    a t e d t o respondent's job i n D i l l o n .                         W therefore find there
    e
    is n o t        substantial            evidence            to    support       the      entire      $7,000
    claim         and     that         the     lien       amount           should        be     reduced       by
    $2,558.60.
    To    evaluate           the      second          item     appellant          claims      was
    erroneously            included           by    the    D i s t r i c t Court,         we m u s t f i r s t
    consider the evidentiary issue before us.                                        Appellant argues
    t h e r e i s a d i s c r e p a n c y b e t w e e n t h e amount r e s p o n d e n t c l a i m e d
    was p a i d t o M           &   M C o n c r e t e a n d t h e amount a c t u a l l y p a i d .
    I n s u p p o r t of t h a t argument a t t r i a l , a p p e l l a n t p r e -
    sented        for     admission           i n t o evidence a t o t a l                account       and     a
    copy of         invoices of              t h e D i l l o n j o b w i t h Anderson C o n s t r u c -
    t i o n from M         &    M Concrete.              The document was p r e p a r e d by t h e
    bookkeeper of M & M Co n c r e t e a t t h e d i r e c t i o n of t h e g e n e r a l
    manager         and        at   the      request       of        appellant's         counsel.           The
    a c c o u n t i n d i c a t e d a d i s c r e p a n c y b e t w e e n t h e amount r e c e i v e d
    by M      &     M C o n c r e t e on           the    job        and    the    amount         respondent
    c l a i m e d had been p a i d .
    R e s p o n d e n t o b j e c t e d on t h e b a s i s t h e o f f e r e d e v i d e n c e
    was     hearsay         and       lacking        proper          foundation.              The D i s t r i c t
    C o u r t o v e r r u l e d t h e o b j e c t i o n and a d m i t t e d t h e e v i d e n c e a s
    d e f e n d a n t ' s E x h i b i t K.
    At    t h e conclusion of                the       trial,       t h e D i s t r i c t Court
    issued         findings           of     fact        and        conclusions        of      law    with      a
    s u p p o r t i n g memorandum.                The memorandum s t a t e d E x h i b i t K had
    b e e n a d m i t t e d s u b j e c t t o r u l i n g a s t o i t s a d m i s s i b i l i t y on
    t h e f i n a l s u b m i s s i o n o f t h e c a s e and t h a t on f u r t h e r r e v i e w ,
    the court found it inadmissible as hearsay.
    Appellant argues the District Court's af ter-the-fact
    ruling on the admissibility of Exhibit K was prejudicial
    because it precluded him from calling other witnesses or
    otherwise presenting proof.
    The transcript shows the court did not specifically
    reserve judgment regarding Exhibit K.     The court's statement
    was:      "Well, the objection is overruled and it will        be
    admitted. "
    The court's later determination of Exhibit K as inad-
    missible was, however, correct. The document was a statement
    other than one made by the declarant while testifying at
    trial and was offered to prove the truth of the matter as-
    serted.    As such, it was hearsay.   Rule 801(c), M0nt.R.Evi.d.
    Since the account statement was made, not in the ordinary
    course of business of M    &   M Concrete but at the request of
    appellant's counsel, it was not excepted from the hearsay
    rule and was inadmissible. Rule 803(6), Mont.R.Evid.
    While the District Court's final ruling on Exhibit K
    was correct, the manner in which it was reached was proce-
    durally irregular and resulted in substantial prejudice to
    appellant.     Had he been aware of the court's determination
    or its reservation of judgment during the trial, appellant
    could have presented and made available for cross-examina-
    tion the witnesses who prepared the M     &   M Concrete account.
    To allow the District Court's exclusion of Exhibit K to
    stand in the face of such prejudice would be inherently
    unjust. We therefore remand this matter for reconsideration.
    The final item appellant claims was erroneously
    included in the lien is that amount claimed for respondent's
    personal wages as a carpenter.            Appellant first argues that
    because there was no mention of the possibility of a per-
    sonal    claim   in   this    agreement    between   the   parties   and
    respondent made no submission of such a charge to appellant
    prior to this suit, that respondent is not entitled to the
    claim.
    In support of this argument, appellant cites Article
    10, Paragraph 10.1.6, of the parties1 contract which states
    as costs not to be reimbursed:             "The cost of any item not
    specifically and expressly included in the items described
    in Article 9."
    Article 9, Paragraph 9.1.1, however, specifies that
    costs include "[wlages paid for labor in the direct employ
    of the contractor.     . ."    Since wages for labor are expressly
    included in the contract and there is no specific limitation
    on who performs the labor, the contract did not preclude
    Anderson from working on the project.
    Appellant    also argues the hourly compensation the
    District Court allowed for Anderson's work was excessive and
    unsupported by credible evidence.
    The parties1 contract in Article 9 , Paragraph 9.1,
    allows for reimbursement of costs necessarily incurred in
    the proper performance of the work.              It further provides
    that "[sluch costs shall be at rates not higher than the
    standard paid in the locality of the work except with prior
    consent    . . ."
    At trial Anderson, a carpenter with twenty years1
    exerience, testified he charged $18 an hour for his labor.
    Of that amount, $14 was for his work as a skilled carpenter
    and $4 for use of his tools.          He testified the $14 amount
    was b a s e d      on c o s t s     in the       area      for    h i s work.         No      other
    t e s t i m o n y was o f f e r e d by e i t h e r p a r t y r e g a r d i n g t h e v a l u e o f
    t h e work o f a c a r p e n t e r o f A n d e r s o n ' s s k i l l .
    Based      on A n d e r s o n ' s   unrebutted         testimony,          the Dis-
    t r i c t C o u r t f o u n d t h a t t h e $14-an-hour            wage p o r t i o n o f t h e
    c h a r g e was r e a s o n a b l e .     W agree.
    e
    The $4-an-hour              charge f o r t h e use of Anderson's t o o l s
    i s a n o t h e r m a t t e r , however.           While Anderson t e s t i f i e d a s t o
    w h a t t h e $4 was f o r , h e d i d n o t t e s t i f y o r p r o v i d e e v i d e n c e
    of    any     kind      i n d i c a t i n g what     the    f i g u r e was     based      on    or
    w h e t h e r i t was r e a s o n a b l e .     W i t h o u t any s u p p o r t i n g e v i d e n c e
    we    are        unable     to     uphold       the     District        Court's        judgment
    a l l o w i n g $ 4 a n hour f o r t h e u s e o f t o o l s .
    We     remand      this       matter      for     a   reaccounting           of     the
    costs.       A t t h e same t i m e , w e s u g g e s t a r e v i e w o f           the calcu-
    l a t i o n s i n t h e o r i g i n a l f i n d i n g s o f f a c t and c o n c l u s i o n s o f
    l a w , s i n c e t h e r e a p p e a r s t o be a n a r i t h m e t i c e r r o r         in the
    computation of Anderson's out-of-pocket                            expenses.
    Justices
    Mr. Justice John C. Sheehy concurring:
    I concur in the foregoing, but I also think the lien
    filed in this case was timely under the facts.
    Justice
    

Document Info

Docket Number: 81-097

Filed Date: 12/7/1981

Precedential Status: Precedential

Modified Date: 3/3/2016