Matzinger v. Remco Inc. ( 1976 )


Menu:
  •                                     No.    13064
    I N T E SUPREME C U T O THE STATE O M N A A
    H           OR    F           F OTN
    1976
    R. P. MATZINGER, d /b /a MATZINGER ELECTRIC,
    P l a i n t i f f and A p p e l l a n t ,
    -vs    -
    REMCO, I N C . ,   a Utah Corporation,
    Defendant and Respondent.
    Appeal from:       D i s t r i c t Court of t h e Eighteenth J u d i c i a l D i s t r i c t ,
    Honorable W. W. L e s s l e y , Judge p r e s i d i n g .
    Counsel of Record:
    For Appellant:
    tandoe and Gary, Bozeman, Montana
    Joseph B. Gary argued, Bozeman, Montana
    For Respondent :
    Berg, Angel, Andriolo and Morgan, Bozeman, Montana
    Charles F. Angel argued, Bozeman, Montana
    C a r l T. Smith, Ogden, Utah
    Submitted:             March 1, 1976
    -.
    .
    Decided :-J?
    -
    Filed :
    M r . J u s t i c e Gene B . Daly delivered t h e Opinion of t h e Court.
    This appeal i s from a judgment entered by t h e d i s t r i c t c o u r t ,
    G a l l a t i n County, s i t t i n g without a j u r y .
    Remco I n c . , and Matzinger E l e c t r i c entered i n t o a w r i t t e n
    subcontract agreement providing Matzinger was t o f u r n i s h necessary
    m a t e r i a l s and l a b o r f o r a sixty-one u n i t apartment complex and
    laundry b u i l d i n g , known a s t h e "Village Apartments" being con-
    s t r u c t e d by Remco i n Bozeman, Montana.              The p r i c e f o r t h e work by
    Matzinger pursuant t o t h i s subcontract was $46,000.                      F i n a l payment
    was t o be made 30 days a f t e r completion of t h e p r o j e c t .             This con-
    t r a c t was signed by t h e p a r t i e s on January 15, 1973 and work
    started shortly thereafter.
    The p r o j e c t was completed f o r f i n a l i n s p e c t i o n by October 1,
    1973.      A s of January 1, 1974 Remco had paid Matzinger $41,440.
    O January 3, 1974 Matzinger f i l e d a mechanic's l i e n on t h e a p a r t -
    n
    ment complex f o r $23,538.27 claimed due f o r t h e balance owed                       under
    t h e subcontract plus e x t r a s and modifications claimed t o have been
    ordered by ~ e m c o ' spersonnel.          This l i e n was r e l e a s e d i n May,
    1974 a f t e r Remco paid Matzinger t h e sum of $4,560 t h e balance
    owed     under t h e subcontract and placed an a d d i t i o n a l $11,400 i n
    escrow with a l o c a l t i t l e company pending t h e outcome of l i t i g a t i o n
    of t h i s m a t t e r .
    Matzinger claims he i s e n t i t l e d t o payment f o r e x t r a work
    performed f o r Remco n o t contemplated by t h e p a r t i e s a t t h e time
    t h e c o n t r a c t was signed.    This claim includes work a l l e g e d l y author-
    ized by Thomas Haggerty, Remco's job superintendent i n Bozeman, and
    by Robert Richins, p r o j e c t superintendent, who commuted t o t h e
    Bozeman s i t e from Remco's S a l t Lake C i t y headquarters one o r two
    days each week during construction.
    Specifically Matzinger claimed extra compensation due for
    these items:
    1)    Installation of weatherproof outlets on apartment
    building ;
    2)    Air conditioner outlet installation;
    3)    Temporary lights installed for night watchmen after
    a fire at project during construction;
    4 Hook-up of water well pump for use during construction
    )
    and for repair of boilers;
    5)    Wiring for electric sign in front of project;
    6) Installation of ground lights in area;
    7) Furnishing hoods for kitchen ranges in each apartment;
    8 Wiring of outlets for soft drink dispensers;
    )
    9) Wiring of swimming pool building not included in
    original plan;
    10)    Pool furnace and venting system wiring;
    11)    Grounding system for pool;
    12)    Installation of additional outlets beyond those
    contemplated in the contract in order to comply with local and
    national electrical code standards;
    13)    Installation of additional phone conduit omitted from
    the original plans and specifications;
    14)    Lowering of bathroom overhead fixtures and fans after
    installation upon discovery plumbers were unable to install plumbing
    according to plans;
    15) Move of main electrical service from the exterior of
    building after installation to an interior closet to accommodate
    Montana Power Company plan alteration regarding location of power
    transformer pad; and
    16)    Miscellaneous items n o t covered by c o n t r a c t and done
    by Matzinger a t request of Remco's supervisory personnel.
    These e x t r a items t o t a l a claimed amount of $13,181.71, i n a d d i t i o n
    t o t h e amount due under t h e c o n t r a c t .
    A l e t t e r was s e n t t o Matzinger by Richins, t h e p r o j e c t
    superintendent, on January 4 , 1974, d i s c u s s i n g t h e claim and noting
    Remco's w i l l i n g n e s s t o pay t h e amount claimed f o r a m a j o r i t y of
    t h e items.      Remco's p o s i t i o n i n t h e l e t t e r was t h a t r e l o c a t i o n of
    t h e e l e c t r i c a l s e r v i c e panel and movement of bathroom c e i l i n g
    f i x t u r e s was n e c e s s i t a t e d by Matzinger's f a i l u r e t o coordinate h i s
    work with t h e o t h e r subcontractors.                The l e t t e r a l s o i n d i c a t e d
    Remco's opinion t h a t any e x t r a expense incurred i n i n s t a l l a t i o n
    of telephones was covered by t h e c o n t r a c t and must be borne by
    Matzinger.        Remco's agent s t a t e d he would r e q u i r e a d d i t i o n a l informa-
    t i o n regarding t h e expenses of wiring and grounding t h e pool and
    pool b u i l d i n g before any claims f o r such work would be allowed.
    I n t o t a l , Remco conceded i t would pay $5,485.25 plus whatever was
    determined t o be e q u i t a b l e f o r work done on t h e pool, i n r e t u r n
    f o r t h e r e l e a s e of t h e mechanic's l i e n .
    The d i s t r i c t c o u r t found Matzinger was e n t i t l e d t o t h e
    $1,245 claimed f o r i n s t a l l a t i o n of t h e a i r - c o n d i t i o n e r o u t l e t s
    and t o $847 f o r t h e weatherproof o u t l e t s .              The c o u r t held a l l
    o t h e r claims were covered by t h e o r i g i n a l c o n t r a c t between t h e
    parties.       The court a l s o disallowed Matzinger recovery of any
    a t t o r n e y f e e s f o r recovery on t h e mechanic's l i e n .             Matzinger's
    recovery was a l s o reduced by $1173.75, t h e amount t h e d i s t r i c t
    c o u r t found t o be due a s an allowance on l i g h t f i x t u r e s t o Remco.
    M t z i n g e r appealed.
    a
    The primary issue is: Whether a written contract such as
    was entered into between the parties here, may be amended or modified
    by oral agreement?
    Section 13-907, R.C.M. 1947, provides:
    "A contract in writing may be altered by a contract in
    writing, or by an executed oral agreement, and not other-
    wise. 11
    Section 13-727, R.C.M. 1947, defines an executed contract:
    "An executed contract is one, the object of which is
    fully performed. All others are executory."
    The parties agree the work for which extra compensation is sought
    was performed as claimed by Matzinger.   This work was done for the
    benefit of Remco and enhanced the value of the finished apartment
    complex. The disagreement between the parties is in regard to
    compensation for this extra work.   This Court in Dalakow v. Geery,
    
    132 Mont. 457
    , 464, 465, 
    318 P.2d 253
    , summarized the law in
    Montana and said:
    "Roberts v. Sinnott, 
    55 Mont. 369
    , 
    177 P. 252
    , is
    strikingly similar to the present case.
    "That case involved a written contract to furnish
    certain materials and perform the work necessary for the
    erection of a dwelling. The plaintiff-contractor brought
    action upon the original agreement and each of twenty-five
    oral contracts supplemental thereto.   The original contract
    contained a stipulation that no charges for extra work
    would be allowed unless ordered in writing, so the defendant
    contended there could be no recovery on the oral agreements.
    But this court * * * said:
    "'The provision of the contract above was manifestly
    intended for the protection and benefit of the owner,
    and no reason can be suggested why it might not be waived.
    The authorities are quite uniform in holding that, not-
    withstanding such a provision, the parties may make subse-
    quent independent oral agreements which, when executed,
    have the effect of modifying the original contract, and
    the rule has been recognized in this jurisdiction.'
    "In Roberts v. 
    Sinnott, supra
    , it will be noted that
    defendant did not in effect execute his part of the
    agreement, i.e. payment. This court however did not
    deny that an oral modification had been effected merely
    because of that fact.
    "I*   s
    .    *
    in cases where there is adequate consideration
    for the oral modification and the party relying thereon
    has fully performed, the written contract will be enforced
    as modified whether or not the other party has fully per-
    formed on his part. * * *. "
    '
    See: Gramrn v. Insurance Unlimited, 141Mont. 456, 
    378 P.2d 662
    ;
    Jenson v. Olson, 
    144 Mont. 224
    , 
    395 P.2d 465
    ; Webber v. Killorn,
    
    66 Mont. 130
    , 
    212 P. 852
    .
    In drafting the subcontract, Remco chose to insert the
    provision:       "CONTRACT TO INCLUDE THE FOLLOWING BUT NOT LIMITED TO:"
    This language, when viewed in light of the district court finding
    of the existence of some oral changes and additions to the con-
    tract, requires a finding of the existence of oral modifications
    to the subcontract. Matzinger is entitled to recovery for work
    performed pursuant to such modifications and must not be barred from
    receiving just compensation.
    Having determined Matzinger is entitled to enforce the
    contract as modified by the oral change orders and requests for
    additions by Remco's personnel, the next problem to determine
    is the amount of compensation due under the modified contract. The
    letter written by Mr. Richins, the supervisor and agent of Remco,
    is useful in this regard. The district court admitted the letter
    in evidence, subject to Remco's objection on the ground it consti-
    tuted an offer of compromise, rather than an admission of a fact.
    4 Wigmore, Evidence, 1061, p. 33 (Chadbourn rev. 1972) , notes :
    "Whether an offer to settle a claim by a partial
    or complete payment amounts to an admission of the
    truth of the facts on which the claim is based, and
    is therefore receivable in evidence, is a question
    which has given rise to prolonged discussion and to
    varied but often unsatisfactory attempts at explanation.
    "The solution is a simple one in its principle, though
    elusive and indefinite in its application; it is merely
    this, that a concession which is hypothetical or conditional
    only can never be interpreted as an assertion representing
    the party's actual belief, and therefore cannot be an
    admission; and conversely, an unconditional
    assertion is receivable, without any regard to the
    circumstances which accompany it.1 I
    See: Continental Oil Co. v. Bell, 
    94 Mont. 123
    , 
    21 P.2d 65
    ;
    Magelssen v. Atwell, 
    152 Mont. 409
    , 
    451 P.2d 103
    .
    A review of Richins' letter to Matzinger shows no denial
    of liability and no argument as to whether the work was performed
    on a majority of the items claimed.   In fact, most of the items
    are acknowledged as valid and the amount billed is accepted as
    fair. Those items for which payment was denied by Remco may
    have been covered by the original contract, as asserted.
    Resolution of the question of validity of the various claims
    for which Remco accepted no liability because it alleges they are
    covered by the contract is left to the district court at a rehearing
    of the matter.    From a review of the record, this Court cannot
    determine (1) to what extent the district court considered the
    letter, and (2) what evidence was considered in the district court
    finding that all items claimed were covered by the contract. Addi-
    tionally, the bill for the pool building wiring requires a final
    review for determination of the fairness and acceptability of
    r at zinger' s claim.
    Finally, the district court denied Matzinger any recovery
    of,attorney fees in prosecution of his mechanic's lien foreclosure.
    Section 93-8614, R.C.M. 1947, provides:
    "In an action to foreclose any of the liens.provided
    for by sections 45-501 and 45-512 and sections 45-1001
    to 45-1003, the court must allow as costs the money paid
    for filing and recording the lien, and a reasonable
    attorney's fee in the district and supreme courts * * *."
    (Emphasis added.)
    Under the mandatory language of this statute and this Court's
    determination as to the merits of Matzinger's claim under the oral
    modifications,he is entitled   to recover the reasonable attorney
    fees incurred in the course of this litigation as he received
    an affirmative judgment.
    This case is remanded to the district court for a new
    trial in conformity with this Opinion.
    We Concur:
    Hon. Robert Boyd, District Judge,
    sitting for Chief Justice James
    T. Harrison.
    

Document Info

Docket Number: 13064

Filed Date: 12/29/1976

Precedential Status: Precedential

Modified Date: 3/3/2016