Basin Exploration Inc. v. Tidewater Inc. , 139 F. App'x 605 ( 2005 )


Menu:
  •                                                               United States Court of Appeals
    Fifth Circuit
    F I L E D
    IN THE UNITED STATES COURT OF APPEALS
    July 12, 2005
    FOR THE FIFTH CIRCUIT
    Charles R. Fulbruge III
    Clerk
    No. 04-30395
    BASIN EXPLORATION INC (DELAWARE);
    STONE ENERGY LLC; STONE ENERGY
    CORPORATION,
    Plaintiffs-Appellees,
    versus
    TIDEWATER INC; ET AL,
    Defendants,
    TIDEWATER INC; JACKSON MARINE LLC, in personam,
    Defendants-Appellants.
    Appeal from the United States District Court
    for the Eastern District of Louisiana
    2:01-CV-2271-S
    Before GARWOOD, GARZA and BENAVIDES, Circuit Judges.
    PER CURIAM:*
    *
    Pursuant to 5TH CIR. R. 47.5 the Court has determined that this opinion
    should not be published and is not precedent except under the limited
    circumstances set forth in 5TH CIR. R. 47.5.4.
    Tidewater Inc and Jackson Marine, L.L.C., in personam, and the
    M/V SARA TIDE, in rem (collectively, Tidewater) appeal the district
    court’s judgment in favor of Basin Exploration, Inc., Stone Energy,
    L.L.C., and Stone Energy Corporation (collectively, Basin), for
    damages occasioned by an allision between a Tidewater vessel and an
    oil and gas well owned by Basin.                Only the amount of damages
    awarded is challenged.           We affirm.
    Facts and Proceedings Below
    On July 26, 2000, the M/V SARA TIDE, a Tidewater supply
    vessel, struck Basin’s well, well number 10 in the West Cameron
    Block 45 field in the Gulf of Mexico off the Louisiana coast.               The
    allision bent the well more than 70 degrees down toward the sea
    floor, leaving the entire structure under water. The two outermost
    layers of the well casing were split open, the pipeline connections
    to   the   well    were   torn    off,   and   the   platform   was   destroyed.
    Tidewater does and did not contest liability, so that the sole
    issue between the parties is the amount of damages awarded.
    Basin decided to plug and abandon (P&A) the well, which had
    been shut-in (out of production and closed with temporary plugs)
    since 1986.       The year following the allision, Basin sued Tidewater
    in the district court below, seeking damages for the P&A costs and
    the cost of drilling a replacement well.              Basin contended that it
    had planned to use the structure and casings of the No. 10 well to
    drill a sidetrack well from there into the field at a nearby
    2
    location.     The district court awarded Basin a total of $3,847,802
    plus prejudgment interest from the date of loss.                   This award
    included $2,079,172 in out-of-pocket costs for the P&A operation
    and debris cleanup, $458,630 as the extra cost of the replacement
    well compared to the originally planned sidetrack well, $780,000
    for a replacement platform and $530,000 for replacement flow lines.
    Discussion
    In general, the injured party in a tort action is entitled to
    be placed in as good a position financially as if the injury had
    not occurred.     Gaines Towing and Transp., Inc. v. Atlantia Tanker
    Corp., 
    191 F.3d 633
    , 635 (5th Cir. 1999).               In a maritime action,
    recovery is limited to economically justified expenditures.                  See
    
    id. (when the
    cost to repair a vessel exceeds the market value of
    the vessel, recovery is limited to the market value).
    Tidewater argues that there were insufficient gas reserves in
    the   field    surrounding   Basin’s       well    to   economically   justify
    replacement of the well.       If drilling a replacement well was not
    economically justifiable, then Tidewater should not be assessed
    damages for it.    In addition, if further drilling in the field was
    not   economically   viable,   Basin       would   have   been   obligated   to
    permanently plug and abandon the well at some point even if there
    had been no allision.        Tidewater therefore argues that damages
    assessed should be reduced by the cost of this eventual P&A
    3
    operation, making Tidewater liable only for the additional P&A
    costs occasioned by the allision.
    Even if the field was viable, Tidewater argues that the well
    could have been repaired at a lower cost than the combined cost of
    the P&A and the well replacement (minus the sidetrack costs).
    Therefore, according to Tidewater, Basin’s recovery should be
    capped at the amount that the well could have been repaired for,
    estimated by Tidewater’s expert to be $900,000.
    I.    Standard of Review
    On appeal from a judgment after a bench trial, this court
    reviews legal issues de novo and findings of fact for clear error.
    Houston Exploration Co. v. Halliburton Energy Servs., Inc., 
    359 F.3d 777
    , 779 (5th Cir. 2004).   A clearly erroneous finding is one
    that gives a reviewing court a “definite and firm conviction that
    a mistake has been committed.”   Anderson v. City of Bessemer City,
    
    105 S. Ct. 1504
    , 1511 (1985).     A factfinder’s choice between two
    permissible views of the evidence cannot be clearly erroneous, even
    if the reviewing court would have decided the case differently.
    
    Id. II. Gas
    Reserves
    Basin presented testimony from two employees, Bruce McDonald
    (McDonald) and Randy Young (Young), a geologist and a petroleum
    engineer, on their estimate of the proved gas reserves accessible
    4
    from the vicinity of the destroyed well.1              These employees had
    estimated the proved reserves at 2.9 billion cubic feet (BCF), but
    had used a more conservative estimate, 2.3 BCF, for purposes of
    reporting Basin’s assets as required by the Securities and Exchange
    Commission (SEC) and calculating projected profits from extraction
    of the gas.       Young testified that these profit projections ranged
    from $14.8 million to $4.8 million between late 2000 and mid-2001,
    depending on the price of gas at the time the projections were
    made.       Basin also presented evidence of a prior proved reserves
    estimate made by another Basin geologist, and a very similar
    estimate made by a third-party auditor.             Although these earlier
    analyses indicated different boundaries for the reservoir than
    those determined by McDonald and Young, the earlier proved reserves
    projection was also 2.3 BCF.
    Tidewater presented testimony on estimated proved reserves
    from two experts, a geologist and a petroleum engineer.                The gas
    reservoir projected by Tidewater’s experts had smaller boundaries
    than       that   arrived   at   by   McDonald   and   Young,    and   roughly
    corresponded to the area common to the boundaries of McDonald and
    Young and those of the earlier Basin projection (i.e., generally
    excluding any area that was not common to all those reserve
    1
    Tidewater argues that these witnesses were not properly designated as
    experts, and that the district court erred in treating their testimony as expert
    testimony. Each of these witnesses was tendered by Basin as an expert during the
    trial.   In response, Tidewater’s counsel indicated willingness to let each
    witness testify on certain topics, and made few, if any, objections to the
    witness’s subsequent testimony.
    5
    projections presented by plaintiffs).                  The differences in the
    projections apparently arose from disagreements over interpretation
    of data from another well in the field, the existence and extent of
    a particular fault in the field, and the water level in the
    reservoir.    Tidewater’s experts estimated the proved gas reserves
    at between 0.5 and 0.8 BCF, and projected that recovery of the
    reserves would result in a net loss, rather than a net profit.
    The   district    court    found       Basin’s   testimony   to   be   more
    credible,2 and found that “it was economically feasible to attempt
    to produce the proved reserves.” This finding was not clear error,
    in that there were competing permissible findings from the evidence
    presented.     Tidewater argues that the court erred in failing to
    apply an adverse inference it had granted to Tidewater, where the
    inference involved data from a seismographic study of the gas field
    that Basin had not disclosed to Tidewater.               It is not clear from
    the record that the court actually granted Tidewater’s request for
    an adverse inference, however.3                Adverse inferences regarding
    unproduced evidence are normally a result of a party’s acting in
    bad faith.     King v. Ill. Cent. R.R., 
    337 F.3d 550
    , 556 (5th Cir.
    2
    Tidewater contends that the court disregarded the testimony of its experts
    solely because they were paid experts. Although the court’s opinion mentions
    that Tidewater’s experts developed their opinions for the purposes of litigation,
    there is no indication that the opinions were completely disregarded for this
    reason. The court as factfinder has discretion to weigh the evidence.
    3
    Although Tidewater’s written motion in limine included the request for an
    adverse inference, the court did not explicitly act on the written motion. When
    the evidence came up at trial, the court orally ruled that it would “grant the
    motion in limine and exclude it.”
    6
    2003); Caparotta v. Entergy Corp., 
    168 F.3d 754
    , 756 (5th Cir.
    1999).       The court did not appear to find that Basin had acted in
    bad faith, and did not abuse its discretion in failing to so find
    or in failing to draw an adverse inference.4
    Because     the    district   court    did   not    err   in   finding   that
    production from the vicinity of Basin’s well was economically
    justified, the court did not err in awarding damages to Basin for
    repair or replacement of the well.
    III.       Repair vs. Replacement
    The district court found that repairing the well as opposed to
    plugging it and drilling a replacement well would not have been
    economically feasible.          This finding does not constitute clear
    error.       Although the evidence of actual environmental damage was
    scant,5 the severity of the structural damage to the well made
    concern       about   potential      environmental        liability     reasonable.
    Although Basin’s expert Jim Wilkinson conceded that the well would
    likely      have   been   repaired    after   the   accident      had   it   been   a
    4
    The court expressed understanding of Basin’s explanation that licensing
    restrictions with the third-party provider of the data prevented disclosure, but
    noted that Basin could not “have it both ways.”
    Furthermore, even if an adverse inference had been granted, it appears to
    us that there is no reasonable likelihood that applying the inference would have
    produced a different result. The court excluded the plaintiff’s seismographic
    map and refused to allow the plaintiff’s witness to testify on whether the
    seismographic map supported the witness’s independently generated reserves map.
    There was no assertion or evidence of any particular suspect features of the
    seismographic map (which had been furnished to Tidewater pre-trial) that might
    have formed the basis of an adverse inference.
    5
    All that was observed coming out of the well after the allision were small
    bubbles that may have been associated with a pre-existing leak.
    7
    producing well, he also testified to concerns with the ability of
    a repaired well to withstand the stresses involved in the planned
    sidetrack drilling operation.           In addition, Tidewater’s expert on
    this issue was unwilling to describe Basin’s choice not to repair
    the well as unreasonable.
    Because the district court did not err in finding that Basin’s
    plugging and abandonment of the well was reasonable under the
    circumstances      and   that    drilling     of    a    replacement    well    was
    economically justifiable, the court did not err in awarding Basin
    its out-of-pocket costs in plugging the well and the costs of the
    replacement well to the extent these costs exceeded that of the
    originally planned sidetrack well.             With respect to Tidewater’s
    argument that the damages should be reduced by the amount Basin
    would have paid to plug and abandon its well in the absence of the
    allision,    the   present      value   of   this   eventual     cost   would   be
    difficult to determine, given that when the well would have been
    plugged and at what cost are not known.6                Furthermore, as noted by
    the district court, Basin’s replacement well will eventually need
    to be plugged and abandoned at Basin’s cost. This obligation takes
    the place of Basin’s pre-allision obligation to plug and abandon
    the original well, so that Tidewater is not entitled to a reduction
    in damages.
    6
    A Basin employee testified that a permanent P&A operation on the original
    well could likely have been delayed for about ten years, and that costs of P&A
    operations had been declining over time.
    8
    Conclusion
    For the foregoing reasons the district court’s judgment is
    AFFIRMED.
    9
    

Document Info

Docket Number: 04-30395

Citation Numbers: 139 F. App'x 605

Judges: Benavides, Garwood, Garza, Per Curiam

Filed Date: 7/12/2005

Precedential Status: Non-Precedential

Modified Date: 8/2/2023