Peacock v. City of Greensboro , 196 N.C. 412 ( 1928 )


Menu:
  • CoNNOR, J.

    Defendant first contends that there was error in the refusal of its motion for judgment as of nonsuit (C. S., 567), for that,

    1. The notice of plaintiff’s claim for damages, filed with defendant, as required by a provision in defendant’s charter, was not sufficient in form and substance, to constitute compliance with said provision,

    2. If the notice of claim was sufficient in form and substance, it was not filed within the time required by said provision.

    Section 82, chapter 37, Private Laws of North Carolina, 1923, which is the charter of the city of Greensboro, is as follows:

    “Section 82. That no action for damages against said city of any character whatever, to either person or property, shall be instituted against said city unless, within six months after the happening or infliction of the injury complained of, the complainant, his executors, or administrators, shall have given notice in writing to the council of such injury, stating in such notice the date and place of happening or infliction of such injury and the amount of damages claimed therefor; but this shall not prevent any time of limitation prescribed by law from commencing to run at the date of the happening or infliction of such injuries, or in any manner interfere with its running.”

    Applying the principle upon which Graham v. Charlotte, 186 N. C., 649, 120 S. E., 466, was, in part, decided, we must hold that the notice of claim, set out in the record in this case, was sufficient in form and substance, as a compliance with the foregoing provision. In that case, it was held, both on principle and under authorities cited in the opinion, that a substantial compliance with a provision in the charter of the city of Charlotte, identical in all respects with the foregoing provision in the charter of the city of Greensboro, is all that is required. In the instant case, the notice in writing was sufficient to inform defendant of all the facts upon which plaintiff’s claim for damages was founded, and to enable defendant, after an investigation of the claim within a reasonable time, as fixed by the statute, after the claim for damages arose, to determine whether or not it should admit liability and undertake to adjust and settle said claim. This is the manifest purpose of the statute. The claimant is not required in stating the amount of his *415damages, in bis written notice, to apportion said amount to tbe several acts of tbe city, wbieb be claims caused tbe injuries wbicb resulted in. his damages.

    . Tbe notice in writing filed with tbe city council, as required by statute, is sufficient, if there is stated therein tbe date and place of tbe injury, together with tbe amount of damages claimed therefor. It is not required that tbe notice shall be drawn with tbe technical nicety necessary in a pleading. In tbe instant ease, as in Graham v. Charlotte, supra, tbe city bad ample notice of tbe cause of tbe injury for wbicb damages were claimed, to wit: tbe ponding of water by it on plaintiff’s landf

    ■ ■ .'In. bis complaint, plaintiff alleges that on or about 1 September, 1925, defendant caused to be erected across Reedy Fork tbe dam referred to in bis “amended notice,” filed with' tbe city on 25 May, 1926. He alleges that tbe injuries for wbicb be seeks to recover damages in this action were caused by water impounded on bis land by this dam. There was evidence tending to show that tbe injuries, resulting in tbe first appreciable and substantial damages to plaintiff, were inflicted or happened on or about 1 December, 1925, and that since said date, and continuing up to tbe date of tbe trial, tbe damages have greatly increased-. Tbe water ivhich caused plaintiff’s injuries was not' impounded on bis land immediately after -the construction of tbe .dam in September, 1925. It was only after the water in Reedy Fork bad been greatly increased in volume by rains, that tbe plaintiff’s land was injured. Three or four months elapsed after tbe construction of said dam before any appreciable or substantial damages were sustained by plaintiff.

    Oil 2 March, 1926, plaintiff filed a notice in writing of bis claim for damages caused by the ponding of water on bis land by tbe city of Greensboro. In this notice, be stated that a large dam constructed by the city at its water supply station was the cause of bis damages. There was evidence tending to show that this large dam was constructed in 1924. Tbe city declined to allow tbe claim for wbicb this .notice was filed. Thereafter, on 25 May, 1926, plaintiff filed.“an amended notice” of bis claim. This claim was for tbe same damages, substantially, as those for wbieb tbe original notice was filed, on 2 March, 1926. In bis “amended notice,” plaintiff alleges that tbe small dam constructed by tbe city in September, 1925, was tbe cause of tbe damages wbicb be bad suffered. In both tbe original and tbe amended notice, plaintiff claims damages for injuries to bis land caused by tbe ponding of water thereon by defendant. For tbe purpose of determining defendant’s liability to plaintiff, it is immaterial whether tbe damages were caused by tbe large dam, constructed in 1924, or by tbe small dam, constructed *416in 1925. Plaintiff does not claim that his land was injured by either dam. The injuries for which he claims damages were caused by the ponding of water on his land. There was evidence tending to show that there was no appreciable or substantial damages until on or about 1 December, 1925. Plaintiff’s cause of action accrued on the date when such damages arose. Ragan v. Thomasville, ante, 260; Dayton v. Asheville, 185 N. C., 12, 115 S. E., 827; Cardwell v. R. R., 171 N. C., 365, 88 S. E., 495; Barcliff v. R. R., 168 N. C., 268, 84 S. E., 290; Roberts v. Baldwin, 151 N. C., 408, 66 S. E., 346. While there was evidence to the contrary, there was also evidence from which the jury could find that plaintiff filed with defendant notice in writing of his claim for the damages which he seeks to recover, in this action, within six months from the time when he sustained the first appreciable and substantial damage. Whether plaintiff relies upon the original notice, filed on 2 March, 1926, or on the “amended notice,” filed on 25 May, 1926, if his cause of action arose on or about 1 December, 1925, there was a compliance by him with the provision in defendant’s charter, which makes the filing of a notice in writing, within six months after the cause of action arose, a condition precedent to his recovery. Whether a notice filed within the time prescribed by statute, may be amended after such time has expired, for the purpose of complying with the statutory provisions, is not presented on this record. There was no error in the refusal of defendant’s motion for judgment as of nonsuit. The evidence was properly submitted to the jury, upon the first issue.

    Defendant’s second contention is that upon this record, if plaintiff is entitled to recover at all, he is not entitled to recover permanent damages, for the reason that it appears upon the record that there has been no appropriation of plaintiff’s land for permanent purposes, but that the injuries, if any, to said land, caused by the ponding of water thereon, are temporary, and that said injuries will cease when the small or meter dam is removed by defendant, in accordance with the provision in the judgment, included therein by consent. Defendant contends that at most plaintiff is entitled to recover temporary damages, only, resulting from a trespass. These contentions are presented by assignments of error based upon exceptions (1) to the admission and exclusion of evidence; (2) to the refusal to submit issues tendered by defendant; (3) to the submission of the issues answered by the jury; and (4) to instructions of the court in the charge to the jury upon the issues submitted.

    Defendant, in its answer, admitted that during September, 1925, it caused to be constructed the small or meter dam across Eeedy Fork Creek, by which plaintiff alleges that water was ponded on his land. The *417injuries for which plaintiff demands damages in this action were caused by this dam. In an amendment to its answer, filed by leave of court, defendant alleges:

    “That the structure complained of by plaintiff was erected in Eeedy Fork Creek for the purpose of measuring the volume of water flowing through said stream; that the same consists of wooden timbers and boards, and is temporary in. character and nature of construction. The defendant further avers that it is its purpose to remove said structure within a reasonable time, not exceeding sixty days, from the termination of this, the February Term of this court, and defendant obligates itself so to do; and defendant pleads this in bar of any permanent damages.”

    There was evidence tending to sustain the allegations of fact in this amendment, and the court, in the judgment, by and with the consent of plaintiff, ordered that defendant remove from Eeedy Fork Creek the small or meter dam within sixty days from the .expiration of the term of court at which the judgment was rendered.

    Plaintiff, in the brief filed in his behalf in this Court, says that this action was instituted and proceeded to trial upon the theory that the small dam constructed by defendant was permanent in its nature and character. It was manifestly upon this theory of the case that the court admitted and excluded evidence, over defendant’s objections, and subject to its exceptions; it was upon this theory that the court refused to submit the issues tendered by defendant, and submitted the issues answered by the jury. The instructions of the court, however, to the jury upon the fourth issue, were based upon the law with respect to temporary damages. If plaintiff was entitled to recover permanent damages, these instructions were erroneous; on the other hand, if the plaintiff was entitled to recover only temporary damages, as distinguished from permanent damages, there was error in the admission and exclusion of evidence, and with respect to the issues. Upon the record, it is impossible to determine whether the jury has assessed permanent or temporary damages. It is clear, we think, in view of the provision included in the judgment by consent of counsel for both plaintiff and defendant, with respect to the removal of the small or meter dam, that plaintiff is entitled to recover temporary damages, only, for injuries caused by trespass on his land;' and that as there has been no appropriation of his land for permanent purposes, he is not entitled to recover permanent damages. Mitchell v. Ahoskie, 190 N. C., 235, 129 S. E., 626.

    Defendant is entitled to a new trial. It is so ordered.

    New trial.

Document Info

Citation Numbers: 196 N.C. 412

Judges: Connor

Filed Date: 12/19/1928

Precedential Status: Precedential

Modified Date: 7/20/2022