State ex rel. Util. Comm'n v. Cooper, Att'y Gen. , 368 N.C. 216 ( 2015 )


Menu:
  •                IN THE SUPREME COURT OF NORTH CAROLINA
    No. 347A14
    (Filed 21 August 2015)
    STATE OF NORTH CAROLINA ex rel. UTILITIES COMMISSION; AQUA
    NORTH CAROLINA, INC., Applicant; and PUBLIC STAFF – NORTH CAROLINA
    UTILITIES COMMISSION, Intervenor
    v.
    ATTORNEY GENERAL ROY COOPER, Intervenor
    On direct appeal as of right pursuant to N.C.G.S. §§ 7A-29(b) and 62-90(d)
    from a final order of the North Carolina Utilities Commission entered on 2 May 2014
    in Docket No. W-218, Sub 363. Heard in the Supreme Court on 16 March 2015.
    Sanford Law Office, PLLC, by Jo Anne Sanford; Bennink Law Office, by Robert
    H. Bennink, Jr.; Law Office of Charlotte Mitchell, by Charlotte Mitchell; and
    Allegra Collins Law, by Allegra Collins, for applicant-appellee Aqua North
    Carolina, Inc.
    Antoinette R. Wike, Chief Counsel, and William E. Grantmyre, Staff Attorney,
    for intervenor-appellee Public Staff – North Carolina Utilities Commission.
    Stuart Saunders, Assistant Attorney General, Kevin Anderson, Senior Deputy
    Attorney General, and Jennifer T. Harrod, Special Deputy Attorney General,
    for intervenor-appellant Roy Cooper, Attorney General.
    JACKSON, Justice.
    In this case we consider whether the North Carolina Utilities Commission (the
    Commission) properly concluded that it is in the public interest to allow Aqua North
    Carolina (Aqua) to utilize a rate adjustment mechanism of the type described in
    section 62-133.12 of the North Carolina General Statutes. We conclude that the
    STATE EX REL. UTILS. COMM’N V. COOPER, ATT’Y GEN.
    Opinion of the Court
    Commission’s determination was based upon sufficient findings of fact and was
    supported by competent, material, and substantial evidence in view of the entire
    record. See N.C.G.S. § 62-94 (2013). Accordingly, we affirm.
    Aqua is a public utility that provides water and sewer utility service to
    customers in North Carolina. On 2 August 2013, Aqua filed an application with the
    Commission seeking authority to increase its rates for water and sewer service in
    North Carolina.      As part of its application, Aqua also requested authority to
    implement a rate adjustment mechanism pursuant to section 62-133.12, which states
    in pertinent part:
    The Commission may approve a rate adjustment
    mechanism in a general rate proceeding . . . to allow a
    water or sewer public utility to recover through a system
    improvement charge the incremental depreciation expense
    and capital costs associated with the utility’s reasonable
    and prudently incurred investment in eligible water and
    sewer system improvements.         The Commission shall
    approve a rate adjustment mechanism authorized by this
    section only upon a finding that the mechanism is in the
    public interest. The frequency and manner of rate
    adjustments under the mechanism shall be as prescribed
    by the Commission.
    Id. § 62-133.12(a) (2013).
    On 19 August 2013, the Commission entered an order declaring this
    proceeding to be a general rate case and suspending the proposed new rates for up to
    270 days. The Commission scheduled six hearings across the state to receive public
    witness testimony. The Commission also scheduled an evidentiary hearing for 27
    -2-
    STATE EX REL. UTILS. COMM’N V. COOPER, ATT’Y GEN.
    Opinion of the Court
    January 2014. The Attorney General of North Carolina and the Public Staff of the
    Commission intervened as allowed by law. See id. §§ 62-15, -20 (2013).
    Subsequently, Aqua and the Public Staff entered into a Stipulation that
    resolved all the issues in the case between the two parties.       At the time, the
    Commission had not adopted final rules establishing the appropriate procedures for
    implementing a rate adjustment mechanism. Nevertheless, the Stipulating Parties
    agreed that “this docket is the appropriate forum for a decision by the Commission
    on [Aqua’s] request to implement a [rate adjustment] mechanism based on a finding
    that the [mechanism] is in the public interest.” The Attorney General did not join in
    the Stipulation.
    During the hearings before the Commission, fifty-four Aqua customers
    testified, and the parties presented testimony from several witnesses.        Thirty
    customers expressed service-related concerns, which primarily focused on problems
    with water quality, such as receiving water that appeared discolored, contained
    sediment, caused damage to appliances, and stained laundry items. Customers also
    raised other concerns, including billing issues, low water pressure, and sulfur or
    chlorine odors. Customers “almost unanimously” opposed any rate increase.
    At the evidentiary hearing, Aqua offered evidence supporting the conclusion
    that use of a rate adjustment mechanism is in the public interest. Aqua’s President
    and Chief Operating Officer, Thomas J. Roberts, asserted that the mechanism would
    -3-
    STATE EX REL. UTILS. COMM’N V. COOPER, ATT’Y GEN.
    Opinion of the Court
    allow Aqua to adjust its rates to recover money invested in “necessary, reasonable,
    approved and completed projects,” with the cumulative rate adjustment limited to
    five percent of the total annual service revenues approved by the Commission in the
    current general rate case. Roberts stated that, as a result of these rate adjustments,
    Aqua would be able to fund “earlier and more robust investment in infrastructure”
    and recover its investments “on a more timely basis.” In addition, Roberts noted that
    the mechanism would allow for “incremental adjustments” to rates, “rather than the
    sharp rate changes that are characteristic of general rate cases.”
    Roberts acknowledged that some customers have difficulties with discolored,
    sediment-laden water, and he stated that these problems are caused by naturally
    occurring iron and manganese present in ground water.         Roberts testified that,
    although many customers do not find such water acceptable, it complies with
    environmental regulations and does not create any health risks. Roberts asserted
    that Aqua could employ a number of methods to improve water quality, and he stated
    that use of a rate adjustment mechanism would provide funding “to accelerate the
    investment needed to address these concerns.”
    In addition to discussing customers’ concerns about water quality, Roberts
    stated that other aspects of Aqua’s system need improvements. Roberts testified that
    an internal analysis had revealed that portions of Aqua’s water main infrastructure
    are seriously outdated and need replacement. Roberts also stated that Aqua needs
    -4-
    STATE EX REL. UTILS. COMM’N V. COOPER, ATT’Y GEN.
    Opinion of the Court
    to fund replacement of motors, pumps, and other equipment, as well as implement
    measures to improve how the system copes with significant rain events. Ultimately,
    Roberts asserted that use of a rate adjustment mechanism would facilitate
    improvements to infrastructure and result in “fewer water quality related
    complaints, enhanced water pressure, and decreased main breaks.”
    Aqua witness Robert A. Kopas, Regional Controller for Aqua Ohio, Inc.,
    provides financial supervision and guidance to Aqua North Carolina. He testified
    that Aqua had presented to the Commission a “three-year plan” listing possible future
    projects that could be eligible for recovery through a rate adjustment mechanism.
    Kopas explained that Aqua did not submit this document to seek Commission
    approval of any of the specific projects listed; instead, it was submitted to support the
    company’s contention that use of a rate adjustment mechanism is in the public
    interest. Kopas asserted that before Aqua could recover any money through the
    mechanism, the company would have to construct an eligible improvement, place the
    improvement into service, and propose the improvement for inclusion in a rate
    adjustment, after which the Commission and the Public Staff would determine the
    project’s eligibility and the reasonableness of the associated costs.
    Aqua witness Pauline M. Ahern, a principal with AUS Consultants, testified
    that a rate adjustment mechanism would partially mitigate regulatory lag, “which
    occurs during the time between the incurrence of a utility capital expenditure or
    -5-
    STATE EX REL. UTILS. COMM’N V. COOPER, ATT’Y GEN.
    Opinion of the Court
    expense and the time when the utility can begin to earn a return on . . . the capital
    investment or recovery of the expense incurred.” Ahern stated that the mechanism
    “will improve the capital attractiveness of [Aqua], improve its service quality and
    reliability, and provide for more moderate, gradual rate increases.”
    The Public Staff presented testimony from David C. Furr, Director of the Public
    Staff’s Water and Sewer Division. Furr testified that he had reviewed the three-year
    plan filed by Aqua in order to evaluate whether the listed projects might be eligible
    for recovery through a rate adjustment mechanism. Furr stated that Aqua’s three-
    year plan did not contain enough detail for him to determine whether the projects
    would be eligible, and although the Public Staff had requested additional
    information, Aqua’s response remained “materially inadequate.” In contrast, Roberts
    testified that Aqua believed it had provided sufficient detail and that the company
    was “willing to give all the detail that the Public Staff and the Commission would
    want.”
    The Commission entered an order in Aqua’s general rate case on 2 May 2014.
    The Commission noted that the water quality concerns raised by some Aqua
    customers were related to high concentrations of naturally occurring iron and
    manganese in the source supply of water. The Commission found that iron and
    manganese are “subjects of Department of Environment and Natural Resources
    (DENR) secondary – not primary – water quality standards, and thus do not
    -6-
    STATE EX REL. UTILS. COMM’N V. COOPER, ATT’Y GEN.
    Opinion of the Court
    represent health issues.” Nevertheless, the Commission concluded that “[a]dditional
    attention is required to address the issues which arise from elevated levels of
    naturally occurring iron and manganese in the source water supply in certain Aqua
    systems.”
    In addition, the Commission found that enactment of section 62-133.12 “was
    intended to encourage and accelerate investment in needed water and sewer
    infrastructure” by “alleviat[ing] the effects of regulatory lag by allowing for earlier
    recovery of some portion” of “depreciation expense and capital costs.”             The
    Commission determined that if a rate adjustment mechanism were authorized here,
    “Aqua would be incentivized and encouraged to accelerate its investment in water
    and sewer infrastructure improvements to comply with applicable water quality and
    effluent standards, including secondary water quality standards.” Specifically, the
    Commission explained that the mechanism “will be available to fund projects to
    address problematic systemic secondary water quality issues should the Commission
    direct [Aqua] to undertake them in individual subdivision service areas.”          The
    Commission found that such additional investment in infrastructure would lead to
    “better water quality” and “improved system reliability.” As a result, the Commission
    found that Aqua’s request to implement a rate adjustment mechanism is in the public
    interest and therefore approved the company’s request.
    -7-
    STATE EX REL. UTILS. COMM’N V. COOPER, ATT’Y GEN.
    Opinion of the Court
    At the same time, the Commission ordered Aqua and the Public Staff “to
    develop and implement a plan to identify and respond to [significant] secondary water
    quality concerns” in particular service areas. The Commission required Aqua and
    the Public Staff, “[a]t a minimum,” to file written reports on the first of June and the
    first of December every year while the rate adjustment mechanism is in effect. These
    written reports must describe any secondary water quality concerns affecting Aqua’s
    customers. If a particular concern affects at least ten percent of the customers in an
    individual subdivision or at least twenty-five billing customers, additional
    information must be provided. In such cases the reports must recommend whether
    Aqua should be required to undertake corrective action with respect to specific water
    quality concerns.
    The Commission noted that final rules implementing the rate adjustment
    mechanism had not been approved. The Commission concluded that it should adopt
    alternative procedures, which were set forth in appendices to its order, to enable Aqua
    to make the requisite filings and qualify for implementation of charges pursuant to
    the rate adjustment mechanism without having to file an additional general rate case
    application once final rules were adopted.        The Attorney General appealed the
    Commission’s order to this Court as of right pursuant to N.C.G.S. §§ 7A-29(b) and 62-
    90.
    -8-
    STATE EX REL. UTILS. COMM’N V. COOPER, ATT’Y GEN.
    Opinion of the Court
    Subsection 62-79(a) of the North Carolina General Statutes “sets forth the
    standard for Commission orders against which they will be analyzed upon appeal.”
    State ex rel. Utils. Comm’n v. Carolina Util. Customers Ass’n (CUCA I), 
    348 N.C. 452
    ,
    461, 
    500 S.E.2d 693
    , 700 (1998). Subsection 62-79(a) provides:
    (a) All final orders and decisions of the Commission
    shall be sufficient in detail to enable the court on appeal to
    determine the controverted questions presented in the
    proceedings and shall include:
    (1) Findings and conclusions and the reasons or bases
    therefor upon all the material issues of fact, law, or
    discretion presented in the record, and
    (2) The appropriate rule, order, sanction, relief or
    statement of denial thereof.
    N.C.G.S. § 62-79(a) (2013). When reviewing an order of the Commission, this Court
    may, inter alia,
    reverse or modify the decision if the substantial rights of
    the appellants have been prejudiced because the
    Commission’s findings, inferences, conclusions or decisions
    are:
    (1) In violation of constitutional provisions, or
    (2) In excess of statutory authority or jurisdiction of the
    Commission, or
    (3) Made upon unlawful proceedings, or
    (4) Affected by other errors of law, or
    (5) Unsupported     by    competent,    material    and
    substantial evidence in view of the entire record as
    submitted, or
    -9-
    STATE EX REL. UTILS. COMM’N V. COOPER, ATT’Y GEN.
    Opinion of the Court
    (6) Arbitrary or capricious.
    Id. § 62-94(b). Pursuant to subsection 62-94(b) this Court must determine “whether
    the Commission’s findings of fact are supported by competent, material and
    substantial evidence in view of the entire record.” CUCA I, 348 N.C. at 460, 
    500 S.E.2d at 699
     (citation omitted). “Substantial evidence [is] defined as ‘more than a
    scintilla or a permissible inference.’ ” Id. at 460, 
    500 S.E.2d at 700
     (alteration in
    original) (quoting State ex rel. Utils. Comm’n v. S. Coach Co., 
    19 N.C. App. 597
    , 601,
    
    199 S.E.2d 731
    , 733 (1973), cert. denied, 
    284 N.C. 623
    , 
    201 S.E.2d 693
     (1974)). “It
    means such relevant evidence as a reasonable mind might accept as adequate to
    support a conclusion.” 
    Id.
     (quoting Consol. Edison Co. of New York v. NLRB, 
    305 U.S. 197
    , 229, 
    59 S. Ct. 206
    , 217, 
    83 L. Ed. 126
    , 140 (1938)). The Commission must include
    all necessary findings of fact, and failure to do so constitutes an error of law. 
    Id.
    (citation omitted).
    The Attorney General argues that the Commission’s finding that Aqua’s
    request to use a rate adjustment mechanism is in the public interest is not based
    upon sufficient findings, reasoning, and conclusions, and is not supported by
    substantial evidence. In addition, the Attorney General contends both that the
    Commission had no proper basis for this finding and that the Commission’s
    conclusion that the mechanism would incentivize Aqua to invest in infrastructure
    -10-
    STATE EX REL. UTILS. COMM’N V. COOPER, ATT’Y GEN.
    Opinion of the Court
    and improve its service quality “is, at most, speculative” because the order did not
    impose any “concrete obligation, commitment, or anything else.” We disagree.
    “The Utilities Commission, not this Court, is the finder of fact in this
    proceeding. Findings of fact made by the Commission are prima facie just and
    reasonable on appeal.” State ex rel. Utils. Comm’n v. Eddleman, 
    320 N.C. 344
    , 382-
    83, 
    358 S.E.2d 339
    , 363 (1987) (citations omitted). “[T]he Commission’s findings, if
    supported by competent, material, and substantial evidence in view of the record as
    a whole, are binding upon this Court.” State ex rel. Utils. Comm’n v. Pub. Staff, 
    317 N.C. 26
    , 45, 
    343 S.E.2d 898
    , 910 (1986) (citing State ex rel. Utils. Comm’n v. Carolina
    Tel. & Tel. Co., 
    267 N.C. 257
    , 
    148 S.E.2d 100
     (1966)).        As a result, if there is
    substantial evidence to support the Commission’s determination, this Court will not
    substitute its judgment for that of the Commission. Id. at 46-47, 
    343 S.E.2d at
    910-
    11.
    By enacting section 62-133.12, the General Assembly authorized the use of a
    rate adjustment mechanism upon a “finding” by the Commission “that the
    mechanism is in the public interest.” N.C.G.S. § 62-133.12(a). As previously stated,
    the Commission found that allowing Aqua to use a rate adjustment mechanism is in
    the public interest. In making this determination, the Commission initially found
    that the legislative intent behind section 62-133.12 was to provide a mechanism to
    -11-
    STATE EX REL. UTILS. COMM’N V. COOPER, ATT’Y GEN.
    Opinion of the Court
    incentivize quicker investments in water and sewer infrastructure by allowing for
    faster recovery of some portion of invested costs.
    The Commission explained that, because of the time involved in preparing and
    processing general rate cases, the long periods of construction required for major
    projects, and the Commission’s use of historical test years in setting rates, a
    regulatory lag period occurs between when a utility invests in improvements and
    when it begins to recover the capital costs of those improvements. The Commission
    noted that Roberts had testified that implementing a rate adjustment mechanism
    would allow Aqua to recover invested funds more quickly and therefore enable Aqua
    to invest more capital in this state. Similarly, the Commission observed that Ahern
    had testified that use of the mechanism would result in “[p]artial mitigation of
    [regulatory] lag” and lead to water quality improvements that otherwise would be
    delayed. After considering their testimony and the arguments raised by the Attorney
    General, the Commission concluded that implementing the mechanism “will promote
    adequate, reliable, and economical utility service for Aqua’s customers” by
    “incentiviz[ing] Aqua to increase and accelerate infrastructure improvements.”
    These findings are supported by the testimony of Roberts and Ahern.
    The Commission discussed the “secondary water quality issues” raised by
    Aqua’s customers and found that, as stated by Roberts, these problems result from
    high concentrations of iron and manganese found naturally in sources of groundwater
    -12-
    STATE EX REL. UTILS. COMM’N V. COOPER, ATT’Y GEN.
    Opinion of the Court
    within Aqua’s system. The Commission determined that in the past, water utilities
    may have given lower priority to correcting secondary water quality issues because
    these companies first spend their limited budgets on primary water quality
    improvements. The Commission found that use of a rate adjustment mechanism
    would benefit customers further because accelerated funding will be available for
    projects undertaken at the Commission’s direction to improve secondary water
    quality. The Commission then ordered Aqua and the Public Staff to file written
    reports addressing secondary water quality concerns twice each year while the
    mechanism is in effect and required that these filings detail particular water quality
    problems and make recommendations on whether Aqua should be ordered to pursue
    corrective action. Rather than solely relying upon a commitment by Aqua or the
    Public Staff, the Commission affirmatively imposed obligations to ensure that Aqua
    would use the rate adjustment mechanism only to make meaningful improvements
    to its system.
    The Commission further noted that pursuant to the alternative procedures it
    had adopted in its order, approval of the mechanism would not result in automatic
    surcharges for customers. The Commission explained that these procedures require
    Aqua to obtain Commission approval for any additional charges, and the approval
    process will involve review by the Public Staff and the Commission to determine
    whether Aqua’s investments and costs are reasonable and prudent. Furthermore,
    the Commission explained that Aqua could use the mechanism to recover only those
    -13-
    STATE EX REL. UTILS. COMM’N V. COOPER, ATT’Y GEN.
    Opinion of the Court
    costs that are invested in “eligible system improvements” that are “completed and
    placed in service prior to the Company requesting approval.”
    The Commission acknowledged that witness Furr had testified that Aqua’s
    initial three-year plan was “materially deficient,” but noted that Roberts had testified
    that Aqua “is willing to provide all information required by the Public Staff.” In
    addition, the Commission found that, because this case involves a new process, “one
    party . . . may believe the level of detail provided is sufficient; whereas, another party
    may not.” The Commission also directed Aqua to provide enough information to allow
    the Public Staff to “conduct its investigation and review of [Aqua’s] initial three-year
    plan,” “have productive discussions with [Aqua] regarding the specific projects
    included in the plan,” and “conclude whether the projects included in [the] three-year
    plan meet the criteria established in [section] 62-133.12” to “be considered for
    recovery through the [rate adjustment] mechanism.”
    Ultimately, the Commission found that
    Aqua would be incentivized and encouraged to accelerate
    its investment in water and sewer infrastructure
    improvements to comply with applicable water quality and
    effluent standards, including secondary water quality
    standards, if authorized to utilize a [rate adjustment]
    mechanism to recover some of its investment in a more
    timely manner and alleviate the effects of regulatory lag.
    Such accelerated investment to address aging
    infrastructure and water quality issues would benefit
    customers through improved system reliability and better
    water quality. The [rate adjustment] mechanism would
    further benefit customers because it will be available to
    -14-
    STATE EX REL. UTILS. COMM’N V. COOPER, ATT’Y GEN.
    Opinion of the Court
    fund projects to address problematic systemic secondary
    water quality issues should the Commission direct the
    Company to undertake them in individual subdivision
    service areas, even though such projects may not be
    specifically required by federal and/or state standards and
    might not be of high system priority absent the direction of
    the Commission. The [rate adjustment] mechanism does
    not affect or take away the Commission’s authority to
    disallow recovery for projects and investments found to be
    unreasonable and imprudent.
    The Commission thoroughly explained how Aqua’s use of a rate adjustment
    mechanism would benefit Aqua’s customers, and the Commission took meaningful
    steps to ensure that problems with water quality are addressed and that customers
    are charged only after Aqua has made improvements to the quality and reliability of
    its service. We hold that the Commission provided sufficient findings, reasoning, and
    conclusions to support its ultimate finding that the mechanism is in the public
    interest, and that the Commission’s determination is supported by substantial
    evidence in view of the record as a whole. Accordingly, the Commission’s order is
    affirmed.
    AFFIRMED.
    -15-