Philadelphus Presbyterian Found., Inc. v. Robeson Cnty. Bd. of Adjust. ( 2014 )


Menu:
  • An unpublished opinion of the North Carolina Court of Appeals does not constitute
    controlling legal authority. Citation is disfavored, but may be permitted in accordance
    with the provisions of Rule 30(e)(3) of the North Carolina Rules of Appellate Procedure.
    NO. COA13-777
    NORTH CAROLINA COURT OF APPEALS
    Filed:     7 January 2014
    PHILADELPHUS PRESBYTERIAN FOUNDATION,
    INC., CHRIS EMANUEL BAXLEY, DANNY
    BULLARD & SYBIL BULLARD HARRIS, FRASER
    & HARRIS, LLC, SHELLI BREWINGTON, RICKY
    LYNN BRITT, PHIL LOCKLEAR & DEBORAH
    LOCKLEAR, & MELANIE STRICKLAND HUNT,
    Petitioners
    Robeson County
    v.
    No. 12 CVS 2097
    ROBESON COUNTY BOARD OF ADJUSTMENT,
    ROBESON COUNTY BOARD OF COMMISSIONERS,
    ROBESON COUNTY,
    Respondents
    Appeal by petitioners from order entered 21 March 2013 by
    Judge Robert F. Floyd, Jr., in Robeson County Superior Court.
    Heard in the Court of Appeals 21 November 2013.
    J. Gates Harris for Petitioners-Appellants.
    Parker Poe Adams & Bernstein, LLP, by Melanie Black Dubis
    and Matthew H. Mall, for Respondents-Appellees.
    ERVIN, Judge.
    Petitioners      Philadelphus       Presbyterian      Foundation,       Inc.,
    Chris    Emanuel    Baxley,     Danny    Bullard,     Sybil    Bullard     Harris,
    Fraser & Harris, LLC, Shelli Brewington, Ricky Lynn Britt, Phil
    -2-
    Locklear, Deborah Locklear, and Melanie Strickland Hunt appeal
    from an order dismissing their certiorari petition and denying
    their motion to amend the petition in order to add a necessary
    party.       Although Petitioners concede that they failed to join a
    necessary party at the time that they filed their petition, they
    contend that the trial court erred by depriving them of the
    ability to amend their petition to join the omitted necessary
    party      and   dismissing    their   petition    instead.     After    careful
    consideration of Petitioners’ challenges to the trial court’s
    order in light of the record and the applicable law, we conclude
    that the trial court’s order should be affirmed.
    I. Factual Background
    On 2 July 2012, the Robeson County Board of Commissioners
    met for the purpose of considering an application filed by Buie
    Lakes Plantation, LLC, in which Buie Lakes sought the issuance
    of a conditional use permit authorizing the construction of a
    sand       mining   and   processing   facility.      On   16   July    2012,1   a
    decision determining that the application was complete, complied
    with all applicable land use ordinances, and should be approved
    was authenticated by the County clerk.                 The conditional use
    1
    Although the Board appears to have approved the permit on
    16 July 2012, Buie Lakes did not accept the terms upon which the
    issuance of the permit was conditioned until 9 August 2012 and
    the permit was not recorded in the office of the Robeson County
    Register of Deeds until 13 August 2012.
    -3-
    permit that Robeson County voted to approve set forth numerous
    detailed conditions to which Buie Lakes would have to assent in
    order   to   be     allowed     to    construct     and   operate    the    proposed
    facility, including restrictions on the hours during which the
    facility     was    permitted    to    operate      and   a   prohibition    on   the
    performance of certain blasting operations.
    On 1 August 2012, Petitioners filed a petition requesting
    the issuance of a writ of certiorari for the purpose of seeking
    review of Robeson County’s decision to approve the challenged
    conditional use permit and alleging that the issuance of the
    challenged     conditional       use    permit      was   unlawful   for    numerous
    substantive and procedural reasons.                 On the same date, the Clerk
    of Superior Court of Robeson County issued a writ of certiorari
    requiring Respondents Robeson County Board of Adjustment and the
    Robeson County Commission to prepare and certify a record of the
    proceedings leading to the issuance of the disputed conditional
    use permit for delivery to the court.                      On 13 December 2012,
    Respondents        filed   a   memorandum      in    which    they   disputed     the
    validity of the arguments advanced in the petition and noted
    that, “[c]ontrary to the requirement of N.C. Gen. Stat. §§ 153A-
    -4-
    3549       and    160A-393,    Petitioners   did    not     name   Buie   Lakes
    Plantation as a party in the Petition for Writ of Certiorari.”2
    The matter came on for hearing before the trial court on 14
    February 2013.         During the course of this hearing, Respondents
    made an oral motion to dismiss the petition as the result of
    Petitioners’ failure to join a necessary party under N.C. Gen.
    Stat. § 1A-1, Rule 12(b)(7).            In response, Petitioners sought
    the entry of an order allowing them to amend their petition in
    order to name Buie Lakes as a party.               At the conclusion of the
    hearing, the trial court orally announced that it would deny
    Petitioners’ amendment motion and grant Respondents’ dismissal
    motion.          On 21 March 2013, the trial court entered an order
    denying Petitioners’ amendment motion and granting Respondents’
    dismissal motion.           Petitioners noted an appeal to this Court
    from the trial court’s order.
    II. Legal Analysis
    A. Standard of Review
    According       to     well-established      North     Carolina     law,
    “compliance with the requirements for entry of notice of appeal
    is jurisdictional” and subject to de novo review.                    State v.
    2
    Although Petitioners assert on a number of occasions in
    their brief that they were not aware of this deficiency in their
    petition and that they had been surprised when this contention
    was advanced at the hearing held before the trial court, the
    record plainly reflects that Respondents raised this issue at
    least two months before the hearing held in this case.
    -5-
    Oates, 
    366 N.C. 264
    , 266, 
    732 S.E.2d 571
    , 573 (2012) (citing
    Dogwood Dev. & Mgmt. Co. v. White Oak Transp. Co., 
    362 N.C. 191
    ,
    197-98, 
    657 S.E.2d 361
    , 365 (2008) and Harris v. Matthews, 
    361 N.C. 265
    , 271, 
    643 S.E.2d 566
    , 570 (2007)).                    “A motion to amend
    is addressed to the discretion of the court, and its decision
    thereon is not subject to review except in case of manifest
    abuse.”       Calloway v. Ford Motor Co., 
    281 N.C. 496
    , 501, 
    189 S.E.2d 484
    , 488 (1972).
    B. Dismissal of Petition
    The issuance of a conditional use permit by a county agency
    “shall be subject to review of the superior court in the nature
    of certiorari consistent with [N.C. Gen. Stat. §] 153A-354.”
    N.C. Gen. Stat. § 153A-340(c1).              A petition seeking the issuance
    of a writ of certiorari for the purpose of obtaining judicial
    review of a decision to approve a conditional use permit must
    “be filed with the clerk of superior court within 30 days after
    the   decision      of   the   board   is    filed     in    such      office   as   the
    ordinance       specifies,     or   after      a    written       copy     thereof    is
    delivered      to   every    aggrieved      party    who    has    filed    a   written
    request for such copy with the secretary or chairman of the
    board at the time of its hearing of the case, whichever is
    later.”       N.C. Gen. Stat. § 153A-345(e2).               According to N.C. Gen.
    Stat.     §    153A-349(a),     “[w]henever         appeals       of   quasi-judicial
    -6-
    decisions      of   [county]    decision-making   boards    are   to   superior
    court   and    in   the   nature    of   certiorari   as   required    by    this
    Article, the provisions of [N.C. Gen. Stat. §] 160A-393 shall be
    applicable to those appeals.”              Pursuant to N.C. Gen. Stat. §
    160A-393(e), “[i]f the petitioner is not the applicant before
    the decision-making board whose decision is being appealed, the
    petitioner shall . . . name that applicant as a respondent.”                   As
    a result, in order to properly challenge the issuance of the
    conditional use permit at issue here, Petitioners were required
    to file their petition in a timely manner, which they appear to
    have done, and to name Buie Lakes as a party respondent, which
    they did not do.
    The trial court dismissed the petition with prejudice “for
    the failure of the Petitioners to join a necessary party.”                    In
    support of this decision, Respondents cite Whitson v. Camden
    Cnty. Bd. of Comm’rs, 
    2013 N.C. App. LEXIS 766
     (2013), in which
    this Court upheld the dismissal of a certiorari petition for
    lack of subject matter jurisdiction in light of the petitioner’s
    failure to name the applicant as a respondent as required by
    N.C.    Gen.    Stat.     §    160A-393(a).    Although     Whitson,    as     an
    unpublished decision, is not binding upon us, e.g. Cary Creek
    Ltd. P’ship v. Town of Cary, 
    203 N.C. App. 99
    , 106, 
    690 S.E.2d 549
    , 554, disc. review denied, 
    364 N.C. 600
    , 
    703 S.E.2d 441
    -7-
    (2010);     N.C.R.     App.     P.     30(e)(3),            we    conclude         that    it    is
    consistent with and compelled                    by    our decision in              McCrann v.
    Village of Pinehurst, __ N.C. App. __, 
    716 S.E.2d 667
     (2011), in
    which     the   petitioner’s           challenge            to     the       issuance      of    a
    conditional     use    permit       was     not       filed      within      the    thirty      day
    period specified in N.C. Gen. Stat. § 160A-388(e2) and in which
    we held that this deficiency, like the failure to note an appeal
    in   a    timely     manner,        deprived       the       reviewing        court       of    any
    jurisdiction to hear and determine the issues raised in the
    petition.       McCrann,       __    N.C.    App.       at       __,   
    716 S.E.2d at 670
    (stating that “‘[t]he requirement of timely filing and service
    of   notice     of     appeal        is     jurisdictional,               and      unless       the
    requirement[ is] met, the appeal must be dismissed,’” and that
    “[w]e    see    no    reason    to        treat       the     requirements          for    timely
    ‘appeal’ for judicial review . . . differently”) (quoting Reidy
    v. Whiteheart Ass’n, 
    185 N.C. App. 76
    , 85, 
    648 S.E.2d 265
    , 271-
    72, disc. review denied, 
    361 N.C. 696
    , 
    652 S.E.2d 651
     (2007),
    cert. denied, 
    552 U.S. 1243
    , 
    128 S. Ct. 1484
    , 
    170 L. Ed. 2d 298
    (2008)).
    Although        the   filing      of    a     certiorari          petition       certainly
    bears some resemblance to the institution of a civil action, as
    Petitioners implicitly assert, the analogy between an appeal and
    a request for certiorari review made in McCrann is clearly the
    -8-
    correct   one.         In    such    certiorari      proceedings,          the   “superior
    court is not a trier of fact, but assumes the posture of an
    appellate court.”            In re Appeal of Willis, 
    129 N.C. App. 499
    ,
    500,   
    500 S.E.2d 723
    ,    725   (1998).        More   specifically,         “[i]n
    reviewing zoning decisions, the trial court sits in the posture
    of an appellate court” and is charged with “‘(1) [r]eviewing the
    record for errors in law; (2) insuring that procedures specified
    by law in both statute and ordinance are followed; (3) insuring
    that   appropriate           due    process      rights    of     a     petitioner     are
    protected, including the right to offer evidence, cross-examine
    witnesses and inspect documents; (4) insuring that the decisions
    of   zoning     boards       are    supported       by   competent,        material    and
    substantial evidence in the whole record; and (5) insuring that
    decisions are not arbitrary and capricious.’”                         Ball v. Randolph
    Cnty. Bd. of Adjustment, 
    129 N.C. App. 300
    , 302, 
    498 S.E.2d 833
    ,
    834 (quoting Mize v. Cnty. of Mecklenburg, 
    80 N.C. App. 279
    ,
    284, 
    341 S.E.2d 767
    , 770 (1986)), disc. review improvidently
    granted, 
    349 N.C. 348
    , 
    507 S.E.2d 272
     (1998).                         For that reason,
    we   conclude    that       the    extent   to    which    a    trial      court   obtains
    jurisdiction      to     address      the     issues     raised       in   a     certiorari
    petition should be analyzed in the same manner as the extent to
    which an appellate court obtains jurisdiction over an appeal
    from the General Court of Justice or an administrative agency.
    -9-
    As the Supreme Court stated approximately a half century
    ago, “[t]here is no inherent or inalienable right of appeal from
    an inferior court to a superior court or from a superior court
    to the Supreme Court,” so that “[n]o appeal lies from an order
    or decision of [a subordinate body] unless the right is granted
    by statute.”     In re Halifax Paper Co., 
    259 N.C. 589
    , 592, 
    131 S.E.2d 441
    , 444 (1963).        In view of the fact that “an appeal is
    not a matter of absolute right,” “the appellant must comply with
    the statutes and rules of Court as to the time and manner of
    taking and perfecting his appeal.”          Caudle v. Morris, 
    158 N.C. 594
    , 595, 
    74 S.E. 98
    ,          98 (1912).     As a result, given that
    Petitioners violated the relevant provisions of N.C. Gen. Stat.
    § 160A-393(e) by failing to name Buie Lakes as a respondent, the
    trial court correctly dismissed their certiorari petition for
    lack   of   subject   matter    jurisdiction.      N.C.    Cent.   Univ.    v.
    Taylor, 
    122 N.C. App. 609
    , 612-13, 
    471 S.E.2d 115
    , 118 (1996)
    (stating that “[f]ailure to meet the pleading requirements for
    this extraordinary writ deprives the superior court of subject
    matter    jurisdiction   of    the   particular   matter   over    which   the
    moving party seeks review”), aff’d, 
    345 N.C. 630
    , 
    481 S.E.2d 83
    (1997).
    C. Denial of Amendment Motion
    -10-
    Although they acknowledge that their petition as originally
    filed was flawed, Petitioners contend that the trial court erred
    by refusing to allow them to amend their petition so as to name
    Buie Lakes as a party respondent.                     In essence, Petitioners argue
    that   the    trial    court      acquired          jurisdiction    over     the      issues
    raised by their certiorari petition as a result of the fact that
    the petition in question was filed in a timely manner and should
    have   allowed     them     to    cure        the    deficiency    in    their   original
    petition by amending that filing.                      We do not find Petitioners’
    argument persuasive.
    The    first,   and       most    serious,       problem    with     Petitioners’
    argument      is   that,     for        the     reasons    that     we    have     already
    enunciated, the trial court lacked jurisdiction over the issues
    raised by the certiorari petition given Petitioners’ failure to
    join   Buie    Lakes   as    a    party        respondent.        According      to    well-
    established North Carolina law,                      “‘[i]f a court finds at any
    stage of the proceedings that it lacks jurisdiction over the
    subject matter of a case, it must dismiss the case for want of
    jurisdiction.’”            Sarda        v.      City/Cnty.    of        Durham     Bd.    of
    Adjustment, 
    156 N.C. App. 213
    , 215, 
    575 S.E.2d 829
    , 831 (2003)
    (quoting State v. Linemann, 
    135 N.C. App. 734
    , 739, 
    522 S.E.2d 781
    , 785 (1999)).            As a result, given that the trial court
    lacked jurisdiction over this case as a result of Petitioners’
    -11-
    failure to join Buie Lakes as a party respondent, it also lacked
    the authority to allow them to amend their petition to cure this
    defect.
    In seeking to persuade us to hold that the trial court did
    have jurisdiction to allow their amendment motion, Petitioners
    argue   that   the   timely   filing   of   their   certiorari   petition,
    standing alone, sufficed to give the trial court jurisdiction
    over their challenge to the issuance of the relevant conditional
    use permit regardless of their failure to join Buie Lakes as a
    party respondent.      In support of this proposition, Petitioners
    cite 
    N.C. Gen. Stat. § 63-34
    (a), which provides that a “petition
    [challenging a board decision] shall be presented to the court
    within 30 days after the decision is filed in the office of the
    board.”   As a result of the fact that the statutory provision in
    question relates exclusively to the adoption of airport zoning
    regulations and the fact that Petitioners have completely failed
    to satisfy the applicable jurisdictional prerequisites for the
    filing of a valid certiorari petition challenging the issuance
    of a conditional use permit as set out in N.C. Gen. Stat. §
    160A-393(e), Petitioners’ reliance upon 
    N.C. Gen. Stat. § 63
    -
    34(a) is misplaced.
    In addition, Petitioners argue that the trial court had the
    authority to allow, and was in fact obligated to allow, their
    -12-
    amendment motion pursuant to the principles enunciated in our
    decision in Mize.    In Mize, the petitioners filed a petition
    seeking the issuance of a writ of certiorari for the purpose of
    challenging a decision that they could no longer use their land
    for airport-related purposes.    80 N.C. App. at 280, 
    341 S.E.2d at 768
    .   Although the trial court dismissed the petition for
    failing to join a necessary party pursuant to N.C. Gen. Stat. §
    1A-1, Rule 12(b)(7), id. at 281, 
    341 S.E.2d at 768
    , we reversed
    that decision on the grounds that a proceeding should only be
    dismissed based upon a failure to join a necessary party in the
    event that the defect in question could not be cured and that,
    since it was possible to join the missing party, the trial court
    abused its discretion by dismissing the review proceeding.       Id.
    at 283-84, 
    341 S.E.2d at 769-70
    .       Petitioners’ reliance on Mize
    is, however, misplaced.
    In deciding Mize, this Court specifically noted that:
    The language of [N.C. Gen. Stat. §] 153A-345
    requires only that any petition seeking
    review by the superior court be filed with
    the clerk of superior court within 30 days
    after the decision of the Board is filed or
    after a written copy has been delivered to
    every aggrieved party.       The petitioners
    complied with all the express requirements
    of this vague statute by filing a petition
    in Mecklenburg County Superior Court within
    30 days of the decision of the Board.
    -13-
    Id. at 283, 
    341 S.E.2d at 769
    .                    As a result, although the Mize
    petitioners failed to join a necessary party, they did comply
    with all of the statutorily prescribed prerequisites for the
    filing       of    a     valid   certiorari       petition.      The   same    is     not,
    however, true in this case given that                         Petitioners failed to
    comply with the additional statutory requirements for a valid
    certiorari petition spelled out in N.C. Gen. Stat. § 160A-393, a
    statutory section which was enacted over two decades after the
    issuance of our decision in Mize.                   2009 N.C. Sess. Laws c. 421,
    s. 1(a).          As a result, given that the petitioners’ failure to
    join a necessary party in Mize did not, unlike the failure to
    join     a        necessary       party     at     issue      here,    constitute       a
    jurisdictional defect, Mize provides no basis for an award of
    the relief which Petitioners seek in this case.
    Moreover,          Petitioners      contend     that     the    trial    court’s
    refusal to refrain from allowing Respondents’ dismissal motion
    and to allow their amendment motion instead is inconsistent with
    the principles enunciated in N.C. Gen. Stat. § 1A-1, Rule 15.
    Even assuming that N.C. Gen. Stat. § 1A-1, Rule 15, provided a
    basis for the allowance of Petitioners’ amendment motion despite
    the    fact       that    the    trial    court    lacked   jurisdiction       over   the
    petition due to Petitioners’ failure to join Buie Lakes as a
    party respondent and, thus, applies in certiorari proceedings
    -14-
    such as this one, we still do not find Petitioners’ argument
    persuasive.
    As we have previously noted, the North Carolina Rules of
    Civil   Procedure    “govern       the    procedure     in   the    superior      and
    district courts of the State of North Carolina in all actions
    and   proceedings    of    a     civil    nature   except    when       a   differing
    procedure is prescribed by statute,” N.C. Gen. Stat. § 1A-1,
    Rule 1, including special proceedings.                  See Macon v. Edinger,
    
    303 N.C. 274
    , 279, 
    278 S.E.2d 256
    , 259 (1981).                However, neither
    this Court nor the Supreme Court has ever held that the North
    Carolina Rules of Civil Procedure, considered in their entirety,
    apply in certiorari proceedings conducted pursuant to N.C. Gen.
    Stat. § 160A-393, which, as we have already noted, bear a much
    greater resemblance to appellate proceedings than to ordinary
    civil actions.      Although certain subsections in N.C. Gen. Stat.
    § 160A-393 provide for the utilization of specific provisions of
    the   North   Carolina     Rules     of    Civil    Procedure      in       certiorari
    proceedings,   e.g.,      N.C.    Gen.    Stat.    §§   160A-393(f)         (requiring
    that service of the writ be effectuated in accordance with N.C.
    Gen. Stat. § 1A-1, Rule 4), and 160A-393(h) (providing for the
    consideration of intervention petitions in accordance with N.C.
    Gen. Stat. § 1A-1, Rule 24), nothing in N.C. Gen. Stat. § 160A-
    393 provides for the use of the procedures outlined in N.C. Gen.
    -15-
    Stat. § 1A-1, Rule 15, in such proceedings.                However, despite
    the absence of any statutory justification for concluding that
    the principles enunciated in N.C. Gen. Stat. § 1A-1, Rule 15,
    should   be   incorporated   into   certiorari     proceedings        conducted
    pursuant to N.C. Gen. Stat. § 160A-393, we do agree that some
    sort     of     amendment    procedure        should,      in     appropriate
    circumstances, be available in such proceedings.                 As a result,
    we will assume, without deciding, that the principles enunciated
    in N.C. Gen. Stat. § 1A-1, Rule 15, govern the allowance of
    amendment motions in certiorari proceedings conducted pursuant
    to N.C. Gen. Stat. § 160A-393.
    According to N.C. Gen. Stat. § 1A-1, Rule 15(a), a party to
    civil litigation has a right to amend his or her pleading as a
    matter of right prior to the service of a responsive pleading.
    After that point, however, the party must obtain leave of court
    to   amend    its   pleadings,   with   the   trial     courts   having   been
    instructed     that    requested    amendments        should     be    “freely”
    authorized “when justice so requires.”           N.C. Gen. Stat. § 1A-1,
    Rule 15(a).     “Acceptable reasons for which a motion to amend may
    be denied are ‘undue delay, bad faith, dilatory motive, repeated
    failure to cure deficiencies, undue prejudice, and futility of
    the amendment.’”      Nationsbank of N.C., N.A. v. Baines, 
    116 N.C. App. 263
    , 268, 
    447 S.E.2d 812
    , 815 (1994) (quoting Coffey v.
    -16-
    Coffey, 
    94 N.C. App. 717
    , 722, 
    381 S.E.2d 467
    , 471 (1989), disc.
    review    improvidently        granted,     
    326 N.C. 586
    ,    
    391 S.E.2d 40
    (1990)).       Although “[a] claim asserted in an amended pleading is
    deemed to have been interposed at the time the claim in the
    original pleading was interposed, unless the original pleading
    does not give notice of the transactions, occurrences, or series
    of transactions or occurrences, to be proved pursuant to the
    amended pleading,” N.C. Gen. Stat.                  §    1A-1, Rule 15(c), this
    “relation back” rule “does not apply to the naming of a new
    party-defendant to the action.”                 Crossman v. Moore, 
    341 N.C. 185
    ,    187,    
    459 S.E.2d 715
    ,   717    (1995);         see    also      Piland       v.
    Hertford Cnty. Bd. of Comm’rs, 
    141 N.C. App. 293
    , 301-02, 
    539 S.E.2d 669
    , 674 (2000) (holding that “the plaintiffs’ attempt to
    amend the summons and complaint in the instant case by changing
    the    name    of   the   party-defendant         [in   a   case       arising         from    a
    challenge to a rezoning decision] to Hertford County in place of
    the Board of Commissioners effectively seeks to add a new party-
    defendant      rather     than    merely    correct         a    misnomer,         and    the
    relation-back rule therefore cannot apply”).
    Although     the   trial    court    did    not      specify         a   ground    for
    denying Petitioners’ amendment motion in its order, the record
    clearly       reflects    that     any     amendment        of        the       sort     which
    Petitioners sought leave to make would have been futile.                                As we
    -17-
    have    already   noted,   Petitioners      were   required    to    file   their
    certiorari petition within “30 days after the decision of the
    board is filed in such office as the ordinance specifies, or
    after a written copy thereof is delivered to every aggrieved
    party who has filed a written request for such copy with the
    secretary or chairman of the board at the time of its hearing of
    the case, whichever is later.”          N.C. Gen. Stat. § 153A-345(e2).
    Given    that   the   Board   of   Commissioners    voted     to    approve   the
    challenged conditional use permit on 2 July 2012 and that the
    written order approving the permit was certified on 16 July
    2012, the amendment motion appears to have been made long after
    the expiration of the thirty day period specified in N.C. Gen.
    Stat. § 153A-345(e2).          Since the amendment which Petitioners
    sought to make effectively added a party to this proceeding and
    since amendments adding new parties do not relate back to the
    time of the original filing, any amendment of the nature sought
    by Petitioners would have been futile.             Thus, assuming that N.C.
    Gen. Stat. § 1A-1, Rule 15, governs the process of amending a
    certiorari petition filed pursuant to N.C. Gen. Stat. § 160A-393
    and that, as Petitioners suggest, it provides an independent
    basis for the allowance of an amendment motion despite the fact
    that the trial court lacked jurisdiction over the underlying
    certiorari proceeding, the trial court had ample justification
    -18-
    for denying the proposed amendment on futility grounds and did
    not,    for   that   reason,     err    by    denying     Petitioners’     amendment
    motion.
    In attempting to persuade us that their amendment was not
    subject to denial on futility-related grounds, Petitioners note
    that the thirty day period specified in N.C. Gen. Stat. § 153A-
    345(e2) did not begin to run until the date upon which the
    challenged     decision        was    filed     and    argue    that    “the   record
    prepared by Robeson County even fails to show when the time to
    file the petition expired.”              The fundamental problem with this
    argument is, however, that courts “will not take judicial notice
    of a municipal ordinance,” High Point Surplus Co. v. Pleasants,
    
    263 N.C. 587
    ,    591,     
    139 S.E.2d 892
    ,     895   (1965),    and     that
    compliance with any time limitations applicable to the filing of
    a     certiorari     petition        constitutes      a   requirement      which    is
    jurisdictional in nature.               McCrann, __ N.C. App. at __, 
    716 S.E.2d at 670
    .        As a result of the fact that a valid certiorari
    petition must contain sufficient allegations to establish the
    court’s jurisdiction, Davis v. Hiatt, 
    326 N.C. 462
    , 465, 
    390 S.E.2d 338
    , 340 (1990) (stating that, “if a petition alleges
    facts     sufficient      to     establish       the      right    of     review    on
    certiorari[,] its validity as a pleading is not impaired by the
    fact [that] the petitioner does not specifically pray that the
    -19-
    court    issue    a    writ    of     certiorari”),         and      the    fact    that    a
    “[f]ailure       to     meet    the     pleading          requirements         for     this
    extraordinary writ deprives the superior court of subject matter
    jurisdiction      of    the    particular        matter     over     which    the    moving
    party seeks review,” N.C. Cen. Univ., 122 N.C. App. at 613, 
    471 S.E.2d at 118
    , the trial court lacked jurisdiction to consider
    the substantive allegations of the petition in the absence of an
    allegation    and      proof   that    the       petition      had   been    filed     in   a
    timely manner.         In view of the fact that Petitioner failed to
    allege   or   prove     the    nature       of     the   act    which      triggered    the
    running of the thirty day period set out in N.C. Gen. Stat. §
    153A-345(e2)      as    set     out    in     the    applicable         Robeson      County
    ordinance and the fact that the applicable thirty day period
    would have expired well before the date upon which Petitioners
    sought leave to amend their petition to add Buie Lakes as a
    party respondent on the basis of any of the dates specified in
    or inferable from the petition, the fact that the record does
    not definitively establish the date upon which the challenged
    conditional use permit was filed or served cuts against, rather
    than in favor of, Petitioners’ position.                       As a result, none of
    Petitioners’ challenges to the denial of their amendment motion
    have merit.
    III. Conclusion
    -20-
    Thus, for the reasons set forth above, we conclude that
    none of Petitioners’ challenges to the trial court’s order have
    merit.   As a result, the trial court’s order should be, and
    hereby is, affirmed.
    AFFIRMED.
    Judges CALABRIA and STEPHENS concur.
    Report per Rule 30(e).