J.T. Russell & Sons, Inc. v. Silver Birch Pond, LLC ( 2014 )


Menu:
  • An unpublished opinion of the North Carolina Court of Appeals does not constitute
    controlling legal authority. Citation is disfavored, but may be permitted in accordance
    with the provisions of Rule 30(e)(3) of the North Carolina Rules of Appellate Procedure.
    NO. COA13-662
    NORTH CAROLINA COURT OF APPEALS
    Filed: 18 February 2014
    J.T. RUSSELL & SONS, INC.,
    Plaintiff/Counterclaim-
    Defendant,
    v.                                     Stanly County
    No. 08-CVS-1453
    SILVER BIRCH POND, LLC,
    Defendant/Counterclaim-
    Plaintiff.
    Appeal by defendant from order entered 31 October 2012 by
    Judge Theodore S. Royster, Jr. in Stanly County Superior Court.
    Heard in the Court of Appeals 20 November 2013.
    Womble Carlyle Sandridge & Rice, LLP, by Brent F. Powell,
    John F. Morrow, Jr., and David R. Boaz, for plaintiff-
    appellee.
    James, McElroy & Diehl, P.A., by Preston O. Odom, III, and
    The Jonas Law Firm, P.L.L.C., by Peter C. Capece, for
    defendant-appellant.
    HUNTER, Robert C., Judge.
    Defendant-appellant        Silver     Birch    Pond,     L.L.C.     (“SBP”)
    appeals the order entered 31 October 2012 denying SBP’s motion
    to amend its counterclaim and granting plaintiff’s-appellee’s
    J.T.    Russell    &   Sons,     Inc.’s    (“JTR’s”)      motion    for    summary
    -2-
    judgment.       On appeal, SBP argues that the trial court: (1) erred
    by resolving the issue of damages on summary judgment because
    that ruling exceeded the scope of the appellate mandate; (2)
    abused    its     discretion        in   denying    SBP’s    motion     to    amend    its
    counterclaims;       and      (3)    erred    in     granting      JTR’s     motion    for
    summary judgment.           After careful review,                 we: (1)    affirm the
    order denying the motion to amend; and (2) reverse the order
    granting summary judgment in favor of JTR because it violated
    the mandate of this Court in J.T. Russell & Sons, Inc. v. Silver
    Birch    Pond     L.L.C.,     __    N.C.    App.    __,    
    721 S.E.2d 699
        (2011)
    (“Silver Birch I”), and remand on the issue of damages.
    Background
    This case is before this Court for the second time after a
    trial court has entered an order granting summary judgment for
    JTR.     This Court’s prior opinion contains a detailed recitation
    of the facts underlying this dispute.                     See Silver Birch I.          JTR
    is an asphalt paving company.                 SBP is a North Carolina limited
    liability company formed by Robert Johnson (“Mr. Johnson”) for
    the     purpose     of     developing        Silver       Birch     Pond,    a     planned
    residential subdivision, (“the subdivision”) in Lincoln County.
    Although Mr. Johnson has built modular homes before, he has no
    prior    experience      in    developing          subdivisions.        SBP      and   JTR
    -3-
    entered into a contract on 14 December 2007 whereby JTR agreed
    to    pave    the     roadways       in       the    subdivision           for    $148,000      (“the
    paving contract”).             The amount of the contract was increased
    $4,870.96 based on a change order; consequently, the total price
    of the contract was $152,870.96.
    JTR completed the work on 18 April 2008.                                     However, SBP
    alleged      that     the    work       failed       to    comply      with      the   stone    base
    requirements          in     the     paving          contract.              Specifically,        SBP
    contended that, based on numerous stone base cores taken, the
    stone base of the roads measured less than the eight inches
    required by the paving contract.                           Consequently, SBP refused to
    pay    the    $152,870.96          it     owed       pursuant         to   the    terms    of    the
    contract.          JTR filed an action on 25 September 2008 against SBP
    alleging breach of contract.                        On 3 December 2008, SBP filed an
    answer and counterclaim against SBP, also alleging breach of the
    paving contract.
    Beginning 7 September 2010, the case was tried by a jury in
    Stanly       County    Superior          Court.            On   10     September,       the     jury
    returned       a    verdict        finding          that    SBP      had    not    breached      the
    contract      and     that    JTR       had    breached         the    contract.          The   jury
    awarded SBP $370,765.82 in damages.                         JTR appealed.
    -4-
    On appeal, JTR argued, inter alia, that the trial court
    erred by denying its motion for a directed verdict and that the
    jury’s   award        of    damages     was   contrary       to   law    and   should   be
    vacated.    Silver Birch I, __ N.C. App. at __, 721 S.E.2d at 702-
    704.     On the first issue, this Court concluded that because
    several of the core samples provided more than a scintilla of
    evidence that JTR failed to comply with the stone base terms of
    the    paving    contract,       the       trial     court    properly    denied   JTR’s
    motion for a directed verdict.                      Id. at __, 721 S.E.2d at 703-
    704.
    On the second issue of damages, JTR failed to preserve the
    issue for appellate review; however, the Court invoked Rule 2 to
    address the issue.             Id. at __, 721 S.E.2d at 704.                   The Court
    noted that SBP was seeking three types of damages: (1) direct
    damages measured as the reasonable costs to SBP of labor and
    materials necessary to correct the asphalt paving services to
    bring it into conformity with the requirements of the paving
    contract;       (2)        incidental      damages      based     on     the   costs    of
    engineering      tests       done     by   the      North    Carolina    Department     of
    Transportation; and (3) consequential damages which consisted of
    the interest payments SBP made on a development loan and the
    lost profits on two lot sales.                      Id. at __, 721 S.E.2d at 704.
    -5-
    After    comparing    the    jury    instructions        with    the   evidence     at
    trial,    this    Court   concluded    that        “[SBP’s]     evidence     did   not
    support     the    full     amount    of     the       jury’s    verdict.”         Id.
    Specifically, with regard to the direct damages, i.e., the “cost
    to fix” damages, the Court held that the direct evidence at
    trial only supported an award of $139,560.                    Id.    For incidental
    damages, the evidence only supported an award of $6,502.82 paid
    to a consultant for testing on the asphalt roads.                       Id. at __,
    721 S.E.2d at 704-705.            With regard to SBP’s interest payments
    on the loan, the evidence presented at trial supported an award
    of $72,017.29, as established by testimony by a loan officer
    handling SBP’s loan.        Id.
    In sum, the Court concluded that the evidence supported an
    award     “considerably      less”    than       the    jury’s      verdict.       Id.
    Therefore, it vacated the damages award and remanded for a new
    trial on the issue of damages.             Id.
    The Motion to Amend SBP’s Counterclaims on Remand
    On remand, the trial court reopened discovery.                         After the
    discovery period was complete, on 17 October 2012, SBP moved to
    amend its counterclaims to request additional damages incurred,
    arguing that its “damages ha[d] changed significantly from the
    original trial in this matter.”               SBP drastically increased its
    -6-
    claim for lost profit damages and interest payments damages with
    these new damages falling into three basic types: lost profits,
    “homebuilder premiums,” and interest payments.                        First, instead
    of only claiming lost profits based on the lost sales on two of
    the lots, SBP claimed lost profits for all 39 lots because, as
    Mr. Johnson averred, the bank foreclosed on the subdivision.
    Thus, SBP lost any and all potential revenues from selling lots
    in the subdivision.           Second, SBP now claimed damages for lost
    “homebuilder premiums.”           Mr. Johnson alleged that he was also
    the   principal     of   Willow    Brook     Homes,     Inc.,     a    company    that
    constructs modular homes.           Since the subdivision was a “closed
    development,” each time someone purchased a lot from SBP, he
    would be required to purchase a modular home for that lot from
    Willow Brook.      To pay off SBP’s loan quicker, Willow Brook would
    pay   SBP   a   “homebuilder      premium”    each     time   a   sale    was    made—
    $20,000 for the first 10 lots, $15,000 for the next 10, $10,000
    for the next 10, and $5,000 for the last dwellings sold.                           The
    total   new     amount   of   requested      damages    for     lost    profits    was
    $1,137,906.       Third, SBP requested additional damages for the
    interest payments made to the bank of $75,033.64.                       Finally, SBP
    now claimed an additional amount of $6,205.82 for additional
    -7-
    engineering fees to inspect the defective work (this on top of
    the original damages of $6,502.02).
    In total, on remand, SBP sought to amend its counterclaim
    to request over $1.2 million in damages.
    JTR’s Motion for Summary Judgment
    On   17    October    2012,    JTR      moved   for    summary       judgment.
    Specifically, JTR argued the lost profits damages and damages
    related to the interest payments SBP made to the bank on its
    loan     were     not      reasonably     foreseeable         and     were     overly
    speculative.
    The Hearing
    Both matters came on for hearing on 29 October 2012 before
    Judge    Royster,    Jr.      After     hearing    from   both      parties,       Judge
    Royster, Jr. noted that the Court of Appeals “vacated the jury’s
    award of $371,000 and sent it back for retrial on [the] damage
    issue.      The     Court    of   Appeals      affirmed      the    fact    that    the
    defendant is entitled to damages.                 So the trial is basically
    just on the amount of damages.”                With regard to SBP’s motion to
    amend, the trial court denied it for two reasons.                          First, the
    trial court concluded that it should be denied because it was
    filed over four years after the initial counterclaim was filed.
    -8-
    Second,      it   should   be    denied       due    to    the     speculative         and
    unforeseeable nature of the newly requested damages.
    The trial court granted JTR’s motion for summary judgment.
    Specifically, the trial court found that interest payments on
    the loan would be a “normal cost of doing business” and would
    not be foreseeable.           Moreover, the trial court determined that
    the lost profit damages were too speculative.                       Thus, the trial
    court   concluded     that     SBP    failed    to    “produce         a    forecast   of
    evidence that would demonstrate specific facts as opposed to
    allegations . . . . to show that they have at least a prima
    facie case to be tried.”          By doing so, the trial court dismissed
    SBP’s claims; however, since JTR did not challenge SBP’s claims
    for damages based on the cost it incurred for engineering tests
    in its summary judgment motion, these claims were to be dealt
    with at trial.
    SBP    appealed.        After    filing   its       notice    of      appeal,    SBP
    voluntarily       dismissed     its    claims       for    the     engineering        test
    damages.
    Arguments
    SBP argues that the trial court erred in denying its motion
    to   amend    its   counterclaim.        Specifically,           SBP       contends   that
    -9-
    because a “post-appeal occurrence [] significantly altered what
    damages
    [it]    can    recover        from     JTR,”        the     trial     court      abused    its
    discretion in denying it.               We disagree.
    “A motion to amend is addressed to the discretion of the
    court, and its decision thereon is not subject to review except
    in case of manifest abuse.”                   Calloway v. Motor Co., 
    281 N.C. 496
    , 501, 
    189 S.E.2d 484
    , 488 (1972).                              “If the trial court
    articulates a clear reason for denying the motion to amend, then
    our review ends.          Acceptable reasons for which a motion to amend
    may    be   denied      are    undue    delay,       bad     faith,    dilatory        motive,
    repeated      failure     to     cure       deficiencies,          undue    prejudice      and
    futility      of    the   amendment.”           NationsBank          of    N.C.,    N.A.    v.
    Baines,     
    116 N.C. App. 263
    ,    268,     
    447 S.E.2d 812
    ,   815   (1994)
    (internal quotation marks omitted).
    Here,      the   record    indicates         that     the    trial     court    denied
    SBP’s motion to amend based on undue delay and futility.                               During
    arguments, the trial court focused a great deal not only on the
    length of time that had elapsed between the initial paving work,
    approximately four years, but also on the foreseeability and the
    speculative nature of these new damages.                            If either of these
    -10-
    grounds exist, the trial court did not abuse its discretion in
    denying SBP’s motion to amend.
    Given     the    substantial      amount     of       time     that    had     elapsed
    between the filing of SBP’s counterclaims and the motion to
    amend,    the    trial    court’s     denial      of    the    motion        to    amend   was
    manifestly       supported       by   reason.            SBP     filed        its    initial
    counterclaim in December 2008.                    The first trial occurred in
    2010.      After       this   Court   reversed         and    remanded       the     judgment
    awarding damages to SBP back to the trial court in December
    2011, SBP still did not move to amend its counterclaim until
    October 2012, almost four years after the initial counterclaims
    were filed and almost one year after remand.                          Moreover, we find
    that     SBP’s    reasoning       behind    the        delay     is    not        compelling.
    Therefore,       the    trial    court   did      not    abuse      its   discretion        in
    denying the motion to amend.
    Next,     SBP    argues    that   the      trial      court     erred       since   its
    action violated the appellate mandate.                    We agree.
    It is well-established that an appellate mandate
    is binding upon the trial court and must be
    strictly   followed   without    variation   or
    departure.    No judgment other than that
    directed or permitted by the appellate court
    may be entered.    We have held judgments of
    Superior [C]ourt which were inconsistent and
    at variance with, contrary to, and modified,
    corrected,   altered    or    reversed    prior
    -11-
    mandates of the Supreme Court . . . to be
    unauthorized and void.
    Lea Co. v. N.C. Bd. of Transp., 
    323 N.C. 697
    , 699, 
    374 S.E.2d 866
    ,     868    (1989)        (internal      quotation        marks       and   citations
    omitted).       Thus, the issue is whether the trial court violated
    the Silver Birch I mandate.
    In Silver Birch I, this Court addressed two issues.                          First,
    the    Court    noted    that       the   trial     court    properly      denied   JTR’s
    motion for a directed verdict and submitted the issue to the
    jury,    noting     that      SBP    “provided       more    than     a    scintilla   of
    evidence regarding [JTR’s] failure to comply with one of the
    terms of the paving contract.”                     
    Id.
     at __, 721 S.E.2d at 703.
    Second, the Court held that the amount of damages awarded by the
    jury exceeded what the evidence would support.                            Id. at __, 721
    S.E.2d    at    705.     Noting       that    the    amount    of     damages    was   not
    supported by the evidence,                this Court vacated the award and
    remanded for a new trial “on the issue of damages.”                              Id.    On
    remand, this Court also provided the trial court a formula with
    which to measure SBP’s direct damages.                  Id.
    While we acknowledge that a directive from an appellate
    court     “[does]       not     render       the     Rules    of      Civil     Procedure
    inapplicable” on remand, see Britt v. Allen, 
    37 N.C. App. 732
    ,
    733, 
    247 S.E.2d 17
    , 18 (1978), here, the trial court’s dismissal
    -12-
    of SBP’s claims by summary judgment is directly contrary to this
    Court’s directive in Silver Birch I to hold a new trial on the
    issue of damages because this Court found that SBP was entitled
    to certain damages, even though the jury’s award exceeded the
    evidence.       In fact, the Court even provided the trial court
    with a formula on how to measure the direct damages.                     
    Id.
     at __,
    721 S.E.2d at 705.          Thus, when the trial court foreclosed on the
    possibility    of     SBP    recovering       any    lost   profit   and    interest
    payments damages, it violated this Court’s determination that
    the evidence supported an award of damages, both of which were
    clearly articulated in this Court’s opinion.
    We find our Court’s decision in Metts v. Piver, 
    102 N.C. App. 98
    ,   101,   
    401 S.E.2d 407
    ,     409    (1991),     instructive.      In
    Metts, the plaintiff filed a medical malpractice action against
    the defendants, and the defendants moved for summary judgment.
    
    Id.
     at       at 99, 
    401 S.E.2d at 408
    .                 The trial court granted
    summary judgment, and the plaintiff appealed.                      
    Id.
         On appeal
    the first time, this Court reversed the order granting summary
    judgment in favor of the defendant, concluding that there was a
    genuine issue of material fact as to whether the defendants were
    negligent.      
    Id.
             On   remand,    the     defendants   again     moved   for
    summary judgment, and the trial court granted the motion.                          
    Id.
    -13-
    On    appeal      the   second    time,    this   Court        found    that    the    trial
    court’s “ruling on the existence of a genuine issue of material
    fact [on remand] is directly contrary to our earlier holding.”
    Id. at 100, 
    401 S.E.2d at 408
    .                    Thus, the Court reversed the
    order and remanded for trial.               Id. at 101, 
    401 S.E.2d at 409
    .
    Similarly, here, since this Court ordered a new trial on
    the    issue      of    damages   and     provided    a    formula      with        which   to
    measure those damages, the trial court’s conclusion that there
    was no issue of material fact with regard to SBP’s claim for
    lost profit damages and damages based on interest payments SBP
    made on its loan conflicted with this Court’s decision in Silver
    Birch    I    that      the   evidence    supported       an    award    of    direct       and
    consequential damages.             Although this Court concluded that the
    amount       of   damages      awarded     exceeded       the    amount        of    damages
    supported by the evidence in Silver Birch I, it affirmed that
    SBP was entitled to some lost profit damages, damages based on
    SBP’s interest payments,             and direct       damages.1          Moreover, the
    trial court reiterated this point at the hearing on JTR’s motion
    1
    In addition, this Court held that SBP was entitled to $6,502.82
    in incidental damages based on payments SBP made to a consultant
    to test the roads.     Silver Birch I, __ N.C. App. at __, 721
    S.E.2d at 704-705. However, after the trial court granted JTR’s
    motion for summary judgment, SBP voluntarily dismissed its claim
    for incidental damages.    Therefore, we need not discuss these
    damages on appeal.
    -14-
    for summary judgment when it noted that: “The Court of Appeals
    affirmed the fact that the defendant is entitled to damages.”
    Thus, as in Metts, we reverse the trial court’s order granting
    summary judgment and remand for trial on the issue of damages.2
    Next, we will determine what damages SBP will be entitled
    to on remand.      In the original trial, the trial court instructed
    the jury that the direct damages were “the reasonable cost to
    [SBP] of labor and materials necessary to correct the asphalt
    paving     services       to   bring     it     into    conformity     with     the
    requirements of the contract.”            Silver Birch I, __ N.C. App. at
    __, 721 S.E.2d at 704.           This Court specifically found that the
    evidence    at   trial     supported     an   award    of   $139,560   in   direct
    damages—$124,250 to repair the subdivision asphalt, $11,310 to
    repair   and     reseed    the   sides    of    the    roads,   and    $4,000    in
    additional engineering costs.             Id.    Since “the cost of repairs
    required to bring the property into compliance with the warranty
    or contract” is a proper method of measuring damages for defects
    in construction contracts, Warfield v. Hicks, 
    91 N.C. App. 1
    ,
    11, 
    370 S.E.2d 689
    , 695 (1988), SBP is entitled to $139,560 in
    direct “cost to fix” damages.             However, given that SBP has not
    2
    Since we are reversing the trial court’s order granting summary
    judgment, we need not address SBP’s final argument regarding the
    merits of summary judgment.
    -15-
    paid JTR for its work on the contract, Silver Birch I, __ N.C.
    App. at __, 721 S.E.2d at 705, these damages must be offset by
    the value of the work performed by JTR for SBP so that SBP does
    not receive a windfall recovery.       See id.    Therefore, SBP would
    owe   JTR   $13,310.96—the   amount    of   the   contract   price   of
    $152,870.96 less the amount of the “cost to fix” direct damages
    of $139,560.    Under this measure of damages, SBP will get the
    work it contracted for and will pay the price it contracted for,
    $152,870.96.
    Furthermore, SBP would be entitled to the lost profits on
    two of the lots and damages based on the interest payments SBP
    made on its loan.    “[L]ost profits damages are usually defined
    as lost net profits[.]”      Stan D. Bowles Distrib. Co. v. Pabst
    Brewing Co., 
    80 N.C. App. 588
    , 597, 
    343 S.E.2d 543
    , 548 (1986).
    Accordingly, the jury must determine what SBP’s net profit on
    each of the two lost lot sales would be measured in accordance
    with this opinion.     Furthermore, as stated by this Court in
    Silver Birch I, SBP is entitled to damages based on the interest
    payments SBP made to the bank on its loan.         The Silver Birch I
    Court held that the amount of the interest payments supported by
    the evidence was $72,017.29.     Silver Birch I, __ N.C. App. at
    -16-
    __, 721 S.E.2d at 705.         Thus, any damages must include the
    $72,017.29 for the interest payments SBP made.
    Conclusion
    In summary, we affirm the trial court’s order denying SBP’s
    motion to amend its counterclaims on the basis of undue delay.
    However, we reverse the order granting summary judgment in favor
    of JTR and remand on the issue of damages in accordance with
    this opinion.    The trial court must award $72,017.29 to SBP, the
    amount of interest payments that SBP made on its loan to the
    bank.   Second, with regard to the cost to fix damages, while SBP
    is entitled to $139,560, the amount it would cost to fix the
    roads which was established by the evidence in the original
    trial, this amount must be offset by the value of the work
    performed by JTR based on the contract price since SBP has not
    paid anything to JTR for its work.          Accordingly, JTR would be
    entitled   to   $13,310.96—the    amount     of    the    contract    price,
    $152,870.96,    less   the   amount   of   the    “cost   to   fix”   direct
    damages, $139,560.      Finally, the lost profit damages for two
    lots is a question for the jury to determine in accordance with
    this opinion.
    AFFIRMED IN PART; REVERSED IN PART; REMANDED ON THE ISSUE
    OF DAMAGES.
    -17-
    Judges CALABRIA and HUNTER, JR., ROBERT N. concur.
    Report per Rule 30(e).