Tsonev v. McAir ( 2020 )


Menu:
  •                IN THE COURT OF APPEALS OF NORTH CAROLINA
    No. COA19-674
    Filed: 4 August 2020
    Dare County, No. 16-CVS-644
    DIANA TSONEV for the ESTATE of ROBERT SHEARER and MINERVA SHEARER
    by DIANA TSONEV, Plaintiffs,
    v.
    MCAIR, INC. d/b/a OUTER BANKS HEATING & COOLING and MCAIR, INC. d/b/a
    DR. ENERGY SAVER, Defendant.
    Appeal by plaintiffs from orders entered 20 March 2019 by Judge Alma Hinton
    in Dare County Superior Court. Heard in the Court of Appeals 7 January 2020.
    The Wills Law Group, by Gregory E. Wills, for plaintiff-appellants.
    McAngus Goudelock & Courie, PLLC, by Walt Rapp and Sean R. Madden, for
    defendant-appellees.
    BRYANT, Judge.
    Parties are generally free to contract as they see fit. Where, as here, the
    contract contains an express provision that no action may be brought more than two
    years after the completion of the work contracted, we affirm the trial court’s directed
    verdict dismissing an action commenced more than five years after completion of the
    work.
    PROCEDURAL HISTORY/ FACTS
    TSONEV V. MCAIR, INC.
    Opinion of the Court
    Mr. and Mrs. Robert Shearer, represented by Diana Tsonev,1 (“plaintiffs”) filed
    a complaint against defendant McAir, Inc. d/b/a Outer Banks Heating and Cooling
    (“defendant McAir OBHC”) and McAir, Inc, d/b/a Dr. Energy Saver (“defendant McAir
    DES”) (collectively “defendants”) on 29 November 2016 in Dare County Superior
    Court. Plaintiffs alleged that defendants did not properly remediate flood damage to
    their home and negligently caused damage in excess of $25,000. Plaintiffs sought
    recovery for negligence, negligent misrepresentation, breach of contract, breach of
    implied warranty, and breach of express warranty. On 28 January 2019, a jury trial
    commenced before the Honorable Alma Hinton, Judge presiding.
    The evidence of record shows that plaintiffs owned a house in Kill Devil Hills,
    North Carolina. On 27 August 2011, the home was damaged by flood waters as a
    result of Hurricane Irene. Plaintiffs hired defendant McAir OBHC to repair the
    HVAC system, which included replacing the duct system under the house. Defendant
    McAir informed plaintiffs that their affiliated company, defendant McAir DES, could
    remediate other damage to the subfloor and crawlspace under the house. Defendant
    McAir DES submitted a proposal to plaintiffs detailing the scope of the work to be
    performed, which included six items. Defendant McAir DES would (1) remove all
    insulation under the home, (2) foam seal the chimney base and all penetrations of
    electrical or plumbing works, (3) treat all biochemical areas of the crawlspace, (4)
    1  Upon the death of Robert Shearer his daughter, Diana Tsonev, was allowed to be substituted
    as plaintiff for Robert and allowed to represent Minerva Shearer as her attorney in fact.
    -2-
    TSONEV V. MCAIR, INC.
    Opinion of the Court
    install new R-19 bat insulation, (5) clean all wood in the crawlspace, and (6) clean up
    and remove all debris. The proposal stated that a chemical treatment and seal
    (“Aftershock”) would be applied in order to stop existing mold growth. A number of
    terms and conditions provided that the contract would supply only the work specified
    and that all services performed and materials supplied would be free from defects for
    two years following installation. “[Defendant McAir DES] [is] not liable for any
    consequential, incidental, indirect, punitive, treble, speculative, or special damages
    of any kind whatsoever, and [purchasers] may not bring any action against
    [defendant McAir DES] more than two (2) years after the Completion Date.” Finally,
    the proposal contained a merger clause which stated the following:
    This Agreement (and all attachments) contain the entire,
    final agreement between you and us, and supersedes all
    prior written and oral agreements, proposals, and
    understandings. You (i) have had the opportunity to
    review it with an attorney of your choice, (ii) have read and
    understood each part, (iii) are satisfied with all of its
    provisions, and (iv) affirm that neither we, nor any of our
    representatives, have made, nor have you relied on any
    other representatives or promises, oral or otherwise, that
    are outside this Agreement. All waivers must be in writing
    to be effective.
    Plaintiffs signed and accepted the proposal on 2 September 2011. The crawlspace
    remediation was completed at the end of September 2011.
    Almost five years later, in July 2016, plaintiffs noticed that the floor of the
    residence was sagging. Thereafter, plaintiffs discovered that in the crawlspace, the
    -3-
    TSONEV V. MCAIR, INC.
    Opinion of the Court
    wood which had been painted with Aftershock had rotted. A building inspector later
    examined the crawlspace. Floor joists and girders had failed and collapsed, and the
    rest were in the process of failing. The inspector condemned the house as being
    unsafe for human occupants.
    Following the close of plaintiff’s case-in-chief, the court rendered a directed
    verdict in favor of defendants. Plaintiffs filed a motion for a new trial. On 20 March
    2019, the court entered its written order granting defendants’ motion for directed
    verdict.
    [T]he [c]ourt . . . finds that there is a contract in this case
    that calls for any action to be taken within two years. That
    action was not taken. The contract was signed by [p]laintiff
    and it appears to be a valid contract acknowledged by
    [defendant McAir DES], or a representative thereof, that
    requires action to be taken within two years.
    On 20 March 2019, the court also entered its order denying plaintiffs’ motion for a
    new trial. Plaintiffs appeal both orders.
    _______________________________________________________
    On appeal, plaintiffs contend the trial court erred by (I) failing to apply the
    “discovery rule,” (II) excluding evidence in support of the claim for negligent
    misrepresentation, (III & IV) excluding expert witness testimony, and (V) entering a
    directed verdict and failing to grant plaintiffs’ motion for a new trial.
    Standard of Review
    -4-
    TSONEV V. MCAIR, INC.
    Opinion of the Court
    When considering a motion for a
    directed verdict, a trial court must view the
    evidence in the light most favorable to the
    non-moving party, giving that party the
    benefit of every reasonable inference arising
    from the evidence.         Any conflicts and
    inconsistencies in the evidence must be
    resolved in favor of the non-moving party. If
    there is more than a scintilla of evidence
    supporting each element of the non-moving
    party’s claim, the motion for a directed verdict
    should be denied.
    . . . [B]ecause the trial court’s ruling on a motion for a
    directed verdict addressing the sufficiency of the evidence
    presents a question of law, it is reviewed de novo.
    Bradley Woodcraft, Inc. v. Bodden, 
    251 N.C. App. 27
    , 31, 
    795 S.E.2d 253
    , 257 (2016)
    (citations omitted).
    I
    Plaintiffs argue that the trial court erred by granting the motion for a directed
    verdict and not applying the “discovery rule,” pursuant to N.C. Gen. Stat. §§ 1-52(16)
    and 1-50(5) (describing periods of repose and limitation for the commencement of
    actions arising from improvements to real property). Plaintiffs contend that the
    directed verdict granted on the basis of their failure to bring this action within the
    two-year period expressed in the contract was improper as they commenced the action
    within the periods set by our statutes of limitation and repose as defined by sections
    1-52(16) and -50(5). We disagree.
    -5-
    TSONEV V. MCAIR, INC.
    Opinion of the Court
    N.C. Gen. Stat. § 1-52(16) states that “unless otherwise provided by law, for . .
    . physical damage to claimant’s property, the cause of action . . . shall not accrue until
    . . . physical damage to his property becomes apparent . . . .” N.C. Gen. Stat. § 1-
    52(16) (2019). Additionally, N.C. Gen. Stat. § 1-50(5) states that,
    [n]o action to recover damages based upon or arising out of
    the defective or unsafe condition of an improvement to real
    property shall be brought more than six years from the
    later of the specific last act or omission of the defendant
    giving rise to the cause of action or substantial completion
    of the improvement.
    Id. § 1-50(5). N.C.
    Gen. Stat. § 1-50(5) sets out a six-year statute of repose that is meant to
    provide “protection to those who make improvements to real property.” Christie v.
    Hartley Constr., 
    367 N.C. 534
    , 540, 
    766 S.E.2d 283
    , 288 (2014). In Christie, our
    Supreme Court reasoned that there was “no public policy reason why the beneficiary
    of a statute of repose cannot bargain away, or even waive, that benefit.” Id. at 540,
    
    766 S.E.2d 283
    , 287. “North Carolina has long recognized that parties generally are
    ‘free to contract as they deem appropriate.’ ” Id. at 540, 
    766 S.E.2d 283
    , 287 (quoting
    Hlasnick v. Federated Mut. Ins. Co., 
    353 N.C. 240
    , 244, 
    539 S.E.2d 274
    , 277 (2000)).
    This Court has also stated that when “the language of a contract ‘is clear and only
    one reasonable interpretation exists, the courts must enforce the contract as written.’
    ” State ex rel. Utils. Comm’n v. Thrifty Call, Inc., 
    154 N.C. App. 58
    , 63, 
    571 S.E.2d 622
    , 626 (2002) (quoting Woods v. Nationwide Mut. Ins. Co., 
    295 N.C. 500
    , 506, 246
    -6-
    TSONEV V. MCAIR, INC.
    Opinion of the Court
    S.E.2d 773, 777 (1978)); see also Hall v. Refining Co., 
    242 N.C. 707
    , 709, 
    89 S.E.2d 396
    , 397 (1955) (“While contracts exempting persons from liability for negligence are
    not favored by the law, and are strictly construed against those relying thereon
    nevertheless, the majority rule, to which we adhere, is that, subject to certain
    limitations . . . a person may effectively bargain against liability for harm caused by
    his ordinary negligence in the performance of a legal duty arising out of a contractual
    relation.” (citations omitted)); Bob Timberlake Collection, Inc. v. Edwards, 176 N.C.
    App. 33, 43–44, 
    626 S.E.2d 315
    , 323–24 (2006) (holding that the plaintiff’s failure to
    adhere to the express provision of the contract—setting the period during which an
    action for damages could be brought—was controlling).
    Agreements signed by plaintiffs can exempt defendants from liability for
    negligence alleged in the complaint. See 
    Hall, 242 N.C. at 709
    , 89 S.E.2d at 397 (“[A]
    person may effectively bargain against liability for harm caused by his ordinary
    negligence in the performance of a legal duty arising out of a contractual relation.”
    (citations omitted)).   While we are not unsympathetic to the injury suffered to
    plaintiffs’ real property and otherwise, our sympathy cannot displace our duty to
    apply the law. Had plaintiffs not signed the agreement which clearly limited the time
    in which an action could be brought, plaintiffs’ claims could have gone forward subject
    to the discovery rule and/or the statute of repose. However, absent evidence of fraud
    or misrepresentation in the making of the contract, plaintiffs are bound by the
    -7-
    TSONEV V. MCAIR, INC.
    Opinion of the Court
    language in the contract into which they entered. See Herring v. Herring, 231 N.C.
    App. 26, 28, 
    752 S.E.2d 190
    , 192 (2013) (“[A]ny . . . contract . . . may be set aside or
    reformed based on grounds such as fraud, mutual mistake of fact, or unilateral
    mistake of fact procured by fraud.” (citations omitted)); Top Line Constr. Co. v. J.W.
    Cook & Sons, Inc., 
    118 N.C. App. 429
    , 432–33, 
    455 S.E.2d 463
    , 465 (1995) (affirming
    summary judgment against the plaintiff who sought monetary damages for work
    completed but not compensated where the plaintiff expressly agreed to be bound by
    the decision of a third party architect or engineer as to the satisfaction, approval, or
    acceptance of the plaintiff’s work).
    In the instant case, the contract provided that the writing contained the entire,
    final agreement of the parties. The provisions of the contract included an express
    limitation: “[defendant is] not liable for any consequential, incidental, indirect,
    punitive, treble, speculative, or special damages of any kind whatsoever, and you may
    not bring any action against us more than two (2) years after the Completion Date.”
    (emphasis added). The crawlspace remediation was completed in September 2011.
    Plaintiffs’ brought suit in November 2016, more than five years later.
    Because the express provision of the contract is clear, the contract must be
    enforced as written. See 
    Hall, 242 N.C. at 709
    , 89 S.E.2d at 397; Herring, 231 N.C.
    App. at 
    28, 752 S.E.2d at 192
    ; Bob Timberlake Collection, 
    Inc., 176 N.C. App. at 43
    44, 626 S.E.2d at 323
    –24; Thrifty Call, 
    Inc., 154 N.C. App. at 63
    , 571 S.E.2d at 626;
    -8-
    TSONEV V. MCAIR, INC.
    Opinion of the Court
    Top Line Constr. 
    Co., 118 N.C. App. at 432
    –33, 455 S.E.2d at 465. The trial court did
    not err by failing to apply the discovery rule in accordance with N.C. Gen. Stat. §§ 1-
    52(16) and 1-50(5), and thus, plaintiff’s argument is overruled. Accordingly, we
    affirm the 20 March 2019 order of the trial court granting defendants’ motion for a
    directed verdict.
    As we affirm the court’s 20 March 2019 order granting defendant’s motion for
    a directed verdict based on the express limitation in the contract, we need not reach
    plaintiffs’ remaining arguments.
    AFFIRMED.
    Judges ZACHARY and COLLINS concur.
    -9-