RM Campbell Indus. v. Midwest Renewable Energy , 294 Neb. 326 ( 2016 )


Menu:
  • Nebraska Supreme Court Online Library
    www.nebraska.gov/apps-courts-epub/
    07/29/2016 09:07 AM CDT
    - 326 -
    Nebraska Supreme Court A dvance Sheets
    294 Nebraska R eports
    RM CAMPBELL INDUS. v. MIDWEST RENEWABLE ENERGY
    Cite as 
    294 Neb. 326
    RM Campbell Industrial, Inc., appellee,
    v. M idwest R enewable Energy,
    LLC, appellant.
    ___ N.W.2d ___
    Filed July 29, 2016.    No. S-15-529.
    1.	 Res Judicata: Collateral Estoppel. The applicability of claim and issue
    preclusion is a question of law.
    2.	 Statutes. Statutory interpretation presents a question of law.
    3.	 Principal and Agent. The scope of an agent’s authority is a question
    of fact.
    4.	 Jury Instructions: Appeal and Error. Whether a jury instruction
    is correct is a question of law, which an appellate court indepen-
    dently decides.
    5.	 Jury Instructions: Proof: Appeal and Error. To establish reversible
    error from a court’s failure to give a requested jury instruction, an appel-
    lant has the burden to show that (1) the tendered instruction is a correct
    statement of the law, (2) the tendered instruction was warranted by the
    evidence, and (3) the appellant was prejudiced by the court’s failure to
    give the requested instruction.
    6.	 Contracts. The determination of whether goods or nongoods predomi-
    nate a contract is generally a question of law.
    7.	 Judgments: Res Judicata. The doctrine of res judicata, or claim pre-
    clusion, bars the relitigation of a matter that has been directly addressed
    or necessarily included in a former adjudication if (1) the former
    judgment was rendered by a court of competent jurisdiction, (2) the
    former judgment was a final judgment, (3) the former judgment was
    on the merits, and (4) the same parties or their privies were involved in
    both actions.
    8.	 Res Judicata. The doctrine of res judicata, or claim preclusion, bars
    relitigation not only of those matters actually litigated, but also of those
    matters which might have been litigated in the prior action.
    - 327 -
    Nebraska Supreme Court A dvance Sheets
    294 Nebraska R eports
    RM CAMPBELL INDUS. v. MIDWEST RENEWABLE ENERGY
    Cite as 
    294 Neb. 326
    9.	 ____. The doctrine of res judicata, or claim preclusion, rests on the
    necessity to terminate litigation and on the belief that a person should
    not be vexed twice for the same cause.
    10.	 Judgments: Collateral Estoppel. Under the doctrine of collateral estop-
    pel, or issue preclusion, when an issue of ultimate fact has been deter-
    mined by a final judgment, that issue cannot again be litigated between
    the same parties in a future lawsuit.
    11.	 Collateral Estoppel. There are four conditions that must exist for issue
    preclusion to apply: (1) The identical issue was decided in a prior action,
    (2) there was a judgment on the merits which was final, (3) the party
    against whom the rule is applied was a party or in privity with a party
    to the prior action, and (4) there was an opportunity to fully and fairly
    litigate the issue in the prior action.
    12.	 Res Judicata: Collateral Estoppel. In contrast to claim preclusion, the
    doctrine of issue preclusion does not apply to matters which might or
    could have been litigated but were not.
    13.	 Principal and Agent: Words and Phrases. An “agent” is a person
    authorized by the principal to act on the principal’s behalf and under the
    principal’s control.
    14.	 Agency. For an agency relationship to arise, the principal manifests
    assent to the agent that the agent will act on the principal’s behalf and
    subject to the principal’s control and the agent manifests assent or other-
    wise consents so to act.
    15.	 Agency: Intent. An agency relationship may be implied from the
    words and conduct of the parties and the circumstances of the case evi-
    dencing an intention to create the relationship irrespective of the words
    or terminology used by the parties to characterize or describe their
    relationship.
    16.	 Principal and Agent. Actual authority is authority that the princi-
    pal expressly grants to the agent or authority to which the principal
    consents.
    17.	 ____. A subcategory of actual authority is implied authority, which
    courts typically use to denote actual authority either to (1) do what is
    necessary to accomplish the agent’s express responsibilities or (2) act
    in a manner that the agent reasonably believes the principal wishes the
    agent to act, in light of the principal’s objectives and manifestations.
    18.	 ____. When a principal delegates authority to an agent to accomplish
    a task without specific directions, the grant of authority includes the
    agent’s ability to exercise his or her discretion and make reasonable
    determinations concerning the details of how the agent will exercise
    that authority.
    - 328 -
    Nebraska Supreme Court A dvance Sheets
    294 Nebraska R eports
    RM CAMPBELL INDUS. v. MIDWEST RENEWABLE ENERGY
    Cite as 
    294 Neb. 326
    19.	 ____. Apparent authority is authority that is conferred when the princi-
    pal affirmatively, intentionally, or by lack of ordinary care causes third
    persons to act upon an agent’s apparent authority.
    20.	 ____. Apparent authority gives an agent the power to affect the princi-
    pal’s legal relationships with third parties. The power arises from and
    is limited to the principal’s manifestations to those third parties about
    the relationships.
    21.	 Principal and Agent: Proof. Apparent authority for which a principal
    may be liable exists only when the third party’s belief is traceable to the
    principal’s manifestation and cannot be established by the agent’s acts,
    declarations, or conduct. Manifestations include explicit statements the
    principal makes to a third party or statements made by others concern-
    ing an actor’s authority that reach the third party and the third party can
    trace to the principal.
    22.	 Principal and Agent. For apparent authority to exist, the principal
    must act in a way that induces a reasonable third person to believe that
    another person has authority to act for him or her.
    23.	 ____. Whether an agent has apparent authority to bind the principal
    is a factual question determined from all the circumstances of the
    transaction.
    24.	 Jury Instructions: Pleadings: Evidence. A litigant is entitled to have
    the jury instructed upon only those theories of the case which are pre-
    sented by the pleadings and which are supported by competent evidence.
    25.	 Contracts: Actions: Substantial Performance. To successfully bring
    an action on a contract, a plaintiff must first establish that the plaintiff
    substantially performed the plaintiff’s obligations under the contract. To
    establish substantial performance under a contract, any deviations from
    the contract must be relatively minor and unimportant.
    26.	 Contracts: Substantial Performance. If there is substantial perform­
    ance, a contract action may be maintained, but without prejudice to any
    showing of damage on the part of the defendant for failure to receive
    full and complete performance.
    27.	 Contracts: Substantial Performance: Damages. Where there is a
    lack of substantial performance, but there has been a part performance
    and it has been of substantial benefit to the other party and he or she
    has accepted and retained the benefits thereof, he or she should not
    be permitted entirely to avoid the duties assumed by him or her under
    his or her contract, and, under such circumstances, the party partially
    performing is entitled to recover the reasonable or fair value of such
    performance, subject to the reciprocal right of the other party to recoup
    such damages as he or she has suffered from the failure of the part-
    performing party to perform fully or substantially his or her contract.
    - 329 -
    Nebraska Supreme Court A dvance Sheets
    294 Nebraska R eports
    RM CAMPBELL INDUS. v. MIDWEST RENEWABLE ENERGY
    Cite as 
    294 Neb. 326
    28.	 Uniform Commercial Code. Nebraska’s Uniform Commercial Code
    applies to transactions in goods. If a transaction is not for the sale of
    goods, the provisions of the Uniform Commercial Code do not apply to
    that transaction.
    29.	 Uniform Commercial Code: Sales: Warranty. The test for inclusion
    in or exclusion from the sales provisions of the Uniform Commercial
    Code is not whether the contracts are mixed but, granting that they are
    mixed, whether their predominant factor, their thrust, their purpose,
    reasonably stated, is the rendition of service, with goods incidentally
    involved, or whether they are transactions of sale, with labor inciden-
    tally involved.
    30.	 ____: ____: ____. The Uniform Commercial Code applies when the
    principal purpose of the transaction is the sale of goods, even though
    in order for the goods to be utilized, some installation is required. On
    the other hand, if the contract is principally for services and the goods
    are merely incidental to the contract, the provisions of the Uniform
    Commercial Code do not apply.
    31.	 Contracts: Quantum Meruit. Quantum meruit is premised on the
    existence of a contract implied by law; however, the law only implies a
    contract and allows a recovery under the theory when the parties have
    not entered into an express agreement.
    Appeal from the District Court for Douglas County: Timothy
    P. Burns, Judge. Affirmed.
    Jerrold L. Strasheim for appellant.
    Karl Von Oldenburg, of Brumbaugh & Quandahl, P.C.,
    L.L.O., for appellee.
    Heavican, C.J., Wright, Connolly, Miller-Lerman, Cassel,
    Stacy, and K elch, JJ.
    Heavican, C.J.
    INTRODUCTION
    RM Campbell Industrial, Inc. (Campbell), filed suit against
    Midwest Renewable Energy, LLC (Midwest), for breach of
    contract and sought damages in the amount of $158,010.98.
    Following trial, the jury found for Campbell in the amount of
    $154,510.98. Midwest appeals. We affirm.
    - 330 -
    Nebraska Supreme Court A dvance Sheets
    294 Nebraska R eports
    RM CAMPBELL INDUS. v. MIDWEST RENEWABLE ENERGY
    Cite as 
    294 Neb. 326
    FACTUAL BACKGROUND
    Midwest owns an ethanol plant in Sutherland, Nebraska. At
    the relevant time, Randall Kramer worked for both Midwest and
    another entity, KL Process Design Group, LLC (KL Process).
    In August 2006, at a time when Kramer worked for both enti-
    ties simultaneously, Kramer entered into a purchase order con-
    tract with Campbell for work on the first phase in the construc-
    tion of the Sutherland plant. It is not disputed that the work
    pursuant to this contract was paid for and completed.
    In November 2006, Kramer again approached Campbell
    about doing work as a subcontractor on the expansion of the
    Sutherland plant. Second and third phases were anticipated,
    but Campbell and Kramer entered into a contract for goods and
    services for only the second phase of the project. The contract,
    entered into on November 9, totaled $2,411,431.02. By this
    time, Kramer was employed only by KL Process and the terms
    of the contract itself indicated that the contract was between
    Campbell and KL Process.
    Initially, Campbell sent invoices for payment to KL Process’
    offices in South Dakota. But by May 2007, the owner and
    president of Campbell testified he was told to send the invoices
    directly to Midwest at the address of the Sutherland plant.
    Invoices were approved by KL Process and then paid by
    Midwest’s controller on Midwest’s account; the evidence shows
    that this was done primarily to take advantage of tax incentives
    offered by the State of Nebraska, colloquially referred to as
    “L.B. 775” incentives.1
    In August 2007, KL Process updated Campbell on its finan-
    cial situation and Midwest’s current inability to pay outstand-
    ing balances until new financing had been obtained. No com-
    plaint was made about Campbell’s performance. In February
    2008, Midwest wrote to Campbell regarding Midwest’s lack of
    1
    See, 1987 Neb. Laws, L.B. 775; Employment and Investment Growth
    Act, Neb. Rev. Stat. §§ 77-4101 to 77-4112 (Reissue 2009 & Cum. Supp.
    2014).
    - 331 -
    Nebraska Supreme Court A dvance Sheets
    294 Nebraska R eports
    RM CAMPBELL INDUS. v. MIDWEST RENEWABLE ENERGY
    Cite as 
    294 Neb. 326
    payment and acknowledged an amount owed of $919,020.45.
    Midwest also sent a check for $32,089.96, with the promise of
    an additional $30,000 to be paid monthly thereafter.
    But no payment was made in March. Midwest acknowl-
    edged the debt in writing once more, made no complaint about
    Campbell’s services, and promised to make payment as soon
    as there was money to do so. That same month, KL Process
    informed Campbell that it had ceased work on the second
    phase of the project, but that it believed the work stoppage
    was temporary; however, work never resumed on the sec-
    ond phase.
    Campbell filed suit against KL Process (now KL Energy
    Corporation) and Midwest. KL Energy Corporation is in bank-
    ruptcy and is not a party to this appeal. Suit proceeded against
    Midwest for breach of contract based upon the 2-page pur-
    chase order between KL Process and Campbell.
    Several threshold issues were decided prior to trial and are
    relevant on appeal. Midwest contended that a prior lien action
    involving the Sutherland plant filed in Lincoln County District
    Court barred Campbell’s action under the principles of col-
    lateral estoppel and res judicata. Midwest also contended that
    Campbell, a foreign corporation, lacked the appropriate certifi-
    cate to transact business or file suit in Nebraska. These argu-
    ments were both rejected by the district court.
    At trial, Midwest argued that there was no contract between
    it and Campbell because KL Process lacked the actual or
    apparent authority to bind Midwest to any agreement. Midwest
    also argued that Campbell failed to substantially complete its
    obligations under the contract. The jury found for Campbell in
    the amount of $154,510.98.
    ASSIGNMENTS OF ERROR
    Midwest assigns, consolidated and restated, that the district
    court erred in (1) finding that Campbell’s breach of contract
    action was not barred by res judicata or collateral estoppel; (2)
    finding that Campbell could maintain suit despite its failure to
    - 332 -
    Nebraska Supreme Court A dvance Sheets
    294 Nebraska R eports
    RM CAMPBELL INDUS. v. MIDWEST RENEWABLE ENERGY
    Cite as 
    294 Neb. 326
    hold a Nebraska certificate of authority; (3) concluding there
    was sufficient evidence for a jury question on (a) whether
    KL Process acted as an agent of Midwest in entering into the
    subcontract with Campbell and (b) whether KL Process had
    actual or apparent authority to bind Midwest to the subcontract,
    such that there was an enforceable contract between Midwest
    and Campbell, and in instructing the jury as it did; (4) not find-
    ing that Campbell had to prove substantial compliance with
    the subcontract and not instructing the jury on this; (5) finding
    there was a jury question regarding proximate causation; (6)
    applying article 2 of Nebraska’s Uniform Commercial Code
    (U.C.C.) and not the common law to the agreement; and (7)
    finding there was a jury question on damages and incorrectly
    instructing the jury regarding damages.
    STANDARD OF REVIEW
    [1] The applicability of claim and issue preclusion is a ques-
    tion of law.2
    [2] Statutory interpretation presents a question of law.3
    [3] The scope of an agent’s authority is a question of fact.4
    [4] Whether a jury instruction is correct is a question of law,
    which an appellate court independently decides.5
    [5] To establish reversible error from a court’s failure to
    give a requested jury instruction, an appellant has the burden
    to show that (1) the tendered instruction is a correct statement
    of the law, (2) the tendered instruction was warranted by the
    evidence, and (3) the appellant was prejudiced by the court’s
    failure to give the requested instruction.6
    2
    McGill v. Lion Place Condo. Assn., 
    291 Neb. 70
    , 
    864 N.W.2d 642
    (2015).
    3
    Pettit v. Nebraska Dept. of Corr. Servs., 
    291 Neb. 513
    , 
    867 N.W.2d 553
          (2015).
    4
    Koricic v. Beverly Enters. - Neb., 
    278 Neb. 713
    , 
    773 N.W.2d 145
    (2009).
    5
    Golnick v. Callender, 
    290 Neb. 395
    , 
    860 N.W.2d 180
    (2015).
    6
    
    Id. - 333
    -
    Nebraska Supreme Court A dvance Sheets
    294 Nebraska R eports
    RM CAMPBELL INDUS. v. MIDWEST RENEWABLE ENERGY
    Cite as 
    294 Neb. 326
    [6] The determination of whether goods or nongoods pre-
    dominate a contract is generally a question of law.7
    ANALYSIS
    Effect of Lincoln County
    Construction Lien.
    In its first assignment of error, Midwest assigns that the dis-
    trict court erred in not finding that the dismissal of Campbell’s
    construction lien at the time of the judicial foreclosure of
    another lienholder’s lien operated to preclude Campbell’s suit.
    Campbell filed a construction lien on the Sutherland plant
    in Lincoln County, Nebraska, on April 11, 2008. Another sup-
    plier, Avid Solutions, Inc. (Avid), subsequently commenced a
    foreclosure on its own construction lien on September 29. Avid
    named Campbell as a fellow lienholder and served it with the
    complaint against Midwest. Campbell did not appear.
    Proceedings continued against Midwest in Avid’s foreclo-
    sure. In a journal entry dated June 7, 2011, the district court
    ruled on several preliminary matters, including noting that a
    “default judgment will be entered against any Defendant who
    does not appear at the contested trial.” The district court’s
    decree, entered on July 14, noted that Campbell, as well as oth-
    ers, did not appear at trial and that their liens were “dismissed
    and released.”
    [7-9] The doctrine of res judicata, or claim preclusion, bars
    the relitigation of a matter that has been directly addressed or
    necessarily included in a former adjudication if (1) the former
    judgment was rendered by a court of competent jurisdiction,
    (2) the former judgment was a final judgment, (3) the for-
    mer judgment was on the merits, and (4) the same parties or
    their privies were involved in both actions.8 The doctrine bars
    7
    See MBH, Inc. v. John Otte Oil & Propane, 
    15 Neb. Ct. App. 341
    , 
    727 N.W.2d 238
    (2007) (citing to other jurisdictions as issue of first impression in
    Nebraska).
    8
    Eicher v. Mid America Fin. Invest. Corp., 
    270 Neb. 370
    , 
    702 N.W.2d 792
          (2005).
    - 334 -
    Nebraska Supreme Court A dvance Sheets
    294 Nebraska R eports
    RM CAMPBELL INDUS. v. MIDWEST RENEWABLE ENERGY
    Cite as 
    294 Neb. 326
    relitigation not only of those matters actually litigated, but also
    of those matters which might have been litigated in the prior
    action.9 The doctrine rests on the necessity to terminate litiga-
    tion and on the belief that a person should not be vexed twice
    for the same cause.10
    [10,11] Under the doctrine of collateral estoppel, or issue
    preclusion, when an issue of ultimate fact has been deter-
    mined by a final judgment, that issue cannot again be litigated
    between the same parties in a future lawsuit.11 There are four
    conditions that must exist for issue preclusion to apply: (1) The
    identical issue was decided in a prior action, (2) there was a
    judgment on the merits which was final, (3) the party against
    whom the rule is applied was a party or in privity with a party
    to the prior action, and (4) there was an opportunity to fully
    and fairly litigate the issue in the prior action.12
    [12] As an initial matter, we conclude that issue preclu-
    sion is not applicable here to bar Campbell’s suit. In contrast
    to claim preclusion, the doctrine of issue preclusion does not
    apply to matters which might or could have been litigated but
    were not.13 Campbell never appeared in Avid’s lien foreclosure
    proceedings, and the issue of whether Campbell and Midwest
    had an agreement was not fully and fairly litigated for pur-
    poses of issue preclusion.
    Turning next to claim preclusion, we conclude that the
    issue of an agreement between Campbell and Midwest was
    not decided on its merits. Claim preclusion bars relitigation,
    not only of those matters actually litigated, but also of those
    matters which might have been litigated in the prior action.
    But we conclude that there was no decision on the merits in
    the underlying lien foreclosure, because Campbell did not
    9
    
    Id. 10 Id.
    11
    
    Id. 12 Id.
    13
    47 Am. Jur. 2d Judgments § 493 (2006).
    - 335 -
    Nebraska Supreme Court A dvance Sheets
    294 Nebraska R eports
    RM CAMPBELL INDUS. v. MIDWEST RENEWABLE ENERGY
    Cite as 
    294 Neb. 326
    participate in the Avid foreclosure and was a party only by
    virtue of Neb. Rev. Stat. § 52-155(2) (Reissue 2010), which
    provides that “all claimants having recorded liens may join as
    plaintiffs and those who do not join as plaintiffs may be joined
    as defendants.”
    The district court and Campbell rely on Tilt-Up Concrete
    v. Star City/Federal,14 which holds that a construction lien
    did not eliminate a contractor’s common-law right to sue for
    breach of contract. While we do not find Tilt-Up Concrete to
    be absolutely dispositive as to issue preclusion, we noted in
    that case that a plaintiff on similar facts was not precluded
    from bringing a contract action simply because the plaintiff
    also foreclosed on a construction lien. The choice inherent
    from Tilt-Up Concrete would be obviated if we were to con-
    clude that, here, Avid’s foreclosing on its own lien precluded
    other lienholders from bringing a separate action to recover
    contract damages.
    Midwest’s first assignment of error is without merit.
    Certificate of Authority.
    In its second assignment of error, Midwest assigns that the
    district court erred in not dismissing Campbell’s suit, because
    Campbell is a foreign corporation that does not hold a Nebraska
    certificate of authority. It is not disputed that Campbell is a
    foreign corporation and has not, at any relevant time, held a
    certificate of authority in Nebraska.
    Neb. Rev. Stat. § 21-20,168(1) (Reissue 2012) provides
    that “[a] foreign corporation may not transact business in
    this state until it obtains a certificate of authority from the
    Secretary of State.” As relevant to this analysis, subsection
    (2) of § 21-20,168 explains that, among other exceptions,
    transacting business in interstate commerce shall not constitute
    transacting business within the meaning of subsection (1) of
    14
    Tilt-Up Concrete v. Star City/Federal, 
    261 Neb. 64
    , 
    621 N.W.2d 502
          (2001).
    - 336 -
    Nebraska Supreme Court A dvance Sheets
    294 Nebraska R eports
    RM CAMPBELL INDUS. v. MIDWEST RENEWABLE ENERGY
    Cite as 
    294 Neb. 326
    § 21-20,168.15 Neb. Rev. Stat. § 21-20,169(1) (Reissue 2012)
    provides that “[a] foreign corporation transacting business in
    this state without a certificate of authority may not maintain a
    proceeding in any court in this state until it obtains a certificate
    of authority.”
    A court must attempt to give effect to all parts of a statute,
    and if it can be avoided, no word, clause, or sentence will be
    rejected as superfluous or meaningless.16 Statutes relating to
    the same subject, although enacted at different times, are in
    pari materia and should be construed together.17
    Reading §§ 21-20,168 and 21-20,169 together, we conclude
    that because Campbell was transacting business in interstate
    commerce, it was not transacting business for purposes of
    § 21-20,169(1).
    This result is consistent with Allenberg Cotton Co. v.
    Pittman.18 There, the plaintiff, a foreign corporation, sued
    to enforce a contract with a Mississippi defendant. The
    Mississippi Supreme Court held that the contract was in intra-
    state commerce and could not be maintained by a foreign cor-
    poration. The U.S. Supreme Court disagreed and held that the
    contract was in interstate commerce and that the Mississippi
    statute precluding suit by a foreign corporation which did
    not hold a certificate of authority was in contravention of the
    Commerce Clause.
    We conclude that Campbell did not need to obtain a certifi-
    cate of authority in order to maintain this suit against Midwest.
    There is no merit to Midwest’s second assignment of error.
    Existence of Contract.
    In its third assignment of error, Midwest contends that
    there was no enforceable contract between it and Campbell,
    15
    See, also, Allenberg Cotton Co. v. Pittman, 
    419 U.S. 20
    , 
    95 S. Ct. 260
    , 
    42 L. Ed. 2d 195
    (1974).
    16
    Stick v. City of Omaha, 
    289 Neb. 752
    , 
    857 N.W.2d 561
    (2015).
    17
    Caniglia v. Caniglia, 
    285 Neb. 930
    , 
    830 N.W.2d 207
    (2013).
    18
    Allenberg Cotton Co. v. Pittman, supra note 15.
    - 337 -
    Nebraska Supreme Court A dvance Sheets
    294 Nebraska R eports
    RM CAMPBELL INDUS. v. MIDWEST RENEWABLE ENERGY
    Cite as 
    294 Neb. 326
    because it did not directly enter into a contract with Campbell
    and because KL Process was not Midwest’s agent and was not
    acting with actual or apparent authority. Midwest also assigns
    that instruction No. 5 was an incorrect statement of the law
    and that the district court erred in not giving its proposed
    instructions Nos. 6 through 8.
    [13-15] An “agent” is a person authorized by the principal to
    act on the principal’s behalf and under the principal’s control.19
    For an agency relationship to arise, the principal “manifests
    assent” to the agent that the agent will “‘act on the principal’s
    behalf and subject to the principal’s control.’”20 And the agent
    “‘manifests assent or otherwise consents so to act.’”21 An
    agency relationship may be implied from the words and con-
    duct of the parties and the circumstances of the case evidencing
    an intention to create the relationship irrespective of the words
    or terminology used by the parties to characterize or describe
    their relationship.22
    [16-18] Actual authority is authority that the principal
    expressly grants to the agent or authority to which the prin-
    cipal consents.23 A subcategory of actual authority is implied
    authority, which courts typically use to denote actual authority
    either to (1) do what is necessary to accomplish the agent’s
    express responsibilities or (2) act in a manner that the agent
    reasonably believes the principal wishes the agent to act, in
    light of the principal’s objectives and manifestations.24 When
    a principal delegates authority to an agent to accomplish a
    task without specific directions, the grant of authority includes
    the agent’s ability to exercise his or her discretion and make
    19
    Koricic v. Beverly Enters. - Neb., supra note 4.
    20
    
    Id. at 717,
    773 N.W.2d at 150.
    21
    
    Id. 22 Id.
    23
    
    Id. 24 Koricic
    v. Beverly Enters. - Neb., supra note 4.
    - 338 -
    Nebraska Supreme Court A dvance Sheets
    294 Nebraska R eports
    RM CAMPBELL INDUS. v. MIDWEST RENEWABLE ENERGY
    Cite as 
    294 Neb. 326
    r­easonable determinations concerning the details of how the
    agent will exercise that authority.25
    [19-21] Apparent authority is authority that is conferred
    when the principal affirmatively, intentionally, or by lack of
    ordinary care causes third persons to act upon an agent’s appar-
    ent authority.26 Apparent authority gives an agent the power
    to affect the principal’s legal relationships with third parties.27
    The power arises from and is limited to the principal’s mani-
    festations to those third parties about the relationships.28 Stated
    another way, apparent authority for which a principal may be
    liable exists only when the third party’s belief is traceable
    to the principal’s manifestation and cannot be established
    by the agent’s acts, declarations, or conduct.29 Manifestations
    include explicit statements the principal makes to a third party
    or statements made by others concerning an actor’s author-
    ity that reach the third party and the third party can trace to
    the principal.30
    [22,23] For apparent authority to exist, the principal must
    act in a way that induces a reasonable third person to believe
    that another person has authority to act for him or her.31
    Whether an agent has apparent authority to bind the principal
    is a factual question determined from all the circumstances of
    the transaction.32
    Midwest is, of course, correct in that it did not directly
    contract with Campbell. Midwest further argues that this
    25
    
    Id. 26 StoreVisions.
    v. Omaha Tribe of Neb., 
    281 Neb. 238
    , 
    795 N.W.2d 271
          (2011).
    27
    
    Id. 28 Id.
    29
    
    Id. 30 Id.
    31
    
    Id. 32 Id.
                                 - 339 -
    Nebraska Supreme Court A dvance Sheets
    294 Nebraska R eports
    RM CAMPBELL INDUS. v. MIDWEST RENEWABLE ENERGY
    Cite as 
    294 Neb. 326
    court need look no further than the terms of the contract
    between it and KL Process to see that KL Process was not
    acting as its agent. That contract specifically notes:
    Nothing in the Contract Documents is intended or deemed
    to create any legal or contractual relationship between
    [Midwest] and Design Consultant, any Subcontractor
    or Sub-Subcontractor, except that KL Process shall
    provide in its contracts with such Subcontractor and
    Sub-Subcontractors that [Midwest] is an intended third
    party beneficiary of those contracts with the right to
    enforce them.
    But there is no evidence that Campbell or its owner and
    president was aware of the terms of the contract between
    Midwest and KL Process. Moreover, the contract between
    Campbell and KL Process was executed in November 2006. At
    that time, the contract between Midwest and KL Process had
    not yet been executed; the latter contract was not entered into
    until July 18, 2007.
    A review of other provisions of that contract show that while
    Midwest may not have wanted to be liable on contracts entered
    into by KL Process, it nevertheless maintained a significant
    amount of control over KL Process. For example, KL Process
    had to provide notice to Midwest of any design consultant or
    subcontractor it wished to use and could not enter into bind-
    ing contracts with those parties without notice to Midwest.
    And Midwest had veto power over any design consultant or
    subcontractor.
    In any case, how KL Process and Midwest characterized
    their relationship does not affect our resolution of this issue.
    As this court has noted, an agency relationship may be implied
    from the words and conduct of the parties and the circum-
    stances of the case evidencing an intention to create the rela-
    tionship, irrespective of the words or terminology used by the
    parties to characterize or describe their relationship.
    The jury was instructed in instruction No. 4 as follows:
    - 340 -
    Nebraska Supreme Court A dvance Sheets
    294 Nebraska R eports
    RM CAMPBELL INDUS. v. MIDWEST RENEWABLE ENERGY
    Cite as 
    294 Neb. 326
    An agency relationship existed in this case between
    [Midwest] and KL Process if you find [Midwest] con-
    sented to these two things:
    1. That KL Process would act on behalf of [Midwest],
    and
    2. That [Midwest] would have the right to control
    KL Process’ acts. It does not matter whether [Midwest]
    actually exercised control over KL Process, so long as
    [Midwest] had the right to do so.
    Instruction No. 5 provided:
    An agency may also exist, by apparent authority, if
    you find:
    1. That [Midwest] led [Campbell] to believe that KL
    Process was authorized to act on behalf of [Midwest],
    and
    2. That [Campbell’s] belief that KL Process had author-
    ity to act for [Midwest] was reasonable.
    If you so find, then as between [Midwest] and
    [Campbell], [Midwest] is bound by the acts of KL Process.
    The evidence at trial was that the contract between Midwest
    and KL Process indicated that Midwest was not legally bound
    by any contract with a subcontractor. But the evidence also
    showed that Midwest hired KL Process to build its ethanol
    plant and that Campbell knew the work it had been hired to do
    was to be done for Midwest. The evidence also showed that at
    the time of the first phase of the project, Kramer worked for
    both Midwest and KL Process when he hired Campbell. The
    evidence showed that Midwest paid Campbell and acknowl-
    edged the debt owed to Campbell on multiple occasions via
    e-mail and letter. Finally, the evidence showed that because
    of the tax incentives,33 it was to Midwest’s advantage to pay
    Campbell directly. Given all this, we conclude there was suf-
    ficient evidence that an agency relationship existed in this
    case, by either actual or apparent authority.
    33
    See, L.B. 775; §§ 77-4101 to 77-4112.
    - 341 -
    Nebraska Supreme Court A dvance Sheets
    294 Nebraska R eports
    RM CAMPBELL INDUS. v. MIDWEST RENEWABLE ENERGY
    Cite as 
    294 Neb. 326
    [24] We turn next to Midwest’s arguments regarding the jury
    instructions on the question of apparent authority. To estab-
    lish reversible error from a court’s failure to give a requested
    jury instruction, an appellant has the burden to show that (1)
    the tendered instruction is a correct statement of the law, (2)
    the tendered instruction was warranted by the evidence, and
    (3) the appellant was prejudiced by the court’s failure to give
    the requested instruction.34 A litigant is entitled to have the
    jury instructed upon only those theories of the case which are
    presented by the pleadings and which are supported by compe-
    tent evidence.35
    Midwest objected to instruction No. 5 and had requested
    instead that its proposed instructions Nos. 6 through 8 be given
    to the jury.
    As to instruction No. 5, Midwest contends that the jury
    should have been instructed that the party relying on apparent
    authority cannot be negligent and must use ordinary prudence
    and that instruction No. 5 was in error because it did not so
    state. Midwest contended that its proposed instruction No. 6
    was a virtual copy of NJI2d Civ. 6.08, entitled “Agency—
    Apparent Authority,” and that instruction No. 7, regarding
    reliance on apparent authority, and instruction No. 8, defining
    negligence, should have also been given to the jury.
    We disagree with Midwest’s characterization of its pro-
    posed instruction No. 6. In reality, the instruction given,
    instruction No. 5, and not proposed instruction No. 6, was
    almost identical to NJI2d Civ. 6.08. Contrary to Midwest’s
    assertion, NJI2d Civ. 6.08 does not require that the jury find
    that the party relying on the apparent authority not be negli-
    gent and use ordinary prudence. Rather, a jury must only find
    that the party must be acting reasonably.
    The district court did not err in instructing the jury in con-
    formity with instruction No. 5 instead of Midwest’s proposed
    34
    Golnick v. Callender, supra note 5.
    35
    Worth v. Kolbeck, 
    273 Neb. 163
    , 
    728 N.W.2d 282
    (2007).
    - 342 -
    Nebraska Supreme Court A dvance Sheets
    294 Nebraska R eports
    RM CAMPBELL INDUS. v. MIDWEST RENEWABLE ENERGY
    Cite as 
    294 Neb. 326
    instructions Nos. 6 and 7, dealing with apparent authority.
    And because the jury did not need to be instructed as to
    negligence, it was not error for the court to refuse proposed
    instruction No. 8. There is no merit to Midwest’s third assign-
    ment of error.
    Substantial Compliance.
    In its fourth assignment of error, Midwest contends that the
    district court erred in not finding that Campbell had to prove
    that it had substantially complied with the contract and so
    instructing the jury.
    [25,26] To successfully bring an action on a contract, a
    plaintiff must first establish that the plaintiff substantially
    performed the plaintiff’s obligations under the contract.36 To
    establish substantial performance under a contract, any devia-
    tions from the contract must be relatively minor and unimport-
    ant.37 If there is substantial performance, a contract action may
    be maintained, but without prejudice to any showing of dam-
    age on the part of the defendant for failure to receive full and
    complete performance.38
    [27] Where there is a lack of substantial performance, but
    there has been a part performance and it has been of substan-
    tial benefit to the other party and he or she has accepted and
    retained the benefits thereof, he or she should not be permitted
    entirely to avoid the duties assumed by him or her under his or
    her contract, and, under such circumstances, the party partially
    performing is entitled to recover the reasonable or fair value of
    such performance, subject to the reciprocal right of the other
    party to recoup such damages as he or she has suffered from
    the failure of the part-performing party to perform fully or
    substantially his or her contract.39
    36
    VRT, Inc. v. Dutton-Lainson Co., 
    247 Neb. 845
    , 
    530 N.W.2d 619
    (1995).
    37
    
    Id. 38 Id.
    39
    See Young v. Tate, 
    232 Neb. 915
    , 
    442 N.W.2d 865
    (1989).
    - 343 -
    Nebraska Supreme Court A dvance Sheets
    294 Nebraska R eports
    RM CAMPBELL INDUS. v. MIDWEST RENEWABLE ENERGY
    Cite as 
    294 Neb. 326
    Midwest argues that instructions Nos. 3 and 8, provid-
    ing for damages generally and giving the specific measure
    of damages, were incorrect, because they did not instruct
    regarding substantial performance. But on these facts, we find
    no error.
    There is no dispute that the full terms of the goods and
    services contract were not met; Campbell ceased providing
    goods and services when Midwest stopped paying for the
    work already done. But the record shows that on these facts,
    this was part performance that was a substantial benefit to
    Midwest, which accepted and retained the benefit through both
    the goods received and the tax incentives.
    First, we note that the record shows that Midwest attempted
    to resell the products which Campbell provided under the con-
    tract. And Midwest acknowledged on various occasions that
    it owed the amount now at issue in this litigation. As such,
    Midwest should not be permitted to avoid the duty to pay.
    There is no merit to Midwest’s fourth assignment of error.
    Proximate Causation.
    In its fifth assignment of error, Midwest contends Campbell
    did not prove that Midwest’s ceasing payments was the proxi-
    mate cause of its claimed damages. Particularly, Midwest con-
    tends that Campbell’s contract was with KL Process and that
    the reason Campbell was not paid was because KL Process
    declared bankruptcy.
    Having concluded that the jury could find that KL Process
    was acting as Midwest’s agent, there was also sufficient evi-
    dence for a jury to find that Campbell’s contract losses were
    due to Midwest’s failure to pay. The record is replete with
    evidence that Midwest, and not KL Process, paid Campbell’s
    invoices and that Midwest acknowledged that a cash short-
    age meant it had not paid Campbell what was due and further
    indicated Midwest would pay Campbell as soon as it had
    funds to do so.
    This assignment of error is without merit.
    - 344 -
    Nebraska Supreme Court A dvance Sheets
    294 Nebraska R eports
    RM CAMPBELL INDUS. v. MIDWEST RENEWABLE ENERGY
    Cite as 
    294 Neb. 326
    Applicability of U.C.C.
    In its sixth and seventh assignments of error, Midwest
    contends that the district court erred in treating this as a con-
    tract under the U.C.C. rather than as one under common law
    and, accordingly, erred in its damages instruction to the jury.
    Specifically, Midwest objected to instructions Nos. 6 and 8.
    As to instruction No. 6, Midwest argues that it utilized sale-
    of-goods language from the U.C.C. when the contract was not
    controlled by the U.C.C. but by common law. And Midwest
    contends that, accordingly, the instruction on damages—
    instruction No. 8—should have been on quantum meruit, not
    the contract price instruction given to the jury.
    [28-30] The U.C.C. applies to transactions in goods.40 If a
    transaction is not for the sale of goods, the provision of the
    U.C.C. do not apply to that transaction.41
    The test for inclusion in or exclusion from the sales
    provisions is not whether the contracts are mixed but,
    granting that they are mixed, whether their predominant
    factor, their thrust, their purpose, reasonably stated, is the
    rendition of service, with goods incidentally involved, or
    whether they are transactions of sale, with labor inciden-
    tally involved.42
    The U.C.C. applies when the principal purpose of the transac-
    tion is the sale of goods, even though in order for the goods to
    be utilized, some installation is required.43 On the other hand,
    if the contract is principally for services and the goods are
    merely incidental to the contract, the provisions of the U.C.C.
    do not apply.44
    40
    Neb. U.C.C. § 2-102 (Reissue 2001).
    41
    Mennonite Deaconess Home & Hosp. v. Gates Eng’g Co., 
    219 Neb. 303
    ,
    
    363 N.W.2d 155
    (1985).
    42
    
    Id. at 308,
    363 N.W.2d at 160.
    43
    Design Data Corp. v. Maryland Cas. Co., 
    243 Neb. 945
    , 
    503 N.W.2d 552
          (1993).
    44
    
    Id. - 345
    -
    Nebraska Supreme Court A dvance Sheets
    294 Nebraska R eports
    RM CAMPBELL INDUS. v. MIDWEST RENEWABLE ENERGY
    Cite as 
    294 Neb. 326
    The total original contract was for $2,411,431.02. From
    examining that contract, over one-half of the total contract
    appears to be for goods, with the remainder for services. As
    such, we conclude that this contract was predominantly for the
    sale of goods and that the U.C.C. controls. There was no error
    in the damages instruction as given.
    [31] And even if the contract were governed by the common
    law, we disagree that the proper measure of damages would
    have been under quantum meruit. Quantum meruit is premised
    on the existence of a contract implied by law; however, the law
    only implies a contract and allows a recovery under the theory
    when the parties have not entered into an express agreement.45
    But there is no dispute that there was an express contract
    in this case; the real issue is whether Midwest is a party to
    it. We have concluded that it was. Quantum meruit is there-
    fore inapplicable.
    Moreover, contrary to Midwest’s contention, Campbell
    introduced proof of its damages in the form of the original
    contract price, the amount of goods and services provided to
    Midwest, and the amount actually paid by Midwest. This was
    an adequate measure of damages.
    There is no merit to Midwest’s sixth and seventh assign-
    ments of error.
    CONCLUSION
    The decision of the district court is affirmed.
    A ffirmed.
    45
    Tobin v. Flynn & Larsen Implement Co., 
    220 Neb. 259
    , 
    369 N.W.2d 96
          (1985).
    

Document Info

Docket Number: S-15-529

Citation Numbers: 294 Neb. 326

Filed Date: 7/29/2016

Precedential Status: Precedential

Modified Date: 3/3/2020

Authorities (13)

Design Data Corp. v. Maryland Casualty Co. , 243 Neb. 945 ( 1993 )

VRT, INC. v. Dutton-Lainson Co. , 247 Neb. 845 ( 1995 )

Young v. Tate , 232 Neb. 915 ( 1989 )

Caniglia v. Caniglia , 285 Neb. 930 ( 2013 )

Tobin v. Flynn & Larsen Implement Co. , 220 Neb. 259 ( 1985 )

Koricic v. BEVERLY ENTERPRISES-NEBRASKA , 278 Neb. 713 ( 2009 )

MBH, INC. v. John Otte Oil & Propane, Inc. , 15 Neb. Ct. App. 341 ( 2007 )

Eicher v. Mid America Financial Investment Corp. , 270 Neb. 370 ( 2005 )

Mennonite Deaconess Home & Hospital, Inc. v. Gates ... , 219 Neb. 303 ( 1985 )

Tilt-Up Concrete, Inc. v. Star City/Federal, Inc. , 261 Neb. 64 ( 2001 )

Worth v. Kolbeck , 273 Neb. 163 ( 2007 )

RM Campbell Indus. v. Midwest Renewable Energy , 294 Neb. 326 ( 2016 )

Allenberg Cotton Co. v. Pittman , 95 S. Ct. 260 ( 1974 )

View All Authorities »

Cited By (91)

Rodriguez v. Lasting Hope Recovery Ctr. , 308 Neb. 538 ( 2021 )

City of Sidney v. Municipal Energy Agency of Neb. , 301 Neb. 147 ( 2018 )

Bloedorn Lumber Co. v. Nielson , 300 Neb. 722 ( 2018 )

Bloedorn Lumber Co. v. Nielson , 300 Neb. 722 ( 2018 )

Bloedorn Lumber Co. v. Nielson , 300 Neb. 722 ( 2018 )

City of Sidney v. Municipal Energy Agency of Neb. , 301 Neb. 147 ( 2018 )

Armstrong v. Clarkson College , 297 Neb. 595 ( 2017 )

Armstrong v. Clarkson College , 297 Neb. 595 ( 2017 )

Armstrong v. Clarkson College , 297 Neb. 595 ( 2017 )

Bloedorn Lumber Co. v. Nielson , 300 Neb. 722 ( 2018 )

Bloedorn Lumber Co. v. Nielson , 300 Neb. 722 ( 2018 )

Bloedorn Lumber Co. v. Nielson , 300 Neb. 722 ( 2018 )

Bloedorn Lumber Co. v. Nielson , 300 Neb. 722 ( 2018 )

City of Sidney v. Municipal Energy Agency of Neb. , 301 Neb. 147 ( 2018 )

City of Sidney v. Municipal Energy Agency of Neb. , 301 Neb. 147 ( 2018 )

Bloedorn Lumber Co. v. Nielson , 300 Neb. 722 ( 2018 )

Armstrong v. Clarkson College , 297 Neb. 595 ( 2017 )

City of Sidney v. Municipal Energy Agency of Neb. , 301 Neb. 147 ( 2018 )

Bloedorn Lumber Co. v. Nielson , 300 Neb. 722 ( 2018 )

Bloedorn Lumber Co. v. Nielson , 915 N.W.2d 786 ( 2018 )

View All Citing Opinions »