Western Ethanol Co. v. Midwest Renewable Energy , 305 Neb. 1 ( 2020 )


Menu:
  • Nebraska Supreme Court Online Library
    www.nebraska.gov/apps-courts-epub/
    03/20/2020 09:07 AM CDT
    -1-
    Nebraska Supreme Court Advance Sheets
    305 Nebraska Reports
    WESTERN ETHANOL CO. v. MIDWEST RENEWABLE ENERGY
    Cite as 
    305 Neb. 1
    Western Ethanol Company, LLC,
    appellee, v. Midwest Renewable
    Energy, LLC, appellant.
    ___ N.W.2d ___
    Filed February 14, 2020.   No. S-18-1192.
    1. Judgments: Jurisdiction: Appeal and Error. When a jurisdictional
    question does not involve a factual dispute, determination of a juris-
    dictional issue is a matter of law which requires an appellate court to
    reach a conclusion independent from the trial court’s; however, when
    a determination rests on factual findings, a trial court’s decision on the
    issue will be upheld unless the factual findings concerning jurisdiction
    are clearly incorrect.
    2. Jurisdiction: Appeal and Error. Before reaching the legal issues
    presented for review, it is the duty of an appellate court to determine
    whether it has jurisdiction over the matter before it.
    3. Jurisdiction: Final Orders: Appeal and Error. For an appellate court
    to acquire jurisdiction of an appeal, the party must be appealing from a
    final order or a judgment.
    4. Final Orders: Appeal and Error. The three types of final orders that
    an appellate court may review are (1) an order that affects a substantial
    right and that determines the action and prevents a judgment, (2) an
    order that affects a substantial right made during a special proceeding,
    and (3) an order that affects a substantial right made on summary appli-
    cation in an action after a judgment is rendered.
    5. ____: ____. A substantial right is affected if an order affects the subject
    matter of the litigation, such as diminishing a claim or defense that was
    available to an appellant before the order from which an appeal is taken.
    6. Contracts: Assignments. An assignment is a contract between the
    assignor and the assignee, and is interpreted or construed according to
    the rules of contract construction.
    7. Contracts: Parties. Only a party (actual or alleged) to a contract can
    challenge its validity.
    -2-
    Nebraska Supreme Court Advance Sheets
    305 Nebraska Reports
    WESTERN ETHANOL CO. v. MIDWEST RENEWABLE ENERGY
    Cite as 
    305 Neb. 1
    8. ____: ____. Parties can recover as third-party beneficiaries of a contract
    only if it appears that the rights and interest of the third parties were
    contemplated and that provision was being made for them.
    9. Assignments: Debtors and Creditors. If the assignment is effective to
    pass legal title, the debtor cannot interpose defects or objections which
    merely render the assignment voidable at the election of the assignor
    or those standing in his or her shoes. However, a debtor may assert as
    a defense any matter which renders the assignment absolutely invalid,
    ineffective, or void.
    10. Assignments: Actions. An assignee of a chose in action assigned for
    the purpose of collection is the real party in interest and authorized to
    maintain an action thereon.
    11. Assignments: Actions: Parties: Standing: Jurisdiction: Proof. An
    assignee can establish standing to bring an action in its own name, and
    thus show the court had subject matter jurisdiction, if it proves by a pre-
    ponderance of the evidence the existence of a written assignment under
    Neb. Rev. Stat. § 25-304 (Reissue 2016).
    12. Evidence: Records: Pleadings: Appeal and Error. An appellate record
    typically contains the bill of exceptions, used to present factual evidence
    to an appellate court, and the transcript, used to present pleadings and
    orders of the case to the appellate court.
    13. Evidence: Records: Appeal and Error. A bill of exceptions is the only
    vehicle for bringing evidence before an appellate court; evidence which
    is not made a part of the bill of exceptions may not be considered.
    14. Actions: Judicial Notice: Appeal and Error. In interwoven and inter-
    dependent cases, an appellate court may examine its own records and
    take judicial notice of the proceedings and judgment in a former action
    involving one of the parties.
    15. Actions: Judicial Notice: Records: Appeal and Error. An appellate
    court may take judicial notice of a document, including briefs filed in
    an appeal, in a separate but related action concerning the same subject
    matter in the same court.
    16. Pleadings: Evidence: Waiver: Words and Phrases. A judicial admis-
    sion is a formal act done in the course of judicial proceedings which is
    a substitute for evidence, thereby waiving or dispensing with the pro-
    duction of evidence by conceding for the purpose of litigation that the
    proposition of fact alleged by the opponent is true.
    17. Jurisdiction. While parties cannot confer subject matter jurisdiction
    upon a judicial tribunal by either acquiescence or consent, nor may
    subject matter jurisdiction be created by waiver, estoppel, consent, or
    conduct of the parties, such does not prevent a party from conclusively
    admitting the truth of an underlying fact required to establish subject
    matter jurisdiction by judicial admission.
    -3-
    Nebraska Supreme Court Advance Sheets
    305 Nebraska Reports
    WESTERN ETHANOL CO. v. MIDWEST RENEWABLE ENERGY
    Cite as 
    305 Neb. 1
    18. Estoppel. The doctrine of judicial estoppel protects the integrity of the
    judicial process by preventing a party from taking a position inconsistent
    with one successfully and unequivocally asserted by the same party in a
    prior proceeding.
    19. Estoppel: Intent. Fundamentally, the intent behind the doctrine of judi-
    cial estoppel is to prevent parties from gaining an advantage by taking
    one position in a proceeding and then switching to a different position
    when convenient in a later proceeding.
    20. Estoppel. Whether judicial estoppel is applicable turns on whether the
    court has accepted inconsistent positions from the plaintiff.
    21. ____. Judicial acceptance does not require that a party prevail on the
    merits, but only that the first court adopted the position urged by the
    party, either as a preliminary matter or as part of a final disposition.
    22. Trial: Waiver: Appeal and Error. Failure to make a timely objection
    waives the right to assert prejudicial error on appeal.
    Appeal from the District Court for Lincoln County: Richard
    A. Birch, Judge. Affirmed.
    Dean J. Jungers for appellant.
    William J. Troshynski, of Brouillette, Dugan & Troshynski,
    P.C., L.L.O., for appellee.
    Heavican, C.J., Miller-Lerman, Cassel, Stacy, Funke,
    Papik, and Freudenberg, JJ.
    Funke, J.
    The judgment debtor, Midwest Renewable Energy, LLC
    (Midwest Renewable), appeals from the denial of its motion to
    quash execution of a judgment. Midwest Renewable argued to
    the district court that the original judgment creditor, Western
    Ethanol Company, LLC (Western Ethanol), had not assigned
    the judgment to Douglas B. Vind, the managing member
    of Western Ethanol who requested execution after Western
    Ethanol dissolved. The district court disagreed and found that
    the judgment had been assigned to Vind. Finding no merit in
    Midwest Renewable’s appeal, we affirm the decision of the
    district court.
    -4-
    Nebraska Supreme Court Advance Sheets
    305 Nebraska Reports
    WESTERN ETHANOL CO. v. MIDWEST RENEWABLE ENERGY
    Cite as 
    305 Neb. 1
    I. BACKGROUND
    A judgment against Midwest Renewable was transcribed
    in Nebraska in 2010. This is the second appeal brought by
    Midwest Renewable disputing the ownership of that judgment.
    In its first appeal,1 Midwest Renewable argued that Western
    Ethanol had no interest in the judgment because the judgment
    had been assigned to Vind. Midwest Renewable argues in the
    present appeal that there was no valid assignment to Vind. The
    following background describes the two different cases, which
    involve the same judgment, and the circumstances which led
    Midwest Renewable to assert contradictory positions when it
    filed appeals with this court.
    Western Ethanol was a limited liability company formed
    under Nevada law and registered in California. In September
    2010, Western Ethanol obtained a judgment against Midwest
    Renewable in California for attorney fees in the amount of
    $30,066.59, plus interest. In November 2010, pursuant to the
    Nebraska Uniform Enforcement of Foreign Judgments Act,
    Neb. Rev. Stat. §§ 25-1587.01 to 25-1587.09 (Reissue 2016),
    Western Ethanol filed an action in Nebraska and transcribed
    the California judgment. Western Ethanol then filed a writ of
    execution on the judgment and attempted to execute upon the
    judgment multiple times to no avail. In 2013, Western Ethanol
    dissolved and distributed its assets to its members.
    In September 2014, Midwest Renewable filed a quiet title
    action against Western Ethanol, and other entities, which
    claimed an interest in Midwest Renewable’s ethanol manu-
    facturing facility located in Lincoln County, Nebraska. When
    Midwest Renewable moved for partial summary judgment
    against Western Ethanol, an affidavit executed by Vind was
    entered into evidence which alleged that Western Ethanol
    had transferred the California judgment to him. There was no
    assignment of judgment in the record, and Vind had not been
    made a party to the litigation. The district court overruled the
    1
    See Midwest Renewable Energy v. American Engr. Testing, 
    296 Neb. 73
    ,
    
    894 N.W.2d 221
    (2017).
    -5-
    Nebraska Supreme Court Advance Sheets
    305 Nebraska Reports
    WESTERN ETHANOL CO. v. MIDWEST RENEWABLE ENERGY
    Cite as 
    305 Neb. 1
    motion for partial summary judgment. Midwest Renewable
    settled with the other parties, and the matter proceeded to
    trial against Western Ethanol as the only remaining defendant.
    Following trial, the court found that Western Ethanol had trans-
    ferred its interest to Vind and that the judgment lien was valid
    and subsisting. Thus, the court dismissed the quiet title action
    against Western Ethanol.
    Midwest Renewable appealed to this court and argued that
    the district court erred by failing to quiet Western Ethanol’s
    claim. Midwest Renewable argued that “Western Ethanol has
    no interest in the judgment because it transferred all of its
    assets, including the judgment, to Vind and its other members
    on or before December 31, 2013.”2
    In our opinion disposing of that appeal, issued in March
    2017, we concluded that the judgment against Midwest
    Renewable was assignable and that “if Midwest Renewable
    is correct in arguing that Western Ethanol’s judgment was
    assigned, then . . . Vind would be the only party capable of
    enforcing or defending the judgment and judgment lien against
    Midwest Renewable.”3 We determined that Vind was an indis-
    pensable party; that the court erred in failing to make Vind a
    party to the action before rendering a decision; and that with-
    out Vind’s presence, the court lacked subject matter jurisdiction
    to make a determination as to the owner of the judgment and
    the judgment lien. We vacated the district court’s decision with
    direction to order Vind be named a party to the action.
    Following remand in the quiet title action, Midwest
    Renewable unsuccessfully attempted to personally serve Vind
    with a summons. The court then permitted service by publi-
    cation, which Midwest Renewable completed. Vind filed an
    answer, and Midwest Renewable served Vind with discovery
    requests. We have no further information in our record regard-
    ing the status of the quiet title action.
    2
    
    Id. at 86,
    894 N.W.2d at 234.
    3
    
    Id. at 88,
    894 N.W.2d at 235.
    -6-
    Nebraska Supreme Court Advance Sheets
    305 Nebraska Reports
    WESTERN ETHANOL CO. v. MIDWEST RENEWABLE ENERGY
    Cite as 
    305 Neb. 1
    In June 2017, in the present registration and enforce-
    ment of a foreign judgment case, Western Ethanol filed an
    “Acknowledgment of Assignment of Foreign Judgment.” The
    document was signed by Vind as managing member and trustee
    on behalf of Western Ethanol. It stated, “PLEASE TAKE
    NOTICE that [Western Ethanol] does hereby acknowledge
    assignment of all interest, right and title to the foreign judg-
    ment entered against [Midwest Renewable].” Western Ethanol
    then filed an amended acknowledgment of assignment which
    clarified that the judgment had been assigned to Vind.
    Without filing a formal pleading or motion to enter the case,
    Vind, as assignee, filed a praecipe for writ of execution. The
    praecipe stated that based on the amount of the judgment plus
    interest, Midwest Renewable owed Vind $51,156.64. Vind
    requested execution on Midwest Renewable’s real estate. The
    clerk of court issued a writ of execution in conformance with
    the praecipe.
    Midwest Renewable filed a motion to quash the execution.
    The motion argued that (1) no assignment of the judgment to
    Vind had been recorded with the court, (2) any assignment
    of the judgment was improper because Western Ethanol had
    dissolved, (3) Vind lacked authority to enforce the judgment,
    and (4) the validity of the judgment was under litigation in the
    quiet title action.
    At the hearing on the motion to quash, Vind’s counsel
    appeared, without objection from Midwest Renewable, and
    argued against the motion. Vind’s counsel argued that the
    acknowledgments of assignment provide notice of the assign-
    ment to Midwest Renewable and the public.
    After reviewing evidence and the parties’ briefs, the court
    entered an order finding that the amended acknowledgment of
    assignment was sufficient to establish that Vind was the suc-
    cessor in interest to the foreign judgment. The court further
    found that the judgment was not dormant, and it overruled the
    motion to quash. Midwest Renewable filed a motion to alter
    or amend which asserted that Vind lacked standing and is not
    -7-
    Nebraska Supreme Court Advance Sheets
    305 Nebraska Reports
    WESTERN ETHANOL CO. v. MIDWEST RENEWABLE ENERGY
    Cite as 
    305 Neb. 1
    the real party in interest, requesting a hearing pursuant to our
    holding in Jacobs Engr. Group v. ConAgra Foods.4 Following
    a hearing, the court found that Vind is the real party in interest
    and overruled the motion.
    Midwest Renewable appealed, and Vind appeared as appel-
    lee. We moved the appeal to our docket pursuant to our statu-
    tory authority to regulate the caseloads of the appellate courts
    of this State.5
    II. ASSIGNMENTS OF ERROR
    Midwest Renewable assigns, restated, that the district court
    erred in (1) finding that Vind owns the judgment to be exe-
    cuted, (2) finding that Vind had properly been made a party to
    the case, and (3) overruling the motion to quash.
    III. STANDARD OF REVIEW
    [1] When a jurisdictional question does not involve a factual
    dispute, determination of a jurisdictional issue is a matter of
    law which requires an appellate court to reach a conclusion
    independent from the trial court’s; however, when a determi-
    nation rests on factual findings, a trial court’s decision on the
    issue will be upheld unless the factual findings concerning
    jurisdiction are clearly incorrect.6 Other standards of review are
    articulated in our analysis of the issues below.
    IV. ANALYSIS
    1. Appellate Jurisdiction
    [2] Before reaching the legal issues presented for review,
    it is the duty of an appellate court to determine whether
    it has jurisdiction over the matter before it.7 The threshold
    4
    Jacobs Engr. Group v. ConAgra Foods, 
    301 Neb. 38
    , 
    917 N.W.2d 435
        (2018).
    5
    See Neb. Rev. Stat. § 24-1106 (Cum. Supp. 2018).
    6
    Jacobs Engr. Group, supra note 4.
    7
    Webb v. Nebraska Dept. of Health & Human Servs., 
    301 Neb. 810
    , 
    920 N.W.2d 268
    (2018).
    -8-
    Nebraska Supreme Court Advance Sheets
    305 Nebraska Reports
    WESTERN ETHANOL CO. v. MIDWEST RENEWABLE ENERGY
    Cite as 
    305 Neb. 1
    issue is whether we have appellate jurisdiction over Midwest
    Renewable’s appeal.
    [3] In Nebraska, for an appellate court to acquire jurisdic-
    tion of an appeal, the party must be appealing from a final
    order or a judgment.8 Here, Western Ethanol transcribed the
    California judgment and allegedly assigned the judgment to
    Vind, who filed a praecipe for writ of execution. Midwest
    Renewable filed a motion to quash the execution which was
    denied by the district court. Midwest Renewable then timely
    filed a motion to alter or amend, which was denied by the
    district court. Midwest Renewable then timely appealed from
    the district court’s order denying the motion to alter or amend.
    The existence of appellate jurisdiction in this case therefore
    depends on whether Midwest Renewable has appealed from a
    final order.
    A number of courts have held that an order refusing to quash
    an execution is an appealable order.9 Nebraska appellate courts
    have previously exercised jurisdiction over appeals from orders
    overruling a motion to quash execution.10
    [4,5] The three types of final orders that an appellate court
    may review are (1) an order that affects a substantial right
    and that determines the action and prevents a judgment, (2)
    an order that affects a substantial right made during a special
    proceeding, and (3) an order that affects a substantial right
    made on summary application in an action after a judgment is
    rendered.11 A substantial right under § 25-1902 is an essential
    legal right.12 A substantial right is affected if an order affects
    8
    
    Id. 9 In
    re Marriage of DeLotel, 
    73 Cal. App. 3d 21
    , 
    140 Cal. Rptr. 553
    (1977);
    C. E. McCune Co. v. Warndorf, 
    55 Ohio App. 279
    , 
    9 N.E.2d 709
    (1936);
    Farmers Bank of North Henderson v. Stenfeldt, 
    258 Ill. App. 428
    (1930);
    Opening of Parkway, 
    267 Pa. 219
    , 
    110 A. 144
    (1920).
    10
    Chitwood Packing Co. v. Warner, 
    138 Neb. 800
    , 
    295 N.W. 882
    (1941);
    Lincoln Lumber Co. v. Elston, 
    1 Neb. Ct. App. 741
    , 
    511 N.W.2d 162
    (1993).
    11
    See Neb. Rev. Stat. § 25-1902 (Reissue 2016).
    12
    Big John’s Billiards v. State, 
    283 Neb. 496
    , 
    811 N.W.2d 205
    (2012).
    -9-
    Nebraska Supreme Court Advance Sheets
    305 Nebraska Reports
    WESTERN ETHANOL CO. v. MIDWEST RENEWABLE ENERGY
    Cite as 
    305 Neb. 1
    the subject matter of the litigation, such as diminishing a
    claim or defense that was available to an appellant before the
    order from which an appeal is taken.13 Substantial rights under
    § 25-1902 include those legal rights that a party is entitled to
    enforce or defend.14
    In Cattle Nat. Bank & Trust Co. v. Watson,15 we concluded
    that an order overruling objections to execution is classified
    within the third type of final order, a summary application
    in an action after judgment is rendered. In that case, the trial
    court issued orders overruling the debtor’s objections to execu-
    tion and garnishments. We found that the orders affected the
    debtor’s substantial rights, because they eliminated the debtor’s
    objections to the execution and garnishments, and that the exe-
    cution and garnishments authorized the seizure of property or
    money which would otherwise have remained in the debtor’s
    ownership and control. Thus, we concluded that the debtor had
    appealed from final orders and that there was jurisdiction over
    the appeal.
    However, in another case in the context of garnishment
    proceedings under Neb. Rev. Stat. § 25-1011 (Reissue 2016),
    we determined that an order overruling a debtor’s objections
    to garnishments was not a final order, because the order did
    not include a determination that the creditor was entitled to
    the funds.16 The order appealed from did not authorize execu-
    tion of a garnishment, did not affect a substantial right, and
    was not a final, appealable order.17 Therefore, the existence of
    appellate jurisdiction turns on whether the order appealed from
    here authorized seizure of Midwest Renewable’s property and
    affected a substantial right of Midwest Renewable.
    13
    
    Id. 14 Id.
    15
    Cattle Nat. Bank & Trust Co. v. Watson, 
    293 Neb. 943
    , 
    880 N.W.2d 906
         (2016).
    16
    Shawn E. on behalf of Grace E. v. Diane S., 
    300 Neb. 289
    , 
    912 N.W.2d 920
    (2018).
    17
    
    Id. - 10
    -
    Nebraska Supreme Court Advance Sheets
    305 Nebraska Reports
    WESTERN ETHANOL CO. v. MIDWEST RENEWABLE ENERGY
    Cite as 
    305 Neb. 1
    In overruling Midwest Renewable’s motion to quash, the
    district court concluded that the foreign judgment had been
    validly registered in Nebraska and is a lien upon Midwest
    Renewable’s real estate. In addition, the court found that
    the judgment is not dormant and that Vind holds the interest
    in the judgment. The court reaffirmed its ruling in denying
    Midwest Renewable’s motion to alter or amend. Therefore,
    consistent with our decision in Cattle Nat. Bank & Trust Co.,
    the court’s orders declining to quash execution affected a sub-
    stantial right because the execution authorized the seizure of
    Midwest Renewable’s property.18 As a result, we have appellate
    jurisdiction in this matter.
    2. Merits
    Midwest Renewable argues that the judgment has not been
    assigned to Vind and that the district court lacked jurisdic-
    tion over Vind’s attempt to execute on the judgment. Midwest
    Renewable asserts that “[t]here is a substantial question as to
    the ownership of the judgment and the judgment lien herein”19
    and that there is “a conflict in the evidence presented [as to]
    when and if there was a valid assignment made.”20 Midwest
    Renewable contends that without an assignment, Vind is not the
    real party in interest. In response, Vind contends that pursuant
    to Marcuzzo v. Bank of the West,21 Midwest Renewable lacks
    standing to challenge the assignment from Western Ethanol
    to Vind.
    We conclude that Midwest Renewable has standing to
    challenge the assignment, that Vind is the real party in inter-
    est, and that Midwest Renewable’s assignments of error lack
    merit.
    18
    See Cattle Nat. Bank & Trust Co., supra note 15.
    19
    Brief for appellant at 12.
    20
    
    Id. at 14.
    21
    Marcuzzo v. Bank of the West, 
    290 Neb. 809
    , 
    862 N.W.2d 281
    (2015).
    - 11 -
    Nebraska Supreme Court Advance Sheets
    305 Nebraska Reports
    WESTERN ETHANOL CO. v. MIDWEST RENEWABLE ENERGY
    Cite as 
    305 Neb. 1
    (a) Midwest Renewable Has Standing
    Vind argues that Midwest Renewable lacks standing to chal-
    lenge the validity of the assignment of the foreign judgment,
    because Midwest Renewable is not a party to the assignment
    and cannot articulate an injury caused by the assignment.
    Before a party is entitled to invoke a court’s jurisdiction, that
    party must have standing to sue.22 To have standing to sue, a
    party must have some legal or equitable right, title, or interest
    in the subject matter of the controversy.23 Standing requires
    that a party show his or her claim is premised on his or her
    own legal rights as opposed to rights of a third party.24
    [6-8] An assignment is a contract between the assignor
    and the assignee, and is interpreted or construed according to
    the rules of contract construction.25 Nebraska law states that
    only a party (actual or alleged) to a contract can challenge its
    validity.26 Parties can recover as third-party beneficiaries of a
    contract only if it appears that the rights and interest of the
    third parties were contemplated and that provision was being
    made for them.27
    In Marcuzzo, the plaintiffs defaulted on their mortgage loan
    and their home was foreclosed and sold.28 The plaintiffs filed
    suit alleging that the assignment of their mortgage was defec-
    tive because there were “discrepancies and irregularities in the
    paperwork of the assignment.”29 In analyzing the plaintiffs’
    22
    
    Id. 23 See
    id.
    24
    See 
    id.
    25
    Schoonmaker 
    v. Lawrence Brunoli, Inc., 
    265 Conn. 210
    , 
    828 A.2d 64
         (2003); 6 Am. Jur. 2d Assignments § 1 (2018).
    26
    Marcuzzo, supra note 21, citing Spanish Oaks v. Hy-Vee, 
    265 Neb. 133
    ,
    
    655 N.W.2d 390
    (2003).
    27
    
    Id., citing Palmer
    v. Lakeside Wellness Ctr., 
    281 Neb. 780
    , 
    798 N.W.2d 845
    (2011).
    28
    Marcuzzo, supra note 21.
    29
    
    Id. at 818,
    862 N.W.2d at 289.
    - 12 -
    Nebraska Supreme Court Advance Sheets
    305 Nebraska Reports
    WESTERN ETHANOL CO. v. MIDWEST RENEWABLE ENERGY
    Cite as 
    305 Neb. 1
    claims on appeal, we applied the principle followed by a major-
    ity of courts that borrowers do not have standing to challenge
    an assignment of their mortgage, because they are not a party
    to the assignment contract.30 We held that a borrower who is not
    a party to a mortgage assignment or a third-party beneficiary
    of the assignment lacks standing to challenge the assignment.
    We explained that if the assignment were in fact irregular, that
    would be an issue between the assignor and assignee.31
    However, we recognized an exception to this rule. We indi-
    cated that a borrower could have standing to challenge the
    assignment of his or her mortgage where the borrower can
    show actual prejudice by the improper assignment, an injury
    that is directly traceable to the assignment, such as being at
    risk for paying the same debt twice, or by otherwise showing
    that the assignment is invalid, ineffective, or void.32
    [9] We therefore limited the standing rule in Marcuzzo
    based on the type of challenge raised to the assignment.33 The
    plaintiffs had alleged the assignment was ineffective because
    of deficiencies in the assignment paperwork. We explained
    that the plaintiffs had failed to allege an injury directly trace-
    able to the assignment, because even if the plaintiffs’ argument
    were correct that would make the assignment merely voidable
    at the election of a party to the assignment, but the assignment
    would otherwise be effective to pass legal title. If the assign-
    ment is effective to pass legal title, the debtor cannot interpose
    defects or objections which merely render the assignment
    voidable at the election of the assignor or those standing in his
    or her shoes.34 However, a debtor may assert as a defense any
    30
    See 
    id. (citing cases).
    31
    
    Id., citing Livonia
    Properties Holdings, LLC v. 12840-12976 Farmington
    Road Holdings, LLC, 
    399 Fed. Appx. 97
    (6th Cir. 2010).
    32
    
    Id., citing Culhane
    v. Aurora Loan Services of Nebraska, 
    708 F.3d 282
    (1st
    Cir. 2013).
    33
    See Marcuzzo, supra note 21.
    34
    6A C.J.S. Assignments § 133 (2016).
    - 13 -
    Nebraska Supreme Court Advance Sheets
    305 Nebraska Reports
    WESTERN ETHANOL CO. v. MIDWEST RENEWABLE ENERGY
    Cite as 
    305 Neb. 1
    matter which renders the assignment absolutely invalid, inef-
    fective, or void.35
    In the present matter, the assignment does not appear in
    the record. Midwest Renewable has made various assertions
    regarding the assignment and generally argues that no valid
    assignment was made. As we will later illustrate, Midwest
    Renewable has taken conflicting positions with regard to the
    assignment and its effect. However, for purposes of stand-
    ing, Midwest Renewable’s challenge to the assignment here is
    distinct from the challenge at issue in Marcuzzo.36 If Midwest
    Renewable were correct that there was no valid assignment,
    then legal title would not have passed to Vind and Midwest
    Renewable would be directly injured by becoming obligated to
    pay a debt to a party without a legal right to collect the foreign
    judgment. Midwest Renewable has standing to argue the lack
    of a valid assignment to Vind.
    (b) Vind Owns Judgment
    and Judgment Lien
    We must determine whether Vind is the real party in inter-
    est for purposes of enforcing the judgment against Midwest
    Renewable. Whether a party who commences an action has
    standing and is therefore the real party in interest presents
    a jurisdictional issue.37 The stage of the litigation in which
    a party claims that its opponent lacks standing affects how
    a court should dispose of the claim.38 If a motion challeng-
    ing standing is made at the pleadings stage, it is considered
    a “facial challenge” and a court will review the pleadings to
    determine whether there are sufficient allegations to establish
    the plaintiff’s standing.39 But if the challenge to standing, and
    35
    
    Id. 36 See
    Marcuzzo, supra note 21.
    37
    Jacobs Engr. Group, supra note 4.
    38
    
    Id. 39 See
    id.
    - 14 
    -
    Nebraska Supreme Court Advance Sheets
    305 Nebraska Reports
    WESTERN ETHANOL CO. v. MIDWEST RENEWABLE ENERGY
    Cite as 
    305 Neb. 1
    thus the court’s subject matter jurisdiction, is raised after the
    pleadings stage and the court holds an evidentiary hearing
    and reviews evidence outside the pleadings, it is considered a
    “factual challenge” and the party opposing the challenge must
    offer evidence to support its burden of establishing subject
    matter jurisdiction.40
    Where the trial court’s decision on a question of subject
    matter jurisdiction is based on a factual challenge, the court’s
    factual findings are reviewed under the clearly erroneous stan-
    dard.41 But aside from any factual findings, the trial court’s rul-
    ing on subject matter jurisdiction is reviewed de novo, because
    it presents a question of law.42
    Here, the district court received evidence on the issue of
    Vind’s standing to execute the California judgment. We review
    the court’s factual findings on this jurisdictional issue for
    clear error, and we review de novo the ultimate question of
    Vind’s standing.
    [10] Vind claims to be the assignee of a judgment against
    Midwest Renewable. An assignment is a transfer vesting in
    the assignee all of the assignor’s rights in the property which
    is the subject of the assignment.43 The assignee of a chose in
    action acquires no greater rights than those of the assignor,
    and takes it subject to all the defenses existent at the time.44
    A judgment, as a chose in action, is assignable.45 A judgment
    may be assigned to someone who was not a party to the ini-
    tial action, and the assignee receives the right to enforce such
    a judgment.46 A judgment creditor may assign his rights in a
    40
    See 
    id. 41 See
    id.
    42
    See 
    id.
    43
    Midwest 
    Renewable Energy, supra note 1.
    44
    
    Id. 45 Id.
    See 46 Am. Jur. 2d Judgments § 410 (2017).
    46
    Gilroy v. Lowe, 
    626 P.2d 469
    (Utah 1981).
    - 15 -
    Nebraska Supreme Court Advance Sheets
    305 Nebraska Reports
    WESTERN ETHANOL CO. v. MIDWEST RENEWABLE ENERGY
    Cite as 
    305 Neb. 1
    judgment for attorney fees.47 An assignee of a chose in action
    assigned for the purpose of collection is the real party in inter-
    est and authorized to maintain an action thereon.48
    [11] Nebraska’s real party in interest statute provides that
    “[e]very action shall be prosecuted in the name of the real party
    in interest . . . .”49 Neb. Rev. Stat. § 25-304 (Reissue 2016)
    states in relevant part: “Assignees of choses in action assigned
    for the purpose of collection may sue on any claim assigned in
    writing.” Neb. Rev. Stat. § 25-302 (Reissue 2016) states: “The
    assignee of a thing in action may maintain an action thereon in
    the assignee’s own name and behalf, without the name of the
    assignor.” Recently, in Hawley v. Skradski,50 we held that an
    assignee can establish standing to bring an action in its own
    name, and thus show the court had subject matter jurisdiction,
    if it proves by a preponderance of the evidence the existence
    of a written assignment under § 25-304. Under this rule, Vind
    can establish that he is the real party in interest and has stand-
    ing to execute the judgment if he can prove by a preponderance
    of the evidence the existence of a written assignment of the
    California judgment.
    Here, the bill of exceptions shows that the only exhibits
    received into evidence are a copy of the California judgment
    and copies of unanswered discovery requests and returns of
    service from the quiet title action. The court took judicial
    notice of its case file and the fact that no written assignment
    appeared in the record. The court found that the amended
    acknowledgment of assignment of the foreign judgment was
    sufficient proof of Vind’s interest. However, the acknowledg-
    ment and amended acknowledgment of assignment appear in
    the transcript and not in the bill of exceptions.
    47
    See Boarman v. Boarman, 
    210 W. Va. 155
    , 
    556 S.E.2d 800
    (2001).
    48
    See Archer v. Musick, 
    147 Neb. 1018
    , 
    25 N.W.2d 908
    (1947).
    49
    Neb. Rev. Stat. § 25-301 (Reissue 2016).
    50
    Hawley v. Skradski, 
    304 Neb. 488
    , 
    935 N.W.2d 212
    (2019).
    - 16 -
    Nebraska Supreme Court Advance Sheets
    305 Nebraska Reports
    WESTERN ETHANOL CO. v. MIDWEST RENEWABLE ENERGY
    Cite as 
    305 Neb. 1
    [12,13] An appellate record typically contains the bill of
    exceptions, used to present factual evidence to an appellate
    court, and the transcript, used to present pleadings and orders
    of the case to the appellate court.51 A bill of exceptions is the
    only vehicle for bringing evidence before an appellate court;
    evidence which is not made a part of the bill of exceptions may
    not be considered.52
    The only evidence recited in the court’s decision is the
    amended acknowledgment of assignment, which states that all
    interest, right, and title to the California judgment has been
    assigned to Vind. Because the acknowledgments of assignment
    do not appear in the bill of exceptions, we cannot consider
    them as evidence. None of the evidence contained in the bill
    of exceptions shows the existence of a written assignment.
    However, the fact that the bill of exceptions lacks evidence
    to support the court’s decision is not dispositive in this case.
    Under the circumstances presented here, we must take judicial
    notice of facts admitted by Midwest Renewable in the prior
    appeal which obviate the need for evidence of a written assign-
    ment to Vind.
    [14,15] Neb. Rev. Stat. § 27-201(2)(b) (Reissue 2016) pro-
    vides that judicial notice may be taken of any fact not subject
    to reasonable dispute, when such fact is capable of accurate and
    ready determination by resort to sources whose accuracy can-
    not reasonably be questioned. The Midwest Renewable Energy
    opinion53 is a source of which the accuracy cannot reasonably
    be questioned.54 In interwoven and interdependent cases, we
    may examine our own records and take judicial notice of the
    proceedings and judgment in a former action involving one of
    51
    In re Estate of Radford, 
    297 Neb. 748
    , 
    901 N.W.2d 261
    (2017).
    52
    
    Id. 53 See
    Midwest Renewable Energy, supra note 1.
    54
    See, e.g., Nebraska Liq. Distrib. v. Nebraska Liq. Cont. Comm., 
    269 Neb. 401
    , 
    693 N.W.2d 539
    (2005).
    - 17 -
    Nebraska Supreme Court Advance Sheets
    305 Nebraska Reports
    WESTERN ETHANOL CO. v. MIDWEST RENEWABLE ENERGY
    Cite as 
    305 Neb. 1
    the parties.55 We have further held that we may take judicial
    notice of a document, including briefs filed in an appeal, in a
    separate but related action concerning the same subject matter
    in the same court.56
    In our opinion in the previous appeal, we referred to the fact
    that both Western Ethanol’s articles of dissolution in Nevada
    and its certificate of cancellation in California attested that it
    had distributed all of its assets to its members.57 In that appeal,
    the statement of facts section of Midwest Renewable’s brief
    of appellant referred to the affidavit filed by Vind which indi-
    cated that, as the result of Western Ethanol’s dissolution, Vind
    received the asset of the judgment against Midwest Renewable.
    Midwest Renewable’s brief stated Vind’s affidavit established
    that the judgment against Midwest Renewable had been trans-
    ferred to Vind and that he was then the interested party.
    Western Ethanol’s brief of appellee stated in its statement of
    facts that Vind had received the judgment against Midwest
    Renewable. In its reply brief, Midwest Renewable accepted
    the statement of facts and explained that Vind had received
    the judgment prior to December 31, 2013, the date of Western
    Ethanol’s dissolution.
    [16] A judicial admission is a formal act done in the
    course of judicial proceedings which is a substitute for evi-
    dence, thereby waiving or dispensing with the production of
    evidence by conceding for the purpose of litigation that the
    proposition of fact alleged by the opponent is true.58 Similar
    to a stipulation, judicial admissions must be unequivocal,
    deliberate, and clear, and not the product of mistake or
    inadvertence.59 Additionally, an admission does not extend
    55
    Pennfield Oil Co. v. Winstrom, 
    276 Neb. 123
    , 
    752 N.W.2d 588
    (2008).
    56
    
    Id. 57 See
    Midwest Renewable Energy, supra note 1.
    58
    In re Estate of Radford, supra note 51.
    59
    
    Id. - 18
    -
    Nebraska Supreme Court Advance Sheets
    305 Nebraska Reports
    WESTERN ETHANOL CO. v. MIDWEST RENEWABLE ENERGY
    Cite as 
    305 Neb. 1
    beyond the intendment of the admission as clearly disclosed
    by its context.60
    [17] Here, to support its argument that Western Ethanol’s
    claim should be quieted, Midwest Renewable clearly, delib-
    erately, and unequivocally declared that the judgment was
    validly assigned to Vind. Midwest Renewable asserted that the
    judgment was assigned solely to Vind and prior to Western
    Ethanol’s dissolution. These admissions obviate the need for
    evidence of a written assignment in the present matter and
    defeat each of the arguments raised by Midwest Renewable in
    its challenge to Vind’s standing. While parties cannot confer
    subject matter jurisdiction upon a judicial tribunal by either
    acquiescence or consent, nor may subject matter jurisdiction be
    created by waiver, estoppel, consent, or conduct of the parties,
    such does not prevent a party from conclusively admitting the
    truth of an underlying fact required to establish subject matter
    jurisdiction by judicial admission.61
    For the sake of completeness, to the extent that Midwest
    Renewable may contend that its admissions lack clarity or were
    made unintentionally, Midwest Renewable is estopped from
    asserting a position that is inconsistent from the position that it
    previously advocated before this court.
    [18,19] The doctrine of judicial estoppel protects the integ-
    rity of the judicial process by preventing a party from taking
    a position inconsistent with one successfully and unequivo-
    cally asserted by the same party in a prior proceeding.62
    Fundamentally, the intent behind the doctrine of judicial estop-
    pel is to prevent parties from gaining an advantage by taking
    one position in a proceeding and then switching to a different
    position when convenient in a later proceeding.63 This doc-
    trine, however, is to be applied with caution so as to avoid
    60
    
    Id. 61 Jacobs
    Engr. Group, supra note 4.
    62
    Hike v. State, 
    297 Neb. 212
    , 
    899 N.W.2d 614
    (2017).
    63
    
    Id. - 19
    -
    Nebraska Supreme Court Advance Sheets
    305 Nebraska Reports
    WESTERN ETHANOL CO. v. MIDWEST RENEWABLE ENERGY
    Cite as 
    305 Neb. 1
    impinging on the truth-seeking function of the court, because
    the doctrine precludes a contradictory position without exam-
    ining the truth of either statement.64 We have held that bad
    faith or an actual intent to mislead on the part of the party
    asserting inconsistent positions must be demonstrated before
    the judicial estoppel doctrine may be invoked.65
    [20,21] Whether judicial estoppel is applicable turns on
    whether the court has accepted inconsistent positions from the
    plaintiff.66 Judicial acceptance does not require that a party
    prevail on the merits, but only that the first court adopted
    the position urged by the party, either as a preliminary mat-
    ter or as part of a final disposition.67 In the prior appeal, we
    accepted Midwest Renewable’s position to the extent that we
    were persuaded that Vind qualified as an indispensable party.
    We did not adopt Midwest Renewable’s position that Vind is
    the real party in interest; we ordered the district court to make
    that determination. But we credited Midwest Renewable’s
    position on the factual issue of Vind’s ownership interest,
    which was supported by Vind’s affidavit. We found that there
    was a question in the case as to the owner of the judgment
    and judgment lien and that the district court “could not make
    a determination as to the owner of the judgment and the
    judgment lien without affecting Vind’s ownership rights.”68
    Midwest Renewable was advantaged by having this court
    accept its factual position that the judgment had been assigned
    to Vind, because we vacated a judgment that had been entered
    against Midwest Renewable and remanded the cause for fur-
    ther proceedings, which gave Midwest Renewable another
    64
    Cleaver-Brooks, Inc. v. Twin City Fire Ins. Co., 
    291 Neb. 278
    , 
    865 N.W.2d 105
    (2015).
    65
    
    Id. 66 Jardine
    v. McVey, 
    276 Neb. 1023
    , 
    759 N.W.2d 690
    (2009).
    67
    
    Id., citing Edwards
    v. Aetna Life Ins. Co., 
    690 F.2d 595
    (6th Cir. 1982).
    68
    Midwest Renewable Energy, supra note 
    1, 296 Neb. at 92
    , 894 N.W.2d at
    237.
    - 20 -
    Nebraska Supreme Court Advance Sheets
    305 Nebraska Reports
    WESTERN ETHANOL CO. v. MIDWEST RENEWABLE ENERGY
    Cite as 
    305 Neb. 1
    opportunity to quiet Western Ethanol’s claim. As such, the
    requirement of judicial acceptance of a prior inconsistent
    position for purposes of the doctrine of judicial estoppel is
    met here.
    We find no evidence that Midwest Renewable acted in bad
    faith. Midwest Renewable made efforts to obtain a copy of the
    assignment and stated at oral argument before this court that
    it did not know for sure who owned the judgment. However,
    as demonstrated above, Midwest Renewable’s position in the
    quiet title appeal went further than that by affirmatively declar-
    ing that Vind owned the judgment.
    Midwest Renewable’s self-contradictory approach is harmful
    to the judicial process. In its two appeals, Midwest Renewable
    has requested relief from this court while taking opposite sides
    of the same factual issue. To permit Midwest Renewable to
    argue the lack of evidence of a written assignment in this
    case would be to allow Midwest Renewable to withdraw its
    factual representations in the previous case, despite the fact
    that we granted Midwest Renewable relief based on its prior
    representations. For purposes of analyzing intent, we note that
    Midwest Renewable’s previous position is more plausible than
    its new position, because the previous position was consistent
    with Western Ethanol’s position and was supported by Vind’s
    affidavit, and there is no information in the record to corrobo-
    rate the new position. These considerations, especially when
    considered in light of the stark contrast between Midwest
    Renewable’s factual positions in the two cases involving the
    same judgment, lead us to conclude that there has been suf-
    ficient demonstration of an intent to mislead in order to delay
    execution on the judgment. Judicial estoppel is appropriate in
    this instance.
    Midwest Renewable’s judicial admissions establish that Vind
    owns the judgment and judgment lien and is the real party in
    interest. Midwest Renewable is estopped from asserting a con-
    trary position. This assignment of error is without merit.
    - 21 -
    Nebraska Supreme Court Advance Sheets
    305 Nebraska Reports
    WESTERN ETHANOL CO. v. MIDWEST RENEWABLE ENERGY
    Cite as 
    305 Neb. 1
    (c) Vind Proper Party
    Midwest Renewable’s final assignment of error is that Vind
    should not have been permitted to enforce the judgment in his
    own name, because he did not file a formal pleading or motion
    to enter the case. Midwest Renewable argues that the court
    never approved either a formal complaint for intervention or a
    motion for substitution of parties.
    We clarify that this argument comes to us in a different
    context than the indispensable party issue we confronted in the
    quiet title appeal. In that appeal, the district court found that
    Vind held the sole interest in the judgment, yet Vind had never
    appeared in the case. All persons whose rights will be directly
    affected by a decree in equity must be joined as parties in order
    that complete justice may be done and that there may be a
    final determination of the rights of all parties interested in the
    subject matter of the controversy.69 We held that the court erred
    in not making Vind a party to the action sua sponte, vacated
    the court’s judgment, and remanded the cause with direction to
    make Vind a party.
    [22] Here, Midwest Renewable raises a procedural objection
    as to how Vind became a party in the case rather than a juris-
    dictional objection about Vind’s lack of presence in the case.
    We review this assignment of error for abuse of discretion.70 As
    noted, Vind filed the praecipe for writ of execution in his own
    name as assignee and personally appeared without objection
    at the hearing on the motion to quash. The record shows that
    the court accepted Vind’s appearance in the case. The court’s
    decision is supported by legal authority. An action to enforce
    a judgment may be prosecuted in the name of the assignee.71
    As discussed above, § 25-302 states: “The assignee of a thing
    69
    
    Id. See Neb.
    Rev. Stat. § 25-323 (Reissue 2016).
    70
    See, Eicher v. Mid America Fin. Invest. Corp., 
    270 Neb. 370
    , 
    702 N.W.2d 792
    (2005); John P. Lenich, Nebraska Civil Procedure § 7:6 (2019).
    71
    Exchange Elevator Company v. Marshall, 
    147 Neb. 48
    , 
    22 N.W.2d 403
         (1946).
    - 22 -
    Nebraska Supreme Court Advance Sheets
    305 Nebraska Reports
    WESTERN ETHANOL CO. v. MIDWEST RENEWABLE ENERGY
    Cite as 
    305 Neb. 1
    in action may maintain an action thereon in the assignee’s
    own name and behalf, without the name of the assignor.” Neb.
    Rev. Stat. § 25-322 (Reissue 2016) provides that in the case
    of a “transfer of interest, the action may be continued in the
    name of the original party or the court may allow the person
    to whom the transfer is made to be substituted in the action.”
    Neb. Rev. Stat. § 25-705(5) (Reissue 2016) provides that
    “[p]arties may be dropped or added by order of the court on
    motion of any party or of its own initiative at any stage of the
    action . . . .” Having determined that Vind is the real party in
    interest and has the right to execute the judgment, and in con-
    sideration of the court’s authority to add a party to a proceed-
    ing at any time, we find no abuse of discretion by the court in
    accepting Vind’s appearance in this case. Midwest Renewable
    never moved for a substitution of parties and did not raise an
    objection to Vind’s appearance until it filed its motion to alter
    or amend. Failure to make a timely objection waives the right
    to assert prejudicial error on appeal.72 This assignment of error
    is without merit. The court did not err in overruling the motion
    to quash.
    V. CONCLUSION
    For the foregoing reasons, the judgment of the district court
    is affirmed.
    Affirmed.
    72
    State v. Swindle, 
    300 Neb. 734
    , 
    915 N.W.2d 795
    (2018).
    

Document Info

Docket Number: S-18-1192

Citation Numbers: 305 Neb. 1

Filed Date: 2/14/2020

Precedential Status: Precedential

Modified Date: 3/20/2020

Authorities (21)

William Edwards v. Aetna Life Insurance Company , 690 F.2d 595 ( 1982 )

In Re Marriage of DeLotel , 140 Cal. Rptr. 553 ( 1977 )

Webb v. Nebraska Dept. of Health & Human Servs. , 301 Neb. 810 ( 2018 )

Jacobs Engr. Group v. ConAgra Foods , 301 Neb. 38 ( 2018 )

State v. Swindle , 300 Neb. 734 ( 2018 )

Jardine v. McVey , 276 Neb. 1023 ( 2009 )

Pennfield Oil Co. v. Winstrom , 276 Neb. 123 ( 2008 )

Nebraska Liq. Distrib. v. NEB. LIQ. CONTROL , 269 Neb. 401 ( 2005 )

Spanish Oaks, Inc. v. Hy-Vee, Inc. , 265 Neb. 133 ( 2003 )

Eicher v. Mid America Financial Investment Corp. , 270 Neb. 370 ( 2005 )

Cattle Nat. Bank & Trust Co. v. Watson , 293 Neb. 943 ( 2016 )

Shawn E. on behalf of Grace E. v. Diane S. , 300 Neb. 289 ( 2018 )

Western Ethanol Co. v. Midwest Renewable Energy , 305 Neb. 1 ( 2020 )

Hawley v. Skradski , 304 Neb. 488 ( 2019 )

Lincoln Lumber Co. v. Elston , 1 Neb. Ct. App. 741 ( 1993 )

Midwest Renewable Energy v. American Engr. Testing , 296 Neb. 73 ( 2017 )

C.E. McCune Co. v. Warndorf , 55 Ohio App. 279 ( 1936 )

Hike v. State , 297 Neb. 212 ( 2017 )

Gilroy v. Lowe , 626 P.2d 469 ( 1981 )

In re Estate of Radford , 297 Neb. 748 ( 2017 )

View All Authorities »