Cardno Wrg v. Rbc Real Estate Finance C/W 60599 ( 2015 )


Menu:
  •                         the deed. The construction project was later halted and Las Vegas Paving
    and WRG recorded mechanics' liens.
    Las Vegas Paving, WRG, and RBC each attempted to foreclose
    on lot G-2. The district court found that RBC's deed of trust held priority
    over appellants' mechanics' liens. Las Vegas Paving and WRG separately
    appealed and we consolidated the appeals. See NRAP 3(b)(2).
    Moot ness
    After Las Vegas Paving and WRG appealed, the City of
    Henderson mailed a bill for tax assessments due on lot G-2 to the property
    owner.' RBC foreclosed on lot G-2 following the district court's order and
    the City initiated foreclosure proceedings shortly thereafter.
    At the tax foreclosure sale, lot G-2 was sold to Douglas
    Gerrard, RBC's attorney. He paid the amount of the delinquent payment
    plus interest, penalties, and costs. The City then sent a notice of the sale
    to RBC, as it had become the owner just before the sale, informing RBC
    that it had 120 days to redeem the property. Approximately 62 days after
    the sale, Gerrard assigned his rights and interest in the certificate of sale
    to RBC. Five months later, the City issued an absolute deed, free of all
    encumbrances, to RBC.
    RBC filed a motion in this court to dismiss these appeals as
    moot. RBC argued that the tax sale wiped out any interest Las Vegas
    Paving and WRG may have had in lot G-2. This court ordered that it
    ILLV-1, a subsidiary of the project's master developer, originally
    owned both lot G-1 and lot G-2. LLV-1 later sold lot G-2 to CRV Lake Las
    Vegas G-Lots, a California limited partnership.
    SUPREME COURT
    OF
    NEVADA
    2
    (0) 1947A    ...girt.
    would defer ruling on the motion until after full briefing and asked the
    parties to address mootness in their briefs.
    RBC argues that appellants' mechanics' liens were
    extinguished by the tax sale following RBC's foreclosure and, therefore,
    that appellants' claims are moot. Under the mootness doctrine, this court
    will only decide cases if a live controversy is present or they "involve[ ] a
    matter of widespread importance that is capable of repetition, yet evading
    review." Personhood Nevada v. Bristol, 
    126 Nev. 599
    , 602, 
    245 P.3d 572
    ,
    574 (2010).
    However, RBC's position depends upon the validity of the deed
    obtained from the City as a result of the tax sale. NRS 271.595(3) requires
    the treasurer to provide a deed to the purchaser at the tax sale, but only
    after notice of a demand for the deed has been given by the holder of the
    certificate of the tax sale to the owners of the property. Further, if
    redemption is not made within 60 days after the date of service of the
    notice required in NRS 271.595(3), the deed may issue. NRS
    271.594(4). The merits of this case concern the proper ownership of the
    property based upon the priority of the parties underlying liens. If
    appellant's liens have priority over RBC's mortgage, they would have been
    entitled to notices under NRS 271.595(3) & (4). Therefore, the tax sale
    does not moot this appeal and we deny the motion to dismiss."
    Lien priority
    On cross-summary judgment motions, the district court ruled
    that RBC's deed was senior to Las Vegas Paving's and WRG's liens on
    three grounds: (1) Las Vegas Paving only commenced work on lot G-1 not
    G-2; (2) the grading work on lot G-2 was not visible work as a matter of
    SUPREME COURT
    OF
    NEVADA
    3
    (0) 1947A    e).
    law; and (3) equitable subrogation applies, changing RBC's younger
    interest into a senior one.
    We will affirm a grant of summary judgment when there are
    no genuine issues of material fact and a "party is entitled to judgment as a
    matter of law."   Wood v. Safeway, Inc., 
    121 Nev. 724
    , 731, 
    121 P.3d 1026
    ,
    1031 (2005). We conclude that the district court erred because the timing
    and scope of a work of improvement are genuine issues of material fact in
    this case. Summary judgment was not appropriate.
    Commencement of the work of improvement
    A mechanics' lien achieves priority over a deed of trust "after
    the commencement of construction of a work of improvement." NRS
    108.225(1)(a). "The scope of an 'improvement' is a question of fact for the
    trial court to determine and this court will not set aside the district court's
    factual findings unless those findings are clearly erroneous."           L Cox
    Constr. Co., LLC v. CH2 Investments, LLC,        129 Nev., Adv. Op. 14, 
    296 P.3d 1202
    , 1204 (2013) (citations omitted). "[T]he fact-finder must define
    the work of improvement before it can determine when that work of
    improvement visibly commenced."        Byrd Underground, LLC v. Angaur,
    LLC, 130 Nev., Adv. Op. 62, 
    332 P.3d 273
    , 279 (2014).
    In some cases the evidence at the summary judgment stage
    might show that there is no genuine issue of fact regarding the
    commencement of a work of improvement or the scope of such work. For
    example, we have recognized that "contracts and permits may assist in
    determining the scope of the work of improvement's 'structure or scheme .
    . as a whole.' If the contract expressly or impliedly excludes certain
    work, then that work might not be a part of the 'work of improvement."
    
    Id.
     (quoting NRS 108.22188). And, in I. Cox Construction, 129 Nev., Adv.
    SUPREME COURT
    OF
    NEVADA
    4
    (0) 1947A    e
    Op. 14, 296 P.3d at 1203, this court considered whether a district court
    erred in determining that the subsequent soundproofing of a shooting
    range was not part of the same work of improvement as construction of
    the range. We held that the district court's decision was not erroneous
    where it considered evidence of permits, the parties' contemplated scope of
    the project, and the purpose of the soundproofing project. Id., 296 P.3d at
    1205.
    In this case, however, the district court appears to have simply
    based its decision on the fact that lot G-1 and lot G-2 are different legal
    parcels. It thusly concluded that any work on lot G-1 was not relevant to
    whether work was performed on lot G-2. To the contrary, we have said
    that the scope of an improvement is a question of fact. Byrd Underground,
    130 Nev., Adv. Op. 62, 332 P.3d at 279. The district court did not make
    findings regarding the• construction permits, the parties' contemplated
    scope of the project, or the purpose of the project.   See I. Cox Constr., 129
    Nev., Adv. Op. 14, 296 P.3d at 1205. Furthermore, the record shows that
    Las Vegas Paving's contract with the general partner of the lot's owner
    was combined with a contract with the master developer. The master
    developer's subsidiary had owned both parcels before selling them to
    separate limited partnerships It is possible that the parties to the
    construction contracts might have intended the scope of the project to
    cover both parcels.
    In the summary judgment briefing, Las Vegas Paving treated
    lot G-1 and lot G-2 as a single work of improvement. RBC countered that
    Las Vegas Paving did not provide sufficient evidence showing that the
    improvement contract was for both lots. Because the scope of the project
    was a material question of fact, /. Cox Constr. Co., 129 Nev., Adv. Op. 14,
    SUPREME COURT
    OF
    NEVADA
    5
    (0) 1947A    e
    296 P.3d at 1204, that was genuinely at issue, the district court erred by
    granting summary judgment.
    Visibility
    The district court found that Las Vegas Paving performed
    grading work on lot G-2 but concluded that the grading work was not
    visible as a matter of law. This was error.
    Construction commences once the work performed "is visible
    from a reasonable inspection of the site." MRS 108.22112(1). We analyzed
    NRS 108.22112 in J.E. Dunn Northwest, Inc. v. Corus Construction
    Venture, LLC, and concluded that, "visibility alone determines priority."
    127 Nev., Adv. Op. 5, 
    249 P.3d 501
    , 506 (2011). Yet we went on to say that
    preparatory work is not "commencement of construction" and that clearing
    and grading were examples of such preparatory work. Id. at 509.
    In Byrd Underground, we clarified that, despite J.E. Dunn's
    statement that clearing and grading were examples of preparatory work,
    this court did not mean to express, as a matter of law, that grading is
    never visible work. 130 Nev., Adv. Op. 62, 332 P.3d at 278. Accordingly,
    grading work may constitute visible "commencement of construction"
    under NRS 108.22112 as long as it is visible from a reasonable inspection
    of the site. Id. at 278-80. Byrd Underground emphasized that whether
    work is visible from a reasonable inspection is an issue for the trier of fact.
    Id. at 279-80.
    Here, the district court erroneously relied upon the dicta in
    J.E. Dunn, 127 Nev., Adv. Op. 5, 249 P.3d at 509, to conclude as a matter
    of law that grading work "does not constitute commencement of
    construction." We hold that whether work is visible is an issue of fact
    that, when at issue, should be left for the ultimate trier of fact.
    SUPREME COURT
    OF
    NEVADA
    6
    (0) 1947A
    Equitable subrogation
    The district court found that RBC's loan paid the remaining
    balance of the property owner's promissory note to the former property
    owner. It therefore applied equitable subrogation as a separate basis to
    prioritize RBC's deed over appellants' liens. Appellants argue that the
    district court erred by applying the doctrine of equitable subrogation to
    their mechanics' liens. RBC responds that the district court's application
    of equitable subrogation is valid as an equitable assignment of the lien.
    "Equitable subrogation permits 'a person who pays off an
    encumbrance to assume the same priority position as the holder of the
    previous encumbrance." Houston v. Bank of Am. Fed. Savings Bank,            
    119 Nev. 485
    , 488, 
    78 P.3d 71
    , 73 (2003) (quoting Mort v. U.S., 
    86 F.3d 890
    ,
    893 (9th Cir. 1996)). In other words, the doctrine "enables 'a later-filed
    lienholder to leap-frog over an intervening lien[holder]." Am. Sterling
    Bank v. Johnny Mgmt. LV, Inc.,      
    126 Nev. 423
    , 429, 
    245 P.3d 535
    , 539
    (2010) (quoting Hicks v. Londre, 
    125 P.3d 452
    , 456 (Cob. 2005)). "The
    practical effect of equitable subrogation is a revival of the discharged lien
    and underlying obligation and assignment to the payor or subrogee,
    permitting the subrogee to enforce the seniority of the satisfied lien
    against junior lienors." Am. Sterling, 126 Nev. at 429, 245 P.3d at 539.
    Under Nevada law, "mechanics' liens tha[ve] no place in equity
    jurisprudence." In re Fontainebleau Las Vegas Holdings, LLC, 128 Nev.,
    Adv. Op. 53, 
    289 P.3d 1199
    , 1212 (2012) (quoting Lamb v. Lucky Boys M.
    Co., 
    37 Nev. 9
    , 16, 
    138 P. 902
    , 904 (1914)). In Fontainebleau, we
    concluded "that the plain and unambiguous language of NRS 108.225
    precludes application of the doctrine of equitable subrogation, as it
    unequivocally places mechanics' lien claimants in an unassailable priority
    SUPREME COURT
    OF
    NEVADA
    7
    (0) 1947A
    position." Id. at 1212. We reasoned that "equitable principles will not
    justify a court's disregard of statutory requirements."               Id. (quoting
    Pellegrini v. State, 
    117 Nev. 860
    , 878, 
    34 P.3d 519
    , 531 (2001)).
    In this case, the district court applied equitable subrogation to
    give RBC's lien priority over appellants' mechanics' liens. Yet the
    unambiguous language of MRS 108.225 precludes application of equitable
    subrogation or any other equitable rule that would upset the Legislature's
    decision to give priority to mechanics' liens.           See 
    id.
       Accordingly, the
    district court erred in applying the doctrine of equitable subrogation. The
    same reasoning applies to RBC's equitable assignment argument, which
    we also reject. Accordingly, we
    ORDER the judgment of the district court REVERSED AND
    REMAND this matter to the district court for proceedings consistent with
    this order.
    Hardesty
    LAC4-4 crest)   C.J.
    c:241)t
    --        C‘jitSvirisr7
    Parraguirre
    'Cherry
    ,J.                 CiLte
    Saitta
    Gibborfg
    ".•.13.1
    Pickering
    Pitt aA, .      J.
    SUPREME COURT
    OF
    NEVADA
    8
    (0) 1947A
    cc: Hon. James M. Bixler, District Judge
    Robert F Saint-Aubin, Settlement Judge
    Howard & Howard
    Peel Brimley LLP/Henderson
    Peel Brimley LLP/Seattle
    Gerrard Cox & Larsen
    Eighth District Court Clerk
    SUPREME COURT
    OF
    NEVADA
    9
    (0) 1947A    e).)