Park West Companies, Inc. v. Amazon Const. Corp. ( 2013 )


Menu:
  •                 settlement process negotiated by the parties, and the district court held
    that the auditor's findings were binding on the parties. Subsequently,
    Amazon moved for summary judgment based on the binding nature of
    those findings, which the district court granted. Park West now appeals.
    The parties are familiar with the facts, so we do not recount them further
    except as pertinent to our disposition.
    This court reviews "a district court order granting summary
    judgment de novo. Summary judgment is appropriate when there is no
    genuine issue of material fact and the moving party is entitled to
    judgment as a matter of law. . . . [T]his court views the record in the light
    most favorable to the nonmoving party."       Sparks v. Alpha Tau Omega
    Fraternity, Inc., 127 Nev. „ 
    255 P.3d 238
    , 242-43 (2011) (citations
    and internal quotations omitted).
    We conclude that summary judgment is not appropriate in
    this matter for two reasons. First, the district court erred when it
    determined that the auditor's findings were binding on the parties. The
    district court reasoned that the parties' consent to be bound by the
    auditor's findings was analogous to an agreement to submit to binding
    arbitration; thus, it found that the auditor's findings were automatically
    binding on Park West and Amazon. However, the settlement process
    negotiated by the parties did not include an express agreement to
    arbitrate and did not designate the auditor as an arbitrator.       See NRS
    38.209 (defining "[a]rbitrator" as "an individual appointed to render an
    award, alone or with others, in a controversy that is subject to an
    agreement to arbitrate"). Therefore, we conclude that the parties did not
    agree to be bound by the auditor's findings as if the findings were those of
    an arbitrator.
    SUPREME COURT
    OF
    NEVADA
    2
    (0) 1947A
    .M4t::;01114114WW&15",                      OttS   MEMESIIIMEMICUM
    Second, genuine issues of material fact remain as to the
    proper scope of the audit, including the proper accounting method to be
    used and whether all material terms of an enforceable settlement
    agreement were reached. Although Amazon argues that the parties
    stipulated to a valid settlement process, this court has held that "[t]o be
    valid, a stipulation requires mutual assent to its terms and either a signed
    writing by the party against whom the stipulation is offered or an entry
    into the court minutes in the form of an order."     Lehrer McGovern Bovis,
    Inc. v. Bullock Insulation, Inc., 
    124 Nev. 1102
    , 1118, 
    197 P.3d 1032
    , 1042
    (2008). Furthermore, in Nevada, "a court cannot compel compliance [with
    a settlement agreement] when [the] material terms remain uncertain."
    May v. Anderson, 
    121 Nev. 668
    , 672, 
    119 P.3d 1254
    , 1257 (2005).
    The record reflects that at a hearing before the district court,
    Park West and Amazon did recite a settlement process, but that process
    was never reduced to a signed writing or order. Further, although the
    parties agreed to the appointment of an independent auditor, the
    negotiated settlement process included only a general accounting
    structure for the allocation of job costs, overhead costs, and profits. It did
    not indicate whether particular expense items, such as payroll costs, fell
    under the category of job costs or overhead costs, nor did it indicate
    whether the parties intended for the auditor to use a particular accounting
    method. Therefore, summary judgment is not appropriate because factual
    issues remain as to the scope of the construction audit, including the
    accounting methodology the auditor was to utilize, and whether, as a
    result of the uncertainty of the scope of the audit, there was mutual assent
    to all material terms of the settlement process.
    SUPREME COURT
    OF
    NEVADA
    3
    (0) I947A
    Accordingly, we reverse the district court's summary judgment
    and remand this matter to the district court for it to determine whether an
    enforceable settlement agreement was reached, and, if so, to determine
    the proper scope of the construction audit, including the accounting
    methodology to be utilized by the auditor.
    It is so ORDERED.
    Gibbons
    Hardesty
    SUPREME COURT
    OF
    NEVADA
    4
    (0) 1947A
    "7"7fAREAMIEMBEINEIIIMENINIENME      IMe:"I'          ''-
    cc: Hon. Mark R. Denton, District Judge
    Robert F. Saint-Aubin, Settlement Judge
    Lionel Sawyer & Collins/Las Vegas
    Pezzillo Lloyd
    Gordon & Rees, LLP
    Eighth District Court Clerk
    SUPREME COURT
    OF
    NEVADA
    5
    (0) 1947A
    

Document Info

Docket Number: 57905

Filed Date: 9/12/2013

Precedential Status: Non-Precedential

Modified Date: 10/30/2014