Desert Valley Contracting, Inc. v. In-Lo Props. ( 2022 )


Menu:
  • IN THE SUPREME COURT OF THE STATE OF NEVADA
    DESERT VALLEY CONTRACTING, INC., No. 83338
    A NEVADA CORPORATION,
    Appellant,
    vs.
    IN-LO PROPERTIES, A NEVADA F L E U
    LIMITED LIABILITY COMPANY; AUG 11 2022
    EUGENE INOSE, AN INDIVIDUAL; AND
    JEFFREY LOUIE, AN INDIVIDUAL,
    Respondents.
    ELIZARH PH A. BROWN |
    OF PUPREME COURT
    EPUTyY CLERK
    ORDER OF AFFIRMANCE
    This is an appeal from a final judgment in a contract dispute.
    Eighth Judicial District Court, Clark County; Joseph Hardy, Jr., Judge.}
    Respondents (collectively, Inose) hired appellant Desert Valley
    Contracting, Inc., to repair and restore a home after it suffered extensive
    water damage.? Their contract required Desert Valley to perform the
    restoration work in a good and workmanlike manner, while Inose agreed to
    immediately forward insurance proceeds to Desert Valley and instruct the
    insurer to make Desert Valley a payee on all insurance drafts for the work.
    Desert Valley performed extensive work on the home but made mistakes
    and decisions that increased costs and resulted in additional damage.
    Meanwhile, Inose requested changes and upgrades that were not in the
    scope of the repair work, believing those costs could be offset. Throughout
    the restoration work, Inose turned over some, -but not all, of the insurance
    1Pursuant to NRAP 34(f)(1), we have determined that oral argument
    is not warranted in this appeal.
    Respondent Eugene Inose is the principal of In-Lo Properties, which
    owns the subject property.
    Supreme GourT
    OF
    Nevapa
    mos 22-2514
    a | s
    proceeds to Desert Valley. Eventually Desert Valley stopped work on the
    home. Inose thereafter worked with Desert Valley's subcontractors directly
    to complete the work. Desert Valley filed the underlying lawsuit alleging
    breach of contract and related claims; Inose responded with similar
    counterclaims. Following a seven-day bench trial, the district court
    dismissed both parties’ claims. The district court found that both parties
    breached the contract and concluded that neither party was entitled to
    damages. In relevant part, the district court concluded that a scrivener’s
    error in the parties’ contract rendered the contract ambiguous, construed
    the ambiguity against Desert Valley, and found that Desert Valley failed to
    establish damages because it was paid for the work it completed.
    On appeal, this court concluded that the district court erred by
    finding the scrivener’s error made the contract ambiguous such that it
    should be construed against Desert Valley, and by concluding that the
    ambiguity barred Desert Valley from seeking damages for its expected
    profits. Nevertheless, because this court could not determine whether the
    error was harmless, we reversed and remanded for further proceedings on
    two issues. First, “the [district] court did not determine who breached first
    or if the breaches were mutual, thereby precluding relief.” Desert Valley
    Contracting, Inc. v. In-Lo Props., No. 79751, 
    2021 WL 818191
     (Nev. Mar. 3,
    2021) (Order of Reversal and Remand). Second,
    because the district court erred in determining the
    profit provision was ambiguous and that Desert
    Valley therefore could not establish damages, the
    district court did not address whether, in light of
    the evidence presented, the contract, once reformed
    to omit the scrivener’s error, entitled Desert Valley
    to its expected profit and overhead in the event of
    termination by Inose.
    
    Id.
    Supreme Court
    OF
    NEVADA 9
    (0) 197A Gh
    On remand, the district court largely incorporated its findings
    of fact from its previous order. It also made three alternative legal
    conclusions, that: (1) both parties materially breached their contract,
    precluding recovery by either side; (2) Desert Valley is barred from
    recovering because it committed the first material breach of the contract by
    stopping work and instructing the subcontractors to also stop working on
    Inose’s project; and (3) that regardless of whether it materially breached the
    contract, Desert Valley failed to demonstrate its damages by a
    preponderance of the evidence. The district court also found that its
    previous order awarding fees and costs to Inose—based on Desert Valley
    not obtaining an award more than Inose’s offer of judgment—remained in
    effect.
    Desert Valley appeals, arguing the district court erred by
    concluding that it materially breached the contract first, or at all. But the
    record supports the district court’s finding that the parties mutually
    breached the contract, and that Desert Valley therefore is not entitled to
    damages for lost profits.2 See Wells Fargo Bank, N.A. v. Radecki, 
    134 Nev. 619
    , 621, 
    426 P.3d 593
    , 596 (2018) (holding that we will not overturn a
    district court’s findings of fact “unless they are clearly erroneous or not
    supported by substantial evidence”); State, Univ. & Cmty. Coll. Sys. v.
    Sutton, 
    120 Nev. 972
    , 983, 
    103 P.3d 8
    , 15 (2004) (“Factual disputes
    regarding breach of contract are questions for [the factfinder] to decide.”);
    Westinghouse Elec. Corp. v. Garrett Corp., 
    601 F.2d 155
    , 158 (4th Cir. 1979)
    (observing that, under general contract law, “in proper circumstances a
    3The record does not contain substantial evidence regarding which
    party breached first, but, because we can affirm on an alternative basis, the
    lack of evidence on this issue is inconsequential.
    Supreme Court
    OF
    NevaDa 3
    (0) 19470 cE
    court may refuse to allow recovery by either party to an agreement because
    of their mutual fault”); see also Restatement (Second) of Contracts § 244
    (2022) (explaining that a party’s responsibility for damages is discharged
    where the injured party would not have performed the contract).
    Specifically, as to Desert Valley’s breach, the contract required that “[i]f any
    requests for additional work to be performed are made during the scope of
    the job, all such requests must be put in writing so that these costs will be
    added to the Scope of Work.” (Emphasis added). Desert Valley’s owner
    confirmed that without written and approved change orders signed by the
    homeowner, Desert Valley would have no obligation to, and would not pay
    the subcontractor for, any change to its scope of work. And both the owner
    and another Desert Valley representative testified that Desert Valley failed
    to obtain Inose’s approval or signature on any change orders throughout the
    course of its work on Inose’s property.
    Additionally, there was evidence that Desert Valley breached
    the contract by failing to perform in a good and workmanlike manner. For
    example, there was testimony——-deemed credible by the district court—that
    Desert Valley’s decision to paint before installing tile resulted in the paint
    being damaged and having to be redone at an additional cost. See Castle v.
    4Desert Valley argues that Inose was aware of the change orders but
    fails to provide relevant authority or cogent argument as to why this would
    excuse it from performing under the terms of the contract, which required
    Inose’s signed approval. See Edwards v. Emperor’s Garden Rest., 
    122 Nev. 317
    , 330 n.38, 
    130 P.3d 1280
    , 1288 n.38 (2006) (holding that we need not
    address arguments not cogently argued or supported by relevant authority).
    Additionally, there was evidence that Inose refused to sign the change
    orders because Desert Valley consistently represented to Inose that it could
    offset the costs of certain changes in scope by removing other items that
    were part of the original scope without affecting the total cost of the project.
    SupREME Court
    OF
    Nevaba
    (0) 147A 120 Nev. 98
    , 103, 
    86 P.3d 1042
    , 1046 (2004) ((W]e will not
    reweigh the credibility of witnesses on appeal; that duty rests within the
    trier of fact’s sound discretion.”). There was also testimony that Desert
    Valley left the home unlocked and failed to supervise the workers, resulting
    in items being stolen from the home and additional water damage from a
    rainstorm. And that Desert Valley then incorporated the cost of repairs for
    this damage and missing items into the cost it sought to collect from Inose.
    Thus, substantial evidence supports the district court’s finding that Desert
    Valley’s contractual breaches precluded it from any award of damages.> We,
    therefore,
    ORDER the judgment of the district court AFFIRMED.®
    Parraguirre ¥
    Biber? ai ~
    Silver Gibbons
    cc: Hon. Joseph Hardy, Jr., District Judge
    William C. Turner, Settlement Judge
    Hurtik Law & Associates
    Holley Driggs/Las Vegas
    Eighth District Court Clerk
    5Based on this conclusion, we need not consider the argument that
    the district court erred in concluding Desert Valley failed to prove its
    damages by a preponderance of the evidence.
    6The Honorable Mark Gibbons, Senior Justice, participated in the
    decision of this matter under a general order of assignment.
    Supreme Court
    OF
    NEvaADA 5
    (O) (947A oh