388 Route 22 Readington Realty v. Twp. of Readington (073322) , 221 N.J. 318 ( 2015 )


Menu:
  •                                                      SYLLABUS
    (This syllabus is not part of the opinion of the Court. It has been prepared by the Office of the Clerk for the
    convenience of the reader. It has been neither reviewed nor approved by the Supreme Court. Please note that, in the
    interest of brevity, portions of any opinion may not have been summarized).
    388 Route 22 Readington Realty Holdings, LLC v. Township of Readington (A-63-13) (073322)
    Argued December 2, 2014 – May 5, 2015
    ALBIN, J., writing for a unanimous Court.
    In this appeal, the Court considers the circumstances under which a municipality may exercise its discretion
    to repurchase unused sewer capacity.
    In December 2007, plaintiff purchased property in Readington Township (Township). The property is
    serviced by a septic tank with a capacity of up to 2000 gallons per day (gpd). The Township rezoned plaintiff’s
    property from the Mixed-Use District to the Business District. Thereafter, plaintiff made plans to redevelop the
    property for use as a restaurant and other retail purposes. However, plaintiff’s septic tank does not have sufficient
    capacity to process the wastewater generated by the uses plaintiff proposes.
    In 1999, the Readington-Lebanon Sewerage Authority (Authority) began to expand its plant capacity to
    allow the treatment of an additional 320,000 gpd of the Township’s wastewater. As a result of the expansion, the
    Township was allocated a total of 939,000 gpd of sewer capacity. The Township agreed to pay the Authority
    $6,024,704 for the increased capacity and relied on private investment to finance the project. Each landowner
    purchasing future sewer capacity entered into a sewer allocation agreement with the Township. The sample
    allocation agreement places a time limit on the right of a landowner to hold on to unused capacity and provides that
    the landowner pay a certain sum for unused sewer capacity annually. By ordinance, the Township provides the
    methodology for allocation of sewer capacity to landowners and for the recapturing of unused capacity. According
    to the ordinance, in the case of those development projects which have not received approval by the appropriate
    Township board having jurisdiction at the time a request for gallonage is made, allocation agreements shall provide
    that if the applicant does not make formal application to the appropriate Township board within two years of
    approval of the allocation, then the Township Committee may, in its discretion, terminate the agreement. The
    ordinance also provides that if within two years after preliminary approval, construction has not commenced, the
    Township Committee may, at its discretion, terminate the agreement.
    Plaintiff requested that the Township recapture sufficient sewer capacity to allow its construction project to
    proceed. In response, the Township notified plaintiff that there was no sewer capacity available. Plaintiff filed a
    complaint against the Township and multiple private entities to compel the transfer of allocated, but unused, sewer
    capacity, claiming that the municipal ordinance addressing the allocation of sewer capacity was invalid either on its
    face or as applied by the Township. Plaintiff and defendants subsequently moved for summary judgment. The trial
    court remanded the matter to the Township Committee to review the reasoning set forth in its prior rejection of
    plaintiff’s request for sewer capacity and to provide a statement of reasons as a supplement to its decision. In
    response to the remand order, the Township Committee held a public hearing and issued a resolution denying
    plaintiff’s request for sewer capacity.
    The trial court affirmed the validity of the ordinance, but determined that the Township’s blanket policy of
    not recalling unused sewer capacity violated the dictates of this Court’s decision in First Peoples Bank v. Township
    of Medford, 
    126 N.J. 413
    , 420-21 (1991). According to the trial court, the Township’s obligation is not dependent
    on whether plaintiff can beg, borrow or cadge capacity from others, but rather to terminate agreements where it is
    appropriate to do so. As a remedy, the court ordered that the Township undertake, within ninety days, a review of
    the unused sewer capacity listed by plaintiff and provide a reasoned basis for not recapturing that capacity. Plaintiff
    and several defendants appealed, and in an unpublished opinion, the Appellate Division reversed. The Appellate
    Division agreed with the trial court that the Township relied on a policy of not re-taking sewer rights granted by
    contract, but also found that plaintiff could not overcome the presumption of validity that attaches to municipal
    decision-making. This Court granted plaintiff’s petition for certification. 
    217 N.J. 287
    (2014).
    HELD: A blanket policy of not recapturing unused sewer capacity is the functional equivalent of a moratorium on
    development. The Court approves of the trial court’s approach, requiring the Township both to undertake a detailed
    analysis of the unused capacity in the hands of private parties and to explain whether any of that capacity can be
    recalled.
    1. The Court’s primary task here is to resolve whether the Township’s sewer allocation ordinance is facially valid and
    whether the ordinance as applied by the Township Committee constitutes an improper delegation of land-use authority
    to private parties in violation of First Peoples. The Legislature has the constitutional authority to delegate to
    municipalities the police power to enact ordinances governing the nature and extent of the uses of land and has done so
    through the passage of the Municipal Land Use Law (MLUL). This power, however, is not unlimited. Like all
    ordinances, the Township’s sewer allocation ordinance is entitled to a presumption of validity, and the party
    challenging the ordinance bears the burden of overcoming that presumption. (pp. 29-31)
    2. A sewer ordinance should withstand a challenge unless it is inequitable, unfair, or lacks adequate standards to insure
    the fair and reasonable exercise of municipal authority. In First Peoples, which addressed several of the issues
    presented here, Medford Township financed the expansion of its sewage plant through the sale of sewer permits that
    were available on an equal basis to all developers. There, the question was whether the ordinance articulated adequate
    standards to guide the exercise of municipal discretion when considering the repurchase of permits. This Court
    concluded that the ordinance, although not exquisitely drafted, contained sufficient standards to withstand the plaintiff’s
    challenge and rejected the plaintiff’s as-applied challenge to the ordinance, finding nothing to suggest that Medford had
    acted arbitrarily in deciding whether to exercise its repurchase option. (pp. 32-34)
    3. With those principles in mind, the Court rejects plaintiff’s challenge to the ordinance itself and finds that the
    Township’s sewer allocation ordinance provides adequate standards to guide the exercise of municipal discretion when
    considering the repurchase of permits. The Court presumes that the ordinance’s drafters intended certain practical
    considerations to be taken into account by the Township Committee in exercising its discretion whether to terminate an
    allocation agreement or extend one based on good cause. Such considerations would include (1) the length of time a
    landowner has possessed unused sewer capacity, (2) the development plans of the landowner to tap some or all of the
    unused capacity and the imminence of that happening, (3) the complexity of the development project and the
    importance of the project to the community, (4) whether the economy has retarded economic development, (5)
    proposed development projects by others that cannot proceed because of unavailability of sewer capacity and the
    importance of those projects to the community, and (6) any other relevant factors. As was true in First Peoples, the
    ordinance here was not exquisitely drafted. Nevertheless, it must be liberally construed in favor of its validity. This
    ordinance in no way suggests that the Township as a matter of law has delegated its authority to control land use, or
    access to sewer capacity, to private parties. The Court concludes that the sewer allocation ordinance provides adequate
    guidelines for the Township to exercise its discretion whether and when to repurchase sewer capacity. (pp. 35-37)
    4. In contravention of its own ordinance, the Township maintains a blanket policy of not repurchasing unused sewer
    capacity allocated to developers. The fact that sewer capacity was allocated by contracts to private entities that
    financed the plant expansion project and was paid for at considerable expense cannot be the end of the analysis.
    Otherwise, the ordinance requiring the Township to exercise its discretion in recapturing sewer capacity would be
    meaningless. That other landowners did not participate in purchasing capacity to help finance the plant expansion
    may indicate nothing more than that they did not have a need for sewer capacity at the time. (pp. 37-39)
    5. The Appellate Division placed on plaintiff the burden of showing that defendant developers were acting without
    good cause for delay by not voluntarily surrendering their sewer rights for the fair value offered by plaintiff. That
    defeats the purpose of the ordinance and of the policy of the MLUL, which is to have the Township exercise its
    decision-making authority in land-use matters. The resolution also failed to analyze which developments, if any, fall
    under the dictates of the Permit Extension Act, N.J.S.A. 40:55D-136.1 to -136.6. Last, and most significantly, the
    resolution did not give a reasoned explanation for the Township’s failure to exercise discretion, as required by its
    own ordinance. As a best practice, the Court suggests that the Township maintain updated records of the unused
    capacity held by private parties so that it can exercise its discretion, when necessary, with current information. (pp.
    39-42)
    6. The Court orders the Township Committee, within ninety days, to undertake a critical review of the unused capacity
    identified by plaintiff and to determine whether any such capacity can be recaptured from defendants to satisfy
    plaintiff’s development needs. (p. 42)
    The judgment of the Appellate Division is AFFIRMED IN PART and REVERSED IN PART. The
    matter is REMANDED to the trial court for proceedings consistent with this opinion.
    CHIEF JUSTICE RABNER and JUSTICES PATTERSON, FERNANDEZ-VINA, and SOLOMON
    join in JUSTICE ALBIN’S opinion. JUSTICE LaVECCHIA and JUDGE CUFF (temporarily assigned) did
    not participate.
    2
    SUPREME COURT OF NEW JERSEY
    A-63 September Term 2013
    073322
    388 ROUTE 22 READINGTON
    REALTY HOLDINGS, LLC,
    Plaintiff-Appellant,
    v.
    TOWNSHIP OF READINGTON,
    TOWNSHIP COMMITTEE OF THE
    TOWNSHIP OF READINGTON, SEWER
    ADVISORY COMMITTEE OF THE
    TOWNSHIP OF READINGTON,
    BELLEMEAD DEVELOPMENT
    CORPORATION, READINGTON
    COMMONS, LLC, C. DELVECCHIO,
    S. CARBONE, A. CARBONE, ROLF
    ACKERMAN, VALLEY NATIONAL
    BANK, RYLAND DEVELOPERS, LLC,
    LOT 3 DEVELOPMENT, LLC,
    FALLONE PROPERTIES, LLC,
    URB-FI DEVELOPMENT CORP.,
    FALLONE AT SPRING MEADOW, LLC
    COUNTRY CLASSICS LEGACY
    READINGTON, and WINFIELD
    MANAGEMENT,
    Defendants-Respondents,
    and
    MERCK SHARP & DOHME CORP.,
    f/k/a MERCK & CO., INC.,
    Defendant-Respondent,
    and
    RAMYZ TADROS, SHADIA SAMAAN,
    WHITEHOUSE ATHLETIC
    ASSOCIATION, WLADYSLAW
    1
    ZACIOS, JOANN ZACIOS, BETTY
    ANN COEBLER, CODDINGTON HOMES
    CO., INC., TOM JR. PROPERTY,
    INC., and WPS REALTY, LLC,
    Defendants.
    388 ROUTE 22 READINGTON
    REALTY HOLDINGS, LLC,
    Plaintiff-Appellant,
    v.
    TOWNSHIP OF READINGTON,
    TOWNSHIP COMMITTEE OF THE
    TOWNSHIP OF READINGTON, SEWER
    ADVISORY COMMITTEE OF THE
    TOWNSHIP OF READINGTON, MERCK
    SHARP & DOHME CORP., f/k/a
    MERCK & CO., INC., READINGTON
    COMMONS, LLC, C. DELVECCHIO,
    SCOTT CARBONE, A. CARBONE,
    ROLF ACKERMAN, VALLEY
    NATIONAL BANK, RYLAND
    DEVELOPERS, LLC, LOT 3
    DEVELOPMENT, LLC, FALLONE
    PROPERTIES, LLC, URB-FI
    DEVELOPMENT CORP., FALLONE AT
    SPRING MEADOW, LLC, COUNTRY
    CLASSICS LEGACY READINGTON,
    and WINFIELD MANAGEMENT,
    Defendants-Respondents,
    and
    BELLEMEAD DEVELOPMENT
    CORPORATION,
    Defendant-Respondent,
    and
    2
    RAMYZ TADROS, SHADIA SAMAAN,
    WHITEHOUSE ATHLETIC
    ASSOCIATION, WLADYSLAW
    ZACIOS, JOANN ZACIOS, BETTY
    ANN COEBLER, CODDINGTON HOMES
    CO., INC., TOM JR. PROPERTY,
    INC., and WPS REALTY, LLC,
    Defendants.
    388 ROUTE 22 READINGTON
    REALTY HOLDINGS, LLC,
    Plaintiff-Appellant,
    v.
    TOWNSHIP OF READINGTON,
    TOWNSHIP COMMITTEE OF THE
    TOWNSHIP OF READINGTON, and
    SEWER ADVISORY COMMITTEE OF
    THE TOWNSHIP OF READINGTON,
    Defendants-Respondents,
    and
    BELLEMEAD DEVELOPMENT
    CORPORATION, MERCK SHARP &
    DOHME CORP., f/k/a MERCK &
    CO., INC., READINGTON
    COMMONS, LLC, C. DELVECCHIO,
    SCOTT CARBONE, A. CARBONE,
    ROLF ACKERMAN, VALLEY
    NATIONAL BANK,RYLAND
    DEVELOPERS, LLC, LOT 3
    DEVELOPMENT, LLC, FALLONE
    PROPERTIES, LLC, URB-FI
    DEVELOPMENT CORP., FALLONE AT
    SPRING MEADOW, LLC COUNTRY
    CLASSICS LEGACY READINGTON,
    and WINFIELD MANAGEMENT,
    Defendants-Respondents,
    3
    and
    RAMYZ TADROS, SHADIA SAMAAN,
    WHITEHOUSE ATHLETIC
    ASSOCIATION, WLADYSLAW
    ZACIOS, JOANN ZACIOS, BETTY
    ANN COEBLER, CODDINGTON HOMES
    CO., INC., TOM JR. PROPERTY,
    INC., and WPS REALTY, LLC,
    Defendants.
    388 ROUTE 22 READINGTON
    REALTY HOLDINGS, LLC,
    Plaintiff-Appellant,
    v.
    TOWNSHIP OF READINGTON,
    TOWNSHIP COMMITTEE OF THE
    TOWNSHIP OF READINGTON, SEWER
    ADVISORY COMMITTEE OF THE
    TOWNSHIP OF READINGTON,
    BELLEMEAD DEVELOPMENT
    CORPORATION, MERCK SHARP &
    DOHME CORP., f/k/a MERCK &
    CO., INC., C. DELVECCHIO,
    SCOTT CARBONE, A. CARBONE,
    ROLF ACKERMAN, VALLEY
    NATIONAL BANK, RYLAND
    DEVELOPERS, LLC, LOT 3
    DEVELOPMENT, LLC, FALLONE
    PROPERTIES, LLC, URB-FI
    DEVELOPMENT CORP., TOLL NJ I,
    LLC, and WINFIELD MANAGEMENT,
    Defendants-Respondents,
    and
    COUNTRY CLASSICS LEGACY AT
    READINGTON, READINGTON
    COMMONS, LLC, and RYLAND
    DEVELOPERS, LLC,
    4
    Defendants-Respondents,
    and
    RAMYZ TADROS, SHADIA SAMAAN,
    WHITEHOUSE ATHLETIC
    ASSOCIATION, WLADYSLAW
    ZACIOS, JOANN ZACIOS, BETTY
    ANN COEBLER, CODDINGTON HOMES
    CO., INC., TOM JR. PROPERTY,
    INC., and WPS REALTY, LLC,
    Defendants.
    388 ROUTE 22 READINGTON
    REALTY HOLDINGS, LLC,
    Plaintiff-Appellant,
    v.
    TOWNSHIP OF READINGTON,
    TOWNSHIP COMMITTEE OF THE
    TOWNSHIP OF READINGTON, SEWER
    ADVISORY COMMITTEE OF THE
    TOWNSHIP OF READINGTON,
    BELLEMEAD DEVELOPMENT
    CORPORATION, MERCK SHARP &
    DOHME CORP., f/k/a MERCK &
    CO., INC., READINGTON
    COMMONS, LLC, C. DELVECCHIO,
    SCOTT CARBONE, A. CARBONE,
    ROLF ACKERMAN, VALLEY
    NATIONAL BANK, RYLAND
    DEVELOPERS, LLC, FALLONE
    PROPERTIES, LLC, URB-FI
    DEVELOPMENT CORP., FALLONE AT
    SPRING MEADOW, LLC, and
    COUNTRY CLASSICS LEGACY
    READINGTON,
    Defendants-Respondents,
    and
    5
    LOT 3 DEVELOPMENT, LLC and
    WINFIELD MANAGEMENT,
    Defendants-Respondents,
    and
    RAMYZ TADROS, SHADIA SAMAAN,
    WHITEHOUSE ATHLETIC
    ASSOCIATION, WLADYSLAW
    ZACIOS, JOANN ZACIOS, BETTY
    ANN COEBLER, CODDINGTON HOMES
    CO., INC., TOM JR. PROPERTY,
    INC., and WPS REALTY, LLC,
    Defendants.
    388 ROUTE 22 READINGTON
    REALTY HOLDINGS, LLC,
    Plaintiff-Appellant,
    v.
    TOWNSHIP OF READINGTON,
    TOWNSHIP COMMITTEE OF THE
    TOWNSHIP OF READINGTON, SEWER
    ADVISORY COMMITTEE OF THE
    TOWNSHIP OF READINGTON,
    BELLEMEAD DEVELOPMENT
    CORPORATION, MERCK SHARP &
    DOHME CORP., f/k/a MERCK &
    CO., INC., READINGTON
    COMMONS, LLC, C. DELVECCHIO,
    SCOTT CARBONE, A. CARBONE,
    ROLF ACKERMAN, VALLEY
    NATIONAL BANK, LOT 3
    DEVELOPMENT, LLC, FALLONE
    PROPERTIES, LLC, URB-FI
    DEVELOPMENT CORP., FALLONE AT
    SPRING MEADOW, LLC, COUNTRY
    CLASSICS LEGACY READINGTON,
    and WINFIELD MANAGEMENT,
    Defendants-Respondents,
    6
    and
    RYLAND DEVELOPERS, LLC,
    Defendant-Respondent,
    and
    RAMYZ TADROS, SHADIA SAMAAN,
    WHITEHOUSE ATHLETIC
    ASSOCIATION, WLADYSLAW
    ZACIOS, JOANN ZACIOS, BETTY
    ANN COEBLER, CODDINGTON HOMES
    CO., INC., TOM JR. PROPERTY,
    INC., and WPS REALTY, LLC,
    Defendants.
    388 ROUTE 22 READINGTON
    REALTY HOLDINGS, LLC,
    Plaintiff-Appellant,
    v.
    TOWNSHIP OF READINGTON,
    TOWNSHIP COMMITTEE OF THE
    TOWNSHIP OF READINGTON, SEWER
    ADVISORY COMMITTEE OF THE
    TOWNSHIP OF READINGTON,
    BELLEMEAD DEVELOPMENT
    CORPORATION, MERCK SHARP &
    DOHME CORP., f/k/a MERCK &
    CO., INC., READINGTON
    COMMONS, LLC, C. DELVECCHIO,
    SCOTT CARBONE, A. CARBONE,
    ROLF ACKERMAN, VALLEY
    NATIONAL BANK, RYLAND
    DEVELOPERS, LLC, LOT 3
    DEVELOPMENT, LLC, URB-FI
    DEVELOPMENT CORP., COUNTRY
    CLASSICS LEGACY READINGTON,
    and WINFIELD MANAGEMENT,
    Defendants-Respondents,
    7
    and
    FALLONE PROPERTIES, LLC, and
    TOLL NJ I, LLC,
    Defendants-Respondents,
    and
    RAMYZ TADROS, SHADIA SAMAAN,
    WHITEHOUSE ATHLETIC
    ASSOCIATION, WLADYSLAW
    ZACIOS, JOANN ZACIOS, BETTY
    ANN COEBLER, CODDINGTON HOMES
    CO., INC., TOM JR. PROPERTY,
    INC., and WPS REALTY, LLC,
    Defendants.
    388 ROUTE 22 READINGTON
    REALTY HOLDINGS, LLC,
    Plaintiff-Appellant,
    v.
    TOWNSHIP OF READINGTON,
    TOWNSHIP COMMITTEE OF THE
    TOWNSHIP OF READINGTON, SEWER
    ADVISORY COMMITTEE OF THE
    TOWNSHIP OF READINGTON,
    BELLEMEAD DEVELOPMENT
    CORPORATION, MERCK SHARP &
    DOHME CORP., f/k/a MERCK &
    CO., INC., READINGTON
    COMMONS, LLC, C. DELVECCHIO,
    SCOTT CARBONE, A. CARBONE,
    ROLF ACKERMAN, VALLEY
    NATIONAL BANK, RYLAND
    DEVELOPERS, LLC, FALLONE
    PROPERTIES, LLC, URB-FI
    DEVELOPMENT CORP., FALLONE AT
    SPRING MEADOW, LLC, and
    COUNTRY CLASSICS LEGACY
    READINGTON,
    8
    Defendants-Respondents,
    and
    LOT 3 DEVELOPMENT, LLC, and
    WINFIELD MANAGEMENT,
    Defendants-Respondents,
    and
    RAMYZ TADROS, SHADIA SAMAAN,
    WHITEHOUSE ATHLETIC
    ASSOCIATION, WLADYSLAW
    ZACIOS, JOANN ZACIOS, BETTY
    ANN COEBLER, CODDINGTON HOMES
    CO., INC., TOM JR. PROPERTY,
    INC., and WPS REALTY, LLC,
    Defendants.
    Argued December 2, 2014 – Decided May 5, 2015
    On certification to the Superior Court,
    Appellate Division.
    Lawrence S. Berger argued the cause for
    appellant (Berger & Bornstein, attorneys).
    Christopher John Stracco argued the cause
    for respondent Merck Sharp & Dohme Corp.
    (Day Pitney, attorneys; Mr. Stracco and
    Jennifer Gorga Capone, on the brief).
    Robert A. Ballard argued the cause for
    respondents Township of Readington, Township
    Committee of the Township of Readington, and
    Sewer Advisory Committee of the Township of
    Readington, (Ballard & Dragan, attorneys).
    Glenn S. Pantel argued the cause for
    respondent Bellemead Development Corporation
    9
    (Drinker Biddle & Reath, attorneys; Mr.
    Pantel and Karen A. Denys, on the brief).
    Deborah B. Rosenthal argued the cause for
    respondents Winfield Management Corp. and
    Lot 3 Development, LLC (Gebhardt & Kiefer,
    attorneys; Robert C. Ward, on the brief).
    Alexander G. Fisher argued the cause for
    respondents Ryland Developers, LLC,
    Readington Commons, LLC and Country Classics
    Legacy at Readington, LLC (Mauro, Savo,
    Camerino, Grant & Schalk, attorneys).
    Thomas W. Sweet argued the cause for
    respondents Fallone Properties, LLC and
    Fallone at Spring Meadow, LLC.
    Salvatore Alfieri submitted a letter in lieu
    of brief on behalf of respondents Scott
    Carbone, A. Carbone, and C. DelVecchio
    (Cleary Giacobbe Alfieri Jacobs, attorneys).
    JUSTICE ALBIN delivered the opinion of the Court.
    Access to sewer service is vital to any major development
    of property.   In First Peoples Bank v. Township of Medford, we
    held that a municipality cannot delegate the exercise of its
    land-use authority to private parties by allowing them to
    purchase and hoard unused sewer rights, thereby stifling
    development by those who are prepared to build.    
    126 N.J. 413
    ,
    420-21 (1991).   Instead, a “[t]ownship must retain sufficient
    control to assure that sewer permits are either used or
    repurchased so that others may use them.”   
    Id. at 420.
    Plaintiff 388 Route 22 Readington Realty Holdings, LLC is
    seeking to construct a retail outlet and a restaurant but cannot
    10
    do so unless it secures access to 11,260 gallons per day (gpd)
    of sewer capacity.     At the time that plaintiff requested access
    to that amount of sewer capacity from Readington Township,
    approximately twenty private entities possessed 322,009 gpd of
    unused capacity.     The Township sold most of that unused capacity
    on the private market as a means of financing the expansion of
    sewer service from the Readington-Lebanon Sewerage Authority
    (Sewerage Authority or Authority).
    Plaintiff demanded that the Township -- in accordance with
    a municipal ordinance governing allocation of sewer rights --
    recapture sufficient sewer capacity to allow its construction
    project to proceed.     Consistent with its policy of not
    repurchasing capacity, the Township declined to do so.
    Plaintiff then filed a complaint in lieu of prerogative writs
    against the Township and multiple private entities to compel the
    transfer of allocated but unused sewer capacity.     Plaintiff
    claimed that the municipal ordinance addressing the allocation
    of sewer capacity was invalid either on its face or as applied
    by the Township.
    On cross-motions for summary judgment by the parties, the
    trial court affirmed the validity of the ordinance.     The court,
    however, determined that the Township’s blanket policy of not
    recalling unused sewer capacity violated the dictates of First
    Peoples.   The court issued a writ of mandamus ordering the
    11
    Township to exercise its discretion under its ordinance and to
    provide “a reasoned basis for refusing to recapture” the unused
    capacity held by multiple private entities.
    The Appellate Division reversed.    Although the Appellate
    Division agreed with the trial court that the Township “simply
    relied on a policy of not re-taking sewer rights granted by
    contract,” it concluded that plaintiff could not overcome the
    presumption of validity that attaches to municipal decision-
    making.
    We now conclude that the Appellate Division erred.       As the
    trial court held, the Township cannot meaningfully exercise its
    discretion whether to repurchase sewer capacity unless it
    examines the reasons given by each entity for not using capacity
    assigned to it.   A policy of not recapturing unused sewer
    capacity is the functional equivalent of a moratorium on
    development.   We approve of the sound approach taken by the
    trial court, requiring the Township both to undertake a detailed
    analysis of the unused capacity in the hands of private parties
    and to explain whether any of that capacity can be recalled.
    I.
    We now review the relevant parts of the record on the
    summary-judgment motions.
    In December 2007, plaintiff purchased property and a
    warehouse located at 388 Route 22 West in Readington Township.
    12
    The wastewater at that site is serviced by a septic tank that
    allows for a maximum of 2000 gpd of capacity.1   The Township
    rezoned plaintiff’s property from the Mixed-Use District to the
    Business District, where retail and restaurant uses are
    permitted.   Plaintiff’s septic tank does not have sufficient
    capability to process the wastewater generated for the uses
    plaintiff proposes.
    Plaintiff’s property is in an area serviced by the Sewerage
    Authority, which manages wastewater for Readington and Lebanon
    Townships.   A sewer line is located directly in front of
    plaintiff’s property.    After the zoning change, plaintiff made
    plans to redevelop the property for use as a restaurant and for
    other retail purposes.   Plaintiff’s proposed project requires
    11,260 gpd of sewer capacity, which can only be accomplished by
    connecting to the Authority’s sewer system.    However, the
    Township advised plaintiff that there was no available sewer
    capacity to allocate to the project.
    Around 1999, the Sewerage Authority began the expansion of
    its plant capacity to allow the treatment of an additional
    320,000 gpd of Readington’s wastewater.    As a result of the
    plant expansion, Readington Township was allocated, in all,
    1 N.J.A.C. 7:9A-1.8 prohibits the use of a septic system to
    manage a wastewater capacity of over 2000 gpd without permission
    from the New Jersey Department of Environmental Protection.
    13
    approximately 939,000 gpd of sewer capacity.    The Township
    agreed to pay the Authority $6,024,704 for the increased
    capacity.    To finance the project, the Township relied on
    private investment.    The Township offered landowners the
    opportunity to purchase portions of the 320,000 gpd of increased
    capacity.    In response to the offering, to name a few, Merck
    Sharpe & Dohme Corporation purchased 141,900 gpd of capacity for
    $2,196,764, Bellemead Development Corporation purchased 58,746
    gpd of capacity for $1,106,187, and Readington Commons, LLC
    purchased 7628 gpd of capacity for $143,635.    The prior owner of
    plaintiff’s property declined to invest in future sewer
    capacity.
    Each landowner purchasing future sewer capacity entered
    into a sewer allocation agreement with the Township.    The
    Township’s “Sample Sewer Allocation Agreement,” in part,
    provides:
    Should Developer not begin construction on the
    aforementioned properties within two (2) years
    of the date of this agreement, then the
    Township shall have the option to terminate
    this agreement and all capacity assigned
    herein under shall be returned to the Township
    for reallocation at the discretion of the
    Township.
    The sample allocation agreement -- in compliance with the sewer
    allocation ordinance -- places a temporal limit on the right of
    a landowner to hold on to unused capacity.
    14
    The allocation agreements with Merck, however, do not
    follow the protocols in the ordinance or sample allocation
    agreement.   Merck’s 2003 and amended 2008 sewer allocation
    agreements allow Merck to maintain unused sewer capacity for the
    periods the Township extended Merck’s site plan approvals for
    proposed construction in Readington.   A past approval ran from
    1988 to 2008, and the current approval runs from 2008 to 2018.
    Merck’s agreements have barred the Township from recapturing
    unused capacity for a period lasting at least fifteen years.2
    The typical allocation agreement provides that the
    landowner pay a certain sum for unused sewer capacity annually.
    The full annual amount was due the third year after acquisition.
    The first and second year payments were set at one-third and
    then two-thirds of the full amount annually due.   For example,
    Merck agreed to pay $48,720 the first year, $97,440 the second
    year, and then $146,160 annually for as long as the allocated
    gallonage remained unused.
    2 In 1988, Merck obtained preliminary site plan approvals for
    projects to be constructed on its Readington property. The
    approvals were set to expire in twenty years. In 2008,
    Readington granted Merck a ten-year extension of its preliminary
    site plan approvals, and the Township agreed that it would not
    seek to recapture any unused sewer capacity until 2018.
    15
    As of December 2010, of the 322,009 gpd of unused capacity,
    141,900 was held by Merck, 66,060 by Bellemead,3 32,000 or 38,860
    by Fallone Properties, LLC, and 30,125 by Ryland Developers,
    LLC.    Each remaining defendant held less than 10,000 gpd of
    unused capacity.    Merck’s unused capacity represents forty-four
    percent of the entire capacity yielded from Readington’s portion
    of the Authority’s plant expansion.
    Defendants have not proceeded with construction projects
    for a variety of reasons.    One reason given by some defendants
    has been the downturn in the economy.
    By ordinance, the Township provides the methodology for
    allocation of sewer capacity to landowners and for the
    recapturing of unused capacity.    Readington Township Code § 187-
    26 states:
    A. Order of priority; reserves.
    (1) By existing joint agreement with the
    Readington Lebanon Sewerage Authority,
    the Township of Readington has a total
    sewer allocation of 935,000 gpd. Upon
    study by the Township, there is a limited
    amount of sewer capacity in Readington
    3 In 1988, Bellemead was granted preliminary and final site plan
    approval for its “Halls Mills Farm” development project. The
    approval was set to expire in eight years. Bellemead was
    granted multiple extensions with the final extension set to
    expire in July 2010. As a result of the Authority’s plant
    expansion, Bellemead was allocated 58,746 gpd of capacity,
    making its total capacity 110,746 gpd. Bellemead is using
    44,686 of that gallonage, while 66,060 gpd -- the amount
    required to operate its Halls Mills project -- remains unused.
    16
    Township at the present time. Any
    remaining capacity from Readington’s
    portion of its allotted capacity in the
    Readington Lebanon Sewerage Authority
    sewer service area shall be allocated in
    the following order of priority, subject
    to availability:
    (a) First, to those projects which
    will enable the Township to meet its
    future   Mount   Laurel   affordable
    housing obligations; and
    (b) Secondly, to remedy those
    properties within the sewer service
    area     which    constitute     an
    “emergency” due to failing septic
    systems.
    (2) The Township reserves the right to
    keep that portion of sewerage capacity
    needed for “reserve” to meet NJDEP
    requirements.
    B. Allocations for sewer capacity from
    Readington’s   allotted  portion   of   sewer
    capacity shall be made by the Readington
    Township Committee upon written agreement to
    be entered into with the applicant, after the
    allocation request has been reviewed and a
    favorable recommendation has been made by the
    Readington Township Sewer Advisory Committee.
    C. In the case of those development projects
    which have not received an approval by the
    appropriate      township     board     having
    jurisdiction at the time a request for
    gallonage is made, allocation agreements shall
    provide that if the applicant does not make
    formal application to the appropriate township
    board within two years of approval of the
    allocation, then the Township Committee may,
    in its discretion, terminate the agreement.
    If   within   two   years  after   preliminary
    approval, construction has not commenced, the
    Township Committee may, at its discretion,
    terminate the agreement. The agreement may be
    17
    extended upon application to the Township if
    there is a showing of good cause, at the option
    of the Township Committee.
    D.   Applicants    who   received    capacity
    allocations under this section shall enter
    into a sewer plant expansion developer
    contribution agreement which is intended to
    cover the Township’s share of the portion of
    the   costs   of  expanding   the   [Sewerage
    Authority] treatment plant until such time as
    those costs have been satisfied. . . .
    E. Allocation of sewer capacity may not be
    transferred from the owner without prior
    approval of the Readington Township Committee,
    upon   review   and  recommendation   of   the
    Readington Township Sewer Advisory Committee.
    In March 2010, plaintiff wrote to the Readington Township
    Committee and the Readington Sewer Advisory Committee requesting
    that 388 Route 22 be permitted to hook up to the Authority’s
    sewer system and gain access to approximately 10,000 gpd
    capacity.    Plaintiff expressed its belief that the Township
    possessed sufficient sewer capacity to accommodate plaintiff’s
    request.    Alternatively, in the event that all sewer capacity
    had been allocated, plaintiff stated that Readington should buy
    back unused capacity from property owners who had “not made
    formal application for development of [their] properties” or who
    had “failed to commence construction of improvements within two
    years after receipt of preliminary approval from the appropriate
    Township Board.”    In making this demand for the buyback of
    unused capacity, plaintiff relied on paragraph C of the
    18
    Readington Township sewer allocation ordinance.    The Readington
    Township Committee replied that it did “not wish to terminate
    any of its existing sewer agreements.”
    On August 4, 2010, plaintiff’s attorney and professional
    planner appeared before the Readington Sewer Advisory Committee,
    describing plaintiff’s plan to develop the property at 388 Route
    22 into retail space and a restaurant.   They requested a hookup
    to the sewer system and 11,260 gpd of wastewater capacity.     The
    Committee’s chairman replied that all capacity was either used
    or reserved by property owners who financed the sewer plant’s
    expansion.   He stated that the Township was bound by contracts
    with those property owners, although the ordinance allowed for
    an owner to “voluntarily” give up capacity.   The chairman made
    clear that “the policy of this board and the policy of the
    Township Committee has been not to take any capacity back.”    The
    chairman finally noted that his committee’s recommendation was
    advisory and that the Township Committee would make the final
    decision.
    On September 20, 2010, plaintiff’s attorney appeared before
    the Township Committee and requested 11,260 gpd of sewer
    capacity for plaintiff’s project.    He indicated that plaintiff
    had contacted fifteen property owners, and none were interested
    in selling their unused capacity.    The attorney noted that
    plaintiff would pay the holder its costs in acquiring and
    19
    retaining the unused capacity.    Nevertheless, Committee members
    expressed concern about breaching contracts with landowners
    holding unused capacity.
    By letter dated October 14, 2010, the Township Committee
    advised plaintiff that there was no sewer capacity available.
    The Committee invited plaintiff to present “a conceptual plan,
    either through the Planning Board or Board of Adjustment,
    whichever is applicable, . . . and that the application would be
    conditioned on obtaining a suitable solution to wastewater.”
    II.
    A.
    In November 2010, plaintiff filed its lawsuit seeking an
    order compelling the Township to recapture 11,260 gpd of unused
    sewer capacity for its project.    Plaintiff’s complaint in lieu
    of prerogative writs named as defendants Readington Township,
    Bellemead, Merck, Readington Commons, and various other parties
    listed in the caption.   Among plaintiff’s claims are the
    following:   (1) as a result of Readington Township’s sewer
    allocation ordinance, the Township has failed to retain control
    over the allocation of sewer capacity and, in effect, has
    delegated to certain private landowners the authority to prevent
    other property owners from developing their land; (2) the
    Township’s policy of not recapturing sewer capacity in the hands
    of private entities is arbitrary, capricious, and unreasonable
    20
    under the ordinance; (3) the “Township has sufficient unused
    capacity to allocate to [p]laintiff’s [p]roperty”; and (4) the
    Township’s failure to allocate to plaintiff sewer capacity
    amounts to an unconstitutional taking of its property.
    Plaintiff’s claims, in essence, constitute a facial and as-
    applied challenge to the validity of the municipal ordinance.
    Plaintiff and defendants moved for summary judgment.     The
    trial court -- the Honorable Peter A. Buchsbaum, J.S.C. --
    remanded the matter to the Township Committee to “review the
    reasoning set forth in its prior rejection” of plaintiff’s
    request for sewer capacity and to “provide a statement of
    reasons as a supplement to its decision.”
    In response to the remand order, the Township Committee
    held a public hearing on July 5, 2011 and issued a resolution
    denying plaintiff’s request for sewer capacity.   The resolution
    referenced letters received from defendants Merck, Readington
    Commons, Bellemead, Fallone, and Urb-Fi Development Corp., which
    recited their allocation agreements with the Township and
    described the development status of their projects.   Those and
    other defendants objected to the transfer of any of their unused
    capacity to plaintiff.
    In justifying its refusal to recapture unused sewer
    capacity, the Township Committee adopted in the resolution “the
    full contents and arguments of the listed correspondence
    21
    submitted by various defendants.”   The Township Committee gave
    further reasons for the denial of plaintiff’s request:     (1) all
    excess capacity held by the Township is reserved for affordable
    housing and emergencies; (2) the sewer ordinance allowed the
    Township to extend its sewer allocation agreements with
    defendants for “good cause” and, having done so, the Township
    did not act unreasonably or arbitrarily; (3) several defendants
    “have development approvals which fall under the protections
    afforded by the Permit Extension act,” a separate reason
    constituting “good cause” for continuing the allocation
    agreements; (4) the previous owner of plaintiff’s property
    expressed no “interest in acquiring sewer capacity at the time
    the Township announced that it was available for purchase”; (5)
    Township Committee members did not believe that it was “in the
    public interest to force the termination of . . . existing sewer
    agreements”; and (6) plaintiff had not determined whether the
    holder of any unused capacity had an “interest in voluntarily
    selling their capacity back to the Township.”
    B.
    The trial court held that Readington’s sewer ordinance
    passed muster under First 
    Peoples, supra
    , 
    126 N.J. 413
    .    In a
    written opinion, the court determined that the ordinance, on its
    face, ensures “municipal control of sewer rights” and “provides
    mechanisms” for the Township “to recapture sewer capacity.”       In
    22
    reaching this decision, the court recognized “the tradition of
    judicial deference” in upholding “broad standards for local
    action in the land use area.”
    On the other hand, the court found that the ordinance as
    applied by the Township raised serious doubts about the
    legitimacy of the Township’s sewer policy.     Based on the
    summary-judgment record, it accepted that plaintiff was
    unsuccessful in its efforts to purchase sewer capacity from
    defendant developers and that the policy of the Township, as
    expressed by the Chairman of the Sewer Advisory Committee, “is
    not to take capacity back.”     The court described the Township’s
    resolution as “pro forma” and a “brushoff” that “simply recites
    what was received from [defendants’] counsel.”    The resolution
    failed to “contain a development by development analysis” or to
    provide “a reasoned explanation” for the Township’s decision not
    “to exercise discretion” to recapture any of the unused
    capacity, which constituted one third of the entire flow
    allocated to Readington.   Further, the resolution failed to
    analyze whether the Permit Extension Act, N.J.S.A. 40:55D-136.1
    to -136.6, applied “to each and every development.”     The court
    held that “the ordinance requires the exercise of discretion,”
    yet the Township followed a “flat policy” of refusing to assert
    its right to recapture unused capacity.     It construed First
    Peoples as standing for the proposition that sewer rights
    23
    “cannot be held in perpetuity” and that at some point the
    Township has a duty to recapture unused capacity.
    According to the trial court, the Township’s obligation is
    not dependent on whether plaintiff can “beg, borrow or cadge
    capacity from others” but rather “to terminate agreements where
    it is appropriate to do so.”   It found that the Township’s no-
    buy-back policy “functioned as a de facto moratorium on any
    development which requires sewerage.”
    As a remedy, the court ordered that the Township undertake,
    within ninety days, a review of the unused sewer capacity listed
    by plaintiff and provide “a reasoned basis” for not recapturing
    that capacity.”4   It cautioned that agreements between the
    Township and defendants granting extended sewer rights may not
    control when a present holder of capacity has seemingly reserved
    the right indefinitely and a “party seeking sewer allocation is
    ready to imminently make use of those rights.”    The court
    acknowledged, however, that the application of the Permit
    Extension Act might limit the Township’s discretion.
    Plaintiff and several defendants appealed.
    C.
    4 The court excepted from the order defendants Country Classics
    of Readington and Readington Commons because they evidently are
    using their capacity.
    24
    In an unpublished opinion, the Appellate Division affirmed
    the Law Division’s rejection of plaintiff’s facial challenge to
    the ordinance but reversed the Law Division’s finding that the
    Township Committee did not give a reasoned basis for not
    recapturing sewer capacity for plaintiff’s project.
    Like the trial court, the appellate panel was satisfied
    that the ordinance provided “standards sufficient to insure
    ‘fair and reasonable exercise’ of the discretion granted,”
    quoting First 
    Peoples, supra
    , 126 N.J. at 419.   Nevertheless,
    the panel suggested that the Township follow the guidance
    offered in First Peoples and consider whether the Township and
    property owners would be better served if the ordinance gave
    “‘more specific standards defining the conditions under which’
    good cause for extension will and will not be found, and
    procedural requirements applicants interested in repurchase
    should follow,” quoting 
    id. at 423.
    The panel, however, determined that the Township Committee
    did not abuse its discretion in not recapturing unused sewer
    capacity for plaintiff.   The panel described plaintiff’s
    development plan as “at best speculative” and “vague.”      Although
    the panel acknowledged that the Township “Committee simply
    relied on a policy of not re-taking sewer rights granted by
    contract,” it concluded that plaintiff did not “establish that
    the denial of its request was arbitrary because it failed to
    25
    overcome the presumption of validity to which the decision is
    entitled.”   The panel based its conclusion on the fact that
    defendants paid a “great expense” for their sewer rights and
    that plaintiff failed to identify those who were holding unused
    sewer capacity “without good cause for delay.”    The panel also
    faulted plaintiff for its “preference for litigation or
    settlement over development and presentation of a more
    definitive request.”    Last, the panel declined to rule on
    whether the sewer allocation agreements are protected under the
    Permit Extension Act.
    We granted plaintiff’s petition for certification.        388
    Route 22 Readington Realty Holdings, LLC v. Twp. of Readington,
    
    217 N.J. 287
    (2014).
    III.
    A.
    Plaintiff advances several arguments:    (1) the sewer
    allocation ordinance is invalid because it does not set forth
    adequate standards to guide the Township in determining when
    unused sewer capacity should be recaptured; (2) the Township’s
    blanket refusal to recall unused sewer capacity violates
    principles set forth in First Peoples, amounts to an
    unconstitutional delegation of governmental authority over land
    use into the hands of private parties, and constitutes an
    unlawful moratorium on development; and (3) the Appellate
    26
    Division mistakenly ratified the Township’s policy on the
    erroneous grounds that plaintiff “should have presented a more
    definitive plan for its proposed development,” the holders of
    sewer rights expended considerable money to acquire the
    allocated capacity, and the Permit Extension Act expresses the
    Legislature’s view that sewer agreements should be extended in
    periods of economic downturn.    With regard to the last of those
    points, plaintiff emphasizes that developers who paid for
    allocations of sewer capacity did so “with full knowledge of the
    recapture rights of the Township under the Ordinance which, in
    many, if not all, instances, were embodied in the allocation
    agreements themselves.”   Plaintiff also maintains that neither
    the Township nor any court has determined whether any particular
    sewer allocation attached to a development project is protected
    by the Permit Extension Act.     Last, plaintiff contends that the
    Appellate Division erred by dismissing its claim that the
    Township has understated its available capacity -- a claim that
    has never been adjudicated.
    B.
    Defendants individually and collectively urge this Court to
    affirm the Appellate Division.     First, they submit that the
    sewer allocation ordinance is valid on its face for the reasons
    given by the Appellate Division:       the ordinance allows the
    Township to terminate or extend allocation agreements for good
    27
    cause, grants the Township authority over the transfer of sewer
    rights, sets benchmarks for the recapture of capacity, and
    establishes an order of priority for allocating available
    capacity.
    Defendants also maintain that the Township Committee did
    not act unreasonably or arbitrarily in declining to recall sewer
    capacity allocated to property owners who funded the sewer plant
    expansion, who have approved site plans, and who paid and
    continue to pay for reserved capacity.   Defendants emphasize
    that plaintiff had purchased 388 Route 22 with notice that sewer
    capacity was unavailable, had no definitive plan to develop the
    property, and made no application for land-use approvals.
    Defendants contend that the Township rightly relied on the
    policy objective of “the Permit Extension Act as well as the
    explicit protections afforded by the Act in finding good cause
    to extend and not recapture the sewer allocations,” particularly
    given the downturn in the economy that stalled development
    projects.   Defendant Merck, in particular, claims that the
    Township is bound to honor its contractual obligations and that
    an impairment of those obligations would violate its rights.
    Merck points out that its agreement bars the Township from
    recalling sewer capacity before Merck’s site plan approvals
    expire in 2018.   Merck maintains that any recapture of its
    “unused sewer capacity prior to that time would unlawfully
    28
    vitiate Merck’s site plan approvals, resulting not only in a
    breach of its contracts with the Township, but also an
    unconstitutional taking.”
    Finally, various defendants represent that they are
    currently using or in the process of using their allocated sewer
    capacity because their projects are either completed or
    underway.
    IV.
    A.
    Our primary task here is to resolve issues of law:      whether
    the Readington sewer allocation ordinance is facially valid, and
    whether the ordinance as applied by the Township Committee
    constitutes an improper delegation of land-use authority to
    private parties in violation of First Peoples.   In construing
    the meaning of a statute, an ordinance, or our case law, our
    review is de novo.   Farmers Mut. Fire Ins. Co. of Salem v. N.J.
    Prop.-Liab. Ins. Guar. Ass’n, 
    215 N.J. 522
    , 535 (2013).     “We
    need not defer to the trial court or Appellate Division’s
    interpretative conclusions” unless they are correct.     Murray v.
    Plainfield Rescue Squad, 
    210 N.J. 581
    , 584 (2012).
    This appeal comes to us from a grant of summary judgment in
    favor of defendants, resulting in a dismissal of plaintiff’s
    action in lieu of prerogative writs.   In this procedural
    posture, plaintiff, as the non-moving party, is entitled to “the
    29
    benefit of all favorable evidence and inferences presented in
    the record before us.”   
    Murray, supra
    , 210 N.J. at 584-85; see
    also Gormley v. Wood-El, 
    218 N.J. 72
    , 86 (2014) (“A court should
    grant summary judgment only when the record reveals ‘no genuine
    issue as to any material fact’ and ‘the moving party is entitled
    to a judgment or order as a matter of law.’” (quoting R. 4:46-
    2(c))).   Accordingly, the summary-judgment record must be viewed
    “through the prism of [plaintiff’s] best case.”   
    Gormley, supra
    ,
    218 N.J. at 86.
    With those principles in mind, we begin with a review of
    the law that controls the distribution of sewer rights.
    B.
    The Legislature has the constitutional authority to
    delegate to municipalities the “police power” to enact
    ordinances governing “the nature and extent of the uses of
    land,” N.J. Const. art. IV, § 6, ¶ 2, and the Legislature has
    done so through the passage of the Municipal Land Use Law
    (MLUL), N.J.S.A. 40:55D-1 to -163.   The constitutional power
    delegated to municipalities to enact land-use regulations,
    however, is not unlimited.   That power “must be exercised for
    the general welfare,” and “regulations that conflict with the
    general welfare . . . are unconstitutional.”   S. Burlington
    Cnty. N.A.A.C.P. v. Twp. of Mt. Laurel, 
    92 N.J. 158
    , 208 (1983)
    (Mt. Laurel II); see also S. Burlington Cnty. N.A.A.C.P. v. Twp.
    30
    of Mt. Laurel, 
    67 N.J. 151
    , 175 (1975) (Mt. Laurel I) (noting
    that police power exercised by municipality must promote “the
    general welfare”).   Consistent with this fundamental tenet, one
    of the express purposes of the MLUL -- indeed the first
    enumerated purpose -- is “[t]o encourage municipal action to
    guide the appropriate use or development of all lands in this
    State, in a manner which will promote the public health, safety,
    morals, and general welfare.”   N.J.S.A. 40:55D-2(a).
    Like all ordinances, Readington’s sewer allocation
    ordinance is entitled to a presumption of validity, and the
    “party challenging the ordinance bears the burden of overcoming
    that presumption.”   See Rumson Estates, Inc. v. Mayor & Council
    of Fair Haven, 
    177 N.J. 338
    , 350 (2003).    An ordinance must be
    “‘liberally construed’” in favor of its validity.     
    Id. at 351
    (quoting N.J. Const. art. IV, § 7, ¶ 11).     Our charge is to pass
    not on the wisdom of a municipal ordinance, but only on whether
    it complies with the Constitution and the MLUL.     See 
    ibid. Courts must also
    pay deference to the decision-making of
    municipal bodies, recognizing that they possess “peculiar
    knowledge of local conditions [and] must be allowed wide
    latitude in the exercise of delegated discretion.”    Kramer v.
    Bd. of Adjustment, 
    45 N.J. 268
    , 296 (1965).     A municipal land-
    use determination should not be set aside unless the public body
    has engaged in “a clear abuse of discretion.”     
    Id. at 296-97.
    31
    If there is “substantial evidence to support” the municipal
    decision, a court should not interfere by substituting its
    judgment.   
    Id. at 296.
    Specific to this case, “a sewer ordinance should withstand
    a challenge unless it is inequitable, unfair, or lacks adequate
    standards to insure the fair and reasonable exercise of
    municipal authority.”     First 
    Peoples, supra
    , 126 N.J. at 419
    (citing 5 McQuillin, The Law of Municipal Corporations § 18.12
    at 453 (3d ed. 1989)).      Nevertheless, “[t]he municipal
    obligation is to provide a level playing field so that
    applicants are treated equally.”        
    Ibid. In assessing the
    validity of Readington’s sewer ordinance
    and the Township’s application of that ordinance, we are not
    addressing novel issues.     We are returning to issues that we
    reviewed in First Peoples, and therefore a discussion of that
    case will help guide us here.
    In First Peoples, Medford Township financed the expansion
    of its sewage plant through the sale of sewer permits that were
    available on an equal basis to all developers.       
    Id. at 415-17.
    Medford’s sewer ordinance gave property owners “the option to
    purchase connection permits before obtaining municipal land use
    approvals.”   
    Id. at 416.
       The plaintiff bank declined the
    opportunity to do so.     
    Id. at 417.
       Later, when the plaintiff
    wanted to develop its property, its request for several sewer
    32
    permits was denied because all permits had been allocated.       
    Id. at 418.
      The plaintiff then instituted a lawsuit, challenging
    the validity of the ordinance and seeking an order directing
    Medford to repurchase unused permits.5     
    Ibid. Our focus in
    First Peoples was whether the ordinance
    articulated “adequate standards to guide the exercise of
    municipal discretion when considering the repurchase of
    permits.”    
    Id. at 421.
      Ultimately, we concluded that the
    “ordinance, although not exquisitely drafted, contain[ed]
    sufficient standards to withstand the [plaintiff’s] challenge.”
    
    Id. at 422.
      We gleaned from various clauses of the ordinance,
    including one that provided that “reservation of capacity is not
    irrevocably committed to a proposed user,” that Medford “when
    exercising its right of repurchase, must consider the public
    health, safety, and welfare, a reasonable and equitable
    allocation of costs, and the allowance of moderate growth.”       
    Id. at 422-23.
       Importantly, we considered Medford’s sewer ordinance
    to be far from a model ordinance.      
    Id. at 423.
      We stated that
    it would better serve both the Township and
    property owners if it contained more specific
    standards defining the conditions under which
    permits would be subject to repurchase. Such
    standards could appropriately include the
    criteria the municipality will apply when
    exercising its rights to repurchase permits
    5 The plaintiff also unsuccessfully sought an order requiring
    Medford to expand the capacity of the sewage plant. 
    Id. at 418,
    423-24.
    33
    and a formula for more closely correlating the
    issuance of building permits and sewer
    permits.   In the absence of such standards,
    the municipality runs the risk that in another
    case the ordinance might be found vulnerable
    as applied.
    [Ibid.]
    Significantly, in First Peoples, no one disputed that “the
    Township must retain sufficient control to assure that sewer
    permits are either used or repurchased so that others may use
    them.”   
    Id. at 420.
      We declared that “[w]ithout an adequate
    repurchase provision, the ordinance could result in the improper
    delegation of access to the sewer system to private landowners
    who, by purchasing permits, could prevent other owners from
    developing their land.”    
    Id. at 420-21.
    We nevertheless rejected the plaintiff’s as-applied
    challenge to the ordinance, finding nothing to suggest that
    Medford had “acted arbitrarily in deciding whether to exercise
    its repurchase option.”    
    Id. at 423.
      We specifically noted that
    Medford “had repurchased approximately fifteen permits and that
    it was considering the repurchase of others,” and that the
    record did not indicate that the plaintiff “had made demand on
    Medford to repurchase specific permits.”      
    Ibid. For those reasons,
    we viewed the plaintiff’s “attack on the repurchase
    provision as essentially facial.”     
    Ibid. 34 With those
    principles in mind, we now turn first to the facial
    challenge to Readington’s sewer allocation ordinance and then its
    application of the ordinance to this case.
    V.
    A.
    We reject plaintiff’s challenge to the ordinance itself.
    We find that Readington’s sewer allocation ordinance provides
    “adequate standards to guide the exercise of municipal
    discretion when considering the repurchase of permits.”     First
    
    Peoples, supra
    , 126 N.J. at 421.
    First, the ordinance sets temporal limits on the right of a
    property owner to keep unused sewer capacity.   The Township has
    the discretion to terminate an allocation agreement and
    repurchase capacity if a developer (1) does not make application
    for development approvals within two years of having received
    sewer capacity or (2) has not begun construction within two
    years after having received preliminary approval.    Readington
    Code, supra, § 187-26C.    Second, the ordinance provides that an
    allocation agreement “may be extended upon application to the
    Township if there is a showing of good cause, at the option of
    the Township Committee.”     
    Ibid. As was true
    in First 
    Peoples, supra
    , the ordinance here was
    not “exquisitely drafted.”    
    See 126 N.J. at 422
    .   Nevertheless,
    we must “‘liberally construe[]’” the ordinance in favor of its
    35
    validity.   Rumson 
    Estates, supra
    , 177 N.J. at 351 (quoting N.J.
    Const. art. IV, § 7, ¶ 11).   We presume that the ordinance’s
    drafters intended certain practical considerations to be taken
    into account by the Township Committee in exercising its
    discretion whether to terminate an allocation agreement or
    extend one based on good cause.    Such considerations would
    include (1) the length of time a landowner has possessed unused
    sewer capacity, (2) the development plans of the landowner to
    tap some or all of the unused capacity and the imminence of that
    happening, (3) the complexity of the development project and the
    importance of the project to the community, (4) whether the
    economy has retarded economic development, (5) proposed
    development projects by others that cannot proceed because of
    unavailability of sewer capacity and the importance of those
    projects to the community, and (6) any other relevant factors.
    Plans for the treatment of wastewater is a critical
    component of any development project, for without sewer approval
    no development project can go forward.     Field v. Franklin Twp.,
    
    190 N.J. Super. 326
    , 328-35 (App. Div.), certif. denied., 
    95 N.J. 183
    (1983).   This ordinance, as written, in no way suggests
    that the Township as a matter of law has delegated its authority
    to control land use -- and more specifically to control access
    to sewer capacity -- to private parties.    The ordinance suggests
    36
    that access to sewer capacity is to be managed by the Township
    Committee for the general welfare of the community.
    We conclude that the sewer allocation ordinance -- when
    read with the commonsense considerations implied within the
    enactment -- provides adequate guidelines for the Township to
    exercise its discretion whether and when to repurchase sewer
    capacity.
    We next turn to plaintiff’s argument that the ordinance, as
    applied, violates the dictates of First Peoples.
    B.
    In First 
    Peoples, supra
    , we did not find evidence that
    Medford had acted arbitrarily in deciding whether to exercise
    its option to repurchase sewer 
    capacity. 126 N.J. at 423
    .   That
    was so because the “Township had repurchased approximately
    fifteen permits” and “was considering the repurchase of others”
    and because the plaintiff had not demanded that Medford
    “repurchase specific permits.”     
    Ibid. We noted that
    had Medford
    acted arbitrarily, “a court might direct it to exercise its
    option to repurchase.”     
    Ibid. That scenario, envisioned
    by our
    Court, presents itself here.
    Based on the summary-judgment record before us, it is
    apparent that, despite its ordinance, Readington maintains a
    blanket policy of not repurchasing unused sewer capacity
    allocated to developers.    The Chairman of the Sewer Advisory
    37
    Committee told plaintiff’s attorney that “the policy of this
    board and the policy of the Township Committee has been not to
    take any capacity back.”   The Chairman’s statement reinforced
    the Township attorney’s earlier communication to plaintiff that
    the Township Committee did “not wish to terminate any of its
    existing agreements.”
    Approximately one-third of Readington’s entire sewer
    capacity -- 322,009 gpd -- is not in use.    That unused capacity
    is largely in the hands of a relatively small number of private
    entities.   Currently, Merck has 141,900 gpd and Bellemead has
    66,060 gpd of unused sewer capacity -- capacity allocated for
    more than a decade but still not in use.    Both companies
    received approvals for their development projects in the late
    1980s.   That sewer capacity was allocated by contracts to
    private entities that financed the plant expansion project and
    was paid for at considerable expense cannot be the end of the
    analysis.   Otherwise, the ordinance requiring Readington to
    exercise its discretion in recapturing sewer capacity would be
    meaningless.   Those entities that purchased unused capacity did
    so knowing that the ordinance placed potential temporal limits
    on how long that capacity could be held in reserve and gave the
    Township the authority to recapture unused capacity for
    distribution to developers with projects ready to go.     The
    ordinance made clear that sewer rights were not to be held in
    38
    perpetuity.    That other landowners did not participate in
    purchasing capacity to help finance the plant expansion may
    indicate nothing more than that they did not have a need for
    sewer capacity at the time.
    The Township Committee invited plaintiff to present “a
    conceptual plan” of its development project to the appropriate
    land-use board, adding “that the application would be
    conditioned on obtaining a suitable solution to wastewater.”
    But given the Township’s stated policy not to recapture sewer
    capacity, the presentation of that plan would have constituted
    an exercise in futility.     A developer may be hesitant to expend
    great sums of money to secure preliminary approvals for a
    development project that has no prospect of securing necessary
    sewer capacity.    Plaintiff can hardly be faulted for deciding
    that judicial relief was the only viable option.
    Plaintiff identified the entities that were holding unused
    capacity and contacted approximately fifteen of those entities,
    inquiring whether they would relinquish some of their unused
    capacity.     The opposition to this lawsuit is the ultimate
    testament to defendants’ unwillingness to freely give back any
    of their unused capacity.
    The Appellate Division placed on plaintiff the burden of
    showing that defendant developers were acting “without good
    cause for delay” by not voluntarily surrendering their sewer
    39
    rights for the fair value offered by plaintiff.    But that
    defeats the purpose of the ordinance and of the policy of the
    MLUL, which is to have the Township exercise its decision-making
    authority in land-use matters.   One of the objectives of the
    sewer allocation ordinance was to ensure that the Township
    exercised discretion, when appropriate, to recapture unused
    capacity and to avoid “the improper delegation of access to the
    sewer system to private landowners who, by purchasing permits,
    could prevent other owners from developing their land.”       See
    First 
    Peoples, supra
    , 126 N.J. at 420-21.   The MLUL requires
    that townships exercise their authority to develop lands “in a
    manner which will promote the . . . general welfare,” N.J.S.A.
    40:55D-2(a), and the repurchase provision of the sewer
    allocation ordinance was a means to that end.     We concur with
    the trial court that the Township’s obligation to terminate
    agreements, when appropriate, was not dependent on whether
    plaintiff could “beg, borrow or cadge capacity from others.”
    The Township’s no-buy-back policy has rendered the ordinance
    toothless, and, as the trial court determined, “functioned as a
    de facto moratorium on any development which requires sewerage.”
    We substantially agree with the conclusions that Judge
    Buchsbaum reached from the summary-judgment record.    In
    declining to recapture unused sewer capacity for plaintiff’s
    project, the Township in its resolution incorporated by
    40
    reference, wholesale and uncritically, the arguments of the
    developer defendants.   That approach suggests that the Township
    had effectively delegated its land-use authority to private
    entities.   The resolution failed to analyze development by
    development why none of the unused capacity -- after years of
    lying idle -- could be recaptured.
    The resolution also failed to analyze which developments,
    if any, fall under the dictates of the Permit Extension Act,
    N.J.S.A. 40:55D-136.1 to -136.6.       The Permit Extension Act tolls
    the expiration date of certain land-use approvals for a period
    of time “due to the present unfavorable economic conditions.”
    N.J.S.A. 40:55D-136.2(m).   The Act covers “an agreement” between
    a developer and municipality “for the use or reservation of
    sewerage capacity.”   N.J.S.A. 40:55D-136.3.      Admittedly, the
    Permit Extension Act would take precedence over an ordinance and
    therefore might limit the Township’s discretion.
    Last, and most significantly, the resolution did not give a
    “reasoned explanation” for the Township’s failure to exercise
    discretion, as required by its own ordinance.       The Township and
    defendant developers cannot contract away their obligation to
    comply with the law -- whether it is First Peoples, the MLUL, or
    the Readington sewer ordinance.    Private parties do not have a
    right to hoard unused sewer capacity indefinitely and therefore
    effectively impose a moratorium on development.       As a best
    41
    practice, we suggest that the Township maintain updated records
    of the unused capacity held by private parties so that it can
    exercise its discretion, when necessary, with current
    information.   In addition, a property owner seeking capacity
    should have access to data that is necessary to making an
    informed decision whether to proceed with a development plan.
    We adopt the thoughtful approach taken by Judge Buchsbaum.
    We order the Township Committee, within ninety days, to
    undertake a critical review of the unused capacity identified by
    plaintiff and to determine whether any such capacity can be
    recaptured from defendants to satisfy plaintiff’s development
    needs.   The Committee should consider the factors outlined
    earlier to guide the exercise of its discretion.     We add that if
    a property owner, presently holding a substantial amount of
    unused capacity, has moved its business operations to another
    municipality and there is no realistic prospect that approvals
    previously acquired will result in a project coming to fruition,
    that factor must be given significant weight in deciding whether
    to recall capacity.
    Last, we address when a party has a sufficient stake to
    purchase unused capacity.    Needless to say, the Township should
    not recapture unused sewer capacity from one party and allow its
    sale to another party that is unlikely to put that capacity to
    use in the near future.     A party that has received preliminary
    42
    site plan approval obviously will have a stake in requesting
    capacity, but we are loath to impose that as the necessary test
    because of the significant costs involved in securing such an
    approval.   Here, the Township offered plaintiff the opportunity
    to present a concept plan to the appropriate board.6   If such a
    plan is satisfactory, and assuming that sufficient unused
    capacity is available, then the Township could commence the
    process of recapturing capacity at plaintiff’s expense and hold
    that capacity in escrow, contingent on plaintiff securing all
    necessary approvals.   If plaintiff does not secure the necessary
    approvals, then the Township can sell that capacity to another
    developer that needs it for an imminent project, or resell it to
    the original owner.
    VI.
    For the reasons given, we affirm the Appellate Division’s
    judgment upholding the trial court’s dismissal of plaintiff’s
    6 The concept plan suggested by the Township resembles the
    informal review available under N.J.S.A. 40:55D-10.1. A
    planning board is permitted to conduct “an informal review of a
    concept plan for a development for which the developer intends
    to prepare and submit an application for development.” N.J.S.A.
    40:55D-10.1. An applicant can “benefit from the exchange of
    ideas and expression of the board’s preferences” without having
    to “expend[] the significant amounts of money required in the
    preparation of development plans and applications.” 36 New
    Jersey Practice, Land Use Law § 13.10 (David J. Frizell & Ronald
    D. Cucchiaro) (3d ed. 2014). However, importantly, neither the
    board nor the applicant are bound by the discussions. N.J.S.A.
    40:55D-10.1. An applicant must still proceed through the
    ordinary approval process.
    43
    facial challenge to the Readington Township sewer allocation
    ordinance.   We reverse, however, the Appellate Division’s
    judgment rejecting the trial court’s determination that the
    ordinance, as applied, violates principles espoused in First
    Peoples.   The Township Committee shall undertake a critical
    review of the unused capacity identified by plaintiff and
    determine within ninety days whether any capacity can be
    recaptured to satisfy plaintiff’s development needs.   We remand
    to the trial court for proceedings consistent with this opinion.
    CHIEF JUSTICE RABNER and JUSTICES PATTERSON, FERNANDEZ-
    VINA, and SOLOMON join in JUSTICE ALBIN’s opinion. JUSTICE
    LaVECCHIA and JUDGE CUFF (temporarily assigned) did not
    participate.
    44
    SUPREME COURT OF NEW JERSEY
    NO.    A-63                                     SEPTEMBER TERM 2013
    ON CERTIFICATION TO              Appellate Division, Superior Court
    388 ROUTE 22 READINGTON
    REALTY HOLDINGS, LLC,
    Plaintiff-Appellant,
    v.
    TOWNSHIP OF READINGTON, ET AL.,
    Defendants-Respondents,
    and
    MERCK SHARP & DOHME CORP.,
    f/k/a MERCK & CO., INC.,
    Defendant-Respondent,
    and
    RAMYZ TADROS, ET AL.,
    Defendants.
    DECIDED               May 5, 2015
    Chief Justice Rabner                           PRESIDING
    OPINION BY                   Justice Albin
    CONCURRING/DISSENTING OPINIONS BY
    DISSENTING OPINION BY
    AFFIRM IN PART/
    REVERSE IN
    CHECKLIST
    PART/
    REMAND
    CHIEF JUSTICE RABNER                         X
    JUSTICE LaVECCHIA                   --------------------   --------------------
    JUSTICE ALBIN                                X
    JUSTICE PATTERSON                            X
    JUSTICE FERNANDEZ-VINA                       X
    JUSTICE SOLOMON                              X
    JUDGE CUFF (t/a)                    --------------------   --------------------
    TOTALS                                       5