ALAN O'CONNELL VS. MR. JOHN (L-1222-17, CAMDEN COUNTY AND STATEWIDE) ( 2021 )


Menu:
  •                                 NOT FOR PUBLICATION WITHOUT THE
    APPROVAL OF THE APPELLATE DIVISION
    This opinion shall not "constitute precedent or be binding upon any court ." Although it is posted on the
    internet, this opinion is binding only on the parties in the case and its use in other cases is limited. R. 1:36-3.
    SUPERIOR COURT OF NEW JERSEY
    APPELLATE DIVISION
    DOCKET NO. A-1760-19
    ALAN O'CONNELL and
    LINDA O'CONNELL, his wife,
    Plaintiffs-Respondents,
    v.
    MR. JOHN,
    Defendant,
    and
    NETWORK CONSTRUCTION
    COMPANY, INC.,
    Defendant-Appellant.
    __________________________
    Argued May 26, 2021 – Decided June 25, 2021
    Before Judges Whipple, Rose and Firko.
    On appeal from the Superior Court of New Jersey, Law
    Division, Camden County, Docket No. L-1222-17.
    Michael J. Marone argued the cause for appellant
    (McElroy, Deutsch, Mulvaney & Carpenter, LLP,
    attorneys; Michael J. Marone and Richard J. Williams,
    Jr., of counsel and on the briefs).
    Michael A. Galpern argued the cause for respondents
    (Javerbaum Wurgaft Hicks Khan Wikstrom & Sinins,
    PC, attorneys; Eric G. Kahn, of counsel and on the
    brief; Annabelle Steinhacker, on the brief).
    PER CURIAM
    Defendant Network Construction Company, Inc. appeals the Law
    Division's December 6, 2019 order entering judgment and awarding plaintiffs,
    Alan O'Connell and Linda O'Connell, $2,522,881.53, inclusive of pre-judgment
    interest, in this construction accident case tried before a jury. Defendant also
    appeals the denial of its motion for a new trial. We affirm.
    I.
    We discern the following facts and procedural history from the record on
    appeal. On April 1, 2015, plaintiff Alan O'Connell 1 worked as a tile finisher for
    a subcontractor, Baumgardner Floor Coverings (BFC), on a construction project
    in Galloway Township, managed by defendant, the general contractor. As of
    that date, plaintiff had already been working for three or four days in a building
    1
    We refer to Alan O'Connell as "plaintiff" in this opinion unless otherwise
    noted.
    A-1760-19
    2
    at the jobsite and had been using temporary portable toilets 2 located near an exit
    in the middle of the building.
    However, on April 1, those toilets were blocked off due to newly poured
    concrete, leaving only one available portable toilet located outside, several
    hundred yards away against the building's exterior, and inside a narrow planting
    bed. Plaintiff testified that there was an eighteen-inch space between the door
    of the portable toilet and the curb framing the edge of the planting bed. No one
    had measured the height or width of the curb. On the opposite side of the curb
    was a parking lot where there was a small wooden step or ramp that workers
    with wheelbarrows would lift up and use to dispose of debris in an adjacent
    dumpster. When the door of the portable toilet was fully opened, it could hit the
    dumpster.
    That day, plaintiff had no difficulty stepping from the parking lot over the
    curb to enter the portable toilet. He had enough room to open the door without
    having to step into the planting bed. Upon exiting, plaintiff opened the door,
    stepped out, and was simultaneously looking for a front-end loader that he
    previously observed in the parking lot before entering the portable toilet. At
    2
    In this opinion, we refer to portable toilet as "porta john," "porta-potty," "port-
    o-potty," and "toilet" interchangeably.
    A-1760-19
    3
    that moment, the heel of his boot struck the curb, causing him to trip, fall, and
    twist his right knee.
    Dr. Matthew Pepe, an orthopedic surgeon, diagnosed plaintiff as suffering
    from complex tears of the medial and lateral menisci and a neuroma of the right
    knee. After undergoing knee injections and five surgeries, Dr. Pepe opined that
    plaintiff would never work again as a tile finisher; would always have pain and
    limited function; and eventually would require knee replacement surgery.
    On March 21, 2017, plaintiffs filed a negligence complaint against
    defendant and co-defendant Mr. John, seeking damages resulting from plaintiff's
    accident at the construction site. Plaintiff's wife also asserted a claim for loss
    of consortium. Defendant and Mr. John filed answers to the complaint. Prior
    to trial, plaintiffs' claims against Mr. John were settled and dismissed.
    The case was tried over eight days from October 21 to November 1, 2019.
    The parties stipulated that plaintiff's past medical expenses totaled $101,980.79.
    Plaintiff's wife testified he is in pain on a daily basis and that his injuries
    substantially worsened his life and their lives together.      Plaintiffs' liability
    expert, Dr. Stephen A. Estrin, was qualified as an expert in Occupational Safety
    A-1760-19
    4
    and Health Administration (OSHA) and construction safety. 3 Estrin opined that
    as the general contractor, defendant was solely responsible for plaintiff's
    accident and injuries under three theories: (1) failing to meet federal OSHA
    requirements; (2) failing to meet the obligations of defendant's prime
    construction contract; and (3) failing to meet the obligations of the industry's
    standard practice to maintain a jobsite free of obvious tripping hazards that could
    cause injury.4
    Specifically, Estrin first testified that the OSHA construction regulations
    found in 
    29 C.F.R. § 1926
     placed sole responsibility on the general contractor
    for the safety of all workers at a jobsite. 5 That is, defendant, as a general
    3
    In April 2019, defendant moved to bar Estrin's testimony and report. On
    October 21, 2019, the trial court denied defendant's motion but permitted
    defendant to renew its motion at the time of trial.
    4
    During oral argument, counsel for the parties could not confirm whether
    defendant was cited for any OSHA violations or if an OSHA hearing was
    conducted.
    5
    We note that OSHA's general safety and health provisions for construction
    and general industry, 
    29 C.F.R. § 1926.20
    , were amended in February 2020
    following this trial. The summary of the amendments states: "These revisions
    do not affect the substantive requirements or coverage of the standards, do not
    modify or revoke existing rights or obligations, and do not establish new rights
    or obligations." OSHA Standards and Regulations; Corrections, 
    85 Fed. Reg. 8726
     (Feb. 18, 2020) (Summary).
    A-1760-19
    5
    contractor controlled by a prime construction contract, was ultimately
    responsible under OSHA standards for the safety of all workers who came onto
    the construction site.
    Estrin next testified about defendant's prime construction contract. 6 An
    enlarged copy was shown to the jury. It read in part:
    § 3.3 SUPERVISION               AND   CONSTRUCTION
    PROCEDURES
    § 3.3.1 The [c]ontractor shall supervise and direct the
    [w]ork, using the [c]ontractor's best skill and attention.
    The [c]ontractor shall be solely responsible for, and
    have control over, construction means, methods,
    techniques, sequences and procedures and for
    coordinating all portions of the [w]ork under the
    [c]ontract, unless the [c]ontract [d]ocuments give other
    specific instructions concerning these matters.
    Estrin stated that those general contract conditions came from the
    industry-wide standard legal forms prepared by the American Institute of
    Architects (AIA) for construction projects and conferred sole liability on
    defendant for jobsite worker safety. He explained:
    [T]he general conditions of the contract in this case are
    [taken from] an AIA, . . . general conditions to the
    prime contract. It's the AIA 201-20[0]7. They have
    within it a lot of stuff, but the two parts of it that are
    6
    Plaintiff describes the contract as defendant's "contract with [p]laintiff's
    employer." However, Estrin was speaking about the prime construction contract
    "between Barrett, the owner of the property" and defendant.
    A-1760-19
    6
    extremely important are Article 3 Contractor,
    specifically . . . section 3.3.1, which states, in sum and
    substance, that the contractor shall apply his best skill
    and ability to the work and that he is solely responsible
    for construction means and methods, techniques,
    procedures, sequencing, and coordination of the work.
    Now, construction means and methods in and of
    themselves, by definition, include job site safety.
    However, because the writers of that general conditions
    [sic], which go all the way back to 1992, have a specific
    section which deals with personal safety and property.
    And that's Article 10. Article 10.2 deals specifically
    with workers.
    ....
    That's the safety article of the general conditions.
    It deals with personal and property protection.
    Estrin further stated that Section 3.3.1 of the AIA's standard form
    conditions and of defendant's signed contract made the general contractor "one
    hundred percent responsible. No matter what you subcontract out, whatever you
    do, you are solely responsible, one hundred percent, for your direct employees
    and your subcontractors . . . ." Under Section 3.3, the general contractor also
    was solely responsible for "housekeeping," which meant "[h]ow you set
    equipment up on the job, how you set temporary toilets up on the job, all of that
    is housekeeping." Thus, in addition to OSHA regulations making defendant
    A-1760-19
    7
    responsible for everyone on the jobsite, defendant had signed a "contractual
    promise to be solely responsible for the safety and the housekeeping ."
    Next, Estrin testified that defendant was liable for all of plaintiff's injuries
    because it failed to meet the obligations of the industry's standard practice to
    maintain a jobsite free of obvious tripping hazards that could cause injury.
    Specifically, defendant had failed to exercise reasonable care in the portable
    toilet's positioning, which created an obvious tripping hazard.          In addition,
    Estrin attributed responsibility to defendant's representative, the construction
    site supervisor, superintendent, John L. Carman, and pointed to defendant's
    safety manual.
    First, according to the interrogatories submitted by defendant's president,
    Carman was the person responsible for directing placement of the portable toilet
    on the jobsite. Plaintiff's counsel then read Carman's deposition testimony to
    the jury:
    Q. Did you ever receive any OSHA training?
    A. No.
    Q. Before this accident ever happened either on this job
    site or at any other job site, you had [sic] ever seen a
    portable toilet near a curb?
    A. Specifically no, but I've seen them a lot of different
    places.
    A-1760-19
    8
    Q. But you have to move them and put them in an area
    on the job site that [is] not only convenient, but [is] as
    safe as possible. Is that correct?
    A. That's correct.
    Q. And, sir, if you look at the location of the portable
    toilet there, is there any reason why that door has to
    open out facing the curb?
    A. No. It could have been spun the other way.
    Q. However, nothing would prevent that . . . portable
    toilet . . . [f]rom being spun [ninety] degrees, though,
    would it?
    A. Not that I'm aware of.
    Q. And if it was spun [ninety] degrees, someone could
    walk out and take multiple steps on a flat surface; right?
    A. Yes.
    Q. Sir, I think we already went over it, but can we agree
    that someone shouldn't step out of a portable toilet and
    onto a curb; right?
    A. Yes.
    Q.    And we already said that [defendant] was
    responsible for the overall safety of the job site; right?
    A. That's true.
    Q. Do you agree with me that locating a place for
    portable toilets should not create any unsafe or tripping
    hazards to exposed workers?
    A-1760-19
    9
    A. I agree.
    Q. And we agree that someone should not be hurt
    stepping out of a portable toilet and onto a curb;
    correct?
    A. Yes.
    Based on this deposition testimony, Estrin concluded that Carman was not
    a "competent person" and that defendant did not have any competent person
    supervising the jobsite. According to Estrin, a "competent person" would have
    noticed there were tripping hazards near the portable toilet and corrected them.
    He elaborated:
    [A] competent person, by definition under OSHA, at
    [29 C.F.R. §] 1926.32(f) states that it is an individual
    who is capable of determining existing and predictable
    hazards in the workplace and has the authority to take
    immediate correction when those hazards are
    identified.
    So now we start with you're going to put a porta
    john in a location. That's a predictable hazard if that
    location has a curb in front of the porta john access and
    egress. That's predictable. So you don't put it there to
    begin with. If, for some reason, you decide to put it
    there, you make a mistake, well now it's an existing
    hazard.
    This unit was in place approximately four weeks
    prior to [plaintiff]'s accident. They -- and a competent
    person is required under 1926.20(b)(2) to make regular
    and frequent inspections of the job site, which Mr.
    A-1760-19
    10
    Carman testified that he did. Therefore, he had to check
    this site out not only for a porta john, but for the
    dumpster.
    Now, Mr. Carman . . . has . . . no training to
    identify these kind of hazards under OSHA, because he
    was never trained by his employer. Therefore, if he had
    been competent, he would have picked it up before it
    was placed and definitely after it was placed, and well
    before [plaintiff] was subjected to the unsafe condition
    of the porta john or the temporary toilet behind a curb.
    In fact, based on his own OSHA and construction knowledge and experience,
    Estrin asserted to make the site safer, defendant only had to "[t]urn the toilet
    [ninety] degrees so that the long flat dirt area was where the door opened up to
    get in[gress] or egress from. Then you could just walk down that way and then
    it just flares out from there and there's no problem."
    Second, Estrin testified about defendant's safety manual. That document
    stated:
    [T]he program contained in this manual shall be
    established through accomplished -- a series of bullet
    points.
    The first is "To protect and promote the health
    and safety of employees by integrating safety into our
    daily operations."
    Second, "To minimize employee injuries by
    providing safe and healthful work environments,
    preventing unsafe acts, and controlling exposures to
    health and safety hazards on all jobs."
    A-1760-19
    11
    Third, "To assure all managers and employees
    have received orientation instruction and training in
    health and safety."
    ....
    Five, "To comply with pertinent regulatory
    obligations."
    And six, "Assure the safety, health and
    environmental and loss control programs are given the
    proper priority and attention and are achieving the
    required results."
    Applying those bullet points, Estrin opined that defendant had not met the
    policies espoused in its own safety manual because it had not: (1) complied with
    OSHA standards; (2) trained Carman; or (3) provided a safe and healthful
    environment for subcontractors and employees like plaintiff. Estrin explained
    that the second bullet point affected defendant's employees and all outside
    subcontractors and their employees on the sites defendant controlled as the
    general contractor. The fifth bullet point meant federal and/or state OSHA
    standards and regulations and other laws. Thus, Estrin concluded that:
    pursuant to the contract between Barrett, the owner of
    the property, and [defendant], and the OSHA
    regulations which established the fact that the general
    contractor [defendant] is 100 percent responsible for
    job site worker safety, the proximate cause of the
    accident is [defendant's] failure to have done what was
    necessary to ensure [plaintiff]'s safety; that he had a
    A-1760-19
    12
    [jobsite] free of a tripping hazard and going to a
    temporary toilet is part of the [jobsite] as important as
    any other part of the [jobsite], and it be free of a tripping
    hazard, and that was not done. That they had more than
    adequate time to have identified the tripping hazard and
    to have corrected it as they were required to do if in fact
    they had a competent person on the job in the form of
    their superintendent, Mr. Carman. He was not an
    OSHA qualified competent person, and therefore, was
    unable to do what he was required to do pursuant to the
    contract which required them to be 100 percent
    responsible for not only construction means and
    methods, but also the safety of all workers on the job.
    And the OSHA responsibility is exactly the same.
    Further, Estrin testified that Mr. John, which had an oral contract with
    defendant, was not liable for plaintiff's injuries because its employees only had
    the responsibilities to service, clean and sanitize the portable toilets on "a
    weekly basis" and "to inform the construction superintendent on a job site if they
    discover anything that they feel is unsafe." Also, Mr. John was not responsible
    for the toilet's improper placement that resulted in a tripping hazard. Estrin
    emphasized:
    Pursuant to [Mr. John's] policy and their
    standards or procedures, very simply that if the
    individual who delivers the toilet is told to place it in a
    location in which that individual feels it is unsafe, he is
    to tell the superintendent on the job not to place it there
    or to move it.
    ....
    A-1760-19
    13
    If in fact he does not get a positive response from
    the superintendent, he's to call back to the office and
    talk to his superior, and his superior there would then
    go forward and try and work out a reasonable solution
    so everybody was happy.
    Additionally, Estrin testified that BFC was not liable for plaintiff's
    injuries. He explained, citing OSHA's 
    29 C.F.R. § 1926.20
    (b)(2), that BFC was
    responsible for "provid[ing] a safe workplace free of recognized hazards,
    tripping hazard[s], which would cause injury to a worker," and for "mak[ing]
    regular and frequent inspections of the job site by a competent person to
    determine the predictable and existing hazards on the job site."7 However, there
    was no evidence that BFC or any of its employees had ever worked in the area
    where this particular portable toilet had been located before plaintiff's fall on
    April 1, 2015.
    Estrin also testified that plaintiff:
    did not in any manner contribute to his accident because
    for example, under the OSHA regulations, he has a
    responsibility to comply with those regulations, if he
    was trained. He was trained in the OSHA regulations,
    but it has to be an issue of unforeseeable worker
    misconduct. There was no misconduct here.
    7
    
    29 C.F.R. § 1926.20
    (b)(2) states: "Accident prevention responsibilities . . .
    Such programs shall provide for frequent and regular inspections of the job sites,
    materials, and equipment to be made by competent persons designated by the
    employers."
    A-1760-19
    14
    This man went to a temporary toilet because the
    temporary toilets which were safe for him to access and
    egress on the other side of the building where he was
    working were not available to him because the general
    contractor had sequenced a series of concrete pours and
    had not seen fit to move the portable or temporary
    toilets to another location, forcing [plaintiff] to go into
    the building, walk through the building, go down the
    stairs, and go to an area which he had never experienced
    before. And it had a tripping hazard. It had a dumpster,
    so he had to watch out for moving equipment, and to
    see that he wasn't run over or hit by falling objects. So
    that is not something that he would have to do.
    He does not have a responsibility to investigate
    or inspect the [jobsite] . . . .
    Based on those reasons, Estrin concluded that defendant was solely liable for
    plaintiff's accident and injuries.
    During cross-examination, Estrin testified that plaintiff did not trip
    because of the dumpster opening out or blocking his view; plaintiff tripped only
    because of the curb. According to Estrin, plaintiff "opened the door and took
    his one step outward" and "his he[e]l caught that curb."
    Nevertheless, Estrin agreed that Mr. John's employees had serviced the
    portable toilet four times before April 1; should have noticed it was in an unsafe
    placement; and should have advised Carman.              Although Mr. John was
    responsible under OSHA for the safety of its own employees, there were no
    OSHA safety standards governing portable toilets or their placements,
    A-1760-19
    15
    recommended placements or servicing. Instead, 
    29 C.F.R. § 1926.51
    (d) only
    required that toilets shall be provided for employees, and then addressed the
    types and numbers of toilet facilities needed on a jobsite.
    Defense counsel also cross-examined Estrin on OSHA's Multi-Employer
    Citation Policy (MECP), which provided "that any employer on a job site that
    has the ability to abate a hazard or prevent it, has the duty to do so." The MECP,
    according to Estrin, created four categories of employers at a multi-employer
    jobsite: (1) the controlling employer; (2) the creating employer; (3) the
    correcting employer; and (4) the exposing employer. Estrin clarified:
    There's the controlling employer. That is the
    individual who by function of either contract or
    agreement other than a written contract has overall
    responsibility for all work on the job site to include
    safety.
    There is the creating employer who is that
    employer who actually creates the volatile solution
    condition, like the tripping hazards, the unsafe
    condition or if it's a worker's involvement, an unsafe
    act.
    There is the correcting employer who is the
    employer who has been tasked with correcting the
    hazard, and on certain big jobs there are firms that are
    hired to construct the safety aspects of all of the work.
    It may be a carpentry firm putting up guardrails and that
    type of thing.
    A-1760-19
    16
    And the final one is the exposing employer. That
    is the employer who actually sends his worker in harm's
    way, is the easy way to put it.
    Although Estrin categorized BFC as plaintiff's "direct employer," and
    therefore "directly responsible" for plaintiff's health, safety and well -being, he
    opined that defendant was "solely liable" for plaintiff's accident and inju ries.
    Estrin did not believe BFC was "expected to" determine where portable toilets
    were going to be used on the site and whether those were appropriately placed
    for its employees.
    Estrin further explained that "the multi[-]employer [jobsite] policy by
    OSHA is unenforceable." The MECP was "not a standard and ha[d] no bearing,
    and cannot be enforced against anyone in the industry." He asserted that the
    MECP was rejected by the Occupational Safety and Health Review Commission
    (OSHRC) and the Circuit Courts of Appeals, because "the controlling employer
    . . . may have less than that of the exposing employer in terms of responsibility
    for worker safety." The OSHRC was "the administrative review commission of
    OSHA . . . It is a separate and independent body and has the force of law."
    Nevertheless, when defense counsel confronted Estrin with language from
    one of the OSHA's general interpretation letters on the MECP, he agreed that it
    stated:
    A-1760-19
    17
    "A controlling employer," which in this case is
    [defendant], "must exercise reasonable care to prevent
    and detect violations on the site. The extent of the
    measures that a controlling employer must implement
    to satisfy this duty of reasonable care is less than what
    is required of an employer with respect to protecting its
    own employees. This means that the controlling
    employer is not normally required to inspect for
    hazards as frequently or to have the same level of
    knowledge of the applicable standards or trade
    expertise as the employer it has hired."
    However, Estrin explained that an administrative interpretation letter,
    even one from OSHA, had "no bearing on any enforcement policy" and "no
    regulatory authority." It was not fact specific; for example, it did not discuss
    what would happen if the general contractor had signed a contract agreeing to
    be solely responsible for safety on the project.
    Lastly, Estrin acknowledged that there were other construction standards
    that governed portable bathrooms on construction sites, such as the American
    National Standards Institute's (ANSI)8 standards, trade or professional
    8
    According to its website, ANSI "is a private, non-profit organization that
    administers and coordinates the United States voluntary standards and
    conformity assessment system. Founded in 1918, the Institute works in close
    collaboration with stakeholders from industry and government to identify and
    develop standards- and conformance-based solutions to national and global
    priorities." About ANSI, ANSI, https://www.ansi.org/about/introduction (last
    visited June 9, 2021).
    A-1760-19
    18
    association standards like the Portable Sanitary Association International and
    the American Association of General Contractors, and that there were
    construction standards promulgated by local municipalities. However, none of
    those other standards, like OSHA, provided any guidance on portable toilet
    placement according to Estrin because placement was "up to the general
    contractor and [it] has the ability to make that decision based upon the actual
    conditions that exist on the site at the time [it] places the toilet. . . ." Moreover,
    Estrin posited that portable toilet placement was based on teaching and
    experience.
    Chana Goldsmith, plaintiffs' expert in nursing and lifetime care planning,
    testified that plaintiff's future care would cost $462,339. Plaintiffs' vocational
    expert, Sonya Mocarski, opined that plaintiff suffered "[a] complete and total
    loss of earning capacity." Andrew Verzilli, plaintiffs' economic expert, testified
    that plaintiff's lost wages and future financial losses was approximately
    $1,936,000.
    Steven L. Bisbee testified as the defense expert. He is OSHA certified
    and has over thirty years' experience in the portable toilet rental industry. Bisbee
    testified that Mr. John would have completely relied on "[t]he customer" or
    defendant's construction site contact for directions on portable toilet placement.
    A-1760-19
    19
    He explained that if the site contact instructed the driver to place a portable toilet
    in a hazardous position, the driver would encourage the contact to relocate the
    toilet. If it was not moved, the driver was trained to submit a formal "relocate
    ticket" to Bisbee and to the customer or general contractor.
    After reviewing the accident site photos, Bisbee opined that there was
    nothing wrong or unsafe with placement of the portable toilet. Portable toilets
    were usually placed "near a dumpster or a construction trailer, up against a
    building, to put them out of the way." He and his drivers had placed "thousands"
    in those "normal" areas.
    On cross-examination, Bisbee admitted that he was concerned only with
    two things: whether a portable toilet was placed within the length of a hose so
    that his workers could clean the unit; and whether the unit was placed on a level
    surface so users could walk out onto level ground and avoid tripping.
    Michael Cronin, who investigated and conducted accident reconstruction
    investigations, including "curb cases" when individuals tripped either ascending
    or descending a curb, testified as an expert in civil engineering on behalf of the
    defense. He completed a thirty-hour OSHA construction safety course; was
    familiar with OSHA and ANSI standards; and with state building and
    construction codes. He also had reviewed OSHA's general duty clause and
    A-1760-19
    20
    multi-employer jobsite policy for general contractors and subcontractors
    working on the same site.
    Cronin found no OSHA regulation or standard governing the placement
    of portable toilets on construction sites or near curbs. He noted Estrin also never
    found that defendant had violated any OSHA regulation or standard. Cronin
    stated:
    Just because [defendant is] responsible for the job site,
    they're not citeable [sic] unless there's a violation of an
    OSHA standard. And Estrin's report never established
    any violation of any OSHA standard, so therefore
    [defendant] nor anyone else on the job site is citeable
    [sic] under OSHA, because there's simply no violation
    of any OSHA standard.
    Additionally, based on his review of the accident site photos, witness
    depositions and expert reports, Cronin opined that the location of the portable
    toilet at issue did "not violate any standard, code, ordinance, industry practice ."
    He noted that a curb greater in height than a half inch from ground level was a
    "tripping hazard" and, based on the photos, "there's just no evidence that there's
    any tripping hazard on this job site." On cross-examination, Cronin agreed that
    the photos showed the curb height was more than half an inch to the parking lot
    and to the dirt of the planting bed.
    A-1760-19
    21
    Nevertheless, Cronin opined that it was a "normal industry standard" that
    workers on a construction site have no "expectation for a perfectly flat surface,"
    especially when the area "was a natural ground surface." Cronin pointed out
    plaintiff testified "that as he exited the—the portable toilet, he—he looked down
    and he observed the curb condition prior to tripping." Thus, Cronin testified, "if
    [plaintiff] observed it, he should have taken reasonable steps and—and
    descended the curb in a safe manner, and—and in a similar manner to the way
    he ascended the curb just a few minutes before that."
    In addition, although Cronin had not examined defendant's prime
    construction contract, he agreed that its terms—defendant "[s]hall supervise and
    direct the work" and "'[t]he contractor shall be solely responsible' . . . for
    providing a safe [jobsite]"—meant defendant was 100 [percent] "responsible for
    providing a safe [jobsite]" for all workers. He acknowledged that his own duties
    had included ensuring that all construction work was performed in accordance
    with contract documents and that Carman was defendant's supervisor and the
    person "in charge of the project."
    Following the testimony, counsel and the trial court held a charge
    conference and then discussed the jury charge on the record. In their pretrial
    proposed jury instructions, plaintiffs requested the trial court charge the jury
    A-1760-19
    22
    with Model Jury Charges (Civil) 5.10G, "Standards of Construction, Custom
    and Usage in Industry or Trade" (approved Mar. 2010) (formerly Model Jury
    Charge 5.10H) (Model Charge 5.10G).9 During the charge conference, plaintiffs
    also presented supplemental instructions, asking the trial court to instruct the
    jury that OSHA regulations constitute evidence establishing the duty of care
    required for negligence, and the jury should consider violations of those
    regulations as evidence of negligence.
    Defendant's pretrial proposed jury instructions also requested the court
    charge the jury with Model Charge 5.10G.             However, during the charge
    conference, defendant's counsel stated he did not want any OSHA charge given,
    and instead, he asked the trial court to advise the jury that "a general contractor
    is required to provide a reasonably safe place to work, but is not required to
    eliminate all potential hazards."
    9
    Rule 1:8-7(a) provides in civil cases:
    [A]s to issues not anticipated prior to trial any party
    may submit written requests that the court instruct the
    jury on the law as set forth in the requests. The requests
    shall make specific reference to the Model Civil Jury
    Charges, if applicable . . . . The court shall, on the
    record, rule on the requests prior to closing arguments
    to the jury.
    A-1760-19
    23
    The trial court noted that defendant's suggested language was "not in the
    Model Charge," and then denied both parties' requests "to be consistent with
    both sides." The court continued:
    This is . . . a case of generic negligence against a
    general contractor for placing what's an easily
    understandable tripping hazard.
    ....
    This jury's going to have to decide based upon
    their own visceral sense of fairness whether or not the
    general contractor should have allowed this curb to be
    so close from the front door of the porta[-]potty.
    The trial court stated that it would instruct the jury on business invitees
    since the parties wanted that charge, in addition to general negligence,
    foreseeability, and defendant's duty to make the site reasonably safe.
    Nonetheless, the court stated it would include Model Charge 5.10G if the parties
    agreed to each other's language for the charge. Defendant's counsel did not
    agree. On the other hand, plaintiffs' counsel objected to the trial court's refusal
    to include language about OSHA violations. The court emphasized:
    The Supreme Court says the burden is on the plaintiff
    that it must prove some OSHA violation to get to the
    jury on a negligence cause of action against a
    contractor.
    A-1760-19
    24
    You're transforming that into an obligation of the
    judge to include in the charge language concerning an
    OSHA violation over the defendant's objection.
    ....
    Think about it this way. In many . . . cases courts
    don't include into the charge every single item of
    evidence educed by all sides in the case and comment
    specifically on that in the jury charge. . . .
    ....
    What you're citing to is a piece of evidence in this
    case. There is -- by the way, note that this case is
    actually pretty weak for the argument. The reason why
    it's weak is that there was nothing explicitly in OSHA
    in regards to the placement of a porta[-]potty. There's
    general language which is obvious. Everything's got to
    be placed in a safe condition. So, this is actually a poor
    case to argue that the Court should tailor a specific
    OSHA charge on a workplace accident.
    Your argument would be stronger if OSHA said,
    just for example, there shall be no obstacles within
    [twenty-four] inches of the front door of a porta[-]potty.
    Then you could make -- you could make an argument
    analogous to what we do in auto negligence cases when
    a defendant pleads guilty to some type of traffic
    offense, that type of stuff. But suppose OSHA found
    -- it would be even more analogous if OSHA
    investigated, and found, and cited an OSHA violation
    under these circumstances. Then it really is analogous
    to the Model Charge.
    ....
    A-1760-19
    25
    Secondly, again, the OSHA violations here are
    more generic. They weren't specific.
    Ultimately, the trial court did not include Model Charge 5.10G or make
    any reference to the OSHA standards or regulations in its final charge. During
    deliberations, the jury asked five questions related to damages; none were
    related to liability, negligence, or OSHA issues.
    The jury found: (1) defendant was 100 percent negligent; (2) Mr. John
    was not negligent; (3) plaintiff was not comparatively negligent; (3) plaintiff
    incurred past medical expenses of $101,980.79, and past lost earnings of
    $220,000; (4) plaintiff will incur future medical expenses of $111,720, and has
    a future lost earning capacity of $660,000; (5) plaintiff suffered and will suffer
    past, present, and future pain and suffering, embarrassment, humiliation,
    disfigurement, and loss of enjoyment of life, totaling $625,000; and (6)
    plaintiff's wife incurred per quod damages of $625,000.
    Following the jury's verdict, defendant's counsel moved for a new trial,
    arguing the trial court erred by not striking or limiting Estrin's testimony because
    it was a net opinion, and because he testified about contracts and safety language
    that were beyond his expertise. Defendant further contended that Estrin never
    cited to any specific OSHA regulation, standard, or duty that defendant violated
    even though he opined defendant was one hundred percent liable for plaintiff's
    A-1760-19
    26
    fall. Defense counsel further argued that, after refusing to strike or limit Estrin's
    testimony, the trial court erred by not instructing the jury on OSHA violations
    or telling them that a violation of OSHA "doesn't necessarily mean anything ."10
    In denying defendant's motion, the trial court initially noted that defendant
    had argued expressly against mentioning OSHA in the liability charge. The
    court next discussed the scope of Estrin's testimony:
    So, you may be right, that I was a bit overindulgent in
    regard to allowing the expert to testify about what the
    contract said between your client and their obligations
    to provide a safe work site.
    But, the jury is perfectly capable, independent of
    that, of determining whether or not the placement of
    this porta[-]potty was done in a negligent manner,
    without regard to whether the expert said that that
    implicated the contractual provision to provide a safe
    workplace, et cetera, et cetera.
    The court highlighted:
    As I indicated, the case was very -- was very well
    tried. I thought from the beginning that actually the
    plaintiff had the better case on liability for a very
    simple reason. It had nothing to do with OSHA
    violations, or experts, or anything like that. Merely
    looking at a picture of the port-o-potty, and seeing
    where -- and it was a tripping hazard. This was a piece
    of wood or something sticking out, I don't know, about
    10
    Defense counsel also argued that the jury's allocating 100 percent liability to
    defendant was against the weight of the evidence.
    A-1760-19
    27
    [six] inches, [eight] inches, whatever it was. It was a
    tripping hazard. People can trip on it.
    [Plaintiff] should have been looking where he
    was going. And as I indicated a few minutes ago, had
    this been a bench trial, I probably would have found
    [fifteen], [twenty], [twenty-five] percentage points of
    comparative negligence.
    But I certainly, for what it's worth, I agree with
    the jury's determination that [defendant], which was the
    general contractor, and had overall responsibility for
    the safety of the workers. And the port-o-potty could
    have [been] turned around 180 degrees so that there was
    no tripping hazard.
    On December 6, 2019, the trial court entered an order denying defendant's
    motion for a new trial and entered a memorializing order. This appeal followed.
    On appeal, defendant raises two points: (1) the trial court's failure to
    instruct the jury on the significance of OSHA regulations led to an unjust result;
    and (2) the jury's apportionment of one hundred percent of the liability for
    plaintiff's accident to defendant was against the weight of the evidence and
    warrants a new trial.
    II.
    "It is fundamental that '[a]ppropriate and proper charges to a jury are
    essential for a fair trial.'" Prioleau v. Ky. Fried Chicken, Inc., 
    223 N.J. 245
    , 256
    (2015) (alteration in original) (quoting Velazquez ex rel. Velazquez v. Portadin,
    A-1760-19
    28
    
    163 N.J. 677
    , 688 (2000)). The jury charge is "a road map that explains the
    applicable legal principles, outlines the jury's function, and spells out 'how the
    jury should apply the legal principles charged to the facts of the case at hand.'"
    Toto v. Ensuar, 
    196 N.J. 134
    , 144 (2008) (quoting Viscik v. Fowler Equip. Co.,
    
    173 N.J. 1
    , 18 (2002)). It therefore "should set forth in clear understandable
    language the law that applies to the issues in the case." 
    Ibid.
     In a civil case, we
    "uphold even erroneous jury instructions when those instructions are incapable
    of producing an unjust result or prejudicing substantial rights."         Fisch v.
    Bellshot, 
    135 N.J. 374
    , 392 (1994). Cf. Walker v. Costco Wholesale Warehouse,
    
    445 N.J. Super. 111
    , 120 (App. Div. 2016) (stating failure to give jury charge
    on mode-of-operation was "clearly capable of affecting the verdict on liability").
    Defendant argues that the trial court's failure to instruct the jury on the
    significance of the OSHA regulations as set forth in Model Jury Charge 5.10G,
    led to an unjust result. That charge states:
    Some evidence has been produced in this case as
    to the standard of construction in the industry. Such
    evidence may be considered by you in determining
    whether the defendant’s negligence has been
    established. If you find that the defendant did not
    comply with that standard, you may find the defendant
    to have been negligent. However, the general custom
    of the industry, although evidential as to what is the
    reasonable standard in such industry, does not
    conclusively establish the care the defendant was
    A-1760-19
    29
    required to exercise in the performance of its
    operations. Compliance with an industry standard is
    not necessarily conclusive as to the issue of negligence,
    and does not, of itself, absolve the defendant from
    liability. The defendant must still exercise reasonable
    care under all the circumstances, and if you find that
    the prevailing practices in the industry do not comply
    with that standard, the defendant may be found
    negligent by you notwithstanding compliance with the
    custom or standard of the industry.
    [Model Charge 5.10G.]
    And in a footnote, the charge declares:
    Where it is alleged that a contractor violated
    [OSHA] regulations, such violation is treated similarly
    to a violation of an industry standard. See Costa v.
    Gaccione, 
    408 N.J. Super. 362
    , 372 (App. Div. 2009)
    (citing Alloway v. Bradlees, Inc., 
    157 N.J. 221
    , 236
    (1999) ("violation of OSHA regulations without more
    does not constitute the basis for an independent or
    direct tort remedy.")[).]    Thus, as with industry
    standards, OSHA regulations are pertinent in
    determining the nature and extent of any duty of care,
    but compliance with OSHA does not preclude a finding
    of negligence and, conversely, non-compliance with
    OSHA does not preclude a finding that there was no
    negligence. 
    Id. at 237
    .
    [Model Charge 5.10G n.2.]
    Plaintiffs respond that defendant invited the error when it expressly
    advocated against the court charging the jury with Model Charge 5.10G on the
    OSHA regulations and then failed to object to the absence of that instruction.
    A-1760-19
    30
    They claim the trial court correctly charged the jury on the general principles of
    negligence.
    In reply, defendant asserts the court had an independent duty to charge the
    jury with Model Charge 5.10G, or in the alternative, defendant claims that, even
    if it had invited or acquiesced in an erroneous jury charge, we are required to
    reverse because the charge was clearly capable of producing an unjust result
    under the plain error standard. We disagree.
    "[G]eneral negligence principles govern the determination of whether a
    legal duty should be imposed on a contractor for injuries sustained by another
    contractor's employee." Slack v. Whalen, 
    327 N.J. Super. 186
    , 191 (App. Div.
    2000) (citing Alloway, 
    157 N.J. at 230
    ). To prevail in a negligence case, a
    plaintiff must demonstrate that (1) the defendant owed the plaintiff a duty of
    care; (2) the defendant breached that duty; (3) the defendant's breach of its duty
    actually and proximately caused the plaintiff's injury; and (4) the plaintiff
    sustained damages. Fernandes v. DAR Dev. Corp., 
    222 N.J. 390
    , 403-04 (2015).
    Whether a defendant owes a plaintiff a duty and the scope of that duty are legal
    questions. Shields v. Ramslee Motors, 
    240 N.J. 479
    , 487-88 (2020).
    Determining whether a duty exists "involves identifying, weighing, and
    balancing several factors—the relationship of the parties, the nature of the
    A-1760-19
    31
    attendant risk, the opportunity and ability to exercise care, and the public interest
    in the proposed solution." Hopkins v. Fox & Lazo Realtors, 
    132 N.J. 426
    , 439
    (1993). The foreseeability of an injury "is 'crucial' in determining whether a
    duty should be imposed." J.S. v. R.T.H., 
    155 N.J. 330
    , 338 (1998) (quoting
    Carter Lincoln-Mercury, Inc. v. EMAR Grp., Inc., 
    135 N.J. 182
    , 194 (1994)).
    "Foreseeability requires a determination of whether the defendant was
    reasonably able to ascertain that his allegedly negligent conduct could injure the
    plaintiff in the manner it ultimately did." Robinson v. Vivirito, 
    217 N.J. 199
    ,
    212 (2014). Foreseeability "is the major consideration for imposing a tort duty,
    [but] additional factors should [also] be considered, such as 'the relationship of
    the parties, the nature of the attendant risk, the opportunity and ability to
    exercise care and the public interest . . . .'" Slack, 
    327 N.J. Super. at 191
     (quoting
    Alloway, 
    157 N.J. at 230
    ).
    An OSHA violation may be considered with those factors in determining
    the existence and scope of duty but does not alone create a "tort duty of care."
    Costa v. Gaccione, 
    408 N.J. Super. 362
    , 372-73 (App. Div. 2009); see also
    Tarabokia v. Structure Tone, 
    429 N.J. Super. 103
    , 120 (App. Div. 2012).
    "Whether a [d]uty exists is ultimately a question of fairness." Goldberg v. Hous.
    A-1760-19
    32
    Auth. of Newark, 
    38 N.J. 578
    , 583 (1962). See also Olivo v. Owens-Illinois,
    Inc., 
    186 N.J. 394
    , 401 (2006).
    Here, as plaintiffs correctly claim, defendant expressly argued during the
    charge conference against the trial court's instructing the jury with Model
    Charge 5.10G and, in fact, against even its mentioning OSHA. "The doctrine of
    invited error operates to bar a disappointed litigant from arguing on appeal that
    an adverse decision below was the product of error, when that party urged the
    lower court to adopt the proposition now alleged to be error." N.J. Div. of Youth
    & Fam. Servs. v. M.C. III, 
    201 N.J. 328
    , 340 (2010) (quoting Brett v. Great Am.
    Recreation, Inc., 
    144 N.J. 479
    , 503 (1996)).
    "[A] defendant cannot beseech and request the trial
    court to take a certain course of action, and upon
    adoption by the court, take his[, hers or its] chance on
    the outcome of the trial, and if unfavorable, then
    condemn the very procedure he[, she or it] sought . . .
    claiming it to be error and prejudicial."
    [Ibid. (quoting State v. Jenkins, 
    178 N.J. 347
    , 358
    (2004) (citation omitted)). See Titus v. Lindberg, 
    49 N.J. 66
    , 78 (1967) (finding Board of Education was
    barred from asserting error in jury charge it requested).]
    Nevertheless, a court "would not automatically apply the doctrine [of invited
    error] if it were to 'cause a fundamental miscarriage of justice.'" M.C. III, 
    201 N.J. at 342
     (quoting Brett, 
    144 N.J. at 508
    ).
    A-1760-19
    33
    Here, we discern no fundamental injustice that would warrant relaxing
    the invited error doctrine since defendant's counsel ostensibly made a strategic
    decision when he changed his plan and decided to advocate against the trial
    court's charging the jury on OSHA evidence or with Model Charge 5.10G.
    Nevertheless, defendant correctly asserts, "the ultimate responsibility rests with
    the [trial] court to instruct the jury regarding the appropriate law that is
    applicable to the evidence."       Das v. Thani, 
    171 N.J. 518
    , 530 (2002).
    Consequently, we will evaluate an invited error under "the plain error standard."
    Willner v. Vertical Reality, Inc., 
    235 N.J. 65
    , 79 (2018) (quoting State v.
    Wakefield, 
    190 N.J. 397
    , 473 (2007)).
    Rule 2:10-2 defines "plain error" as error that is "clearly capable of
    producing an unjust result." It states:
    Any error or omission shall be disregarded by the
    appellate court unless it is of such a nature as to have
    been clearly capable of producing an unjust result, but
    the appellate court may, in the interests of justice,
    notice plain error not brought to the attention of the trial
    or appellate court.
    [R. 2:10-2.]
    With regard to a jury charge, "plain error is 'legal impropriety in the
    charge prejudicially affecting the substantial rights of the [party] and
    sufficiently grievous to justify notice by the reviewing court and to convince the
    A-1760-19
    34
    court that of itself the error possessed a clear capacity to bring about an unjust
    result.'" Mason v. Sportsman's Pub, 
    305 N.J. Super. 482
    , 495 (App. Div. 1997)
    (quoting State v. Hock, 
    54 N.J. 526
    , 538 (1969)).
    In the matter under review, the initial disputes for the jury to resolve were
    the nature of the care defendant was required to provide for subcontractors on
    its jobsite and then whether it violated its duty of care. 11 There was extensive
    testimony on OSHA standards and regulations. "OSHA regulations are pertinent
    in determining the nature and extent of any duty of care." Alloway, 
    157 N.J. at 236
    . See Kane v. Hartz Mountain Indus., Inc., 
    278 N.J. Super. 129
    , 144 (App.
    Div. 1994) (finding "error in the trial judge's failure to provide adequate
    guidance to the jury regarding the proper interpretation of the OSHA
    regulations"), aff'd o.b., 
    143 N.J. 141
     (1996).
    The purpose of OSHA, 
    29 U.S.C. §§ 651
     to 678, is "to provide for the
    general welfare, to assure so far as possible every working man and woman in
    the Nation safe and healthful working conditions and to preserve our human
    resources . . . ." 
    29 U.S.C. § 651
    (b). It requires "employers to comply with
    specific OSHA standards and also imposes a general duty on employers to
    11
    We note the nature of the duty is different from the question of wheth er one
    owes a duty in the first place, which is a question of law to be decided by the
    trial judge. Carvalho v. Toll Bros. & Devs., 
    143 N.J. 565
    , 572 (1996).
    A-1760-19
    35
    provide a workplace 'free from recognized hazards that are causing or are likely
    to cause death or serious physical harm.'" Gonzalez v. Ideal Tile Importing Co.,
    
    371 N.J. Super. 349
    , 359-60 (App. Div. 2004) (quoting 
    29 U.S.C. § 654
    (a)).
    Based upon our careful review of the record, we conclude that, the
    omission of Model Charge 5.10G and OSHA from the trial court's instructions
    was not clearly capable of producing an unjust result here. Estrin did not point
    to any specific OSHA regulation governing the toilet's placement, and Cronin
    agreed that there had been no violation of any OSHA standard. In fact, no
    violation of any specific OSHA provision on portable toilets was ever presented
    to the jury. Instead, the evidence referred to general OSHA standards and
    regulations offering the same level of care as the general theory of negligence.
    We "must read the charge as a whole." Sons of Thunder, Inc. v. Borden,
    Inc., 
    148 N.J. 396
    , 418 (1997); see also Estate of Kotsovska ex rel. Kotsovska
    v. Liebman, 
    221 N.J. 568
    , 592 (2015) (stating that a court presented with a
    contested jury charge must evaluate the entirety of the charge and not focus on
    individual, isolated errors). "[T]he prejudicial effect of an omitted instruction
    must be evaluated in light of the totality of the circumstances including all of
    the instructions to the jury, [and] the arguments of counsel." State v. Townsend,
    
    186 N.J. 473
    , 499 (2006) (second alteration in original) (quoting State v.
    A-1760-19
    36
    Marshall, 
    123 N.J. 1
    , 145 (1991)); see also Piech v. Layendecker, 
    456 N.J. Super. 367
    , 377 (App. Div. 2018) ("We must consider . . . whether counsel
    voiced any contemporaneous objection, . . . and the likelihood that the flaw was
    so serious that it was likely to have produced an unfair outcome.").
    Although defendant's argument is subject to the invited error doctrine, in
    the interests of justice, we review the jury instructions for plain error. Here, we
    are satisfied that the trial court clearly explained the elements of negligence and
    plaintiffs' obligation to prove negligence by a preponderance of the credible
    evidence.
    Moreover, a violation of the OSHA standards and regulations is not
    dispositive of a general contractor's liability.     Alloway, 
    157 N.J. at 234
    .
    "Compliance with an OSHA regulation does not in and of itself preclude a
    finding of negligence," and, for the same reason, the violation of an OSHA
    regulation "does not ipso facto constitute a basis for assigning negligence as a
    matter of law." Kane, 
    278 N.J. Super. at 142, 144
    . Thus, while the existence of
    an OSHA violation may be some evidence that defendant did not follow the
    regulations, it is not conclusive evidence that defendant was liable as a general
    contractor or property occupier.
    A-1760-19
    37
    More importantly, there was substantial, credible evidence presented that
    Carman's duty was to supervise the entire jobsite, including toilet placement,
    and defendant's duties were specifically enumerated in its prime construction
    contract, which made defendant "solely responsible for, and ha[ving] control
    over, construction means, methods, techniques, sequences and procedures and
    for coordinating all portions of the Work under the Contract."              Cronin,
    defendant's expert, even agreed with Estrin that Carman was in charge of the
    project, as confirmed in defendant's answers to interrogatories certified by its
    president, and the terms in the prime construction contract meant defendant had
    an absolute duty and was one hundred percent responsible for providing a safe
    jobsite for all workers.
    In light of this compelling evidence, the jury had a strong, independent
    basis on which to find defendant's negligence. The jury clearly rejected the
    testimony presented by the defense witnesses, and instead found more credible
    plaintiffs and their witnesses. Therefore, we conclude the absence of any charge
    on OSHA standards and regulations, including Model Charge 5.10G, was
    irrelevant to the jury's liability verdict and its findings on the care defendant was
    required to provide for subcontractors and employees on its jobsite, relative to
    defendant's violation of that care. Applying these standards, we conclude the
    A-1760-19
    38
    trial court's decision not to charge the jury on OSHA standards and regulations,
    as in Model Charge 5.10G, was not "clearly capable of producing an unjust
    result" constituting plain error under Rule 2:10-2 and does not warrant reversal.
    III.
    Defendant next argues that the trial court erred by failing to strike or limit
    the scope of Estrin's testimony, and the court's alleged improper comment
    further underscored the need to charge the jury about OSHA standards and
    regulations. According to defendant, the trial court's failure to give a proper
    jury instruction on OSHA regulations led to an unjust result. 12
    In April 2019, defendant moved to bar Estrin's report and testimony as a
    net opinion, arguing that he had cited no specific OSHA standard for the
    placement of portable toilets and had failed to include any measurements of the
    scene. During oral argument, the trial court asked defendant's counsel why he
    believed OSHA regulations were not applicable:
    12
    Defendant also claims in various footnotes throughout its brief and reply brief
    that many points in Estrin's testimony were "legally incorrect" or "patently
    false." These allegations of error are waived because defendant raised them in
    footnotes and not under point headings. Almog v. Isr. Travel Advisory Serv.,
    Inc., 
    298 N.J. Super. 145
    , 155 (App. Div. 1997) (holding legal issues raised in
    footnotes and not under appropriate point headings required by Rule 2:6-2(a)(5)
    will not be considered on appeal).
    A-1760-19
    39
    THE COURT: . . . but what's your complaint
    about the plaintiff's expert . . . citing the OSHA
    standards even if only as to -- as to the general
    proposition, as opposed to whether or not there should
    be a curb three feet from the front door of a porta[-]
    potty?
    [DEFENDANT'S COUNSEL]: Well, because
    now it looks like we violated two different standards.
    If you just say, well, he's just going to come in and
    blather on about negligence or failure to comply with
    OSHA, that doesn't matter, because what matters is the
    standard due to an invitee on the premises. Which
    plaintiff is. He's an invitee on the premises. That's the
    standard. Not the OSHA standard. So, to the extent
    that you allow an expert to come in and say, oh, OSHA
    requires him to do this and OSHA requires him to do
    that, and then you come along later and go, oh yeah,
    OSHA requires him to do this and OSHA requires him
    to do that; oh, and by the way, the law -- the -- you
    know, the general law is that a business owner owes this
    duty to an invitee, so now the defense has a -- has the
    burden of fighting two different fronts and two different
    theories of liability. There shouldn't be two different
    theories of liability. There should be one theory of
    liability which can be supported by alleged OSHA
    violations, but the OSHA violations in and of
    themselves do not establish the standard.
    ....
    THE COURT: . . . [T]hat would be an issue that
    will be taken up at the charge conference, in terms, of
    exactly what the charge is. But I don't see there being
    any problem with an expert -- in fact, they do it all the
    time -- citing to various standards -- OSHA is one of
    the more predominant ones -- in regard to the basis of
    their opinion. . . .
    A-1760-19
    40
    Thereafter, the trial court denied the motion, with the proviso that
    defendant could renew the objection at trial. However, the record shows that
    during Estrin's testimony, defense counsel raised no specific objections to the
    expert's comments about the scope of OSHA standards and regulations,
    defendant's prime construction contract, or OSHA's MECP.
    After Estrin testified, defendant renewed its motion to strike his
    testimony, arguing that the applicable standard of liability was general
    negligence, because the matter involved a contractor or occupier of property.
    Defense counsel contended that Estrin's testimony on OSHA's general safety
    standards confused the jury, thereby allowing the jury to find defendant
    potentially culpable under two different liability standards: general negligence
    and OSHA.
    The trial court again denied the motion and explained:
    To me I don't see it as a basis for disqualifying
    Estrin. He essentially used these standards as a basis
    for arguing that there was negligence in maintaining
    this particular area due to the presence of the curb.
    The more difficult question is whether or not the
    charge should include explicit to [sic] OSHA violations
    particularly in this case where there's nothing narrowly
    tailored to an OSHA violation.
    ....
    A-1760-19
    41
    So we'll deal with that at the charge conference,
    but I'm denying the motion to strike the entirety of
    Estrin's testimony.
    A trial court's evidentiary rulings, including those regarding expert
    testimony, are "entitled to deference absent a showing of an abuse of discretion."
    State v. Brown, 
    170 N.J. 138
    , 147 (2001) (quoting State v. Marrero, 
    148 N.J. 469
    , 484 (1997)); see also Townsend v. Pierre, 
    221 N.J. 36
    , 53 (2015); Bender
    v. Adelson, 
    184 N.J. 411
    , 428 (2006). "[An] abuse of discretion only arises on
    demonstration of 'manifest error or injustice,'" Hisenaj v. Kuehner, 
    194 N.J. 6
    ,
    20 (2008) (quoting State v. Torres, 
    183 N.J. 554
    , 572 (2005)), and occurs when
    the trial judge's "decision is 'made without a rational explanation, inexplicably
    departed from established policies, or rested on an impermissible basis.'" Milne
    v. Goldenberg, 
    428 N.J. Super. 184
    , 197 (App. Div. 2012) (quoting Flagg v.
    Essex Cnty. Prosecutor, 
    171 N.J. 561
    , 571 (2002)). We discern no abuse of
    discretion here.
    Generally, the admission of expert testimony is governed by Rule 702,
    which provides:
    If scientific, technical, or other specialized knowledge
    will assist the trier of fact to understand the evidence or
    to determine a fact in issue, a witness qualified as an
    expert by knowledge, skill, experience, training, or
    A-1760-19
    42
    education may testify thereto in the form of an opinion
    or otherwise.
    Admissibility turns on three basic requirements:
    (1) the intended testimony must concern a subject
    matter that is beyond the ken of the average juror; (2)
    the field testified to must be at a state of the art such
    that an expert's testimony could be sufficiently reliable;
    and (3) the witness must have sufficient expertise to
    offer the intended testimony.
    [Agha v. Feiner, 
    198 N.J. 50
    , 62 (2009) (quoting State
    v. Kelly, 
    97 N.J. 178
    , 208 (1984)).]
    Rule 703 addresses the foundation for expert testimony.             The rule
    mandates that expert opinion be grounded in "facts or data derived from (1) the
    expert's personal observations, or (2) evidence admitted at the trial, or (3) data
    relied upon by the expert which is not necessarily relied upon by experts in
    forming opinions on the same subject." Polzo v. Cnty. of Essex, 
    196 N.J. 569
    ,
    583 (2008) (quoting Townsend, 
    186 N.J. at 494
    ).
    The net opinion rule is a "corollary of [Rule 703] . . . which forbids the
    admission into evidence of an expert's conclusions that are not supported by
    factual evidence or other dat[a]." 
    Ibid.
     (alteration in original). The rule requires
    that an expert "'give the why and wherefore' that supports the opinion, 'rather
    than a mere conclusion.'" Borough of Saddle River v. 66. E. Allendale, LLC,
    
    216 N.J. 115
    , 144 (2013) (quoting Pomerantz Paper Corp. v. New Cmty. Corp.,
    A-1760-19
    43
    
    207 N.J. 344
    , 372 (2011)); see also Buckelew v. Grossbard, 
    87 N.J. 512
    , 524
    (1981) (explaining that "an expert's bare conclusion[], unsupported by factual
    evidence, is inadmissible").
    The net opinion rule does not mandate an expert organize or support an
    opinion in a particular manner that opposing counsel deems preferable. Pierre,
    221 N.J. at 54. An expert's proposed testimony should not be excluded merely
    "because it fails to account for some particular condition or fact which the
    adversary considers relevant." Creanga v. Jardal, 
    185 N.J. 345
    , 360 (2005)
    (quoting State v. Freeman, 
    223 N.J. Super. 92
    , 116 (App. Div. 1988)).
    The net opinion rule, however, mandates that experts "be able to identify
    the factual bases for their conclusions, explain their methodology, and
    demonstrate that both the factual bases and the methodology are scientifically
    reliable." Landrigan v. Celotex Corp., 
    127 N.J. 404
    , 417 (1992). An expert's
    conclusion "is excluded if it is based merely on unfounded speculation and
    unquantified possibilities." Grzanka v. Pfeifer, 
    301 N.J. Super. 563
    , 580 (App.
    Div. 1997) (quoting Vuocolo v. Diamond Shamrock Chem. Co., 
    240 N.J. Super. 289
    , 300 (App. Div. 1990)). By definition, unsubstantiated expert testimony
    cannot provide to the factfinder the benefit that Rule 702 envisions: a qualified
    specialist's reliable analysis of an issue "beyond the ken of the average juror."
    A-1760-19
    44
    Polzo, 
    196 N.J. at 582
    ; see N.J.R.E. 702. Given the weight that a jury may
    accord to expert testimony, a trial court must ensure than an expert is not
    permitted to express speculative opinions or personal views that are unfounded
    in the record. Pierre, 221 N.J. at 55.
    Applying these standards, we conclude the trial court did not abuse its
    discretion by refusing to strike or limit Estrin's testimony. The entirety of
    Estrin's opinions and his testimony were contained in his pretrial expert report.
    Nonetheless, defendant asserts that the following statements by Estrin "were
    legally incorrect, improper, and had a clear impact on the jury" and "exceeded
    the permissible scope of expert testimony": (1) characterizing the OSHRC as
    having the force of law; (2) calling the MECP unenforceable and suggesting that
    courts had rejected the argument that a controlling employer or general
    contractor has less responsibility to protect workers than an exposing employer;
    (3) declaring that the OSHA regulations rendered defendant 100 percent
    responsible for plaintiff's accident; and (4) stating that plaintiff was not
    responsible for his fall unless he had engaged in misconduct.
    We reject defendant's arguments. The record reveals that defense counsel
    never objected to Estrin's statements. In any event, defense counsel extensively
    cross-examined Estrin.     And in fact, Estrin made the first two challenged
    A-1760-19
    45
    statements during his cross-examination. Therefore, we discern no error or
    abuse of discretion by the trial court in denying defendant's motion to strike or
    limit the scope of Estrin's testimony.
    IV.
    Finally, defendant contends the trial court erred by not granting its motion
    for a new trial as the jury's finding defendant 100 percent liable for plaintiff's
    fall and injuries was against the weight of the evidence. 13 We disagree.
    A trial judge shall not reverse a jury verdict as against the weight of the
    evidence unless, "having given due regard to the opportunity of the jury to pass
    upon the credibility of the witnesses, it clearly and convincingly appears that
    there was a miscarriage of justice under the law." R. 4:49-1(a).
    A "miscarriage of justice" has been described as
    a "pervading sense of 'wrongness' needed to justify [an]
    appellate or trial judge undoing of a jury verdict . . .
    [which] can arise . . . from manifest lack of inherently
    credible evidence to support the finding, obvious
    overlooking or undervaluation of crucial evidence, [or]
    a clearly unjust result. . . ."
    [Risko v. Thompson Muller Auto. Grp., 
    206 N.J. 506
    ,
    521-22 (2011) (alterations in original) (quoting
    13
    In its new trial motion, defendant also argued the trial court erred by not
    striking Estrin's testimony and by not instructing the jury on OSHA regulations.
    However, on appeal, defendant only challenges the jury's liability apportionment
    as against the weight of the evidence.
    A-1760-19
    46
    Lindenmuth v. Holden, 
    296 N.J. Super. 42
    , 48 (App.
    Div. 1996)).]
    We look to the same standard as the trial court when reviewing the denial
    of a motion for new trial. R. 2:10-1; Pellicer ex rel. Pellicer v. St. Barnabas
    Hosp., 
    200 N.J. 22
    , 52 (2009). That is, as an appellate court, we must make our
    own determination and shall not reverse a jury verdict as against the weigh t of
    the evidence "unless it clearly appears that there was a miscarriage of justice
    under the law." R. 2:10-1. The only exception from the trial court's review is
    that we must defer to the trial judge's views on "witness credibility,"
    "demeanor," "feel of the case," and other intangible aspects that are not
    transmitted by the written record. Dolson v. Anastasia, 
    55 N.J. 2
    , 6 (1969). The
    trial judge's decision, however, is not entitled to any special deference when "it
    rests upon a determination as to worth, plausibility, consistency or other tangible
    considerations apparent from the face of the record." 
    Id. at 7
    .
    After the jury's verdict, defendant's counsel moved for a new trial, arguing
    the jury's findings that defendant was 100 percent liable and that Mr. John was
    not liable were against the weight of the evidence.
    As to the jury's liability percentages, the trial court noted:
    I agree with you; I was surprised that they didn't find
    any comparative. It's fairly common for a jury in these
    A-1760-19
    47
    scenarios to find some comparative on the part of the
    plaintiff.
    And because plaintiff's expert did blame the
    porta[-]potty company -- of course, the plaintiff settled
    with the porta[-]potty company, so the shift -- then the
    shift always occurs. And I don't say that pejoratively,
    that's the way litigation is played. So I was, I would
    say, a bit surprised it was a hundred zero.
    But the standard is very -- obviously I'm not here
    to second-guess the jury. It was -- it was certainly
    within reason for the jury to determine that the porta[-]
    potty company was not responsible for making sure that
    there wouldn't be a tripping hazard, [eighteen] feet --
    [eighteen] inches, or whatever it was, from the front
    door of the porta[-]potty.
    As far as comparative goes, yeah, the plaintiff
    should have been looking where he was walking, and
    had it been a bench trial, I certainly would have
    attributed some percentages of comparative on the
    plaintiff. But the jury's refusal to do so was within the
    range of reasonability. That's basically where you end
    up.
    I agree with you on the merits. In terms of the
    -- those percentages, but it wasn't my call, it was the
    jury's call.
    The trial court stated that it "thought from the beginning that actually the
    plaintiff had the better case on liability for a very simple reason. It had nothing
    to do with OSHA violations, or experts, or anything like that." By merely
    looking at the photos, the jury could see "it was a tripping hazard," so the court
    A-1760-19
    48
    "certainly . . . agree[d] with the jury's determination that [defendant], which was
    the general contractor, . . . had overall responsibility for the safety of the
    workers.   And the port-o-potty could have [been] turned around 180 [sic]
    degrees so that there was no tripping hazard."
    Defendant specifically argues that the jury's apportionment of fault was
    "directly contrary" to Estrin's testimony and the undisputed evidence. That is,
    Estrin testified that Mr. John was negligent both in the placement of the portable
    toilet and in subsequent visits to the site when its representatives or employees
    did not advise Carman of a potentially hazardous condition. Moreover, it was
    uncontroverted that plaintiff had a clear view of the curb area in front of the
    portable toilet and was able to safely navigate over the curb when entering the
    toilet. Defendant's arguments are devoid of merit.
    We note the record adequately supports the jury's verdict. See R. 2:10-1.
    Estrin testified that Mr. John's employees had weekly responsibilities only to
    clean the toilets and to inform Carman, defendant's onsite supervisor, if they
    discovered anything unsafe. The toilet already had been in place four weeks
    prior to plaintiff's fall, so the jury could have determined that Carman had plenty
    of time to notice and correct its hazardous placement. According to defendant's
    president, Carman was defendant's supervisor and the person responsible for the
    A-1760-19
    49
    whole jobsite, including directing placement of the portable toilets. Also, Estrin
    and defendant's expert, Cronin, agreed that the terms of defendant's prime
    contract rendered it 100 percent and solely liable for providing a safe jobsite for
    all workers.
    Additionally, Estrin testified that plaintiff had no responsibility to
    investigate or inspect the placement of a portable toilet, especially in an area
    that he had never visited before the day of his fall. Indeed, there was no evidence
    presented that BFC or any of its employees had ever worked in the area where
    the toilet was located before plaintiff's fall.
    Furthermore, the jury could have considered that plaintiff was not
    contributorily negligent due to defendant's sole responsibility for placement of
    the dumpster and the wood step in the parking lot near the toilet. As Estrin
    testified, because of the dumpster, plaintiff had to be on the lookout for moving
    construction vehicles and equipment near the toilet. And, the jury evaluated and
    credited plaintiff's testimony that, when he exited the toilet, plaintiff was
    cognizant of the front-end loader he observed in the parking lot before entering
    the portable toilet.
    As we discern no clear miscarriage of justice under the law, we affirm the
    jury verdict and the denial of defendant's motion for a new trial.
    A-1760-19
    50
    Affirmed.
    A-1760-19
    51