LESSNER ELECTRIC COMPANY VS. FIDELITY AND DEPOSIT COMPANY OF MARYLAND (L-1353-17, UNION COUNTY AND STATEWIDE) ( 2018 )


Menu:
  •                         NOT FOR PUBLICATION WITHOUT THE
    APPROVAL OF THE APPELLATE DIVISION
    This opinion shall not "constitute precedent or be binding upon any court."
    Although it is posted on the internet, this opinion is binding only on the
    parties in the case and its use in other cases is limited. R. 1:36-3.
    SUPERIOR COURT OF NEW JERSEY
    APPELLATE DIVISION
    DOCKET NO. A-0081-17T3
    LESSNER ELECTRIC COMPANY,
    Plaintiff-Appellant,
    v.
    FIDELITY AND DEPOSIT COMPANY OF
    MARYLAND, ZURICH AMERICAN
    INSURANCE CO., and APS
    CONTRACTING, INC.,
    Defendants-Respondents.
    _____________________________________
    Argued July 31, 2018 – Decided August 8, 2018
    Before Judges Sabatino and Mawla.
    On appeal from Superior Court of New Jersey,
    Law Division, Union County, Docket No. L-1353-
    17.
    Glenn C. Slavin argued the cause for appellant
    (Slavin & Morse, LLC, attorneys; Glenn C.
    Slavin, on the brief).
    Eric   J.   Levine   argued  the   cause   for
    respondents Fidelity and Deposit Company of
    Maryland and Zurich American Insurance Company
    (Baron Samson, LLP, attorneys; Eric J. Levine,
    on the brief).
    Daniel Connolly Carmalt argued the cause for
    respondent APS Contracting, Inc. (Carmalt Law,
    LLC, attorneys; Daniel Connolly Carmalt, on
    the brief).
    PER CURIAM
    Plaintiff Lessner Electric Company (Lessner) appeals from
    August 22, 2017 and September 20, 2017 orders dismissing its
    complaint alleging breach of contract, delay damages, and unjust
    enrichment on grounds of a failure to state a claim.         We affirm.
    In   July   2013,   Lessner   entered   into   a   subcontract   with
    defendant APS Contracting, Inc. (APS) to perform electrical work
    on the construction of the Union County Family Courthouse.              In
    pertinent part, the contract between Lessner and APS stipulated
    as follows:
    To the fullest extent permitted by law,
    [Lessner] waives its right to any claim for
    damage for delay from [APS] . . . . [Lessner]
    expressly confirms its understanding that this
    is a complex project with multiple prime
    contractors      and/or     numerous     other
    subcontractors, which conditions may result
    in, by way of example only and not by the way
    of limitation, coordination and interference
    issues, out of sequence work, recurring
    schedule    revisions,   compression    and/or
    acceleration of the [w]ork, stoppage of the
    [w]ork, and/or other unspecified delays to the
    [p]roject and for which [Lessner] may not be
    compensated. [Lessner] expressly undertakes
    and assumes the risks of the above and
    disclaims any liability for same on the part
    of [APS].
    [(Emphasis added).]
    2                             A-0081-17T3
    Defendants Fidelity and Deposit Company of Maryland, and its
    parent company Zurich American Insurance Co. (collectively, the
    surety) insured the performance of APS through a warranty bond.
    In April 2015, APS was removed from the project, and the surety
    assumed APS's role for the remainder of the project.
    In August 2015, the surety entered into an Assignment and
    Ratification Agreement (ratification agreement) with Lessner to
    reaffirm   its   subcontract,   bring   Lessner   current   for   certain
    payments and costs Lessner believed were due from APS, and have
    Lessner complete the remainder of its work.
    The ratification agreement expressly stipulated in paragraph
    2: "Except as otherwise modified by this Agreement, the terms of
    the Subcontract remain in full force and effect." The ratification
    agreement further stated Lessner "hereby: (i) ratifies and affirms
    its obligations under the Subcontract . . . [and] (iv) agrees
    . . . [it] shall complete the Subcontract and the Subcontract Work
    . . . for [the] Surety, as a subcontractor for [the] Surety, in
    accordance with the terms of the Subcontract and Contract [with
    APS] . . . ." The ratification agreement also set forth the amount
    Lessner claimed it required from the surety in order to return and
    complete its work.     This figure was comprised of the original
    amount agreed upon between Lessner and APS with an addition for a
    change order, less sums already paid to Lessner.
    3                              A-0081-17T3
    The surety and Lessner agreed on no other conditions on
    Lessner's return to the project, other than to contract for the
    payment of the sums due under the original contract.        However, the
    ratification agreement did identify damages Lessner claimed it had
    suffered as a result of the delay of the project.         Specifically,
    paragraph 4 of the ratification agreement released APS and the
    surety,
    from any and all claims, of any type or kind,
    known or unknown, asserted or unasserted,
    which in any way arise from, relate to, or
    concert the Subcontract, the Contract, the
    Project, the Bond, and/or the [Lessner's]
    performance under the Subcontract, which
    claims have accrued or arise out of or relate
    to events occurring prior to the date of this
    Agreement, excluding only: . . . (ii) such
    claims as may be identified . . . in Rider A,
    which is attached hereto and made a part
    hereof.
    Rider A was entitled "PENDING REQUESTS FOR CHANGE ORDERS AND
    RESERVED CLAIMS," and allegedly included Lessner's non-waiver of
    a claim for delay damages although the rider did not describe them
    specifically as such.1
    In September 2016, Lessner asserted a claim against the surety
    seeking   "additional    compensation   due   to   the   delay   damages"
    1
    The bottom of Rider A obliquely references a May 20, 2015
    "Scheduling Concerns/Delays" letter. However, the letter was not
    supplied to the motion judge, and is not part of the record before
    us.
    4                               A-0081-17T3
    totaling $1.82 million allegedly resulting in a twenty-four month
    delay caused by APS's replacement on the project.                 The surety
    noted Lessner's sole remedy for delay under the contract was to
    seek an extension of time to complete its work.            The surety also
    noted   there   had   been   "no   meeting    of   the   minds"   under   the
    ratification agreement to compensate Lessner for delay damages.
    Lessner filed a complaint in the Law Division for breach of
    contract against defendants seeking payment of the delay damages.
    The complaint asserted three counts against the surety, alleging
    a breach of the bonding agreement, the contract with APS, and
    unjust enrichment.     The surety and APS filed motions to dismiss
    for failure to state a claim.            Defendants argued their motions
    should be granted because of the express waiver of delay damages
    clause under the contract with APS, and that delay damages were
    not recoverable under the express terms of the bond and the Bond
    Act, N.J.S.A. 2A:44-143 to -147.
    The motion judge granted the surety's motion to dismiss.             The
    judge found Lessner knew of its delay damages claim, yet entered
    into the ratification agreement, which did not provide for payment
    of the alleged damages.        The judge also concluded the express
    waiver of delay damages under the contract with APS was binding,
    and therefore likewise dismissed the claims against APS.                  This
    appeal followed.
    5                               A-0081-17T3
    We begin by reciting our standard of review. Appellate review
    of a trial court's ruling on a motion to dismiss is de novo.
    Frederick v. Smith, 
    416 N.J. Super. 594
    , 597 (App. Div. 2010)
    (citing Seidenberg v. Summit Bank, 
    348 N.J. Super. 243
    , 250 (App.
    Div. 2002)).       "A complaint should be dismissed for failure to
    state a claim pursuant to Rule 4:6-2(e) only if 'the factual
    allegations are palpably insufficient to support a claim upon
    which relief can be granted.'"                 
    Ibid. (quoting Rieder v.
    State
    Dep't of Transp., 
    221 N.J. Super. 547
    , 552 (App. Div. 1987)).
    "This standard requires that 'the pleading be searched in depth
    and with liberality to determine whether a cause of action can be
    gleaned    even    from    an    obscure       statement.'"      
    Ibid. (quoting Seidenberg, 348
    N.J. Super. at 250); see also Printing Mart-
    Morristown v. Sharp Elecs. Corp., 
    116 N.J. 739
    , 746 (1989).
    On    appeal,   Lessner      asserts       the   motion   judge   prematurely
    dismissed its complaint and applied the wrong legal standard for
    Rule 4:6-2(e) motions by requiring Lessner to prove the allegations
    in the complaint, rather than afford it every favorable inference.
    Lessner argues APS acted in bad faith and contrary to the intent
    of the contract by delaying the project by two years.                         Lessner
    asserts    the    motion   judge     failed      to   search   the     contract      to
    understand its intent.          Additionally, Lessner argues the "no delay
    damages"    clause   allowed       for   a     modification,    and     the    surety
    6                                  A-0081-17T3
    allegedly ratified the modification provision when it entered into
    the ratification agreement, which contained Rider A.         We address
    these arguments in turn.
    "A   contract    is   an   agreement   resulting   in   obligation
    enforceable at law. . . .        To be enforceable as a contractual
    undertaking, an agreement must be sufficiently definite in its
    terms that the performance to be rendered by each party can be
    ascertained with reasonable certainty."      W. Caldwell v. Caldwell,
    
    26 N.J. 9
    , 24-25 (1958) (citing Friedman v. Tappan Dev. Corp., 
    22 N.J. 523
    , 531 (1956)).     "The polestar of contract construction is
    to discover the intention of the parties as revealed by the
    language used by them."    Karl's Sales & Serv. v. Gimbel Bros., 
    249 N.J. Super. 487
    , 492 (App. Div. 1991).
    "Generally, the terms of an agreement are to be given their
    plain and ordinary meaning."      M.J. Paquet v. N.J. DOT, 
    171 N.J. 378
    , 396 (2002).     "[W]here the terms of a contract are clear and
    unambiguous there is no room for interpretation or construction
    and the courts must enforce those terms as written." Karl's 
    Sales, 249 N.J. Super. at 493
    (citing Kampf v. Franklin Life Ins. Co.,
    
    33 N.J. 36
    , 43 (1960)); see also Cty. of Morris v. Fauver, 
    153 N.J. 80
    , 103 (1998).
    Courts may not "remake a better contract for the parties than
    they themselves have seen fit to enter into, or to alter it for
    7                            A-0081-17T3
    the benefit of one party and the detriment of the other."      
    Ibid. (citing James v.
    Fed. Ins. Co., 
    5 N.J. 21
    , 24 (1950)).      "A court
    has no power to rewrite the contract of the parties by substituting
    a new or different provision from what is clearly expressed in the
    instrument."   E. Brunswick Sewerage Auth. v. E. Mill Assocs., Inc.
    
    365 N.J. Super. 120
    , 125 (App. Div. 2004).
    Here, as we noted, the contract between Lessner and APS
    contained an express waiver of delay damages.     Lessner concedes
    as much, and also does not dispute the ratification agreement
    generally reaffirmed the terms and conditions of the contract with
    APS.
    The motion judge concluded:
    [The contract] says no damages for delay. And
    when [Lessner] . . . ratified, [it] knew what
    the delay was at that point. At that point
    in time, now [the] surety is in. It's not APS
    you're suing or anything like that, it's the
    surety that comes in and says . . . do you
    want to finish . . . this job? Here's your
    contract, list everything that's outstanding,
    list your retainage . . . and then we'll have
    a Rider A which has things that you're going
    to ask them for that are beyond the price of
    the contract, and they're going to say yes to
    some things and no to . . . some other things.
    But when a contract provision is clear, and
    we all know what delay damages are, when
    that's clear then I think [defendants have] a
    right to have that interpreted with the plain
    meaning. No damages for delay.
    8                           A-0081-17T3
    Our de novo review leads us to the same conclusion as the
    motion judge. Lessner's complaint could only proceed if defendants
    were responsible for payment of delay damages.   The plain language
    of the contract provides for a clear waiver of delay damages.
    Therefore, the motion judge properly dismissed Lessner's complaint
    for failure to state a claim.
    Moreover, the ratification agreement did not contain a mutual
    agreement to compensate Lessner for delay damages, and thus did
    not modify or afford greater rights to Lessner than those set
    forth in its contract with APS.       Indeed, as we noted, at most
    Rider A merely reflected Lessner's position that it was not waiving
    its right to assert a claim for delay damages.        However, the
    complaint and the record do not support Lessner's argument that
    the surety agreed to compensate Lessner for any alleged delay
    damages.   Thus, in the absence of any evidence of a mutual
    agreement to modify the contract, dismissal of Lessner's complaint
    for delay damages was appropriate.2
    Furthermore, as the motion judge noted, the surety did not
    have greater obligations than APS had under the contract.          In
    disputes such as the one at bar, we have held "[t]he rights of a
    2
    Because we have determined the contract and the ratification
    agreement enforceable, as interpreted by the trial judge in
    dismissing Lessner's contract claims, it follows that Lessner's
    unjust enrichment claim cannot survive as well.
    9                          A-0081-17T3
    third-party beneficiary . . . depend upon and are measured by the
    terms of the bond, the contractual undertaking between the promisor
    and the promisee."    Ribiera & Lourenco Concrete Constr. Co. v.
    Jackson Health Care Assocs., 
    231 N.J. Super. 16
    , 24 (App. Div.
    1989).   "[A] surety is chargeable only according to the strict
    terms of its undertaking and its obligations cannot and should not
    be extended either by implication or by construction beyond the
    confines of its contract."   Eagle Fire Prot. Corp. v. First Indem.
    of Am. Ins. Co., 
    145 N.J. 345
    , 356 (1996) (quoting Monmouth Lumber
    Co. v. Indem. Ins. Co. of N. America, 
    21 N.J. 439
    , 452 (1956)).
    Finally, Lessner argues, for the first time on appeal, the
    delay damages waiver should not be enforced because "APS did not
    act reasonable and, in fact, acted in bad faith in its dealings
    with Lessner."   Our Supreme Court has stated:
    It is a well-settled principle that our
    appellate courts will decline to consider
    questions or issues not properly presented to
    the trial court when an opportunity for such
    a presentation is available "unless the
    questions so raised on appeal go to the
    jurisdiction of the trial court or concern
    matters of great public interest."
    [Nieder v. Royal Indem. Ins. Co., 
    62 N.J. 229
    ,
    234 (1973) (quoting Reynolds Offset Co., Inc.
    v. Summer, 
    58 N.J. Super. 542
    , 548 (App. Div.
    1959)).]
    Our review of the record reveals Lessner's bad faith argument
    was not asserted either in its pleadings or argued before the
    10                          A-0081-17T3
    motion judge.   For these reasons, we decline to consider that
    claim here.
    Affirmed.
    11                        A-0081-17T3