United Water New Jersey, Inc. v. Borough of Hillsdale , 438 N.J. Super. 309 ( 2014 )


Menu:
  •                 NOT FOR PUBLICATION WITHOUT THE
    APPROVAL OF THE APPELLATE DIVISION
    SUPERIOR COURT OF NEW JERSEY
    APPELLATE DIVISION
    DOCKET NO. A-0299-13T4
    UNITED WATER NEW JERSEY, INC.,
    APPROVED FOR PUBLICATION
    Plaintiff-Respondent,
    November 26, 2014
    v.                                         APPELLATE DIVISION
    BOROUGH OF HILLSDALE, MAYOR
    AND COUNSEL OF THE BOROUGH OF
    HILLSDALE,
    Defendants.
    ________________________________________
    HILLSDALE & WESTWOOD FLOOD
    SOLUTION GROUP, and ANTONIO
    XAVIER AND WENDY XAVIER,
    Intervenors-Appellants.
    _________________________________________
    Argued October 28, 2014 – Decided November 26, 2014
    Before Judges Yannotti, Hoffman and Whipple.
    On appeal from Superior Court of New Jersey,
    Law Division, Bergen County, Docket No. L-
    4634-12.
    Donald S. MacLachlan argued the cause for
    appellants (MacLachlan Law Offices, LLC,
    attorneys; Mr. MacLachlan, on the briefs).
    Thomas J.    Herten argued the cause for
    respondent    (Archer  &   Greiner, P.C.,
    attorneys; Mr. Herten, of counsel; Andrew T.
    Fede, on the brief).
    Lisa M. Almeida, Deputy Attorney General,
    argued the cause for amicus curiae State of
    New   Jersey  Department    of  Environmental
    Protection (John J. Hoffman, Acting Attorney
    General,   attorney;    Melissa   H.   Raksa,
    Assistant Attorney General, of counsel; Ms.
    Almeida, on the brief).
    The opinion of the court was delivered by
    YANNOTTI, P.J.A.D.
    Intervenors    Hillsdale      and       Westwood    Flood   Solution   Group
    (the "HWFSG"), Antonio Xavier and Wendy Xavier (the "Xaviers")
    appeal from an order of the Law Division dated August 1, 2013,
    finding     that   the   Borough    of    Hillsdale       ("Hillsdale"   or    the
    "Borough") was preempted by state law from applying its land use
    approval requirements and other ordinances to a dam improvement
    project to be undertaken by plaintiff United Water New Jersey,
    Inc. ("UWNJ" or the "Company"). We affirm but remand for entry
    of a modified judgment.
    I.
    The    relevant    facts     are        essentially     undisputed.     UWNJ
    provides water to customers in sixty municipalities in Bergen
    and   Hudson   Counties.    To     do    so,    UWNJ     utilizes,   among   other
    facilities, the Woodcliff Lake Reservoir, which is located in
    Hillsdale and the Borough of Woodcliff Lake ("Woodcliff Lake").
    One of the reservoir's structures is a dam across the Pascack
    2                              A-0299-13T4
    Brook,      which   UWNJ's        predecessor,        Hackensack     Water        Company,
    constructed in 1904. The dam is traversed by Church Road, a
    private road owned by UWNJ that is subject to use easements held
    by Hillsdale and Woodcliff Lake.
    The New Jersey Department of Environmental Protection (the
    "NJDEP") has classified the dam as a "Class I, High Hazard"
    structure pursuant to N.J.A.C. 7:20-1.8(a)(1), because there are
    "normally occupied homes in the area that are susceptible to
    significant damage in the event of a dam failure."                                N.J.A.C.
    7:20-1.8(a)(1)(i). Between 2005 and 2006, the NJDEP asked UWNJ
    to    undertake     a    study    of    the   dam     "to   determine       the   maximum
    probable precipitation and water runoff volume projected to flow
    into the [Woodcliff Lake Reservoir] during future severe weather
    events."
    UWNJ retained engineering consultants to perform the study
    and    in   2007,       they   reported       that,    in    the    event    of     severe
    precipitation,          "excess    storm      related       water   could     rise      and
    overtop the [d]am." The consultants recommended "doubling the
    amount of impounded water passed downstream from the [dam] into
    the Pascack Brook."
    On December 20, 2007, the NJDEP notified UWNJ that the dam
    was not in compliance with spillway capacity regulations adopted
    pursuant to       the     Safe    Dam    Act (the "SDA"), N.J.S.A. 58:4-1 to
    3                                   A-0299-13T4
    -14. The NJDEP directed UWNJ to make modifications to the dam to
    address this condition. UWNJ developed a plan to modify the dam,
    and provided the plan to Hillsdale for informational purposes.
    Thereafter, UWNJ submitted its plan to the NJDEP, accompanied by
    construction drawings, details, and specifications prepared by
    its professional engineers.
    On   November      7,   2011,      the     NJDEP   granted     UWNJ   a   permit,
    requiring      the    Company     to    "construct      an   auxiliary     spillway,
    rehabilitate the low level outlet and rehabilitate the dikes
    for" the dam. The NJDEP's permit approved the drawings prepared
    by   UWNJ's          engineers,        as       well    as   certain       technical
    specifications. The permit specified the terms and conditions
    for the project.
    Those terms and conditions indicated that the work was at
    all times subject to supervision and inspection by the NJDEP's
    Bureau    of   Dam     Safety   and     Flood      Control   (the    "Bureau");       no
    changes to the approved plans may be made without the Bureau's
    written consent; all construction activities must be undertaken
    in accordance with dam safety standards in N.J.A.C. 7:20-1.10;
    construction work on lands encompassed by the permit shall be
    stabilized in accordance with standards for soil erosion and
    sediment control; trees or brush shall not be allowed to grow on
    the dam structure; and after construction, inspection reports
    4                                  A-0299-13T4
    shall    be   submitted    to    the   Bureau       in     accordance    with    the
    standards in N.J.A.C. 7:20-1.11.
    In addition, the permit required UWNJ to obtain a current
    and valid water lowering permit from the Bureau of Freshwater
    Fisheries for the manipulation of water levels of any lake or
    impoundment. The permit also stated in bold typeface that it did
    not give any property rights to its holder, and that it would
    not be valid "until such time as all other required approvals
    and permits have been obtained."
    Along with the permit, John H. Moyle, P.E. ("Moyle"), the
    manager of the NJDEP's Bureau of Dam Safety and Flood Control,
    issued a letter. In that letter, Moyle stated that because the
    dam was not in compliance with applicable safety standards, and
    posed a potential hazard, construction of the dam improvements
    must begin within six months.
    On January 10, 2012, Hillsdale advised UWNJ that the dam
    modification     project    required         site   plan    approval     from    the
    Borough's     planning    board.   UWNJ's       attorney      responded    with     a
    letter   dated   March     13,   2012,       asserting     that   site    plan   and
    conditional use approval were not required for the project. The
    planning board's attorney replied in a letter dated April 2,
    2012, asserting that the board had jurisdiction to review the
    project.
    5                                 A-0299-13T4
    On May 1, 2012, Hillsdale adopted Ordinances No. 12-09 and
    12-10. Ordinance No. 12-09 amended the tree removal provisions
    of   the   borough's    land      use   ordinances.          Ordinance      No.     12-10
    revised the conditional use standards for public utilities. The
    ordinance     required      public        utilities          to   submit          formal
    applications for site plan approval of such uses.
    That same day, UWNJ filed a petition with the Board of
    Public Utilities (the "BPU") pursuant to the Municipal Land Use
    Law ("MLUL"), specifically N.J.S.A. 40:55D-19, which provides,
    among other things, that a municipal ordinance or regulation
    adopted    pursuant    to   the    MLUL       shall    not    apply    to    a    public
    utility's development in more than one municipality, if the BPU
    determines that the installation "is reasonably necessary for
    the service, convenience or welfare of the public."
    On February 20, 2013, the BPU issued an opinion and order
    on UWNJ's petition. The BPU noted that there was no dispute
    requiring    it   to   decide      whether       the    project       is    reasonably
    necessary for the service or convenience of the public. The BPU
    noted that the NJDEP had maintained that its authority under the
    SDA and the Water Supply Management Act (WSMA), N.J.S.A. 58:1A-1
    to -26, completely preempted local regulation of the dam and
    reservoir.
    6                                      A-0299-13T4
    The BPU accepted, without ruling on, the NJDEP's assertion
    that the SDA and WSMA preempted local ordinances. The BPU noted
    that the NJDEP had asserted jurisdiction over dam safety and
    reliability under the SDA and it declined to consider issues
    over which the NJDEP had claimed preemption. The BPU elected not
    to exercise its jurisdiction pursuant to N.J.S.A. 40:55D-19, and
    dismissed the petition, stating that any party could file a
    petition if, in the future, an issue arises in an area in which
    the NJDEP has not claimed preemption.
    On   June    15,   2012,    UWNJ       filed    an   action     in     lieu      of
    prerogative writs in the Law Division. UWNJ alleges, among other
    things, that Hillsdale adopted and sought to enforce ordinances
    that   were    preempted    by    state       law,    and   that    the     NJDEP      had
    exclusive     jurisdiction       over    the    project.      On    July    26,    2012,
    Hillsdale     and   its   Mayor    and    Council     filed    an    answer       to   the
    complaint.
    Thereafter, the trial court permitted the HWFSG and the
    Xaviers to intervene in the action pursuant to Rule 4:33-2, but
    limited their participation to the preemption issues raised in
    paragraph 89 of the complaint.1 The court bifurcated the matter
    1
    In that paragraph, UWNJ alleged that Ordinances 12-09 and 12-10
    violate substantive due process "because they seek to regulate
    the Dam Improvement Project when such regulation is preempted
    by, and exclusive jurisdiction rests with the NJDEP."
    7                                   A-0299-13T4
    and determined that it would adjudicate the preemption claims
    first,    with    the    other     claims       to    be   tried    in       a    separate
    proceeding, if necessary.
    The court conducted a trial in the matter on April 23,
    2014,     which   was    limited     to     oral      argument     by    counsel          and
    consideration       of   the   documentary           evidence    presented          by    the
    parties. Thereafter, the court filed an opinion finding that the
    NJDEP has exclusive jurisdiction over the project pursuant to
    the SDA and the WSMA. The court determined that Hillsdale's
    ordinances    are    preempted      by    these       statutes.    The       order       that
    accompanied the opinion stated that Hillsdale is "preempted from
    imposing on [UWNJ] local land use approval requirements, as well
    as requiring compliance with Hillsdale's soil movement and tree
    removal ordinances."
    On     September     16,     2013,    intervenors        filed       a       notice    of
    appeal. The Borough has not appealed. Thereafter, we granted the
    NJDEP's motion for leave to participate in the appeal as amicus
    curiae.
    II.
    Intervenors argue that the trial court erred by finding
    that Hillsdale is preempted from applying its ordinances to the
    UWNJ's dam modification project. Intervenors argue that they are
    not challenging the NJDEP's exclusive authority to enforce the
    8                                        A-0299-13T4
    SDA and the WSMA. They contend, however, that the fact that the
    NJDEP issued a permit for the construction of modifications to
    the dam does not exempt UWNJ from complying with certain local
    zoning laws and other regulations.
    Intervenors         maintain       that          Hillsdale's       ordinances    do    not
    address    or    seek    to     regulate             the     "construction,       operation,
    maintenance      or    repairs"       of    the        dam    structure.    According       to
    intervenors,     the    ordinances          merely         seek   to    require    municipal
    review     and    evaluation           of        the       "construction,         operation,
    maintenance or repairs" through the municipal site plan review
    process,   so    that    certain       "legitimate            local     concerns"    may    be
    addressed.
    Intervenors assert that UWNJ "thwarted" the early review
    process contemplated by the ordinances when it refused to submit
    to the required site plan review process                               before obtaining a
    permit from the NJDEP. Intervenors maintain that the intent of
    the ordinances is to address "specified local concerns" with the
    public utility, so that the parties "may at least attempt to
    arrive at a mutually acceptable plan which addresses the local
    concerns   and    can    then     be    submitted            to   NJDEP   for     review   and
    approval, before the permit is issued."
    We note again that the trial court limited HWFSG's and the
    Xaviers'     intervention        to        the       preemption        issues     raised    in
    9                                   A-0299-13T4
    paragraph 89 of UWNJ's complaint, which pertains to the claim
    that Ordinances No. 12-09 and No. 12-10 are preempted by state
    law. We are convinced that the trial court correctly determined
    that Hillsdale was preempted by state law from applying these
    ordinances to UWNJ's dam improvement project.
    The   Supreme   Court   has   identified    several     factors     to   be
    considered   in   determining     whether   a   municipal    ordinance        is
    preempted by state law. Mack Paramus Co. v. Mayor & Council of
    Paramus, 
    103 N.J. 564
    , 573 (1986) (citing Overlook Terrace Mgmt.
    Corp. v. Rent Control Bd. of W. New York, 
    71 N.J. 451
    , 461-62
    (1976)). Those factors are:
    1. Does the ordinance conflict with [the]
    state law, either because of conflicting
    policies or operational effect[,] []that is,
    does   the   ordinance    forbid  what   the
    Legislature has permitted . . . ?
    2. Was the state law intended[] expressly or
    impliedly[] to be exclusive in the field?
    3. Does the subject matter reflect a need
    for uniformity?
    4. Is the state scheme so pervasive or
    comprehensive that it precludes coexistence
    of municipal regulation?
    5. Does the ordinance stand []as an obstacle
    to the accomplishment and execution of the
    full   purposes  and  objectives[]  of   the
    Legislature?
    [Ibid. (quoting Overlook 
    Terrace, supra
    , 71
    N.J. at 461-62) (alterations in original).]
    10                                A-0299-13T4
    The SDA prohibits the making of repairs, alterations, or
    improvements to existing dams on any river or stream in New
    Jersey, without the consent of the Commissioner of Environmental
    Protection ("Commissioner") if the project involved will cause
    the waters in the river or stream to rise more than five feet
    above   its    mean    low-water   height.           N.J.S.A.     58:4-1a.      The   SDA
    requires any entity "owning and maintaining or having control
    of" a dam, upon written request, to furnish the Commissioner
    with a description of the dam, as well as any surveys, plans,
    and drawings that might be necessary for the Commissioner to
    make a determination regarding the dam's safety. N.J.S.A. 58:4-
    3.
    The      SDA    provides   that     owners       or   other    persons      having
    control of reservoirs or dams must "[i]mplement all measures
    required" by the SDA. N.J.S.A. 58:4-5a(1). The SDA also provides
    that owners and others having control of a reservoir or dam must
    take actions deemed necessary to bring a reservoir or dam into
    compliance      with    SDA   standards,        or    "any   rule    or    regulation
    adopted, or permit or order issued pursuant thereto." N.J.S.A.
    58:4-5a(3).
    We    are      convinced    that,     in        the   SDA,    the    Legislature
    contemplated        uniform   regulation      by     the   NJDEP    of    the   design,
    construction, operation and maintenance of dams and reservoirs
    11                                     A-0299-13T4
    in this State. The SDA reflects the Legislature's intention that
    regulation of such matters should be uniform on a state-wide
    basis. Furthermore, the State's regulatory scheme for dams and
    reservoirs is pervasive and comprehensive, thereby precluding
    the co-existence of municipal regulation of the sort reflected
    in Hillsdale Ordinances No. 12-09 and No. 12-10.
    Ordinance    No.    12-09      prohibits    the     removal     of    more    than
    three trees from a lot in the Borough within a calendar year.
    The ordinance requires that every tree removed from a flood
    plain   be   replaced     with    four   trees.     The    ordinance        gives    the
    planning board jurisdiction to waive the requirements of the
    ordinance "if the literal enforcement of one or more provisions
    is   impracticable       or   will    exact   [undue]      hardship        because    of
    peculiar conditions pertaining to the land in question."
    Ordinance No. 12-09 directly conflicts with the regulations
    adopted by the NJDEP pursuant to the SDA. Among other things,
    those regulations provide that trees are not permitted on a dam
    embankment unless approved by the NJDEP. N.J.A.C. 7:20-1.4(n).
    Moreover,    the   permit      issued    to   the       NJDEP   for    the    project
    requires the removal of trees as part of the dam improvement
    project.     Hillsdale's      tree     removal      ordinance       stands     as     an
    obstacle to the uniform regulation by the NJDEP of dam design,
    construction, operation and maintenance of dams and reservoirs
    12                                   A-0299-13T4
    in this State. The trial court correctly determined that the
    ordinance could not be applied to UWNJ's project.
    The same conclusion applies to Ordinance No. 12-10, which
    establishes "conditional use standards for public utilities."
    The ordinance provides, among other things, that the Borough's
    land use boards have authority to review, deny, or approve with
    conditions,   plans    for   any     "design,           redesign,   construction,
    repair,   replacement,       improvement,               modification,      upgrade,
    rehabilitation,      alteration,     expansion,           or   addition    to     any
    [utility development]" before construction may begin.
    Ordinance No. 12-10 conflicts with the NJDEP's exclusive
    authority to regulate dam design, construction, operation, and
    maintenance under the SDA. The regulations adopted by the NJDEP
    pursuant to the SDA require the owner or those in control of a
    dam to obtain a permit for modifications to the dam. The permit
    application   must    address      the        design,     structure,     stability,
    elevations, spillway and overflow details, the project schedule
    and other technical matters. N.J.A.C. 7:20-1.7(b) to (e).
    Furthermore,      as   indicated      by     the     permit   that   the    NJDEP
    issued for the project, the improvements must be undertaken in
    accordance with the approved plans and specifications. Moreover,
    due to the danger presented by the dam's condition, the NJDEP
    required UWNJ to begin making the improvements within six months
    13                                A-0299-13T4
    after   the     permit       was   issued.      The    trial      court   correctly
    determined that the ordinance requiring UWNJ to obtain site plan
    approval from the Borough's planning board conflicts with the
    NJDEP's pervasive regulation in this area under the SDA.
    Intervenors        argue       that    Ordinance     No.      12-10    addresses
    matters that fall outside the purview of the NJDEP's exclusive
    regulation      of   dam     construction,      operation,        maintenance      and
    repair. Intervenors point to certain conditions imposed by the
    ordinance, which they say pertain solely to matters of local
    concern.   We    are   convinced,         however,    that   requiring      UWNJ    to
    secure site plan approval pursuant to Ordinance No. 12-10, and
    compliance    with     the    requirements      imposed      by   that    ordinance,
    would substantially undercut the NJDEP's pervasive regulation
    under the SDA by superimposing local site plan review upon the
    NJDEP's permitting process.
    The ordinance empowers the Borough's local planning board
    to impose conditions in addition to those required by the NJDEP,
    and to deny approval of the project unless those conditions are
    met. The exercise of such regulatory authority cannot coexist
    with the exclusive authority conferred upon the NJDEP in the
    SDA. Moreover, local review of the modifications could delay
    construction that the NJDEP directed UWNJ to begin promptly.
    14                               A-0299-13T4
    Intervenors        further   argue    that   the   NJDEP   could,    in   the
    exercise    of   its     regulatory      authority,    override    conditions
    imposed by the Borough pursuant to the ordinance. However, the
    ordinance does not provide for the NJDEP's review of any local
    planning board action. By its terms, the ordinance allows the
    local board to delay or disapprove a dam improvement project
    unless it meets the conditions imposed therein.
    In     addition,     Ordinance       No.   12-10   provides    for     local
    oversight of the impact a dam improvement project might have on
    the Borough's management of its stormwaters. This provision of
    the ordinance conflicts with the NJDEP's authority under the
    WSMA. Under the WSMA, the NJDEP has the exclusive authority to
    "control, conserve, and manage the water supply of the State and
    the diversions of that water supply." N.J.S.A. 58:1A-5.
    The NJDEP has adopted comprehensive regulations governing
    the water supply, which include a detailed application process
    for water supply allocation or diversion in the public interest.
    See, e.g., N.J.A.C. 7:19-2.2(a) to (f). Decisions as to the
    allocation and diversion of water from the dam are conferred
    upon the NJDEP by the WSMA, and the NJDEP's pervasive authority
    in this area precludes local regulation of the sort contemplated
    by Ordinance No. 12-10.
    15                                A-0299-13T4
    In   support    of    their   arguments,     intervenors       rely     upon
    Shupack v. Manasquan River Reg'l Sewerage Auth., 
    194 N.J. Super. 199
    (App. Div. 1984). There, the Regional Sewerage Authority
    (the "Authority") obtained approval of the NJDEP and the federal
    Environmental Protection Agency to construct a sewerage pumping
    station. 
    Id. at 201.
    The Township of Howell (the "Township") and
    its   construction    official      maintained    that   the   Authority       was
    required to obtain site plan approval for the project under the
    Township's land use ordinance, as well as a construction permit
    pursuant to the State Uniform Construction Code (the "UCC"). 
    Id. at 202.
    In response, the Authority argued that construction of the
    pumping station was governed by the Water Pollution Control Act
    ("WPCA"), N.J.S.A. 58:10A-1 to -69, and the Sewerage Authorities
    Law ("SAL"), N.J.S.A. 40:14A-1 to -45, which exempted it from
    compliance with the local permit and approval requirements. 
    Id. at 203.
    We held that the Authority was required to obtain site
    plan approval from the local planning board, and construction
    permits pursuant to the UCC. 
    Id. at 204-05.
    We   noted     that    neither    the      WPCA    nor   the      SAL    was
    "particularly      concerned   with    the    construction     aspect    of    the
    facilities nor with aesthetic considerations in the sense that
    such matters are regulated by permits issued under the [UCC] or
    16                                A-0299-13T4
    site plan approval ordinances." 
    Id. at 204.
    We concluded that
    the Township's plan approval ordinance was not preempted by the
    WPCA    or    the    SAL.     
    Id. at 205.
         We    also   saw     no    inconsistency
    between those laws and the requirement that the Authority obtain
    a building permit for the project. 
    Ibid. We said, however,
    that our opinion should not be read to
    approve       "any    procedure        relating           to   site     plan     approval       or
    building permits that would interfere with the purposes of the
    project as authorized by the [WPCA] or the [SAL]." 
    Ibid. We noted that
    the Township and its construction official had not
    taken    the    position       that       the   municipality          had      the    power    "to
    prohibit       by     zoning        proscription           the    construction           of    the
    [project], including the building for which it is claimed site
    plan approval and construction permits should have been issued."
    
    Ibid. (internal quotation marks
    omitted).
    In     our     view,     intervenors'              reliance       upon        Shupack    is
    misplaced. Here, the Borough's ordinance confers upon the local
    planning      board    the     power      to    deny      site    plan    approval       if    the
    project      does    not    meet     the    specified          conditions,       even     though
    those conditions have not been imposed by the NJDEP through its
    permitting process. The ordinance is concerned with matters over
    which the NJDEP has exclusive authority under the SDA and the
    WSMA, and it essentially allows the municipality to prohibit by
    17                                       A-0299-13T4
    zoning    proscription     the   construction      of    the   project.      Thus,
    Shupack    is    not   inconsistent       with   our    conclusion    that     the
    Borough's site plan approval ordinance is preempted.
    Intervenors also rely upon Morris Cnty. Fair Hous. Council
    v. Boonton Twp., 
    228 N.J. Super. 635
    (Law Div. 1988), aff'd, 
    230 N.J. Super. 345
    (App. Div. 1989). In that case, the municipality
    agreed    to     change    its     zoning     regulations      to    allow     the
    construction of a number of units of lower income housing. 
    Id. at 638-39.
    In furtherance of this agreement, the municipality
    rezoned certain properties, and the intervenors sought site plan
    approval for a development. 
    Id. at 639.
    The plans provided that
    stormwater would be directed to a reservoir and then released to
    downstream properties. 
    Ibid. The local planning
    board denied site plan approval, finding
    among    other   things,    that    the     proposal    did    not   include    an
    adequate stormwater management plan. 
    Id. at 639-40.
    The board
    noted that the reservoir included a dam, which was in need of
    repairs and/or modification. 
    Id. at 640.
    The trial court upheld
    that decision, noting that site plan approval was subject to
    improvements to the dam and reservoir. 
    Id. at 645-46.
    The trial
    court stated that the repairs or modifications to the dam and
    reservoir were subject to the approval by the NJDEP. 
    Id. at 646.
    The court held that the planning board did not act arbitrarily,
    18                               A-0299-13T4
    capriciously      or     unreasonably      in    denying     site     plan    approval
    because     it    could     not     determine       whether        the     applicants'
    stormwater management plan was adequate until the NJDEP acted.
    
    Id. at 646.
    The    Morris      County    case     does    not     support      intervenors'
    position in this case. As we have explained, in Morris County,
    the court emphasized that the NJDEP had exclusive authority to
    decide what modifications had to be made to the reservoir and
    dam. The court did not suggest that a local planning board could
    impose conditions upon a dam improvement project, as part of the
    site plan approval process, in addition to those imposed by the
    NJDEP in its permit approving the project.
    III.
    Intervenors also contend that the trial court failed to
    provide adequate findings of fact to support its decision. We do
    not   agree.      Here,    the     court's       decision    was     based    on     the
    undisputed       facts    concerning      the     project    and     the     terms   of
    Ordinances No. 12-09 and No. 12-10. The court determined, as a
    matter of law, that the Borough was preempted from applying
    these ordinances to the project. The court's findings of fact
    were sufficient to support its determination.
    Intervenors        further   argue     that   the     trial    court    did    not
    address the following issues: (1) whether issuance by the NJDEP
    19                                 A-0299-13T4
    of a dam construction permit precludes local land use regulation
    of the sort reflected in the conditional use ordinance; (2)
    whether     the     NJDEP's       permit     effectively       exempts           UWNJ   from
    complying     with        local    zoning     or       other   law        "wherever       and
    whenever"; and (3) whether the permit makes the Borough's Church
    Road easement null and void, thereby taking property rights away
    from the Borough and unilaterally granting those rights to the
    NJDEP or UWNJ.
    The trial court's opinion makes clear, however, that the
    NJDEP's regulatory authority over dam construction and safety
    under the SDA, and its exclusive authority to regulate the water
    supply     under    the    WSMA    preclude      application      of      the     Borough's
    conditional       use     and    tree    removal    ordinances       to    the     project.
    Moreover,     the    court's       decision      was    limited   to       the    issue   of
    preemption presented in the complaint and did not address the
    question of whether UWNJ is exempt from local zoning and other
    laws "wherever and whenever."
    Furthermore,         the    court's     decision     does      not    address       the
    effect the project might have on the Borough's easement rights
    to the Church Road. That issue was not raised in the complaint
    and   it     was        beyond     the     limits      imposed       on     intervenors'
    participation in the case.
    20                                     A-0299-13T4
    Intervenors additionally argue that, in the permit for the
    project, the NJDEP acknowledged that the Borough could exercise
    regulatory authority over the project as to matters of local
    concern. The permit states in pertinent part:
    This permit DOES NOT GIVE ANY PROPERTY
    RIGHTS, in either real or personal property
    or material, nor any exclusive privileges;
    neither does it authorize any injury to
    private property, nor invasion of private
    rights, nor any infringement of Federal,
    State or local laws or regulations; nor does
    it waive the obtaining of Federal or other
    State or local government consent when
    necessary. THIS PERMIT IS NOT VALID AND NO
    WORK SHALL BE UNDERTAKEN UNTIL SUCH TIME AS
    ALL OTHER REQUIRED APPROVALS AND PERMITS
    HAVE BEEN OBTAINED.
    Intervenors contend that the permit requires UWNJ to obtain
    local approval for the project, and that the permit is not valid
    until such approval is obtained. Intervenors also assert that
    the permit mandates that "the right of Hillsdale pursuant to the
    grant of easement from [plaintiff] to 'supervise and control'
    Church Road, the roadway which passes upon the top of the Dam,
    must stand intact." Again, we disagree.
    As    the   trial   court   observed,    the   above-quoted   language
    merely is intended to ensure that UWNJ obtains all necessary
    permits   and   consents.   The   court     also   noted   that   UWNJ   had
    conceded that the language in the permit quoted above applies to
    necessary NJDEP wetlands or fish and wildlife permits. The court
    21                             A-0299-13T4
    correctly found that the NJDEP's permit does not recognize local
    regulation of the project of the sort reflected in Ordinances
    No. 12-09 and No. 12-10.
    The    other    arguments   raised       by    intervenors    are      without
    sufficient merit to warrant discussion. R. 2:11-3(e)(1)(E).
    We     therefore   conclude      that    the     trial   court    correctly
    determined that the Borough may not apply Ordinances No. 12-09
    and No. 12-10 to the UWNJ's dam improvement project.
    We note, however, that the court's order goes beyond the
    scope   of    the    issues   raised   in     the    pleadings.    As   we    stated
    previously, the order provides that Hillsdale is "preempted from
    imposing on [UWNJ] local land use approval requirements, as well
    as   requiring      compliance    with    [its]      soil   movement    and      tree
    removal ordinances." The pleadings made no mention of the soil
    movement ordinance, and the litigation was limited to whether
    Ordinances No. 12-09 and No. 12-10 are preempted by state law.
    The judgment should be modified accordingly, and the ruling
    limited to the two ordinances referenced in paragraph 89 of the
    complaint. The order should state that the Borough is precluded
    from applying those ordinances to the UWNJ's Woodcliff Lake dam
    improvement project. We therefore affirm and remand the matter
    to the trial court for entry of an order modifying the judgment
    to state that the Borough is preempted by the SDA and the WSMA
    22                                  A-0299-13T4
    from   applying   Ordinances   No.   12-09   and   No.   12-10   to     UWNJ's
    Woodcliff Lake dam improvement project.
    Affirmed and remanded for entry of a modified judgment in
    accordance with this opinion.
    23                               A-0299-13T4